Professional Documents
Culture Documents
2 Nit04
2 Nit04
(SH :-C/O
Administration / Academic block, Boy's cum Girls hostel (D/S),
Dining/Common room and,1 no. Type-IV quarter (S/S) including water
supply, sanitary installations, sewerage, drainage, manual fire alarm
system, development and electrical works.
INDEX
Sl. No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Description
Page No.
PART A
Notice Inviting Tender (CPWD-6)
CPWD-8
Schedules (A to F)
Form of Performance Security/Form of Earnest Money Deposit
Amendments in GCC 2014 upto CON 283
PART B
General Conditions / Additional Specifications/Brief Specifications of
different part of the building
PART C
Schedule of Quantities (for Civil Works)
PART D
Schedule A to F ( Electrical Works)
Additional conditions and Specifications for Electrical works
PART E
Schedule of Quantities (for Electrical Works)
2
3 - 10
11 - 12
13 - 23
24 - 25
26 - 30
31
32 - 71
72
73 - 98
99
100 - 102
103 - 122
123
124 135
APPROVED
Chief Engineer
NEZ-II, CPWD, Agartala
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 1
PART A
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 2
The work is estimated to cost Rs.8,03,13,620/- in which Civil Works cost Rs.7,23,84,221/-
and Electrical Works cost Rs.79,29,399/-.This estimate, however, is given merely as a rough
guide.
1.1.1 The eligibility of bidders will correspond to the combined estimated cost of different
components put to bid.
2.
Agreement shall be drawn with the successful bidders on prescribed Form No. CPWD 8 (or
other Standard Form as mentioned) which is available as a Govt. of India Publication and also
available on website www.cpwd.gov.in. Bidders shall quote his rates as per various terms and
conditions of the said form which will form part of the agreement.
3. The time allowed for carrying out the work will be 360 days from the date of start as defined
in schedule 'F' or from the first date of handing over of the site, whichever is later, in accordance
with the phasing, if any, indicated in the bid documents.
4.(i) The site for the work is available
(ii) The architectural and structural drawings shall be made available in phased manner, as per
requirement of the same as per approved program of completion submitted by the contractor
after award of the work.
5 . The bid document consisting of plans, specifications, the schedule of quantities of various
types of items to be executed and the set of terms and conditions of the contract to be complied
with and other necessary documents except Standard General Conditions of Contract Form can
be seen on website www.tenderwizard.com/CPWD or www.cpwd.gov.in free of cost.
6.After submission of the bid the contractor can re-submit revised bid any number of times but
before last time and date of submission of bid as notified.
7.
While submitting the revised bid, contractor can revise the rate of one or more item(s) any
number of times (he need not re-enter rate of all the items) but before last time and date of
submission of bid as notified.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 3
8.
Earnest Money in the form of Treasury Challan or Demand Draft or Pay order or Bankers
Cheque or Deposit at Call Receipt or Fixed Deposit Receipt (drawn in favour of Executive
Engineer, Aizawl Central Division, CPWD, Mizoram.) shall be scanned and uploaded to the eTendering website within the period of bid submission.
A part of earnest money is acceptable in the form of bank guarantee also. In such case, minimum
50% of earnest money or Rs. 20 lac, whichever is less, shall have to be deposited in shape
prescribed above, and balance may be deposited in shape of Bank Guarantee of any scheduled
bank having validity for six months or more from the last date of receipt of bids which is to
be scanned and uploaded by the intending bidders.
The physical EMD of the scanned copy of EMD uploaded shall be deposited by the lowest
bidder within a week after opening of financial bid failing which the bid shall be rejected and
enlistment of the agency shall be withdrawn by the enlisting authority. The agency shall be
debarred from tendering in CPWD.
The following undertaking in this regard shall also be uploaded by the intending bidders:The Physical EMD shall be deposited by me/us with the EE calling the bid in case I/we
become the lowest bidder within a week of the opening of financial bid otherwise department may
reject the bid and also take action to withdraw my/our enlistment/debar me/us from tendering in
CPWD.
Interested contractor who wish to participate in the bid has also to make following payments
within the period of bid submission:
(i) e-Tender Processing Fee Rs. 5700/- (Rupees five thousand seven hundred only) shall
be payable to M/s ITI Limited through their e-gateway by credit /debit card, internet
banking or RGTS/NEFT facility
Copy of Enlistment Order and certificate of work experience and other documents as specified in
the press notice shall be scanned and uploaded to the e-Tendering website within the period of
bid submission. However, certified copy of all the scanned and uploaded documents as specified
in press notice shall have to be submitted by the lowest bidder only along with physical EMD of
the scanned copy of EMD uploaded within a week physically in the office of tender opening
authority.
Online bid documents submitted by intending bidders shall be opened only of those bidders, who
has deposited e-Tender Processing Fee with M/s ITI Limited and Earnest Money Deposit and
other documents scanned and uploaded are found in order.
The bid submitted shall be opened at 4.00 PM on 09/10/2015.
9. The bid submitted shall become invalid and e-Tender processing fee shall not be refunded if:
(i)The bidder is found ineligible.
(ii) The bidder does not upload all the documents (including service tax registration/ VAT
registration/ Sales Tax registration) as stipulated in the bid document including the
undertaking about deposition of physical EMD of the scanned copy of EMD uploaded.
(iii) If any discrepancy is noticed between the documents as uploaded at the time of
submission of bid and hard copies as submitted physically by the lowest bidder in the office of
bid opening authority.
(iv) The lowest bidder does not deposit physical EMD within a week of opening of bid.
(v) If a terderer quotes nil rates against each item in item rate tender, the tender shall be
treated as invalid and will not be considered as lowest tenderer.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 4
10. The contractor whose bid is accepted will be required to furnish performance guarantee of
5% (Five Percent) of the bid amount within the period specified in Schedule F. This guarantee
shall be in the form of cash (in case guarantee amount is less than Rs. 10000/-) or Deposit at
Call receipt of any scheduled bank/Banker's cheque of any scheduled bank/Demand Draft of any
scheduled bank/ Pay order of any Scheduled Bank of any scheduled bank (in case guarantee
amount is less than Rs. 1,00,000/-) or Government Securities or Fixed Deposit Receipts or
Guarantee Bonds of any Scheduled Bank or the State Bank of India in accordance with the
prescribed form. In case the contractor fails to deposit the said performance guarantee within the
period as indicated in Schedule'F', including the extended period if any, the Earnest Money
deposited by the contractor shall be forfeited automatically without any notice to the contractor.
The earnest money deposited along with bid shall be returned after receiving the aforesaid
performance guarantee.
The contractor whose bid is accepted will also be required to furnish either copy of
applicable licenses / registrations or proof of applying for obtaining labour licenses,
registration with EPFO, ESIC and BOCW Welfare Board and Programme Chart (Time and
Progress) within the period specified in Schedule F.
11. The description of the work is as follows:
Page 5
14. The competent authority on behalf of President of India reserves to himself the right of
accepting the whole or any part of the bid and the bidders shall be bound to perform the same at
the rate quoted.
15. The contractor shall not be permitted to bid for works in the CPWD Circle (Division in case
of contractors of Horticulture/Nursery category) responsible for award and execution of contracts,
in which his near relative is posted a Divisional Accountant or as an officer in any capacity
between the grades of Superintending Engineer and Junior Engineer (both inclusive). He shall
also intimate the names of persons who are working with him in any capacity or are subsequently
employed by him and who are near relatives to any Gazetted officer in the Central Public Works
Department or in the Ministry of Urban Development. Any breach of this condition by the
contractor would render him liable to be removed from the approved list of contractors of this
Department.
16.
No Engineer of Gazetted Rank or other Gazetted Officer employed in Engineering or
Administrative duties in an Engineering Department of the Government of India is allowed to
work as a contractor for a period of one year after his retirement from Government service,
without the prior permission of the Government of India in writing. This contract is liable to be
cancelled if either the contractor or any of his employees is found any time to be such a person
who had not obtained the permission of the Government of India as aforesaid before submission
of the bid or engagement in the contractor's service.
17. The bid for the works shall remain open for acceptance for a period of ninety (90) days from
the date of opening of bids). If any bidders withdraws his bid before the said period or issue of
letter of acceptance, whichever is earlier, or makes any modifications in the terms and conditions
of the bid which are not acceptable to the department, then the Government shall, without
prejudice to any other right or remedy, be at liberty to forfeit 50% of the said earnest money as
aforesaid. Further the bidders shall not be allowed to participate in the rebidding process of the
work.
18.
This notice inviting Bid shall form a part of the contract document. The successful
bidders/contractor, on acceptance of his bid by the Accepting Authority shall within 15 days from
the stipulated date of start of the work, sign the contract consisting of:(a) The Notice Inviting Bid, all the documents including additional conditions,
specifications and drawings, if any, forming part of the bid as uploaded at the time of invitation of
bid and the rates quoted online at the time of submission of bid and acceptance thereof together
with any correspondence leading thereto.
(b) Standard C.P.W.D. Form 8& GCC 2014 modified upto15.09.2015
19. For Composite Bids
19.1.1 The Executive Engineer in charge of the major component will call bids for the composite
work. The cost of bid document and Earnest Money will be fixed with respect to the combined
estimated cost put to tender for the composite bid.
19.1.2 The bid document will include following three components:
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 6
Part A:-CPWD-6, CPWD-8 including schedule A to F for the major component of the work,
Standard General Conditions of Contract for CPWD 2014 as amended/modified up to15.09.2015
Part B:- General / specific conditions, specifications and schedule of quantities applicable to
major component of the work (civil).
Part C:-Schedule A to F for major component of the work. (SE/EE in charge of major
component shall also be competent authority under clause 2 and clause 5 as mentioned in
schedule A to F for major components), General/specific conditions, specifications and schedule
of quantities applicable to minor component(s) of the work.
Port D & Port E : Schedule A to F for minor component of the work (SE/EE in-charge of major
component shall also be competent authority under clause 2 and clause 5 as mentioned in
schedule A to F for major components) General / specific conditions, specifications and Part-E
schedule of quantities applicable to minor components of one work.
19.1.3 The bidders must associate himself, with agencies of the appropriate class of
CPWDeligible to bid for each of the minor component individually.
19.1.4 The eligible bidders shall quote rates for all items of major component as well as for all
items of minor components of work.
19.1.5 After acceptance of the bid by competent authority, the EE in charge of major component
of the work shall issue letter of award on behalf of the President of India. After the work is
awarded, the main contractor will have to enter into one agreement with EE in charge of major
component and has also to sign two or more copies of agreement depending upon number of
EE's/DDH in charge of minor components. One such signed set of agreement shall be handed
over to EE/DDH in charge of minor component(s). EE of major component will operate Part A
and Part B of the agreement. EE/DDH in charge of minor component(s) shall operate Part C
along with Part A of the agreement.
19.1.6 Entire work under the scope of composite bid including major and all minor components
shall be executed under one agreement.
19.1.7 Security Deposit will be worked out separately for each component corresponding to the
estimated cost of the respective component of works.
19.1.8 The main contractor has to associate agency(s) for minor component(s) conforming to
eligibility criteria as defined in the bid document and has to submit detail of such agency(s) to
Engineer-in-charge of minor component(s) within prescribed time. Name of the agency(s) to be
associated shall be approved by Engineer-in-charge of minor component(s).
19.1.9 In case the main contractor intends to change any of the above agency/agencies during
the operation of the contract, he shall obtain prior approval of Engineer-in-charge of minor
component. The new agency/agencies shall also have to satisfy the laid down eligibility criteria.
In case Engineer-in-charge is not satisfied with the performance of any agency, he can direct the
contractor to change the agency executing such items of work and this shall be binding on the
contractor.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 7
19.1.10 The main contractor has to enter into agreement with contractor(s) associated by him for
execution of minor component(s). Copy of such agreement shall be submitted to EE/ DDH in
charge of each minor component as well as to EE in charge of major component. In case of
change of associate contractor, the main contractor has to enter into agreement with the new
contractor associated by him.
19.1.11 Running payment for the major component shall be made by EE of major discipline to
the main contractor. Running payment for minor components shall be made by the Engineer- incharge of the discipline of minor component directly to the main contractor.
19.1.12 Running payment of the major component shall be made by the Executive Engineer of
major discipline to the main contractor. Running payment for minor components shall be made by
the Engineer-in-Charge of the discipline of minor component directly to the main contractor.
19.1.13AThe composite work shall be treated as complete when all the components of the work
are complete. The completion certificate of the composite work shall be recorded by Engineer-incharge of major component after record of completion certificate of all other components
19.1.13B Final bill of whole work shall be finalized and paid by the EE of major component.
Engineer(s) in charge of minor component(s) will prepare and pass the final bill for their
component of work and pass on the same to the EE of major component for including in the final
bill for composite contract.
Executive Engineer,
Aizwal Central Division,
CPWD, Aizwal
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 8
360days
Time
&
date of opening of bid
Period of Completion
Earnest Money
08.10.2015
upto 3.00
P.M.
Rs. 16,06,272/-
CIVIL-Rs. 7,23,84,221/-
NIT No.
Name of
Location
Construction of Centre for
Disability Studies in Aizawl,
Mizoram.
(SH
:-C/O
Administration / Academic
block, Boy's cum Girls hostel
(D/S), Dining/Common room
and 1 no. Type-IV quarter (S/S)
including
water
supply,
sanitary
installations,
sewerage, drainage, manual
fire
alarm
system,
development and electrical
works.
04/2015-16/ACD/MZU/ACSD-II
Sl. No.
Work
&
Date
09.10.20
15
at
4.00
P.M.
1.
The intending bidder must read the terms and conditions of CPWD-6 carefully. He should
only submit his bid if he considers himself eligible and he is in possession of all the documents
required.
2. Information and instructions for bidders posted on website shall form part of bid
document.
3. The bid document consisting of plans, specifications, the schedule of quantities of various
types of items to be executed and the set of terms and conditions of the contract to be complied
with and other necessary documents can be seen and downloaded from website
www.tenderwizard.com/CPWD or www.cpwd.gov.in free of cost.
4. But the bid can only be submitted after depositing Processing Fee in favour of ITI
Limited and uploading the mandatory scanned documents such as Demand Draft or Pay order or
Banker's Cheque or Deposit at call Receipt or Fixed Deposit Receipts and Bank Guarantee of
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 9
Executive
Engineer
and
other
The contractors already registered on e-tendering portal will have option to continue by
paying tender processing fee at existing rates up to one year from the date of registration,
or to switch over to the new registration system without tender processing fee any time.
All new registrations from 01.04.2015 will be without tender processing fee.
5.Those contractors not registered on the website mentioned above, are required to get
registered beforehand. If needed they can be imparted training on online bidding process as per
details available on the website.
6.The intending bidder must have valid class-III digital signature to submit the bid.
7.On opening date, the contractor can login and see the bid opening process. After opening of
bids he will receive the competitor bid sheets.
8.Contractor can upload documents in the form of JPG format and PDF format.
9.Contractor must ensure to quote rate of each item. The column meant for quoting rate in
figures appears in pink colour and the moment rate is entered, it turns sky blue.
In addition to this, while selecting any of the cells a warning appears that if any cell is left
blank, the same shall be treated as 0.
Therefore, if any cell is left blank and no rate is quoted by the bidder, rate of such item shall
be treated as 0 (Zero)
List of Documents to be scanned and uploaded within the period of bid submission:
I.
II.
III.
Certificate of Registration for Sales Tax / VAT with Mizoram State Government and
acknowledgement of -up to date filed return if required.
IV.
An undertaking that The physical EMD shall be deposited by me/us with the EE
calling the tender in case I/we become the lowest tenderer within a week of the
opening of financial bid otherwise department may reject the tender and also take
action to withdraw my/our enlistment debar me/us from tendering in CPWD.
V.
VI.
The consent letter submitted to the enlisting authority for conservation of the enlistment
into composite category.
Executive Engineer,
Aizwal Central Division,
CPWD, Aizwal
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 10
CPWD-8
GOVERNMENT OF INDIA
CENTRAL PUBLIC WORKS DEPARTMENT
Branch: B&R Zone: NEZ-IICircle: SE, SCC
Item Rate Tender & Contract for Works
Tender for the work of Construction of Centre for Disability Studies in Aizawl,
Mizoram. (SH :-C/O Administration / Academic block, Boy's cum Girls hostel (D/S),
Dining/Common room and 1 no. Type-IV quarter (S/S) including water supply,
sanitary installations, sewerage, drainage, manual fire alarm system, development
and electrical works.
(i)
(ii)
09.10.2015
Executive Engineer
Aizawl Central Division
CPWD, Aizawl.
TENDER
I/We have read and examined the notice inviting tender, schedule, A, B, C, D, E & F
Specifications applicable, Drawings & Designs, General Rules and Directions, Conditions of
Contract, clauses of contract, Special conditions, Schedule of Rate & other documents and Rules
referred to in the conditions of contract and all other contents in the tender document for the work.
I/We hereby tender for the execution of the work specified for the President of India within the
time specified in Schedule F viz., schedule of quantities and in accordance in all respect with the
specifications, designs, drawing and instructions in writing referred to in Rule-1 of General Rules
and Directions and in Clause 11 of the Conditions of contract and with such materials as are
provided for, by, and in respect of accordance with, such conditions so far as applicable.
We agree to keep the tender open for sixty (60) days from the date of its opening of bid and not to
make any modification in its terms and conditions.
A sum of Rs. ___________*** is hereby forwarded in cash/receipt treasury challan/deposit at call
receipt of a scheduled bank/fixed deposit receipt of scheduled bank/demand draft of a scheduled
bank/bank guarantee issued by a scheduled bank as earnest money.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 11
Signature of Contractor
Postal Address
Address:
Occupation:
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 12
ACCEPTANCE
The above tender (as modified by you as provided in the letters mentioned hereunder) is
accepted by me for and on behalf of the President of India for a sum of Rs. ......
(Rupees.......
................................................................................................................................)
The letters referred to below shall form part of this contract agreement:(a)*
(b)*
(c)*
For & on behalf of the President of India.
Signatures.............................
Dated:
* To be filled in by EE
Designation............................
