Notice: Reports and Guidance Documents Availability, Etc.: Golden Pass LNG Terminal LP

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

35234 Federal Register / Vol. 70, No.

116 / Friday, June 17, 2005 / Notices

also states that a person obtaining party DEPARTMENT OF ENERGY proceeding. See 18 CFR
status will be placed on the service list 385.2001(a)(1)(iii) and the instructions
maintained by the Secretary of the Federal Energy Regulatory on the Commission’s Web site at
Commission and will receive copies of Commission http://www.ferc.gov under the ‘‘e-
all documents filed by the applicant and Filing’’ link and the link to the User’s
by all other parties. Unless filing Draft General Conformity Guide. Before you can file comments
electronically, a party must submit 14 Determination; Golden Pass LNG you will need to create a free account,
copies of filings made with the Terminal and Pipeline Project; which can be created by clicking on
Commission and must mail a copy to Jefferson, Newton, and Orange ‘‘Login to File’’ and then ‘‘New User
the applicant and to every other party in Counties, TX, and Calcacieu Parish, LA Account.’’
the proceeding. June 10, 2005. After all comments are reviewed, the
Only parties to the proceeding can ask In Reply Refer to: OEP/DG2E/Gas Branch 2,
staff will publish and distribute a Final
for court review of Commission orders Golden Pass LNG Terminal LP, Docket No. General Conformity Determination for
in the proceeding. CP04–386–000, Golden Pass Pipeline LP, the Project.
Docket Nos. CP04–400–000, CP04–401–000,
However, a person does not have to and CP04–402–000.
Magalie R. Salas,
intervene in order to have comments Secretary.
considered. The second way to To the Party Addressed
Table of Contents
participate is by filing with the The staff of the Federal Energy
Secretary of the Commission, as soon as 1.0 Introduction to Proposed Action
Regulatory Commission (FERC or 2.0 Regulatory Background—General
possible, an original and two copies of Commission) has prepared a draft Conformity
comments in support of or in opposition General Conformity Determination to 3.0 General Conformity Applicability
to this project. The Commission will assess the potential air quality impacts 4.0 Air Emissions Inventory
consider these comments in associated with the construction and 5.0 Preliminary General Conformity
determining the appropriate action to be operation of a liquefied natural gas Determination
taken, but the filing of a comment alone (LNG) import terminal and natural gas 5.1 NOX Emission Offsetting
will not serve to make the filer a party 5.2 Other Impact Mitigation Practices
pipeline proposed by Golden Pass LNG
to the proceeding. The Commission’s 5.3 Conditions for Granting a Final
Terminal LP and Golden Pass Pipeline Conformity Determination
rules require that persons filing LP, referred to as the Golden Pass LNG
comments in opposition to the project Tables:
Terminal and Pipeline Project, in the
provide copies of their protests only to above referenced dockets. Table 4–1 Estimated Onshore and Marine
the party or parties directly involved in This Draft General Conformity Construction Emissions
the protest. Determination was prepared to satisfy Table 4–2 Controlled Air Emission Estimates
for the Proposed LNG Terminal
Persons who wish to comment only the requirements of the Clean Air Act.
Table 4–3 Estimated Indirect Emissions
on the environmental review of this Comment Procedures During Terminal Operation
project should submit an original and
Any person wishing to comment on Attachments:
two copies of their comments to the
Secretary of the Commission. the Draft General Conformity 1 September 24, 2004, Conditional
Determination may do so. To ensure Conformity Certification From the Texas
Environmental commenters will be
consideration of your comments in the Council of Environmental Quality
placed on the Commission’s
environmental mailing list, will receive Final General Conformity Introduction to Proposed Action
copies of the environmental documents, Determination, it is important that we
receive your comments before the date On July 29, 2004, Golden Pass LNG
and will be notified of meetings Terminal LP filed an application with
associated with the Commission’s specified below. Please carefully follow
these instructions to ensure that your the Federal Energy Regulatory
environmental review process. Commission (FERC or Commission) in
Environmental commenters will not be comments are received in time and
properly recorded: Docket No. CP04–386–000 for
required to serve copies of filed authorization under Section 3(a) of the
documents on all other parties. • Send an original and two copies of
your comments to: Magalie R. Salas, Natural Gas Act (NGA) to site, construct,
However, the non-party commenters and operate a liquefied natural gas
will not receive copies of all documents Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., (LNG) terminal on the Port Arthur
filed by other parties or issued by the Channel of the Sabine-Neches Waterway
Commission (except for the mailing of Room 1A, Washington, DC 20426.
• Reference Docket Nos. CP04–386– (SNWW) in Jefferson County, Texas. In
environmental documents issued by the related applications filed on August 20,
Commission) and will not have the right 000 and CP04–400–000 et al.;
• Label one copy of the comments for 2004, Golden Pass Pipeline LP seeks a
to seek court review of the Certificate of Public Convenience and
the attention of Gas Branch 2, PJ11.2;
Commission’s final order. Necessity (Certificate) to site, construct,
and
Comments, protests and interventions • Mail your comments so that they and operate a new natural gas pipeline
may be filed electronically via the will be received in Washington, DC on system and ancillary facilities to
Internet in lieu of paper. See, 18 CFR or before July 12, 2005. connect the LNG terminal to existing
385.2001(a)(1)(iii) and the instructions Please note that we are continuing to intrastate and interstate gas
on the Commission’s Web site under the experience delays in mail deliveries transmission facilities in Texas and
‘‘e-Filing’’ link. from the U.S. Postal Service. As a result, Louisiana (Docket No. CP04–400–000); a
Comment Date: July 1, 2005. we will include all comments that we blanket certificate to perform routine
receive within a reasonable time frame activities in connection with the future
Magalie R. Salas, in our environmental analysis of this construction, operation, and
Secretary. Project. However, the Commission maintenance of the proposed natural gas
[FR Doc. E5–3100 Filed 6–16–05; 8:45 am] strongly encourages electronic filing of pipelines (Docket No. CP04–401–000);
BILLING CODE 6717–01–P any comments or interventions to this and authority to provide open-access

