Professional Documents
Culture Documents
Estimate For IIS
Estimate For IIS
Estimate For IIS
NO
A
DESCRIPTION
Earth Works
Site clearing
Excavation for wall foundation(2'*2') and Column
Footing
Earth Filling & Compacting the Floor
Masonry Work
Random Rubble Masonry in cement sand mortar 1:5 in
foundation up to DPC Level
5'' Block work Casting and Placing
4'' Block work Casting and Placing
Concrete Work
Lean concrete 1:3:6(1'') for Wall Foundation & Column
Footing
Column Footing including 10mm tor bar & F/W as per
details
Column Concreting including 4Nos 12mm tor bar &
F/W and plastering
Beam concreting including R/F details in drawing and
Formwork
4'' Slab concreting including R/F and Formwork
Lintel 6''*4'' including R/F and F/W
Arch Lintel 6''*4'' including R/F and F/W
3'' Floor concrete 1:21/2:5 including ramping on front
site
Page 1 of 14
QUANTITY
1.00
UNIT
Item
14.00 Cube
17.00 Cube
19.00 Cube
15.50 Sqrs
16.50 Sqrs
7.00
Sqrs
4.00
Nos
48.00
L.ft
25.00
L.ft
6.25
340.00
34.00
Sqrs
L.ft
L.ft
17.00
Sqrs
17.50
Sqrs
1.00
1.00
3.00
4.00
2.00
6.00
4.00
4.00
Nos
Nos
Nos
Nos
Nos
Nos
Nos
Nos
NO
E
DESCRIPTION
Roof Work
Roof frame work
ridge tiling
9'' Valance board
Upvc gutter
Down pipe
QUANTITY
Plasterer
DPC
Plinth Plaster
Tiling
Plastering internal
Plastering external
sofit plastering
3.50
2.25
19.50
48.50
15.50
12.50
Sqrs
Sqrs
Sqrs
Sqrs
Sqrs
Sqrs
15.50
48.50
12.50
Sqrs
Sqrs
Sqrs
1.00
1.00
1.00
1.00
2.00
1.00
No
No
No
No
No
Item
7.00
10.00
12.00
6.00
2.00
1.00
No
No
No
No
No
No
1.00
30.00
55.00
Item
L.ft
L.ft
Electrical work
Fan with wiring
Tube light
Bulb
5 amp
15 amp
Main
Sqrs
L.ft
L.ft
L.ft
L.ft
Plumbing
Commode with necessary pipe lines
Squatting pan with necessary pipe lines
Wash basin with necessary pipe lines
Sink with necessary pipe lines
bib tap and showers
Pipe lines connected to existing pit
21.00
110.00
172.00
172.00
96.00
Painting
External
Internal
Soffit
UNIT
Miscellaneous
work top and chimney
design work for Verandah
cement grill work for above verandah
Page 2 of 14
NO
DESCRIPTION
Construction of Boundary wall
Construction of water tank
Construction of soakage pit
Landscaping
Earth Works
Masonry Work
C
D
Concrete Work
Carpentry and Joiner
Roof Work
Plasterer
Painting
Plumbing
Electrical work
Miscellaneous
QUANTITY UNIT
200.00 L.ft
1.00 Item
1.00 Item
1.00 Item
Total
Discount
Grand total
Page 3 of 14
RATE
AMOUNT
5000.00
5000.00
1500.00
2400.00
21000.00
40800.00
66,800.00
21000.00
17500.00
15500.00
399000.00
271250.00
255750.00
926,000.00
8000.00
56000.00
5000.00
20000.00
650.00
31200.00
500.00
12500.00
55000.00
450.00
500.00
343750.00
153000.00
17000.00
9000.00
153000.00
786,450.00
22000.00
385000.00
36000.00
18500.00
21500.00
19500.00
10000.00
29500.00
26500.00
4000.00
36000.00
18500.00
64500.00
78000.00
20000.00
177000.00
106000.00
16000.00
901,000.00
Page 4 of 14
RATE
AMOUNT
29500.00
100.00
175.00
160.00
150.00
619500.00
11000.00
30100.00
27520.00
14400.00
702,520.00
5500.00
4500.00
26000.00
3500.00
3500.00
4200.00
19250.00
