Download as pdf or txt
Download as pdf or txt
You are on page 1of 73

Design Consultancy for Upgradation of NH 47 Final Detailed Project Report

From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report


NH 47B From Nagercoil to Kavalkinaru Package - I

LIST OF CONTENTS

1.0 EXECUTIVE SUMMARY ....................................................................................................1


1.1 Project Background.............................................................................................................1
1.2 Socio-Economic Profile.......................................................................................................2
1.3 Alignment and Engineering ................................................................................................3
1.4 Geometrics ..........................................................................................................................3
1.5 Drainage..............................................................................................................................3
1.6 Cross Drainage Structures .................................................................................................3
1.7 Pavement Design................................................................................................................4
1.8 At-Grade and Grade Separated Intersections....................................................................5
1.9 Project Facilities ..................................................................................................................5
1.10 Cost Estimates ....................................................................................................................5
1.11 Economic Analysis ..............................................................................................................5
1.12 Financial Analysis for BOT Project .....................................................................................6
2.0 PROJECT BACKGROUND ...............................................................................................6
2.1 Introduction .........................................................................................................................6
2.2 Slope protection by RE wall and Soil Nailing: ....................................................................7
2.3 Demography........................................................................................................................8
2.3.1 Kerala State Profile .........................................................................................................8
2.3.2 Density Pattern ...............................................................................................................8
2.3.3 Human Settlements ........................................................................................................9
2.3.4 Occupational Structure ...................................................................................................9
2.3.5 Religious Composition ....................................................................................................9
2.3.6 Linguistic and Socio – Cultural Characteristics ..............................................................9
2.3.7 Some other Demographic Characteristics .....................................................................9
2.4 Agriculture ...........................................................................................................................9
2.5 Land Use ...........................................................................................................................10
2.5.1 Irrigation ........................................................................................................................10
2.5.2 Fertilizer Consumption ..................................................................................................11
2.5.3 Livestock .......................................................................................................................11
2.6 Forests ..............................................................................................................................11
2.7 Industries ...........................................................................................................................11
2.8 Infrastructure – Transport .................................................................................................12
2.8.1 An Overview ..................................................................................................................12
2.8.2 Roads ............................................................................................................................12
2.8.3 Air Transport .................................................................................................................13
2.8.4 Water Transport ............................................................................................................13
2.8.5 Rail Transport ...............................................................................................................13
2.8.6 Tourism .........................................................................................................................13
2.9 Project Influence Area, District Thiruvananthapuram ......................................................14
2.9.1 Area & Climate ..............................................................................................................14
2.9.2 Socio – Demographic Characteristics ..........................................................................14
2.9.3 Livestock and Poultry ....................................................................................................15
2.9.4 Transport Vehicles ........................................................................................................15
2.9.5 Social Aspects ..............................................................................................................15
2.10 State Economy..................................................................................................................15
2.10.1 Growth of State Domestic Product ...............................................................................15

SECON i NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

3.0 SUMMARY OF SURVEY AND INVESTIGATIONS ........................................................17


3.1 Topographical and Cadastral Surveys .............................................................................17
3.1.1 Topographical Survey ...................................................................................................17
3.1.2 Methodology for Topographical Survey........................................................................18
3.2 Cadastral Survey ..............................................................................................................19
3.3 Investigation Data .............................................................................................................19
3.3.1 Inventory for Structures ................................................................................................19
3.3.2 Benkelman Beam Deflection Survey ............................................................................19
3.3.3 Bump Integrator Test ....................................................................................................19
3.3.4 Existing Soil Strata upto 2m below Ground Level ........................................................19
3.3.5 Borelog details ..............................................................................................................19
4.0 TRAFFIC STUDY AND ANALYSIS .................................................................................20
4.1 Traffic Surveys ..................................................................................................................20
4.1.1 General .........................................................................................................................20
4.1.2 Motorised Traffic ...........................................................................................................20
4.1.3 Non-Motorised Traffic ...................................................................................................21
4.2 Traffic surveys on NH-47 ..................................................................................................21
4.2.1 Classified Traffic Volume Counts .................................................................................21
4.2.2 Classified Turning Movement Surveys .........................................................................21
4.2.3 O-D Survey and Commodity Movement Survey ..........................................................21
4.2.4 Axle Load Surveys ........................................................................................................22
4.2.5 Pedestrian / Cattle Surveys ..........................................................................................22
4.2.6 Speed and Delay (Travel Time) Surveys .....................................................................22
4.2.7 Willingness to Pay Surveys ..........................................................................................22
4.3 Traffic Analysis ..................................................................................................................22
4.3.1 Historical Traffic Data ...................................................................................................22
4.3.2 Seasonal Variation ........................................................................................................23
4.3.3 Present Traffic Conditions ............................................................................................23
4.3.4 Traffic Flow along the Project Road .............................................................................23
4.3.5 Travel Pattern ...............................................................................................................25
4.3.6 Axle Load Spectrum .....................................................................................................26
4.3.7 Turning Movement Survey............................................................................................26
4.3.8 Travel Time Analysis ....................................................................................................26
4.3.9 Willingness to Pay (WTP) Toll ......................................................................................27
4.3.10 Accident Studies for NH-47 Section .............................................................................27
4.4 Traffic Projections for NH-47 ............................................................................................27
4.4.1 Economic Profile - Project Influence Area ....................................................................27
4.4.2 Kerala ............................................................................................................................27
4.4.3 Tamil Nadu ....................................................................................................................29
4.5 Economic Forecasts .........................................................................................................29
4.5.1 Elasticity of Traffic Demand ..........................................................................................30
4.5.2 Economic Growth Rate .................................................................................................30
4.5.3 Traffic Growth Rates .....................................................................................................30
4.5.4 Traffic Forecast .............................................................................................................31
4.5.5 Traffic Forecast for Intersection ....................................................................................32
5.0 ALIGNMENT AND ENGINEERING .................................................................................32
5.1 Project Description ............................................................................................................32
5.1.1 General .........................................................................................................................32
5.1.2 Location and Terrain Conditions...................................................................................32
5.2 Proposed Alignment .........................................................................................................33

SECON ii NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

5.2.1 Proposed Alignment for existing Thiruvananthapuram Bypass (km 0.000 to km 22.600)
33
5.2.2 Proposed Alignment for beyond existing Thiruvananthapuram Bypass (km 22.600 to
km 43.000) ....................................................................................................................................33
5.3 Geometrics ........................................................................................................................34
5.4 Structure Design ...............................................................................................................34
5.5 Design Parameters ...........................................................................................................35
5.5.1 Design Standards .........................................................................................................35
5.5.2 Design Loads ................................................................................................................35
5.5.3 Materials ........................................................................................................................36
5.5.4 Bearing ..........................................................................................................................36
5.5.5 Expansion Joints ...........................................................................................................36
5.5.6 Wearing Coat ................................................................................................................36
5.5.7 Approach .......................................................................................................................37
5.5.8 Structure........................................................................................................................37
5.6 Proposed Structures .........................................................................................................37
6.0 SUBGRADE INVESTIGATION FOR PAVEMENT ..........................................................42
6.1 General .............................................................................................................................42
6.2 Test Pitting ........................................................................................................................42
6.3 Additional tests ..................................................................................................................42
6.4 Laboratory testing programme .........................................................................................42
6.5 Planning and Implementation of Test Programme...........................................................42
6.6 Implications for pavement designs ...................................................................................43
7.0 ENVIRONMENTAL IMPACT ASSESSMENT AND MANAGEMENT PLAN..................43
7.1 Project Area ......................................................................................................................43
7.2 Objectives .........................................................................................................................43
7.3 Major Negative Impacts and their Mitigation ....................................................................43
7.4 Significant Findings ...........................................................................................................44
7.5 Cost of Environmental Management Plan ........................................................................45
8.0 RESETTLEMENT ACTION PLAN ...................................................................................45
8.1 Description of Project........................................................................................................45
8.2 Objectives .........................................................................................................................46
8.3 Socio Economic and Census Surveys .............................................................................46
8.4 Project Affected Persons (PAPs)......................................................................................46
8.5 Category of Project Affected Families ..............................................................................47
8.6 Affected Structures By type ..............................................................................................47
8.7 Loss of Land (Private and Government) ..........................................................................47
8.8 Community Infrastructure and Assets ..............................................................................48
8.9 Resettlement Principles ....................................................................................................48
8.10 Consultation and Disclosures ...........................................................................................48
8.11 Institutional Mechanism and Grievance Redressal ..........................................................49
8.12 Total Cost of Rehabilitation and Resettlement .................................................................49
8.13 Monitoring and Evaluation ................................................................................................49
9.0 COST ESTIMATES ..........................................................................................................50
9.1 Project Road Packages ....................................................................................................50
9.2 Unit Rate Analysis.............................................................................................................50

SECON iii NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

9.3 Materials ............................................................................................................................50


9.3.1 Stone Metals .................................................................................................................50
9.3.2 Sand ..............................................................................................................................50
9.3.3 Gravel ............................................................................................................................50
9.3.4 Earth Works ..................................................................................................................50
9.3.5 Cement ..........................................................................................................................51
9.3.6 Steel ..............................................................................................................................51
9.3.7 Bitumen .........................................................................................................................51
9.3.8 Labour ...........................................................................................................................51
9.3.9 User charges for machineries.......................................................................................51
9.3.10 Rates for RE Wall and Soil Nailing ...............................................................................51
9.3.11 Unit Rate Analysis.........................................................................................................51
9.4 Unit Cost ...........................................................................................................................51
9.4.1 Estimation of quantities for Road work .........................................................................51
9.4.2 Estimation of Quantities for Structures .........................................................................52
9.4.3 Junction Improvements.................................................................................................52
9.4.4 Miscellaneous Provisions .............................................................................................53
9.4.5 Land Acquisition and Compensation for Structures .....................................................53
9.4.6 Contingencies ...............................................................................................................53
9.4.7 Construction Supervision ..............................................................................................54
9.4.8 Landscaping ..................................................................................................................54
9.5 Project Cost for Package I ................................................................................................54
10.0 ECONOMIC ANALYSIS ...................................................................................................54
10.1 Introduction .......................................................................................................................54
10.2 Evaluation Framework ......................................................................................................54
10.3 The Project ........................................................................................................................55
10.4 Traffic Growth Scenarios ..................................................................................................56
10.5 Economic Cost ..................................................................................................................56
10.6 Economic Benefits ............................................................................................................57
10.6.1 Estimation of Vehicle Operating Cost...........................................................................57
10.6.2 Savings in Value of Time ..............................................................................................58
10.7 Results of Economic Evaluation .......................................................................................58
10.8 Conclusion ........................................................................................................................58
11.0 BOT Analysis ...................................................................................................................59
11.1 Preface ..............................................................................................................................59
11.2 Project Cost.......................................................................................................................59
11.2.1 Civil Construction Cost .................................................................................................59
11.2.2 Interest during Construction (IDC) ................................................................................60
11.2.3 Contingencies ...............................................................................................................60
11.2.4 Independent Consultant and Preoperative expenses ..................................................60
11.3 Toll Rates ..........................................................................................................................60
11.3.1 New Toll Policy .............................................................................................................60
11.4 Traffic ................................................................................................................................61
11.4.1 Traffic Growth rates ......................................................................................................61
11.5 Toll Revenue .....................................................................................................................61
11.6 Tax ....................................................................................................................................62
11.7 Sources of Finance ...........................................................................................................62
11.8 Expenses ..........................................................................................................................62

SECON iv NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

11.8.1 Expenses during Construction Period ..........................................................................62


11.8.2 Expenses during Operation and Maintenance Period .................................................62
11.9 Viability Criteria .................................................................................................................63
11.9.1 BOT with and without NHAI grant.................................................................................63
11.9.2 BOT Annuity ..................................................................................................................64
11.10 Results of Financial Analysis ............................................................................................64
12.0 CONCLUSIONS AND RECOMMENDATIONS ...............................................................64
12.1 General .............................................................................................................................64
12.2 Existing Road Conditions..................................................................................................64
12.3 Proposed Alignment .........................................................................................................64
12.4 Typical Cross Sections .....................................................................................................65
12.5 Proposed Structures .........................................................................................................65
12.6 Pavement Design..............................................................................................................65
12.7 Cost Estimate ....................................................................................................................66
12.8 Economic Analysis ............................................................................................................66

SECON v NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

LIST OF TABLES

Table 1.1: Details of the Construction Packages ...........................................................................1


Table 1.2: List of cross drainage structures ...................................................................................4
Table 1.3(a): Pavement Layer Thickness for Main Carriageway...................................................4
Table 1.3(b): Overlay Pavement Layer Thickness for Main Carriageway (Existing Road) ...........4
Table 1.4: Pavement Layer Thickness for Service Road...............................................................4
Table 1.5: List of At-Grade and Grade Separated Intersections ...................................................5
Table 1.6: Summary of Economic Viability Analysis ......................................................................5
Table 1.7: Summary of Financial Analysis .....................................................................................6
Table 2.1: Widths of Cross Sectional Elements .............................................................................7
Table 2.2: Availability of space based on the CS Type .................................................................7
Table 2.3: Growth of Population, Kerala and India: 1971-2001 (in Millions) .................................8
Table 2.4: Growth Rate of Urban Population in Kerala, 1981-1991 ..............................................8
Table 2.5: Livestock and Poultry Population ................................................................................11
Table 2.6: Growth of working factories and employment.............................................................11
Table 2.7: National Highways in the State ...................................................................................12
Table 2.8: Growth of Registered Motor Vehicles in the State of Kerala ......................................13
Table 2.9: Demographic Details of Thiruvananthapuram District (2001 Census) .......................14
Table 2.10: Livestock and Poultry population (1996 Census) .....................................................15
Table 2.11: Motor Vehicles on Road in Thiruvananthapuram (1999-2000) ................................15
Table 2.12: State Income (NSDP) of Kerala by Industrial Origin (At constant Prices)................15
Table 2.13: State Income (NSDP) of Kerala by Industrial Origin (At Current Prices) .................16
Table 4.1: Traffic Volume Count Location ....................................................................................21
Table 4.2: Turning Movement Traffic Volume Count Locations ..................................................21
Table 4.3: Origin-Destination Survey Locations ...........................................................................21
Table 4.4: Willingness to Pay Survey Locations ..........................................................................22
Table 4.5: Vehicle registration data for Thiruvananthapuram District .........................................22
Table 4.6: PCU Values Adopted...................................................................................................23
Table 4.7: Present Traffic Count Result .......................................................................................24
Table 4.8: Average Compositions of Vehicles at each Location .................................................25
Table 4.9: Directional Split ............................................................................................................25
Table 4.10: VDF for Different Category of Vehicles .....................................................................26
Table 4.11: Present Peak Hour Traffic Flow ................................................................................26
Table 4.12: Accident Data for ThiruvananthapuramDistrict for NH-47 Section ...........................27
Table 4.13: Growth of Population, Kerala and India: 1971-2001 (in Millions) .............................27
Table 4.14: Growth Rate of Urban Population in Kerala, 1981-1991 ..........................................28
Table 4.15: Growths in NSDP and Per Capita Income in Kerala State .......................................28
Table 4.16: Growths in NSDP and Per Capita Income in Tamil Nadu State ...............................29
Table 4.17: Elasticity values .........................................................................................................30
Table 4.18 (a): Estimated traffic growth rates for Low Scenario ..................................................30
Table 4.18 (b): Estimated traffic growth rates for Medium Scenario ...........................................31
Table 4.18 (c): Estimated traffic growth rates for High Scenario .................................................31
Table 4.19: Future Projected Volume for existing Road Based on Medium Growth rates .........31
Table 4.20: Projected Volume for existing Road Based on 5% growth .......................................31
Table 4.21: Projected Traffic at Intersections by Medium Growth Rates ....................................32
Table 5.1: Proposed Road Widening Schedule ..........................................................................34
Table 5.2: List of Major Bridges ....................................................................................................37
Table 5.3: List of Minor Bridges ....................................................................................................37
Table 5.4: List of Box Culverts Proposed for Improvement or New Construction .......................37
Table 5.5: List of Pipe Culverts Proposed for Improvement or New Construction ......................38
Table 5.6: Details of Underpasses/Overpasses ...........................................................................41
Table 5.7: Details of Proposed ROB ............................................................................................42
Table 7.1: Negative Impacts and their Mitigation Measures ........................................................43
Table 7.2: ‘Hot Spots’ identified during Environmental / Social Screening Analysis ...................44
Table 8.1: PAFs & PAPs in Terms of Project Impact ..................................................................47

SECON vi NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Table 8.2: Category of PAFs in Terms of Project Impacts...........................................................47


Table 8.3: Details of Structures ....................................................................................................47
Table 8.4: Land Acquisition within Project ROW .........................................................................48
Table 8.5: Details of Community Structures, Assets and Religious structures ...........................48
Table 8.6: Total Costs of Rehabilitation and Resettlement..........................................................49
Table 9.1: Details of Packages .....................................................................................................50
Table 9.2: Pavement Layer Thickness for Main Carriageway .....................................................52
Table 9.3: Pavement Layer Thickness for Service Road.............................................................52
Table 9.4: Cost for Land Acquisition and Structure .....................................................................53
Table 10.1: Details of Package-I ..................................................................................................55
Table 10.2: Base Year Traffic Volume considered for Economic Evaluation ..............................56
Table 10.3: Traffic Growth Rates..................................................................................................56
Table 10.4: Results of Economic Viability Analysis for Package-I...............................................58
Table 11.1: Package Details .........................................................................................................59
Table 11.2: Construction Cost for Package-I ...............................................................................59
Table 11.5: Toll Rates ...................................................................................................................60
Table 11.6: Projected Toll Rates ..................................................................................................61
Table 11.7: Base Year Traffic for the Package-I : Tollable Traffic ...............................................61
Table 11.8: Toll Plaza Expenses ..................................................................................................63
Table 11.9: Maintenance Cost in Rs Million per Km ....................................................................63
Table 11.10: Details of Viability Criteria .......................................................................................63
Table 11.11: Summary of Financial Analysis ...............................................................................64
Table 12.1: Widths of Cross Sectional Elements .........................................................................65
Table 12.2: List of Structures Proposed for Package I ................................................................65
Table 12.3: Pavement Layer Thickness for Main Carriageway ...................................................66
Table 12.4: Pavement Layer Thickness for Service Road...........................................................66

SECON vii NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

1.0 EXECUTIVE SUMMARY


1.1 Project Background
The existing NH 47 from Thiruvananthapuram to Kanyakumari is 2-Lane carriageway
and presently the traffic on this road is much more than the capacity. Most of the road
length has continuous built-up area very close to the road. The existing NH 47B from
Nagercoil to Kavalkinaru is also 2-Lane carriageway. Geometrics of both the road
sections are not up to the standards as per IRC for National Highways.

In order to decongest the existing NH 47 within Thiruvananthapuram city, bypass for a


length of 22.6km has already been constructed. Beyond the city limits, widening of the
existing NH was investigated in detail, but ruled out due to large scale demolition
involved. Hence, it was decided to adopt a new alignment for about 95% of road length
except existing Thiruvananthapuram Bypass.

The project road starts at Kazhakkottam, about 10 km North of Thiruvananthapuram city,


on existing NH 47 (km 552/00) which is reckoned as km 00/000 for the project. The road
further continues on the existing Thiruvananthapuram Bypass up to km 22/600 and
traverses through cross country crossing Kerala/Tamilnadu Border at Karode village at
design Chainage of km 43/000. It is aligned cross country in Tamilnadu state and rejoins
the existing NH 47 at km 626/187 (existing chainage) and again deviates at 627/000
(existing chainage) bypassing Chungankadai, Nagercoil and Suchindram rejoining the
existing NH 47 at km 642/800. From km 642/800 it follows the existing road up to km
646/238 and deviates on RHS for bypassing Kottaram built-up area and joins NH 7 at
Kanyakumari Bypass (km 231/653 of NH7).

NH 47B from Nagercoil to Kavalkinaru where it joins NH 7 has been provided with a new
alignment except for an initial length of 600m. It starts near the junction of Nagercoil
Bypass (km 82/181 of NH 47) and existing NH 47B.

M/s. SECON Pvt. Ltd has been entrusted for preparation of Detailed Project Report for
both stretches as a combined project.

The above mentioned project road has been divided into two construction packages
based on the state boundaries. The details of the packages are given in Table 1.1
below.

Table 1.1: Details of the Construction Packages


Sl. Length
Package Chainage Remarks
No (km)
Package I Includes existing
km 0/000 to Km 43/000 of NH 47 Thiruvananthapuram Bypass
1. 43.00
(Kazhakkoottam to (length 22.60 km) from
Kerala/Tamilnadu Border) Kazhakkoottam to Kovalam
Package II
(km 43/000 to km 96/714 of NH 47,
from Kerala/Tamilnadu Border to Includes existing NH 47
2. 70.36
Kanyakumari )and km 0/000 to km 4.013km and NH 47B 0.60km
16/376 of NH 47B from Nagercoil to
Kavalkinaru)
Total Length 113.36

Present Report is pertaining to the Package I i.e. from Kazhakkoottam (North of


Thiruvananthapuram) to Karode (Kerala/Tamilnadu Border) of NH 47.

SECON 1 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

The scope of the project is to conduct feasibility study and preparation of Detailed
Project Report for 4/6 laning of NH 47 and NH 47B.

The Study has been planned under the following stages:

Stage 1: Preparation of Inception Report


Stage 2: Preparation of Feasibility Study Report
Stage 3: Preparation of Preliminary Project Report
Stage 4: Preparation of Detailed Project Report

Based on the various stages planned, the following stages have been completed.

Stage 1: The Quality Assurance Plan (QAP) was submitted on 20th June, 2004 and
Inception Report was submitted on 24th July, 2004. The revised QAP was submitted on
24th August, 2004.

Stage 2: Draft Feasibility Study Report for NH-47 was submitted on 20th December,
2004 and for NH-47B on 18th Jan, 2005. The Final Feasibility Study Report was
submitted on 11th April, 2005.

Stage 3: Draft Preliminary Project Report was submitted on 20th July, 2005. Final
Preliminary Project Report was submitted on 16th August, 2005.

Stage 4: The Draft Detailed Project Report for Package I was submitted on 23rd Sept,
2005 and for Package II on 30th Nov, 2005.