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 13
PROFORMA OF SCHEDULES
SCHEDULE A
Description
of item
2
Quantity
Place of issue
NIL
SCHEDULE 'C'
Description
2
Place of Issue
4
NIL
SCHEDULE D
a)
b)
c)
SCHEDULE E
Construction
of
Centre
for
Disability Studies in Aizawl,
Mizoram. (SH :-C/O Administration
/ Academic block, Boy's cum Girls
hostel (D/S), Dining/Common room
and 1 no. Type-IV quarter (S/S)
including water supply, sanitary
installations, sewerage, drainage,
manual
fire
alarm
system,
development and electrical works.
TOTAL
CIVIL COMPONENT
ELECTRICALCOMPONENT
(i)
Earnest Money :
(ii)
(iii)
Performance Guarantee
Security Deposit
79,29,399/-
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 14
SCHEDULE `F:
GENERAL RULES & DIRECTIONS:
Officer Inviting tender :
Executive Engineer,
Aizawl Central Division, CPWD
or
his successor in- charge of work
Definitions :
2 (v)
Engineer-in-charge
Executive Engineer,
Aizawl Central Division,CPWD
or
his successor in- charge of work
2(viii)
Accepting Authority
2 (x)
2 (xi)
2 (xii)
Department
9(ii)
15 %
DSR 2014 with correction slips up to
No. DG/DSR/08 dated 23.04.2015
CPWD
GCC 2014, CPWD Form 8 modified
&amendment up to 15.09.2015
including DGW/CON/287 dated
24.08.2015
Clause 1:
15 days
7 days
Clause 2:
Clause 2A:
NO
Clause 5:
30 days
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 15
Mile stones: Construction of disability study centre for National Institute for the
Orthopedically Handicapped at the premises of Mizoram University Aizawl
(Mizoram).SH: C/O Admn. block, Academic block, Boys and Girls Hostel, 1 no.
Type IV qtr. and development works.
Sl.
no.
Time
allowed in
days
(From
date of
start)
Amount to be withheld in
case of Non-achievement
of each physical Mile
stone(s) subject a total
maximum of 5% ( five
Percent) of the total
tendered value of work
80 days
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 16
120 days
150 days
180 days
4
(a) Admn. Block:
slab.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 17
210 days
260 days
Complete internal
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 18
300 days
330 days
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 19
360 days
360 days.
Note : Successful tenderer may request to the competent authority for rescheduling of above
mile stones before award of work.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 20
Authority to decide:
(i)
Extension of time
Executive Engineer,
Aizawl Central Division,CPWD
or
his successor in- charge of work
Clause 6,6 A
6A
Clause 10 A:
Listoftestingequipmentstobeprovidedbythecontractoratsitelab.:
7.Enameltrays(forefflorescencetestforbric
1. BalancesWeighingbalancewithrequiredbrassandironweig
ksandothertests).
ht
2. OvenElectrically operated, thermostatically 8. ISI marked 150 x 150 x 150 mm
controlled upto 2000C, Sensitivity 10C
concrete cube moulds as per site
requirement.
3. Brassandmetalsieveofrequiredsizefortestingcoa 9.100
tones
compression
testing
rseandfineaggregate
machine,
electrical
cum
manually
operated
4. Equipmentforslumptest
10. Sieve Shaker capable of 200mm and
SlumpCone,SteelPlate,TampingRod,SteelScalea
300 mm Sieve,manually operated with
ndScoop
timing switch assembly
11. Moisture meter.
5. VicatApparatus
6. Graduatedmeasuringcylinders200mland1000ml
capacity
Thecontractor
shallhavethefollowingfieldtestinginstruments
forcheckingofqualityofworkat fieldbyhimandbytheofficersofthedepartment
1. Steeltapes3meter/10meter
11. Screwdriver30cmslong
2. VernierCalipers(onenumberdigital)
12. Hammer100gms
3. Screwgauge(onenumberdigital)
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 21
4. Goodqualityplumbobs
5. Spiritlevelsminimum30cmlongwith3bubblesfor
horizontal/verticallevel
6. Wiregauge(circulartype)disc
15. Theodolite/Levellinginstruments/kits
7. Longnylonthread
8. Magnifyingglass
Yes
Clause 10 C:-
Yes, Applicable
Reinforcement bars
Not Applicable
3.
Reinforcement bars
(gradeFe500D) Secondary
Not Applicable
producers
to
be
followed
12 months
Not Applicable
Clause 12:
Type of work
12.2
&
12.3
Original Work
30% (thirty percent) for all except
foundation items.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 22
12.5:
Clause 16:
Competent Authority for deciding reduced
rates
Clause 18
List of Mandatory machinery, tools and plants to be deployed by the contractor at site.
Sl.no.
1.
6.
3 nos
7.
Welding Generator
1 no
3.
2 nos
8.
Welding transformer
2 nos
4.
3 nos
9.
1 no
5.
Needle vibrator(electrical/Petrol)
4 nos
2.
Qty.
Sl.no
Clause25
Dispute redressalCommittee(DRC)shall contain the following officers
(A) For total Claims more than Rs.25.0 Lac
S.N
1.
2.
3.
Constitution
Chairman
CasespertainingtoNEZ-IICPWD
Remarks
Member
Member
TheconcernedSE,in-chargeoftheworkwillputupthecase
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 23
CasespertainingtoNEZ-IICPWD
1.
Chairman
2.
Member
ExecutiveEngineer(P),TCD-I,CPWD, Agartala
3.
Member
Remarks
TheconcernedEE,in-chargeoftheworkwillputupthecase
Clause36(i):
Sl.
Minimum
No Qualification
of Technical
representative
Discipline
Designation
Graduate
Engineer
or
Diploma
Engineer
Principal Technical
representative
Civil
Graduate
Engineer
Project planning
/quality/Site/billing
Engineer
Minimum
experience
5 Year of
similar
composite
work
2 Year (for
Graduate)
or
5year (for
Diploma)
Nos.
1
(one) No.
1
(one) (1
Civil)
AssistantEngineersretiredfromGovernmentservicesthatareholdingDiplomawillbetreatedatpar
with Graduate Engineers.
Diploma holder with minimum 10 year relevant experience with a reputed
construction co. can be treated at par with Graduate Engineers for the purpose of such
deployment subject to the condition that such diploma holders should not exceed 50% of
requirement of degree engineers.
Clause42
(i)
(a)
Schedule/statement On
the
basis
of
fordeterminingtheoreticalquantityofcement&bit DelhiScheduleofRates2014modified/corre
umen
cted i n c l u d i n g c o r r e c t i o n s l i p N o .
DG/DSR/08 dated 23.04.2015
(ii)
Variationspermissibleontheoreticalquantiti
es
a)Cementforworkswithestimatedcostput
totendermorethanRs.5lakh.
b)Bitumenforallwork
2%plus/minus
c)Steelreinforcementandstructuralsteel
sectionsforeachdiameter,sectionandcategory.
d) All other materials.
2%plus/minus
2.5%plusonly&Nilonminusside
Nil
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 24
Sl.
No
DescriptionofItem
Ratesinfiguresandwordsatwhichrecoveryshall
bemadefromthecontractor.
Excessbeyond permissiblevariation
1.
Cement
Nil
2.
Steel Reinforcement
Nil
3.
4.
Structural Sections
Water-Proofing Materials
Nil
Nil
5.
Nil
Lessusebeyondthe
Permissiblevariation.
Not Permitted
Page 25
6. This guarantee will not be discharged due to the change in the constitution of the Bank or the
Contractor(s).
7. We, . (indicate the name of the Bank) lastly undertake not to revoke
this guarantee except with the previous consent of the Government in writing.
8. This guarantee shall be valid up to unless extended on demand by the
Government.
Notwithstanding anything mentioned above, our liability against this guarantee is restricted to Rs.
(Rupees ..) and unless a claim in writing is lodged with us within
six months of the date of expiry or the extended date of expiry of this guarantee all our liabilities
under this guarantee shall stand discharged.
Dated the .day of for. (indicate the name of the Bank)
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 26
*Date to be worked out on the basis of validity period of 6 months from last date of receipt of
tender.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 27
Existing Provision
Sl.No. Clause25(ii) 5th Paragraph
1
The arbitration shall be conducted in
accordance with the provisions of the
Arbitration and Conciliation Act-1996(26 of
1996) or any statutory modification or reenactment
thereof
and
the
rules
madethereunder and For the time being
In force shall apply to the arbitration
proceeding under this clause.
ModifiedProvision
Clause25(II) 5th Paragraph
The arbitration shall be conducted in the
accordance with the provisions of the
Arbitration and Conciliation Act-1996(26 of
1996)/The Jammu
&
Kashmir
Arbitration
and
Conciliation
Act,
1997(35 of 1997) (as the case may be ) or
ay statutory modification or re-enactment
thereof and the rules made thereunder and
for the time being in force shall apply to
the arbitration proceeding under this
clause.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 28
Existing Provision
Modified Provision
x) It shall be the duty of the contractor to x) It shall be the duty of the contractor to
ensure the disbursement of wages in the ensure the disbursement of wages through
presence of the Junior Engineer or any bank account of labour.
other authorised representative of the
Engineer-in-Charge who will be required to
be present at the place and time of
disbursement of wages by the contractor to
workmen.
xi) The contractor shall obtain from the
Junior Engineer or any other authorised
representative of the Engineer-in-Charge
as the case may be, a certificate under his
signature at the end of the entries in the
Register of Wages or the Wage-cumMuster Roll as the case may be in the
following form:-
Clause 5.1
The Contractor shall submit Programme
Chart (Time and Progress) for each mile
stone along with performance guarantee
and
get
it
approved
by the
Department. The Chart shall be prepared
in direct relation to the time stated in the
Contract documents for completion of
items of the works. It shall indicate the
forecast of the dates of commencement
and completion of various trades of
sections of the work and may be
amended as necessary by agreement
between the Engineer-in-Charge and the
Contractor within the limitations of time
imposed in the Contract documents, and
further to ensure good progress during the
execution of the work, the contractor shall
in all cases in which the time allowed
for any work, exceeds one month (save for
special jobs for which a separate
programme has been agreed upon)
complete the work as per mile stones given
in Schedule 'F'.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 29
Clause 7A
No Provision
Clause 7A
No Running Account Bill shall be paid
for the work till the applicable labour
licenses, registration with EPFO, ESIC
and BOCW Welfare Board, whatever
applicable are submitted by the
contractor to the Engineer-in-Charge
Clause 19
The contractor shall obtain a valid license
under the Contract Labour (R&A) Act, 1970
and the Contract Labour (Regulation and
Abolition) Central Rules, 1971 before the
commencement of the work, and continue
to have a valid license until the completion
of the work
Clause 19
The contractor shall obtain a valid license
under the Contract Labour (R&A) Act, 1970
and the Contract Labour (Regulation and
Abolition) Central Rules, 1971 before the
commencement of the work, and continue
to have a valid license until the completion
of the work
The contractor shall also comply with
provisions of the Inter-State Migrant
workmen (Regulation of Employment
and Conditions of Service) Act, 1979.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 30
59
2. Clause 19 L
The ESI and EPF contribution on the part of
employer in respect of this contract shall be
paid by the contractor. These contributions
on the part of the employer paid by the
contractor shall be reimbursement by the
Engineer-in-Charge to the contractor on
actual basis.
2. Clause 19 L
The ESI and EPF contribution on the part
of employer in respect of this contract shall
be paid by the contractor.
These
contributions on the part of the employer
paid by the contractor shall be
reimbursement by the Engineer-in-Charge
to the contractor on actual basis. The
applicable and eligible amount of EPF &
ESI shall be reimbursed preferably
within 7 days but not later than 30 days
of submission of documentary proof of
payment provided same are in order.
ii)
iii)
iv)
v)
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 31
Generals Rules & Directions of GCC Generals Rules & Directions of GCC
2014
2014
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 32
PART B
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 33
GENERAL CONDITIONS
1. The tenderer shall acquaint himself with the proposed site of work, its approach roads,
working space available before quoting his rates.
2.The work shall be executed and measured as per metric dimensions given in the Schedule of
quantities, drawings etc. (F.P.S. units wherever indicated are for guidance only).
3.Wherever any reference to any Indian Standard Specification occurs in the documents
relating to this contract , the same shall be inclusive of all amendments issued
upto15.09.2015.
4.Unless otherwise provided in the Schedule of quantities the rates bidded by the contractor
shall be all inclusive and shall apply to all heights, lifts, leads, depths and also for working in
or under water & foul conditions and nothing extra shall be payable to him on this account.
Payment for centering, shuttering, however if required to be done for floor to floor heights
greater than 3.5 m. shall be admissible at rates arrived at in accordance with clause-12 of
the agreement if the rates for the same are not specified / existing in the contract.
5. BYE-LAWS
i.
The building work will be carried out in the manner complying in all respects with
the requirements of relevant by laws of the local body under the jurisdiction of which the
work is to be executed or as directed by the Engineer-in-Charge and nothing extra will be
paid on this account.
ii.
Water tanks, taps, sanitary, water supply and drainage pipes, fittings and accessories should
conform to bye-laws and specifications of the Municipal Body/ Corporation where C.P.W.D.
specifications are not available. The contractor should engage licensed plumbers for the
work and get the materials (fixtures/fittings) tested by the Municipal Body/ Corporation
Authorities wherever required at his own cost.
iii.
The contractor shall comply with proper and legal orders and directions of the local or public
authority or municipality and abide by their rules and regulations and pay all fees and
charges which he may be liable.
iv.
If as per municipal rules the huts for labour are not to be erected at the site of work by the
contractors, the contractors are required to provide such accommodation as is acceptable to
local bodies and nothing extra shall be paid on this account.
v.
Royalty at the prevalent rates shall have to be paid by the contractor on all the boulders,
metals, shingle, sand and bajri etc. collected by him for the execution of the work, direct to
the Revenue Authority or authorised agent of the State Government concerned or Central
Government as the case may be.
6. SETTING OUT
i.
The contractor shall carryout survey of work area at his own cost, establish, maintain and
assume responsibility for grades, lines, levels and bench marks. He shall report any errors
or inconsistencies regarding grades, lines, levels, dimensions to the Engineer-in-Charge
before commencing work. It shall be responsibility of the contractor to ensure correct setting
out of alignment. Total station survey instrument only shall be allowed to be used for layout,
fixing boundaries, centre line etc. along with theodolites. Commencement of work shall be
regarded as the contractors acceptance of such grades, lines, levels and dimensions and no
claim shall be entertained at a later date for any errors found.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 34
ii.
If at any time, any error in the respect of setting out appears during the progress of the work,
the contractor shall, at his own expense rectify such error if so required, to the satisfaction of
the Engineer-in-Charge.
iii.
Though the site levels may be indicated in the drawings, the contractor shall ascertain
himself and confirm the site levels with respect to GTS bench mark from the concerned
authorities
iv.
The approval by the Engineer-in-Charge of the setting out by the contractor shall not relieve
the contractor of any of his responsibilities of any inaccuracy creeping in.
v.
The contractor shall be entirely and exclusively responsible for the horizontal, vertical and
other alignments, the level and correctness of every part of the work and shall rectify
effectively any errors or imperfections therein. Such rectifications shall be carried out by the
contractor at his own cost to the instructions and satisfaction of the Engineer-in-Charge.
vi.
Contractor(s) shall provide permanent bench marks, flag tops and other reference points for
the proper execution of work and these shall be preserved till the end of the work. All such
reference points shall be in relation to the levels and locations, given in the Architectural and
plumbing drawings. On completion of work, the Contractor(s) shall submit at his own cost
four prints of as built drawings to the Engineer-in-Charge. These drawings shall have the
following information.
a)Run off all piping and their diameters including soil waste pipes and vertical stacks.
b) Ground and invert levels of all drainage pipes together with locations of all manholes and
connections, upto outfall.
c) Run off of all water supply lines with diameters, location(s) of control valves, access panels
etc.
7. TEMPORARY WATER/ ELECTRICITY/ TELEPHONE CONNECTION FOR CONTRACTOR
i.
Arrangement of temporary telephone connection, water and electricity required by him, shall
be made by the Contractor at his own cost and also necessary permissions shall be obtained
by him directly from concerned authorities, under intimation to the Department. Also, all
initial cost and running charges, and security deposit, if any, in this regard shall be borne by
him. The Contractor shall abide by all the rules/ bye laws applicable in this regard and he
shall be solely responsible for any penalty on account of violation of any of the rules /
byelaws in this regard. Nothing extra shall be payable on this account.
ii.
The Contractor shall be responsible for maintenance and watch and ward of the complete
installation and water / electricity meter and shall also be responsible for any pilferage, theft,
damage, penalty etc. in this regard. The Contractor shall indemnify the Department against
any claim arising out of pilferage, theft, damage, penalty etc. whatsoever on this account.
Security deposit for the work shall be released only after No Dues Certificates are obtained
from the local Authorities from whom temporary electric/ water / telephone connection have
been obtained by the Contractor. Nothing extra shall be payable on this account.
iii.
The Department shall in no way be responsible for either any delay in getting electric and/or
water and/or telephone connections for carrying out the work or not getting connections at
all. No claim of delay or any other kind, whatsoever, on this account shall be entertained
from the Contractor. Also contingency arrangement of stand-by water & electric supply shall
be made by the Contractor for commencement and smooth progress of the work so that
work does not suffer on account of power failure or disconnection or not getting connection
at all. No claim of any kind whatsoever shall be entertained on this account from the
Contractor. Nothing extra shall be payable on this account.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 35
iv.
The Contractor shall arrange electricity at his own cost for testing of the various electrical
installations as directed by Engineer-in-Charge and for the consumption by the contractor for
executing the work. Also all the water required for testing various electrical installations, fire
pumps, wet riser / firefighting equipment, fire sprinklers etc. and also testing water supply,
sanitary and drainage lines, water proofing of underground sump, overhead tanks, water
proofing treatment etc. shall be arranged by the contractor at his own cost. Nothing extra
shall be payable on this account.
8. DRAWINGS
i.
The work shall be carried out in accordance with the Architectural drawings and structural
drawings, to be issued from time to time, by the Engineer-in-Charge. Before commencement
of any item of work the contractor shall correlate all the relevant architectural and structural
drawings, nomenclature of items and specifications etc. issued for the work and satisfy
himself that the information available from there is complete and unambiguous. The figure
and written dimension of the drawings shall be superseding the measurement by scale. The
discrepancy, if any, shall be brought to the notice of the Engineer-in-charge before execution
of the work. The contractor alone shall be responsible for any loss or damage occurring by
the commencement of work on the basis of any erroneous and or incomplete information
and no claim whatsoever shall be entertained by the department on this account.
ii.
