Professional Documents
Culture Documents
RiskDetail V201 20150921
RiskDetail V201 20150921
RiskDetail V201 20150921
ID
1616
Rank
Record Type
Risk
Status
Open
Title
Delays due to interface with JPS for works along Sg. Gasi monsoon drain and retention Pond 1 and Pond 2 at Damansara
Damai (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
23-Dec-2015
Impact
Programme delay
Additional cost of constraints imposed
Cause
Description
V1 - Interface with JPS for construction works along monsoon drain and retention ponds. All works shall comply to JPS
Justification
None
Scoring Scheme
SSP Line
Initial
Critical 25
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
6,562,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Critical 25
Owner Organisation
SSP LINE
Min
Very High
Max
7,500,000
Expected
Risk Level
Moderate
20
Min
High
Expected
Critical
Max
7,500,000
14
Risk Level
Moderate
Major
Actions
Action ID
Action Title
5359
Due Date
Completed
Action
(Successfully)
30-Jan-2015
3703
Completed
Action
(Successfully)
30-Apr-2015
3704
Design review with (DDC) to reduce impact on the Teoh, Chin Siang
monsoon drain and retention pond. Plan for
proposed works at pond 1 and pond 2 was
submitted on 15th June 2015
Completed
Action
(Successfully)
30-Jun-2015
7821
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
Actionee
Teh, Ming Hu
21/09/2015 16:51
Planned Cost
(RM)
Page 1 of 58
7825
Completed
Action
(Successfully)
14-Jul-2015
7826
Active
23-Dec-2015
- RiskDetail
Action
21/09/2015 16:51
Page 2 of 58
ID
2158
Rank
Record Type
Risk
Status
Open
Title
Existing 1.85m dia. water pipe along Jalan Kuala Selangor and Sg. Gasi which clashes with proposed alignment (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
1. Undiscovered existing 1.85m dia. water pipe along Jalan Kuala Selangor
2. Sg. Gasi located at the same position as proposed MRT alignment and pier position
3. Alignment along busy Jalan Kuala Selangor and existing U-turn ramp
Description
Existing 1.85m dia. water pipe along Jalan Kuala Selangor and Sg. Gasi clashes with proposed MRT alignment and pier
position
Justification
1.85m dia. water pipe along Jalan Kuala Selangor clashing with alignment along Damansara Damai to Sri Damansara
West where either one needs to be relocated
None
Scoring Scheme
SSP Line
Initial
Critical 25
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
21,875,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Critical 25
Owner Organisation
SSP LINE
Min
Very High
Min
Medium
Expected
Max
Risk Level
25,000,000
Critical
20
Critical
Expected
Max
7,500,000
14
Risk Level
Moderate
Major
Actions
Action ID
Action Title
Actionee
Due Date
4993
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
16-Feb-2015
5213
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
30-Jun-2015
5214
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 3 of 58
5215
5700
Completed
Action
(Successfully)
30-Jun-2015
Piloting works to identify exact location and routing Ong, Sang Woh
of existing water pipe completed on 30th April
2015
Completed
Action
(Successfully)
30-Jun-2015
6899
Completed
Action
(Successfully)
30-Jun-2015
6900
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
7346
Completed
Action
(Successfully)
15-Jul-2015
7347
Active
Action
14-Aug-2015
6997
Active
Action
03-Nov-2015
- RiskDetail
Tsou, Cheng
Hsien
21/09/2015 16:51
Page 4 of 58
ID
3256
Rank
17
Record Type
Risk
Status
Open
Title
Existing 1.85m dia. water pipe at Sri Damansara East Station which is in close proximity with proposed alignment (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
1. Undiscovered existing 1.85m dia. water pipe along Jalan Kuala Selangor
2. proposed MRT alignment pier position located right along existing 1.85m dia. water pipe and located next to Sg. Gasi
3. Alignment along busy Jalan Kuala Selangor and existing U-turn ramp
Description
Existing 1.85m dia. water pipe along Jalan Kuala Selangor and Sg. Gasi clashes with proposed MRT alignment and pier
position
Justification
1.85m dia. water pipe along Jalan Kuala Selangor clashing with alignment along Damansara Damai to Sri Damansara
West where either one needs to be relocated
None
Scoring Scheme
SSP Line
Initial
Critical 25
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Critical 25
Owner Organisation
SSP LINE
Min
Very High
Max
Expected
Risk Level
NIL
20
Min
Medium
Expected
Critical
Max
0
14
Risk Level
NIL
Major
Actions
Action ID
Action Title
Actionee
Due Date
8930
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
16-Feb-2015
8931
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
30-Jun-2015
8932
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 5 of 58
8933
8934
Completed
Action
(Successfully)
30-Jun-2015
Piloting works to identify exact location and routing Ong, Sang Woh
of existing water pipe completed on 30th April
2015
Completed
Action
(Successfully)
30-Jun-2015
8935
Completed
Action
(Successfully)
30-Jun-2015
8936
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
8938
Completed
Action
(Successfully)
15-Jul-2015
8939
Active
Action
14-Aug-2015
8937
Active
Action
03-Nov-2015
- RiskDetail
Tsou, Cheng
Hsien
21/09/2015 16:51
Page 6 of 58
ID
2569
Rank
27
Record Type
Risk
Status
Open
Title
Construction works along Pesiaran Dagang resulting to social impact - Protest, complaint from residents and commercial
owners (V201)
Trend?