VerDate jul<14>2003 17:59 Jun 16, 2005 Jkt 205001 PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 E:\FR\FM\17JNN1.SGM 17JNN1
Federal Register / Vol. 70, No. 116 / Friday, June 17, 2005 / Notices 35235

transportation of natural gas to others Transcontinental Gas Pipe Line to an approved CAA implementation
(Docket No. CP04–402–000). Golden Corporation (Transco) interstate plan The applicable plan for this Project
Pass LNG Terminal LP and Golden Pass pipeline near Starks, Louisiana (to be is the Beaumont-Port Arthur ozone
Pipeline LP hereafter are referred to installed over an estimated 14-month attainment State Implementation Plan
collectively as Golden Pass. period); (SIP).
Golden Pass’ proposed facilities • Loop—A 42.8-mile-long, 36-inch- The General Conformity Rule is
would import, store, and vaporize an diameter pipeline that would be codified in Title 40 of the Code of
average of approximately 2 billion cubic installed adjacent to (e.g.,) loop 1 the Federal Regulations (CFR) part 51,
feet per day (Bcfd) of natural gas (with Mainline and would extend from the subpart W, ‘‘Determining Conformity of
a peak capacity of 2.7 Bcfd) for delivery LNG import terminal in Jefferson General Federal Actions to State or
into the existing intrastate and interstate County to an interconnection with the Federal Implementation Plans’’ and the
pipeline systems. The LNG import existing American Electric Power (AEP) conformity analysis criteria are
terminal would be constructed in two intrastate Texoma Pipeline in Orange specified in 40 CFR part 93. General
phases, each lasting approximately 48 County, Texas (to be installed over an conformity provisions are also
months. Phase 2 construction would estimated 9-month period beginning incorporated in Texas regulations at 30
begin approximately 12 months after the with and concurrently with the TAC § 114.260. The General Conformity
start of Phase 1 construction and would Mainline); Rule applies to all Federal actions
increase the average capacity from 1.0 to • Beaumont Lateral—A 1.8-mile-long, except programs and projects requiring
2.0 Bcfd. The import terminal would be 24-inch-diameter pipeline extending funding or approval from the U.S.
designed to accept LNG cargoes, from the Mainline in Jefferson County, Department of Transportation (DOT),
temporarily store and vaporize LNG, Texas to industrial customers in the Federal Highway Administration,
and would contain the following Beaumont-Port Arthur, including the the Federal Transit Administration, or
facilities: Exxon Mobil Corporation (ExxonMobil) the Metropolitan Planning Organization.
• A protected LNG unloading slip, Beaumont Refinery Complex (to be In lieu of a conformity analysis, these
LNG ship and support vessel installed over an estimated 1-month latter types of programs and projects
maneuvering area that would be capable period after installation of the Loop is must comply with the Transportation
of receiving up to 200 LNG ships per complete); Conformity Rule promulgated originally
year; • Meter stations and interconnection
by the EPA on November 24, 1993 (58
• Ship unloading facilities consisting facilities to interconnect with up to 11
FR 62188) and revised several times
of two berths, each capable of existing intrastate and interstate
thereafter, most recently on July 1, 2004.
accommodating LNG ships ranging from pipelines; 2 and
• Associated pipeline facilities, Title 1, Section 176(c)(1), of the CAA
125,000 cubic meters (m3) to 250,000
including pig launchers and receivers, defines conformity as the upholding of
m3, and associated facilities (the first
and block valves. ‘‘an implementation plan’s purpose of
berth would be constructed during