In case of any discrepancy in the item given in the schedule of quantities appended with the
bid and Architectural drawings relating to the relevant item, the former shall prevail unless
and otherwise given in writing by the Engineer-in-Charge.
9. COMPLETION CERTIFICATE
The date of completion as prescribed under clause 8 of the contract, on completion of
the work will be the date on which the required sets of completion drawings/ plans and inventory
duly verified by the Engineer-in-Charge along with handing over notes in the format approved by
the Engineer-in-Charge are submitted by the Contractor in the office of the Engineer-in-Charge.
10. The contractor shall give a performance test of the entire installation(s) as per
standing specifications before the work is finally accepted and nothing extra whatsoever
shall be payable to the contractor for the test.
11. The contractor shall bear all incidental charges for cartage, storage and safe custody of
materials issued by department or procured by the contractor and nothing extra shall be
payable to the contractor on their accounts.
12. The full nomenclature of items shall be adopted in preparing abstract of final bill in
the measurement book and also in the bill form for final bill.
13. The bidder shall abide by the rules and regulations under relevant State VAT Act/ Work
Contract Tax Act, Workers Welfare Cess Act etc., as amended from time to time and
deductions shall be made at source as per the provisions of above stated Acts from the
gross value of the work done, which shall be recovered from each running bill including
final bill of the work by the Engineer-in-Charge. Nothing extra on account of this deduction
shall be paid.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 36
ii.
The cement shall be brought at site to bulk supply of approximately 100 tones or as
decided by the Engineer-in-Charge
iii.
The cement godown of the capacity to store a minimum of 2000 bags of cement
shall be constructed by the contractor at site of work for which no extra payment shall be
made Double lock provision shall be made to the door of the cement godown. The keys of
one lock shall remain with the Engineer-in-Charge or his authorized representative and the
key of the other lock shall remain with the contractor. The contractor shall be responsible
for the watch & ward and safety of the cement godown. The contractor shall facilitate for
the inspection of the cement godown by the Engineer-in-Charge at any time.
iv.
The contractor shall supply free of charge the cement required for testing, the cost of tests
shall be borne by the contractor / Department in the manner indicated below.
(i) By the contractor, if the results show that the cement does not conform to relevant BIS
codes.
(ii) By the Department, if the results show that the cement conforms to relevant BIS codes.
v.
The actual issue and consumption of cement on work shall be required and proper
accounts maintained as provided in clause 10 of the contract. The theoretical consumption
of cement shall be worked out as per procedure prescribed in clause 42 of the contract or
as per other condition/ specification of the bid documents if otherwise applicable.
vi.
Cement brought to site and cement remaining unused after completion of work shall not be
removed from site without written permission of the Engineer-in-Charge.
vii.
For all kind of RCC works only O.P.C. grade 43 shall be used.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 37
vi. For checking nominal mass, tensile strength, bend test, re-bend test etc. specimen of
sufficient length shall be cut from each size of the bar at random at frequency not
less than that specified below:-
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 38
Size of bar
10 mm to 16 mm dia
bars
vii. The contractor shall supply free of charge the steel required for testing including its
transportation to testing laboratories. The cost of tests shall be borne by the contractor.
viii. The actual issue and consumption of steel on work shall be regulated and proper accounts
maintained as provided in clause 10 of the contract. The theoretical consumption of steel
shall be worked out as per procedure prescribed in clause 42 of the contract and shall be
governed by condition laid therein.
ix. Steel brought to site and steel remaining unused shall not be removed from site without the
written permission of the Engineer-in-Charge.
x. In case contractor is permitted to use TMT reinforcement bars procured from ISPs or
secondary producers then
a)
The base price of TMT reinforcement bars as stipulated under schedule F shall be
reduced by Rs. 7000/- per MT **
b) The rate of providing & laying TMT reinforcement bars as quoted by the contractor
in the tender shall also be reduced by Rs. 8.05 per kg**.
**
i. The contractor shall take instructions from the Engineer-in-Charge for stacking of materials in
any place. No excavated earth or building material shall be stacked on areas where other
buildings, roads, services of compound walls are to be constructed.
ii. The contractor shall be fully responsible for the safe custody of the materials even if the
materials are under double lock system.
iii. Contractor shall construct suitable godowns, yards at the site of work for storing all other
materials so as to be safe against damage by sun, rain, damages, fire, theft etc. at his own
cost and also employ necessary watch and ward establishment for the purpose at his cost.
iv. Drilling holes to secure fastener/ screws in walls and chase cutting in the walls wherever
necessary shall be done by mechanical means i.e. by hammer drill machine & the chase
cutting machine respectively for which nothing extra will be paid to the contractor.
v. Any cement slurry added over base surface (or) for continuation of concreting for better bond
is deemed to have been in built in the items and nothing extra shall be payable (or) extra
cement considered in consumption on this account.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 39
17-TESTING OF MATERIAL
i. The contractor shall procure all the materials in advance so that there is sufficient time for
testing and approving of the material and clearance of the same before use in work.
ii. In case of concrete and reinforced concrete work, the contractor shall be required to make
arrangement for carrying out compression strength tests at his own cost. He shall render all
assistance for the preparation of cubes, safe custody of the same proper curing and carriage
upto the laboratory where the test is to be performed.
iii. Time allowed for execution of the work provided in clause 5 of Schedule F is inclusive of the
time required for any kind of testing of materials and preparation of Design mix of cement
concrete for all R.C.C. work, time required for initial load testing / routine load testing of piles
and time required for testing of weld etc.
iv. Samples of various materials required for testing shall be provided free of charge by the
contractor. Testing charges, if any, shall be borne by the department.
However in case
samples fail in testing, the testing charges if any shall be borne by the contractor. All other
expenditure required to be incurred for taking the samples; conveyance, packing etc. shall be
borne by the contractor himself
18.
DEFECT LIABILITY:
The contractors liability for rectification of defects which in the opinion of Engineer-incharge are not due to natural calamity during the defect liability period from the final date of
completion as per clause 17 shall be limited to rectification of defects including replacement as
follows.
Sl.
No.
1
Description
Defect Liability
Concrete
Brick work
Rectification of
Joinery
Builders Hardware
Roof treatment
Plastering
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 40
Sl.
No.
8
10
11
12
13
14
15
Description
Defect Liability
Flooring
16
Water Proofing
17
General
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 41
ADDITIONAL SPECIFICATIONS
1. EARTH WORK:i. Excavation shall be undertaken to the width of footing including necessary margins for
construction operation as per drawing or directed otherwise. Where the nature of soil or the
depth of the trench and season of the year, do not permit vertical sides, the contractor at
his own expense shall put up the necessary shoring, strutting and planking or cut slopes
with or without steps, to a safer angle or both with due regard to the safety of personnel
and works and to the satisfaction of the Engineer. Measurement of plan area of excavation
for payment shall be permitted only.
ii. All the major excavation shall be carried out by mechanical excavator. No extra payment
shall be made for that.
iii. Disposal of surplus earth shall be done as per direction of Engineer-in-charge.
2. Brick Work.
i. Bricks shall be obtained from kilns approved by the Engineer-in-Charge and shall be of
nominal size as per CPWD specification for non-modular bricks of class designation 7.5
N/mm2.
ii. Dimensional tolerance: - The dimension tolerance shall be as per CPWD specification Vol
I,Para 6.1.3.3.
iii. The Bricks shall be fully saturated with water by dipping in water tank just before utilizing in
the work so that it does not soak any moisture from mortar. For ensuring proper dipping of
bricks in water, the contractor shall always maintain a portable drum/ PVC tank filled with
water nearby the location where brick masonry is in progress. If at any time unsaturated
bricks are found used in the work, such work shall be dismantled and redone by using
saturated bricks. All these operations shall be done by the contractor at his own cost and
nothing extra shall be paid to the contractor for all these operations.
3. R.C.C. Work.
3.1Ingredients:i. Coarse Aggregate:
a. The maximum size of stone aggregates shall be 20mm nominal.
b. The Contractor shall make separate dedicated arrangement for washing of stone aggregate
at site of work. The stone aggregate immediately on bringing at site of work, shall be
washed to remove all dirt, silt and earth from it and then the washed stone aggregate shall
be kept separately for use in the work. Unwashed and washed stone aggregate shall be
kept separately. If at any time unwashed stone aggregate is found used in the work; such
work shall be dismantled and redone by using washed stone aggregate. All these
operations shall be done by the contractor at his own cost and nothing extra shall be paid
to the contractor for all these operations.
c. All stone aggregate and stone ballast shall be of hard stone variety to be obtained from
approved quarries or any other source to be got approved by the Engineer-in- Charge.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 42
and CPWD
iv. Cement : It shall be of OPC 43 grade and shall conform to IS: 8112.
v. Admixtures: Wherever required, admixtures of approved quality shall be mixed with
concrete to achieve the desired workability within specified water cement ratio. The
admixtures shall conform to IS: 9103. The chloride content in the admixture shall satisfy the
requirement of BIS: 5075. The total amount of chlorides in the admixture mixed concrete
shall also satisfy the requirements of IS: 456:2000.The contractor shall not be paid anything
extra for admixture required for achieving desired workability without any change in
specified water cement ratio for RCC/CC work.
3.2.
MIX DESIGN.
i. The Contractor shall design mixes for each class of concrete meeting the requirements as
specified as per clause 5.8.4.1 of CPWD specifications 2009 Vol. I with correction slips
upto15.09.2015
ii. One month in advance to commencement of concreting work, the contractor shall submit
proposal of mix designs and test results from approved laboratory for the approval of the
Engineer-in-Charge. No concreting shall be done until the mix design is approved.
iii. All cost of mix designing and testing connected therewith including charges payable to the
laboratory shall be borne by the Contractor.
iv. The R.C.C. work shall be done with Design Mix Concrete unless specified. In the
nomenclature of items, wherever letter M has been indicated, the same shall imply for the
Design Mix Concrete. For the nominal mix in RCC, CPWD specifications shall be followed.
The Design Mix Concrete will be designated based on the principles given in IS: 456,
10262 & SP 23. The contractor shall design mixes for each class of concrete indicating
the concrete ingredients and proportions that will result in concrete mix meeting
requirements specified. In case of use of admixture and or white cement, the mix shall be
designed with these ingredients as well. The specification mentioned herein below shall be
followed for Design Mix Concrete.
3.3 Grade of Concrete: i. The characteristic compressive strength of all grades of Concrete manufactured/ produced
shall be as per CPWD Specifications 2009 Vol. I with correction slip upto15.09.2015.
ii. The mix will be designed for minimum workability as specified in Para 7 of IS: 456: 2000.
iii. For all grade of design mix concrete manufactured/produced, the Minimum cement
contents in the concrete shall be 310 kg/cum of concrete. Also irrespective of grade of
concrete the maximum cement content shall not be more than 500 kg/cum of concrete.
These limitations shall apply for all type of concrete of all strength.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 43
iv. Actual cement content in each grade of concrete for various design conditions of variables
shall be established by design mixes with in the limit.
v. The concrete mix design shall be done by the contractor at his own cost through one of the
following laboratories/Test houses:
(i)
NIT, Silchar
(iv)
vi.
vii.
For ensuring proper curing during the curing period, water shall be kept standing on the
horizontal surface whereas the vertical surface of Concrete/RCC shall be kept covered
with wet thick gunny bags/ jute cloth for which nothing extra shall be payable.
3.4
The mix design for a specified grade of concrete shall be done for a target mean
compressive strength
_fck = fck + 1.65s
Where fck = Characteristic compressive strength at 28 days.
S = Standard deviation which depends on degree of quality control.
The degree of quality control for this work is good for which the standard deviation (s)
obtained for different grades of concrete shall be as follows:Sl No
1
2
3
4
5
GRADE OF CONCRETE
M-15
M-20
M-25
M-30
M-35
STANDARD DEVIATION
3.5
4.6
5.3
6.0
6.3
Out of the six specimen of each set, three shall be tested at seven days and remaining
three at 28 days. The preliminary tests at seven days are intended only to indicate the
strength to be attained at 28 days.
3.5
The concrete shall be sourced from ready mix concrete plants or from on site/ off site
batching and mixing plant conforming to IS: 4925 or suitable weigh batching system as
approved by Engineer in charge. It shall have the facilities of presenting the quality to be
weighed with the suitable out off system when the same is achieved. All other operation in
concreting work like Mixing, Slump, Laying/ placing of concrete, compaction, curing etc. not
mentioned in this particular specification for design mix of Concrete shall be as per the IS:
456- 2000 and Additional / special condition forming part of this bid document.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 44
3.6
PREPERATION
OF
MIXES
AS
PER
APPROVED
CONDUCTING CONFORMITY TEST AT FIELD LAB:-
DESIGN
MIX
AND
The contractor shall make the cubes of trial mixes as per approved Mix design at
site laboratory for all grades, in presence of Engineer in charge using sample of
approved materials proposed to be used in the work, prior to commencement of concreting
and get them tested in his presence to the entire satisfaction for 7 days & 28 days. Test
cubes shall be taken from trial mixes as follows:
For each mix, a set of six cubes shall be made from each of the three consecutive batches.
Three cubes from each set of six shall be tested at age of 28 days. The cubes shall be
made, cured, transported and tested strictly in accordance with specifications. The
average strength of nine cubes at age of 28 days shall exceed the specified target mean
strength for which design mix has been approved, the evaluation of test results will be
done as per IS: 456-2000.
WORK STREGTH TEST: - TEST SPECIMEN
Sample from concrete shall be taken as per IS 1199.Work strength test shall be
conducted in accordance with IS: 516 on random sampling. Each test shall be
conducted on six specimens, three of which shall be tested at 7 days and
remaining three at 28 days. Additional samples shall be prepared as per the direction of
Engineer in charge for testing cured by accelerated method as described in IS: 9103.
TEST RESULT OF SAMPLE
The test result of the sample shall be the average of the strength of three specimens.
The individual variation shall not be more than +15 percentage of the average. If more,
the test results of the sample are invalid. At least 10 % of the total test shall be done at
the laboratory as directed by the Engineer-in-Charge, remaining tests will be done
in the laboratory established at site by the contractor.
3.7. STANDARD OF ACCEPTANCE
Standard of acceptance shall be same as specified in CPWD Specifications 2009 Vol. I with
correction slip upto15.09.2015 in pursuance to IS 456:2000.
3.7.1. In order to keep the floor finish as per architectural drawings and to provide required
thickness of the flooring as per specifications, the level of top surface of RCC shall be
accordingly adjusted at the time of its centering, shuttering and casting for which nothing
extra shall be paid to the Contractor.
4.8
Quality control of ready mixed concrete will be divided into three convenient areas:
Forward control, immediate control, Retrospective control.
A) FORWARD CONTROL
Forward control and consequent corrective action are essential aspects of quality control. It
includes:i. Control of Purchased Material Quality
It shall be assured that all the materials purchased and used in the production of
concrete conform to the stipulation of the relevant agreed standards with the material
supplier and the requirements
of the product mix design and quality control
procedures.
This can be accomplished by visual checks, sampling and testing,
certification from material supplier and information/ data from material supplier.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 45
Weighing (correct reading of batch data and accurate weighing). For each load, written,
printed or graphical records shall be made of the weights of the materials batched, the
estimated slumps, the total amount of water added to the load, the delivery tickets number
for that load and the time of loading the concrete into the truck.
b. Visual observation of concrete during production and delivery or during sampling and
testing of fresh concrete (assessment of uniformity, cohesion, workability, adjustment to
water content). The workability of the concrete shall be controlled on a continuous basis
during production and any necessary corrective action taken.
c.
Retrospective Control
Retrospective control covers:
a. Sampling of concrete, testing, monitoring of results.
b. Any property of materials or concrete such as aggregate grading, slump, air content,
but it is particularly associated with 28 day cube strength because of its very nature
as it cannot be measured ahead of or at the time of manufacture.
c. Weigh bridge checks of laden and unladen vehicle weights.
d. Stock control of materials.
e. Diagnosis and correction of faults identified from complaints.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 46
Control of designed and the prescribed mixes: a quality control system shall be operated
to control the strength of designed mixes to the required levels. The system shall include
continuous analysis of result from cube tests to compare actual with the target values
together the procedures for modifying mix proportions to correct for observed differences.
For prescribed mixes periodic and systematic checks shall be made to ensure that the
cementations materials contents of prescribed mixes comply with their mix proportion
3.9 FORM WORK
In provision of CPWD specification 2009 Vol. I with correction slipsupto17.02.15and R.C.C.
Work (in pursuance to I.S. 456-2000) in respect of form work it is provided that basically only
steel shuttering shall be adopted in general. However, a combination of steel and shuttering ply
conforming to I.S: 848-1974 and I.S: 5539 may be allowed by the Engineer-in-Charge in
consideration of the special request of the contractor to maintain quality and speed of the
work. In such cases the use of shuttering ply shall be permitted only for circular columns, beam
sides and bottom and in other locations wherever it is felt necessary on account of
difficulty in using steel shuttering in such locations. But in other areas like slab,
rectangular/square columns etc. steel shuttering shall be invariably used. However, no extra
payment or deduction will be admissible or made for use of shuttering ply. All prop, bracing,
scaffolding etc shall be in steel. To maintain the quality and speed the contractors have to
arrange and bring the following minimum quantities steel centering shuttering with necessary
steel vertical props, horizontal and diagonal bracings before execution of the following items of
work.
i.
Foundation and footings.
200 sqm.
ii.
Beams.
500 sqm.
iii.
Columns.
250 sqm
iv.
Slab
700 sqm
v.
Steel props
1000 cum space
The aforesaid quantities of shuttering materials should be kept at site for execution of the
columns, footings and beams.