The present submission comprises of Final Detailed Project Report for Package I.

(Note: All the chainages mentioned hereafter in the report refer to Design project
chainages, unless otherwise mentioned.)

1.2 Socio-Economic Profile


The entire section of the project road passes through Thiruvananthapuram District in
Kerala.

The present project of 4/6 laning of existing 2 lane NH 47 from Thiruvananthapuram to


Kanyakumari is intended to improve the social and economic welfare of the people.
Thiruvananthapuram, the state capital is situated in the Southern part of Kerala. The
District is bound by Kollam in the North, Tirunelveli in the East, Kanyakumari in the
South and the Arabian Sea in the West. The District stretches along the shores of
Arabian Sea for a distance of 78km having an area of 2192sqkm. It has got a population
of 3,234,707. The area gets comparatively good rainfall and soil is gravelly. The main
occupation of the people is agriculture. Rubber, Coconut, Cashew and Paddy are
produced. The world famous Kovalam beach is in Thiruvananthapuram located close to
the alignment.

The project corridor has mixed rural and urban population. Major settlements that come
in these sections are Kazhakuttam, Chakka, Inchakkal, Kovalam, Mukkola, Puthenkada,
Thirupuram and Ayira (Parassala). General impact of this project is that it will affect
shops, houses, schools and agricultural land, which are coming in the ROW. But it will
not affect any historical monuments and forest land. The above issues can be sorted out
by mitigative measures and co-operation of Project Affected Persons (PAPs).

SECON 2 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

1.3 Alignment and Engineering


Under the present proposal for four/six laning, the existing Thiruvananthapuram bypass
has been utilized from km 0/000 to km 22/600, which will be widened from two lane to
four lane width. Thereafter the proposed bypass alignment will be followed upto Ayira
village near Kerala / Tamilnadu border and further a cross-country alignment bypassing
the built up areas of existing highway is adopted. The new alignment utilizes the existing
road partially and connects NH 47 with NH7 at two points viz. Kanyakumari and
Kavalkinaru with bifurcation near Nagercoil.

Thiruvananthapuram to Kerala-Tamil Nadu border stretch of NH 47 under Package I,


starts from Kazhakkoottam junction at km 552/000 of the existing highway, which is also
the take off point of Thiruvananthapuram bypass, and hence referred to as km 0/000 of
the new alignment. The proposal envisages widening of the existing 2-lane bypass to
four lane from km 0/000 to km 22/600. Thereafter the original bypass alignment
proposed by Kerala PWD (NH) is followed upto Ayira village (km 40/343). Further it
deviates from the PWD alignment for a short length and crosses Kerala Border at km
43/000. Under the proposal, the existing bypass is to be widened to four lane with
central median of 4.5m, hard shoulders of 1.5m and earthen shoulders of 1.5m.

Though the terrain is termed as rolling, most of the alignment passes through hillocks
and deep valleys especially in the cross – country portion from km 22/600 to km 43.000.
However, ruling gradients as applicable to plain and rolling terrain is provided in the
design of vertical alignment.

The existing ROW of Thiruvananthapuram bypass upto Kovalam (km 22/600) is 45m.
Further land has been acquired for the proposed bypass alignment from km 22/600 to
km 25/880 (Mukkola) for a width of 45m. Due to problems involved in acquisition and
high cost of land it is proposed to restrict the ROW to 45m in Kerala region.

1.4 Geometrics
It is observed that the existing Thiruvananthapuram bypass from km 0/000 to km 22/600
predominantly has a straight alignment and traverses through rolling terrain. The
horizontal curves in general conform to acceptable geometric standards in terms of
radius and sight distance. Super elevation/camber need to be improved in some
stretches. Beyond km 22.600 upto Kerala border, the proposal involves new
construction of four-lane highway. Design speed of 100kmph is considered for
geometric designs. Minimum radius of horizontal curves provided is 400m. Maximum
super elevation of 7% and maximum gradient of 3.3% is provided.

1.5 Drainage
Many stretches of the road are not provided with proper camber to allow free drainage
of surface water. Drainage system, where they exist are also not found in operational
condition at several places. Adequate provision for drainage of surface water is made
by providing proper roadside drains with required longitudinal slope.

1.6 Cross Drainage Structures


Condition of the structures, where they are being utilized for widening, and requirement
of new cross drainage structures have been carefully studied. Suitable proposals have
been made according to the site conditions. The details of proposed cross drainage
structures are given in Table 1.2 below.

SECON 3 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Table 1.2: List of cross drainage structures


Sl. Type of Existing Structures to be New Structures
No. Structures Widened or Reconstructed proposed
1 Major Bridges 2 2
2 Minor Bridges 3 12
3 Box Culverts 2 25
4 Pipe Culverts 68 33

1.7 Pavement Design


Main Carriageway
For the proposed alignment, a flexible pavement has been proposed for entire section
based on the commercial vehicles on the road section.

Average Commercial Vehicles per day = 1478CVPD


Expected Traffic on New Alignment = 65% of CVPD
Design Period = 15 years.
Sub-Grade CBR = 8%.
Vehicle Damage Factor = 4.5
Lane Distribution Factor = 0.75
Traffic Movement in each direction = 50%
Traffic Growth per annum = 7%
Design Traffic loading for 15 years = 19 msa

From Plate 2 of IRC: 37-2001, for CBR of 8% the following pavement thickness has
been arrived and is presented in Table 1.3 below.

Table 1.3(a): Pavement Layer Thickness for Main Carriageway


Type of Layer Layer Thickness (mm)
Bituminous Concrete (BC) 40
Dense Bituminous Macadam (DBM) 85
Wet-Mix Macadam (WMM) 250
Granular Sub-Base (GSB) 200
Total 575

Overlay design has been done as per IRC 81 1997. Benklemen Beam Deflection (BBD)
Test results have been taken into consideration. Average deflection of existing
pavement is less and 2mm deflection has been considered for design purpose for a
period of 15 years.

Table 1.3(b): Overlay Pavement Layer Thickness for Main Carriageway (Existing Road)
Type of Layer Layer Thickness (mm)
Bituminous Concrete (BC) 40
Dense Bituminous Macadam (DBM) 85
Total 125

Service Road
For the service roads, traffic loading of 5 msa is adopted and the pavement design has
been arrived from Plate 1 of IRC: 37-2001 for CBR of 8% as presented in Table 1.4.

Table 1.4: Pavement Layer Thickness for Service Road


Type of Layer Layer Thickness (mm)
Semi-Dense Bituminous Concrete (SDBC) 25
Dense Bituminous Macadam (DBM) 50

SECON 4 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Type of Layer Layer Thickness (mm)


Wet-Mix Macadam (WMM) 250
Granular Sub-Base (GSB) 150
Total 475

1.8 At-Grade and Grade Separated Intersections


The details of at grade and grade separated intersections for the entire stretch has been
summarised in Table 1.5 below.

Table 1.5: List of At-Grade and Grade Separated Intersections


Description No.
Major Junctions 07
Minor Junctions 08
Vehicular Underpasses 05
Vehicular Overpasses 05
ROBs 01

1.9 Project Facilities


For the convenience of the passengers bus bays with bus shelters have been provided
at 2 locations including both directions on main carriageway and 31 locations including
both directions on service roads.

One Toll Plaza has been proposed on the project road. Tentatively location of Toll Plaza
has been proposed at km 38.200.

1.10 Cost Estimates


Detailed cost estimate have been worked out based on Rate Analysis /PWD Schedule
of Rates / Local Market rates and latest data approved by MoSRT&H. Total Civil
Construction Cost is 582.21 crore.

1.11 Economic Analysis


Economic evaluation is carried out to assess whether the proposed investment on
highway improvement is economically feasible. In other words, the objective of the
appraisal is to evaluate if the investment proposed enhances or leads to maximization of
social welfare of the community in the hinterland. The yardstick to measure such
economic viability is usually in terms of Economic Internal Rate of Return (EIRR). As per
the TOR, we have estimated Net Present Value (NPV) as well as Benefit - Cost Ratio
(B/C Ratio) indicators, in order to evaluate the viability in a comprehensive manner.

Economic viability is carried out with 25 years benefit period. The result of economic
viability analysis as furnished in Table 1.6 below reveals that the project is economically
viable with 25 years benefit period when considered for the savings in value of time for
Package I. Detailed economic viability analysis is furnished in Chapter 10 of this report.

Table 1.6: Summary of Economic Viability Analysis

EIRR EIRR NPV (Only NPV (VOC+


Improvement B/C
Sensitivity Cost
(Only (VOC+ VOC in VOT in Mill
Ratio
VOC) VOT) Mill Rs) Rs)

Case-1 6408.54 6.16% 13.15% (3004.00) 845.34 1.13


Case-2 7369.82 5.20% 11.98% (3864.12) (14.78) 1.00
Case-3 6408.54 5.05% 11.80% (8510.60) (141.58) 0.98

SECON 5 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Case-4 7369.82 4.13% 10.69% (4273.64) (1001.70) 0.86

Analysis for the project road shows that the project is economically viable.

1.12 Financial Analysis for BOT Project


The purpose of this analysis is to assess the financial viability of the project on BOT
basis. BOT assumes that the entire revenue comes from tolls collected from the traffic
as per NHAI toll rates and the investment is funded through a 70:30 mix of debt and
equity .The viability is assessed from point of view of Equity Investor (Concessionaire),
Lender and the project as a whole for periods of 30 years The other parameters
considered for the analysis has been detailed in Chapter 11.

Table 1.7: Summary of Financial Analysis


Parameters For 40% NHAI GRANT
PROJECT FIRR (Post Tax) 9.35%
EQUITY FIRR (Post Tax) 9.54%
NPV
Rs. (-) 133.62 Crores

2.0 PROJECT BACKGROUND


2.1 Introduction
National Highways Authority of India (NHAI) has taken up the development of National
Highways under the Golden Quadrilateral (GQ) and North-South/East-West (NSEW)
Corridor projects under National Highway Development Project (NHDP) Scheme Phase
I and II. Also NHAI has been entrusted with development of 10000 km of selected
stretches of National Highways under NHDP Phase-III. Since the State Capital of
Kerala is not connected either by the GQ or NSEW corridors, the present project of
connecting Thiruvananthapuram with NH 7 is included in the NHDP Phase-III
Programme. The original scope of the consultancy is to prepare feasibility study to
establish the technical, economical and financial viability of the project and prepare
detailed project report for the re-habilitation and upgrading or providing alternate
alignment for the existing 2-lane National Highway NH 47 to 4 lane divided carriageway.
Further, preparation of the Detailed Project Report (DPR) for developing NH 47B from
Nagercoil to Kavalkinaru to 4-lane divided carriageway configuration was taken up as an
addition to the original scope of the project under instructions from NHAI.

The entire stretch of the project road is divided into two packages. This report pertains
to Package-I, which contains the Kerala portion of the road.

The package starts from Kazhakkoottam junction at km 552/000 of the existing highway,
which is also the take off point of Thiruvananthapuram bypass, and hence referred as
km 0/000 of the new alignment. The proposal envisages widening of the existing 2 lane
bypass to four lane from km 0/000 to km 22/600. Thereafter the original bypass
alignment proposed by Kerala, PWD (NH) is followed upto Ayira village (km 40/343).
Further it deviates from the PWD alignment for a short length and crosses Kerala Border
at km 43/000.

Under the proposal, the existing bypass is to be widened to four lane with central
median of 4.5m, hard shoulders of 1.5m and earthen shoulders of 1.5m. Side slopes of
1:2 have been proposed. One side widening only is proposed for ease of construction
and land acquisition. ROW is kept as 45m generally in the entire stretch. The
alignment is passing through rolling and hilly terrain with deep valleys and hillocks all
along the route.

SECON 6 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

The details of the proposed Typical Cross Section Elements are furnished in Table 2.1
below

Table 2.1: Widths of Cross Sectional Elements


Elements Width (m) Remarks
Main Carriage way 2 X 7.000 14.000 -
Paved shoulder 2 X 1.500 3.000 -
Gravel Shoulder 2 X 1.500 3.000 -
Space for
Slope/Future reserve
Drain 2 X 1.000 2.000 -
Service Roads 2 X 5.500 11.000 -
Utility corridor 2 X 2.000 4.000 -
Median 1 X 4.500 4.500 -
Shy off distance 2 x 0.250 0.500 -
Total 45.00 -

Wherever there is a change in the widening from concentric to eccentric or vice versa
proper flaring will be used for introducing the transition so that the change is gradual.

2.2 Slope protection by RE wall and Soil Nailing:


The proposed ROW is 45m at all locations. The undulating terrain and codal
requirements for 100 kmph design speed has necessitated the provision of high fills and
cuts. At such locations, the slope has been reduced to 1:1.5 to accommodate the cross
section.

Based on the availability of space and height of cut or fill, suitable retaining structures,
such as Reinforced Earth Wall for high fills and Soil Nailing for high cuts, have been
provided in locations where a slope of 1:1.5 cannot be provided. Table 2.2 gives the
availability of space for each cross section type.

Table 2.2: Availability of space based on the CS Type


Sl Available Space
No. CS TYPE in ‘m'
Type - B - 1: Typical cross section for eccentric widening Fill portion – 3.5
1
for 4-lane Cut portion – 2.5
Type - B - 2: Typical cross section for eccentric widening Fill portion – 3.5
2
for 4-lane High cut and fill Cut portion – 2.5
Type - B - 3: Typical cross section for concentric widening
3
for 4-lane 3.5
Type - B - 4: Typical cross section for 4-lane new road with
4
service road 3.5
Type - B - 5: Typical cross section for 4-lane new road
5
without service road 9
Type - B - 6: Typical cross section for 4-lane new road with
6
service road (high fill) 3.5
Type - B - 7: Typical cross section for 4-lane new road
7
without service road (high fill) 9
Type - B - 8: Typical cross section for 4-lane new road with
8
service road (high cut) 2.5
Type - B - 9: Typical cross section for 4-lane new road
9
without service road (high cut) 9

SECON 7 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

In case of high fill portions without service road a berm of 1m is provided next to the
drain, a slope of 1:1.5 is provided for the remaining 8m and further down RE wall is
provided.

2.3 Demography

2.3.1 Kerala State Profile


Kerala’s population has grown from 6.4 million to 31 million from 1901 to 2001, a five-
fold increase in the last Century (Table 2.3). Kerala recorded a consistently higher
growth rate than that of India’s average from 1931 to 1971. The decline in growth rate
since 1971 is perhaps due to large-scale migration to other States and abroad,
particularly Gulf countries. The other reasons may also include increasing levels of
literacy and per capita income.

Table 2.3: Growth of Population, Kerala and India: 1971-2001 (in Millions)
Kerala India
Year
Rural Urban Total Rural Urban Total
1971 17.88 3.47 21.35 439.05 109.11 548.16
1981 20.68 4.77 25.45 (19.24%) 523.87 159.46 683.33 (24.66%)
1991 21.42 7.68 29.10 (14.32%) 628.69 217.61 846.30 (23.86%)
2001 23.57 8.26 31.84 (9.42%) 741.66 285.35 1027.02 (21.35%)

Kerala has witnessed a steady growth in urban population in the past two decades.
While the percentage of urban population to the total population in 1981 was only 18% it
increased to 26% in 1991 registering a growth rate of 60%. The decennial growth rate
for the same between 1971-1981 was only 38%.

In the year 1991, Kerala had 197 urban centers while there were 106 towns in 1981.
Moreover, a study by the Department of Town Planning shows that there are 113 more
settlements in the State, which satisfy the ‘near-urban’ criteria of the census. The urban
sector in Kerala comprises of five Municipal Corporations, 53 Municipalities and 6
Development Authorities.

Table 2.4: Growth Rate of Urban Population in Kerala, 1981-1991


Item 1981 1991
Total Population 25453680 29032828
Urban Population 4771275 7676371
% Urban Population 18.74 26.44
Share of Urban population to Total (%) 2.99 3.54
Decennial Growth Rate of Urban Population (%) 37.64 60.89
Source: Census of India, 1991

2.3.2 Density Pattern


The region has an average density of about 1476 persons per km². The influence of
physical factors like topography, soil fertility, rainfall etc., on the distribution pattern of
population is significant. Additional advantages are, however, provided by transport and
communication lines and proximity of urban center and newly emerging centers in the
vicinity of tehsil and block headquarters and along the trunk routes.

SECON 8 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

2.3.3 Human Settlements


The important human settlement falling in the ROW are Kazhakkoottam, Attipra, Chakka,
Vazhamuttam, Vellar, Kovalam, Azhakkulam, Mukkola, Punnakulam, Puthenkada,
Thirupuram, Piravankonam, Mundaplavila and Ayira.

2.3.4 Occupational Structure


The working population is dominated by male, but there is a very high percentage of
female working group in comparison to other states of India. Though no appreciable
changes at Tehsil level are observed in the percentage of male workers to total males,
the percentages of female workers record wide fluctuations in different parts of the
region.

2.3.5 Religious Composition


The religious composition shows the predominance of Hindus. Christians constitute the
second largest religious community.

2.3.6 Linguistic and Socio – Cultural Characteristics


The mother tongue of the population in the study region is Malayalam. Rural society,
which is distinct from its urban counterpart, generally consists of simple, orthodox and
God-fearing people in whom is seen the greatest spirit of cooperation and communal
harmony. It is less amenable to new changes and innovations, a characteristic
responsible for the preservation of ancient local culture.

2.3.7 Some other Demographic Characteristics


Among other demographic characteristics age and sex structure, marital status, and
literacy rate and migration pattern were considered and analysed as follows.

2.3.7.1 Age and Sex Structure

Age composition is an index of potential labour supply as well as the possible growth-
trend of the population in the region. More than half of the region’s population is in the
working age group (15-60 years). Females record greater percentage of their population
below 39 years of age, while reverse trend is noticed in case of males who have larger
percentage above 39 years of age. The sex ratio is in favor of male owing to high
mortality rates in females.

2.3.7.2 Literacy

Total literate (excluding the population in the age group of 0-6 years) is 89.36% and
88.12% of the total population. The literacy percentage of males is higher than that of
females, showing a comparatively lesser gap in comparison to state figure.

2.4 Agriculture
Agriculture has been the primary occupation of the district. Cultivable land may be
classified as wet, dry, garden and plantations. Paddy is the most important crop
cultivated in the wet lands. Tapioca and pulses are the important dry land crops.
Coconut, one of the most important crops of the district, is cultivated in an area of
84,308 hectares and the annual production is about 516 million nuts.

SECON 9 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Newly introduced agricultural development schemes have opened new vistas in this
field. Fresh schemes are introduced in every Panchayat with a view to maximize yield
per unit area by exploiting the production potential of paddy and vegetables.

Cashew is grown in 2,184 hectares of land and the production is about 1745 tonnes.
Pepper cultivation covers an area of 5,090 hectares and the yield is about 1824 tonnes.

Paddy :Paddy is the main crop of the district and is raised in two seasons i.e. Kannipoo
(April –June) and Kumbapoo (September – October) respectively.

Tapioca: Tapioca is raised as a subsidiary food crop in this district. The main planting
season is April - May. In some pockets, September – October planting is also done as
second season crop.

Pulses: Pulses are raised in rice-fallow and as intercrop in Tapioca. The important
pulses are Blackgram, Greengram, Horsegram, Cowpea and Redgram. In the months of
April – May and September – October pulses are grown as intercrop with Tapioca. In
the months of February – March pulses are raised as pure crop in rice-fallows.

Coconut: Coconut is an important cash crop of this district. The main planting season is
May – July.

Banana: Banana is cultivated mainly during March – May and September – October.

Groundnut: Groundnut is raised during March – April and October – November as


rainfeed crop in small extent. Vegetables are cultivated during January – February and
July – August.

Vegetables: Vegetables are also grown as 3rd crop after the harvest of 2nd crop paddy
in some pockets of this district. Proximity to equator, topography and other climate
factors favor the cultivation of varied crops. In addition, Pepper, Cloves, arecanut,
Betelvine, Cocoa, Gingelly, Ginger, turmeric, Arrowroot etc. are also grown.

2.5 Land Use


Land use has a strong impact on environment of any region. The clearing of plantation
for settlements, agriculture, transport and communication networks and consequent
disappearance of wild animals have adversely affected the ecological balance. Land
use analysis of a region plays vital role in decision-making process of any proposed
activity / project; specifically in road/highway projects the impact may be very significant.
Thus, the land use study has been done in order to evaluate the regional land for the
present project of road construction and widening.

Total geographical area of the state according to village documents is 3885497 hectares
of which net area sown in 1998-99 was 2258674 hectares constituting 58.13 percent of
total area. Forestland constitutes 27.83% of total area where as the area of cultivable
waste land is 1.61 percent.
2.5.1 Irrigation
Since the rainfall is variable, the region needs supplement water requirements for
agricultural purposes. In the study area canal network is good and it fulfils the irrigation
requirement of the area.

Thiruvananthapuram-Neyyar Project, commissioned in 1959, irrigates an area of 11,665


hectare. Neyyar River is the source of water for the reservoir. The length of dam is
294.13 meters and the height is 50.6 meters. The catchments draining into the reservoir,

SECON 10 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

cover an area of 140 sqkm of forest land, receiving an annual rainfall of about 226 cm.
from two monsoons. The total length of the main canal and its branches is 266 km.
Apart from canals, tanks are the source of irrigation for the cultivated area.

2.5.2 Fertilizer Consumption


Total consumption of fertilizer in the state in 1999-2000 was 211632 tonnes. The break
up was 87061 tonnes, Nitrogen 43975 tonnes, Phosphate and 80326 tonnes Potash.
2.5.3 Livestock
Livestock and poultry population as per census figures of 1996 is given in Table 2.5
below.

Table 2.5: Livestock and Poultry Population


Sl. Type Livestock/ Population of
No. Poultry Livestock/Poultry
1 Cattle 3396335
2 Buffaloes 165125
3 Sheep 6058
4 Goats 1860501
5 Pigs 142784
6 Other livestock 6114
Total Livestock 5576917
Total Poultry 26946091

2.6 Forests
Total area under forests in the state is 1998-99 was 1081509 ha. This accounts for
27.83% of the total area of the state. Major produce of forests in 1998-99 was 26663
cum of Timber in round logs, 275050 round poles, 6,662 cum of sawn and squared
timber and 18423 metric Tonnes of fire wood.