All of these facilities are referred to as eliminating or reducing the severity and
Phase 1 and the second during Phase 2);
• A total of five full-containment LNG the Golden Pass LNG Terminal and number of violations of the National
storage tanks each with a working Pipeline Project. The LNG terminal Ambient Air Quality Standards
capacity of 155,000 m 3 (three tanks facilities (or Project) would be located in (NAAQS) and achieving attainment of
would be constructed during Phase 1 Jefferson County, Texas, in the such standards.’’ Conforming activities
and two during Phase 2); Beaumont-Port Arthur area, which is or actions should not, through
• A total of ten shell-and-tube heat currently designated nonattainment for additional air pollutant emissions:
transfer fluid (HTF) LNG heat the l-hour ozone standard. Therefore, • Cause or contribute to new
exchangers to vaporize the LNG (five oxides of nitrogen (NOX) and volatile violations of any NAAQS in any area;
exchangers would be installed during organic compounds (VOCs) are • Increase the frequency or severity of
Phase 1 and five during Phase 2); and regulated as nonattainment pollutants any existing violation of any NAAQS; or
• Associated support facilities, for this project and may trigger the • Delay timely attainment of any
including administrative buildings, general conformity requirements NAAQS or interim emission reductions.
storage and maintenance areas, electric established by the U.S. Environmental The General Conformity Rule
power systems, access roads, and other Protection Agency (EPA). establishes conformity in coordination
facilities related to the LNG import with and as part of the National
Regulatory Background—General Environmental Policy Act process. The
terminal.
Golden Pass also proposes to Conformity rule takes into account air pollution
construct a pipeline system, capable of The EPA promulgated the General emissions associated with actions that
transporting up to 2.5 Bcfd of natural Conformity Rule on November 30, 1993 are federally funded, licensed,
gas and consisting of three pipelines in Volume 58 of the Federal Register permitted, or approved, and ensures
and associated pipeline support (FR) Page 63214 (58 FR 63214) to emissions do not contribute to air
facilities, including pig launchers and implement the conformity provision of quality degradation, thus preventing the
receivers, and meter stations. The title I, section 176(c)(1) of the Federal achievement of State and Federal air
pipeline system would be installed in Clean Air Act (CAA). Section 176(c)(1) quality goals. In short, General
overlapping phases across three requires that the Federal Government Conformity refers to the process of
counties in Texas and one parish in not engage, support, or provide financial evaluating plans, programs, and projects
Louisiana, and would consist of the: assistance for licensing or permitting, or to determine and demonstrate that they
• Mainline—A 77.8-mile-long, 36- approving any activity not conforming meet the requirements of the CAA and
inch-diameter pipeline extending from the SIP. The purpose of this General
the LNG import terminal in Jefferson 1 A loop is a segment of pipeline that isusually
Conformity requirement is to ensure
County through Orange, and Newton installed adjacent to an existing pipeline and that Federal agencies consult with State
connected to it at both ends).
Counties, Texas (66.5 miles) and 2 Currently, there are no formal agreements in and local air quality districts so that
Calcacieu Parish, Louisiana (11.3 miles) place for interconnects between the Golden Pass these regulatory entities know about the
to an interconnection with an existing pipeline system and other existing pipelines. expected impacts of the Federal action