NO
Actionee
Tan, Dan NY
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Tan, Dan NY
Completion Date
23-Dec-2015
Impact
Delay
Protest
Political interference
Cause
1. Noise
2. Air pollution
3.Traffic congestion
4.Disruption during construction
Description
Construction along Pesiaran Dagang - Protest, complaint from resident and commercial owners
Justification
None
Scoring Scheme
SSP Line
Initial
Critical 20
Exposure
Threat
Risk Level
Critical 20
Owner Organisation
SSP LINE
Min
Expected
Max
Risk Level
CV %
Cost (RM)
EMV (RM)
13,125,000
Time (Weeks)
Distribution
Single Point
Probability
88%
Residual
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Tan, Dan NY
Very High
Major
14
Major
NIL
Enviromental Impact
(Work Area)
NIL
Min
High
15,000,000
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Actions
Action ID
Action Title
Actionee
Due Date
7841
Selecting the of most appropriate alignment alignment at south of Persiaran Dagang adopted
as shown in submission on 15th June 2015
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
30-Jun-2015
7840
Teh, Ming Hu
Completed
Action
(Successfully)
31-Jul-2015
6360
Active
31-Dec-2015
- RiskDetail
Action
21/09/2015 16:51
Planned Cost
(RM)
Page 7 of 58
6361
Tan, Dan NY
Completed
Action
(Successfully)
31-Dec-2015
6362
Tan, Dan NY
Completed
Action
(Successfully)
31-Dec-2015
- RiskDetail
21/09/2015 16:51
Page 8 of 58
ID
2578
Rank
Record Type
Risk
Status
Open
Title
Further damage to existing underground SYABAS reservoir at the south of Persiaran Dagang during construction (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Insufficient width of road reserve with plenty of large water pipes, existing utilities and SYABAS reservoir. The existing
SYABAS reservoir is currently is a poor state and the necessary precautions and consideration shall be taken during
construction works. Further damage to existing underground SYABAS reservoir at the south of Persiaran Dagang during
construction
Justification
None
Scoring Scheme
SSP Line
Initial
Critical 20
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
13,125,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
Major 12
Exposure
Threat
Risk Level
Critical 20
Owner Organisation
SSP LINE
Min
Very High
Min
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
Probability
63%
Action Plan
Actionee
- RiskDetail
32
High
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
21/09/2015 16:51
Page 9 of 58
Actions
Action ID
Action Title
Actionee
Due Date
6395
Ethan Hsiao,
Yung-Teng
Completed
Action
(Successfully)
30-Jun-2015
6396
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
6398
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
6399
Completed
Action
(Successfully)
30-Jun-2015
6901
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
6902
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
7348
Active
Action
17-Aug-2015
7349
Active
Action
17-Aug-2015
7350
Active
Action
17-Aug-2015
6397
Jeevaratnam,
Thavaraj
Active
Action
30-Sep-2015
7832
Active
Action
30-Sep-2015
8942
Completed
Action
(Successfully)
30-Oct-2015
8943
Active
30-Oct-2015
- RiskDetail
Action
21/09/2015 16:51
Planned Cost
(RM)
Page 10 of 58
ID
2672
Rank
45
Record Type
Risk
Status
Open
Title
Persiaran Dagang (a) Possible land acquisition of existing houses and commercial lots at Sri Damansara, SD-1 to SD-4.
(V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Insufficient width of road reserve with plenty of large water pipes, existing utilities and SYABAS reservoir. Also a social
impact on the existing residential houses and commercial lots along Persiaran Dagang.
Justification
None
Scoring Scheme
SSP Line
Initial
Critical 20
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Critical 20
Owner Organisation
SSP LINE
Min
Very High
Max
Expected
Risk Level
NIL
14
Min
Medium
Expected
Major
Max
0
10
Risk Level
NIL
Moderate
Actions
Action ID
Action Title
6698
Due Date
Completed
Action
(Successfully)
30-Jun-2015
6699
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
6701
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
Actionee
21/09/2015 16:51
Planned Cost
(RM)
Page 11 of 58
6702
Completed
Action
(Successfully)
30-Jun-2015
6703
Completed
Action
(Successfully)
30-Jun-2015
6903
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
7351
To provide provisional sum for additional pre and Chen, Chean Sin
post construction condition survey for any affected
existing structures
Active
Action
17-Aug-2015
7352
Ethan Hsiao,
Yung-Teng
Active
Action
31-Aug-2015
8944
Jeevaratnam,
Thavaraj
Active
Action
30-Oct-2015
8945
Active
Action
30-Oct-2015
6700
Jeevaratnam,
Thavaraj
Active
Action
23-Dec-2015
7833
Active
Action
23-Dec-2015
- RiskDetail
21/09/2015 16:51
Page 12 of 58
ID
2571
Record Type
Risk
Status
Closed - Duplication
Title
CLOSED-COMBINED WITH RISK 2578: Construction adjacent to sensitive buildings - Existing SYABAS reservoir (V201)
Trend?