2.7 Industries
Growth of working factories and average employment is given in Table 2.6.

Table 2.6: Growth of working factories and employment


Number of Working Factories Employment
Year
Private Public Total Private Public Total
1988 11733 295 12028 214723 65965 280688
1989 11841 265 12106 281066 94739 345805
1990 12035 413 12448 239562 115988 355550
1991 12800 455 13255 243211 125527 368738
1992 14113 495 14605 248198 127538 375736
1993 14646 486 15132 277266 111492 388758
1994 14824 481 15305 281669 108291 390260
1995 14840 491 15331 263878 111270 375148
1996 15906 528 16434 293923 111144 405067
1997 16803 533 17336 317592 111248 428840
1998 17177 542 17719 334143 109698 443841
1999 17788 552 18340 340809 110086 450895

SECON 11 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

2.8 Infrastructure – Transport

2.8.1 An Overview
Kerala depends on the three components of surface transport viz. road transport, rail
transport, and inland water transport for the movement of passengers and goods traffic.
The year 2000-2001 witnessed good growth in the transport sector in the State in
general and road sector in particular.

During the period, the total length of the road in the State increased from 1,23,889 km to
1,25,835 km. The number of motor vehicles in the state stood at 21,11,885 as against
19,10,237 in the preceding year thereby registering an increase of 10.56%. The total
number of road accidents increased by 8.33% from 34387 in 1999-200 to 37252 in
2000-2001. Railway route length as on 31.3.2001 in the State was 1148 km.

2.8.2 Roads
Kerala has a comfortable network of roads having a total length of 1,25,835 km as on
31.3.2001. It accounts for 4.13% of total road length in the country. Agencies
maintaining roads in the State include State PWD, Panchayats, Municipalities and
Corporations, National Highways, Irrigation Department, Forest Department, Kerala
State Electricity Board etc.

Out of total road length, 87,094 km are maintained by Panchayats (69.2%) followed by
21508 km (17.1%) by State PWD. Corporations maintain a road length of 4776.84 km
(3.7%), Municipalities maintain 3,193 km (2.5%) and NH cover 1560 km (1.23%). While
Irrigation Departments maintain 3787km (3%) of road, the share of Forest Department is
3633 km (2.9%), share of the Indian Railway is 142.88 km (0.11%) and that of Kerala
State Electricity Board 139 km (0.11%). Of the 87,094km roads under Panchayats,
54339.722 km (62.39%) are graveled and earthen roads and 21067 km (24%) are black
topped.

Of the 14 districts in the State, Kottayam district accounted for the maximum road length
of 2225 km (10.3%) followed by Ernakulam district with 2165 km (10%). Wayanad
district had the lowest PWD road length of 515 km (2.4%).

During the period 2000-01 there were 1994 bridges and 47,557 culverts on PWD roads.
Of these, 171 bridges and 1371 culverts were unsafe.

Total length of National Highways in the State during 2000-2001 remained at 1560kms.
Details of National Highways in Kerala are given Table 2.7 below.

Table 2.7: National Highways in the State


Sl. Name Length (km)
No.
1. NH 47 – Valayar – Kaliyikkavila 416.80
2. NH 17 – Thalappadi – Edappally 420.80
3. NH 49 – Bodimettu – Kundannoor (Kochi – Madurai) 167.60
4. NH 47A – Kundanoor – Willington Island 5.90
5. NH 208 – Kollam – Aryankavu 81.00
6. NH 212 – Kozhikode – Muthanga 117.00
7. NH 213 – Palakkad – Kozhikode 114.00
8. NH 220 – Kollam – Theni 210.00
Total Length 1560.10

2.8.2.1 Transport Vehicles

SECON 12 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Vehicle Population in the state is given in Table 2.8.

Table 2.8: Growth of Registered Motor Vehicles in the State of Kerala


2 3 Cars / Goods
Year Buses Tractors Others Total
Wheelers Wheelers Jeeps Vehicles
1991 288498 67317 189432 21454 66190 4305 10426 647622
1992 330316 75244 193533 22833 71089 4573 10584 708172
1993 369537 83725 205564 25245 77336 4315 15573 781295
1994 428641 92296 226806 30370 88455 4691 16413 887672
1995 496873 103465 247605 34862 100252 5045 17820 1005922
1996 591923 127913 273922 38177 111762 5296 21248 1170241
1997 694242 148902 257048 43030 131311 5785 77507 1357825
1998 798982 164834 330603 55482 139145 5567 13425 1508038
1999 904961 197595 370964 48884 151082 5801 29651 1708938
2000 1020797 227895 396874 58888 163443 7782 34558 1910237

2.8.3 Air Transport


Though Kerala is a small state in terms of area, there are three International Airports at
Thiruvananthapuram, Kochi and Calicut. The newly built airport at Kochi
(Nedumbassery) is known as CIAL (Cochin International Airport Limited) and is the first
airport in the country built and run by a Corporate body.

2.8.4 Water Transport


The state has major harbor facility at Cochin. There is a ship building yard which caters
for building of ships as well as maintenance and repair of ships. Also major facilities of
Southern Naval Command of Indian Navy are located at this harbor. There are number
of fishing harbors all along the west coast which includes Purakkad (Alleppey),
Neendakara (Quilon), Vizhinjam (Thiruvananthapuram) and Calicut. In addition to this
Kerala has a network of Inland waterways including a National Water Way.

2.8.5 Rail Transport


Kerala has a fairly good network of railway lines running along the length of the state.
The complete system falls under Southern Railways and Broad Gauge network include
the main lines from Coimbatore to Thiruvananthapuram towards South and Shornur to
Kasargod in the North. Also there is a loop line from Ernakulam to Kayankulam via
Alleppey and branch line from Thrissur to Guruvayur. Meter gauge lines consist of
Pallakad-Pollachi and Quilon-Tenkashi lines up to Kerala Border. Total length of Kerala
railway lines in Kerala are as under.

Total Length of Broad Gauge Lines : 908 km


Total Length of Meter Gauge Lines : 110 km

2.8.6 Tourism
Tourism industry plays a very vital role in the state economy. Some of the important
tourist attractions are given below:

Back Waters: Alappuzha backwaters, Q S T and R Block Kayal, Pathiramanal.

Beaches: Alappuzha, Cherai, Valapattanam Payyambalam, Muzhapilangad, Kappil,


Bekal Fort, Thirumullavaram, Kappad, Kozhikode, Kovalam.

SECON 13 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Water Falls: Keezharkuth, Athirapilly, Vazhachal.

Picnic Spots: Bhoothathankettu, Thattekadu Bird Sanctuary, Pattumala, Eravikulam


National Park, Vagamon, Pullumedu, Parassini Kadavu, Malayala Kalagramam,
Chandragiri, Palaruvi.

Hills: Echo Point, Ramakalmedu, Peermedu, Munnar, Thrissanku and Peeru hills,
Ramala Pandikuzhi, Ponmudi, Agasthyarkoodam.

Wildlife: Marayoor, Idukki Wildlife Sanctuary, Periyar Wildlife Sanctuary, Chinnar


Wildlife Sanctuary, Idukki Aralam Wildlife Sanctuary, Shenduruny Wildlife Sanctuary,
Green adventure Parambikulam wild life Sanctuary, Peppava Wildlife Sanctuary,
Peechi- Vazhani Wildlife Sanctuary, Muthanga Wildlife Sanctuary, Wayanad.

Dams: Siruvani, Neyyar, Idukki.

Museums: Bay Island Driftwood museum, Kuthiramalika (Puthen malika) palace


museums, Science and Technology museums, Priyadarshini Planetarium, Napier
museum and Art Gallery Thiruvananthapuram, Archaeological museum, Ambalavayal
Heritage Museum

Forts: St. Angelo Fort Thalasseri, Fort Bekel.

Historical Monuments: Krishnapuram Palace Kayamkulam, Synagogue Fort Kochi,


Vasco da Gama Square, Mattanchery Palace, Bolghatty Island, The hill Palace Museum
Thripunithura, Madhavan Major Foundation Chendamangalam, The antique sellers of
Jew Street.

Pilgrim Centres : Parassini Kadavu, Sri. Muthappan Temple, Thodikkulam Temple


Kannur, The Cave Temple, Niranam, Padmanabha Swamy Temple, Varkala,
Shabarimala, Guruvayoor.

Places of Interests: Kuttanad, The Vijaya Beach Park, Mannarsala Sreenagaraja


Temple, Chavara Bhavan, Ambalappuzha Sree Krishna Temple, Edathua Church,
Chettikulangara Bhagavathy Temple Mavelikkara, Alappuzha – Aqua tourism,
Champakulam Church, St. Francis Church

Others: Kodanad Sahyadri Ayurvedic Centre, Picnicking in the hills- C.V.N. Kalari
Edakkad, Kottakkal, The Gandhi Seva Sadan, Kathakali and Classic Arts Academy,
Vasthuvidya Gurukulam.

2.9 Project Influence Area, District Thiruvananthapuram

2.9.1 Area & Climate


Area: 2192 sqkm
Rain Fall: 2493 mm

2.9.2 Socio – Demographic Characteristics


Total estimated population of the district according to 2001 census is given in Table 2.9.

Table 2.9: Demographic Details of Thiruvananthapuram District (2001 Census)


Total population Density of Sex Ratio Literacy rate

SECON 14 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Population females/ (%)


Male Female Total (per sqkm) 1000
males
15,71,424 16,63,283 32,34,707 1476 1058 89.36

2.9.3 Livestock and Poultry


The livestock and poultry population in 1996 in both the districts are given in Table 2.10.

Table 2.10: Livestock and Poultry population (1996 Census)


Name of District Livestock Poultry

Thiruvananthapuram 4,16,822 23,33,387

2.9.4 Transport Vehicles


Vehicle population in the two districts in 199-2000 is given in Table 2.11.

Table 2.11: Motor Vehicles on Road in Thiruvananthapuram (1999-2000)


Goods Cars & Station Wagons, Three Two
Buses Others Total
vehicles Taxis & Jeeps Wheelers Wheelers
1684 2030 3363 23602 12056 2835 172040
2.9.5 Social Aspects
The second part of the socio- economic profile deals with social aspects of the proposed
project delineating in particular poverty alleviation, gender, local populace, industry, land
use, employment, health, land acquisition and resettlement dimension.

2.10 State Economy

2.10.1 Growth of State Domestic Product


Estimate of Net State Domestic Product (NSDP) at factor cost by industrial origin and
per capita NSDP (at 1993-94 constant prices and at current prices) for the years 1993-
94 to 1999-2000 are given in Table 2.12 & Table 2.13.

Table 2.12: State Income (NSDP) of Kerala by Industrial Origin (At constant
Prices)
(Rs in Lakhs)
Sector
1999-
1993 -1994 1994 -1995 1995 -1996 1996 -1997 1997 -1998 1998-1999*
2000**
(i) Primary Sector
1. Agriculture 625603 689697 694671 711466 677678 668665 660240
2. Forestry & logging 74340 81401 71661 74640 72479 74835 77229
3. Fishing 63849 68241 59774 66012 53424 58720 60599
4. Mining & Quarrying 5010 4064 5768 5048 5600 5712 5826
Sub – Total – Primary 768802 843403 831874 857166 809181 807932 803894

SECON 15 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

(Rs in Lakhs)
Sector
1999-
1993 -1994 1994 -1995 1995 -1996 1996 -1997 1997 -1998 1998-1999*
2000**
(ii)Secondary Sector
5. Manufacturing: 269832 325889 353751 340550 329021 344433 358428
5.1 Registered 135764 155733 175239 168617 172039 181329 189126
5.2 Un-registered 134068 170156 178512 171933 156982 163104 169302
6. Electricity Gas 17658 18452 18240 24320 29806 32012 34528
&Water supply
6.1 Electricity 13499 14636 14685 20903 26421 28799 31449
6.2 Gas 839 815 763 756 742 718 694
6.3 Water Supply 3320 3031 2792 2661 2643 2495 2385
7. Construction 197049 199786 199276 204232 227233 234732 243417
Sub – Total –Secondary 484539 544157 571267 569102 586060 611177 636373
(iii) Tertiary Sector
8. Transport storage &
communication:
8.1 Railways 134320 148948 172976 181348 202925 225995 250210
8.2 Transport by other 4474 5403 6320 7402 6549 6650 6753
means & storage
8.3 Communication 104310 114529 127718 134156 148310 161984 176689
9. Trade Hotels & 25536 29016 38938 39790 57361 66768 66768
Restaurants 448431 483457 513594 528555 598324 598324 633864
10. Banking & Insurance 111005 122968 141407 180090 168681 179098 191993
11. Real Estate
Ownership of 131203 135063 140048 147185 157287 165104 174284
Dwellings
12. Public Administration
13. Other Services 116533 109158 115657 119124 134495 139678 145226

Sub Total Teritary 190274 203638 207924 220075 242148 258050 275288
Net State Domestic 1131766 1203232 1291606 1376377 1468074 1566249 1670865
Product 2385107 2590792 2694747 2802645 2863315 2985358 3111132
Population(‘000)
Per Capita
Income Rs. 30048 30424 30805 31186 31539 31856 32145

7938 8516 8748 8987 9079 9371 9678

*Provisional Estimate
**Quick Estimate

Table 2.13: State Income (NSDP) of Kerala by Industrial Origin (At Current Prices)

(Rs in Lakhs)

Sector 1999-
1993 -1994 1994 -1995 1995 -1996 1996 -1997 1997 -1998 1998-1999*
2000**

1. Agriculture 625603 771327 956859 1078575 1068818 1161486 1262998


2. Forestry & 74340 94561 95168 101481 97894 100954 103983
logging
3. Fishing 63849 66853 83515 102436 104198 109657 114372
4. Mining & 5010 5789 6371 6139 7067 7703 8396
Quarrying

Sub – Total –
768802 938530 1141913 1288631 1277977 1379800 1489749
Primary

SECON 16 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

(Rs in Lakhs)

Sector 1999-
1993 -1994 1994 -1995 1995 -1996 1996 -1997 1997 -1998 1998-1999*
2000**
5 Manufacturing: 269832 357673 441924 472480 493201 549679 600725
5.1 Registered 135764 173906 216999 226908 250334 279198 307118
5.2 Un-registered 134068 183767 224925 245572 242867 270481 293607
6. Electricity Gas 17658 20515 22590 32824 43362 48942 55099
& Water Supply
6.1 Electricity 13499 16246 18210 28219 38445 43816 49731
6.2 Gas 839 905 946 1013 1084 1145 1205
6.3 Water Supply 3320 3364 3434 3592 3833 3981 4163
7. Construction 197049 230912 284128 343518 432857 491682 556781
Sub – Total -
Secondary 484539 609100 748642 8488822 969420 1090303 1212605
8. Transport
storage & 134320 166724 207727 235240 279221 333223 398492
communication:
Railways 4474 4985 6090 7253 8233 8489 8817
Transport by 104310 130539 160948 186930 222783 269385 322916
other means
& storage 25536 31200 40689 41057 48205 55349 66759
Communication
9. Trade Hotels & 448431 566227 707354 824432 991030 1195275 1462060
Restaurants
10. Banking & 111005 135337 174179 233927 221209 243776 280099
Insurance
11. Real Estate
Ownership of 131203 141543 161506 184811 211557 243948 283224
Dwellings
12. Public 116533 120368 140247 158079 190663 221063 267296
Administration
13. Other 190274 224407 251463 295926 347270 409395 476955
Services
Sub Total
Teritary 1131766 1354606 1642476 1932415 2240950 1566249 1670865

Net State
Domestic Product 2385107 2902236 3533031 4069868 4488347 5116783 5870480
Population(‘000)
Per Capita 30048 30424 30805 31186 31539 31856 32145
Income Rs. 7938 9539 11469 13050 14231 16062 18262
* Provisional Results
** Quick Estimates

The data given in Table 2.12 indicates a compound rate of 4.53 for NSDP and 3.36 for
per capita income for the last Six years.

3.0 SUMMARY OF SURVEY AND INVESTIGATIONS


3.1 Topographical and Cadastral Surveys

3.1.1 Topographical Survey


Topographical survey was conducted for the purpose of creating a digital terrain model
(in order to design the road and structures) for the stretch of the road from
Kazhakkoottam to Kerala border on proposed alignment km 0.000 to km 43.000.

SECON 17 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

3.1.2 Methodology for Topographical Survey


The survey was carried out as follows:

3.1.2.1 Basic plan control

The coordinates of the basic plan control points were established with the use of
differential GPS equipment (Leica-SR 530) providing accurate and homogeneous
control all along the length of the road stretch. There are 27 GPS stations most of which
are on rock-out-crop / sheet rocks situated along the proposed alignment. For each GPS
station there is a reference point situated at about 200m away, which was also fixed by
differential GPS method and on similar object as for the GPS station, to serve the
purpose of providing starting and closing bearing for Total Station traverse as well as for
providing extra primary control point. The co-ordinates were obtained on WGS – 84
system on Transverse Mercator’s Projection with the central meridian of projection
passing through the center of the stretch of the NH, thereby having practically no scale
error for the coordinates.

3.1.2.2 Extension of Planimetric control

In between GPS stations, Total Station traverses were run providing planimetric
positions at about 250m apart. Since Bench Marks are established at about 250m apart
along the road length, these points were connected during the Total Station traverse for
control. Total Stations of 1 second accuracy (Leica TC 1800L and Topcon GTS 710)
were used, providing both plan and height control for the pillars / other control points.

3.1.2.3 Height Control

Double tertiary leveling was done along the entire stretch with precision automatic levels
connecting the existing GTS BM at Palayam junction in Thiruvananthapuram city. The
DT leveling was started from this GTS BM and closed on another GTS BM at
Balaramapuram, about 40 km from the first BM.
The misclosures were seen to be below the tolerant limit of 12 k mm, where k is the
length of the leveling line in km. The misclosures were adjusted and heights given to all
Bench Marks established at about 250m apart all along the alignment on RCC pillars (as
specified by NHAI vide Terms of Reference). Thus, all the Bench Marks established
along the stretch are in terms of GTS Bench Marks established by Survey of India.

3.1.2.4 Detailed Survey

All the details / features along the road within the survey boundary were picked up by
conducting a detailed Total Station Survey in between the planimetric control points. X,
Y and Z coordinates of relevant points were captured by this Total Station survey, such
as electric / telephone pole, tree with type, statue, wells and points on string lines (i.e.,
points on the same linear feature such as centerline of road, left / right edge of
carriageway, left / right edge of embankment top, left / right embankment toe line, break
points on ground, visible property lines, streams, building etc., within the limit of survey).

3.1.2.5 Creation of Digital Terrain Model

The survey data were down loaded and converted to graphic files using Automap and
Nova Point software. With the help of x, y, z coordinates of the several points picked up
in the field, digital terrain models were created in which the road design is done.

SECON 18 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

3.2 Cadastral Survey


The cadastral survey has been carried out along the existing Thiruvananthapuram
Bypass upto km 22.600 to identify the ownership details and extent of additional land
required for widening and improvement of junctions. Beyond Kovalam (km 22.600) upto
Mukkola (km 25.800) land Acquisition has already been completed by Kerala
Government as per the original alignment. ROW was limited to 45m in Kerala region.
The draft Gazette Notification No.3 for details of land to be acquired village wise and
mandal wise are prepared for submission to NHAI authorities for necessary notification
and acquisition of additional land.

3.3 Investigation Data

3.3.1 Inventory for Structures


Detailed condition survey of the existing structures was carried out simultaneously along
with the detailed inventory survey. Visual examination of the structures using
conventional standard tools mentioned in QAP is considered / recommended for the
assessment of the condition of the structure. Signs of degradation and deterioration of
the structures such as cracks, exposure of reinforcement, rust stains, corrosion,
deflection, if any, condition of expansion joints, bearings, condition of the drain were
noted. Details of Condition of Bridges are furnished.

3.3.2 Benkelman Beam Deflection Survey


The design of pavement overlays for the existing pavements requires an evaluation of
the available strength in the pavement. The Benkelman Beam(BB) allows an estimate of
this available strength to be made by recording of the deflection of the pavement
surface at a point when a standard load moves past that point. Because of the inherent
variability in the pavement structure it is found that the characteristic value of the
pavement deflection is best taken as function of the mean of a series of readings rather
than a single reading. To generate the required coverage without generating an
excessive number of tests the routine BBD testing was specified at 1 Km intervals. All
testing was carried out in accordance with the requirements of IRC 81-1997.

3.3.3 Bump Integrator Test


The roughness surveys along the existing Thiruvananthapuram Bypass as well as the
entire stretch of NH-47 from Kazhakkoottam to Kanyakumari have been carried out by
using Bump Integrator equipment developed by Central Road Research Institute, New
Delhi. The road roughness is measured for every 200m intervals along the stretch by
towing the bump integrator on each lane. Two runs have been made for each lane. The
collected data has been processed to find out the roughness value.

3.3.4 Existing Soil Strata upto 2m below Ground Level


The existing soil strata for about 2m depth from the ground level have been studied by
detailed soil classification from the samples collected at site.

3.3.5 Borelog details


The goe-technical investigations have been carried out at all the major and minor bridge
locations and other structures locations. The details of the Borelogs have been
presented in Design Report.

SECON 19 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

4.0 TRAFFIC STUDY AND ANALYSIS


4.1 Traffic Surveys

4.1.1 General
Information about traffic is essential for the highway project since it forms the basis for
deciding the number of lanes, design of intersections, design of pavement as well as
economic appraisal of the project. Traffic studies require collection of basic information
regarding the current level of traffic and its characteristics viz., volume, composition,
origin and destination studies, axle load spectrum, speed and delay studies, turning
movements, vehicle occupancy etc. These studies generally consist of mode wise traffic
estimates, travel patterns of passenger and freight (goods) etc.

The locations for traffic studies were finalised on the basis of a reconnaissance survey
undertaken for the project road and in consultation with the NHAI. The project road is a
section of the National Highway NH 47 connecting Kanyakumari and
Thiruvananthapuram and a section NH 47B connecting Nagercoil and Kavalkinaru.
NH 47 connects the industrial belts in its influence area to Cochin Port, which falls in its
alignment. Proforma designed for traffic surveys have been submitted in QAP.