3.10. REINFORCEMENT
i. The rate of item of reinforcement of RCC work includes all operations including straightening,
cutting, bending, welding, binding with annealed steel or welding and placing in position at all
the floors with all leads and lift complete as per CPWD Specifications.
ii. The contractor shall provide approved type of support for maintaining the bars in position and
ensuring required spacing and correct cover of concrete to reinforcement as called for in the
drawings, spacer blocks of required shape and size. Chairs and spacer bars shall be used in
order to ensure accurate positioning of reinforcement.
iii. To ensure proper cover, only factory made round type cover blocks of same mix shall be
used to avoid displacement of bars in any direction.
iv. Element of reinforcement as per standard design is included in the item of brick masonry
manholes. Therefore, the reinforcement used in the manholes shall not be separately
measured for payment under the item of reinforcement.
v. Before placing the reinforcement bars in position, contractor shall submit the bar bending
schedule indicating the shape of bar, type/ designation of bar, number of bars, the diameter
bars, quantity of reinforcement etc., as per structural drawing for approval by the Engineer-inCharge in writing. After the approval of the bar bending schedule by the Engineer-in-Charge,
the reinforcement shall be placed in position and thereafter it shall be measured in the
measurement book and got test checked of its accuracy before embedding or before placing it
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 47
WOOD WORK
The samples of species of timber to be used shall be deposited by the contractor with the
Executive Engineer before commencement of the work. The contractor shall produce cash
vouchers and certificate from standard kiln seasoning chemically pressure treatment
plant operators about the timber section to be used on the work having been kiln
seasoned chemically pressure treated by them, failing which it would not be to accept as
kiln seasoned & chemically pressure treated.
ii.
Specified timber shall be of good quality and well seasoned. It shall have uniform colour,
reasonably straight grains and shall be free from knots, cracks, shakes and sapwood.
iii.
Wood work shall not be painted, oiled or otherwise treated before it has been approved by
the Engineer-in-Charge.
iv.
All portion of timber including architrave abutting against masonry concrete stone or
embedded in ground shall be painted with approved wood preservative or with boiling coal
tar.
v.
All fittings and fixtures shall be got approved from the Engineer-in-Charge before
procurement well in advance and the approved samples shall be kept at site till completion
of the work
vi.
Factory made shutter, as specified shall be obtained from factories approved by the Chief
Engineer-NEZ-II, NEZ I,NEZ of CPWD and shall conform to IS: 2202 (Part-I) 1977. The
contractor shall inform well in advance to the Engineer-in-Charge the names and address
of the factory where from the contractor intends to get the shutters manufactured. The
contractor will place order for manufacture of shutters only after written approval of the
Engineer-in-Charge in this regard is given.
The contractor is bound to abide by the
decision of the Engineer-in-Charge and recommend a name of another factory from the
approved list in case the factory already proposed by the contractor is not found competent
to manufacture quality shutters. Shutters will, however, be accepted only, if this meet the
specified tests. The contractor will also arrange stage-wise inspection of the shutters at
factory by the Engineer-in-Charge or his authorized representative. Contractor will have
no claim if the shutters brought at site are rejected by Engineer-in-Charge in full lot due to
bad workmanship/quality. Such shutters will not be measured and paid and the contractor
shall remove the same from the site of work within 7 days after the written instructions in
this regard are issued by Engineer-in-charge or his authorized representative.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 48
vii.
viii.
Original purchase vouchers and delivery challan from the factory in support of having
purchase the factory made door shutters from the approved factory, shall have to be
produced to the Engineer-in-Charge for verification.
ix.
Inspection of shutters shall be carried out for dimensions & tolerances, size & type general
construction & workmanship, finish & glazing at the following frequency: Sl no
Sample Size
Upto 25
26 to 50
51 to 100
101 to 150
13
151 to 300
20
301 to 500
32
501 to 1000
50
80
1
2
3
4
5
6
7
8
Lot Size
x.
xi.
Testing The shutters shall be tested for species seasoning & treatment, defects in the
timber, panel material, construction & workmanship in the approved Govt. Laboratory at the
frequency mentioned in CPWD specification. If shutters are found defective in any one of the
criterion double the shutter shall be tested & if found permissible can be accepted. If shutter is
found defective in more than one criterion, the whole lot shall be rejected.
xii. Finish
a)
b)
c)
5. STEEL WORK:
i. The steel doors, windows, ventilators and composite units shall be got fabricated in Work
shop approved by the Chief Engineer concerned.
ii.
The M.S. plate clamps 15x6mm thick for holding arrangements are to be provided and
added as per site conditions. The rate is inclusive of the cost of such clamps.
iii.
All welded steel work shall be tested for quality of weld as laid down in IS: 822:1970 before
actual erection, unless otherwise specified in the nomenclature of the item.
iv.
In the MS Tee/angle iron frames for doors, four numbers S S hinges for each door
shutters and one no. 50mm MS hinge for wooden cleat wherever necessary, the cost of
which are deemed to include in the rate of the item, shall have to be provided.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 49
6. SANITARY INSTALLATIONS / WATER SUPPLY / DRAINAGE:i. The contractor at his own cost shall submit schematic drawing of water supply and sanitary
installation showing details of layout, including internal water supply and drainage details,
showing the detail of water supply lines including fittings diameter wise and fixtures
connecting to soil waste through traps and connection of W.C. to main shaft pipe for
drainage including its ventilation system for approval of Engineer-in-Charge.
ii. For the work of water supply and sanitary installations, the contractor shall engage the
approved licensed plumbers and submit the name of proposed plumbing agencies with their
credentials for approval of the Engineer-in-Charge.
iii. All PVC pipes and PVC fittings to be provided shall be able to sustain 6 kg/cm2
hydraulic pressure.
internal
iv. The tendered rates shall include the cost of cutting holes in walls, floors, RCC slabs etc.
wherever required and making good the same for which nothing extra shall be paid.
v. The Centrifugally spun cast iron pipe IS: 3989-1984 wherever necessary shall be fixed to
RCC columns, beams etc. with rawl plugs of approved quality and nothing extra shall be paid
for on this account.
vi. The Centrifugally spun cast iron pipe IS: 3989-1984 wherever necessary shall be fixed to
RCC columns, beams etc. with rawl plugs of approved quality and nothing extra shall be paid
for on this account.
vii. Cutting of centrifugal cast (spun) iron pipes wherever required shall be done by
electric machine. Pipes of different lengths as required having sockets will be brought to site
and used in the work. No collar will be permitted to be used in the work. If at any place collar
is found used, no payment of the pipes connecting that collar and the sanitary fittings
thereon shall be made in any case.
viii. GI tank nipples of appropriate size shall be used as per written approval of the Engineer-inCharge for making connection of pipes with the PVC water storage tanks.
ix. Nothing extra for providing & fixing CP Brass caps /extension pieces wherever required for
CP Brass fittings shall be paid beyond the rates payable for corresponding CP Brass fittings
x. Cleaning and Disinfection of Pipelines:On completion of hydraulic tests and before a pipe is disinfected, it shall be proved to be free
from obstruction, debris and sediment by scouring or by any other process which the
Engineer-in-charge may prescribe. Upon satisfactory completion of testing and cleaning, the
pipelines shall be disinfected as order. Chlorine solution shall be applied at the charging
point as the pipeline is being filed and dosing shall be continued until the pipeline is full and
at least 50 parts of chlorine per million parts of water have been made available and
distributed evenly. If ordinary bleaching power is used, proportions will 150 gms of power to
1000 litre of water. If a proprietary brand is used, the proportion shall be as specified by the
manufacturer. The treated water shall be left in pipeline for a period as directed but not
exceeding 24 hours chlorine residual tests shall be taken at various points along the pipeline.
The disinfection process shall be repeated until the sample of water taken from the pipeline
are declared fit for human consumption by a recognized laboratory
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 50
xi. The entire responsibility for the quality of work will however rest with the building contractor
only and he shall submit a Guarantee Bond for five years as per Proforma at ANNEXURE-A2. 5% (five percent) of the cost of these items would be retained as Guarantee Money (in
addition to general security deposit mentioned in the Schedule-E) by the government and
the amount so deducted would be released after five years from the date of expiry of
maintenance period prescribed in the contract after the date of completion of the entire work
under the agreement, if the performance of the items is found satisfactory by the Engineerin-charge.
xii. If any defect is noticed during the guarantee period, the contractor should rectify it within
seven days and if not attended to the same will be got done from another agency at the risk
and cost of contractor.
7.
i.
The variation in consumption of material shall be governed as per CPWD specification 2009
Vol. I & II with correction slips upto 15.09.15and clauses of the contract to the extent
applicable. The following specific clauses shall govern the variation in consumption of pig
lead.
ii.
The pig lead for caulking of joints of SCI pipes shall be issued as per theoretical
consumption for SCI pipes of size 100mm, 75mm, 50mm at 0.98kg, 0.88kg, and 0.77
kg. per joint respectively. Over and above the theoretical quantities of lead as worked out,
variation of 5% shall be allowed for wastage etc. Any difference between the actual
consumption of pig lead and theoretical consumption worked out on the above basis i/c the
authorised variation shall be recovered at rates in schedule B plus 10% in case material
issued by department. Where the pig lead is arranged by the contractor, in case variation is
on higher side 5% will be allowed. In case the variation is on lower side, the quantity of pig
lead used less shall be recovered from the contractor at market rate to be determined by
Engineer-in-Charge whose decision in the matter will be final.
iii.
8:-WATER PROOFING
i.
The contractor must associate himself with the specialized firm to be approved by the
Engineer- in-Charge in writing, for integral cement based water proofing treatment for
sunken floors and on roofs. 10 years guarantee in prescribed Performa at Annexure-A shall
be given by the contractor. In addition, 10% (ten percent) of the cost of these items
would be retained as guarantee money to watch the performance of the work done.
However half of this amount retained would be released after five years, if the performance
of the work done is found to be satisfactory. If any defect is noticed during the guarantee
period, it should be rectified by the contractor within seven days and if not attended to, the
same will be got done by the Engineer- In-Charge through another agency at the risk and
cost of the contractor. The retained guarantee money could be released to the contractor, if
he submits FDR of equal amount having maturity period not less than guarantee period.
Before execution of the items of integral water proofing treatment/finishing work, the
contractor must submit the following details and get the same approved by the Engineer-inCharge.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 51
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 52
vii. For providing granite stone in counters, window sills, kitchen platforms and other similar
locations, the rate shall deemed to include semicircular mirror finished and mirror polished
pre-molding of the free/ exposed edges which shall have to be done and nothing extra shall
be paid on this account. Further for granite stone upto 2 meter, for treads of steps and risers,
kitchen counters, window sills and any other locations wherever decided by the Engineer-inCharge, single stone shall be used for which nothing extra shall be paid.
viii. The colour and shade of the granite and granite tiles shall be decided by the Engineer-inCharge.
10. CERAMIC GLAZED TILES.
i. The 1st quality ceramic glazed wall tiles shall be provided and fixed as per the relevant item
appearing in the schedule and shall have a minimum thickness of 5 mm.
ii. The 1st quality ceramic glazed floor tiles shall be provided and fixed as per the relevant item
appearing in the schedule and shall have a minimum thickness as per manufacturer's
specifications.
11. FLOORING
i. The rate of items of flooring is inclusive of Providing Sunken Flooring in Bathrooms, Kitchen,
W.C., etc. and nothing extra on this account is admissible.
ii. The vitrified tiles shall be as specified in the item. The tiles shall be of specified colours as
shown in the drawings and will be laid in pattern as per architectural drawings. Nothing extra
shall be paid for laying tiles in specific pattern. The tiles shall be of first quality of approved
make.
iii. Proper gradient shall be given to flooring for toilets, verandah, kitchen, courtyard etc. so that
the wash water flows towards the direction of floor trap. Any reverse slop if found, shall be
made good by the contractor by ripping open the floor/grading concrete and nothing shall be
paid for such rectifications.
iv. The flooring and skirting will be executed as per pattern shown in the Architectural drawings
and as per approval of Engineer-in-Charge and nothing extra shall be payable on this
account.
v. Samples of flooring material are to be deposited well in advance to the Engineer-in-Charge
for approval. Approved samples should be kept at site with the Engineer-in-Charge and the
same shall not be removed except with the written permission of Engineer-in-Charge. No
payment whatsoever will be made for these samples.
vi. The rate shall include the cost of all materials and labour involved in all the operations.
Nothing extra shall be paid for use of cut/sawn tiles in the work.
12. FINISHING
i. The Primer, Synthetic Enamel paint, distemper etc., of makes as approved by the Engineer
in charge and of low VOC, shall only be used and brought to the site of, work in the original
sealed containers. The material brought to the site of work shall be sufficient for at least 60
days of work. The material shall be kept under the joint custody of contractor and
representative of the Engineer-in-Charge. The empty containers shall not be removed from
the site till the completion of the work without permission of the Engineer-in-Charge.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 53
ii. Brand and trade name of the paint to be used in the work shall be got approved in writing
from the Engineer-in-Charge before application of the samples of different shades. After the
written approval of the Engineer-in-Charge about brand, trade name, sample and shades of
the paints the contractor shall make bulk procurement of the paint. Before start of the item of
painting, the original purchase vouchers, delivery challan of purchase of full quantity of paint
materials shall have to be produced by the contractor to the Engineer-in-Charge.
The contractor shall bring full quantity of required painting material at site and get it
inspected from the Engineer-in-Charge before start of the item of painting.
ii. Samples of doors, windows and ventilators as per the drawings approved by the Engineerin-Charge shall be fabricated and got approved by the Engineer-in-Charge before taking up
the execution of these items of work.
iii. The aluminium sections shall be jointed to each other wherever required with extruded
aluminium angle cleats of suitable size and of thickness not less than 6mm for doors and
4mm for windows and ventilators with stainless steel screws. Unless otherwise specified all
joints shall be mitred.
iv. Various tests on aluminium sections shall be conducted in accordance with the relevant
provisions of IS:1868 ( anodic coatings on aluminium and its alloys) and IS:5523 ( Method
of testing anodic coating on aluminium and its alloys).
v. The fabricated aluminium frame work shall be given a lacquer coating which shall be
maintained during the entire period of construction to prevent damage to the anodic coating
of aluminium sections. The surface shall be cleaned and polished before handing over the
works.
vi. The doors, windows, ventilators, fixed glazing etc. individually or forming composite unit
shall be provided with glazing and panelling as specified with neoprene felt. Glazing and
panelling shall be fixed with aluminium snap beading. The sliding shutters of windows shall
be provided with nylon pullers with concealed bearings, aluminium stoppers and special
locking arrangements as approved by the Engineer-in-Charge. The interlocking styles of
sliding windows shall be provided with PVC/ neoprene weather sealing gaskets. The
windows with side hung shutters shall be provided with best quality heavy type anodized
aluminium hinges with stainless steel pins/bolts, anodized aluminium peg stays and
fasteners of suitable size and shape.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 54
vii. For the purpose of payment, the weight of each door, window, ventilator, louvered window,
fixed glazing etc. individually or forming composite unit shall be the actual weight of
extruded aluminium sections, cleat angles and aluminium snap beading excluding the
weight of all fittings & fixtures. If the variation between the actual unit weight and unit
weight specified in the manufacturers catalogue is more than +10%,The materials shall be
rejected as being substandard. The cost of hinges, locking arrangements, gaskets,
stainless steel screws, pins/bolts etc and the wastage of extruded aluminium sections shall
be deemed to be included in the agreement rate and nothing extra whatsoever shall be
payable. Paneling and glazing shall be paid separately.
QUALITY ASSURANCE
(i)
(ii)
(iii)
(iv)
Third party quality assurance (TPQA): The department may decide to engage
third party quality assurance system and the contractor shall render all the
necessary assistance and render arrangement for the inspection of work similar
to clause 16 of agreement.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 55
(v)
The Contractor shall submit, within 15 days after the date of award of work, a detailed
and complete method statement for the execution, testing and Quality Assurance, of
such items of works, as directed by the Engineer-in-Charge.
All the materials to be used in the work, to make the finished work complete in all
respects, shall comply with the requirements of the specifications and shall pass all
the tests required as per specifications as applicable or such specifications /
standards as directed by the Engineer-in- Charge. However, keeping the Quality
Assurance in mind, the Contractor shall submit, on request from the Engineer-inCharge, his own Quality Assurance procedures for basic materials and such items, to
be followed during the execution of the work, for approval of the Engineer-in-Charge.
(vi)
All materials and fittings brought by the contractor to the site for use shall conform to
the specification and the samples approved by the Engineer-in-charge. The contractor
should get the samples of all the materials got approved from the Engineer in charge
before bringing the bulk quantity, which shall be preserved at site of execution till the
completion of the work. If a particular brand of material is specified in the item of work
in Schedule of Quantity, the same shall be used after getting the same approved from
Engineer-In-Charge. Wherever brand / quality of material is not specified in the item of
work, the contractor shall submit the samples as per approved list of brand names
given in the tender document / particular specifications for approval of Engineer-InCharge. For all other items, materials and fittings of ISI Marked shall be used with the
approval of Engineer-In-Charge. Wherever ISI Marked material / fittings are not
available, the contractor shall submit samples of materials / fittings manufactured by
firms of repute conforming to relevant specifications or IS codes and use the same
only after getting the approval of Engineer-In-Charge.
(vii) The Contractor shall procure and provide all the materials from the
manufacturers / suppliers as per the list attached with the tender documents, as per
the item description and particular specifications for the work. The equivalent brand
for any item shall be permitted to be used in the work, only when the specified make is
not available. This is, however, subject to documentary evidence produced by the
contactor for non-availability of the brand specified and also subject to independent
verification by the Engineer-in-Charge. In exceptional cases, where such approval is
required, the decision of Engineer-in-Charge as regards equivalent make of the
material shall be final and binding on the Contractor. No claim, whatsoever, of any
kind shall be entertained from the Contractor on this account. Nothing extra shall be
payable on this account. Also, the material shall be procured only after written
approval of the Engineer-in-Charge.
(viii) All materials whether obtained from Govt. stores or otherwise shall be got checked by
the Engineer-in-Charge or his authorized supervisory staff on receipt of the same at
site before use.
(ix)
To avoid delay, contractor should submit all samples well in advance so as to give
timely orders for procurement.