NO
Actionee
Tan, Dan NY
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Tan, Dan NY
Completion Date
23-Dec-2015
Impact
Delay
Damages
Disruption to supply of water to end user
Cause
Description
Further damage to existing underground SYABAS reservoir at the south of Persiaran Dagang during construction
Justification
None
Scoring Scheme
SSP Line
Initial
Critical 20
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
13,125,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
NIL 0
Exposure
Threat
CV %
Cost (RM)
NIL
EMV (RM)
Time (Weeks)
NIL
Distribution
Single Point
NIL
63%
Enviromental Impact
(Work Area)
NIL
Probability
- RiskDetail
Rank
57
Risk Level
Critical 20
Owner Organisation
SSP LINE
Min
Very High
Min
High
21/09/2015 16:51
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
Page 13 of 58
ID
2679
Rank
58
Record Type
Risk
Status
Open
Title
Launching of Long Span Crossing No.1 segmental box girder across KTM tracks before Damansara Damai (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
23-Dec-2015
Impact
Cause
1. Pier SB04 construction with very limited space in between KTM tracks and Jalan Kuala Selangor
2. Pier SB05 and SB06 located on slopes at both sides of the Sg. Gasis river bank
3. Insufficient vertical clearance across Jalan Kuala Selangor
4. Short window for the construction/ launching of viaduct across KTM rail
Description
Launching of segmental box girder across KTM tracks for Long Span No. 1
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
High
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Actions
Action ID
Action Title
6726
Due Date
Completed
Action
(Successfully)
30-Jun-2015
6727
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
6728
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
Actionee
21/09/2015 16:51
Planned Cost
(RM)
Page 14 of 58
6729
6730
Completed
Action
(Successfully)
30-Jun-2015
Completed
Action
(Successfully)
30-Jun-2015
7353
Completed
Action
(Successfully)
15-Jul-2015
7354
Active
Action
17-Aug-2015
6905
Jeevaratnam,
Thavaraj
Active
Action
03-Nov-2015
7834
Tan, Dan NY
Active
Action
23-Dec-2015
7835
Teh, Ming Hu
Active
Action
23-Dec-2015
7836
Tan, Dan NY
Active
Action
23-Dec-2015
7837
Tan, Dan NY
Active
Action
23-Dec-2015
- RiskDetail
21/09/2015 16:51
Page 15 of 58
ID
2857
Rank
70
Record Type
Risk
Status
Open
Title
Sg. Gasi diversion works for construction of foundation of MRT piers at Damansara Damai (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Sg. Gasi must first be diverted prior to construction of foundation of MRT piers at Damansara Damai
Justification
JPS approval is required for detention pond reclamation and realignment works in JPS Reserve
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
7,500,000
14
Risk Level
Moderate
Major
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
7383
Completed
Action
(Successfully)
30-Jun-2015
7384
Completed
Action
(Successfully)
30-Jun-2015
7385
Completed
Action
(Successfully)
30-Jun-2015
7386
Completed
Action
(Successfully)
30-Jun-2015
7388
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 16 of 58
7389
Active
Action
17-Aug-2015
7387
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 17 of 58
ID
2150
Rank
77
Record Type
Risk
Status
Open
Title
Backfilling of Pond 1 for foundation works of Damansara Damai Station and enlargement of Pond 2 to replace loss
capacity from Pond 1 causing possible programme constraints(V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Backfilling of Pond 1 for foundation works of Damansara Damai Station and enlargement of Pond 2 to cater for the original
capacity of Pond 1 and loss volume from MRT works
Justification
JPS approval is required for detention pond reclamation and realignment works in JPS Reserve
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
CV %
EMV (RM)
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Medium
Max
Expected
Risk Level
NIL
14
Min
Cost (RM)
Expected
Major
Max
0
10
Risk Level
NIL
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
4987
Completed
Action
(Successfully)
30-Jun-2015
5211
Completed
Action
(Successfully)
30-Jun-2015
5212
Completed
Action
(Successfully)
30-Jun-2015
6835
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 18 of 58
7360
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
7361
Active
Action
17-Aug-2015
7006
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 19 of 58
ID
2673
Rank
84
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
17-Mar-2014
Impact
Cause
Description
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
Expected
Max
Risk Level
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
High
Min
Medium
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Actions
Action ID
Action Title
6704
Due Date
Workshop with MRTC 11th April 2014 to 18th April Chin, Chee Wee
2014
Completed
Action
(Successfully)
30-Jun-2015
6705
Completed
Action
(Successfully)
30-Jun-2015
6706
Completed
Action
(Successfully)
30-Jun-2015
6707
Teh, Ming Hu
Active
Action
31-Aug-2015
6708
Teh, Ming Hu
Active
Action
23-Dec-2015
- RiskDetail
Actionee
21/09/2015 16:51
Planned Cost
(RM)
Page 20 of 58
ID
2675
Rank
89
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Jeevaratnam, Thavaraj
