Professional Documents
Culture Documents
Engineering Report Heat Exhanger B
Engineering Report Heat Exhanger B
Engineering Report Heat Exhanger B
hot
water
system
was
composed
of
the
following
requirements;
Design Total Heat Capacity
Heat Capacity of hot water at the Guest Room
Detailed Calculation of Pipe Sizing to Guest Room
Required Capacity and Thickness of Hot Water Tank
Calculation of Heat loss of Tank and Pipe
Total flow rate and total dynamic head of secondary circulating
pump
Area of Heating Coil
Duct Sizing of Recovery Cold Air
3
wall
thickness
of
2.4mm,
2.1mm
and
1.6mm
coefficient free
copper
pipe
are
often
used
in
water
supply
System Control
Due to its recovery, the control will interface different system. It
will help the activation or sequence required during operation by
means of Building Management System.
Electric Motor
High Efficiency electric motor, Totally Enclosed Fan Cooled
(TEFC), IEC standard, IP 55 and class F insulation and NEMA 3R
controller for hot water circulating pump.
DESIGN CALCULATIONS
Design Total Heat Capacity
To determine the total required heat capacity of guest room, add
the heat load of water consumption of guest room, heat lost of
tank and heat lost of pipe by the following equation;
QH
QL + QLT + QLP
Where:
QH
QL
QLT
QLP
2.3.1.1
QL
Where:
7
Mhw
Cpw
Thw
Tcw
To determine the total heat capacity required for the guest room, get
the maximum load demand required in the guest room using 90%
occupancy of 172 guest room. The design average room occupancy is
2 person per unit (see Appendices for Architectural Layout Annex 1A-1D).
% Usage
0
0
0
0
0
360
900
4,680
1,440
360
360
180
0
0
180
360
360
720
1,080
4,680
1,080
720
540
0
0%
0%
0%
0%
0%
2%
5%
26%
8%
2%
2%
1%
0%
0%
1%
2%
2%
4%
6%
26%
6%
4%
3%
0%
18,000
100%
Based on Table 1.1 we can get the average hourly demand of Hot
Water System approximately 1,125 Liters/hr or 39.70 ft3/hr;
Mhw
Vx
9
Mhw
Mhw
2,477.28 lb/hr
QL
QL
124,854.91 Btu/hr
V/v
Where:
V
Pi, (3.1416)
For hot water header pipe @ peak load capacity of 165.40 ft 3/hr
or 0.046 ft3/s.
In Area;
10
V/v
In diameter;
(d2) / 4
sqrt (3.744 in2 x 4) /
2.2 inches
In Area;
V/v
In diameter;
(d2) / 4
1.6 in
11
In Area;
V/v
In diameter;
(d2) / 4
1.1 inches
The pipe sizes are 2.5 inches, 2 inches and 1- inches for header, sub
header and riser, respectively (See Appendices for schematic diagram of hot
water piping in Annex 2A-2B).
12
VT
V 1 + V 2 + V3
Where:
VT
V1
V2
Expansion Capacity
V3
V2 + V 3 =
20% (V1)
VT
V 1 + V 2 + V3
VT
V1 + 20% (V1)
VT
V1
V1
6,696 Liters
VT
V C + VE
Where:
13
VT
VC
Volume of Cylinder
VE
Volume of Ellipsoid
hT
dT
Diameter of Tank
VE
4/3 x x a x b x c