(x)
The contractor has to establish field laboratory at site including all necessary
equipment for field tests as given in Schedule F. All the relevant and
applicable standards and specifications shall be made available by the
contractor at his cost in the field laboratory. The contractor shall designate one
of his technical representatives possessing required qualification and
experience specified in the Schedule F as Quality Assurance Engineer, who
shall be responsible for carrying out all mandatory field/laboratory tests. The
contractor shall also provide adequate supporting staff at his cost for carrying
out field tests, packaging and forwarding of samples for outside laboratory
tests and for maintaining test records.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 56
(xi)
All the registers of tests carried out at Construction Site or in outside laboratories and
all material at site (MAS) registers including cement register shall be maintained by
the contractor which shall be issued to the contractor by Engineer-in-charge. All the
entries in the registers will be made by the designated Engineering Staff of the
contractor and same should be regularly reviewed by AE/AEE/EE. Contractor shall be
responsible for safe custody of all the registers.
(xii) The contractor shall at his own cost submit samples of all materials sufficiently in
advance and obtain approval of Engineer-in-Charge. The materials to be used in
actual execution of the work shall strictly conform to the quality of samples approved
by the Engineer-in-Charge and nothing extra shall be paid on this account. The
acceptance of any sample or material on inspection shall not be a bar to its
subsequent rejection, if found defective.
(xiii) The contractor shall at his cost, make all arrangements and shall provide necessary
facilities as the Engineer-in-Charge may require for collecting, preparing, packing,
forwarding and transportation of the required number of samples for tests and for
analysis at such time and to such places as directed by the Engineer-in-Charge.
Nothing extra shall be paid for the above operations including the cost of materials
required for tests and analysis. Testing charges, if any, will be borne by the
department if the test passes. In case it fails, the same shall be borne by the
contractor.
(xiv) The necessary tests shall be conducted in the laboratory approved by the Engineer-inCharge. The samples for carrying out all or any of the tests shall be collected by the
Engineer-in-charge or on his behalf by any other officer of CPWD. The contractor or
his authorized representative shall associate himself in collection, preparation,
packing and forwarding of such samples for the prescribed tests and analysis. In case
the contractor or his authorized representative is not present or does not associate
him in the aforesaid operation the results of such tests and consequences thereon
shall be binding on the contractor.
(xv)
Materials used on work without prior inspection and testing (where testing is
necessary) and without approval of the Engineer-in-Charge are liable to be
considered unauthorized, defective and not acceptable. The Engineer-in-Charge shall
have full powers to require the removal of any or all of the materials brought to site
by contractor which are not in accordance with the contract specifications or do not
conform, in character or quality to the samples approved by the Engineer-in-Charge.
In case of default on the part of the contractor in removing rejected materials, the
Engineer-in-Charge shall be at liberty to have them removed at the risk and cost of
the contractor.
(xvi)
The contractor shall make his own arrangement of water required for execution of
work and get the water tested at his own cost with regard to its suitability for use in
the works and getwritten approval from the Engineer-in-Charge before he proceeds
with the use of same for execution of work and thereafter it is got tested at he
prescribed interval as per specification.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 57
(xvii)
All the hidden items such as water supply lines, drainage pipes, conduits, sewers
etc. are to be properly tested as per the design conditions before covering and their
measurements in computerized measurement book duly test checked shall be
deposited with Engineer in charge or his authorized representative, prior to hiding
these items.
(xviii) Water tanks, taps, sanitary, water supply and drainage pipes, fittings and
accessories should conform to local bye-laws rules and specification of municipal /
corporation, If CPWD Specifications are not available for the same. The contractor
should engage licensed plumbers for the work and get the materials (fixtures/fittings)
tested by the Municipal Body/Corporation authorities wherever required at his own
cost.
1.
Specialized Agencies
(i) The composite tender comprises of two components: viz. Main Component - Civil and
Minor Component - Electrical. The list of specialized items for civil component works
which are to be got executed through specialized agencies are as below:
CIVIL WORKS:
a.
b.
c.
d.
e.
Anti-termite treatment.
Water proofing works.
Aluminium doors, windows and aluminium partition.
Structural glazing facades
Fire check doors.
2.
The Contractor shall do proper sequencing of the various activities by suitably staggering the
activities within various pockets in the plot so as to achieve early completion. The agency
should deploy adequate and suitable equipment, machinery and labour as required for the
completion of the entire work within the stipulated period specified. Also ancillary facilities
shall be provided by contractor commensurate with requirement to complete the entire work
within the stipulated period. Nothing extra shall be payable on this account. Adequate
number/sets of equipment in working condition, along with adequate stand-by arrangements,
shall be deployed during entire construction period. It shall be ensured by the Contractor that
all the equipment, Tools & Plants, machineries etc. provided by him are maintained in proper
working conditions at all times during the progress of the work and till the completion of the
work. Further, all the constructional tools, plants, equipment and machineries provided by
the Contractor, on site of work or his workshop for this work, shall be exclusively intended for
use in the construction of this work and they shall not be shifted/ removed from site without
the permission of the Engineer-in-Charge.
3.
Display Boards : The Contractor shall provide and erect a display board of size and shape
as required, in a legible and workman like manner, the details about the salient features of
the project, as directed by the Engineer-in-Charge. The Contractor shall fabricate and put up
a display board of approved design indicating name of the project, Client/Owner, Engineerin-charges, Structural Consultants, Department etc. besides providing space for names of
other Contractors, Sub-Contractors and specialized agencies etc at the site within 15 days
from issue of award letter. Nothing extra shall be payable on this account. In case of non
compliance/delay in compliance in this, a penalty @ Rs. 500/- per day will be imposed
which will be recovered from the immediate next R/A Bill of the Contractor.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 58
4.
INSPECTION OF WORK
(i) In addition to the provisions of relevant clauses of the contract, the work shall also be
open to inspection by Senior Officers of CPWD the committee constituted for the purpose
of NIOH & the representative of the NIOH Consultants .The contractor shall at times
during the usual working hours and at all times at which reasonable notices of the
intention of the Engineer-in-charge or other officers as stated above to visit the works
shall have been given to the contractor, either himself be present to receive the orders
and instructions or have a responsible representative duly accredited in writing, to be
present for that purpose.
(ii) Inspection of the work by NIOH
a) The committee/consultant appointed by NIOH, may inspect the works including
workshops and fabrication factory to ensure that the works in general being
executed according to the design, drawings and specifications laid down in the
contract. Their observations shall be communicated by the Engineer-in Charge
and compliance is to be reported by the contractor to the Engineer-in-Charge.
5.
Weekly Review Meetings: Shall be attended by Local Team headed by Project-incharge of the Contractor and specialized agencies engaged by the Contractor.
Agenda
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 59
(ii) Monthly Review Meetings : Shall be attended by Project in charge and the
Management Representative of the Contractor who can take independent
decisions and Management Representative of the specialized agencies engaged
by the Contractor as per the contract conditions who is to take decisions.
Agenda
a) Progress Status/Statistics.
b) Completion Outlook.
c) Major hold ups/slippages.
d) Assistance required.
e) Critical issues.
f) Any decision on queries raised either by
Contractor/PMC.
g) Anticipated cash flow requirement for next two
months.
(iii) Apart from the above meeting the Engineer-in-Charge may convene meeting at
any time according to the necessity and the Contractor is bound to attend the
meeting with his team and specialized agencies with requisite details.
Description
Foundation
2.
Super structure
3.
(a)
Doors
Frame-
(i)
Rooms
(ii)
(b)
(i)
Toilet
Shutters
Rooms
Specification
Allowable bearing capacity as intimated by the EE/ ACD is 15
ton/sqm at 2.0 m depth below ground level. RCC isolated / combined
footing for columns with M-25 grade concrete. Before the actual
construction is taken up the bearing capacity of soil has to be
confirmed. The Admn. / Academic block is designed as double
storied.
The floor height of Admn. / Academic block shall be 3.60 m as per
Arch drawing. The structure shall be RCC framed construction in M25 concrete. Filler walls in brick masonry in cement mortar 1:6 using
7.5N/mm2 brick, internal partition with half brick masonry in cm 1:4
using 7.5N/mm2 brick. Portland pozzolana cement shall be used for
brick masonry
For all doors& cup boards except Toilet pressed steel M.S. Profile
section with 4 hinges for each leaf for fixing the door shutter of room
and piano hinges for cupboard shutter has been considered for
ensuring longevity. For hostels and canteen, M.S.T-iron frames to be
provided for doors and cub boards.
PVC frame
35 mm thick commercial type flush door shutter with M.S Sliding
door bolt, Aluminium tower bolt on inside of shutter (250X10mm on
top & 150x10mm at middle), 125mm Aluminium handle on both
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 60
faces, Aluminium twin type hanging floor door stopper has been
considered
Door closer: one hydraulic door closer on each leaf of door in all
rooms.
25 mm thick commercial type flush door shutter with 150mm M.S
hasp & staple, Aluminum tower bolt on inside of one
shutter(150X10mm on top), 125mm Aluminium handle on front face
of each leaf , has been considered
Shelves: 25mm finished thickness RCC pre-cast shelves with
IRC fabric as reinforcement.
(ii)
Cup boards
(iii)
(iv)
4.
Windows
5.
Ventilators
Window Sills
18mm thick, silver grey colour granite duly pre-finished with edge
moulding shall be laid in out ward slope of 5mm to drain off rain
water.
Gap between window frame & granite sill shall be filled up with baker
rod & weather silicon sealant 5 mm x 5 mm .
7.
(a)
Flooring
All corridor and open
yard
(b)
(c)
Ramp flooring
(d)
Skirting in corridor
(e)
Single piece Polished Kota stone (i) 25mm thick for Treads duly
prefinished with semicircular nosing & (ii) 20mm thick for 150 mm
high risers.
(f)
Toilets
Skirting/dado for
Toilets
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 61
Finishing
(a)
Internal (plaster)
(b)
External (plaster)
(c)
Painting (Internal)
(d)
Painting (External)
10.
Roofing
11.
(i)
White cement based putty on walls & ceiling.
(ii)Acrylic distemper on walls &ceiling .
(iii) White wash in rest of the area.
(iv) Synthetic enamel paint on all wood work & M.S. steel work.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 62
12
(a)
Services
Water supply
(b)
Sanitary installation
Drainage
13
Water proof
treatment
Sunken area of Toilets & Inner side of Gutter : With tape crete
water proofing.
Flat Roof treatment: Integral cement based water proofing over roof
(flat roof).
14.
Plinth protection
Specification
Allowable bearing capacity as intimated by the EE/ ACD is 15
ton/sqm at 2.0 m depth below ground level. RCC isolated/ combined
footing for all columns with M-25 grade concrete. Before the actual
construction is taken up the soil investigation has to be confirmed.
The residential qtrs. is designed as double storey.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 63
2.
Super structure
3. Doors
(a) Frame
(i) All doors except
Toilet(ii) Toilet doors
(b) Shutters
(i) Doors for rooms
(ii)
Kitchen
The floor to floor height of qtrs. shall be 3.00 mtr as per Arch drg.
The structure shall be RCC framed construction in M-25 concrete.
Filler walls in brick masonry in cement mortar 1:6 using 7.5N/mm2
brick, internal partition with half brick masonry in cm 1:4 using
7.5N/mm2 brick. Portland pozzolana cement shall be used for
brick masonry
Frame of all doors except external door shall be with profile B and
for external door frames shall be with profile E.
PVC frame
-All doors except toilet & kitchen shall be 35 mm thick commercial
type flush door with M.S Sliding door bolt, Aluminum tower bolt on
inside of shutter(250X10mm on top & 150x10mm at middle), 125mm
Aluminium handle on both faces, Aluminium twin type hanging floor
door stopper has been considered.
-Magic eye shall be provided in main entrance door of each qtr
30 mm thick second class teak wood two paneled full height
stainless steel wire mesh shutter with M.S Sliding door bolt,
Aluminum tower bolt on inside of shutter(250X10mm on top &
150x10mm at middle), 125mm Aluminium handle on both faces,
Aluminium twin type hanging floor door stopper has been considered
35 mm thick commercial type flush door and 35 mm thick second
class teak wood two panelledshutter stainless steel wire mesh with
M.S Sliding door bolt, Aluminum tower bolt on inside of
shutter(250X10mm on top & 150x10mm at middle), 125mm
Aluminium handle on both faces, Aluminium twin type hanging floor
door stopper has been considered
.
30 mm thick PVC door shutter plain with one Aluminium tower bolt
(150x10mm) and 125mm Aluminium handle on each face inside as
well as outside
4.
Windows and
ventilators
5.
Windows Sills
18mm thick, silver grey colour granite duly pre-finished with edge
moulding shall be laid in out ward slope of 5mm to drain off rain
water.
Gap between window frame &granite sill shall be filled up with
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 64
Flooring
(i)
(ii)
Kitchen
(iv) Toilet
7.
Skirting/dado
(i)
Kitchen
Ceramic tile dado 1300 mm high above kitchen counter. The joints of
tiles shall be filled with matching grout recommended by tile
manufacturer.
(ii)
Glazed tiles of size 200 x 300 mm 2.10 m The joints of tiles shall
be filled with polymer modified grout recommended by tile
manufacturer. For base mortar Portland pozzolana cement shall be
used.
8.
(i)
Finishing
Internal
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 65
(ii)
External
9.
Mild steel round/rectangular 'U' tubes for hand rail over M.S. square
bar/ flat balustrade as per Arch drawing.
Vertical balustrades shall be embedded in the treads concrete
for required depth.
10. Services
(i)
Water supply
(ii)
Sanitary installation
All EWC shall be provided except for servant qtr where Indian Type
WC shall be provided
Wash Basin: 550x400mm with a single CP Brass auto closing Push
cock for all qtrs.
Kitchen Sink : Stainless steel Kitchen sink with Swan neck
swivel type Sink Cock to be provided in all qtrs.
11. Drainage
13. Roofing
(i) Sanitary lines & fittings: SCI Centrifugally cast pipes & fittings
jointed with lead joints.
(ii) Vertical stack in SCI pipe shall be connected to the floor
traps/ closets through 'Y' junction having door bend with access
door & plain 'Y' branch of required degree.
CC 1:3:6(1 cement :3 coarse sand:6 graded stone aggregate 20 mm
nominal size) finished smooth over brick aggregates, and brick
edging.
RCC flat roof shall be finished with integral cement based water
proofing Coba treatment
(ii)
Roof treatment
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 66
Development works 1. Retaining wall: RCC retaining wall of varying depth 3m high 60 m & 5 m 30 m,
according to the sloping terrain as per the details made available by the Executive
Engineer, AzCD to take care of the NIOH building, qtrs, UG sump & rain water collection
sump against sliding on sloping terrain and to retain the terrace formed by filled up earth
against sliding during torrential rains has been considered.
2. RCC Underground sump: 50 KL for drinking, toilet requirement etc. including rain water
collection tank.
3. Water supply : 80 mm GI main grid from sump and separate line of 40 mm GI pipe from
sump to terrace tank one to building and one line to qtrs.
4. Road :
150mm thickness
CC Pavement with
concrete over 100mm thick CC1:5:10 base concrete laid over sub grade consolidated
with road roller shall be laid in panels made with 6mm thick cement based board. The
width of the road shall be 5.00 meter for main building and residential area.
5. Storm water drainage :Trapezoidal 65mm thick RCC open surface drain with nominal
reinforcement. The drain near the main building to be covered with perforated RCC slab
cover. Drain water to be discharged outside boundary of school so that there is no
soil erosion.
6. Septic tank:
2 nos. - 50 users each with 2 soak pit for each septic tank
to be
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 67
ANNEXURE A
GUARANTEE BOND TO BE EXECUTED BY THE CONTRACTOR FOR REMOVAL OF
DEFECTS AFTER COMPLETION IN RESPECT OFWATER-PROOFING WORKS
(All Water - Proofing Items).
The agreement made this.................... day of ................. (Two Thousand _______ only)
..............between ....................................S/o ...............................................(hereinafter called the
GUARANTOR of the one part) and the PRESIDENT OF INDIA (hereinafter called the
Government of the other part)
WHEREAS THIS agreement is supplementary to a contract (Hereinafter called the Contract)
dated ...................... and made between the GUARANTOR OF THE ONE PART AND the
Government of the other part whereby the contractor inter alia undertook to render the building
and structures in the said contract recited completely water and leak-proof.
AND WHEREAS THE GUARANTOR agreed to give a guarantee to the affect that the said work
will remain water and leak proof, for ten years after the date of expiry of maintenance period
prescribed in the contract.
NOW THE GUARANTOR hereby guarantee that work executed by him will render the
structures completely leak proof and the minimum life of such water proofing treatment shall be
ten years to be reckoned from the date after the expiry of maintenance period prescribed in the
contract.
The decision of the Engineer-in-charge with regard to nature and cause of defect shall be final
and binding on Guarantor.
During this period of guarantee, the guarantor shall make good all defects and in case of any
defect being found render the building water proof including replacement of sanitary & plumbing
pipes, traps & fittings connecting, flooring, skirting & dado requiring demolishment for
replacement /repair of the water proofing wok at his cost to the satisfaction of the Engineer-InCharge calling upon him to rectify the defects failing which the work shall be got done by the
Department by some other contractor at the Guarantors cost and risk. The decision of the
Engineer-in-charge as to the cost payable by the Guarantor shall be final and binding.
That if the guarantor fails to execute the water proofing or commits breach there under, then the
guarantor will indemnify the principal and his successor against all loss, damage, cost expense
or otherwise which may be incurred by him by reason of any default on the part of the
GUARANTOR in performance and observance of this supplementary agreement. As to the
amount of loss and/or damage and / or cost incurred by the Government, the decision of the
Engineer-in-charge will be final and binding on both the parties.
That 10% (Ten percent) of the cost of water proofing works (all water proofing items) shall be
retained by the Government as Guarantee Money and the amount as retained would be released
after ten years after the date of expiry of maintenance period prescribed in the contract after
completion of entire work, if the performance of the water proofing works is found satisfactory by
the Engineer-in-charge.
IN WITNESS WHEREOF these presents have been executed by the obligator
.......................and ........................................ by ................................. for and on behalf of the
PRESIDENT OF INDIA on the day, month and year first above written.
SIGNED, sealed and delivered by OBLIGATOR in the presence of :1. ................................................ 2. ...........................................
SIGNED FOR AND BEHALF OF THE PRESIDENT OF INDIA BY .................in the presence of
:1. ............................................... 2. ..........................................