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Insufficient vertical height clearance of roads during construction at Jalan Kuala Selangor, Jalan PJU 10/9, Jalan Kuala
Selangor, Persiaran Utama, Jalan Jati, Persiaran Cemara, Jalan Dagang, Jalan Puncak Desa, Jalan Kepong, Jalan Metro
Perdana, Jalan Jinjing, Jalan Kuching, Duke and Jalan Ipoh
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Minor
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Jeevaratnam, Thavaraj
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
7,500,000
Risk Level
Moderate
Actions
Action ID
Action Title
6714
Due Date
Completed
Action
(Successfully)
30-Jun-2015
6715
Completed
Action
(Successfully)
30-Jun-2015
7376
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
17-Aug-2015
7377
Jeevaratnam,
Thavaraj
Active
17-Aug-2015
- RiskDetail
Actionee
Action
21/09/2015 16:51
Planned Cost
(RM)
Page 21 of 58
7391
- RiskDetail
Active
Action
21/09/2015 16:51
17-Aug-2015
Page 22 of 58
ID
2677
Rank
94
Record Type
Risk
Status
Open
Title
Utility mapping data does not accurately capture all existing utilities along alignment and affected areas (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Inadequate and inaccurate utility mapping data along the proposed alignment and other affected areas not being captured
in design
Justification
Unable to plan & proposed proper utility diversion plan due to uncharted utilities.
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Medium
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
6718
Completed
Action
(Successfully)
30-Jun-2015
6719
Completed
Action
(Successfully)
30-Jun-2015
6720
Piloting along Jalan Kuala Selangor and Persiaran Ong, Sang Woh
Dagang completed on 10th April 2015
Completed
Action
(Successfully)
30-Jun-2015
6721
Cross checking of utility mapping data with piloting Ong, Sang Woh
data obtained
Active
Action
30-Sep-2015
6904
Active
Action
30-Oct-2015
- RiskDetail
Jeevaratnam,
Thavaraj
21/09/2015 16:51
Planned Cost
(RM)
Page 23 of 58
6999
- RiskDetail
Active
Action
21/09/2015 16:51
03-Nov-2015
Page 24 of 58
ID
1994
Rank
100
Record Type
Risk
Status
Open
Title
Launching of Long Span Crossing No.3 segmental box girder crossing junction of Jalan Kuala Selangor - LDP - DUKE
Highway extension before Sri Damansara East station (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
1. Construction of tall piers approximately 20m in height with close proximity to the new DUKE extension
2. Construction works at busy Jalan Kuala Selangor and LDP intersection
3. Construction likely to take place after completion of DUKE 2
Description
Special span support on bearing and requires temporary support during construction
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Actions
Action ID
Action Title
Actionee
Due Date
7371
Completed
Action
(Successfully)
17-Jun-2015
4933
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
5248
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
5249
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 25 of 58
5250
7370
Completed
Action
(Successfully)
30-Jun-2015
Completed
Action
(Successfully)
14-Jul-2015
7372
Teh, Ming Hu
Active
Action
18-Aug-2015
7001
Teh, Ming Hu
Completed
Action
(Successfully)
03-Nov-2015
- RiskDetail
Tsou, Cheng
Hsien
21/09/2015 16:51
Page 26 of 58
ID
2112
Rank
108
Record Type
Risk
Status
Open
Title
Cantilever structure along Sg. Gasi for pier construction and road diversion along Jalan Kuala Selangor (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Cantilever structure encroaching into JPS reserve requires approval to construct within JPS reserve
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Actions
Action ID
Action Title
Actionee
Due Date
4928
Completed
Action
(Successfully)
30-Jun-2015
5209
Completed
Action
(Successfully)
30-Jun-2015
5210
Completed
Action
(Successfully)
30-Jun-2015
6833
Completed
Action
(Successfully)
30-Jun-2015
7358
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 27 of 58
7359
Active
Action
17-Aug-2015
7002
Teh, Ming Hu
Active
Action
03-Nov-2015
7003
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 28 of 58
ID
2856
Rank
116
Record Type
Risk
Status
Open
Title
Demolition and reconstruction of new Ingress/ Egress bridge across Sg. Gasi at Sri Damansara Station (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Ingress/ egress bridge encroaching into JPS reserve requires approval to construct within JPS reserve
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Actions
Action ID
Action Title
Actionee
Due Date
7362
Completed
Action
(Successfully)
30-Jun-2015
7363
Completed
Action
(Successfully)
30-Jun-2015
7364
Completed
Action
(Successfully)
30-Jun-2015
7365
Completed
Action
(Successfully)
30-Jun-2015
7368
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 29 of 58
7369
Active
Action
17-Aug-2015
7366
Teh, Ming Hu
Active
Action
03-Nov-2015
7367
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 30 of 58
ID
2113
Rank
124
Record Type
Risk
Status
Open
Title
Encroachment of viaducts ROW in existing IWK pump house NPS PJA270 at Damansara Damai (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Relocation of pump house will delay construction as land allocation or land acquisition is involved