VerDate jul<14>2003 17:59 Jun 16, 2005 Jkt 205001 PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 E:\FR\FM\17JNN1.SGM 17JNN1
35236 Federal Register / Vol. 70, No. 116 / Friday, June 17, 2005 / Notices

and can include expected emissions in General Conformity Applicability they would conform to the Beaumont-
their SIP emissions budget. The General Conformity Rule applies Port Arthur SIP.
Pursuant to the General Conformity to all nonattainment and maintenance Air Emissions Inventory
Rule, a Federal agency must make a areas. The LNG terminal would be
General Conformity Determination for located in the Beaumont-Port Arthur The air emissions inventory for the
all Federal actions in nonattainment or Ozone Nonattainment Area, which has Project was prepared using widely-
maintenance areas where the total of been designated as a serious ozone accepted methods. Emissions were
direct and indirect emissions of a nonattainment area with respect to the estimated for both construction and
nonattainment pollutant or its 1-hour NAAQS for ozone. The Project operation of the proposed project.
precursors exceeds levels established by area is in attainment with NAAQS for Onshore construction emissions
the regulations. all other criteria pollutants. estimates include exhaust resulting from
A General Conformity Determination combustion of fuels to operate
The Beaumont-Port Arthur area equipment, fugitive dust emissions from
in a serious ozone nonattainment area is
currently does not have an approved operation of construction equipment at
required for any project that would
ozone SIP. On March 30, 2004, EPA the construction site, offsite vehicle
result in combined direct and indirect
published a final rule in the Federal exhaust, and fugitive dust from vehicle
emissions of either NOX or VOCs equal
Register withdrawing its approval of the travel to the site. Marine construction
to or greater than 50 tons per year (tpy).
Beaumont-Port Arthur attainment emissions estimates include vehicle
A General Conformity Determination is
demonstration and the associated 2007 exhaust from deliveries made by off-site
not required for actions where the total
attainment date, and finding that the vehicles, exhaust from marine
of direct and indirect emissions is below
Beaumont-Port Arthur area had failed to these emissions levels. In addition, even construction equipment, exhaust from
come into attainment by applicable if the total of direct and indirect operation of the dredge, dredged
deadlines. The Beaumont-Port Arthur emissions of NOX or VOCs is below 50 material maintenance activities, and
area was reclassified as a serious one- tpy, when the total of direct and indirect fugitive dust generated from these
hour nonattainment area for ozone emissions of any pollutant from the activities. Estimated construction
effective April 29, 2004 with an Federal action represents 10 percent or emissions are listed in Table 4–1 for
attainment deadline of November 15, more of a nonattainment or maintenance onshore and marine construction
2005. Even though the Beaumont-Port area’s total emissions of those activities.
Arthur area does not currently have an pollutants, then the action is defined as Emission estimates for terminal
approved ozone SIP, a General a regionally significant action and a operations include emissions from the
Conformity Determination is still General Conformity Determination HTF heaters, diesel fuel storage tanks,
needed to ensure that the Project would would be required. diesel firewater pumps, the emergency
not interfere with efforts to achieve Consistent with section 176(c)(1) of diesel electric generator, and from
attainment of the NAAQS. the CAA, a Federal action is generally fugitive emissions from the terminal.
This draft General Conformity defined as any activity engaged in or Emissions from the eight natural gas-
Determination has been prepared supported in any way by any fired HTF heaters are based on an
pursuant to the CAA section 176(c)(1) to department, agency, or instrumentality operating heat duty of 227 MMBtu/hr
assess whether the emissions that would of the Federal Government (40 CFR per heater. Emission estimates from
result from the FERC’s action in 51.852). Federal actions include diesel fuel storage include a nominal
authorizing the Golden Pass LNG providing Federal financial assistance or 33,600-gallon primary storage tank, a
Project would be in conformity with the issuing a Federal license, permit, or 3,800-gallon day tank to supply diesel
Beaumont-Port Arthur SIP for ozone. approval. Where the Federal action is a fuel for the emergency electric
The FERC has worked with Golden Pass permit, license, or other approval for generator, and two 500-gallon day tanks
to quantify and present the emissions some aspect of a non-Federal to supply diesel fuel for each of the two
associated with the Project described undertaking, the relevant activity is the firewater pumps. Emissions from the
herein. Should the FERC act favorably part, portion, or phase of the non-federal diesel generator are based on a 2,500 kW
on Golden Pass’ application, any final undertaking that requires the Federal unit using diesel fuel containing 0.3
authorization for construction would be license, permit, or approval. Because the percent sulfur, and an assumed 100
withheld by the FERC until any FERC would authorize the construction hours of operation per year. Fugitive
appropriate mitigation measures and operation of the proposed Golden emissions as based on the number of
required to ensure the Project’s Pass LNG Terminal and Pipeline Project valves, pumps, compressors, relief
conformity with the SIP are finalized pursuant to Section 3 of the Natural Gas valves, flanges/connections, open-ended
and agreed to by Texas Council on Act, it is considered a Federal action, lines, and sampling connections
Environmental Quality (TXCEQ) and and the resulting emissions of NOX and incorporated into the terminal facility
Golden Pass. VOCs must be assessed to determine if design.