Where:
a
VE
4/3 x x a x b x c
VE
VE
21.72 ft3
For cylinder;
VC
VT - V E
VC
118.14 21.72
VC
96.42 ft3
14
VC
x r2 x h
96.42 / ( x 2.32)
5.8 ft
hT
c+h
hT
hT
7.8 ft
And the wall thickness of tank using 125 psi operating pressure and
4.6 ft or 55.2 inches diameter;
tm
(P x r x FS) / TS x E
Where:
tm
TS
FS
Efficiency 90%
tm
(P x r x FS) / TS x E
tm
tm
17,250 / 49,526.10
15
tm
0.348 in
QLT1 + QLT2
QLT1
QLT2
Where:
QLT
QLT1
QLT2
AT
Tin
Tout
ho
hi
16
QLT1
QLT1
(Tin x Tout) / R
R1
1 / Ai x h i
R1
R1
R1
For resistance of tank given the inside and outside diameter of tank
and the film coefficient;
R2
ln (Do / Di) / (2 x x L x K)
R2
R2
0.0065 / 947.51
R2
17
R3
ln (Do / Di) / (2 x x L x K)
R3
ln (4.77/4.6) / (2 x x 5.8 ft x
0.28/12 Btu-in/hr-ft2-F)
R3
0.036 / 0.85
R3
R4
ln (Do / Di) / (2 x x L x K)
R4
ln (4.7766/4.77) / (2 x x 5.8 ft x
1,400/12 Btu-in/hr-ft2-F)
R4
R4
0.0014 / 4,251.63
3.29 x 10-7 hr-F / Btu
R5
1 / Ao x h o
R5
R5
R5
R1 + R2 + R3 + R4 + R5
5.74 x 10-3
R
QLT1
(Tin x Tout) / R
QLS1
QLS1 =
862.5 Btu/hr
Compute the surface area of top and bottom of tank with the formula
of ellipsoidal;
SA
Where:
a
1.6075
SA
SA
SA
SA
SA
4 x x (21.9/3) 0.622
SA
43.27 ft2
19
L/K =
L/K =
L/K=
Given the surface area of top and bottom of tank and the summation
of L/K, substitute the values in the equation;
QLS2
QLS2
QLS2
QLS2
1,791.38 / 7.791
QLS2 =
229.93 Btu/hr
QLT
QLS1 + QLS2
QLT
QLT
1,092.43 Btu/hr
20
Since the selected number of hot water tank is two (2) the total
heat lost of tank has a total of 2,184.86 Btu/hr.
QLP
Where:
Tin
Tout
ho
hi
R1
1 / Ai x h i
21
R1
R1
R1
For resistance of copper pipe 2.64 inches given the inside and outside
diameter of pipe and the film coefficient;
R2
ln (Do / Di) / (2 x x L x K)
R2
ln (0.22/0.2125) / (2 x x 44 ft x
2,616/12 Btu-in / hr- ft2-F)
R2
0.035 / 60,268.45
R2
ln (Do / Di) / (2 x x L x K)
R3
ln (0.345/0.22) / (2 x x 44 ft x
0.27/12 Btu- in/hr-ft2-F)
R3
0.4499 / 6.22
R3
R4
ln (Do / Di) / (2 x x L x K)
R4
ln (0.352/0.345) / (2 x x 44 ft x
3/12 Btu-in/hr-ft2-F)
22
R4
0.02 / 69.12
R4
R5
1 / Ao x h o
R5
R5
R5
R1 + R2 + R3 + R4 + R5
QLP
QLP
R1
1 / Ai x h i
R1
R1
R1
For resistance of copper pipe 2.13 inches given the inside and outside
diameter of pipe and the film coefficient;
R2
ln (Do / Di) / (2 x x L x K)
R2
ln (0.18/0.17) / (2 x x 334 ft x
2,616/12 Btu-in / hr- ft2-F)
R2
0.057 / 457,492.36
R2
R3
ln (Do / Di) / (2 x x L x K)
R3
ln (0.26/0.18) / (2 x x 334 ft x
0.27/12 Btu- in/hr-ft2-F)
R3
0.37 / 47.22
R3
R4
ln (Do / Di) / (2 x x L x K)
R4
ln (0.267/0.26) / (2 x x 334 ft x
3/12 Btu-in/hr-ft2-F)
24
R4
0.027 / 524.65
R4
R5
1 / Ao x h o
R5
R5
R5
R1 + R2 + R3 + R4 + R5
QLP
QLP
R1