Cause
Description
IWK does not allow encroachment of the ROW to encroach into their airspace
Justification
Close proximity of viaduct to the existing IWK pump house NPS PJA270 at Damansara Damai
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 6
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
450,000
Time (Weeks)
Distribution
Single Point
Probability
15%
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Low
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
3,000,000
10
Risk Level
Minor
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
4918
30-Jun-2015
5230
30-Jun-2015
5231
30-Jun-2015
5232
Completed
Action
(Successfully)
30-Jun-2015
6906
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
Jeevaratnam,
Thavaraj
21/09/2015 16:51
Due Date
Planned Cost
(RM)
Page 31 of 58
7373
Action
17-Aug-2015
7004
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 32 of 58
ID
2393
Rank
131
Record Type
Risk
Status
Open
Title
Settlement and instability due to adjacent construction site at Proposed International School at Sierramas before
Damansara Damai Station and Proposed Mixed Development at Sri Damansara before Sri Damansara East Station (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Delay in Construction.
Unexpected ground conditions.
Compensation claims
Cause
1. Settlement and stability of slope due to construction works and resulting to collapse
2. Operation and mobilization of heavy machinery and construction vehicles
Description
Justification
Construction of piers in close proximity to existing RE wall at Kepong Sentral may cause damage to existing structure
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Minor 4
Exposure
Threat
CV %
Cost (RM)
3,000,000
Minor
EMV (RM)
450,000
Time (Weeks)
Minor
Distribution
Single Point
NIL
Probability
15%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Low
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
Actions
Action ID
Action Title
Actionee
Due Date
5859
Completed
Action
(Successfully)
30-Jun-2015
5860
Completed
Action
(Successfully)
30-Jun-2015
5861
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
Tsou, Cheng
Hsien
21/09/2015 16:51
Planned Cost
(RM)
Page 33 of 58
5862
Completed
Action
(Successfully)
30-Jun-2015
7008
Completed
Action
(Successfully)
03-Nov-2015
7009
Completed
Action
(Successfully)
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 34 of 58
ID
2193
Rank
137
Record Type
Risk
Status
Open
Title
Alignment of new DUKE Highway extension conflicting with MRT before Sri Damansara East station (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Gittoes, Glenn
Completion Date
03-Nov-2015
Impact
Cause
Description
Justification
New Proposed DUKE Highway extension conflicting with MRT before Sri Damansara East station (V1)
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
9,375,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Insignificant 1
Exposure
Threat
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
High
Min
Expected
Max
Risk Level
15,000,000
Major
14
Major
Expected
Max
Risk Level
CV %
Cost (RM)
EMV (RM)
12,500
Time (Weeks)
Insignificant
Distribution
Single Point
NIL
Probability
3%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Undefined
Very Low
500,000
Insignificant
Actions
Action ID
Action Title
Actionee
Due Date
7374
Completed
Action
(Successfully)
14-May-2015
5147
Completed
Action
(Successfully)
30-Jun-2015
6518
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
7375
Completed
Action
(Successfully)
17-Aug-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 35 of 58
7007
- RiskDetail
Completed
Action
(Successfully)
21/09/2015 16:51
03-Nov-2015
Page 36 of 58
ID
1618
Rank
142
Record Type
Risk
Status
Closed - Duplication
Title
CLOSED-COMBINED WITH RISK 2150: Possible programme constraints at Damansara Damai Station (Construction
works at retention pond 1 and pond 2) (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
31-Dec-2015
Impact
Programme constraints
Cause
Description
Justification
None
Scoring Scheme
SSP Line
Initial
Major 16
Exposure
Threat
Risk Level
Major 16
Owner Organisation
SSP LINE
Min
Expected
Max
CV %
EMV (RM)
Time (Weeks)
Distribution
Single Point
Probability
63%
Residual
NIL 0
Exposure
Threat
CV %
Cost (RM)
NIL
EMV (RM)
Time (Weeks)
NIL
Distribution
Single Point
NIL
Probability
0%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Undefined
High
Risk Level
Cost (RM)
14
Major
NIL
Enviromental Impact
(Work Area)
NIL
Min
NIL
NIL
Expected
Max
Risk Level
Actions
Action ID
Action Title
Actionee
Due Date
3705
Tan, Dan NY
Completed
Action
(Successfully)
31-May-2015
3706
Completed
Action
(Successfully)
31-May-2015
7838
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
5146
Saunders, Julian
Derek
Active
31-Aug-2015
- RiskDetail
Action
21/09/2015 16:51
Planned Cost
(RM)
Page 37 of 58
8511
- RiskDetail
Saunders, Julian
Derek
Active
Action
21/09/2015 16:51
31-Dec-2015
Page 38 of 58
ID
2572
Record Type
Risk
Status
Open
Title
Long Span Crossing No. 3 crossing over LDP interchange - High structure and working above busy traffic (V201)
Trend?