TABLE 4–1.—ESTIMATED ONSHORE AND MARINE CONSTRUCTION EMISSIONS


Emission estimates (lb/hr) Total emission estimates
(tons/yr)
Description
NOX CO VOC SO2 PM10 NOX CO VOC SO2 PM10

Estimated Onshore Emissions:


Onsite Construction—Ex-
haust ................................. 145.8 45.5 8.1 26.0 9.4 150.5 48.1 8.6 26.9 10.0
Offsite Vehicle—Exhaust ...... 36.6 66.1 5.2 4.9 2.8 60.9 75.1 6.1 9.1 4.1
Construction—Fugitive Dust
Emissions .......................... .............. .............. .............. .............. 269.6 .............. .............. .............. .............. 245.1

VerDate jul<14>2003 17:59 Jun 16, 2005 Jkt 205001 PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 E:\FR\FM\17JNN1.SGM 17JNN1
Federal Register / Vol. 70, No. 116 / Friday, June 17, 2005 / Notices 35237

TABLE 4–1.—ESTIMATED ONSHORE AND MARINE CONSTRUCTION EMISSIONS—Continued


Emission estimates (lb/hr) Total emission estimates
(tons/yr)
Description
NOX CO VOC SO2 PM10 NOX CO VOC SO2 PM10

Offsite Vehicle Travel—Fugi-


tive Dust ............................ .............. .............. .............. .............. 107.4 .............. .............. .............. .............. 103.8

Total .............................. 182.4 111.6 13.3 30.9 389.3 211.4 123.2 14.7 35.9 363.0

Estimated Marine Emissions:


Dredge Spoils Manage-
ment—Exhaust ................. 7.9 1.8 0.5 1.5 0.6 a 34.6 a 7.8 a 2.1 a 6.4 a 2.4

Marine Deliveries—Exhaust 34.9 3.4 0.3 26.2 0.9 a 4.8 a 0.5 a 0.04 a 3.6 a 0.1

Dredging Exhaust ................. 143.1 29.7 7.4 23.8 6.9 a 479.2 a 99.5 a 24.8 a 79.7 a 23.2

Slip Construction Activities—


Exhaust ............................. 87.4 80.3 8.6 31.9 6.0 a 143.6 a 138.0 a 14.5 a 54.0 a 9.9

Total .............................. 273.3 115.2 16.8 83.3 14.4 a 662.2 a 245.8 a 41.4 a 143.7 a 35.9

a Emissions are presented in total tons instead of tpy because most of the individual marine construction activities will be completed in less
than a year.

Estimated LNG terminal operating Selective Catalytic Reduction (SCR) The total estimated direct long-term
emissions are listed in Table 4–2. The control system for NOX control. The emissions from the Golden Pass LNG
listed values represent emissions with SCR system will also incorporate an terminal equipment are a maximum of
the application of add-on emission oxidation catalyst for reduction of CO 47.7 tpy NOX and 33.4 tpy of VOCs.
controls for the HTF heaters, which emissions.
consist of low-NOX burners and a

TABLE 4–2.—CONTROLLED AIR EMISSION ESTIMATES FOR THE PROPOSED LNG TERMINAL
Emission estimates (lb/hr) Emission estimates (tons/yr)
Description
NOX CO VOC SO2 PM10 HAPs NH3 NOX CO VOC SO2 PM10 HAPs NH3

