Professional Documents
Culture Documents
Variable Labor Productivity Unit Rate: Evaluation by Professionals
Variable Labor Productivity Unit Rate: Evaluation by Professionals
Professionals
Ubiraci Espinelli Lemes de Souza
Associate Prof. of Dept. of Construction, University of So Paulo
(email: ubiraci.souza@poli.usp.br)
Fernanda Fernandes Marchiori
PhD student of Dept. of Construction, University of So Paulo
(email: fernanda.marchiori@poli.usp.br)
Luis Otvio Cocito de Arajo
PhD student of Dept.of Construction, University of So Paulo
(email: luis.otavio@poli.usp.br)
Abstract
To forecast labor productivity indexes is a very important task to be performed, by the
construction managers, in order to compose reliable building construction budgets and
schedules. To do so, the main information sources have been the estimating manuals. These
type of manuals are normally available in several countries, both developed and developing
ones. The data, in such manuals, usually represent mean values for regional contractors
performance. Although very easy to use, this approach, in the opinion of the authors, cannot be
considered appropriate to the present context of Construction; the very competitive environment
demands more accurate indexes to support managersdecisions.
Some recently developed researches, in Brazil, demonstrate the importance of considering a
range of values to represent labor productivity unit rates instead of adopting a mean value for a
broad scope of situations. The choice of a value from the proposed range would be based on the
jobs features.
Keywords: Labor productivity, productivity forecast, formwork, estimating manuals.
1. Introduction
The construction companies seldom measure the real productivity in their sites. So it is a current
practice in Brazil to utilize productivity indexes gathered from estimating manuals to make
budgets and schedules (Figure 1 shows the steps of a traditional budgeting process). These
budgets and schedules are based on the physical resources consumption, which is composed by
the labor, material and equipment consumption. This paper focus on labor consumption forecast
for formwork job. Labor is the physical resource more difficult to manage and which demand
have the highest variability. On the other hand, formwork is a labor-intensive task and often
represents an event in the critical step of the project [1].
194
Product to
build
Design
Quantity
survey
Price
Final cost
TCPO 2000
SBC
For slabs
For beams
For columns
Carpenter
For whole
formwork job
1,35 Mh/m
0,928 Wh/m
1,268 Wh/m
1,361 Wh/m
Helper
1,35 Wh/m
1,443 Wh/m
1,773 Wh/m
1,907 Wh/m
195
The use of parametric equations was presented on [1]. Other research, as [11], added confidence
to the statistical analysis. This paper deals with more recent parametric equations, as showed in
2.1 and productivity ranges on 2.2.
Median (wh/m2)
0.14
Maximum (wh/m2)
0.30
(2)
Where:
BL = median beams length;
TU = 0 for when no tie is used; and = 1 for ties utilization;
STRbeam = part of bUR referring to disassemble beam forms. The proposed values for STR
vary as showed by Table 2. One should choose higher whenever expects more difficulties in
stripping the panels. The proposed values for STRvary as showed by Table 3. One should
choose higher whenever expects more difficulties in stripping the panels.
Table 3STRbeamvalues variation range.
Minimum (wh/m2)
0.10
Median (wh/m2)
1.18
Maximum (wh/m2)
2.60
196
formwork in conventional structures, where slabs rely on beams, and in plain slab structures,
where slabs rely directly on columns.
Table 4 bURslab values variation range.
Floors
Conventional
structure (slabs
with beams)
Plain slab
bURslab (wh/m2)
Minimum
0.40
Maximum
0.96
Median
0.69
Median
0.33
Stairs formwork
During the floor production
After the floor production
1.78
2.64
1.93
1.00
(bUR column xAcolumn + bUR beam xAbeam + bUR slab xAslab + bUR stair xAstair )
Acolumn + Abeam + Aslab + Astair
(3)
Where:
bUR= baseline for the skilled team
A= area (m2 of structure).
J minimum
K median
Favorable factors,
better productivity
L maximum
Unfavorable factors,
worst productivity
Expected labor
unit rate
197
In the Figures from 3 to 6 are presented labor productivity indexes range to carpenters of
formwork job. The job envolves 4 tasks: column formwork (Figure 3), beam formwork (Figure
4), slab formwork (Figure 5) and stair formwork (Figure 6).
0,52 Wh/m
1,80 Wh/m
0,94 Wh/m
UR column
Wh / mof structure
Removable ties
Incorporated ties
External ties
Internal ties
0,73 Wh/m
2,60 Wh/m
1,18 Wh/m
UR beam
Wh / mof structure
No tie is used
Is tie used
0,33 Wh/m
0,69 Wh/m
0,96 Wh/m
UR slab
Wh / mof structure
Plain slab
1,00 Wh/m
2,64 Wh/m
1,93 Wh/m
UR stair
Wh / mof structure
198
In order to know the UR for all structure formwork, it should be done using the Equation 3. It
will be necessary to chose on ranges what productivity better adequate to your build (minimum,
median or maximum) and to know the dates of quantity extracted from projects.
Chosen approach
Application of both
approaches to a real
case study
Evaluation for a
case study
Construction Manager
opinion based on real case
study
Final analysis
199
b) Second step the authors did a forecast to a real build (that one in which the manager was
questioned in the first step) utilizing as the range as the equation.