The traffic surveys undertaken for the purpose include:


 Classified 7-day continuous Traffic Volume Counts.
 Intersection Turning Movement Surveys
 Origin-Destination Surveys
 Willingness to Pay Toll Surveys
 Pedestrian/Cattle Movement Surveys
 Axle Load Surveys
 Travel Time Surveys

In addition to the above, data on traffic accidents on the project road stretch was
collected to identify black spot locations to suggest suitable remedial measures.

Traffic on the Project Road is characterised by a high degree of motorised vehicles,


which consist of passenger vehicles such as cars, two wheelers (scooters/motor cycles),
buses, and commercial vehicles such as light commercial vehicles (LCVs) and trucks.
Non-motorised vehicles in the traffic stream, consist mostly of bicycles with negligible
number of animal drawn vehicles. The classification system specified in the Terms of
Reference and detailed hereinafter was adopted for the counts.

4.1.2 Motorised Traffic


 2-wheeler (Scooter/motor Cycle)
 3-Wheeler (Autorickshaw)
 Passenger car
 Utility Vehicle (Jeep, Van etc.)
 Bus (Standard)
 Mini Bus
 Light Commercial Vehicle (LCV) Passenger
 Light Commercial Vehicle (LCV) Freight
 Truck - MCV – 2 Axle Rigid Chassis
 Truck - HCV – 3 Axle Rigid Chassis
 Truck - MAV – Semi Articulated
 Truck - MAV – Articulated

SECON 20 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

4.1.3 Non-Motorised Traffic


 Bicycle
 Animal Drawn Vehicle
 Others

4.2 Traffic surveys on NH-47

4.2.1 Classified Traffic Volume Counts


Classified Traffic Volume Counts for 7 continuous days is conducted at two locations,
which provides the information about the traffic along the project road. The survey
locations are given in Table 4.1 below.

Table 4.1: Traffic Volume Count Location


Sl. Volume Count
Location
No. No.
1 VC-1 km 550/400 on existing NH 47
2 VC-2 km 13/600 on Thiruvananthapuram Bypass
3 VC-3 km 626/000 on existing NH 47

The survey locations approximately coincide with the regular (historical) traffic count
station of the National Highways. The classified traffic counts at station VC1 and VC2
were conducted between 27th September 2004 to 03rd October 2004. The number of
vehicles in either direction was noted at 15-minute intervals in accordance with their
classification by observers specially trained for this purpose.

4.2.2 Classified Turning Movement Surveys


On the basis of the reconnaissance survey, two intersections along the project road
were identified for conducting detailed turning movement surveys. The intersection
details are as detailed in Table 4.2 below:

Table 4.2: Turning Movement Traffic Volume Count Locations


Sl.
Count No. Location
No.
1 IC-1 km 550/400 on existing NH 47
2 IC-2 Round about (Chakka) on
Thiruvananthapuram bypass, km 10/300

4.2.3 O-D Survey and Commodity Movement Survey


An Origin-Destination (O-D) and Commodity Movement Survey was carried out adopting
Road Side Interviews (RSI) method at two stations for a continuous period of 24 hours.
The random sampling method was adopted for this survey. The local police assistance
was available to stop the vehicles for interviewing the road users. The RSI was carried
out through pre-planned and structured questionnaires suitable for computer analysis.
Table 4.3 shows the locations adopted for the O-D surveys.

Table 4.3: Origin-Destination Survey Locations


Sl.
Number Location Details
No.
1 OD-1 km 550/400 of existing NH 47
2 OD-2 km 13/600 on
Thiruvananthapuram bypass

SECON 21 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

The information collected during these surveys for passenger vehicles included the
origin and destination; purpose, occupancy and frequency of the trip and income of the
main passenger in the vehicle. In the case of freight vehicles the information sought
included type and quantity of commodity being transported, in addition to origin and
destination, and frequency of travel on the route.

4.2.4 Axle Load Surveys


Axle load surveys were conducted at Km 550/000 on NH-47 on both directions of traffic
for a period of 24 hours on 29th November 2004. Light commercial vehicles, two-axle,
three-axle and multi-axle trucks (both loaded and empty) were selected at random and
their individual axle weights were determined using axle load weighing pads. A certain
number of buses were also weighed.

4.2.5 Pedestrian / Cattle Surveys


There is no appreciable pedestrian/cattle movement across the existing
Thiruvananthapuram Bypass. Hence, pedestrian survey was not considered essential in
any of the stretches in this package.

4.2.6 Speed and Delay (Travel Time) Surveys


Travel Time survey was carried out using “Moving Car Observer Method” on the entire
project road on 22nd and 23rd November 2004 on NH-47. The survey was carried out
during peak as well as off peak periods. Information on journey time, number of vehicles
in opposite direction, number of vehicles overtaken by the test car, vehicles overtaking
the test car and any delays occurring en-route were recorded during the survey. Two
runs were made in each direction.

4.2.7 Willingness to Pay Surveys


The willingness to pay survey was conducted at the following locations. The surveys
were conducted at the locations of the OD surveys as given in Table 4.4 below:

Table 4.4: Willingness to Pay Survey Locations


Sl. Number Location Details
No
1 WPS-1 km 550/400 on existing NH 47
2 WPS-2 Thiruvananthapuram bypass km 13/600

4.3 Traffic Analysis

4.3.1 Historical Traffic Data


The historical data of total and classified number of registered vehicles available with
departments have been collected at Thiruvananthapuram and are tabulated in Table 4.5.

Table 4.5: Vehicle registration data for Thiruvananthapuram District


Year Cars TW Auto Buses LCVs Trucks Any Other Total
Until 1998 44736 165615 21447 10059 4023 10764 2402 257046
1999 3530 -- 2223 253 326 452 --- 6794
2000 4038 18904 2135 1150 394 104 72 26797
2001 4099 19139 1364 840 764 408 198 26812
2002 6505 20616 1292 1145 269 534 28 30389
2003 7515 25537 1957 1524 620 754 400 38307

SECON 22 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

4.3.2 Seasonal Variation


Traffic levels along a study stretch vary during different periods of time i.e., in different
months/seasons. Information on this aspect is necessary to estimate the AADT
(Average Annual Daily Traffic). This is best understood by studying monthly historical
traffic volumes on the project road. Since no past traffic volume data along the project
road was available, the commercial vehicle data obtained at Amaravila Check post near
Thiruvananthapuram for the last four years was considered. It has been found that the
maximum vehicles were recorded in the month of January followed by May. The factors
were compared with the factors mentioned in the Kerala State Highway Project, wherein
the monthly sales of motor fuel have been used to derive the seasonal correction factors.
The survey factors corresponding to the survey period were in the range of 0.95 to 0.98
and so, the traffic volumes of passenger and freight vehicles observed in September
and October are to be factored by 0.95 and 0.98 respectively to determine the Average
Annual Daily Traffic (AADT) considering the fact that the traffic volume during the study
period is closer to the peak season volume.

4.3.3 Present Traffic Conditions


Classified Traffic Volumes obtained during the traffic surveys were analysed both in
terms of vehicles and PCUs. PCU factors adopted for the study are as per the
recommendations of IRC-64:1990. The Average Day Traffic (ADT) on the study stretch
was estimated from the 7-day observed counts. Average Annual Daily Traffic (AADT) at
each location was assessed using the estimated ADT and Seasonal Factors (SF). The
estimated AADT is the basis for the estimates of future traffic volumes on the project
road. Table 4.6 given below gives tentative equivalency factors considered for
presenting the traffic in PCU.

Table 4.6: PCU Values Adopted


Sl. PCU
Vehicle Type
No. Factors
1. Two Wheeler 0.50
2. Auto–rickshaw 1.00
3. New Technology Car/Jeep 1.00
4. Old Technology Car/Jeep 1.00
5. Van/Tempo 1.00
6. Mini Bus 1.50
7. Bus 3.00
8. Light Commercial Vehicle (LCV) 1.50
9. Two Axle Truck 3.00
10. Three Axle Truck 3.00
11. Multi Axle Truck 4.50
12. Agriculture Tractor/Trailer 4.50
13. Animal Drawn 8.00
14. Cycle 0.50

4.3.4 Traffic Flow along the Project Road


4.3.4.1 Traffic Volumes and Characteristics
The traffic volume study is used in planning, traffic operations and control of existing
facility and also planning and designing of the new facilities. Hence, Volume Count
Survey is the main factor in deciding the number of lanes required and the type &
composition of pavement. The results of the traffic counts undertaken for the project are
summarized in Table 4.7. The result from the different sites shows average traffic
volumes in the range of 12000 to 25000 vehicles per day (ADT). Each count included

SECON 23 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

all traffic during one week, resulting in possible random errors of ±1% only (95%
confidence interval). The uncertainty regarding seasonal variations is larger but the total
error margins are still no more than a few percent of ADT, or say ±200 VPD.

Table 4.7: Present Traffic Count Result


Sl.
Vehicle Type VC-1 VC-2 VC-3
No.
1 Two-Wheeler 8840 6071 4487
2 Auto/Three-Wheeler 1642 2718 583
3 Car-Jeep-Taxi 6995 3751 3150
4 Mini-Bus 1585 229 319
5 Bus 1504 112 1503
6 LCV 960 372 1103
7 2-Axle 805 398 1225
8 3-Axle 66 13 163
9 MAV 38 25 7
10 Tractors 3 1 16
11 Total Motarised Traffic 22439 13689 12558
12 Cycle 952 869 792
13 Cycle Rickshaw 6 0 17
14 Animal Drawn Vehicles 0 0 0
15 Hand Cart 1 0 0
16 Total Non-Motarised Traffic 959 870 809
17 Total Traffic 23398 14558 13367
18 Total PCU 25723 12526 17322

4.3.4.2 Hourly Variation of Traffic

Generally peak flow occurs during 4 PM to 5 PM at VC-1 location, 9 AM to 10 AM at VC-


2 location and 7 PM to 8 PM at VC-3. Average

4.3.4.3 Daily Variation of Traffic Volume

The daily variation of traffic with respect to ADT is generally not perceptible, with most of
the daily volume being near to ADT volumes except on Saturday and Sunday.

4.3.4.4 Composition of Traffic

From the analysis it is found that Two Wheelers contribute to the major percentage,
followed by Car/Jeep and then other commercial vehicles. The compositions of the
vehicles at each location for the project are summarized in Table 4.8.

SECON 24 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Table 4.8: Average Compositions of Vehicles at each Location


Sl.
Vehicle Type VC-1 VC-2 VC-3
No.
1 Two-Wheeler 37.78% 41.70% 33.57%
2 Auto/Three-Wheeler 7.02% 18.67% 4.36%
3 Car-Jeep-Taxi 29.89% 25.76% 23.57%
4 Mini-Bus 6.77% 1.57% 2.39%
5 Bus 6.43% 0.77% 11.25%
6 LCV 4.10% 2.55% 8.25%
7 2-Axle 3.44% 2.74% 9.17%
8 3-Axle 0.28% 0.09% 1.22%
9 MAV 0.16% 0.17% 0.05%
10 Tractors 0.01% 0.01% 0.12%
11 Cycle 4.07% 5.97% 5.92%
12 Cycle Rickshaw 0.03% 0.00% 0.13%
13 Animal Drawn Vehicles 0.00% 0.00% 0.00%
14 Hand Cart 0.01% 0.00% 0.00%
Total Traffic 100.00% 100.00% 100.00%

4.3.4.5 Directional Distribution of Traffic

The directional split from the analysis is in the range of 48 to 52%. Directional split at
each of the location is shown in Table 4.9. This is a useful input for capacity analysis
and pavement design. Hence it can be concluded that directional split for up and down
traffic is nearly equal.

Table 4.9: Directional Split


Sl. Thiruvananthapuram- Kanyakumari -
Location
No. Kanyakumari Thiruvananthapuram
1 VC-1 51.86 % 48.14 %
2 VC-2 49.56 % 50.44 %
3 VC-3 50.40 % 49.60 %

4.3.5 Travel Pattern


The Origin and Destination study is carried out mainly to plan the road network & other
facilities for vehicular traffic and to plan the schedule of different modes of transportation
for trip demand of commuters. The O-D survey helps in assessing the adequacy of the
existing road network.

A comprehensive 36-Zone System was adopted for the study to understand the travel
pattern of the traffic using the project road. The entire length of the project road
(Package I) is located in Thiruvananthapuram District.

O-D surveys were carried out for all the vehicle types. But at the time of analysis, it was
necessary to group them, especially vehicle type such as cars (sum of new and old
technology vehicles) and jeeps including vans. State Road Transport Corporation buses
were not stopped and no O-D for such vehicles was obtained. Thus the sample size for
bus is low. The sample size for two wheelers and autos is low primarily because they
are local traffic and many road users were unwilling to state further details. Additionally
these vehicles will not be tolled. The sample size for cars is over 5 percent at Station-
OD1, about 3.5 percent at Staion-OD2. The sample size is reasonable considering the

SECON 25 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

level of traffic moving on the project road. The survey was conducted such that no major
inconvenience is caused to the road users due to stoppage and resulting queue of large
number of vehicles.

The sample size of freight vehicles at the two stations is about 19 percent. Trucks with
two and three axle configuration constitute the major share of such vehicles.

4.3.6 Axle Load Spectrum


For design of pavements, the intensity of traffic loading is an important parameter. The
intensity of traffic loading is defined in terms of cumulative number of standard axle load
repetitions in a given period of time. IRC 37:2001 provides a scientific method for
design of flexible pavements based on the concept of Equivalent Standard Axle (ESA)
and Vehicle Damage Factor (VDF).

Vehicle Damage Factors (VDF) was estimated from the observed axle loads on the
project roads (NH-47) for each class of vehicles at different locations. Table 4.10 gives
the VDF calculated for each class of vehicle.

Table 4.10: VDF for Different Category of Vehicles


Vehicle Type VDF for NH-47
LCV 0.37
BUS 0.22
2-Axle Trucks 4.06
3-Axle-Trucks 1.29
MAV 2.90

Since the VDF obtained for all class of vehicles was found to be low, the VDF value of
4.5 as a national average is adopted for the calculations of MSA.
4.3.7 Turning Movement Survey
The Turning Movement Survey is used in design of intersections, in planning signal
timings channelisation and other control devices. The main aim of turning movement
survey is to determine the directional movement of the traffic in order to assess the
traffic engineering measures required to improve their capacity and to regulate the traffic
flow. Table 4.11 gives the Present peak hour Traffic flow at intersections on the project
road.

Table 4.11: Present Peak Hour Traffic Flow


Sl. Peak Hour Flow
Location Details
No. Vehicles/ Hour PCU / Hour
1 Km 552/000 (IC-1) 2555 2523
Round about (Chakka) on Thiruvananthapuram
2 3648 3117
bypass km 10/300 (IC-2)
4.3.8 Travel Time Analysis
The purpose of the speed and delay study is to assess the running speed, overall speed,
fluctuations in speed and the delay between the two selected locations on a road. The
study also gives information such as the amount, location, duration, frequency and
causes of the delay along the road. The results of the speed and delay studies help in
identifying the congestion spots along the road stretch.

The traffic flows fairly uninterrupted with marginal delays along the project road. Traffic
experiences an average delay of about 706 seconds while moving in

SECON 26 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Thiruvananthapuram to Nagercoil direction and about 871 seconds in the other


direction. The locations with major delays are observed at Marthandam, Nagercoil, and
Neyyatinkara. Journey speeds along the project road varies in different sections and
ranges between 20.7 kmph to 85.4 kmph. Average speed along the project road is
41km/h with very little variation in the two directions.

4.3.9 Willingness to Pay (WTP) Toll


The Willingness to Pay Survey is done to know the opinion of the road users about the
existing road condition and the requirement and assessing the willingness to pay toll for
the improved facilities. The introduction of tolls on the project road is likely to divert
traffic to alternative routes and in turn have an impact on the project revenue from tolls.
Thus, willingness to pay toll and its level are to be assessed from the data obtained for
the purpose.

4.3.10 Accident Studies for NH-47 Section


The Traffic accident data along the project road received from District Police Officials of
Thiruvananthapuram are presented in Table 4.12 below

Table 4.12: Accident Data for ThiruvananthapuramDistrict for NH-47 Section


No. of
Total No. of Total No.
Year District Persons
Accidents Injured
Killed
1996 Thiruvananthapuram 994 1387 98
2000 -do- 1113 1284 98
2002 -do- 1146 1264 96
2003 -do- 1340 1786 128

4.4 Traffic Projections for NH-47

4.4.1 Economic Profile - Project Influence Area


The thirty-six traffic zones of the study can be grouped into the following economic
zones as listed hereinafter.

 Kerala
 Tamil Nadu
 Karnataka
 Andhra Pradesh
 Maharashtra
 North India
 East India

4.4.2 Kerala
Kerala’s population has grown from 6.4 million to 31 million from 1901 to 2001, a five-
fold increase in the last Century (Table 4.13 below). Kerala recorded a consistently
higher growth rate than that of India’s average from 1931 to 1971. The decline in growth
rate since 1971 is perhaps due to large-scale migration to other States and abroad,
particularly Gulf countries. The other reasons may also include increasing levels of
literacy and per capita income.

Table 4.13: Growth of Population, Kerala and India: 1971-2001 (in Millions)
Kerala India
Year
Rural Urban Total Rural Urban Total

SECON 27 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

1971 17.88 3.47 21.35 439.05 109.11 548.16


1981 20.68 4.77 25.45 (19.24%) 523.87 159.46 683.33 (24.66%)
1991 21.42 7.68 29.10 (14.32%) 628.69 217.61 846.30 (23.86%)
2001 23.57 8.26 31.84 (9.42%) 741.66 285.35 1027.02 (21.35%)
Source: Census of India, 1991 and 2001;
Note: Figures in brackets indicate Growth Rates in %.

4.4.2.1 State Profile

Kerala has witnessed a steady growth in urban population in the past two decades.
While the percentage of urban population to the total population in 1981 was only 18% it
increased to 26% in 1991 registering a growth rate of 60%. The decennial growth rate
for the same between 1971 and1981 was only 38%.

In the year 1991, Kerala had 197 urban centers and while there were 106 towns in 1981.
Moreover, a study by the Department of Town Planning shows that there are 113 more
settlements in the State, which satisfy the ‘near-urban’ criteria of the census. The urban
sector in Kerala comprises of five Municipal Corporations, 53 Municipalities and 6
Development Authorities.

Table 4.14: Growth Rate of Urban Population in Kerala, 1981-1991


Description 1981 1991
Total Population 25453680 29032828
Urban Population 4771275 7676371
% Urban Population 18.74 26.44
Share of Urban population to Total (%) 2.99 3.54
Decennial Growth Rate of Urban Population (%) 37.64 60.89
Source: Census of India, 1991

4.4.2.2 General Economic Profile

The state of Kerala had been very progressive since its formation in 1958. Kerala ranks
twelfth amongst the other states, in terms of income. The state economy, over the last
five years has been experiencing a growth of 2 to 7% per annum, as against an all India
average of 5.8% per annum.

4.4.2.3 State Income

The annual growth rate of NSDP from 1997-98 to 2002-03 has been observed to be
5.29%, where as Per Capita Income (PCI) grew at 4.64% per annum over the same
period. The growth rates of NSDP and PCI by years are presented in Table 4.15 below:

Table 4.15: Growths in NSDP and Per Capita Income in Kerala State
At current prices At constant (1993-94) prices
NSDP (in Rs.)
previous year

previous year

previous year

previous year
NSDP

NSDP
Total

Total
NSDP over

NSDP over

NSDP over

NSDP over
NSDP (in
Per capita

Per capita
Growth in

Growth in

Growth in

Growth in

Year
Rs.)
(%)

(%)

(%)

(%)

(Rs (Rs
Lakhs) Lakhs)
1997-98 4488347 14231 2863315 9079
1998-99 5106096 13.76% 16029 12.63% 3064366 7.02% 9619 5.95%

SECON 28 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

At current prices At constant (1993-94) prices

NSDP (in Rs.)


previous year

previous year

previous year

previous year
NSDP

NSDP
Total

Total
NSDP over

NSDP over

NSDP over

NSDP over
NSDP (in
Per capita

Per capita
Growth in

Growth in

Growth in

Growth in
Year

Rs.)
(%)

(%)

(%)

(%)
(Rs (Rs
Lakhs) Lakhs)
1999-00 5692604 11.49% 17709 10.48% 3271615 6.76% 10178 5.81%
2000-01 6371511 11.93% 19951 12.66% 3356516 2.60% 10510 3.26%
2001-02 7304895 14.65% 22668 13.62% 3490599 3.99% 10832 3.06%
2002-03 8378201 14.69% 25764 13.66% 3703133 6.09% 11388 5.13%
Average 13.30% 12.61% 5.29% 4.64%
Source: Department of Economics and Statistics, Govt. of Kerala

4.4.3 Tamil Nadu


It is observed that the economy in terms of NSDP of the state has increased from Rs.
5164330Lakhs in 1993-94 to Rs. 8181770 Lakhs in 2002-03 resulting in a growth of
economy of about 5.30 percent per annum during the period. An average of of 4.28%
growth rate was observed in per capita income considering the NSDP. Table 4.16 gives
the growth rates of NSDP and PCI by years.

Table 4.16: Growths in NSDP and Per Capita Income in Tamil Nadu State
At current prices At constant (1993-94) prices

NSDP (in Rs.)


previous year

previous year

previous year

previous year
NSDP

NSDP
Total

Total
NSDP over

NSDP over

NSDP over

NSDP over
NSDP (in
Per capita

Per capita
Growth in

Growth in

Growth in

Growth in
Year
Rs.)
(%)

(%)

(%)

(%)
(Rs
(Rs Lakhs)
Lakhs)
1993-94 5164330 8955 5164330 8955
1994-95 6127581 18.65% 10503 17.29% 5793555 12.18% 9931 10.90%
1995-96 6971916 13.78% 11818 12.52% 5985425 3.31% 10146 2.16%
1996-97 7912106 13.49% 13270 12.29% 6231974 4.12% 10452 3.02%
1997-98 9268985 17.15% 15388 15.96% 6755934 8.41% 11216 7.31%
1998-99 10579315 14.14% 17394 13.04% 7059878 4.50% 11608 3.50%
1999-00 11274064 6.57% 18367 5.59% 7454344 5.59% 12144 4.62%
2000-01 12609957 11.85% 20367 10.89% 8013892 7.51% 12944 6.59%
2001-02 13256719 5.13% 21239 4.28% 8181253 2.09% 13108 1.27%
2002-03 13678087 3.18% 21738 2.35% 8181770 0.01% 13003 -0.80%
Average 11.55% 10.47% 5.30% 4.28%
Source: Department of Economics and Statistics, Govt. of Tamil Nadu

4.5 Economic Forecasts


Traffic growth rates needed to assess the likely future traffic levels on the project road
are a product of the economic growth rate and the elasticity of the traffic demand vis-à-
vis economic growth. This can be expressed by the following equation.