HTF Heaters ................. 12.7 27.3 9.8 24.9 13.5 0.7 11.4 41.8 89.5 32.2 5.0 44.5 2.2 37.5
Diesel Fuel Storage
Tanks ........................ .......... .......... 1.2 .......... .......... .......... .......... .......... .......... 0.0 .......... .......... .......... ..........
Diesel Firewater Pumps 37.2 8.0 3.0 2.5 2.6 0.1 .......... 1.9 0.4 0.2 0.1 0.1 0.0 ..........
Emergency Generator .. 80.4 18.4 2.1 8.1 2.3 0.2 .......... 4.0 0.9 0.1 0.4 0.1 0.0 ..........
Fugitives—VOC from
Piping ........................ .......... .......... 0.2 .......... .......... .......... .......... .......... .......... 1.0 .......... .......... .......... ..........
Ammonia Piping Fugi-
tives .......................... .......... .......... .......... .......... .......... .......... 0.2 .......... .......... .......... .......... .......... .......... 0.8

Total ...................... 130.3 53.7 16.4 35.5 18.5 1.0 11.6 47.7 90.9 33.4 5.5 44.7 2.2 38.4

The indirect long-term emissions indirect emissions associated with carriers and correspond to the estimated
associated with operation of the LNG operation of the LNG terminal are emissions submitted by Golden Pass to
terminal include emissions from LNG summarized in Table 4–3. The the TXCEQ on August 9, 2004.
ships, tug assists, and from commuting estimated emissions are based on an
and delivery vehicles. Estimated assumption of 200 calls per year by LNG

TABLE 4–3.—ESTIMATED INDIRECT EMISSIONS DURING LNG TERMINAL OPERATION


Total estimated emissions (tons/yr)
Source Description NOX
CO VOC SO2 PM10

LNG Carriers ............................ Main Propulsion Engines .......................................................... 332.8 32.6 11.1 414.3 5.8
LNG Carriers ............................ On-board Electric Generators—Vessels Transiting .................. 84.2 4.7 9.7 58.0 1.9
LNG Carriers ............................ On-board Electric Generators—Vessels at the Slip ................. 252.4 14.7 28.2 178.5 5.9
Tug Assists ............................... Initial Tug Escort ....................................................................... 24.3 1.9 0.2 18.0 0.6
Tug Assists ............................... Tug Assist—Midpoint Channel .................................................. 48.7 3.9 0.3 36.0 1.2
Tug Assists ............................... Maneuvering/Docking ................................................................ 16.4 5.8 1.0 13.6 0.4
Motor Vehicles ......................... Commuting and Deliveries ........................................................ 0.8 12.2 1.1 0.01 0.04

Total .................................. .................................................................................................... 759.6 75.8 51.6 718.4 15.8

VerDate jul<14>2003 17:59 Jun 16, 2005 Jkt 205001 PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 E:\FR\FM\17JNN1.SGM 17JNN1
35238 Federal Register / Vol. 70, No. 116 / Friday, June 17, 2005 / Notices