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 68
ANNEXURE A.1
GUARANTEE BOND TO BE EXECUTED BY THE CONTRACTOR FOR REMOVAL OF
DEFECTS AFTER COMPLETION IN RESPECT OFANTI TERMITE TREATMENT WORKS.
The agreement made this.................... day of ................. (Two Thousand
only) ..............between ....................................S/o ...............................................(hereinafter
called the GUARANTOR of the one part) and the PRESIDENT OF INDIA (hereinafter called the
Government of the other part)
WHEREAS THIS agreement is supplementary to a contract (Hereinafter called the
Contract) dated ...................... and made between the GUARANTOR OF THE ONE PART AND
the Government of the other part whereby the contractor inter alia undertook to render the
building and structures in the said contract recited completely termite proof.
AND WHEREAS THE GUARANTOR agreed to give a guarantee to the affect that the said
structure will remain termite proof, for ten years from the date after the maintenance period
prescribed in the contract expires.
NOW THE GUARANTOR hereby guarantees that work executed by him will render the
structures completely termite proof and the minimum life of such termite proofing treatment shall
be ten years to be reckoned from the date after the expiry of maintenance period prescribed in
the contract.
The decision of the Engineer-in-charge with regard to nature and cause of defect shall be
final and binding on Guarantor.
During this period of guarantee, the guarantor shall make good all defects and for that
matter, shall replace at his risk & cost such wooden members as may be damaged by termites
and in case of any other defect being found, he shall render the building termite proof at his cost
to the satisfaction of the Engineer-In-Charge and shall commence the works of such rectification
within seven days from date of issuing notice from Engineer-in-charge calling upon him to rectify
the defects failing which the work shall be got done by the Department by some other contractor
at the Guarantors cost and risk and in the latter case the decision of the Engineer-in-charge as
to the cost recoverable from the Guarantor shall be final and binding.
That if the guarantor fails to execute the anti termite treatment or commits breach hereunder,
then the guarantor will indemnify the principal and his successor against all loss, damage, cost,
expense or otherwise which may be incurred by him by reason of any default on the part of the
GUARANTOR in performance and observance of this supplementary agreement. As to the
amount of loss and/or damage and / or cost incurred by the Government, the decision of the
Engineer-in-charge will be final and binding on both the parties.
That 10% (Ten percent) of the cost of anti termite work shall be retained by the Government
as Guarantee Money and the amount as retained would be released after ten years after the date
of expiry of maintenance period prescribed in the contract after completion of entire work, if the
performance of the anti termite work is found satisfactory by the Engineer-in-charge.
IN WITNESS WHEREOF these presents have been executed by the obligator
.......................and ........................................ by ................................. for and on behalf of the
PRESIDENT OF INDIA on the day, month and year first above written.
SIGNED, sealed and delivered by OBLIGATOR in the presence of :1. ............................................... 2. ...........................................
SIGNED & sealed by SPECIALIZED AGENCY in the presence of :1. ............................................... 2. ...........................................
SIGNED FOR AND BEHALF OF THE PRESIDENT OF INDIA BY ................... in the presence of
:1. ............................................... 2. ..........................................
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 69
ANNEXURE-A-2
GUARANTEE BOND TO BE EXECUTED BY THE CONTRACTOR FOR REMOVAL OF
DEFECTS AFTER COMPLETION IN RESPECT OF SANITARY INSTALLATIONS / WATER
SUPPLY / DRAINAGE WORK.
The agreement made this.................... day of ................. (Two Thousand only)
..............between ....................................S/o ...............................................(hereinafter called the
GUARANTOR of the one part) and the PRESIDENT OF INDIA (hereinafter called the
Government of the other part)
WHEREAS THIS agreement is supplementary to a contract (Hereinafter called the
Contract) dated .................................. and made between the GUARANTOR OF THE ONE
PART AND the Government of the other part, whereby the contractor inter alia, undertook to
render the work in the said contract recited structurally stable, leak proof and sound material,
workmanship, anodizing, colouring, sealing.
AND WHEREAS THE GUARANTOR agreed to give a guarantee to the affect that the said
work will remain structurally stable, leak proof and guaranteed against faulty material and
workmanship, and finishing for five years from the date after expiry of maintenance period
prescribed in the contract.
NOW THE GUARANTOR hereby guarantee that work executed by him will be free from any
leakage, seepage, cracks in pipes and guaranteed against faulty material and workmanship,
defective galvanizing for five years to be reckoned from the date after the expiry of maintenance
period prescribed in the contract.
The decision of the Engineer-In-Charge with regard to nature and cause of defect shall be final.
During this period of guarantee, the guarantor shall make good all defects and in case of any
defect to satisfaction of Engineer-in-charge at his cost and shall commence the work for such
rectification within seven days from the date of issue of the notice from the Engineer-in-charge
calling upon him to rectify the defects failing which the work shall be got done by the Department
by some other contractor at the guarantors cost and risk. The decision of the Engineer-in-Charge
as to the cost payable by the Guarantor shall be final and binding.
That if the guarantor fails to make good all defects or commits breach there under, then
the guarantor will indemnify the principal and his successor against all loss, damage, cost
expense or otherwise which may be incurred by him by reason of any default on the part of the
GUARANTOR in performance and observance of this supplementary agreement. As to the
amount of loss and/or damage and or cost incurred by the Government, the decision of the
Engineer-in-charge will be final and binding on both the parties.
That 5% (Five percent) of the cost of Sanitary Installations, Water Supply, Drainage works
shall be retained by the Government as Guarantee Money and the amount as retained would be
released after five years after the date of expiry of maintenance period prescribed in the contract
after completion of entire work, if the performance of the Sanitary Installations, Water Supply,
Drainage works is found satisfactory by the Engineer-in-charge.
IN WITNESS WHEREOF these presents have been executed by the obligator
........................................and ................................................. by ........................................... for
and on behalf of the PRESIDENT OF INDIA on the day, month and year first above written.
SIGNED, sealed and delivered by OBLIGATOR in the presence of:1. .................................................... 2. ............................................
SIGNED FOR AND ON BEHALF OF THE PRESIDENT OF INDIA BY...................... in the
presence of:1. .................................................. 2. ............................................
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 70
ANNEXUREB
LISTOFAPPROVEDMAKE OFMATERIALS
Thematerialsoffirst/standardqualityfromthefollowingpreferredmakesaretobe
used.
Incaseitis established thatthebrandsspecified belowarenotavailableinthemarket,contractor
shallsubmit alternativeproposalfortheapprovalofEngineer-in-Charge.
ThecontractorshallprovidethematerialsaspertheMakeorBrandindicatedbelow. Whentwoor
morealternativebrandshavebeenmentioned,thebrandtobefinallyusedshallbeas
decidedbythe
Engineer-in-Charge. ThecontractorshallobtaintheapprovalofSE, S C C forthealterativebrands,
beforetheactualexecutionofitems.
A.General
Materials.
SlNo.
Materials
Brand/ManufacturerName
1
OrdinaryPortlandcement A.C.C., L&T, J.P. Rewa, Vikram, Shree Cement, Gujarat
Ambuja,BirlaJute,CementCorporation
ofIndia,Taj, Star
Cement, Max Cement, Valley Strong, Dalmia Cementetc
having valid approval oftheADG, ER-II asondateof
procurement.
2
Pozzolana Portland
cement
SteelReinforcement(TMT
bars)
a)PrimaryProducers
SAIL,TISCO,RINL, Jindal Steel & Power Ltd., JSW Steel Ltd.
4
5
6
7
8
9
b)
Biscon, Kamdhenu, MeghaShakti, X-Tech TMTbars
SecondaryProducers(Sub etc.havingvalidapprovalofthe
ADG,
ER-II
asondateof
ject
procurement.
togeneralconditionNo.14&
subconditionthereof)
CGISheet
TataShakti,Jindal
SyntheticEnamelPaint/E Berger,AsianPaints, Nerolac, Jenson&Nicholson, ICI paints.
mulsion / steel/ wood
primer
AcrylicwashableDistempe Berger,AsianPaints, Nerolac, Jenson&Nicholson, ICI paints.
r
Waterproofingcementpain Berger,AsianPaints, Nerolac, Jenson&Nicholson,
ICI
t,
paints.
Primer
AcrylicExteriorPaint
Berger,AsianPaints, Nerolac, Jenson&Nicholson,
ICI
paints.
MorticeLatch
Godrej,Harrison
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 71
10
WhiteCement
Birlawhite,J.K.whiteorequivalent.
11
CeramicTiles
12(b)
13
14
15
16
Alucobond or equivalent
Rajshree, Polyline
CICO,FOSROC, Pidilite, BASF
Vista,Mac
M/sMultiwynIndustrialCorporationKolkataetchaving
validapprovalofCE,NEZ-IIasondateofprocurement.
17
FlushDoorShutters
18
19
20
21
22
23
HILTI, Fischer
GKW, Atul
Fosroc, MBT, Sika, CICO, Asian
Somany, Kajaria, H&RJohnson, Asian, NITCO
As approved by Engineer-in-charge.
Hardwyn, Godrej, Dorma.
24
25
26
27
EPDM Gasket
Tile Adhesive
Wall putty
Clear glass/clear float
glass/toughened glass
Hanu/ Annand
CICO, Dipilite, Ferrous
Birla white wall care, JK wall care white
1. Modi
2. Saint Gobain
3. AIS
28
Friction hinges
Parryware,Hindware,Cera
Jaquar, King ston (ELTA) ESS-ESS or equivalent as
per decision and direction of Engineer-in-Charge
C.P.flushvalvesforW.C.s
C.P.BathroomAccessories
5
6
7
StainlessSteelSink
Neelkant,Kingston cobra/Nirali
Bevellededgemirror
Atul,Jolly,Modiguard
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 72
Pipes andFittings
1
CentrifugallyCast(Spun)Iron
JayaswalNeco, HEPCO.
soil,wasteandventpipesand fittings
G.I.Pipes
G.I.Fittings
RBrand,Unik,Zoloto / Atam
C.I.ClassLAPipes
Stonewarepipes
Bhaskar, Anand,ISImarkedofapprovedQuality
R.C.C.Pipes
ISImarkedofapprovedQuality
PP-RPipesandFittings
Supreme,Prince,
CI Sluice valve
10 MS Pipe
Insulation
1
SyntheticPolymericRubber
Compound
Vidoflex,Superlon,Armstrong
Valves
1
Valves,FloatValves
Zoloto,RB,Italy, Prayag
BallValves
RB,CIM,ITAPItaly, Prayag
SteelFibreReinforcedConcrete
ManholeCoversandGrating
K.K.manholes,PragatiConcrete
C.I.ManholeCovers
RIF,Kajeco,Neco, Hepco
AllotheritemsshallbeofISImarked/asperapprovedsamplekeptatsiteofwork.
Correction Nil Deletion Nil Insertion Nil Overwriting NilAE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 73
PART C
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 74
SHEDULE OF QUANTITIES
Name of work:- Construction of Centre for Disability Studies in Aizawl, Mizoram. (SH :-C/O Administration /
Academic block, Boy's cum Girls hostel (D/S), Dining/Common room and 1 no. Type-IV quarter (S/S)
including water supply, sanitary installations, sewerage, drainage, manual fire alarm system, development
and electrical works.
SLNo
1
1.1
1.1.1
1.2
1.2.1
1.3
1.3.1
Description
Unit
Amount
4066
cum
cum
1720
cum
cum
200
cum
cum
2483
cum
cum
71
cum
cum
1.5
1.6
1.6.1.1
Rate
Sub Head: E A R T H W O R K
1.4
1.6.1
Qty
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
meter
Page 75
2.1
2.1.1
2.2
2.2.1
2.3
2.4
2.5
2.6
3
3.1
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
450
cum
cum
cum
cum
123
sqm
sqm
25
kg
kilogram
123.00
sqm
sqm
236
sqm
sqm
1132
sqm
sqm
1368
sqm
sqm
1654
sqm
sqm
2743
sqm
sqm
1367
sqm
sqm
60
sqm
sqm
48
sqm
sqm
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 76
3.1.8
3.1.9
3.2
3.2.1
3.3
3.3.1
3.3.2
3.4
3.5
3.5.1
3.5.2
3.6
3.7
3.8
48
sqm
sqm
72
sqm
sqm
101356
kg
kilogram
88634
kg
kilogram
748
kg
kilogram
5537
sqm
sqm
760
cum
cum
525
cum
cum
714
quintal
480
cum
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
quintal
cum
meter
Page 77
3.9
3.9.1
4
50
4.1
4.1.1
4.2
4.2.1
4.3
4.3.1
5
247
cum
cum
335
cum
cum
554
sqm
sqm
15.00
sqm
sqm
Sub Head: M A R B L E W O R K
Providing and fixing in pattern as per discretion and
decision of Engineer-in-charge 18mm thick gang saw cut
mirror polished (premoulded and prepolished) machine
cut for flooring, kitchen platforms, vanity counters
,window sills , facias and similar locations of required size
of approved shade, colour and texture laid over 20mm
thick base cement mortar 1:4 (1 cement : 4 coarse sand)
with joints treated with white cement, mixed with
matching pigment, epoxy touch ups, including rubbing,
curing, semi circular moulding and machine polishing to
edges to give high gloss finish etc. complete at all levels
and making smooth hole for gas pipe.[Note: In case
the edges of premoulded moulding are not found
rubbed to give high gloss finish (without application
of wax), recovery @ Rs. 250/- per meter length of
moulding edge for granite work and @ Rs. 200/- per
metre for marble work for full length of moulding of
counter/sill/ plateform/ facia etc will be made ].
5.1.1
5.1.2
metre
cement :4
5.1
5.1.1.1
WORK
5.1.2.1
62
sqm
sqm
5.1.2.2
12.00
sqm
sqm
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 78
5.2
5.2.1
5.2.1.1
5.3
5.4
5.5
5.5.1
Sub head: W O O D A N D P. V. C.
20
sqm
sqm
20
metre
nos.
each
sqm
sqm
122
sqm
sqm
WORK
6.1
6.1.1
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 79
6.1.2
58
sqm
sqm
6.2
54
sqm
sqm
6.3
6.3.1
12 mm thick
70
sqm
sqm
6.4
6.4.1
300x16 mm
28
nos.
each
6.5
no.
each
58
sqm
sqm
6.6
6.6.1
6.6.1.1
6.7
6.7.1
6.8
6.8.1
6.9
221
meter
5125
kg
kilogram
6.9.1
300x16 mm
6.10
6.10.1
250x10 mm
6.10.2
150x10 mm
50
nos.
each
154
nos.
each
159
nos.
each
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 80
6.11
6.11.1
6.12
6.12.1
300
nos.
each
25
nos.
each
14
nos.
each
11
nos.
each
78.00
nos.
each
metre
6.13
6.14
6.15
6.15.1
6.16
6.17
150
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 81
7.1
7.2
7.2.1
7.3
7.3.1
7.3.1.1
7.3.2
7.3.2.1
49
sqm
sqm
28
sqm
sqm
1429
kg
kilogram
147
metre
25
metre
Profile B
Fixing with adjustable lugs with split end tail to each jamb
Profile E
Fixing with adjustable lugs with split end tail to each jamb
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 82
7.4
7.5
7.5.1
7.6
7.6.1
7.8
8.1.1
8.2
each
4963
kg
kilogram
1200
kg
kilogram
794
kg
kilogram
8.1
nos.
7.7
72
20
sqm
sqm
339
sqm
sqm
58
sqm
sqm
Sub Head: F L O O R I N G
Kota stone slab flooring over 20 mm (average) thick base
laid over and jointed with grey cement slurry mixed with
pigment to match the shade of the slab, including
cutting in arc shape as per geometry of wall, rubbing
and polishing complete with base of cement mortar 1 : 4
(1portland pozzolana cement : 4 coarse sand) :
25 mm thick
Kota stone slabs 20 mm thick in risers of steps, skirting,
dado and pillars laid on 12 mm (average) thick cement
mortar 1:3 (1 portland pozzolana cement: 3 coarse sand)
and jointed with grey cement slurry mixed with pigment to
match the shade of the slabs, including rubbing and
polishing complete.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 83
8.3
8.4
8.4.1
sqm
sqm
561
sqm
sqm
162
sqm
sqm
255
sqm
sqm
435.00
sqm
sqm
8.5
8.6
8.7
8.7.1
100
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 84
8.8
8.9
8.10
9
9.1
9.1.1
9.2
9.2.1
9.2.1.1
9.2.2
9.2.2.1
9.3
9.3.1
9.4
9.4.1
51
sqm
sqm
87
sqm
sqm
147
meter
92
metre
44
nos.
each
44
nos.
each
meter
nos.
each
400
60
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 85
9.5
9.6
10
Sub head: F I N I S H I N G
10.1
10.1.1
280
sqm
sqm
865
sqm
sqm
1931
sqm
sqm
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 86
10.2
10.2.1
10.3
10.3.1
10.4
10.5
10.5.1
10.6
10.6.1
10.7.1
sqm
95
sqm
sqm
236
sqm
sqm
5210
sqm
sqm
605
sqm
sqm
2503
sqm
sqm
406
sqm
sqm
936
sqm
sqm
10.8.1
10.9
10.9.1
sqm
10.7
10.8
2041
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 87
10.10
11
11.1
11.2
11.3
5280
sqm
sqm
2175
sqm
sqm
2943
kg
Sub head: R O A D W O R K
kilogram
11.4
11.5
12
12.1
450
sqm
sqm
259
cum
cum
350
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
meter
Page 88
12.1.1
12.2
12.2.1
W.C. pan with ISI marked white solid plastic seat and lid
of same make as of the WC Pan
12.3
12.3.1
12.3.2
12.4
12.4.1
12.4.2
12.4.3
nos.
each
13
nos.
each
nos.
each
nos.
each
12
nos.
each
nos.
each
nos.
each
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 89
12.5
12.5.1
12.5.1.1
12.6
12.6.1
32 mm dia
12.6.1.2
40mm dia
12.7
12.8
12.9
12.10
12.11
12.11.1
12.11.1.1
nos.
each
32
nos.
each
nos.
each
31
nos.
each
23
nos.
each
14
nos.
each
metre
Flexible Pipe
12.6.1.1
12.10.1
12.10.1.1
100 mm dia
Centrifugally cast (spun) iron socket & spigot (S&S) pipe
as per IS: 3989 [Note: All branch connection to the
vertical stack to be in 'Y' junction form with SCI bend
having access door connected to plain single/ double
equal junction of required degree]
137
12.12
12.13
12.13.1
600 mm long towel rail with total length of 645 mm, width
78 mm and effective height of 88 mm, weighing not less
than 190 gms.
nos.
each
nos.
each
nos.
each
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 90
12.14
12.14.1
12.15
12.15.1
12.15.1.1
12.16
12.16.1
12.16.1.1
12.17
12.17.1
12.17.1.1
12.21
12.21.1
12.21.1.1
12.22
nos.
each
29
nos.
each
15
nos.
each
15
nos.
each
nos.
each
210
nos.
each
31
nos.
each
20
nos.
each
12.20.1
10
100 mm dia
12.19
12.20
each
12.19.1.1
nos.