NO
Actionee
Tan, Dan NY
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Tan, Dan NY
Completion Date
23-Dec-2015
Impact
Cause
Description
Special span over LDP interchange - High structure and working above busy traffic
Justification
None
Scoring Scheme
SSP Line
Initial
Major 15
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
6,562,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
88%
Enviromental Impact
(Work Area)
NIL
Residual
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
Probability
63%
Action Plan
Actionee
Undefined
- RiskDetail
Rank
147
Risk Level
Major 15
Owner Organisation
SSP LINE
Min
Very High
Min
High
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
21/09/2015 16:51
Page 39 of 58
ID
2684
Rank
148
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Jeevaratnam, Thavaraj
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Insufficient vertical height clearance of roads post construction at Jalan Kuala Selangor Ramp, Jalan PJU 10/9, Jalan
Kuala Selangor, Persiaran Utama, Jalan Jati, Persiaran Cemara, Jalan Dagang, Jalan Puncak Desa, Jalan Kepong, Jalan
Metro Perdana, Jalan Jinjing, Jalan Kuching, Duke and Jalan Ipoh
Justification
None
Scoring Scheme
SSP Line
Initial
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Minor
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Jeevaratnam, Thavaraj
Risk Level
Major 12
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
7,500,000
Risk Level
Moderate
Actions
Action ID
Action Title
Actionee
Due Date
6744
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
6745
Completed
Action
(Successfully)
30-Jun-2015
7379
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
17-Jul-2015
7380
Jeevaratnam,
Thavaraj
Active
Action
17-Aug-2015
7390
Active
Action
17-Aug-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 40 of 58
ID
2686
Rank
153
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Delay in obtaining approval, require complete design change and overall delivery of project.
Cause
1. Failure in obtaining Road Safety Audit (RSA) approval due to failure of compliance
Description
Road Safety Audit (RSA) approval required on all proposed road diversions traffic improvement plans.
Justification
None
Scoring Scheme
SSP Line
Initial
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
1,125,000
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Risk Level
Major 12
Owner Organisation
SSP LINE
Min
High
Min
Medium
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
3,000,000
10
Risk Level
Minor
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
6748
Completed
Action
(Successfully)
30-Jun-2015
6749
Completed
Action
(Successfully)
30-Jun-2015
6750
Completed
Action
(Successfully)
30-Jun-2015
6751
Completed
Action
(Successfully)
30-Jun-2015
7010
Active
Action
03-Nov-2015
7011
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 41 of 58
ID
1991
Rank
159
Record Type
Risk
Status
Open
Title
Launching of Long Span Crossing No. 2 segmental box girder close to existing u-turn ramp at Jalan Kuala Selangor after
Sri Damansara West station (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Justification
Construction works on top of Jalan Kuala Selangor will require proper planning of works.
None
Scoring Scheme
SSP Line
Initial
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
4,687,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
63%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
Risk Level
Major 12
Owner Organisation
SSP LINE
Min
High
Min
CV %
Cost (RM)
EMV (RM)
1,125,000
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Medium
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
3,000,000
10
Risk Level
Minor
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
7356
Completed
Action
(Successfully)
19-Jun-2015
4931
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
5235
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
5236
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 42 of 58
5237
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
6908
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
7355
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
7357
To provide provisional sum for additional pre and Chen, Chean Sin
post construction condition survey for U-turn ramp
structure
Active
Action
17-Aug-2015
7013
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 43 of 58
ID
1992
Rank
168
Record Type
Risk
Status
Open
Title
DDCs design works have been based on PDP/ MRTCs draft version (a) Employees Requirements doc (b) Design Criteria
doc (c) DEIA doc pending public display (d) Material & Worksmanship (M&W) doc (e) Particular Specifications doc (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
1. Major impact on costs and time if final official document issued by PDP/ MRTC contains significant changes
Description
To date all design works have been based on PDP/ MRTCs draft versions or pending public display
Justification
Major impact on costs and time if final official document issued by PDP/ MRTC contains significant changes
None
Scoring Scheme
SSP Line
Initial
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Risk Level
Major 12
Owner Organisation
SSP LINE
Min
Medium
Max
Expected
Risk Level
NIL
14
Min
Medium
Expected
Major
Max
0
10
Risk Level
NIL
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
4932
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