1 / Ai x h i
R1
R1
R1
For resistance of copper pipe 1.38 inches given the inside and outside
diameter of pipe and the film coefficient;
R2
ln (Do / Di) / (2 x x L x K)
R2
ln (0.155/0.115) / (2 x x 1,300 ft x
2,616/12 Btu-in / hr- ft2-F)
R2
0.298 / 1,780,658.88
R2
R3
ln (Do / Di) / (2 x x L x K)
R3
ln (0.235/0.155) / (2 x x 1,300 ft x
0.27/12 Btu- in/hr-ft2-F)
R3
0.42 / 183.78
R3
R4
ln (Do / Di) / (2 x x L x K)
R4
ln (0.242/0.235) / (2 x x 1,300 ft x
3/12 Btu-in/hr-ft2-F)
26
R4
0.029 / 2,042.04
R4
R5
1 / Ao x h o
R5
R5
R5
R1 + R2 + R3 + R4 + R5
QLP
QLP
R1
1 / Ai x h i
R1
R1
R1
For resistance of polypropylene pipe 0.87 inches given the inside and
outside diameter of pipe and the film coefficient;
R2
ln (Do / Di) / (2 x x L x K)
R2
ln (0.072/0.066) / (2 x x 4,500 ft x
0.69/12 Btu-in / hr- ft2-F)
R2
0.09 / 1,625.78
R2
R3
ln (Do / Di) / (2 x x L x K)
R3
ln (0.152/0.072) / (2 x x 4,500 ft x
0.27/12 Btu- in/hr-ft2-F)
R3
0.75 / 636.17
R3
R4
1 / Ao x h o
R4
R4
R4
R1 + R2 + R3 + R4
QLP
QLP
R1
1 / Ai x h i
R1
R1
R1
For resistance of copper pipe 2.13 inches given the inside and outside
diameter of pipe and the film coefficient;
R2
ln (Do / Di) / (2 x L x K)
R2
ln (0.18/0.17) / (2 x x 400 ft x
2,616/12 Btu-in / hr- ft2-F)
R2
0.057 / 547,895.04
R2
R3
ln (Do / Di) / (2 x L x K)
R3
ln (0.26/0.18) / (2 x x 400 ft x
0.27/12 Btu- in/hr-ft2-F)
R3
0.37 / 56.55
R3
R4
ln (Do / Di) / (2 x L x K)
R4
ln (0.267/0.26) / (2 x x 400 ft x
3/12 Btu-in/hr-ft2-F)
R4
0.027 / 628.32
R4
R5
1 / Ao x h o
R5
R5
R5
R1 + R2 + R3 + R4 + R5
1.49 x 10-3
R
QLP
QLP
QLP
QLP
QLP
QH
QL + QLT + QLP
QH
QH
178,919 Btu/hr
Say;
Total
180,000 Btu/hr,
Flow
Rate
and
Total
Dynamic
Head
of
Secondary
Circulating Pump
Total Volumetric Flow Rate
To get the total volumetric flow rate of secondary pump, 1 gal/min per
each riser for 1- inches or 1- inches pipe size are given in ASHRAE
1995 HVAC Application page 7. Based on architectural layout and pipe
chase, they have 23 risers;
31
VS
VS
23 x 1 gal/min
VS
Hf
Where:
Hf
Friction Coefficient
All data are given except for the value of friction coefficient but we can
now determine the value by the equation;
32
Where:
z
0.005
Compute the friction head given the effective total length of supply hot
water pipe to guest room pipe (see Appendices Annex 6).
Hf
f LV2 / d2g
Hf
Hf
1.04 / 13.52
Hf
0.08 ft
0.0053
Compute the friction head of supply hot water pipe to guest room,
given the effective total length of pipe (see Appendices Annex 6).
Hf
f LV2 / d2g
Hf
Hf
7.87 / 10.95
Hf
0.72 ft
0.0059
Compute the friction head of supply hot water pipe to guest room
given the effective total length of pipe (see Appendices Annex 6).