The combined (direct plus indirect) impact on the Beaumont-Port Arthur DEPARTMENT OF ENERGY
emissions of NOX would exceed 50 tpy SIP cannot be quantified or credited for
during the construction and operational purposes of the general conformity Federal Energy Regulatory
phases of the project. Therefore, a determination. Commission
General Conformity Determination is
required for NOX emissions. Similarly, Golden Pass has committed to [Docket No. RP05–368–000]
the combined emissions of VOCs exceed purchasing and retiring 48 tons of NOX
50 tpy during the operational phases of emission reduction credits prior to Gulfstream Natural Gas System, L.L.C.;
the project, and a General Conformity commencement of operations. The 48 Notice of Filing
Determination is also required for VOC tons of NOX credits offset the maximum
emissions. projected long-term emissions of NOX June 10, 2005.
from terminal operations (47.7 tpy). Take notice that on June 6, 2005,
Preliminary General Conformity
This commitment by Golden Pass is Gulfstream Natural Gas System, L.L.C.
Determination
documented in the September 24, 2004 (Gulfstream) tendered for filing a service
A General Conformity Determination letter from TXCEQ. agreement with Tampa Electric
must be completed for projects requiring Company (TECO).
Federal authorization that are Other Impact Mitigation Practices
undertaken in areas designated as Gulfstream states that it is requesting
‘‘nonattainment’’ or ‘‘maintenance’’ for TXCEQ’s conditional conformity approval of the service agreement with
certain criteria air pollutants and for certification put forth additional TECO as part of the Bayside Lateral
which the combined direct and indirect conditions as requirements for a project, in which TECO will construct a
emissions of those air pollutants will determination of acceptability of the pipeline from its Bayside, Florida
equal or exceed certain thresholds. The project relative to the Beaumont-Port generation facility to Gulfstream’s
EPA has designated the Beaumont-Port Arthur SIP. These additional conditions, mainline in Manatee County, Florida.
Arthur area as a serious nonattainment which are also stated in the September Any person desiring to intervene or to
area for the 1-hour ozone standard. 24, 2004 letter from TCEQ (see protest this filing must file in
Consequently, a General Conformity Attachment 1), are as follows: accordance with Rules 211 and 214 of
Determination is required for certain • Golden Pass will encourage the Commission’s Rules of Practice and
projects undertaken in the Beaumont- construction contractors to participate Procedure (18 CFR 385.211 and
Port Arthur area for which the in the Texas Emission Reduction Plan 385.214). Protests will be considered by
combined direct and indirect emissions (TERP) grant program and to apply for the Commission in determining the
of either NOX or VOCs, as ozone TERP grant funds; appropriate action to be taken, but will
precursors, will equal or exceed 50 tpy. not serve to make protestants parties to
See 40 CFR 93.153(b) and 30 TAC • Golden Pass will establish bidding the proceeding. Any person wishing to
§ 101.30. The Project requires a General conditions to give preference to ‘‘Clean become a party must file a notice of
Conformity Determination for NOX Contractors’’; intervention or motion to intervene, as
because the combined direct and • Golden Pass will direct, through appropriate. Such notices, motions, or
indirect emissions of NOX would equal provisions included in its construction protests must be filed on or before the
or exceed 50 tpy. In addition, the Project contracts, construction contractors to date as indicated below. Anyone filing
requires a General Conformity exercise Best Management Practices an intervention or protest must serve a
Determination for VOC because the relating to air quality; and copy of that document on the Applicant.
combined direct and indirect emissions Anyone filing an intervention or protest
of VOC would equal or exceed 50 tpy. • Golden Pass will encourage
on or before the intervention or protest
On September 24, 2004, the TXCEQ construction contractors to use
date need not serve motions to intervene
issued a conditional general conformity appropriate low emission fuels. or protests on persons other than the
certification for the Project based on a Conditions for Granting a Final Applicant.
review of project emissions estimates, Conformity Determination The Commission encourages
modeling of the emissions from the
electronic submission of protests and
Project, and a number of commitments The commitments by Golden Pass as interventions in lieu of paper using the
proposed by Golden Pass (see described in sections 5.1 and 5.2 above ‘‘eFiling’’ link at http://www.ferc.gov.
Attachment A). These commitments constitute conditions for granting a final Persons unable to file electronically
include: (1) NOX emission offsetting of conformity determination. should submit an original and 14 copies
terminal emissions, and (2) other impact Documentation of fulfillment of each of the protest or intervention to the
mitigation practices. Each is described condition is required prior to issuance Federal Energy Regulatory Commission,
in the sections to follow. of the final conformity determination 888 First Street, NE., Washington, DC
NOX Emission Offsetting and authorization of project 20426.
construction. Golden Pass may not
The Project may potentially result in This filing is accessible on-line at
NOX emission reductions that are far begin construction of the LNG terminal http://www.ferc.gov, using the
greater then the NOX emissions until the Commission has issued its ‘‘eLibrary’’ link and is available for
generated by the LNG terminal and final General Conformity Determination review in the Commission’s Public
associated sources (LNG trucks and and Golden Pass has received written Reference Room in Washington, DC.
ships). This emission reduction would approval by the Director of Office of There is an ‘‘eSubscription’’ link on the
occur when power plants and Energy Projects of its filing stating that Web site that enables subscribers to
residential customers convert boilers it would comply with all requirements receive email notification when a
and furnaces to higher-efficiency natural of the General Conformity document is added to a subscribed
gas fired units. However, these NOX Determination. docket(s). For assistance with any FERC
emission reductions would not be [FR Doc. E5–3124 Filed 6–16–05; 8:45 am] Online service, please email
enforceable reductions; therefore their BILLING CODE 6717–01–P FERCOnlineSupport@ferc.gov, or call

VerDate jul<14>2003 17:59 Jun 16, 2005 Jkt 205001 PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 E:\FR\FM\17JNN1.SGM 17JNN1

You might also like