Tg = e x Eg
Where Tg = Traffic Growth Rate

SECON 29 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

e = Elasticity of Traffic Demand


Eg = Economic Growth Rate

4.5.1 Elasticity of Traffic Demand


Elasticity of traffic demand (e) can be computed considering the historic traffic volumes
and economic trends and are detailed in the forthcoming paragraphs. Future economic
growth rates in the influence area necessary for estimating the traffic growth rates were
based on the national economic forecasts by Planning Commission (PC), Govt of India.
The state level economic forecasts and that of Primary/Secondary sectors are based on
the regression models developed for the purpose in relation to the national level
economic information.

For the present study the past vehicle registration data for Tamil Nadu for a period of
past 10years (i.e. from Year 1993 - 2002) is considered and Regression analysis has
been carried out using vehicle registration data and economic indicators like NSDP. The
elasticity values obtained for passenger and goods vehicles are shown in Table 4.17.
The Elasticity values are reduced by 5% every five year, as there will be increase in the
total traffic and which ultimately leads to the congestion of the road.

Table 4.17: Elasticity values


Year
2005-2009 2010-2014 2015-2019 2020-2024 2025-2029
Vehicle Type
2Wheelers 2.44 2.32 2.20 2.09 1.99
Car 1.23 1.17 1.11 1.05 1.00
Bus 1.02 0.97 0.92 0.87 0.83
Auto 2.28 2.17 2.06 1.95 1.86
Commercial Vehicles 1.80 1.71 1.62 1.54 1.47
Others 1.21 1.15 1.09 1.04 0.99

4.5.2 Economic Growth Rate


The performance of the Indian economy was analysed by international funding agencies,
credit rating agencies and industries bodies in the country. The economic growth will be
in three different scenarios like Low, Medium and High.

The model adopted is based on the IRC: 108-1996 Guidelines. It has suggested relating
traffic with GDP of country. But for predicting traffic growth rates instead of using GDP,
traffic has been co-related with NSDP of Kerala as well as Tamil Nadu. Considering the
past growth in the NSDP of the both states, the economic growth remains at the rate of
minimum of 5.30% every year. Hence an economic growth rate of 5.30% is considered
for the traffic projection purpose for medium scenario. A growth rate of 5% is assumed
for low growth scenario and 6% for high growth scenario.

4.5.3 Traffic Growth Rates


Traffic growth rates necessary to estimate the traffic levels in future on the project road
are a product of economic factors of the influence area and elasticity of traffic demand.
Traffic growth rates for various categories of vehicle types were estimated based on the
economic forecasts in the influence area, the corresponding elasticity of traffic demand
and the weights of each economic zone (represented by the percentage of traffic
generation in each zone) defined earlier. Table 4.18 gives the combined Traffic Growth
Rates for Low, medium and high growth scenario.

Table 4.18 (a): Estimated traffic growth rates for Low Scenario

SECON 30 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Year 2005-2009 2010-2014 2015-2019 2020-2024 2025-2029


Vehicle Type (%) (%) (%) (%) (%)
2Wheelers 12.20 11.59 11.01 10.46 9.94
Car 6.15 5.84 5.55 5.27 5.01
Bus 5.10 4.85 4.60 4.37 4.15
Auto 11.40 10.83 10.29 9.77 9.29
Commercial Vehicles 9.00 8.55 8.12 7.72 7.33
Others 6.05 5.75 5.46 5.19 4.93

Table 4.18 (b): Estimated traffic growth rates for Medium Scenario
Year 2005-2009 2010-2014 2015-2019 2020-2024 2025-2029
Vehicle Type (%) (%) (%) (%) (%)
2Wheelers 12.93 12.29 11.67 11.09 10.53
Car 6.52 6.19 5.88 5.59 5.31
Bus 5.41 5.14 4.88 4.63 4.40
Auto 12.08 11.48 10.91 10.36 9.84
Commercial Vehicles 9.54 9.06 8.61 8.18 7.77
Others 6.41 6.09 5.79 5.50 5.22

Table 4.18 (c): Estimated traffic growth rates for High Scenario
Year 2005-2009 2010-2014 2015-2019 2020-2024 2025-2029
Vehicle Type (%) (%) (%) (%) (%)
2Wheelers 14.64 13.91 13.21 12.55 11.92
Car 7.38 7.01 6.66 6.33 6.01
Bus 6.12 5.81 5.52 5.25 4.98
Auto 13.68 13.00 12.35 11.73 11.14
Commercial Vehicles 10.80 10.26 9.75 9.26 8.80
Others 7.26 6.90 6.55 6.22 5.91

4.5.4 Traffic Forecast


Using the estimated growth rates the future traffic likely to be using the project road is
estimated. Table 4.19 shows the projected traffic volume at the two locations for
medium growth scenario.

Table 4.19: Future Projected Volume for existing Road Based on Medium Growth
rates
VC-1 VC-2 VC-3
Year
Vehicles /Day PCU / Day Vehicles / Day PCU /Day Vehicles / Day PCU /Day
2005 24323 26542 15337 13137 14008 18028
2010 37571 39127 25240 20955 22018 26922
2015 57922 57506 41172 33180 34455 39985
2020 88955 84226 66412 52053 53575 59018
2025 135822 122831 105723 80779 82616 86500
2030 206613 178830 166594 124355 126653 126242
2033 267217 225389 219552 161714 164431 159162

Apart from the above traffic projections based on the econometric method, the
projection has been done by considering the conservative traffic growth rate of 5% per
annum for all categories of vehicles. The projected traffic with 5% growth is presented in
Table 4.20 below.

Table 4.20: Projected Volume for existing Road Based on 5% growth

SECON 31 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

VC-1 VC-2 VC-3


Year Vehicles Per PCU Per Vehicles Per PCU Per Vehicles Per PCU Per
Day Day Day Day Day Day
2005 23449 25818 14593 12578 12460 16323
2010 29928 32951 18625 16053 15903 20833
2015 38196 42055 23771 20488 20297 26589
2020 48749 53674 30338 26148 25904 33935
2025 62218 68503 38720 33372 33061 43310
2030 79407 87429 49417 42593 25904 33935
2033 91924 101210 57207 49306 53853 70548

4.5.5 Traffic Forecast for Intersection


Using the estimated medium growth rates the future traffic is projected for the
intersections. Table 4.21 shows the projected traffic volume at the Intersection
locations.

Table 4.21: Projected Traffic at Intersections by Medium Growth Rates


NH-47 Thiruvananthapuram Bypass
Year Km 552/000 Km 10/300
Vehicles/ Day PCU / Day Vehicles/ Day PCU / Day
2005 2801 2738 4034 3422
2010 4473 4151 6701 5488
2015 7114 6283 11021 8735
2020 11239 9480 17904 13774
2025 17594 14232 28677 21478
2030 27354 21307 45425 33212
2033 35801 27300 60036 43303

5.0 ALIGNMENT AND ENGINEERING


5.1 Project Description

5.1.1 General
The project stretch in this package forms part of NH-47 from Thiruvananthapuram to
Kerala Border falling under NHDP Phase III. The package starts at km 552.000 of
existing NH-47 at Kazhakkoottam (Design Chainage km 0.000) and ends at Kerala
border near Ayira/Parassala at Design Chainage km 43.000.

The entire stretch comes under the administrative jurisdiction of Thiruvananthapuram


and Neyyattinkara Taluks of Thiruvananthapuram District.

5.1.2 Location and Terrain Conditions


The section of NH-47 between Thiruvananthapuram and Kanyakumari traverses from
latitude 8o 41’ N to 8o 11’ N and longitude 76o 51’ E to 77o 30’ E.

The alignment generally runs through rolling and highly undulating terrain requiring
heavy cutting and filling at several locations, especially in the new alignment portion
from km 22.600 to km 43.000.

SECON 32 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Southern railway broad gauge main line from Quilon to Kanyakumari runs on Southern
side of bypass and crosses to Northern side at Chakka (km 9.820) through a newly
constructed 2-lane ROB. There is no other railway line crossing in the package. The
ROB is proposed to be widened to six lane width.

The entire stretch of alignment runs through heavily built up areas both in existing
bypass as well as the cross country alignment portion.

5.2 Proposed Alignment

5.2.1 Proposed Alignment for existing Thiruvananthapuram Bypass (km 0.000 to km


22.600)
The project road utilises the newly formed Thiruvananthapuram bypass from 0/000 to
22/600. The available width of ROW is only 45 m and both sides are built up.
Considering the difficulty in acquiring additional land due to heavy built up area on either
side, and the social impact, NHAI has agreed to keep ROW as 45m thereby avoiding
further acquisition all along the alignment in Kerala State. A typical cross section with
ROW 45m has been incorporated with continuous service roads up to Kovalam
(22/60Km). However, in some stretches extra land acquisition is necessitated for
improvement of geometrics and junctions.

5.2.2 Proposed Alignment for beyond existing Thiruvananthapuram Bypass (km 22.600
to km 43.000)
The second phase of Thiruvananthapuram by pass starts from Kovalam (km 22.600)
and terminates at Parassala (km 599.00). But the alignment as proposed in the
reconnaissance stage follows the by pass route up to km 40.343 and thereafter deviates
and proceeds South wards towards Kerala Border. The terrain is undulating and at
km 23.900 and km 25.100, the valleys are as deep as 26 to 30m, which would require
high embankments. Besides, the alignment also passes through hillocks involving high
cuttings of 8m to 12m. The alignment cuts a number of local roads.

From km 41.200, the original proposal was to deviate from the PWD alignment and
cross Kerala – TN Border near Thirupuram (km 42.200) after crossing Poovar East
Canal (km 34.105) and Neyyar River (km 35.611).

However, the alignment of Thiruvananthapuram bypass Phase II from Kovalam to


Kaliyakkavila was approved by the Ministry of Surface Transport way back in 1989.
Knowing this, the local people who are put up in this alignment stopped construction of
new houses and started shifting from this route as a precaution. As mentioned before,
the alignment proposed earlier deviates from the original bypass alignment at
Kanjiramkulam and takes a route further west, which requires evacuation of people
already shifted from the original alignment. This has raised much hue and cry from the
public and political leaders and there is strong demand to follow the old bypass
alignment and the matter was also taken up with High court of Kerala by the local
villagers. Hence another option was studied in which the original bypass alignment will
be followed up to Ayira Village Km 40/343 and then deviate to cross the Kerala border.

Hence, the original bypass alignment will be followed from Kazhakkoottam to Ayira (km
0.000 to km 40.343) in the Kerala portion.

This alignment will have the following advantages:


• The problematic areas of Kanjiramkulam, Uranvila and Thirupuram villages can be
avoided.

SECON 33 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

• Since this is the original Alignment marked by PWD, Villagers are mentally prepared
to accept the acquisition.
• This alignment has better gradient as it crosses less number of hillocks and valleys.

However, there is a slight increase in length by 1.72 km than the first proposal. This
proposal is adopted as the final alignment for the project and chainages are referred
accordingly.

Great care has been taken while fixing the alignment to avoid major built up areas,
religious structures, tanks etc. Over and above suggestion by peoples representatives
and other public figures has been critically examined and changes effected wherever
possible without compromising geometrics of the alignment. In brief, the alignment is
feasible, economical and technically sound. Also adequate access to local public has
been provided with service roads / underpasses, pedestrian, cattle crossings, etc. The
summary of the proposed widening or new alignment details are presented in Table 5.1
below.

Table 5.1: Proposed Road Widening Schedule


Design Chainage (km) Widening Side
0.000 8.400 Right hand side widening
8.400 8.550 Concentric widening
8.550 10.750 Left hand side widening
10.750 12.300 Right hand side widening
12.300 12.500 Curve improvement on RHS
12.500 16.600 Right hand side widening
16.600 17.500 Curve improvement on RHS
17.500 22.800 Right hand side widening
22.800 43.000 New formation

5.3 Geometrics
It is observed that the existing Thiruvananthapuram bypass from km 0.000 to km 22.600
predominantly has a straight alignment and traverses through rolling terrain. The
horizontal curves in general conform to acceptable geometric standards in terms of
radius and sight distance. Super elevation/camber need to be improved in some
stretches. The existing two lane carriageway is to be widened to four lane with central
median of 4.5m, hard shoulders of 1.5m and earthen shoulders of 1.5m on either side
as per the designs given in DPR. Beyond Km 22.600 upto Kerala border the proposal
involves new construction of four-lane highway. As per the design adopted in DPR,
design speed of 100 kmph is considered for geometric designs. Minimum radius of
horizontal curves provided is 400m, maximum super elevation of 7% and maximum
gradient of 3.3% is provided.

5.4 Structure Design


1. All the culverts and bridges on the existing road are of two lanes.

2. The existing culverts are proposed to be widened to 4-lane road way width in
accordance with the cross sections of the road. Existing Medium and Minor Bridges
are proposed to be widened to 6 lane width. Newly proposed bridges also cater for 6
lane width.

3. The vent height and span length of the existing bridge are maintained in the
proposed bridges as shown in Volume IXC of this DPR.

SECON 34 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

4. Pile/Open foundation, Bank Seat abutments and circular piers are provided for the
proposed medium bridges.

5. The bank seat abutment walls are continuous in the median portion to retain earth
and for safety.

6. New Six Lane major bridge is proposed at Thamprapani river location and its details
are given in Volume IXC of this DPR.

7. Underpass/Overpass for vehicles/pedestrians have been provided in the cross roads


along the highway. The underpasses are provided with RCC box structure with
approach ramp to retain earth. The vent height for the vehicular underpass is
considered as 5m and width considered as per existing cross road width but not less
than 4.5m.

The Overpasses are provided with precast PSC girder with bank seat abutment and
approach ramp to retain earth. Minimum vertical clearance of overpass has been
considered as 5m and width of the structure considered as per existing cross road.

8. New Six Lane ROBs are provided at railway line crossings with minimum vertical
clearance of 6.525 m keeping in view Electrified Railway engines.

5.5 Design Parameters

5.5.1 Design Standards


The design conforms to the following IRC standards

i) IRC:05-1985 General Details


ii) IRC:06-2000 Loads and Stresses
iii) IRC:78-2000 Design of Substructure
iv) IRC 18-2000 Design of Prestressed Members
v) IRC 21-2000 Design of reinforced members
vi) IRC 83-2000 Design of Bearing (Part-I, II and III)
vii) IS:1893-2002 Design of Earthquake resistant structures
Viii) Railway Codal Recommendation and Practice Southern Central Railway

5.5.2 Design Loads


For the design of major structures, following Design Loads are adopted:

(a) Dead Loads (As per IRC:6)


Unit weight of PCC members : 2.4 t/m 3
Unit Weight of RCC Members : 2.5 t/m 3
Unit Weight of Wearing Coat : 2.2 t/m 3

(b) Live Loads (As per IRC:6)


For Global Analysis
One lane of Class 70R Wheel + One lane of Class A wheel

OR

Three lanes of Class A Vehicles whichever governs.


For Local Analysis, Class AA Tracked Vehicle has been considered

SECON 35 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

All the above analysis for the superstructure has been done using STAAD Pro
Software.

(c) Wind Loads, Earthquake Loads, braking loads, Temperature Effects, Water
current forces and Buoyancy forces are considered as per relevant clauses of
IRC : 6

For Earthquake Design, the structure is considered in Zone III as per IS:1893

(d) Design has been carried out using Moderate conditions of exposure as per
IRC:21

5.5.3 Materials
Foundation
Concrete Grade : M35(for major bridge/ROB/underpass/ overpass);
M30 (for minor bridge and cross drainage
structures)
Reinforcement : HYSD of grade Fe415

Abutment/Abutment Cap, Pier /Pier Cap


Concrete Grade : M35 (for major bridge/ROB/underpass/ overpass); M30
(for minor bridge and cross drainage structure)
Reinforcement : HYSD of grade Fe415

Superstructure
Concrete Grade : M40 (PSC for girder; RCC for deck slab)
M30 (RCC Girder & Deck Slab)
Reinforcement : HYSD of grade Fe415

Crash Barrier
Concrete Grade : M40
Reinforcement : HYSD steel of grade Fe415

Approach Slab
Concrete Grade : M30
Reinforcement : HYSD steel of grade Fe415

Clear Cover to any Reinforcements are followed as below:


a) Foundation : 75mm
b) Pier, Piercap, Abutment, Abutment Cap : 50mm
d) RCC Desk Slab : 25mm

5.5.4 Bearing
Neoprene bearing for slab superstructure and Pot-cum- PTFE bearing for girder
superstructure has been adopted.

5.5.5 Expansion Joints


Compression seal for slab superstructures and Elastomeric Strip Seal for girder
superstructures are used.
5.5.6 Wearing Coat
For minor bridge and cross drainage structure 50mm thick bituminous concrete wearing
coat has been proposed.

SECON 36 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

For major bridge and ROB 40mm thick bituminous concrete overlaid with 25mm thick
mastic asphalt has been proposed.
5.5.7 Approach
Earth wall Embankment shall be adopted for the approaches.
5.5.8 Structure
All the salient features of the structures are maintained as per the general arrangement
drawings accordingly.
5.6 Proposed Structures
After proposing the feasible and technically sound alignment, a detailed study was done
to provide the various cross drainage structures and other structures along the
alignment. The cross drainage structures include Major Bridges, Minor Bridges, Culverts
(Box/Pipe) etc. The other structures include Vehicular Underpass, Vehicular Overpass,
ROBs and Pedestrian Underpass etc. The lists of structures proposed along the
alignment are presented in Table 5.2 to 5.7 below. 3-lane structures are proposed on
the existing road where widening is proposed, only on the proposed widening side. But
incase of new formation structures will be 4-lane width.
Table 5.2: List of Major Bridges
Sl. Design Linear Water- Opening
Remarks
No. Chainage (km) way (m) Height (m)
1 5.923 360.78 5.22 New bridge in the widening portion
Dismantling of existing bridge and
2 16.961 112.18 13.41
Reconstruction of new bridge
3 23.800 - 21.33 New Construction
4 35.611 82.08 6.747 New Construction

Table 5.3: List of Minor Bridges


Sl. Design Linear Water- Opening
Remarks
No. Chainage (km) way (m) Height (m)
1 4.169 22.18 3.79 New bridge in the widening portion
2 12.601 7.00 2.29 New bridge in the widening portion
3 13.061 9.50 2.67 New bridge in the widening portion
4 23.680 10.03 11.40 New Construction
5 24.997 16.38 14.03 New Construction
6 27.660 16.68 5.25 New Construction
7 28.700 16.68 12.60 New Construction
8 30.318 10.38 4.46 New Construction
9 30.673 10.38 4.97 New Construction
10 34.105 10.03 5.37 New Construction
11 36.413 10.38 6.67 New Construction
12 40.497 10.03 7.57 New Construction
13 40.710 10.58 8.31 New Construction
14 41.797 10.38 5.99 New Construction
15 42.542 10.39 9.73 New Construction

Table 5.4: List of Box Culverts Proposed for Improvement or New Construction
Existing Proposed Structure
Sl.

ha

ag
o.

in

Remarks
N

C
n

Structure Details Details

SECON 37 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Total width of

Total width of
Ground Level
Structure (m)

Structure (m)
arrangement
Height From
Road Top to

Height (m)
(No x Vent
width) (m)

Opening
Span
(m)
1 11.125 7.33 2 1 X 2.5 2.0 25 Repair and Widening
2 11.378 9.4 2 1 X 2.0 2.0 25 Reconstruction
3 26.750 - - 1 X 2.5 3.5 25 New Construction
4 28.275 - - 1 X 2.5 3.5 25 New Construction
5 29.750 - - 1 X 2.5 3.5 25 New Construction
6 31.475 - - 1 X 2.5 3.5 25 New Construction
7 31.800 - - 1 X 2.5 2.0 25 New Construction
8 32.275 - - 1 X 2.0 2.0 25 New Construction
9 33.000 - - 1 X 2.0 3.5 25 New Construction
10 33.150 - - 1 X 2.5 2.0 25 New Construction
11 33.950 - - 1 X 2.0 2.0 25 New Construction
12 34.300 - - 1 X 2.5 2.0 25 New Construction
13 34.725 - - 1 X 2.0 3.5 25 New Construction
14 34.800 - - 1 X 2.0 3.5 25 New Construction
15 35.860 - - 1 X 2.5 3.5 25 New Construction
16 36.675 - - 1 X 2.0 3.5 25 New Construction
17 36.950 - - 1 X 3.0 3.5 25 New Construction
18 37.250 - - 1 X 2.5 2.0 25 New Construction
19 37.550 - - 1 X 2.0 2.0 25 New Construction
20 38.125 - - 1 X 2.0 2.0 25 New Construction
21 38.400 - - 1 X 2.0 2.0 25 New Construction
22 39.180 - - 1 X 2.0 2.0 25 New Construction
23 39.575 - - 1 X 2.0 2.0 25 New Construction
24 39.800 - - 1 X 2.0 3.5 25 New Construction
25 41.050 - - 1 X 2.5 3.5 25 New Construction
26 41.390 - - 1 X 4.0 3.5 25 New Construction
27 41.575 - - 1 X 2.5 3.5 25 New Construction

Table 5.5: List of Pipe Culverts Proposed for Improvement or New Construction
Existing Structure Proposed Structure
Chainage (km)

Details Details
Height From
Road Top to

Culverts (m)
Design

Diameter of
Sl. No.