Hf
f LV2 / d2g
Hf
Hf
47.44 / 7.406
Hf
6.41 ft
34
Hf
f LV2 / d2g
Hf
Hf
35.01 / 10.95
Hf
3.20 ft
Hf
Hf
9.67 ft
To get the total dynamic head, given the summation of friction head
add the pressure required of fixture;
TDH =
TDH =
9.67 ft + 27.72 ft
TDH =
37.39 ft
35
Usage
Liter/h
%
Usage
Losses
Liter/h
Tank
Capacit
36
Hot
Water
Excess
Cap,Lite
5100
5100
5100
5100
5100
5100
5100
5100
5100
5100
Productio
n Liter/hr
0
0
0
0
2,108
2,108
2,108
2,108
2,108
2,108
4,557
4,236
3,914
3,593
2,108
3,535
4,421
1,528
1,874
3,301
321.4
5100
2,108
4,728
1%
321.4
5100
1,054
5,280
0%
321.4
5100
527
5,486
0%
321.4
5100
5,164
180
1%
321.4
5100
527
5,190
360
2%
321.4
5100
527
5,036
360
2%
321.4
5100
527
4,881
720
4%
321.4
5100
1,581
5,421
1,080
6%
321.4
5100
1,054
5,073
4,680
26%
321.4
5100
2,108
2,180
1,080
6%
321.4
5100
2,108
2,887
720
4%
321.4
5100
2,108
3,953
540
3%
321.4
5100
2,108
5,200
0%
321.4
5100
4,878
18,00
0
100%
day
y Liter
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:0
0
11:0
0
12:0
0
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
24:0
0
0
0
0
0
0
360
900
4,680
1,440
360
0%
0%
0%
0%
0%
2%
5%
26%
8%
2%
321.4
321.4
321.4
321.4
321.4
321.4
321.4
321.4
321.4
321.4
360
2%
180
28,985
In Table 1.2, we can say that the selected capacity is enough to the
requirements of the hotel. At peak load usage of hot water of guest
room, the hot water production of heat pump using 4 compressors
running has almost 10% excess capacity of peak load. Below is graph
of the simulation.
37
FIGURE 1.4
Figure 1.4 shows the line graph of hot water requirements of guest
room in blue line, the green line is the hot water production of selected
capacity of heat pump and red line is the excess capacity in normal
operation of heat pump a day.
Given the 300,967 Btu/hr, we can compute the area of coil inside the
tank by the equation;
QC
U x A x LMTD
QC
300,967 Btu/hr
Where:
QC
LMTD =
LMTD =
LMTD =
LMTD =
36 / 0.98
39
LMTD =
36.73
QC
U x A x LMTD
Since we have two tanks we can the divide the computed area into 2.
The area of copper of each tank is 5.44 m2.
Say; 6 m2, the commercial size tank meets the requirement of heat
pump production.
HP
VP x x H
Where:
VP
HP
Horsepower Required
HP
VP x x H
HP
HP
7,662.72 / 10,890
HP
0.70
41
This will be used for start/stop of the system during the operation to
gain the recovery system.
Additional ducting should be also included. This is to convey the air
discharge of heat pump. The sizes will be determined by the equation;
VAIR
Axv
Where:
VAIR
Area (ft2)
VAIR
/v
8.47 ft2
Width x Height
8.47 ft2 / 2 ft
4.24 ft
42
The required air flow for two units air handling unit for fresh air supply
of guest room is 2 x 8,000 ft3/min. The size of duct is;
VAIR
/v
6.4 ft2
Width x Height
6.4 ft2 / 2 ft
3.2 ft
VAIR
/v
2 ft2
Width x Height
2 ft2 / 1 ft
2 ft
43
VAIR
/v
6.47 ft2
Width x Height
6.47 ft2 / 2 ft
3.23 ft
tested.
pump
unit
should
consist
of
compressor,
controls
and
44
should
be
factory
assembled,
b.
c.
d.
available.
45
e.
f.
Scroll
type,
suitable
for
high
temperature
operation
g.
2.
3.
4.
h.
1.
power on
2.
Normal Stop
3.
4.
j.
Condenser
Coaxial
vented
double
wall
type.
2.
k.
46
m.
Controls The heat pump unit shall be factory wired for fully
automatic operation. Safeties shall include and fan motor
thermal overload protection, manual reset pressure stats, anticycling compressor relays, plus standard items recommended by
the equipment manufacturer.
Combination
of
Hot
Water
Storage
and
Heat
domestic
water
and
storage
tank
in
b.
47
c.
should
be
provided
with
gage
24
d.
e.
Basic Operation
The Hot Water System using heat pump is the primary hot
water supply of the hotel guest room. The system is 24
hours in operation depend on the load requirements of the
guest room. The heat pump has four (4) compressors
simultaneously running depend on the temperature setting
to make sure the hot water temperature will meet the
desired temperature requirements.
At peak load, it will run in four (4) compressors to sustain
the hot water storage and storage recovery. It means the
energy recovery will maximize also. The discharge air will
be supply to elevator machine room, electrical room and
serve as the fresh air of the guest room.