5238
Active
Action
24-Aug-2015
7392
Active
Action
31-Aug-2015
7015
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 44 of 58
5239
Active
Action
30-Nov-2015
5240
Active
Action
30-Nov-2015
5705
Active
Action
30-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 45 of 58
ID
2688
Rank
175
Record Type
Risk
Status
Open
Title
Pile cap level above ground due to irregular survey levels along alignment. Discrepancy in cross sections (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Justification
Pile cap level above ground due to irregular survey levels along alignment. Discrepancy in cross sections
None
Scoring Scheme
SSP Line
Initial
Major 12
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 6
Exposure
Threat
CV %
Cost (RM)
NIL
EMV (RM)
Time (Weeks)
Minor
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Major 12
Owner Organisation
SSP LINE
Min
Medium
Max
Expected
Risk Level
NIL
14
Min
Medium
Expected
Major
Max
Risk Level
Actions
Action ID
Action Title
Actionee
Due Date
7378
Completed
Action
(Successfully)
16-Jun-2015
6756
Completed
Action
(Successfully)
30-Jun-2015
6757
Completed
Action
(Successfully)
30-Jun-2015
6758
Completed
Action
(Successfully)
30-Jun-2015
6759
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 46 of 58
6760
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
6907
Jeevaratnam,
Thavaraj
Active
Action
30-Oct-2015
7012
Active
Action
30-Oct-2015
6761
Active
Action
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 47 of 58
ID
2698
Rank
184
Record Type
Risk
Status
Open
Title
No SI data for proposed locations for MSPRs, station ancillary buildings, facilities and new structures which are located
away from alignment (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
1. Inadequate SI done at site for proposed locations for MSPRs, station ancillary buildings, facilities and new structures
which are located away from alignment
2. Delay in survey information
Description
Inadequate site information or soil parameters for design of foundation, shoring or retaining structures
Justification
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
1,125,000
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Medium
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
3,000,000
10
Risk Level
Minor
Moderate
Actions
Action ID
Action Title
Actionee
Due Date
6790
Completed
Action
(Successfully)
30-Jun-2015
6792
Completed
Action
(Successfully)
30-Jun-2015
6791
Active
30-Oct-2015
- RiskDetail
Action
21/09/2015 16:51
Planned Cost
(RM)
Page 48 of 58
ID
2694
Rank
187
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Jeevaratnam, Thavaraj
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
30-Nov-2015
Impact
Cause
Description
Unable to fully identify and mitigate social impacts along alignment especially buildings and structures affected
Justification
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
Probability
38%
Action Plan
Actionee
Jeevaratnam, Thavaraj
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Medium
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
7381
Ethan Hsiao,
Yung-Teng
Active
Action
14-Sep-2015
6782
Active
Action
30-Oct-2015
6783
Jeevaratnam,
Thavaraj
Active
Action
30-Nov-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 49 of 58
ID
2690
Rank
190
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Justification
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 6
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
1,125,000
Time (Weeks)
Distribution
Single Point
Probability
15%
Action Plan
Actionee
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Low
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
Due Date
6769
Completed
Action
(Successfully)
30-Jun-2015
6770
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jul-2015
6768
Active
Action
03-Nov-2015
6910
Jeevaratnam,
Thavaraj
Active
Action
23-Dec-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 50 of 58
ID
2696
Rank
194
Record Type
Risk
Status
Open
Title
Inadequate coordination between respective fields involving internal & external parties and sub-consultants (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Justification
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Moderate 6
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
450,000
Time (Weeks)
Distribution
Single Point
Probability
15%
Action Plan
Actionee
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Low
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
3,000,000
10
Risk Level
Minor
Moderate
NIL
Enviromental Impact
(Work Area)
NIL
Actions
Action ID
Action Title
Actionee
6786
Action
23-Dec-2015
6787
Action
23-Dec-2015
6911
Jeevaratnam,
Thavaraj
Active
Action
23-Dec-2015
6912
Jeevaratnam,
Thavaraj
Active
Action
23-Dec-2015
- RiskDetail
21/09/2015 16:51
Due Date
Planned Cost
(RM)
Page 51 of 58
ID
2141
Rank
198
Record Type
Risk
Status
Open
Title
Construction of foundation for piers in close proximity to existing L-shaped walls along Sg. Gasi at Sri Damansara West
(V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Pier in close proximity to existing monsoon drain wall along Sg. Gasi
Justification
Pier in close proximity to existing monsoon drain wall along Sg. Gasi may result in damage of the existing monsoon drain
structure
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Minor 4
Exposure
Threat
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
CV %
Cost (RM)