Total width
of Culverts

Height (m)
Proposed
Level (m)

Opening
Ground

No And

Remarks
(m)

1 0.400 38 2.0 2 X 1.2 1.20 Reconstruction

SECON 38 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Existing Structure Proposed Structure

Chainage (km)
Details Details

Height From

Culverts (m)
Road Top to
Design

Diameter of
Sl. No.

Total width
of Culverts

Height (m)
Proposed
Level (m)

Opening
Ground

No And
Remarks

(m)
2 4.837 27.5 2.0 2 X 1.0 1.00 Reconstruction
3 6.303 22.5 2.7 2 X 1.0 1.00 Repair and Widening
4 6.473 30 2.4 1 X 1.0 1.00 Repair and Widening
5 6.620 17.5 2.3 1 X 1.0 1.00 Repair and Widening
6 6.822 22.5 2.0 2 X 1.0 1.00 Repair and Widening
7 6.930 25 2.0 1 X 1.0 1.00 Repair and Widening
8 7.070 13.75 2.0 1 X 1.0 1.00 Repair and Widening
9 7.310 18.75 2.0 2 X 1.0 1.00 Repair and Widening
10 7.574 17.5 2.0 1 X 1.0 1.00 Repair and Widening
11 7.717 17.5 2.4 2 X 1.0 1.00 Repair and Widening
12 8.074 17.5 2.1 2 X 1.0 1.00 Repair and Widening
13 8.188 17.5 2.0 1 X 1.0 1.00 Repair and Widening
14 8.278 17.5 2.5 2 X 1.0 1.00 Repair and Widening
15 8.362 17.75 2.0 2 X 1.2 1.20 Reconstruction
16 8.540 17.5 2.0 1 X 1.0 1.00 Repair and Widening
17 8.642 17.5 2.1 2 X 1.0 1.00 Repair and Widening
18 8.739 18.75 2.2 2 X 1.0 1.00 Repair and Widening
19 8.914 17.5 2.0 2 X 1.0 1.00 Repair and Widening
20 9.060 22.5 2.0 2 X 1.0 1.00 Repair and Widening
21 9.175 27.67 2.0 2 X 1.2 1.20 Reconstruction
22 9.263 25 3.3 2 X 1.0 1.00 Repair and Widening
23 9.405 27.5 5.0 2 X 1.0 1.00 Repair and Widening
24 9.580 35 7.7 2 X 1.0 1.00 Repair and Widening
25 9.698 48.75 10.3 2 X 1.2 1.20 Repair and Widening
26 9.982 48.75 3.4 2 X 1.0 1.00 Repair and Widening
27 10.146 50 10.4 1 X 1.0 1.00 Repair and Widening
28 10.551 34.935 5.9 2 X 1.2 1.20 Reconstruction
29 10.592 23.35 4.8 2 X 1.2 1.20 Reconstruction
30 10.621 22.8 4.4 2 X 1.2 1.20 Reconstruction
31 10.733 22.91 3.5 2 X 1.2 1.20 Reconstruction
32 11.042 12.96 2.5 2 X 1.2 1.20 Reconstruction
33 11.914 8 2.0 1 X 1.0 1.00 Repair and Widening
34 12.296 8 2.0 1 X 1.0 1.00 Repair and Widening
35 12.442 8 2.0 2 X 1.0 1.00 Repair and Widening
36 12.502 45 2.0 2 X 1.0 1.00 Repair and Widening
37 12.662 26.92 1.24 1 X 1.0 1.00 Repair and Widening
38 12.890 8 2.0 1 X 1.0 1.00 Repair and Widening
39 13.178 16.25 2.0 1 X 1.0 1.00 Repair and Widening
40 13.347 17.5 2.0 1 X 1.0 1.00 Repair and Widening
41 13.465 17.5 2.0 1 X 1.0 1.00 Repair and Widening
42 13.953 32.5 2.0 1 X 1.0 1.00 Repair and Widening
43 14.354 16.25 2.0 1 X 1.0 1.00 Repair and Widening
44 16.205 8 2.9 2 X 1.0 1.00 Repair and Widening
45 16.338 17.5 2.0 2 X 1.0 1.00 Repair and Widening
46 17.244 23.75 4.1 2 X 1.0 1.00 Repair and Widening

SECON 39 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Existing Structure Proposed Structure

Chainage (km)
Details Details

Height From

Culverts (m)
Road Top to
Design

Diameter of
Sl. No.

Total width
of Culverts

Height (m)
Proposed
Level (m)

Opening
Ground

No And
Remarks

(m)
47 17.345 23.75 3.8 1 X 1.0 1.00 Repair and Widening
48 17.479 22.5 2.0 1 X 1.0 1.00 Repair and Widening
49 17.619 21.25 2.0 1 X 1.0 1.00 Repair and Widening
50 17.948 21.25 2.0 2 X 1.0 1.00 Repair and Widening
51 18.053 22.5 2.6 1 X 1.0 1.00 Repair and Widening
52 18.279 23.75 2.8 2 X 1.0 1.00 Repair and Widening
53 18.580 22.5 2.0 2 X 1.0 1.00 Repair and Widening
54 18.865 21.25 2.1 1 X 1.0 1.00 Repair and Widening
55 19.031 20 2.4 1 X 1.0 1.00 Repair and Widening
56 19.218 21.25 2.3 2 X 1.0 1.00 Repair and Widening
57 19.348 18.75 2.2 2 X 1.0 1.00 Repair and Widening
58 19.521 22.5 2.0 1 X 1.0 1.00 Repair and Widening
59 19.637 21.25 2.2 1 X 1.0 1.00 Repair and Widening
60 19.778 21.25 2.0 1 X 1.0 1.00 Repair and Widening
61 20.068 20 2.4 1 X 1.0 1.00 Repair and Widening
62 20.206 18.75 2.0 1 X 1.0 1.00 Repair and Widening
63 20.364 21.25 2.2 2 X 1.0 1.00 Repair and Widening
64 20.791 28.75 2.0 2 X 1.0 1.00 Repair and Widening
65 20.846 8 2.2 1 X 1.0 1.00 Repair and Widening
66 21.452 32.5 2.0 1 X 1.0 1.00 Repair and Widening
67 21.576 8 4.6 2 X 1.0 1.00 Repair and Widening
68 21.768 8 4.2 2 X 1.0 1.00 Repair and Widening
69 22.925 - - 2 X 1.2 1.20 New Construction
70 23.025 - - 2 X 1.2 1.20 New Construction
71 23.450 - - 2 X 1.2 1.20 New Construction
72 25.250 - - 2 X 1.2 1.20 New Construction
73 26.350 - - 2 X 1.2 1.20 New Construction
74 27.825 - - 2 X 1.2 1.20 New Construction
75 28.000 - - 2 X 1.2 1.20 New Construction
76 28.456 - - 2 X 1.2 1.20 New Construction
77 28.800 - - 2 X 1.2 1.20 New Construction
78 28.900 - - 2 X 1.2 1.20 New Construction
79 28.975 - - 2 X 1.2 1.20 New Construction
80 29.100 - - 2 X 1.2 1.20 New Construction
81 29.200 - - 2 X 1.2 1.20 New Construction
82 29.400 - - 2 X 1.2 1.20 New Construction
83 29.800 - - 2 X 1.2 1.20 New Construction
84 30.400 - - 2 X 1.2 1.20 New Construction
85 30.600 - - 2 X 1.2 1.20 New Construction
86 31.650 - - 2 X 1.2 1.20 New Construction
87 35.200 - - 2 X 1.2 1.20 New Construction
88 35.275 - - 2 X 1.2 1.20 New Construction
89 35.475 - - 2 X 1.2 1.20 New Construction
90 36.110 - - 2 X 1.2 1.20 New Construction
91 36.500 - - 2 X 1.2 1.20 New Construction

SECON 40 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Existing Structure Proposed Structure

Chainage (km)
Details Details

Height From

Culverts (m)
Road Top to
Design

Diameter of
Sl. No.

Total width
of Culverts

Height (m)
Proposed
Level (m)

Opening
Ground

No And
Remarks

(m)
92 37.400 - - 2 X 1.2 1.20 New Construction
93 37.680 - - 2 X 1.2 1.20 New Construction
94 37.775 - - 2 X 1.2 1.20 New Construction
95 38.200 - - 2 X 1.2 1.20 New Construction
96 38.500 - - 2 X 1.2 1.20 New Construction
97 38.575 - - 2 X 1.2 1.20 New Construction
98 39.325 - - 2 X 1.2 1.20 New Construction
99 41.950 - - 2 X 1.2 1.20 New Construction
100 42.250 - - 2 X 1.2 1.20 New Construction
101 42.436 - - 2 X 1.2 1.20 New Construction

Table 5.6: Details of Underpasses/Overpasses


Design Proposed Clear
Sl. Proposed
Chainage size of in Opening Remarks
No Structure
(km) (m) Height in (m)
Vehicular 2 x 9.25 x Tirvandram - Vallakkadavu
1 10.285 5.750
Underpass 6.75 Road
Vehicular
2 24.542 1 x 41.62 6.065 Venganur - Vizhinjim Road
Overpass
Vehicular Balrampuram - Mukkola
3 25.878 1 x 41.62 6.119
Overpass Junction
Vehicular
4 26.534 7.5 x 6.0 5.000 Kottukal - Nettattanni Road
Underpass
Vehicular Punnakkulam - Chappathu
5 28.532 8.0 x 6.0 5.000
Underpass Road
Vehicular Marapalam - Marapalam
6 29.578 1 x 41.62 6.620
Overpass Junction
Vehicular
7 30.482 7.5 x 6.0 5.000 Homeo- Kazhivur Road
Underpass
Vehicular
8 36.037 7.5 x 6.1 5.000 Local Road
Underpass
Vehicular Pazhayakoda -
9 39.060 7.5 x 6.0 5.000
Underpass Prumuttukadu Road
Vehicular
10 40.350 1 x 41.62 8.557 Kottukomam - Pottailkada
Overpass
Vehicular
11 42.920 1 x 41.62 7.010 Kaduvakuzhi - Chenkavila
Overpass

SECON 41 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Table 5.7: Details of Proposed ROB


Proposed Span Opening
Sl. Total width of
Chainage Arrangement Height Remarks
No. Superstructure (m)
(km) (m) (m)
13.75m Total Width with
6.525 New bridge in the
1 09.820 1 x 34.9 11.0m Carriage way and
(min) widening portion
1.5m Footpath on one side

6.0 SUBGRADE INVESTIGATION FOR PAVEMENT


6.1 General
The Sub-grade soil samples were collected for testing its characteristics by collecting
representative samples along the road for the proposed new alignment and existing
road where it is used for widening followed by an extensive trial pitting with additional
tests.

6.2 Test Pitting


Test pits were excavated along the proposed alignment as well as at the edge of the
existing road where the existing road is being utilized for the widening. Along the
existing alignment, edge pits at 500-750m intervals were excavated in the hard
shoulders at the edge of the existing pavement depending upon the side of widening
envisaged (Left/Right). Centre pits were excavated on widening portion of existing NH at
km 4/700 and km 12/500. For the new alignment, trial pits were excavated at intervals of
1.5 to 2 km generally.

6.3 Additional tests


This was supplemented by in-situ evaluation of Sub-grade using ‘’field density tests’’/
DCPT (Dynamic Cone Penetration Test apparatus). Based on field DCPT values
recorded, field CBR was calculated using the TRRL formula. Pavement & sub-grade
investigation report with relevant details are furnished separately. It is to be noted that
CBR values deduced thereof using the formula are merely representative of subgrade
conditions at the time of investigations.

6.4 Laboratory testing programme


The following laboratory tests were performed on representative samples from test pits to
evaluate characteristics of sub-grade soil.
• Grain size analysis - Wet Sieve analysis and Hydrometer analysis
• Atterberg’s limits - Liquid Limit, Plastic Limit and Plasticity Index
• Field Moisture Content, Field Bulk and Dry Density by Core Cutter method
• Modified Proctor Compaction Test
• Preparation of samples at 97% MDD for conducting un-soaked and 4 days soaked CBR
tests - single trial and three trials.
• Estimating absorbed moisture content after soaking on representative CBR samples.

6.5 Planning and Implementation of Test Programme


Typical samples collected from the sites (widening, proposed & few center pits) were
tested for the package. Initially, extensive visual classification was carried out and tests
were planned accordingly. Lab tests conducted include grain size and hydrometer
analysis, Atterberg’s limits, Modified Proctor Compaction and CBR tests (both unsoaked
and 4 day soaked CBR). For few samples, three trial CBR tests were also carried out. It
is observed that soil for almost entire package is more or less similar.

SECON 42 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

6.6 Implications for pavement designs


Based on extensive CBR tests that included few three trial CBR tests also, a soaked
CBR of 8% is suggested for design purposes.

Based on lab tests, it was observed that soil along the entire package I is ‘interstratified’ &
comprises of silts, sands & clays in various proportions with randomly interspersed gravel.
Clay is present as an interstitial binder. Wherever localized stretches of clayey sand were
noticed, it is inferred that soil is non-swelling and is of intermediate plasticity. Based on CBR
test results, a soaked CBR value of 8% is suggested for design purposes.

7.0 ENVIRONMENTAL IMPACT ASSESSMENT AND MANAGEMENT PLAN


7.1 Project Area
This report is Project Specific and covers the environmental issues within ROW, though
their impacts have been assessed up to the aerial distance of 10 km on both sides of
road. The project is divided into two packages and the present study deals with
Package I (starting from km 00.000 to km 43.000 along NH 47) in Kerala.

7.2 Objectives
The objectives of the EIA include:

• Collection of baseline data on various components of the environment.


• Determination of magnitude of environmental impacts so that due consideration is
given to them during planning, construction and operational phases of the project.
• Assessment of the socio-economic conditions of the project affected persons and
suggestions for their improvement.
• Identification of areas and aspects, which are environmentally or socio-economically
significant.
• Submission of Environmental Enhancement Plan and Environmental Management
Plans for enhancing and mitigating the negative impacts.
• Development of the road alignment in such a way that the environment and
settlements are least affected.
• Presentation of public view on various environmental and socio-economic aspects.

7.3 Major Negative Impacts and their Mitigation


The major direct environmental impacts and their mitigation measures are required to be
implemented, given inn Table 7.1 below:

Table 7.1: Negative Impacts and their Mitigation Measures


Negative Impacts Mitigation Measures
• Two trees to be planted in place of one
removed, ensuring their survival rate.
Loss of trees • Stretches which are devoid of trees at
present, will be developed by planting
trees.
• Providing relocation sites.
• Giving compensation/assistance.
Loss of properties
• Attempts to generate income
restoration.
• Since the impact is of low scale, loss
Loss of surface water sources will be compensated by other water
bodies.

SECON 43 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

• Plantation of trees, especially those


which are known as pollution sink near
Ambient Air/Noise Quality
market place.
• Improving the maintenance of vehicles.
• The new sites of relocation will be
Relocation of religious structures
properly developed.

7.4 Significant Findings


Based upon the study and analysis of the environmental parameters, the following
important observations have been made:

• There will be no loss of bio-diversity as no rare endangered plant or animal species


is going to be affected by the present project.
• There is no major wildlife migrant route within the study area, which could be
affected.
• No Sanctuary or National Park is located within 10 km radius of the road.
• The two most significant issues involved are (i) cutting of trees in the corridor of the
highway, and (ii) acquisition of land.
• No historical monument protected by Archaeological Survey of India (ASI) is
affected due to proposed widening.
• Soil along the proposed road is red in colour.
• The most important factors, which need continuous attention and assessment during
the construction phase, are the ambient air quality, the water quality and the noise
level.
- The ambient air quality of the study area is good except SPM/RPM, which
exceeds the permissible limits near intersections.
- The quality of the ground water is good for drinking as well as other household
purpose.
- Noise levels in the area particularly at crossing points of road exceed the limits
due to heavy vehicular movement.

• The proposed alignment of the road is such that built-up areas are least affected.
Based upon this criteria and social screening analysis, hot spots have been
identified and represented as under:-

Table 7.2: ‘Hot Spots’ identified during Environmental / Social Screening Analysis
Sl. Design
Remarks
No Chainage ( km)
1 5.900 Akulum lake
2 6.950-7.000 Killiyar River
3 22.000 Pond
4 22.600 Kovalam junction, dense population and commercial
plantation.
5 26.000 to 28.000, Coconut plantation, scattered built-up area.
29.550 – 30.000,
30.000 – 35.000
6 35.000 – 40.000 Coconut Plantation and Rubber Estate, Neyyar River at
35.600 KM (Proposed)
7 40.000 – 42.958 Silver Oak plantation between km 40.000 – km 40.200,
coconut plantation, rubber estate.

The Environmental Management Plan (EMP) is prepared for avoidance, mitigation and
management of the negative impacts of the project. It also covers remedial measures
required to be taken for hot spots. EMP includes the list of all the project related

SECON 44 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

activities, their chainage wise impacts at different stages of project i.e., during pre-
construction phase / design phase, construction phase and operational phase on
environment and remedial measures to be undertaken to mitigate these impacts.

The Environmental Monitoring Programs are suggested to provide information on which


management decisions may be taken during construction and operational phase. The
objectives of these programs are:

• To evaluate the efficiency of mitigation and enhancement measures.


• Updating the actions & impacts of baseline data and adaptation of additional
mitigation measures (if the present measures are insufficient).
• Generation of the data that may be incorporated in the EMP in future projects.

7.5 Cost of Environmental Management Plan


The estimated cost for EMP for Package I is Rs. 35,607,000.

A detailed volume describing the Environment Management Plan and Monitoring


Programs has been prepared and furnished separately along with the DPR.

8.0 RESETTLEMENT ACTION PLAN


8.1 Description of Project
The existing NH 47 from Thiruvananthapuram to Kanyakumari is 2-Lane carriageway
and presently the traffic on this road is much more than the capacity. Most of the road
length has continuous built-up area very close to the road. The existing NH 47B from
Nagercoil to Kavalkinaru is also 2-Lane carriageway. Geometrics of both the road
sections are not up to the standards as per IRC for National Highways.

In order to decongest the existing NH 47 within Thiruvananthapuram city, bypass for a


length of 22.6km has already been constructed. Beyond the city limits, widening of the
existing NH was investigated in detail, but ruled out due to large scale demolition
involved. Hence, it was decided to adopt a new alignment for about 95% of road length
except existing Thiruvananthapuram Bypass.

The project road starts at Kazhakkottam, about 10 km North of Thiruvananthapuram city,


on existing NH 47 (km 552/00) which is reckoned as km 00/000 for the project. The road
further continues on the existing Thiruvananthapuram Bypass up to km 22/600 and
traverses through cross country crossing Kerala/Tamilnadu Border at Karode village at
design Chainage of km 43/000. It is aligned cross country in Tamilnadu state and rejoins
the existing NH 47 at km 626/187 (existing chainage) and again deviates at 627/000
(existing chainage) bypassing Chungankadai, Nagercoil and Suchindram rejoining the
existing NH 47 at km 642/800. From km 642/800 it follows the existing road up to km
646/238 and deviates on RHS for bypassing Kottaram built-up area and joins NH 7 at
Kanyakumari Bypass (km 231/653 of NH7).

NH 47B from Nagercoil to Kavalkinaru where it joins NH 7 has been provided with a new
alignment except for an initial length of 600m. It starts near the junction of Nagercoil
Bypass (km 82/181 of NH 47) and existing NH 47B.

M/s. SECON Pvt. Ltd has been entrusted for preparation of Detailed Project Report for
both stretches as a combined project

The report is Project Specific and covers the Resettlement Action Plan for the affected
people along the proposed ROW.

SECON 45 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

The project is divided into two packages. Package I pertains to the road stretch falling in
Kerala State and Package II for Tamil Nadu area. This report is pertaining to Package I
i.e. from Thiruvananthapuram to Karode (Kerala/Tamilnadu Border).

8.2 Objectives
The resettlement plan has been prepared keeping the following broad objectives:-

• The negative impact on persons affected by the project would be avoided or


minimized.
• Affected people and the beneficiary population will be informed and consulted about
the project and its design where the negative impacts are unavoidable.
• The Project-Affected Persons (PAPs) will be assisted in improving or regaining their
standard of living.
• People’s Opinion will be considered in planning and implementation of the project.
• All information related to resettlement plan and implementation will be disclosed to
PAP’s.

8.3 Socio Economic and Census Surveys


A survey was conducted to identify the socio economic status of the population along
the proposed new alignment of Package-I.

The aim of the survey is to establish the impact of the proposed project, number of
project-affected persons, type of perceived impacts, people’s concern, ways of
mitigation, socioeconomic scenario of the area and the basic situation analysis. It also
helped in establishing the types of affected persons and types of loss.

Titled structure owners falling within the proposed corridor were captured in the survey.
Structures partly or wholly within the corridor were surveyed. Social strip mapping
involved capturing all structures and constructions partly or wholly within the ROW. This
helped in discussing alignments with people and design team.

Sample socio-economic survey was conducted in the area traversed by the project to
understand the conditions of the people. This helped in establishing the monitoring
parameters, which would be used to study the project impact on the socio-economic
conditions of the people.

8.4 Project Affected Persons (PAPs)


The following section elaborates the type of losses that the people either residing or
working on the National Highway would incur by way of the loss of land (agricultural,
commercial and residential), loss of structures (commercial and residential), loss of
assets (agricultural, commercial and residential), loss of income (squatters, small
business enterprise and moving businesses such as kiosks) and community resources.
A total of 3657 Project Affected Families (PAFs) and 18285 Project Affected Persons
(along Package-I) have been identified. Out of this 3143 Project Affected Families are
going to lose their agriculture land, while the people loosing structural property are 506.
About 08 structures belonging to Small and cottage industries along the ROW are also
going to be affected; however there are no major industries falling along the alignment
in Package-I. The projected affected families & persons are presented in Table 8.1.

SECON 46 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Table 8.1: PAFs & PAPs in Terms of Project Impact


Type of Loss No. of PAFs No. of PAPs
Agricultural land 3143 15715
Structures - Residential and Commercial 506 2530
Structures – Industrial 08 40
Total 3657 18285

8.5 Category of Project Affected Families


Usually the families will be of two types i.e. nuclear and joint or extended. The type of
family will also have an impact on the resettlement of the PAFs. The average size of
each family in the project area is 5 members. For impact assessment, entitlement and
other analysis family is taken as a unit. The details of PAFs are presented in Table 8.2.