When the systems run in three (3) compressors, the
capacity of discharge is not enough to maintain the
required air requirements. One (1) air handling unit will
turn off and switch to normal mode of air conditioning
system (Chilled Water System) by means of Building
Management System. On the other hand, one (1) air
handling unit using recovery system, will give the exact
49
temperature
setting
meet
the
normal
air-
50
damper
from
elevator
room
will
goes
ECONOMIC ASPECTS
51
out
to
maintenance
cost
during
the
life
span
of
the
equipment.
Since the report is limited to the Design, Installation,
Operation and Maintenance of Hot Water System Using
Heat
Pump
including
Detailed
Calculation
of
Piping,
52
3
4
5
Description
Heat Pump, 1
operational 1 Back up
Including Primary
Pump and Installation
Controller relay of Air
Conditioning System
and Exhaust Fan
Secondary Circulating
Pump including
Controller
Wires and Contacts of
BMS
Ducting Works
including support and
miscellaneous work
Total Cost
Heat Pump
System
Heat Pump
System w/
Recovery
5,700,000
5,700,000
15,000
40,000
25,000
25,000
20,000
200,000
none
1,200,000
P5,760,000.00
P7,165,000.00
53
Fan
KW
0.00
0.00
0.00
0.00
1.30
1.30
1.30
1.30
1.30
PCP
KW
0
0
0
0
0.7
0.7
0.7
0.7
0.7
SCP
KW
0.55
0.55
0.55
0.55
0.55
0.55
0.55
0.55
0.55
WAC
, KW
3.75
3.75
3.75
3.75
3.75
3.75
3.75
3.75
3.75
EF,
KW
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
AHU,
KW
11.2
11.2
11.2
11.2
11.2
11.2
11.2
11.2
11.2
Total
KW
16.0
16.0
16.0
16.0
44.8
44.8
44.8
44.8
44.8
26.8
1.30
0.7
0.55
3.75
0.5
11.2
44.8
26.8
1.30
0.7
0.55
3.75
0.5
11.2
44.8
13.4
0.66
0.7
0.55
3.75
0.5
11.2
30.8
54
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
24:0
0
6.7
0.33
0.7
0.55
3.75
0.5
11.2
23.7
0.00
0.0
0.55
3.75
0.5
11.2
16.0
6.7
0.33
0.7
0.55
3.75
0.5
11.2
23.7
6.7
0.33
0.7
0.55
3.75
0.5
11.2
23.7
6.7
0.33
0.7
0.55
3.75
0.5
11.2
23.7
20.1
0.99
0.7
0.55
3.75
0.5
11.2
37.8
13.4
0.66
0.7
0.55
3.75
0.5
11.2
30.8
26.8
1.30
0.7
0.55
3.75
0.5
11.2
44.8
26.8
1.30
0.7
0.55
3.75
0.5
11.2
44.8
26.8
1.30
0.7
0.55
3.75
0.5
11.2
44.8
26.8
1.30
0.7
0.55
3.75
0.5
11.2
44.8
0.00
0.0
0.55
3.75
1.5
11.2
17.0
Total KW/Day:
783.9
With the total capacity of 783.9 KW-Day as reference for the annual
operating cost;
783.9 KW/Day
286,123.50 KW/year
55
Based
HEAT PUMP
Comp
kW
Fan
KW
Fan
CFM
AHU1 AHU2
8,000 8,000
CFM
CFM
0
0.00
0
stop
0
0.00
0
stop
0
0.00
0
stop
0
0.00
0
stop
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
13.4 0.66 10,586 start
6.7
0.33 5,293
stop
0
0.00
0
stop
6.7
0.33 5,293
stop
6.7
0.33 5,293
stop
6.7
0.33 5,293
stop
20.1 0.99 15,879 start
13.4 0.66 10,879 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.8 1.30 21,172 start
26.7 1.30 21,172 start
0
0.00
0
stop
on tabulation of building
AC
550
CFM
stop
stop
stop
stop
stop
stop
stop
stop
start
start
start
start
start
start
start
start
start
start
start
start
start
start
stop
start
stop
start
stop
stop
stop
start
stop
start
stop
start
stop
start
stop
start
start
start
start
start
start
start
start