100 mm dia
12.18
12.19.1
40
100 mm
Sand cast iron S&S as per IS - 3989
Providing lead caulked joints to sand
cast
iron/centrifugally cast (spun) iron pipes and fittings of
diameter :
100 mm
Providing and fixing trap of self cleansing design with
screwed down or hinged grating with or without vent arm
complete, including cost of cutting and making good the
walls and floors :
100 mm inlet and 100 mm outlet
Sand cast iron S&S as per IS: 3989
Providing and fixing PTMT towel ring trapezoidal shape
215 mm long, 200 mm wide with minimum distances of
37 mm from wall face with concealed fittings arrangement
of approved quality and colour, weighing not less than 88
gms.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 91
12.23
12.23.1
12.24
12.24.1
12.24.1.1
12.24.2
12.24.2.1
12.25
13
80
nos.
metre
13
nos.
each
13
nos.
each
10
nos.
each
13.1
13.1.1
123
metre
13.1.2
66
metre
80
meter
130
meter
13.2
13.2.1
13.2.2
13.3
13.3.1
74
metre
13.3.2
178
metre
13.3.3
150
metre
13
nos.
each
14000
litre
litre
13.4
13.5
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 92
13.6
13.6.1
16
nos.
each
13.6.2
40 mm nominal bore
nos.
each
13.6.3
80 mm nominal bore
nos.
each
47
nos.
each
nos.
each
10
nos.
each
nos.
each
13.7
13.7.1
13.8
13.8.1
13.9
13.9.1
13.10
13.10.1
13.11
Painting G.I. pipes and fittings with two coats of anticorrosive bitumastic paint of approved quality :
13.11.1
86
metre
13.11.2
202
metre
13.11.3
80 mm diameter pipe
150
metre
13.12
13.12.1
86
metre
13.12.2
202
metre
13.12.3
80 mm diameter pipe
150
metre
nos.
each
23
nos.
each
13.13
13.13.1
13.14
13.14.1
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 93
13.14.2
23
nos.
each
13.14.3
25 mm nominal bore
23
nos.
each
13.14.4
40 mm nominal bore
10
nos.
each
13.15
13.15.1
12
meter
13.15.2
87
meter
13.15.3
66
meter
32
nos.
each
13
nos.
each
nos.
each
35
nos.
each
13.16
13.16.1
13.17
13.17.1
13.18
13.18.1
13.19
13.19.1
13.20
13.20.1
nos.
each
13.20.2
nos.
each
18
nos.
each
13.21
13.21.1
13.22
13.22.1
20mm dia
20
nos.
each
13.22.2
25 mm dia
nos.
each
13.22.3
40 mm dia
19
nos.
each
4.00
nos.
each
13.23
14
14.1
14.1.1
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 94
14.1.1.1
14.2
20
nos.
each
14.2.1
140.00
metre
14.2.2
200.00
metre
14.2.3
98
metre
25
nos.
each
metre
nos.
each
metre
14.3
14.3.1
14.3.1.1
14.4
14.4.1
14.4.1.1
14.5
14.5.1
14.6
14.6.1
160mm diameter
28
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 95
14.7
15
15.1
42
15.1.1
nos.
each
15.1.1.1
15.1.2
15.1.2.1
1803
kg
kilogram
1753
kg
kilogram
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 96
15.3
15.3.1
15.3.2
15.3.3
15.3.4
15.4
15.4.1
15.5
15.5.1
15.6
49.00
sqm
sqm
201
sqm
sqm
20.00
sqm
58
sqm
sqm
10
nos.
each
210
nos.
each
105 nos.
each
sqm
205 X 19 mm
Providing and fixing aluminium casement window
fastener of required length for aluminium windows with
necessary screws etc. complete.
15.6.1
15.7
15.7.1
15.8
nos.
each
120
nos.
each
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 97
16
16.1
16.1.1
sqm
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
sqm
Page 98
16.2
16.3
16.3.1
16.4
15
sqm
80
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
sqm
metre
Page 99
17
50
cum
cum
115
sqm
sqm
525
sqm
sqm
Misc.
17.1
17.2
17.2.1
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 100
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 101
PART D
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 102
Name of Work: Construction of Centre for Disability Studies in Aizawl, Mizoram. (SH :- C/o.
Administration / Academic block, Boy's cum Girls hostel (D/S), Dining/Common room and 1
no. Type-IV quarter (S/S) including water supply, sanitary installations, sewerage, drainage,
manual fire alarm system, development and electrical works.
Schedule of quantities (as per PWD 3) --- Enclosed from Page No.124 135
(As per part E)
SCHEDULE 'B'
Sl.No.
Description of item
Quantity
Place of
issue
5
NIL
SCHEDULE 'C'
Sl. No.
1
Place of Issue
4
SCHEDULE D
General conditions,
Additional Conditions,
List of approved makes
SCHEDULE E
Reference to General Conditions of contract
As per part A
SCHEDULE `F:
GENERAL RULES & DIRECTIONS:
Officer Inviting tender :
As per part A
15 %
DSR 2014 (Electrical) with correction
slips up to 15.09.2015
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 103
2 (xii)
Department
CPWD
9(ii)
Clause 1:
Clause 2:
Authority for fixing compensation under clause 2.
Clause 2A:
Whether Clause 2A shall be applicable
Clause 5:
As per part A
As per part A
Amount to be
Time allowed
withheld in case of
in days (From
Non-achievement
date of start)
of Mile stone(s)
As per part A.
Authority to decide:
As per part A
As per part A
As per part A
Clause 6,6 A
6A
Rs. 8,00,000=00
Yes, Applicable
Clause 10 A:
List of testing equipments to be provided by the contractor at site:
1.Chase cutting Machine
2.Tong tester
3.Insulation Megger
4.Slide Callipers
5.Earth Megger
6. Crimping tools
7.Screw gauge
8.Vernier Scale
And all equipments reqd. for installation, testing& Commissioning of E&M Services
Clause : 10B(ii)
Whether clause 10B (ii) shall be applicable
Clause 10 C:Component of labour expressed as percent of
value of work
NO
Yes, Applicable
25 % ( Twenty Five percent)
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 104
Clause 10 CA
Not Applicable
Clause 10 CC
Not Applicable
Clause 11:
Specifications to be followed for CPWD specifications Electrical Internal
part I 2013 and External part II 1995
execution of Civil work
with correction slips upto16.09.2015
Clause 12:
Original Work
Type of work
12.2
&
12.3
12.5:
Clause 16:
Competent Authority for deciding reduced rates
Minimum
Qualification
of Technical
representative
1.
Graduate
Engineer
Or
Diploma
Engineer
Electrical
Sl.
No
Discipline
Designation
Minimum
experience
Two year
Principal Technical
(for
representative(projec
Graduate)
t
Or
planning/Site/billing
5 Years (For
Engineer
Diploma)
Rate at which
recovery shall be
made from the
contractor in the
Nos.
event of not
fulfilling
provisions of
clause 36 (i)
1
Rs.15,000(Fifte
(one) en Thousand)/No.
per month
Assistant Engineers retired from Government services that are holding Diploma will
betreated at par with Graduate Engineers.
Diploma holder with minimum 10 year relevant experience with a reputed
construction co. can be treated at par with Graduate Engineers for the purpose of such
deployment subject to the condition that such diploma holders should not exceed 50% of
requirement of degree engineers.
Clause42
Not Applicable.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 105
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 106
ADDITIONAL CONDITIONS
Sub Head :I to IX - Internal Electrical Installations, Lightning conductors, compound
lighting, water supply pump sets & Service Connection.
1. The work shall be carried out strictly in accordance with the CPWD general specification for
electrical works (part-I 2013 and part-II external 1994, and part-IV Substation as amended up
to date). All installations shall comply with the requirement of Indian electricity rules, 1956 as
amended up to date. In case of items not covered by the above specification, the work shall be
carried out as per the instruction of the Engineer-in-charge. It is mandatory to possess the
electrical license issued by the Govt. of Mizoram before the commencement of the work.
2. Approval of Engineer in charge shall be taken well in advance for all materials to be used in
the work. A list of approved make of materials to be used in the work appended in. The
contractor shall use all the materials within the make list only.
3. The contractor shall make his own arrangement for storage & watch ward of materials at his
own cost till the final handing over the installation to client department.
4. The contractor shall make his own arrangement for all T & P including special T&P.
5. Electrical work shall be progressed by the contractor side by side with the progress of building
work. Laying of conduits for recessed portions shall be in phase to gather with the building
progress so that no hindrance to the progress occurs at any stage. It will be the contractor
responsibility to keep a constant watch on the progress of the building and to co-ordinate laying
of conduits on wall/ceiling.
6. All the Steel conduits for telephone /Fire alarm system etc have to be provided with 16 SWG
steel fish wire and also suitable deep junction boxes shall be provided at a distance of not more
than 10 meters and no extra payment shall be made on this account.
7. Scope of work include providing and fixing copper lugs/ soldering for termination of multi strand
copper wire at switches, DBs and all inter connection. PVC insulated copper conductor cable up
to 6 Sq mm shall be single strand. However multi-strand wire will also be allowed to be used in
the work. In such cases conductor end shall be soldered for connecting with switch / MCB.
8. All repair and patch work shall be neatly carried out to match the original finish and to the entire
satisfaction of Engineer in charge.
9. The electrical work shall be carried out according to the drawing & schedule supplied subject to
change if any made by the Engineer in charge.
10. All the conduit drops shall be laid on walls with rough plaster prior to plastering by the civil
wing. The PVC conduits shall be terminated with suitable PVC glands / reducer.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 107
11. General Arrangement drawing for IEI with layout and drawing for panel board shall be got
approved from the Engineer in charge. These drawing shall be submitted to division office
within 15 Days after award of work.
12. Panel board shall be powder coated painting employing seven tank process.
13. Socket shall be 3 pin / 6 pin only to be used for the work.
14. Installation of MDB, SDB include making niches in walls and making good the same wherever
required.
15. All the switch boards/ MCB DBs shall be recess mounting.
16. Providing earthing lugs in all the switch board for connecting earth wire are included in the
scope of work.
17. Phenolic laminated sheet shall be at least 3 mm thick with ISI marked.
18. The minimum rupturing capacity of the MCB shall be 10 KA.
19. MCB DB, RCCB and MCB shall be same make. The loose wire box provided for the SDB shall also
be of the same make
20. For MCCBs, It should be ensured that Ics = Icuand that the MCCB shall have the rated rupturing
capacity at 415V.
21. All the control switches for point wiring and plug points shall be of Piano/Modular type switches
3pin 5/15 amps sockets shall also be of the same make type and colour to maintain uniformity
and be got approved by the Engineer-in-charge prior to its installation.
22. Bad-workman ship is liable to be rejected in total.
23. The contractor or his authorized representative will have to sign the site order book and comply
with the remarks therein .
24. All the metal boxes housing control switches, regulators and plug sockets, etc. shall be suitably
earthed and no extra amount is payable on this account.
25. Where ever connectors used should be got approved before use in work. In special cases like
fans and certain type of fittings sufficient length of wires should be left so that the same are
straight away connected to the fans and fittings with out the use of connector in between.
26. The contractor has
prevailing in the area.
to
follow
the
local
security
/safety
rules
and
regulations
27. The entire installation shall be guaranteed for proper operation for a period of 12 months from
the date of taking over. All defects noticed during this period shall be rectified immediately.
28. Only deep junction box shall be used for the recesses wiring system.
29. All MS boxes shall be covered with 3mm thick Phenolic laminated sheet.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 108
30. On completion of the work the contractor has to submit completion plan in triplicate with a CD
containing drawing. The drawing shall be developed on AutoCAD showing all electrical points
with layout.
31. The contractor shall also supply insulation and earth test reports, before the installations are
handed over to the engineer-in-charge in good condition as required under CPWD specifications,
failing which a recovery will be effected as per Clause 8B of GCC 2014.
32. The scope of work includes obtaining safety certificate from electrical inspectorate for the
electrical installation, if required for which no extra payment will be paid. However statutory
payment will be made by the department.
33. The following are the approved make of materials to be used for the work.
1
Modular type switch, Socket, Box, MK(Blenz)/ Legrand / Arteor)/ L&T(Oris), Siemens
inner & outer plate (ISI)
(Delta Vega) /CRABTREE (PICADILI)
MCB.s
RCCB
MCB DBs
MCCBs (1 cu=ics=100%)
10
11
12
13
Timer
14
Contactor
15
16
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 109
17
Led Fitting
18
Ceiling rose
19
GI pipe
20
21
22
Telephone DBs
23
PA system
Ahuja/ Philips/Samsung/Panasonic.
24
25
XLPE/ PVC insulated,: PVC Universal / Finolex/ CCI/ Polycab/ Gloster /Havells
sheathed aluminum conductor: ISI marked/RR Kabel /Crystal/
UG cable.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 110
Sl.
No.
1
2
3
4
5
ITEM.
APPROVED MAKE
KIRLOSKER/MATHER PLATT/ TEXMO/CE
KIRLOSKER/CROMPTON GREAVES/ TEXMO/CE
KIRLOSKER/ CUMMINS
TATA/JINDAL/ ZENITH
TATA/JINDAL/ ZENITH
AS PER CPWD APPROVED
PUMP
MOTOR
DIESEL ENGINE
M.S.PIPE
G.I.PIPE
ELECTRICAL PANEL/SYSTEM CONTROLLER &
CONTROL CONSOLE
7
8
PIPE SUPPORTS
SLUICE VALVE
HITECH
KALPANA /UPADHAYA / KARTAR / LEADER
LEADER / ZOLOTO
10
BUTTERFLY VALVE
INTERVALVE / AUDCO
11
HD / SPRAYSAFE
12
DUNLOP
13
PRESSURE SWITCH
WAREE / INDFOS
14
15
16
17
H GURU / FIEBIG
V GUARD
EXIDE/ STANDARD /CUMMINS
HD / SYSTEM SENSOR
WINCO/ NEW AGE / ARIHANT
19
PRESSURE GUAGES
WATER LEVEL CONTROLLER
BATTERIES
FLOW SWITCH
INTERNAL/EXTERNAL HYDRANT(LANDING
VALVE)
HOSE REEL 20 MM DIA
20
INSTALLATION VALVE
HD / SYSTEM SENSOR
21
22
23
24
25
POWER CABLES
26
CONTROL CABLES
27
28
29
30
STARTERS/CONTACTOR
FIRE ALARM PANEL
18
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 111
1. Only Contractors who are registered in CAT-A for lifts in CPWD shall be engaged for the
installation of elevator.
SH :-X ELEVATOR
COMMERCIAL AND ADDITIONAL CONDITION
1. General
1.1
1.2 Location
1.3
1.4
1.5
3.0
Terms of Payment:
The following percentage of contract rates for the various items included in the contract shall
be payable against the stage of work shown herein.
3.1
75 % after initial inspection and delivery at site in good condition of pro-rata basis. All
delivered materials at site must covers valid insurance till the equipment is handed over duly
installed, tested and commissioned.
3.2
3.3
Balance 10% will be paid after testing, commissioning trial run & handing over to the
department for beneficial use.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 112
4.
4.1
4.2
4.3
5.0
Rates:
The rates quoted by the tenderer, shall be firm and inclusive of all taxes (including work
contract taxes), duties and levies and all charges for packing forwarding, insurance, freight
and delivery, installation, testing, commissioning etc. at site i/c temporary constructional
storage, risks, over head charges general liabilities/ obligations and clearance from local
authorities. However, the fee for these inspections shall be borne by the department.
The contractor has to carry out routine & preventive maintenance for 12 months from the
date of handing over. Nothing extra shall be paid.
Octroi in duty shall not be paid separately but octroi exemption certificate can be furnished
by the department on demand. However, the department is not liable to re-imburse the octroi
duty in case exemption certificates are not honored by the concerned authorities.
Completeness of tender:
All sundry equipment, fittings, Unit assemblies, accessories, hardware items, foundation
bolts, termination lugs for electrical connections, and all other items which are useful and
necessary for efficient assembly and installation of equipment and components of the work
shall be deemed to have been included in the tender irrespectively of the fact whether such
items are specifically mentioned in the tender documents or not.
6.0
For item/equipment requiring initial inspection at manufacturer's works the contractor will
intimate the date of testing of equipments at the manufacturer's works before dispatch. The
department also reserves the right to inspect the fabrication job at factory and the successful
tenderer has to make the arrangement for the same. The successful tenderer shall give
sufficient advance notice regarding the dates proposed for such tests/ inspection to the
department's representative(s) to facilities his presence during testing / fabrication. The
Engineer - in - charge at his discretion may witness such testing/fabrication. The cost of the
Engineer s visit to the factory will be borne by the Department. Also equipment may be
inspected at the Manufacturers premises, before despatch to the site by the contractor
7.0
8.0
Care of Building:
Care shall be taken by the contractor while handling & installing the various equipments and
components of the work to avoid damage to the building. He shall be responsible for
repairing all damage and restoring the same to their original finish at his cost. He shall also
remove at his cost all unwanted and waste materials arising out of the installation from the
site of work.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 113
All equipments shall be guarantee for a period of 12 months from the date of taking over the
installation by the department against unsatisfactory performance and/ or break down due to
defective design, workmanship of material. The equipments of components, or any part
thereof, so found defective during guarantee period shall be forthwith repaired or replaced
free of cost, to the satisfaction of the Engineer-in-charge.