Table 8.2: Category of PAFs in Terms of Project Impacts


Category No. of PAFs
Land 3143
Structures 506
Squatters and Encroachers 13
Tenants 9
Kiosk 6
Total 3677

According to the census data structure owners (506 nos.) form the second largest group
of the affected persons apart from agricultural landowners (3143 nos.). The
encroachers are the residential and commercial structure owners who have extended
their structures close to the edge of the road in the project area.

Apart from the families losing agricultural land and structures (residential, residential-
cum- commercial, commercial), 13 nos. of squatters & encroachers and 09 nos. of
tenants are going to be affected along the proposed alignment. The encroachers are
those who have extended their property line onto govt. land; and therefore have been
categorized as non-titleholders. It is only the portion of the property on the Govt. land,
which is getting affected.

8.6 Affected Structures By type


Type of structures also indicates about the economic conditions of the residents. Out of
the total 506 structures (excluding religious and Govt.), 292 are permanent, 100
structures are semi-permanent and 114 are temporary in nature. The details are
presented in the Table 8.3 below.

Table 8.3: Details of Structures


Type Number of Structures
Permanent/Pucca 292
Semi Permanent/Semi Pucca 100
Temporary/Kuchha 114
Total 506

8.7 Loss of Land (Private and Government)


The project authorities will acquire agricultural land, dry lands and other land in different
sections of the project area. Existing Right of Way (ROW) of the existing NH47 is
varying between 12 to 24 m as per the PWD boundary stones and village land maps.

SECON 47 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Since the proposed road is new alignment along the existing Thiruvananthapuram
bypass, the existing ROW for length of 22.6km is 45m. Further the land has been
acquired for another 3.28 km upto Mukkola (km 25/880) for a width of 45m. Beyond
Mukkola fresh land acquisition will be required for the proposed alignment portion upto
km 43/000. However, it may be noted that the Kerala PWD is in the process of acquiring
land along their proposed extension of the Thiruvananthapuram Bypass upto
Neyyattinkara.

Private land acquisition is more compared to the government land acquisition. The
private land to be acquired is mostly agricultural land followed by Dry land. The details
of land acquisition within proposed ROW is presented in Table 8.4 below.

Table 8.4: Land Acquisition within Project ROW


Total area in
Category of Land
sqm Acres-cent
Private Dry land 864290 213-56.99
Private Wet Land 30527 7-54.34
Government Land 64647 15-97.46
TOTAL 959464 237-08.78

The owners of the landholdings to be acquired may have other source of income; but it
is likely that this acquisition would cause partial loss of income for these families. The
replacement cost/compensation will be paid as per the entitlement matrix by the
competent authority.
8.8 Community Infrastructure and Assets
Apart from the demolition of private residential and commercial buildings as described
above, some govt. buildings, bridges, culverts, service roads, bore wells and wells,
tombs and small temples, police station, bus stops, Clinics, cattle sheds etc. will also be
lost. These lost public structures will be replaced, prior to their actual demolition at new
sites. Further, NGO will continue the dialogue with Panchayat officials and will procure
No Objection Certificate. Details of community structures such as temples, shrines etc
and government Structure are shown in the Table 8.5 below

Table 8.5: Details of Community Structures, Assets and Religious structures


Type of Structure Number of Structures
Community Structures 13
Religious Structures 30

8.9 Resettlement Principles


The Resettlement Policy of National Policy for Resettlement and Rehabilitation (NPRR),
2003 and NHAI have been consulted and compared to prepare the Resettlement
Principles (RP) for the project. The entitlement policy recognizes all types of affected
persons such as squatters, encroachers, titleholders, kiosks etc. Squatters who are
present prior to survey are considered for R & R assistance. They will be paid
replacement cost of structures, and ex-gratia. The titleholders of structure losers will be
paid replacement cost of structure including homestead land and cost of trees. The land
losers will be paid replacement costs of land lost and ex-gratia as per the entitlement
matrix. All incidental costs will be borne by the project. The project will rebuild the
community utilities and infrastructures if any, which is to be dismantled.

8.10 Consultation and Disclosures


A number of public consultations were held with various sections of the project-affected
population such as farmers, traders, women, village elders, panchayat members and
other inhabitants etc. People in general agreed on the need for alternative or

SECON 48 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

upgradation/widening the highway and strengthening the same. The process of


information was highly appreciated by the local inhabitants. During public consultation,
issues related to safety, compensation, income restoration, employment generation,
HIV/AIDS, trafficking of women, information flow, grievance redressal, role of
administration etc. were discussed. Issues were also raised about the transparency in
the project implementation process. The RP for core sub-project addresses all issues
raised during public consultation and recommends institutional strengthening measures
as well.

8.11 Institutional Mechanism and Grievance Redressal


The RP for core subproject strongly recommends all efforts shall be made to settle
grievances of the PAPs as amicably as possible. Out of court settlement shall be
preferred since that expedites dispute settlement on one hand and help timely project
implementation on the other hand. Grievance Redressal Committees will be set up at
district level to resolve the concerns of the PAPs. Thorough investigations shall be done
so that PAPs are satisfied.

The NHAI will establish an R & R Cell under the Project Implementation Unit (PIU). The
project Director will head the R & R Cell (PIU), who will be supported by Resettlement
and Rehabilitation officer. The NHAI will engage experienced NGOs for implementation
of RP activities and to coordinate with other departments, which are stakeholders in the
project. The NGOs will also be involved to organize and conduct training programs,
awareness campaigns, verification of PAFs and their assets, help in settling the disputes
etc. The PIU-R & R Cell will be assisted by committees at district level in resolving
issues of disputes and in implementing the Resettlement Plan.

8.12 Total Cost of Rehabilitation and Resettlement


The total cost of rehabilitation and resettlement is calculated based on the above heads.
The total cost of rehabilitation and resettlement are presented in Table 8.6 below.

Table 8.6: Total Costs of Rehabilitation and Resettlement


Sl. Total Value in
Type of Compensation
No. Rs
1 Land Acquisition Cost 154,777,000.00
2 Replacement Cost of Structures 57,116,002.00
3 Replacement cost of Community Structures 1,950,000.00
4 Replacement cost of religious Structures 6,000,000.00
5 Improvement of Community Structures 1,250,000.00
6 Compensation for Squatters, Encroachers, 342,000.00
Kiosks, etc.
7 Ex-gratia 36,770,000.00
Total 258,205,002.00

8.13 Monitoring and Evaluation


Monitoring will be continuous throughout the implementation of the RP. An external M &
E agency will be hired by NHAI to monitor the implementation of RP. The PIU will submit
periodic monthly progress reports to the NHAI HQ. Monitoring will be carried out for a
period of three years from the date of implementation of the RP. The project will be
evaluated from time to time from both internal and external mechanism.

SECON 49 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

9.0 COST ESTIMATES


9.1 Project Road Packages
After thorough study of project road with reference to improvements required, location of
major bridges, ROBs, homogeneity of section, workability, geographical boundaries of
two States etc. the project road has been divided into two packages as mentioned in
Table 9.1 below:

Table 9.1: Details of Packages


Sl. Tentative Location of
Package State NH No. Reach
No. CMP/ Batching Plant
km 0.000 to km
1 I Kerala NH 47 km 21.000 on NH 47
43.000
NH 47 km 43.000 to km
96.714
2 II Tamilnadu km 70.800 on NH 47
km 0.000 to km
NH 47B
16.376

This report pertains to Package-I from km 00.000 to 43.000 of NH 47 of Kerala.

9.2 Unit Rate Analysis


Unit rates have been adopted for the items of the project based on the concerned
National Highways Schedule of rates for kerala circle, State PWD Scheduled of Rates
and latest data approved by MoSRT&H.

The Mixing Plant location has been fixed at km 21.00 and rates have been worked out
based on Plant location. The data for unit rates for the construction materials not
contemplated in the MoSRT&H revised data book or in the NH schedule of rates or
PWD schedule of rates, are worked out based on local enquiries / market rates or
through quotations.

9.3 Materials

9.3.1 Stone Metals


There is no metal quarry in and around Thiruvananthapuram city, adjacent to the project
stretch. Therefore stone aggregates are to be brought from near by Tamil Nadu State.
For this reach, quarries have been identified in Tayyalumudu and Nerrakkadu quary in
Tamil Nadu near Kerala border with a lead of 29km.

9.3.2 Sand
Sand quarrying is banned in Thiruvananthapuram District of Kerala except at Papson
Quarry located at 16km north of Thiruvananthapuram city towards Ernakulam. Also
sand can be transported from the only quarry in Seevalapperi village of Tirunelveli
District with a lead of 160km.

9.3.3 Gravel
It is proposed to bring gravel from Vattappara quarry with an average lead of 34km.

9.3.4 Earth Works


The project road alignment is running on rolling terrain. It involves cutting and filling in
number of locations. 75% of the cutting quantities can be reused for filling with

SECON 50 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

acceptance quality and as directed by the Engineer. The remaining earth can be
obtained from borrow areas with a lead of 5km.

9.3.5 Cement
Market rates prevailing in Kerala have been adopted in the project road.

9.3.6 Steel
Market rates prevailing in Kerala has been adopted.

As the project road runs in coastal area from beginning to end and the structures are
subject to severe corrosion, it is proposed to provide anti corrosive coating to all the
steel used in RCC structures. Only High Corrosion Resistance Material Steel
reinforcement shall be used for all the structures.

9.3.7 Bitumen
Rates for various grades of Bitumen including emulsions have been obtained from
Kochi Refinaries Ltd, and IOCL chennai.

9.3.8 Labour
Rates for all skilled and unskilled labour are based on NH schedule of rates.

9.3.9 User charges for machineries


Rate of hire charges of modern machineries and plants for road and bridge works are
based on the NH schedule of rates as per latest MoSRT&H guidelines.

9.3.10 Rates for RE Wall and Soil Nailing


For high embankments rate of RE wall is adopted as per rate analysis.

In high cut portions Soil Nailing is proposed and the rates upto 8m height, upto 12m
height and upto 16m height are analysed. The rates are analysed based on the services
provided by specialized and approved contractors.

9.3.11 Unit Rate Analysis


Unit rate analysis for various items of work for the road and bridge works have been
done as per MoSRT&H Data Book based on the rates for material, labour and hire
charges for machinery, giving allowance for Contractor’s profit and overheads.

9.4 Unit Cost

9.4.1 Estimation of quantities for Road work


Typical cross sections have been prepared for the following types of widening:

1. Concentric widening of existing two lane road to four lane with central median,
paved and earthen shoulders service roads, drains etc.

2. One side widening of the existing two lane to four lane width with paved and
earthen shoulders with a provision of open drain in between main carriageway
and service roads.

SECON 51 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

3. Construction of new four lane divided carriageway with paved and earthen
shoulders on either side with service roads at identified locations.

Embankments have been provided with a relative compaction of not less than 95% of
Dry density. A minimum sub-grade of 500mm thick of good materials from borrow areas
with a relative compaction of not less than 98% of dry density has been provided over
the compacted embankment.

The GSB layer having LL and PI value of not more than 25 and 6 respectively have
been proposed over the entire formation width of sub-grade to facilitate drainage. A
base course of WMM is provided over the GSB.

It is proposed to provide Pavement Quality Concrete (PQC) for the entire Toll lay out
zone with M 40 grade supported by dry lean concrete of M15.

Pavement design for new alignment and service road has been done and the
compositions of various layers are provided in Table 9.2 and 9.3 below:

Table 9.2: Pavement Layer Thickness for Main Carriageway


Sl.
Type of Layer Layer Thickness (mm)
No.
1 Bituminous Concrete (BC) 40
2 Dense Bituminous Macadam (DBM) 85
3 Wet-Mix Macadam (WMM) 250
4 Granular Sub-Base (GSB) 200
Total 575

Table 9.3: Pavement Layer Thickness for Service Road


Sl.
Type of Layer Layer Thickness (mm)
No.
1 Semi-Dense Bituminous Concrete (SDBC) 25
2 Dense Bituminous Macadam (DBM) 50
3 Wet-Mix Macadam (WMM) 250
4 Granular Sub-Base (GSB) 150
Total 475

Design of overlay has been done for strengthening of the existing pavement wherever
the existing road is being utilized, Pavement Composition for overlay for the existing
Thiruvananthapuram bypass for length of 22.6km it is proposed to provide 85mm DBM
and 40mm BC as overlay for strengthening the existing pavement.

9.4.2 Estimation of Quantities for Structures


For the proposed alignment various structures have been proposed. The estimates
have been worked out for 4 Major Bridges, 15 Minor Bridges, 1 ROB, 27 Box Culverts,
101 Pipe Culverts, 6 Vehicular Underpasses and 5 Vehicular Overpass. The details of
proposed structures are given in Chapter 5.

9.4.3 Junction Improvements


The project road crosses number of roads and there are 07 major junctions and 08
minor junctions in the package.

SECON 52 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

For improving these major and minor junctions, the cost estimate has been worked out
based on the typical design of junctions.

9.4.4 Miscellaneous Provisions


The following miscellaneous/provisional items are provided based on the site conditions.
a. Shifting of utilities
b. Tree planting
c. Social settlement and Environment Management Plan
d. Dismantling of structure and cutting of trees
e. Rehabilitation of bridges
f. Repair and maintenance of road
g. Turfing
h. Road furniture
i. Rest area and truck parking
j. Telephone booth
k. Providing diversions during construction
l. Toll plaza
m. Bus shelter
n. KM / HM boundary stone
o. Revetment with granular backing
p. Filling of Wells
q. Fencing
r. Rainwater harvesting in built up area
s. Stone pitching on high embankment slope

9.4.5 Land Acquisition and Compensation for Structures


Rate per acre of land is assessed from prevailing market rate by local enquiry which has
been verified with Registration Department and is adopted in cost estimate.

The total cost of Land Acquisition based on the market rate and compensation for
structures based on the RAP has been summarised in Table 9.4 below.

Table 9.4: Cost for Land Acquisition and Structure


Total Cost of Land Cost of Structure Total Cost of Land and
(million Rs.) (in million Rs.) Structure (in million Rs.)
154.78 66.32 221.09

9.4.6 Contingencies
A provision of 3 % of the construction cost has been considered as unforseen
contingency items. The following items have been brought under the head of
contingency.

 Variation in project length during actual execution.


 Variation in cutting earth, rock, excavation requiring blasting
 Variation in pavement quantities as per final pavement design based on CBR values
and BBD study during construction.
 Variation in foundation depth of CD and bridge works after detailed study.
 Variation in revetment on hill side after detailed study.
 Variation in land acquisition cost as per detailed land plan schedule.
 Variation in cost of social settlement after detailed study.
 Unforeseen items.
 Variation in other components and miscellaneous items.

SECON 53 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

9.4.7 Construction Supervision


As it is a major road project, it is absolutely necessary to have an independent agency
to supervise the execution of project package. This may consist of appointing a
consultant with qualified engineers for effective supervision at the construction stage of
project. They should be provided with administration staff, office, accommodation,
vehicles, furniture, stationary etc. Hence, provision of 6% of construction cost is made
for construction supervision.

9.4.8 Landscaping
To make certain locations free from eyesore, provision for landscaping has been made
@ 1% of the construction cost.

9.5 Project Cost for Package I


The total project cost for the package as a whole has been worked out by taking in to
account the sum of Road Work, Structures such as Major Bridges, Minor Bridges,
Culverts, ROBs, Vehicular Underpasses/Overpasses and Pedestrian Underpasses etc. ,
Junction improvements, Miscellaneous provisions, Land Acquisition, Compensation for
Structures, contingencies, Q.C charges & Construction Supervision and Landscaping.

Total Estimated Project Cost for Package I is Rs. 822.414 crores.

The work on above packages is expected to commence by mid 2008 and programmed
for completion within 30 months in phases as given below:

1st Year = 30 %
2nd Year = 50 %
3rd Year = 20 %

10.0 ECONOMIC ANALYSIS


10.1 Introduction
Economic evaluation is carried out to assess whether the proposed investment on
highway improvement is economically acceptable or not. In other words, the objective of
the appraisal is to evaluate if the investment proposed enhances or leads to
maximization of social welfare of the community in the hinterland or not. The yardstick to
measure such economic viability is usually in terms of Economic Internal Rate of Return
(EIRR). As per the TOR, we have estimated Net Present Value (NPV) as well as Benefit
Cost Ratio (B/C Ratio) indicators, in order to evaluate the viability in a comprehensive
manner. The project is different in nature when it is compared with other routine projects.
However it is assumed that by providing alternate alignment to existing road it will serve
the benefits in both ways,
(i) it reduces the VOC on the existing road as traffic is being diverted on to the
new road
(ii) it reduces the extent of demolition of structures along the existing road.

10.2 Evaluation Framework


Economic evaluation has been carried out within the framework of cost-benefit analysis
technique that is widely used in the appraisal of public investment projects. The analysis
was carried out for both “with” and “without” project conditions. The Guidelines of
MoSRTH, GOI i.e. IRC-SP-30, revised in 1993 and the Study for updating road user
cost data, 2001 carried out by CRRI for the MoSRT&H, GOI have been followed in this
evaluation.

SECON 54 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

The evaluation is carried out by adopting incremental cost analysis with discounting
cash flow technique. The financial cost is converted into economic cost by adopting
shadow pricing factor as recommended in IRC SP 30 Manual. The updated Road User
Cost Study of MoRT&H carried out by CRRI, 2001 has been followed in estimating the
economic benefits. Benefits considered are savings in Vehicle Operating Cost (VOC)
and savings in value of time arising out of the proposed road widening, strengthening
and improvement from 2 lanes to 4 lanes configuration. Annual maintenance and
periodic maintenance like overlay has been considered. The incremental cost and
benefits are estimated under “with” and “without” project situation to estimate the net
benefit that accrues to the project, which is discounted to estimate EIRR, NPV and B/C
ratio. In addition, sensitivity analysis on the base case has also been carried out for the
following cases to assess the project related risks.

Case-1: Base Cost and Base Benefits


Case-2: Base Cost + 15% increase in Cost and Base Benefits
Case-3: Base Cost and Base Benefits - 15% decrease in Benefit
Case-4: Base Cost + 15% increase in Cost & Base Benefits - 15% decrease in Benefit

In line with the practice in India, we have evaluated the viability with and without time
value to indicate the economic viability under both the conditions.

10.3 The Project


The Project Corridor includes Thiruvananthapuram – Kanyakumari stretch of NH 47 and
Nagercoil – Kavalkinaru section of NH 47B. This report pertains to Package I from km
00.000 to km 43.000 NH 47 of Kerala Stretch.

The Corridor passes through many hamlets and urban settlements enroute. The existing
configuration is mostly 2 lanes with earthen shoulder, although paved shoulders are
found here and there. As a consequence, there is congestion along the road and there
is speed and time delay. The condition of road surface is good.

With the increase in traffic, there is a need to upgrade, strengthen and widen the current
configuration from 2-lane to 4-lane. Heavy built-up areas along both sides of the
Corridor restrict widening at most locations. Therefore, the proposal encompasses new
alignment for most portion of the Corridor including bypasses for built-up areas. It may
be noted that a new cross-country alignment is proposed to the extent that is required in
order to avoid human settlements along the stretch, which is not cost effective for land
acquisition or where acquiring land is not feasible at all. The existing alignment is
utilized to the maximum, wherever feasible.

The current practice of annual and periodical maintenance at 5 yearly intervals has
been incorporated in the project evaluation with appropriate costs. A roughness of
500mm per km is assumed as the deterioration rate for the existing and new pavement
in the evaluation model.

The details of the project corridor are given in Table 10.1 below:

Table 10.1: Details of Package-I


Details NH-47 NH-47 (new)
Section Package I Package I
With Out Project With Out Project With Project
Chainage (Km)
Start 552.4 0
End 599 43

SECON 55 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Distance (Km) 46.6 43


Reference Village
Name
From Kazhakkoottam Kazhakkoottam
To Kaliyikkavaila Karode
Savings in Distance (km) Nil 3.7

10.4 Traffic Growth Scenarios


The base year AADT estimated based on traffic survey is presented below to indicate
the traffic variations among the Sections. The comparative traffic is presented in Table
10.2 below. However for the analysis purpose the average traffic at section 2 and 3 has
been considered without reducing the traffic as project itself is different in nature when
compared with other projects. Hence the benefits due to project implementation has
been considered as combined for existing and proposed road.

Table 10.2: Base Year Traffic Volume considered for Economic Evaluation
Peak Hour
Two- Auto/ Car Total
Year Bus HCV MAV LCV Total Traffic
Wheeler Tempo (NT) PCU
(PCU)
At km 13/000
5767 2582 3563 106 390 38 582 13029 797 10917
(on TVM Bypass)
At km 626/000
4262 554 2993 1428 1201 975 1384 12798 1273 19891
(existing NH 47)

Forecast growth rate for the above vehicle type are presented in Table 10.3 given below.

Table 10.3: Traffic Growth Rates


Year Traffic Growth
Vehicle Type (%)
2Wheelers 12.93
Car 6.52
Bus 5.41
Auto 12.08
Commercial Vehicles 9.54
Others 6.41

10.5 Economic Cost


The estimated financial cost includes taxes and duties, which are transfer payments.
These transfer payments are to be deducted from the financial cost to arrive at
economic cost. As per IRC SP 30 and as adopted in other projects of NHAI, economic
cost is arrived at by applying shadow pricing factor of 0.8 to 0.9 on the financial cost.
The estimated economic cost is set out in Table 10.4 below.

The estimated capital investment is spread over a period of two and half years from
2008 at a proportion of 30%, 50% and 20% during 2009, 2010 and 2011. It is expected
that the new highway will be opened up for traffic in 2011 and the benefit is expected to
accrue from 2011. Accordingly, the estimated economic cost is distributed over these
three years. The estimated cost has been inflated with inflation of 5% per annum and for
2.5years time period in order to arrive at the preset rate and same is used in the
analysis.

The average annual maintenance cost is Rs. 0.25Million/Km and Rs. 0.4Million/Km
without and with project situation. Similarly the periodic maintenance taken at 5 yearly

SECON 56 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

intervals is Rs. 2.5.0Million/Km and Rs.4.5Million/Km for without and with project
situation. The cost of Structural Overlay at the end of 15th year is estimated as
Rs.3.5Million/Km for without project situation and Rs. 6.0Million/Km for with project
situation.

