Professional Documents
Culture Documents
GS 2c Slope Drainage Stabilization Monitoring
GS 2c Slope Drainage Stabilization Monitoring
SECTION
2c
MONITORING
2c.01
SLOPE
DRAINAGE,
STABILIZATION
AND
2c.02
2c.03
Sand Traps
Unless otherwise specified, sand traps shall be constructed of
Grade 30D reinforced concrete. Steel reinforcing bars shall
comply with Construction Standard CS2: 1995.
Sand trap
surfaces shall have a steel-trowelled finish of 12 mm thick 1:3
cement-sand rendering or an off-form finish with major
imperfections made good as specified.
Precast strip covers shall be in Grade 30D reinforced concrete.
Sand traps shall be provided with mild steel grating, hand
packed rubbles and other components as detailed on the
drawings.
289981917.doc
- S2c/1 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
2c.04
(b)
(c)
(d)
(f)
The fine side of the filter D 15 shall be more than 5 times the
coarse side of the base soil D15.
(b)
(c)
(d)
(e)
289981917.doc
- S2c/2 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
2c.06
2c.07
(b)
(c)
(d)
- S2c/3 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
pipe and before that of the inner pipe, the annular space
between the drillhole and the outer pipe shall be completely
filled with cement grout for 1 m only from the face of the slope.
2c.08
2c.09
Shotcreting Materials
Shotcrete, or sprayed concrete, shall consist of:
(a)
(b)
(c)
(d)
Shotcreting Preparations
A trial panel of minimum size 3 m x 3 m and minimum thickness
50 mm shall be constructed on the surface to be sprayed. This
is to demonstrate, among other things, that the mix is of the
right consistency, the mixing and spraying plant and equipment
are in good working order, and the operatives are competent.
The average percentage rebound shall also be measured and
used as the basis of adjustment to the mix if necessary.
Prior to shotcreting, slope surfaces shall generally be cleaned to
remove loose material, vegetation and other foreign matter that
may prevent good bonding of the shotcrete with the surface. For
rock slopes, the cleaning process has to be carried out with an
289981917.doc
- S2c/4 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
(b)
289981917.doc
- S2c/5 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
2c.12
(b)
289981917.doc
- S2c/6 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
2c.13
2c.14
289981917.doc
- S2c/7 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
289981917.doc
- S2c/8 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
(b)
(c)
(d)
289981917.doc
- S2c/9 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
Proving Tests
Unless otherwise specified, proving tests on working soil nails
shall not be carried out until the grout has attained a cube
strength of 21 MPa. The following procedures shall be followed:
(a)
(b)
(c)
2c.18
2c.19
289981917.doc
- S2c/10 -
Dec 2011
General Specification
Section 2c Slope Drainage, Stabilization &
Monitoring
289981917.doc
- S2c/11 -
Dec 2011