start
stop
stop
management
EXCESS
CFM OF
HEAT
PUMP
stop
0
stop
0
stop
0
stop
0
start
4,332
start
4,332
start
4,332
start
4,332
start
4,332
start
4,332
start
4,332
start
1,736
start
4,443
stop
0
start
4,443
start
4,443
start
4,443
start
7,029
start
1,736
start
4,332
start
4,332
start
4,332
start
4,332
stop
0
sequence, the
EF
300
CFM
Fan
KW
0
0
0
0
26.8
0.00
0.00
0.00
0.00
1.30
PC
P
KW
0
0
0
0
0.7
SCP
KW
WAC
kW
EF,
kW
0.55
0.55
0.55
0.55
0.55
3.75
3.75
3.75
3.75
0.00
0.5
0.5
0.5
0.5
0.0
56
5.6
5.6
5.6
5.6
0.0
16.0
16.0
16.0
16.0
29.4
6:00
7:00
8:00
9:00
10:0
0
11:0
0
12:0
0
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
24:0
0
26.8
26.8
26.8
26.8
26.8
1.30
1.30
1.30
1.30
1.30
0.7
0.7
0.7
0.7
0.7
0.55
0.55
0.55
0.55
0.55
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
29.4
29.4
29.4
29.4
29.4
26.8
1.30
0.7
0.55
0.00
0.0
0.0
0.0
29.4
13.4
0.66
0.7
0.55
0.00
0.0
0.0
5.6
20.9
6.7
0.33
0.7
0.55
0.00
0.0
5.6
5.6
19.5
0.00
0.0
0.55
3.75
0.5
5.6
5.6
16.0
6.7
0.33
0.7
0.55
0.00
0.0
5.6
5.6
19.5
6.7
0.33
0.7
0.55
0.00
0.0
5.6
5.6
19.5
6.7
0.33
0.7
0.55
0.00
0.0
5.6
5.6
19.5
20.1
0.99
0.7
0.55
0.00
0.0
0.0
5.6
27.9
13.4
0.66
0.7
0.55
0.00
0.0
0.0
5.6
20.9
26.8
1.30
0.7
0.55
0.00
0.0
0.0
0.0
29.3
26.8
1.30
0.7
0.55
0.00
0.0
0.0
0.0
29.3
26.8
1.30
0.7
0.55
0.00
0.0
0.0
0.0
29.3
26.8
1.30
0.7
0.55
0.00
0.0
0.0
0.0
29.3
0.00
0.0
0.55
3.75
0.5
5.6
5.6
16.0
Total KW/Day:
566.7
With the total capacity of 566.7 KW/Day as reference for the annual
operating cost;
566.17 KW/Day
206,845.5 KW/year
FIGURE 1.5
Figure 1.5 shows the comparison of power consumption of heat pump
system using recovery system in red hidden line is lower than the blue
line heat pump without recovery.
meet
the
required
temperature
the
heat
pump
will
engineer
should
properly
study
the
basic
CONCLUSION
Heat pump system is one of the neglected areas in the
project, owner does not want to invest additional cost for
recovery system so much in hot water system, but if we
realize the impact of energy recovery in operation, we can
say that it is very efficient.
Not because of the development in the hot water system
which is the heat pump recovery, the project owner can
now realize that even we spend additional cost in the
operation
requirements
an
additional
saving
and
or
to
minimize
60
the
environmental
concern
REFERENCES
THE PHILIPPINE MECHANICAL CODE
THE PSME CODE
AND
STANDARDS COMMITTEE
OF
HEATING, REFRIGERATION
AND
AIR-CONDITIONING
ENGINEER , INC.
1791 TULLIE CIRCLE , N.E., ATLANTA, GA 30329
OF
HEATING, REFRIGERATION
AND
ENGINEER , INC.
1791 TULLIE CIRCLE , N.E., ATLANTA, GA 30329
61
AIR-CONDITIONING
OF
HEATING, REFRIGERATION
AND
AIR-CONDITIONING
ENGINEER , INC.
1791 TULLIE CIRCLE , N.E., ATLANTA, GA 30329
ASHRAE EQUIPMENTS
AMERICAN SOCIETY
OF
AND
SYSTEMS
HEATING, REFRIGERATION
AND
ENGINEER , INC.
1791 TULLIE CIRCLE , N.E., ATLANTA, GA 30329
THE THEORY
AND
PRACTICE
OF
STATIONARY
THERMODYNAMICS
VIRGIL MORNING FAIRES
CLIFFORD MAX SIMMANG
CORPORATE FINANCE
BREADLEY / MYERS / ALLEN
62
AIR-CONDITIONING