Estimate For IIS

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 14

Estimate for Construction of House

NO
A

DESCRIPTION
Earth Works
Site clearing
Excavation for wall foundation(2'*2') and Column
Footing
Earth Filling & Compacting the Floor
Masonry Work
Random Rubble Masonry in cement sand mortar 1:5 in
foundation up to DPC Level
5'' Block work Casting and Placing
4'' Block work Casting and Placing
Concrete Work
Lean concrete 1:3:6(1'') for Wall Foundation & Column
Footing
Column Footing including 10mm tor bar & F/W as per
details
Column Concreting including 4Nos 12mm tor bar &
F/W and plastering
Beam concreting including R/F details in drawing and
Formwork
4'' Slab concreting including R/F and Formwork
Lintel 6''*4'' including R/F and F/W
Arch Lintel 6''*4'' including R/F and F/W
3'' Floor concrete 1:21/2:5 including ramping on front
site

Carpentry and Joiner


Under ceiling comprising of 4*2 joists and 2*2 bearers
in class 1 timber including
Main Door with design D1 Muthurai (5''*4'') including
Varnish Painting
Internal doors D2 Vempu
Internal doors D2 Muthurai
Door D3 Muthurai
Bath room door plastic
Window W1
Window W2
Fanlight

Page 1 of 14

QUANTITY
1.00

UNIT
Item

14.00 Cube
17.00 Cube

19.00 Cube
15.50 Sqrs
16.50 Sqrs

7.00

Sqrs

4.00

Nos

48.00

L.ft

25.00

L.ft

6.25
340.00
34.00

Sqrs
L.ft
L.ft

17.00

Sqrs

17.50

Sqrs

1.00
1.00
3.00
4.00
2.00
6.00
4.00
4.00

Nos
Nos
Nos
Nos
Nos
Nos
Nos
Nos

NO
E

DESCRIPTION
Roof Work
Roof frame work
ridge tiling
9'' Valance board
Upvc gutter
Down pipe

QUANTITY

Plasterer
DPC
Plinth Plaster
Tiling
Plastering internal
Plastering external
sofit plastering

3.50
2.25
19.50
48.50
15.50
12.50

Sqrs
Sqrs
Sqrs
Sqrs
Sqrs
Sqrs

15.50
48.50
12.50

Sqrs
Sqrs
Sqrs

1.00
1.00
1.00
1.00
2.00
1.00

No
No
No
No
No
Item

7.00
10.00
12.00
6.00
2.00
1.00

No
No
No
No
No
No

1.00
30.00
55.00

Item
L.ft
L.ft

Electrical work
Fan with wiring
Tube light
Bulb
5 amp
15 amp
Main

Sqrs
L.ft
L.ft
L.ft
L.ft

Plumbing
Commode with necessary pipe lines
Squatting pan with necessary pipe lines
Wash basin with necessary pipe lines
Sink with necessary pipe lines
bib tap and showers
Pipe lines connected to existing pit

21.00
110.00
172.00
172.00
96.00

Painting
External
Internal
Soffit

UNIT

Miscellaneous
work top and chimney
design work for Verandah
cement grill work for above verandah
Page 2 of 14

NO

DESCRIPTION
Construction of Boundary wall
Construction of water tank
Construction of soakage pit
Landscaping

Earth Works

Masonry Work

C
D

Concrete Work
Carpentry and Joiner

Roof Work

Plasterer

Painting

Plumbing

Electrical work

Miscellaneous

QUANTITY UNIT
200.00 L.ft
1.00 Item
1.00 Item
1.00 Item

Total
Discount
Grand total

Page 3 of 14

RATE

AMOUNT

5000.00

5000.00

1500.00
2400.00

21000.00
40800.00
66,800.00

21000.00
17500.00
15500.00

399000.00
271250.00
255750.00
926,000.00

8000.00

56000.00

5000.00

20000.00

650.00

31200.00

500.00

12500.00

55000.00
450.00
500.00

343750.00
153000.00
17000.00

9000.00

153000.00
786,450.00

22000.00

385000.00

36000.00
18500.00
21500.00
19500.00
10000.00
29500.00
26500.00
4000.00

36000.00
18500.00
64500.00
78000.00
20000.00
177000.00
106000.00
16000.00
901,000.00
Page 4 of 14