EMV (RM)
450,000
Time (Weeks)
Minor
Distribution
Single Point
NIL
Probability
15%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Low
3,000,000
Minor
Actions
Action ID
Action Title
Actionee
Due Date
4940
Study of piers in close proximity to existing Lshaped wall along Sg. Gasi submitted on 2nd Jun
2015
Completed
Action
(Successfully)
30-Jun-2015
5276
Completed
Action
(Successfully)
30-Jun-2015
5278
Tsou, Cheng
Hsien
Completed
Action
(Successfully)
30-Jun-2015
6909
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 52 of 58
7382
Completed
Action
(Successfully)
15-Jul-2015
5277
Active
Action
03-Nov-2015
7014
Completed
Action
(Successfully)
03-Nov-2015
- RiskDetail
21/09/2015 16:51
Page 53 of 58
ID
2700
Rank
205
Record Type
Risk
Status
Open
Title
Survey data obtained is not sufficient to accurately capture the actual surface profile along alignment and affected areas
(V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Inadequate and inaccurate survey data along the proposed alignment and other affect areas
Justification
Survey data along the proposed alignment and other affect areas
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Minor 4
Exposure
Threat
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
CV %
Cost (RM)
EMV (RM)
450,000
Time (Weeks)
Minor
Distribution
Single Point
NIL
Probability
15%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Low
3,000,000
Minor
Actions
Action ID
Action Title
Actionee
Due Date
6796
Completed
Action
(Successfully)
30-Jun-2015
6797
Completed
Action
(Successfully)
30-Jun-2015
6798
Completed
Action
(Successfully)
30-Jun-2015
6799
Completed
Action
(Successfully)
30-Jun-2015
6800
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 54 of 58
6913
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
6801
Active
30-Oct-2015
- RiskDetail
Action
21/09/2015 16:51
Page 55 of 58
ID
2704
Rank
212
Record Type
Risk
Status
Open
Title
Pre-condition survey for existing properties especially sensitive structures along alignment at all time of construction (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Asokkumaran, Suhashini
Completion Date
03-Nov-2015
Impact
Cause
Description
Justification
Pre-condition survey for existing private properties especially sensitive structures along alignment in order to monitor the
effects of construction works on existing building
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Minor 2
Exposure
Threat
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
CV %
Cost (RM)
EMV (RM)
75,000
Time (Weeks)
Insignificant
Distribution
Single Point
NIL
Probability
15%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Low
500,000
Insignificant
Actions
Action ID
Action Title
Actionee
Due Date
6812
Active
Action
31-Dec-2015
6813
Completed
Action
(Successfully)
31-Dec-2015
6814
Completed
Action
(Successfully)
31-Dec-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 56 of 58
ID
2692
Rank
215
Record Type
Risk
Status
Open
Title
Design loadings for structural elements - Design Loadings for Pile Analysis (V201)
Trend?
NO
Actionee
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
03-Nov-2015
Impact
Cause
Description
Assumption of design loadings for structural elements made during initial stages
Justification
Accurate design loadings and design parameters are vital in producing an optimized design
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Insignificant 1
Exposure
Threat
CV %
Cost (RM)
500,000
Insignificant
EMV (RM)
12,500
Time (Weeks)
Insignificant
Distribution
Single Point
NIL
Probability
3%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Very Low
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
Actions
Action ID
Action Title
Actionee
Due Date
6774
Completed
Action
(Successfully)
30-Jun-2015
6775
Completed
Action
(Successfully)
30-Jun-2015
6776
30-Jun-2015
6777
Completed
Action
(Successfully)
30-Jun-2015
7018
Active
03-Nov-2015
- RiskDetail
Action
21/09/2015 16:51
Planned Cost
(RM)
Page 57 of 58
ID
2702
Rank
220
Record Type
Risk
Status
Open
Title
Trend?
NO
Actionee
Jeevaratnam, Thavaraj
Last Review
Manager
Undefined
Reviewed By
Undefined
Raised By
Completion Date
30-Nov-2015
Impact
Cause
1. Failure to take into account the affect of the revised alignment on the proposed pylon relocation works
Description
Failure to take into account the affect of the revised alignment on the proposed pylon relocation works will result in clashes
and insufficient clearance between the transmission cables and the MRT line
Justification
None
Scoring Scheme
SSP Line
Initial
Moderate 9
Exposure
Threat
CV %
Cost (RM)
EMV (RM)
2,812,500
Time (Weeks)
Distribution
Single Point
NIL
Probability
38%
Enviromental Impact
(Work Area)
NIL
Residual
Insignificant 1
Exposure
Threat
CV %
Cost (RM)
500,000
Insignificant
EMV (RM)
12,500
Time (Weeks)
Insignificant
Distribution
Single Point
NIL
Probability
3%
Enviromental Impact
(Work Area)
NIL
Action Plan
Actionee
Jeevaratnam, Thavaraj
Risk Level
Moderate 9
Owner Organisation
SSP LINE
Min
Medium
Min
Very Low
Expected
Max
Risk Level
7,500,000
Moderate
10
Moderate
Expected
Max
Risk Level
Actions
Action ID
Action Title
Actionee
Due Date
6808
Completed
Action
(Successfully)
30-Jun-2015
6809
Jeevaratnam,
Thavaraj
Completed
Action
(Successfully)
30-Jun-2015
7842
Teh, Ming Hu
Completed
Action
(Successfully)
30-Jun-2015
- RiskDetail
21/09/2015 16:51
Planned Cost
(RM)
Page 58 of 58