10125.00
507000.00
169750.00
54250.00
52500.00
812,875.00
2000.00
2000.00
2000.00
31000.00
97000.00
25000.00
153,000.00
10500.00
4000.00
5000.00
6000.00
3000.00
20000.00
10500.00
4000.00
5000.00
6000.00
6000.00
20000.00
51,500.00
6000.00
2500.00
1500.00
1750.00
2250.00
15000.00
42000.00
25000.00
18000.00
10500.00
4500.00
15000.00
115,000.00
30000.00
250.00
250.00
30000.00
7500.00
13750.00
Page 5 of 14
RATE
1550.00
250000.00
75000.00
50000.00
AMOUNT
310000.00
250000.00
75000.00
50000.00
736,250.00
66,800.00
926,000.00
786,450.00
901,000.00
702,520.00
812,875.00
153,000.00
51,500.00
115,000.00
736,250.00
5251395.00
1395.00
5,250,000.00
Page 6 of 14
Construction Programme
Se.no
Work
Site Mobilization
Earth Works
3
4
5
6
7
8
9
10
11
No.of workers
Skill , UnSkill
62
Masonry Work
156
274
Concrete Work
Carpentry and Joiner
32
84
188
112
49
58
185
180
70
30
14
14
22
22
130
260
846
1096
Roof Work
Plasterer
Painting
Plumbing
Electrical work
Miscellaneous
Total Workers
1st Month
2nd Month
3rd Month
4th Month
S 105, U 210
S 160, U 230
S 150, U 190
S 180, U 180
5th Month
6th Month
S 136, U 150
S 115, U 136
Item
Description
1
2
3
4
5
End of 1st
End of 2nd
End of 3rd
End of 4th
End of 5th
Month
Month
Month
Month
Month
12.50%
20.19%
25.00%
21.15%
14.42%
12.50%
32.69%
57.69%
78.85%
93.27%
650,000.00 1,050,000.00 1,300,000.00 1,100,000.00
750,000.00
650,000.00 1,700,000.00 3,000,000.00 4,100,000.00 4,850,000.00
585,000.00
945,000.00 1,210,000.00
585,000.00 1,530,000.00 2,740,000.00
50,000.00
10,000.00
10,000.00
50,000.00
25,000.00
10,000.00
200,000.00
30,000.00
50,000.00
20,000.00
50,000.00
200,000.00
30,000.00
75,000.00
100,000.00
30,000.00
40,000.00
20,000.00
200,000.00
300,000.00
400,000.00
150,000.00
25,000.00
20,000.00
30,000.00
50,000.00
150,000.00
155,000.00
155,000.00
370,000.00
805,000.00
720,000.00
275,000.00
525,000.00 1,330,000.00 2,050,000.00 2,325,000.00
115,500.00
73,500.00
126,500.00
104,500.00
99,000.00
82,500.00
d. Blacksmith
e. Plumber
f. Painter
g. Electrician
Total labour cost
Cumulative labour cost
Overheads
Interest
Total expences
Total Cumulative Expencess
189,000.00
126,500.00
104,500.00
99,000.00
82,500.00
189,000.00
315,500.00
420,000.00
519,000.00
601,500.00
80,000.00
75,000.00
60,000.00
60,000.00
60,000.00
20,000.00
20,000.00
20,000.00
20,000.00
20,000.00
444,000.00
591,500.00
989,500.00
899,000.00
437,500.00
444,000.00 1,035,500.00 2,025,000.00 2,924,000.00 3,361,500.00
60000001
2
3
4
5000000
5
6
9
4000000
18
444000
1035500
2025000
2924000
3361500
3591300
3591300
3591300
0
0
585000
1530000
2740000
3840000
4940000
5200000
3000000
2000000
1000000
0
0
10
12
14
16
1000000
0
0
10
12
14
16
End of 6th
End of 9th
End of 18th
Month
Month
Month
6.73%
100.00%
350,000.00
5,200,000.00
1,100,000.00 1,100,000.00
260,000.00
3,840,000.00 4,940,000.00 5,200,000.00
25,000.00
50,000.00
75,000.00
2,400,000.00
74,800.00
74,800.00
676,300.00
60,000.00
20,000.00
229,800.00
3,591,300.00 3,591,300.00 3,591,300.00
Colu
mn D
12
14
16
18
20
12
14
16
18
20