RATE

AMOUNT

29500.00
100.00
175.00
160.00
150.00

619500.00
11000.00
30100.00
27520.00
14400.00
702,520.00

5500.00
4500.00
26000.00
3500.00
3500.00
4200.00

19250.00
10125.00
507000.00
169750.00
54250.00
52500.00
812,875.00

2000.00
2000.00
2000.00

31000.00
97000.00
25000.00
153,000.00

10500.00
4000.00
5000.00
6000.00
3000.00
20000.00

10500.00
4000.00
5000.00
6000.00
6000.00
20000.00
51,500.00

6000.00
2500.00
1500.00
1750.00
2250.00
15000.00

42000.00
25000.00
18000.00
10500.00
4500.00
15000.00
115,000.00

30000.00
250.00
250.00

30000.00
7500.00
13750.00
Page 5 of 14

RATE
1550.00
250000.00
75000.00
50000.00

AMOUNT
310000.00
250000.00
75000.00
50000.00
736,250.00

66,800.00
926,000.00
786,450.00
901,000.00
702,520.00
812,875.00
153,000.00
51,500.00
115,000.00
736,250.00
5251395.00
1395.00
5,250,000.00

Page 6 of 14

Construction Programme
Se.no

Work

Site Mobilization

Earth Works

3
4
5
6
7
8
9
10
11

No.of workers
Skill , UnSkill

62

Masonry Work

156

274

Concrete Work
Carpentry and Joiner

32

84

188

112

49

58

185

180

70

30

14

14

22

22

130

260

846

1096

Roof Work
Plasterer
Painting
Plumbing
Electrical work
Miscellaneous
Total Workers

1st Month

2nd Month

3rd Month

4th Month

S 105, U 210

S 160, U 230

S 150, U 190

S 180, U 180

5th Month

6th Month

S 136, U 150

S 115, U 136

Item

Description

1
2
3
4
5

Progress each month %


Cumulative Progress %
Progress in rupees Rs
Cumulative Progress in rupees Rs
Preliminaries
Revenue:
Payments
Cumulative payments
6 Purchase of Materials
1. cement
2. sand
3. Metal
4. Soil for earth filling
5. Rubbles
6. Shuttering materials
7. Steel
8. Roof Materials
9. Carpentary items
9. Plumbing Items
10. Electrical Items
11. tiles
12. Paint
Total Materials Monthly
Cumulative materials
Man Power
a. Labour
b. Mason
c. Carpenter

End of 1st

End of 2nd

End of 3rd

End of 4th

End of 5th

Month
Month
Month
Month
Month
12.50%
20.19%
25.00%
21.15%
14.42%
12.50%
32.69%
57.69%
78.85%
93.27%
650,000.00 1,050,000.00 1,300,000.00 1,100,000.00
750,000.00
650,000.00 1,700,000.00 3,000,000.00 4,100,000.00 4,850,000.00

585,000.00
945,000.00 1,210,000.00
585,000.00 1,530,000.00 2,740,000.00
50,000.00
10,000.00
10,000.00
50,000.00
25,000.00
10,000.00

200,000.00
30,000.00
50,000.00
20,000.00
50,000.00

200,000.00
30,000.00
75,000.00

100,000.00
30,000.00
40,000.00

20,000.00

200,000.00
300,000.00

400,000.00

150,000.00

25,000.00
20,000.00

30,000.00
50,000.00
150,000.00

155,000.00
155,000.00

370,000.00
805,000.00
720,000.00
275,000.00
525,000.00 1,330,000.00 2,050,000.00 2,325,000.00

115,500.00
73,500.00

126,500.00

104,500.00

99,000.00

82,500.00

d. Blacksmith
e. Plumber
f. Painter
g. Electrician
Total labour cost
Cumulative labour cost
Overheads
Interest
Total expences
Total Cumulative Expencess

189,000.00
126,500.00
104,500.00
99,000.00
82,500.00
189,000.00
315,500.00
420,000.00
519,000.00
601,500.00
80,000.00
75,000.00
60,000.00
60,000.00
60,000.00
20,000.00
20,000.00
20,000.00
20,000.00
20,000.00
444,000.00
591,500.00
989,500.00
899,000.00
437,500.00
444,000.00 1,035,500.00 2,025,000.00 2,924,000.00 3,361,500.00

60000001

2
3
4
5000000
5
6
9
4000000
18

444000
1035500
2025000
2924000
3361500
3591300
3591300
3591300

0
0
585000
1530000
2740000
3840000
4940000
5200000

3000000

2000000

1000000

0
0

10

12

14

16

1000000

0
0

10

12

14

16

End of 6th

End of 9th

End of 18th

Month

Month

Month

6.73%
100.00%
350,000.00
5,200,000.00

1,100,000.00 1,100,000.00
260,000.00
3,840,000.00 4,940,000.00 5,200,000.00

25,000.00
50,000.00
75,000.00
2,400,000.00
74,800.00

74,800.00
676,300.00
60,000.00
20,000.00
229,800.00
3,591,300.00 3,591,300.00 3,591,300.00

Colu
mn D

12

14

16

18

20

12

14

16

18

20

You might also like