Professional Documents
Culture Documents
P1 Session 1A
P1 Session 1A
Presentation outline
Overview
Possible factors that could drive Peninsular Malaysia for more active energy
exchange or trading in the future
Closing remarks
Overview:
Possible factors that could drive
Peninsular Malaysia for more active
energy exchange or trading in the future
National Depletion
Policy (1980)
National Green
Technology Policy (2009)
11th Malaysia Plan (2016-2020)
Source: Ministry of Energy,
Green Technology and Water
Development in progress
RE development & EE will be part of focus area
0.8
0.7
tCO2/MWh
0.6
0.5
0.4
0.3
0.2
0.1
0.0
Gas CC
Gas GT
Coal
Nuclear
Diesel
Energy Sustainability /
Security
Economic Sustainability
Environment sustainability
Renewable Energy
Note :
Power Purchase one direction of power flow
Energy exchange two directions of power flow due to difference in load profile of two systems
139km 5km
50km
OHL
Submarine cable OHL
Teluk Gong
Substation
Perawang
HVAC
Substation
Perawang
Garuda Sakti
Converter
Station
Converter
Station
Melaka
Strait
Rupat
Strait
53km
Submarine cable
150km
170km
50km
30km
HVDC Overhead
Transmission Line
HVDC Overhead
Transmission Line
Selat Rupat
National Border
Telok
Gong
Telok Gong
Converter
Station
Converter
Station
Selat Melaka
Pulau
Rupat
Sumatera
Melaka
5km
53km
Progress to date
Phase 1 Completed
Phase 2 - Tender for EPC to be floated by September 2016 (tentative)
Phase 3 - Appointment of EPC targeted to be by October 2017 (tentative)
Phase 4 - Target commissioning by end 2020 (tentative)
BENTONG (S)
Converter Station
TG LEMAN
(Transition point)
Voltage
Transmission Capacity
Route Length
KG PUEH
(Transition point)
CENTRAL SARAWAK
Converter Station
DC 500kV
1600 - 2000 MW
Total Length of 1380 km
404 km
676 km
300 km
Progress so far
MI cables
Cross-sectional area (CSA) from 2000
mm2 to 2500mm2
Maximum capacity is around 830 MW
Has been used since 1954
MI-PPL cable
CSA is maintained at 2000 mm2
Maximum capacity is around 1000
MW
Relatively new technology
Submarine cable
Sarawak
Normal conditions
Emergency condition and slippage condition
23
26
Following the Harmonization Study, two study groups have been formed, i.e.
(i) ASEAN Transmission System Operator (ATSO)
(ii) ASEAN Generation & Transmission Planning (AGTP)
27
5. The level of
comfortable reserve
margin
4. Transaction should be
at market price
JUNJUNG
NEW PRAI
HULU TERENGGANU
AYER TAWAR
JANAMANJUNG
ULU JELAI
generation capacity
BKT TAREK
BENTONG
KAPAR
LENGGENG
OLAK LEMPIT
JIMAH
BKT BATU
500kV line
500kV line but energized at 275kV
TG BIN
PASIR GUDANG
Closing remarks
30
Closing remarks
THANK YOU