It may be noted that the capital cost includes land acquisition cost and some element of
social and environmental costs, which are included in the project cost.

10.6 Economic Benefits


The economic benefits considered in evaluating the economic viability of the Corridor
are of the following types:

 Savings in vehicle operating cost


 Savings in value of time

There are other indirect benefits such as social benefits in terms of savings in life
(prevention of accident due to improved geometry), citizens riding comfort due to
improved maintenance practice, and increase in value of property adjacent to the
project corridor.

10.6.1 Estimation of Vehicle Operating Cost


VOC comprises of distance related costs and time related costs. The distance related
cost elements are:
 Fuel cost
 Tyre cost
 Engine oil cost
 Other oil cost
 Grease cost
 Spare cost
 Maintenance cost

All the above costs constitute variable cost portion of the VOC estimate. The time
related cost components of VOC includes:

 Fixed cost
 Depreciation
 Wages

The above cost components are estimated for each vehicle type and for each section
corrected for congestion levels, as the cost component estimates are under free flowing
conditions. Therefore, congestion factors have been estimated for distance related and
time related separately. These factors are corrected for congestion level (Factor of 0.8)
and finally VOC per km of distance is estimated for each of the vehicle types and
packages. The distance and time related congestion factors are assumed not to exceed
2 or less than 1, as recommended by the IRC Guidelines.

The factors that affect the Vehicle Operating Cost (VOC) are speed, road roughness
and carriageway width. These factors are calibrated for “with” and “without” project
situation to estimate the VOC “with” and “without” project situation.

The speed flow equations as updated in 2001 by CRRI have been used to estimate the
speed with given forecast traffic on the Corridor by Sections, taking in to account the
condition of pavement, type of terrain and carriageway width. As the estimated speed
based on these equations is under free-flow conditions, we have calibrated the speed

SECON 57 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

for the observed speed using distance related congestion factors and time related
congestion factors, which are estimated using the relationships as given in the Updated
RUCS, 2001.

The road roughness of the existing pavement is from the actual survey carried out and
for the with project situation, it is assumed that on completion of construction, it will have
a roughness of about 2000 mm/km. As a standard practice the pavement deterioration
rate for “without situation” is always higher than “with project situation”, due to pavement
quality and varying maintenance practice. Accordingly, we have assumed the pavement
deterioration rate at 500mm/Km for the existing pavement and 500-mm/ km per year for
the new pavement.

Carriageway width is 7 m wide with earthen shoulders for the existing road and for the
proposed Corridor, it is 4 lane divided carriageway. The highway capacity assumed for
estimating volume capacity ratio is based on IRC recommended values. The peak hour
traffic capacity of 2 lane highways with earthen shoulder is 1500 PCU and for the 4-lane
divided carriageway with paved shoulder is 4000 PCU, as per IRC 64-1990.

Rise and fall is assumed at 10 m/km, on an average for all the Sections. Although it
could vary between sections.

Based on the above-calibrated results as input, the VOC has been estimated for each
type of motorized vehicles.

10.6.2 Savings in Value of Time


With road condition and highway configuration, the travel speed will increase, resulting
in savings in time for both passenger and goods traffic. In order to estimate the value of
time savings, we have used the value of time of passengers and goods, as per the
vehicle type, as furnished in the Updated RUCS, 2001. These values are updated to
reflect the price level in October 2004. The difference between the estimated value of
time for “without and with project condition” is attributed to the project as savings.

10.7 Results of Economic Evaluation


Economic viability is carried out with 25 years benefit period. The result of economic
viability analysis as furnished in Table 10.4 below reveals that the project is
economically viable with 25 years benefit period when considered for the savings in
value of time.

Table 10.4: Results of Economic Viability Analysis for Package-I


NPV NPV
EIRR
Improvement EIRR (Only (VOC+
Sensitivity (VOC+ B/C Ratio
Cost (Only VOC) VOC in VOT in Mill
VOT)
Mill Rs) Rs)
Case-1 6408.54 6.16% 13.15% (3004.00) 845.34 1.13
Case-2 7369.82 5.20% 11.98% (3864.12) (14.78) 1.00
Case-3 6408.54 5.05% 11.80% (8510.60) (141.58) 0.98
Case-4 7369.82 4.13% 10.69% (4273.64) (1001.70) 0.86

10.8 Conclusion
From the analysis it is found that the project implementation will benefit the road user in
terms of sensitivity from Case 1 to Case 3. But in case-4, the project is lack of returns.
However, considering the direct and indirect benefits it would be reasonable to
recommend for taking up the project for implementation.

SECON 58 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

11.0 BOT Analysis


11.1 Preface
The purpose of this analysis is to assess the financial viability of the project on BOT
basis. BOT assumes that the entire revenue comes from tolls collected from the traffic
as per NHAI toll rates and the investment is funded through a 70:30 mix of debt and
equity .The viability is assessed from point of view of Equity Investor (Concessionaire),
Lender and the project as a whole for period of 30 years

In case the project is not found to be viable on BOT, an assessment is made of the
extent of grant from NHAI, which can make the project viable.

In all the above cases discounted cash flow analysis is used to calculate values of
financial Internal rate of return (FIRR) and Net present Value (NPV).

The viability of the project from point of view of all the Stakeholders is ascertained based
on comparing the values of FIRR, NPV, Payback and DSCR obtained from the analysis
with the pre defined hurdle rates. The analysis is carried out for the following scenarios.

Scenario-1: Without NHAI Grant for 30 Years Concession Period


Scenario-2: With NHAI Grant for 30 Years Concession Period

The financial analysis has been carried out for the package but the revenue from toll
collection has been considered for the section based on the traffic variations with the
above-mentioned different scenarios. The details of the package are given in Table 11.1
below:

Table 11.1: Package Details


Sl No Description Length in km
1 Package I: From km 00/000 to km 43/000 to of NH-47 43.00

11.2 Project Cost


The Concessionaire Cost includes Civil Construction Cost including improvement of
existing carriageway and toll plazas, Contingencies and Supervision cost, IC and
preoperative cost, financing cost and Interest during Construction. The project cost from
NHAI point of view comprises of land acquisition, shifting of utilities, acquisition of
existing structures/facilities, rehabilitation, and resettlement and environment mitigation
measures. The cost summary of the package corresponding to both Concessionaire’s
and NHAI are given in Table 11.4 below.

11.2.1 Civil Construction Cost


The Civil Construction Cost for package is summarized below

Table 11.2: Construction Cost for Package-I


Sl. Civil Construction
Description
No Cost Rs. Millions
1 Package –I 5822.10

The total civil construction cost of each Package has been calculated based on 2008
prices. The Construction period is assumed to be 2.5 years starting from mid of 2008.
For purpose of analysis, the civil construction costs for the total package has been
spread over the construction period based on the percentage of progress proposed to
be achieved in each year namely 30%, 50%, and 20%.

SECON 59 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

The base costs have been escalated at the rate of 5% to obtain actual costs in the years
of expenditure in line with the current trend of WPI growth.

11.2.2 Interest during Construction (IDC)


Interest during Construction is the cost incurred on debt availed during construction
period. The portion of debt availed each year is assumed to be in line with proposed
percent progress of construction each year namely 30%, 50% and 20% with the actual
drawdown each year assumed to be in semi annual installments. Interest is calculated
at rate of 11 per annum a small spread over current Prime Lending Rate of State Bank
of India. Debt component is assumed to be 70% of the total project cost. The IDC for the
Package considering different scenarios are summarized below.

11.2.3 Contingencies
Based on the past experience as well as taking into account NHAI norms a reasonable
figure of 3% is assumed for Contingencies and supervision

11.2.4 Independent Consultant and Preoperative expenses


Based on the past experience as well as taking into account NHAI norms a reasonable
figure of 2% is assumed for Independent Consultant and supervision

11.3 Toll Rates


Tolls are determined based on various factors like

a. User willingness to pay


b. Revenue required for project viability
c. Perceived benefit to the user
d. Availability of alternate routes from Origin to Destination

11.3.1 New Toll Policy


In exercise of the powers conferred by section 9 of the National Highways Act, 1956 (48
of 1956) and in supersession of the National Highways (Temporary Bridges) Rules,
1964, the National Highways (Collection of Fees by any Person for the Use of Section of
National Highways/Permanent Bridge / Temporary Bridge on National Highways) Rules,
1997, the National Highways (Fees for the Use of National Highways Section and
Permanent Bridge – Public Funded Project) Rules, 1997 and the National Highways
(Rate of Fees) Rules, 1997, except with respect to things done or omitted to be done
before such supersession, the Central Government makes the following Rules for
collection of fee for use of Sections of National Highways, bridges, tunnels and
structures.

As per the new toll policy the toll rates can also be fixed based on the type of project
and its cost. Presently the toll rates have been fixed based on the Clause 4 (f) of new
Toll Policy. The arrived toll rates for the package are given in Table 11.5 below.

Table 11.5: Toll Rates


Sl. Toll Rates (Rs/Km)
Type of Vehicle
No for the year 2007
1 Car, Jeep, Van 1.790
Light Commercial Vehicle,
2 2.700
Mini-Bus

SECON 60 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Sl. Toll Rates (Rs/Km)


Type of Vehicle
No for the year 2007
3 Truck, Bus 5.370
HCM, EME, MAV (3 to 6
4 8.070
Axles)
Oversized Vehicles (more
5 10.740
than 7 Axles)

The Toll rates for year 2007 have been escalated @ 5% per annum to year 2011 when
the carriageway will be open to traffic. The toll charges adopted for each category of
vehicle for the total road length rounded off to nearest rupee.

Table 11.6: Projected Toll Rates


Sl. Toll Rates Rs./
Vehicle Type
No. km/Vehicle by 2011
1 Car 3.109
2 LCV 4.647
3 Mini-Bus 4.647
4 Bus 9.293
5 2-Axle 9.293
6 3-Axle 13.907
7 MAV 13.907
8 HMV 18.554

11.4 Traffic
In the investigation and survey stages, traffic volume counts have been conducted on
the project corridor during Nov-2004 at three locations and numbers of vehicles that can
be tolled are assessed for the package. Tollable traffic for the package in terms of AADT
with base year as 2004 is given in Table 11.7 below.

Table 11.7: Base Year Traffic for the Package-I : Tollable Traffic
Traffic on Traffic at km
Tollable
Vehicle Type Thiruvananthapuram 626/000 of NH 47
Traffic
Bypass (VC-2) (VC-3)
Car 3563 2993 3278
LCV 365 1081 723
Mini-Bus 224 313 269
Bus 110 1473 791
2-Axle 390 1201 795
3-Axle 13 160 86
MAV 25 7 16

11.4.1 Traffic Growth rates


For the financial analysis purpose the traffic growth is not based on the traffic forecast
based on the economy. But to be on conservative a traffic growth of 5% per annum as
suggested by Planning Commission has been adopted.

11.5 Toll Revenue


Toll revenue for the next 30 years has been calculated based on the base year traffic of
2004 for each vehicle category. product of forecast traffic of the vehicle category and
the toll charge for that category will yield the toll revenue. The toll revenue is calculated
based on the traffic growth of 5% to be on conservative estimate.

SECON 61 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

An escalation of 5% per annum has been applied on toll charges to take care of inflation,
which is reflected in toll revenue projections.

A discount 50% has been considered in traffic volume and hence revenue to allow for
traffic leakage, local traffic, traffic using existing road and exempted traffic. Hence only
50% of the traffic will be exempted from paying toll because of existing road for
Package-I.

11.6 Tax
Section 80-A permits tax holiday for a period of 10 consecutive years in a block of 20
years. The corporate tax rate assumed for calculation is 33.66%. Minimum Alternate
Tax (MAT) of 11.22% has been assumed on book profits.

11.7 Sources of Finance


Sources of finance available with the Concessionaire for funding the project are

 Debt in the form of long-term loans from financial institutions. Interest rates on these
loans would be determined by prime lending rates and creditworthiness and track
record of the Concessionaire/borrower
 Equity in the form of Concessionaire’s own funds

Usually for such capital-intensive projects where the project outlay is large the
Concessionaire normally chooses a larger component of debt and smaller component of
equity typically in the ratio of 70:30 to optimize Concessionaire returns.

In case the calculated returns with the above debt to equity mix are below the required
rates, Concessionaire has the option to seek NHAI grant in the form of a subsidy. The
NHAI grant is spread over the Construction and operating period.

11.8 Expenses
Expenses are of two types depending upon the period in which they are incurred
namely Construction period expenses and Operation and Maintenance period expenses.

11.8.1 Expenses during Construction Period


 Preliminary and Preoperative expenses
 Contingency allowance to take care of unforeseen expenses during construction
period
 Interest during Construction period

The total project cost includes construction cost and expenses during construction
period.

11.8.2 Expenses during Operation and Maintenance Period


 Toll Collection expenses
 Administrative expenses for day to day operation
 Maintenance expenses which include routine and periodic maintenance
 Interest expense on debt

11.8.2.1 Expenses towards Toll Collection

The Concessionaire has the right to collect toll by operating and maintaining toll plazas
or else by subcontracting the same to a third party. The analysis assumes that the

SECON 62 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Concessionaire would operate and maintain toll plazas himself. Two toll plazas for the
package has been assumed. The toll plaza expenses are given in Table 11.8 below.

Table 11.8: Toll Plaza Expenses


Sl. Total Nos Rate per
Description Total (Rs)
No per Day shift (Rs)
1 Cashiers 30 425 4653750
2 Assistants 20 200 1460000
3 Security 20 200 1460000
Security
4 10 375 1368750
Supervisor
5 Toll Supervisor 10 700 2555000
6 Toll Manager 2 900 657000
7 Electricity* 1 150000 150000
8 Telephone* 1 50000 50000
9 Canteen* 1 50000 50000
10 Vehicles* 1 50000 50000
12454500
Total
Say Rs 12.5 Millions

11.8.2.2 Expenses towards Operation and Maintenance

Routine maintenance expenses are required for maintenance of pavement, collection of


litter, traffic management (policing), accident repairs and all ancillary works including
beautification

Periodic maintenance expenses are required for overlay, repair/renovation of road


furniture, drains, buildings etc. Periodic maintenance includes periodic renewal every 5
years.

The estimate for the routine maintenance and periodic maintenance per km is given in
Table 11.9 below.

Table 11.9: Maintenance Cost in Rs Million per Km


Sl Amount (Rs
Description
No Millions)
Routine maintenance (every year): cost per km for
1 0.40
the four lanes with paved shoulder (Rs millions/Km)
Periodic maintenance (every five years): cost per km
2 4.50
for four lanes with paved shoulder (Rs millions/Km)
Operation and Maintenance of Toll Plaza (Rs
3
millions/annum) 12.5

11.9 Viability Criteria

11.9.1 BOT with and without NHAI grant


The criteria for assessing project viability on BOT both with and without NHAI grant is as
mentioned in Table 11.10 below. The minimum requirement for project to be feasible in
terms of BOT project should have the following values.

Table 11.10: Details of Viability Criteria


Sl. No Financial Parameter Should be
1 Project FIRR (Post Tax) Minimum 13%

SECON 63 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

2 Project FIRR (Pre Tax) Minimum 14%


3 Equity FIRR (Post Tax) Minimum 16%
5 NPV Greater than zero
6 Payback Maximum 9 years
7 DSCR Minimum 1.3

11.9.2 BOT Annuity


In case none of the above criteria are met or else only a few of the above criteria are
met, the project is analyzed for assessing the quantum of annuity (in semi annual
installments) that the project must receive from NHAI as assured payments.

To calculate annuity payments, an equal annual revenue figure is arrived by fixing the
FIRR (post tax) on Equity equal to the minimum required for viability as stated above
under BOT. This is done since the payments are assured and the risks of operation are
borne by NHAI.

11.10 Results of Financial Analysis


Based on the assumptions, project costs, scenarios and expenses as explained in
earlier sections, financial analysis has been carried out as BOT Toll project with and
without NHAI grant and also as BOT Annuity project. The summary of analysis is given
in Table 11.11 below.

Table 11.11: Summary of Financial Analysis


Parameters For 40% NHAI GRANT
PROJECT FIRR (Post Tax) 9.35%
EQUITY FIRR (Post Tax) 9.54%
NPV
Rs. (-) 133.62 Crores

12.0 CONCLUSIONS AND RECOMMENDATIONS


12.1 General
The project road consists of Thiruvananthapuram – Kanyakumari section of NH-47 and
Nagercoil – Kavalkinaru section of NH-47B. The project has been taken up by NHAI for
improvement to four / six lane carriageway under NHDP Phase-III. The existing road
and traffic conditions have been investigated in detail and suitable proposals have been
made to suit the site conditions and future requirements, which are summarised below.

12.2 Existing Road Conditions


The existing NH-47 between Thiruvananthapuram to Kerala border is two-lane
carriageway with Earthen shoulders. Geometrics of the road do not conform to NH
standards and there is excessive ribbon development all along the alignment. Widening
of the road would involve extensive demolition of churches, temples, schools,
commercial and residential buildings. In view of this, various alternate proposals have
been investigated and the most suitable one has been adopted for preparation of the
project report.

12.3 Proposed Alignment


The proposed alignment starts from Kazhakkoottam which is the starting point of
Thiruvananthapuram – Neyyanttinkara bypass. The alignment follows the existing
bypass upto km 22/600 (Kovalam) and further upto Karode village near Kerala Border.

SECON 64 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Right of Way (ROW) is kept as 45m generally in the entire stretch. The alignment runs
through cultivated land and uses the existing Thiruvananthapuram bypass for about
22.6 km length and rest of the alignment is new formation.

12.4 Typical Cross Sections


Typical cross sections have been generated for 60m ROW with various elements of
carriageway, shoulders, median, utility corridor and service roads. Details of the cross
sections are given in Table 12.1 below:

Table 12.1: Widths of Cross Sectional Elements


Elements Width (m) Remarks
Main Carriage way 2 X 7.000 14.000 -
Paved shoulder 2 X 1.500 3.000 -
Gravel Shoulder 2 X 1.500 3.000 -
Space for
Slope/Future reserve
Drain 2 X 1.000 2.000 -
Service Roads 2 X 5.500 11.000 -
Utility corridor 2 X 2.000 4.000 -
Median 1 X 4.500 4.500 -
Shy off distance 2 x 0.250 0.500 -
Total 45.00 -

12.5 Proposed Structures


The proposed alignment need to be provided with various types of structures based on
the requirement as per the site conditions. The alignment crosses minor streams, nalas,
tanks, ponds and other water bodies. In addition to the above, the proposed alignment
crosses major roads and minor roads. At all these crossings depending on importance,
suitable structures are proposed, which include Major Bridges, Minor Bridges, Culverts
(Box and Pipe), Vehicular Underpasses, Vehicular Overpass, Pedestrian Underpasses,
ROBs for the existing railway lines where the alignment cross the railway line etc.

All the new structures proposed are of 6-lane carriageway width. Only for the portion
where the existing road is utilized the proposed structures are 3 lane carriageway on the
proposed widening side. The list of the various structures to be constructed/widened
and the numbers are given in Table 12.2 below.

Table 12.2: List of Structures Proposed for Package I


Sl.
Type of Structures No. of Structures
No.
1 Major Bridges 04
2 Minor Bridges 15
3 Box Culverts 27
4 Pipe Culverts 101
5 Vehicular Underpasses 6
6 Vehicular Overpasses 5
7 ROB 1

12.6 Pavement Design


Main Carriageway

For the proposed alignment, a flexible pavement has been proposed for entire section
based on the commercial vehicles on the road section.

SECON 65 NH 47 & 47B-66-PR-O001


Design Consultancy for Upgradation of NH 47 Final Detailed Project Report
From Thiruvananthapuram to Kanyakumari and Volume - I: Main Report
NH 47B From Nagercoil to Kavalkinaru Package - I

Average Commercial Vehicles per day = 1478CVPD


Expected Traffic on New Alignment = 65% of CVPD
Design Period = 15 years.
Sub-Grade CBR = 8%.
Vehicle Damage Factor = 4.5
Lane Distribution Factor = 0.75
Traffic Movement in each direction = 50%
Traffic Growth per annum = 7%
Design Traffic loading for 15 years = 19 msa

From Plate 2 of IRC: 37-2001, for CBR of 8% the following pavement thickness has
been arrived and is presented in Table 12.3 below.

Table 12.3: Pavement Layer Thickness for Main Carriageway


Type of Layer Layer Thickness (mm)
Bituminous Concrete (BC) 40
Dense Bituminous Macadam (DBM) 85
Wet-Mix Macadam (WMM) 250
Granular Sub-Base (GSB) 200
Total 575

Design of overlay has been done for strengthening of the existing pavement wherever
the existing road is being utilized, Pavement Composition for overlay for the existing
Thiruvananthapuram bypass for length of 22.6km it is proposed to provide 85mm DBM
and 40mm BC as overlay for strengthening the existing pavement.

Service Road
For the service road it is assumed for traffic loading of 5msa and the pavement design
has been arrived from Plate 1 of IRC: 37-2001 for CBR of 8% is presented in Table 12.4
below.

Table 12.4: Pavement Layer Thickness for Service Road


Sl. No. Type of Layer Layer Thickness (mm)
1 Semi-Dense Bituminous Concrete (DBM) 25
2 Dense Bituminous Macadam (DBM) 50
3 Wet-Mix Macadam (WMM) 250
4 Granular Sub-Base (GSB) 150
Total 475

12.7 Cost Estimate


The total project cost for the package as whole has been worked out by taking in to
account the sum of Road Work, Structures such as Major Bridges, Minor Bridges,
Culverts, ROBs, Vehicular Underpasses/Overpasses and Pedestrian Underpasses etc. ,
Junction improvements, Miscellaneous provisions, Land Acquisition, Compensation for
Structures, contingencies, Q.C charges & Construction Supervision and Landscaping.

The Total Project Cost for Package I is Rs. 822.414 Crores.

12.8 Economic Analysis


The economic analysis for Package-I reveals that project is viable except in worst
scenario i.e. in Case-4.

SECON 66 NH 47 & 47B-66-PR-O001

You might also like