Productivity Range Forecast
It was chosen the follow values for the productivity:
- URcolumn: 0,94 Wh/m (median value)
- URbeam: 0,73Wh/m (minimum value)
- URslab: 0,69 Wh/m (median value)
- URstair: 2,64 Wh/m (maximum value)
The build had more favorable factors than unfavorable, however, to get more security on
forecast, the median was chosen to column and slab. Only in the case of stair that the worst
situation was chosen to be coherent with the factor, that was unfavorable. Based in these values
and on survey of project quantities, applied on Equation 3, it were obtained the productivity
forecast (0,80 Wh/m).
Parametric Equation Forecast
It was given heights to the characteristics of build as indicated on 2.1 heading. The heights are
presented on 3rd column on Table 6. Utilizing these heights into the Equations 1 and 2 plus the
values chosen on Table 4 and 5, referent to structure components, it were obtained the results
for column, beam slab and stair, which are presented on column 4th. These values were applied
on Equation 3 to get the total productivity for whole structure, whose the result is presented on
7th column. The 5th column present the values chosen in the productivity range approach. The
Table 6 shows yet, the Brazilian estimating manuals (SBC e TCPO 2000) values, on columns 6,
9 and 10.
In order to know the real productivity involved on formwork job in the floor, it were collected
the quantity of hours worked for de formwork crew, which were composed only by carpenters
(583 Wh/type floor; UR = 0,84 Wh/m). This value is presented on 11th column on Table 6.
200
Build
characteristics
Column
(200,5 m)
Beam
(153,3 m)
BLE
SAR
0,12
BPL
TIE
LTI
STR
BL
TU
STR
0,14
3.81
0
0,10
1,16
0,94
0,73
1,27
Laje
(328,5 m)
0,69
(mediana)
0,69
0,93
Escada
(9 m)
1,93
(mediana)
2,64
0,93
nd
rd
th
th
SBC
Tcpo
2000
Real UR
(Wh/m)
1,36
0,40
st
Forecasted total UR
(Wh/m)
6th
0,79
0,80
1,13
1,35
0,84
7th
8th
9th
10th
11th
Observes, therefore, that the forecasted productivity values obtained as for the equation as for
the range (about 0,80 Wh/m) got a great forecast, because they are near to the real productivity
(0,84 Wh/m) reached by the crew on the site building, while the estimate manual values are
more distant to real productivity.
4. Final Considerations
The research with construction manager opinions not shows resistance on using of range. On the
other hand, the position of construction manager interviewed presented critical, probably
justified by the lost of training or sensitization about the subject and due to a form of labor
contraction.
In the results analysis, although of, theoretically, the range presents a minor precision on
forecast, because is a simplification on equations, it provides to a bigger easiness of application
and the value gotten in this in case were satisfactory due to be near to the really it happened in
the site build. On the other hand, the range eliminates some cited problems related to the
traditional position (only presenting the average value).
Recently, one of the most important Brazilian estimating manuals included, beyond the
traditional approach, the alternative approach of productivity ranges. The responsible believes
that it can provide a better understanding for both, construction managers and designers, about
the factors that influence productivity labor.
201
Once providing better understanding of labor productivity, the authors believe the productivity
range approachcan help improving cost and schedule forecasting in the Construction Industry.
Acknowledgements
The authors want to acknowledge the construction managers from So Paulo Construction
Companies that are participating of productivity courses promoted by Department of
Construction of University of So Paulo. In special way, the company Tarjab Ltda., that allowed
visits in its site building to perform this research.
The authors want also to acknowledge the institutions CAPES and FAPESP, which have always
been supporting our efforts to develop construction research.
References
[1] Araujo, L.O.C.; Souza, U.E.L.; Freire, T.M. Development of a formwork labor productivity
forecast model for the Brazilian building construction. Proceedings of 10th International
Symposium CIB W65, Cincinnati, 2002.
[2] TCPO 2000: Tabelas de Composies de Preos Para Oramentos. 11 Ed. Editora Pini.
1999.
[3] SBC (2005). Informativo
http://www.construbid.com.br
SBC.
Avaliable
online
for
subscribers
at:
[4] Isidore, L.J.; Back, E. Multiple Simulation Analysis for probabilistic Cost and Schedule
Integration. Journal of Construction Engineering and Management. ASCE. V.128, n. 3, p 21119, 2002.
[5] Souza, U.E.L.; Almeida, F.M.; Silva, L.R. O conceito de produtividade varivel aplicado aos
manuais de oramentao. In: 3 Simpsio Brasileiro de Gesto e Economia da Construo.
Editor: UFSCar, 16-19 de Setembro de 2003, So Carlos, SP, 2003.
[6] Andrade, A.C.; Souza, U.E.L.; Librais, C.F.; Paliari, J.C. Subsdios para o processo de
oramentao de revestimentos cermicos. In: 2 Simpsio Brasileiro de Gesto da Qualidade e
Organizao do Trabalho no Ambiente Construdo, Fortaleza, CE, 2001.
[7] Arajo, L.O.C. Mtodo para a previso e controle da produtividade da mo-de-obra na
execuo de frmas, armao, concretagem e alvenaria. 2000. 385 p. Dissertao (Mestrado em
Engenharia) - Escola Politcnica, Universidade de So Paulo, So Paulo, 2000.
[8] Freire, T.M.F. Produo de estruturas de concreto armado moldadas in loco, para
edificaes: caracterizao das principais tecnologias e formas de gesto adotadas em So
202
203