1_GMP_Assignment_Building_Typical_Layout.dxf
Office1
MEC
Corridor
Toilet
Void
Office2
Corridor
MEC
Name of zones
Type of the zones
How much far is from ground (0m)
Height of zone
Name of zones
Type of the zones
How much far is from ground (0m)
Height of zone
Tip. Please use construction line to create straight line. It is outline of modeling.
Please click left end point and locate the selected zones above of previous space.
IES provides three options Normally first and second option are used
(1) Add by percentage area This will automatically define window area based on WWR.
IES provides three options Normally first and second option are used
(2) Add by percentage area This will automatically define window area based on WWR.
But it allows users to define WWR with consideration of height of window as well.
Name
Profile
Please define the internal condition. Please click Add/edit to input internal condition.
LPD input.
EPD input.
Occupancy input.
infiltration input.
External Wall