With Tender. The tenderer shall furnish along with the tender, detailed technical literature,
pamphlets and performance data for appraisal and evaluation of the offer.
15.0
The successful tenderer should furnish well in advance three copies for detailed instruction
and manual of manufacturers for all items of equipments regarding installation, adjustment
operation and maintenance i/c preventive maintenance & trouble shooting together with all
relevant data sheets, spare parts catalogue and work shop procedure for repairs assembly
and adjustment etc. all in triplicate.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 114
16.0Extent of work
16.1 The work shall comprise of entire labour including supervision and all materials necessary to
make a complete installation and such tests and adjustment and commissioning as may be
required by the department. The term complete installation shall not only mean major items
of the plant and equipments covered by specifications but all incidental sundry components
necessary for complete execution and satisfactory performance of installation with all lay out
charts whether or not those have been mentioned in details in the tender documents in
connection with this contract.
16.2
Minor building work necessary for installation of equipment, foundation, making of opening
in walls on floors and restoring to their condition, finish and necessary grouting etc. as
required
16.3
The work is turnkey project. Any item required for the completion of the project but left
advertantly shall be executed with-in the quoted rate.
17.0
17.1
17.2
After completion of the work in all respect, the contractor shall offer the installation for testing
and operation.
in-
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 115
20.0
Erection Tools
No tools and tackles either for unloading or for shifting the equipments for erection purposes
would be made available by the department. The successful tenderer shall make his
ownarrangement for all these facilities.
25.0
Painting
This shall include cost of painting of entire exposed iron work complete in the installation. All
equipments works shall be painted at the works before despatch to the site.
26.0
Training
The scope of works includes on job technical training of two persons at site. Nothing extra
shall be payable on this account.
27.0
Maintenance
27.1 Sufficient trained and experienced staff shall be made available to meet any exigency of work
during the guarantee period of one year from the handing over of the installation.
27.2 The maintenance, routine as well as preventive for one year from the date of taking over the
installation as per manufacturers recommendation shall be carried out and the record of the
same shall have to be maintained.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 116
28.0
Interpreting Specifications
In interpreting the specifications, the following order of decreasing importance shall be
followed in case of contradictions:
(a) Schedule of quantities
(b) Technical specifications
(c) Drawing (if any)
(d) General Specifications
(e) Relevant IS or other international code in case IS code is not available.
29.0 A separate supplementary agreement shall be made with the successful tenderer for
operation of lift during guarantee period of 1 year. The payment for operation shall be made
quarterly.
Technical parameters required and offered by firms
S.
No.
1
2
3
4
5
6
7(a)
7(b)
8.
Description of Item
Type of Lift
Number of Lifts Required (With
Location)
Load : Number of Passenger.
Rated Speed
Travel in Meters
Numbers of floor served
Inside size of lift well
Pit Depth
Clear Inside of lift car
(Width x Depth x Height)
Minimum requirement
Passenger Lifts
1 Nos.
884 Kg. (13 Passenger)
1.0 MPS
3.60 mtrs (approx)
G+1 = 2
2500mm x 1900mm
1600 mm
1100 mm x 2000 mm x 2300
mm
Rear of the Car
Microprocessor based AC
Variable Voltage Variable
Frequency
With/without attendant
Type of Operation
12(c)
Potential Free Contacts
13
13(a)
13(b)
13(c)
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 117
15
Type of Signal System
15(a)
15(b)
15(c)
15(d)
15(e)
15(f)
opening
horizontal sliding
stainless steel scratch proof
(moon rock finish/honey comb
finish) fire rated doors rated for
minimum 60 minutes.
Monochrome
LCD
digital
display position and travel
direction indicator in the car
integrated with car operating
panels.
Monochrome
LCD
digital
display position indicator and
travel direction indicator at the
all landing to be provided
above the landing doors.
Gongs & visual indication on
all landings for pre-arrival of
the car for two or more cars.
Overload warning audio and
visual indicator inside the car. (
Lift should not start on over
load)
Battery operated alarm bell
and emergency light.
Car Operating Panel with fade
proof luminous button in car
with intercom. Brail push
button system.
Luminous call buttons on all
landing Brail push button
system.
15(g)
15(h)
15(i)
16
Landing Entrance
16(a) Location of Different landing in
different floors
16(b) Number
16(c) Sizes
16(d)
Type of Door
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 118
17
Electric Supply
Lights & Fans
18
19
20.
21.
22.
Storage space provided
23.
Location of Controller
TERMS AND CONDITIONS FOR ANNUAL COMPREHENSIVE MAINTENANCE OF LIFTS:1) The works should be carried out as per CPWD specification for electrical works Part-I (Internal2005), Part-II(External-1994), Part-III (Lift-2003) amended up to date.
2) Lifts are to be supervised by competent Engineer having supervisory competence certificate
issued by the competent authority as per the standard scheduled checks & maintenance of
manufacturers.
3) Rates are inclusive of sale tax, excise duty, levy and all other taxes etc. The department will not
entertain any claim whatsoever in this regard later on.
4) Minor breakdown calls are to be attended within 24 hours. Proportionate recovery will be made
from the bill if break down is not attended within 24 Hours.
5) The agency shall engage authorised and trained personnel fully conversant with the job to
attend the site of work and the personnel engaged by the contractor shall be purely his liability
and department in no way shall be responsible for any compensation for any of their acts
/accidents.
6) The contractor shall arrange to render efficient preventive service. Prompt action should be
taken to attend the site in case of any breakdown, reported either by the department or by the
client department. However in case he fails to maintain services to the satisfaction of the
Engineer-in-charge and the department has to incur any expenditure on that account the same,
it will be recovered from the contractor. In case any complain pending because of a reason
beyond control of the contractor, he shall intimate the same to JE(E)/AE(E)/Client Department
immediately.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 119
7) The contractor or his representative should not remove or disturb or dislocate the existing
equipments unless and until authorized by the Engineer-in-charge. The contractor shall be
responsible for any damage or theft and shall have to make good to its original shape during
maintenance.
8) The personnel attending the site of work should report to the Junior Engineer (E)-in-charge/
Client department during every visit to the site of work.
1.0 GENERAL
SH :-XI DG SET
COMMERCIAL AND ADDITIONAL CONDITION
2.0 GENERAL
The firms engaged for this works shall be registered contractor in appropriate category.
1.1
This specification covers manufacture, testing as may be necessary before dispatch, delivery at
site, all preparatory work, assembly and installation, commissioning, putting into operation of DG
Set at NIOH, Mizoram.
1.2
Location the DG Set will be installed in NIOH, Mizoram
1.3
The work shall be executed as per CPWD General Specifications for Electrical works(Part VII GD
Set-2013) as per relevant IS and as per directions of E-in-C. These additional specifications are to
be read in conjunction with above and in case of variations, specifications given in this additional
conditions shall apply. However, nothing extra shall be paid on account of these additional
specifications and conditions as the same are to be read along with schedule of quantities for the
work.
1.4
The tenderer should in his/her own interest visit the site and familiarize himself/herself with the site
conditions before tendering.
1.5
No T&P shall be issued by the Department and nothing extra shall be paid on account of this.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 120
COMMERCIAL CONDITIONS
The tenderers are advised preferably not to deviate from the technical specifications/ items,
commercial terms and conditions of NIT like terms of payment, guarantee, arbitration
clause, escalation etc.
Additional Commercial Conditions
1. The Contractor shall engaged the specialized agency with the approval of Chief Engineer
NEZ II, within 90 days from the award of work. If he/she fails to do so than he/she shall
forfeit his/her right to engaged the agency and Executive Engineer( E ) shall engaged the
agency himself and execute the works at the risk and cost of the contractor.
2. If the main contractor fails to make the payment to the associated agency for the specialized
works than Executive Engineer( E ) shall make the payment to the associated agencies on
receipt of the complaint from them, at the agreement rates.
3. Completeness of the tender
All sundries equipment, fittings, assemblies, accessories, hardware items, foundation bolt &
nuts, support, terminal lugs, cable gland, gland plate, junction box, staple items, and others
for proper installation of DG Set and other components of the work shall be deemed to have
been included in the tender.
4. Tender Drawings
The drawings appended with the tender documents are intended to show space allotted for
various equipments. The equipments offered shall be suitable for installation in the spaces
shown in these drawing.
5. Drawing and documents to be furnished on completion of installation.
The contractor shall prepare & submit three sets of following drawing and get them
approved from Engineer in- charge before start of the work. Two set of laminated drawing
shall be submitted by the contractor while handing over the installation to the department.
One set laminated drawing shall be display at DG set Room. Lay out drawing of the
equipment to be installed including control cables, fuel/lube oil pipes and supports/structure
for exhaust piping,
(a) Electrical wiring diagrams from engine-alternator set to electrical control panel, Electrical
control panel to essential LT Board including the sizes and capacity of various
electrical/control cables and equipment, AMF panel given switchgear rating and their
disposition,.
(b) Dimensioned drawings of Acoustic enclosure /engine-Alternator set and Electrical
control panel.
(c) DG Set installation drawing given complete details of the equipments including their
foundations.
(d) Control wiring drawings with all control components and sequence of operation to
explain the operation of control circuits in AMF panel/PCC.
(e) Any other drawings relevant to the work.
(f) Manufacturers technical catalogues of all equipments and accessories.
(g) Operation and maintenance manual of all major equipments, detailing all adjustments,
operation and maintenance procedure.
6. If Clause 5 are not complied with, a sum equal to 2.5% of the value of the work done subject
to the ceiling of Rs.:-50,000/-(Fifty thousand only) shall be recovered from the contractor.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 121
7. The successful tenderer should furnish well in advance three copies of detailed instructions
and manuals of manufacturers for all items of equipments regarding installation, adjustment
operation and maintenance including preventive maintenance &trouble shooting together
with all relevant data sheets, spare parts catalogue etc. all in triplicate.
8. Storage and custody of materials
The DG Set Room & AMF panel room if available, may be used for storage of materials and
equipments or else the agency has to make his own arrangements. No separate storage
accommodation shall be provided by the department. Watch and ward of the store and their
safe custody shall be the responsibility of the contractor till the final taking over of the
installation by the department.
9. Restriction in work
Some restriction may be imposed by the security staff etc. on the working and/ or movement
of labour, materials etc. The contractor shall be bound to follow all such restriction/
instructions and nothing extra shall be payable on this account. No claim for idle labour shall
be entertained.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 122
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 123
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 124
21.
STATUTORY CLEARANCE(S)
Approval/ clearance of the complete installation shall be obtained by the contractor from
CPCB/ State pollution Control Boards/ Local Bodies/ Central Electricity Authority(CEA)/other
licensing authorities wherever required. However, application shall be made by Department
and any statutory fee, as applicable, shall be paid by Department directly to the govt.
authorized concerned.
(a) Clearance certificate CPCB norms for Noise level.
(b) Clearance certificate CPCB norms for Emission level.
22. Compliance with Regulations and Indian Standards.
All works shall be carried out in accordance with relevant regulation, both statutory and
those specified by the Indian Standards related to the works covered by this specification..
In particular, the equipment and installation will comply with the following.
(a) Factories Act.
(b) Indian Electricity rules.
(c) B.I.S & other standards as applicable.
(d) Workmens compensation Act.
(e) Statutory norms prescribed by the local bodies like CEA, Pollution control boards, etc.
23. Erection tools
No tools and tackles either for unloading or for shifting the equipments for erection purpose
would be made available by the department. The successful tenderer shall made his own
arrangement for all these facilities.
24. Co-operation with other Agencies
The successful tenderer shall co-ordinate with other contractors and agencies engaged in
the construction the building works, if any , and exchange freely all technical information so
as to make the execution of this work/ contact smooth.
25. The work will be carried out with least disturbance during shifting & installation of equipment
including test and trial period in consultation with the client department.
26. Insurance and storage.
All consignments are to be duly reached upto the destination from warehouse/ Factories at
the cost of the contractor. The insurance covers shall be valid till the equipment is handed
over duly installed, tested and commissioned.
27. Training.
The scope of works includes the on job technical traning of two persons of department at
site. Nothing extra shall be payable on this account.
28. Interpreting Specifications
In Interpreting the Specifications, the following order of decreasing importance shall be
followed in case of contradictions.
(a) Schedule of Quantities.
(b) Technical Specifications
(c) Drawing( if any)
(d) General specifications
(e) Relevant BIS or other international coad in case BIS code is not available.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 125
Make
Engine
Kirloskar/Cummins/CG
Alternator
Kirloskar/Cummins/CG
AMF Panel
ABB/C&S/Schnider/L&T(CPRI APPROVED)
ABB/C&S/Schnider/L&T(CPRI APPROVED)
Acoustic Enclosure
Kirloskar/Cummins/CG
Relay
ABB/C&S/Schnider/L&T
Contactor
ABB/C&S/Schnider/L&T
MS Pipe
Bansal/TATA/JINDAL
Exide/ Cummins/Amron
Finolex/Gloster/Mescab/RR KABEL/POLYCAB
Power cable
Finolex/Gloster/Mescab/RR KABEL/POLYCAB
ACB
ABB/C&S/Schnider/L&T
ABB/C&S/Schnider/L&T
Ammeter/Voltmeter/P.F Meter
ABB/C&S/Schnider/L&T
Current Transformer
ABB/C&S/Schnider/L&T
Glass wool
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 126
PART E
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-VI) EE(P-II) AE(E) EE(P-E)
Page 127
1.1
Description
Quantity
Rate
Unit
SH-I (WIRING)
Wiring for light point/ fan point/ exhaust fan point/ call
bell point with 1.5 sq.mm FRLS PVC insulated
copper conductor single core cable in surface /
recessed steel conduit, with modular switch, modular
plate, suitable GI box and earthing the point with 1.5
sq.mm. FRLS PVC insulated copper conductor
single core cable etc. as required.
(a)
Group A
118
Points
Point
(a)
Group B
(b)
Group C
Wiring for light/ power plug with 2X4 sq. mm FRLS
PVC insulated copper conductor single core cable in
surface/ recessed steel conduit along with 1 No 4 sq.
mm FRLS PVC insulated copper conductor single
core cable for loop earthing as required.
41
260
Points
Points
Point
Point
1.2
1.3
1.4
(d)
(e)
(f)
(g)
(a)
1.6
Mtr.
400 Mtr.
Mtr.
515 Mtr.
Mtr.
350 Mtr.
Mtr.
75 Mtr.
Mtr.
110 Mtr.
60 Mtr.
Mtr.
Mtr.
800 Mtr.
Mtr.
(a)
1.5
1700 Mtr.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 128
Amount
(a)
1.7
25 mm
Supplying and fixing following sizes/modules, GI box
along with modular base and cover plate for modular
switch in recess etc. as required.
900 Mtr.
Mtr.
(a)
(a)
1 or 2 module
4 module
20 Nos
49 Nos
Each
Each
(b)
12 module
Supplying and fixing following modular type switch/
socket on the existing switch box / cover including
connections etc. as required.
43 Nos
Each
1.8
(a)
172 Nos
Each
(b)
(c)
172 Nos
24 Nos
Each
Each
102
Each
1.9
1.10
1.11
1.12
1.13
1.14
2.1
2.2
Nos.
49 Nos
Each
60 Nos
Each
9 Nos
Each
5 Nos
Each
334 Nos
Each
224
Nos.
Each
30
Nos.
Each
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 129
2.3
2.4
(a)
2.5
2.6
2.7
2.8
2.9
2.10
102 Nos
Each
3 Nos.
Each
18 Nos.
Each
83 Nos
Each
28 Nos.
Each
10 Nos.
Each
4 Nos
Each
10 Nos
Each
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 130
2.11
19 Nos
Each
1 No
3 No
Each
Each
Each
SH-III - (MCB DB )
3.1
3.2
3.3
3.4
63 Amp TP&N
125 Amp TP&N
Providing and fixing following rating and breaking
capacity and pole MCCB in existing cubicle panel
board including drilling holes in cubicle panel,
making connections, etc. as required.
3.4.1
3.5
3.6
3.6.1
3.6.2
3.7
No.
1 No
Each
29 Nos
Each
3 Nos
Each
5 Nos
Each
1 No
Each
3.7.1
3.7.2
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 131
3.8
3.8.1
Single pole
3.8.2
3.9
3.9.1
332 Nos
Each
64 Nos
Each
6 Nos
Each
8 Sets
Set
Set
Set
Set
Set
20 Mtr.
Mtr.
20 Mtr.
Mtr.
40 Mtr.
Mtr.
30
Mtr.
4.1
4.2
4.3
4.4
4.5
4.6
4.7
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 132
5.1
5.2
5.3
5.4
5.5
5.6
6.1
4 Nos
Each
80 Nos.
Each
400 Mtr.
Mtr.
24 Mtr.
Mtr.
4 Nos.
Each
32 Mtr.
Mtr.
150 Mtr.
Mtr.
120 Mtr.
Mtr.
30 Mtr.
Mtr.
20 Mtr.
Mtr.
20 Mtr.
Mtr.
10 Mtr.
Mtr.
6.2
6.3
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 133
6.4
6.5
7.1
7.2
7.3
7.4
Nos.
Nos.
Each
Each
20 Mtr.
Mtr.
28 nos.
Each
cum
cum
4.5
cum
cum
7.5
8
4
28 Mtr.
Mtr.
450 Mtr.
60 Mtr.
20 Mtr.
Mtr.
Mtr.
Mtr.
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 134
7.6
7.7
7.8
7.9
31 Nos
Each
25 Nos
Each
3 Nos
Each
No.
Each
10 Nos.
Each
2 Sets
Set
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 135
8.2
8.3
9.1
9.2
10 Nos.
Each
10 Nos.
Each
2 Jobs
Job
1 Job
Job
50 Mtrs.
Mtr.
4 Nos.
Each
3 Nos.
Each
250 Mtrs.
Mtr.
9.4
9.5
9.6
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 136
9.7
9.8
9.8.1
9.8.2
10.1
100 Mtrs.
Mtr.
2 Sets
Set
1 Set
Set
1 Job
Job
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 137
10.2
11.1
12 months
month
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 138
11.2
11.3
1 Job
12 month
set
Job
month
set
Correction Nil Deletion Nil Insertion Nil Overwriting Nil AE(P-II) EE(P-I) AE(E) EE(P-E) Page 139