Professional Documents
Culture Documents
A Real-Options-Based Analysis For Supply Chain Decisions
A Real-Options-Based Analysis For Supply Chain Decisions
C IIE
Copyright
ISSN: 0740-817X print / 1545-8830 online
DOI: 10.1080/07408170591008073
Harold and Inge Marcus Department of Industrial and Manufacturing Engineering, The Pennsylvania State University,
University Park, PA 16802, USA
E-mail: hbnembhard@psu.edu
2
Department of Industrial Engineering, University of Wisconsin-Madison, Madison, WI 53706, USA
E-mail: leyuan@engr.wisc.edu
3
Department of Industrial Engineering, Ataturk University, Erzurum, 25240, Turkey
E-mail: maktan2000@yahoo.com
Flexibility allows rms to compete more effectively in a world of short product life cycles, rapid product development, and substantial
demand and/or price uncertainty. We develop a supply chain model in which a manufacturing rm can have the exibility to select
different suppliers, plant locations, and market regions and there can be an implementation time lag for the supply chain operations.
We use a real options approach to estimate the value of exibility and to determine the optimum strategy to manage the exibility
under uncertainty in the currency exchange rate. To price the operational exibility, we develop a Monte Carlo simulation technique
that is able to incorporate a large number of variables into the valuation. We show that without considering time lag impact, the value
of the operational exibility can be signicantly overestimated.
1. Introduction
Manufacturing operations have always been required to
adapt to a changing environment. Some drivers, such as
changes in customer demand and shifts in competition,
have always been present. Other forces (such as higher degrees of product proliferation and a more global marketplace) are relatively recent additions. The domination of
customer demand has also dramatically shifted the product market. Customers require more product diversity and
expect to see new products regularly introduced into the
market. In any case, the change that such forces bring about
typically present signicant challenges for many aspects of
an operation. One strategy has been to increase the exibility of the manufacturing operation. Flexibility allows rms
to compete more effectively in a world of short product life
cycles, rapid product development, and substantial demand
and/or price uncertainty.
In the forward to Real Options (Trigeorgis, 1999), Mason
writes: Flexibility has value. While this statement is obvious at the conceptual level, it is surprisingly subtle at the
applied level. The nancial arena was the original proving
ground for the application of the options-based framework
to the valuation of exibility. More recently, managerial
operating exibility has been likened to nancial options.
Corresponding author
C 2005 IIE
0740-817X
Flexibility is usually acquired at a cost premium; therefore proper valuation of benets is important to justify the
added cost. Without such work rms may under-invest or
make an entirely wrong decision about key technologies
or strategies. Thus, exibility potentially provides a competitive advantage to the rm. The question then becomes:
precisely how valuable is exibility? The goal of real options
valuation is to address this question in an environment of
high volatility.
Nembhard et al. (2000) suggested the need for modeling
the exibility surrounding manufacturing operations using
real options. An important issue in applying real options
to manufacturing enterprises is to incorporate the practical operational concerns of the decision-making into the
existing real options framework (Brach, 2003). Financial
options can be exercised instantly; the trader simply tells
the broker to move the contract and the deal is done. In
the existing body of literature on applying real options, the
common assumption is that a real option can be implemented immediately as well. However, in complex manufacturing operations, this assumption does not truly hold.
Manufacturing operations need some time to be executed.
When a decision is made to exercise a real option, there is
some period of time until the decision can be implemented.
Accordingly, in this paper we consider the implications of
a time lag on real options valuation. The main purposes are
to capture this difference into the framework and to analyze
its effect on the outcome and hence the managerial course
946
of action. To facilitate the work, we adapt current solution
procedures to address this problem. Real options whose values depend on multiple sources of uncertainty, rarely have
closed-form solutions so numerical approximation procedures must be used. Specically, we use a multinomial lattice
approach and we develop a Monte Carlo simulation procedure that can be applied in option valuation analysis when
there is a time lag between the decision and the implementation of the option. We nd that whereas the lattice approach
does make a good approximation, a Monte Carlo simulation procedure can more easily incorporate a large number
of variables into the valuation. Using the proposed procedures, a company will be able to obtain better estimates for
the option value, and to produce optimal decisions considering the effect of a time lag between the decision and
the implementation of the option. We show that without
considering time lag impact, the value of the operational
exibility can be signicantly overestimated.
There has been some research in the nancial engineering
literature that is relevant to this problem. McDonald and
Siegel (1985) presented option pricing techniques to study
the investment problem of a rm that has the option to
shut down or change the level of production. Brennan and
Schwartz (1985) presented a problem where the option was
to open, close, or abandon a mine. Majd and Pindyck (1987)
used options analysis to derive optimal decision rules and
to value investment decisions where construction proceeds
exibly and can be adjusted with the arrival of new information. Hodder and Triantis (1993) presented a general framework for modeling and evaluating investments that involve
having exibility to switch between alternative states of operation. Kogut and Kulatilaka (1994) modeled the operating exibility to shift production between two manufacturing plants located in different countries using a stochastic
dynamic programming model. Huchzermeier and Cohen
(1996) developed a stochastic dynamic programming formulation for the valuation of global manufacturing strategy options with switching costs, where a rm maximizes
its expected, discounted, global, after-tax value through
the exercise of product and supply chain network options
through exploitation of exibility contingent on exchange
rate realizations. Dasu and Li (1997) studied the structure
of the optimal policies for a rm operating plants in different countries. They determined the structure of the optimal
policies for deciding when and by how much to alter the production quantities. Smith and McCardle (1998) presented
how stochastic dynamic programming and option pricing
theory can be protably integrated to evaluate oil properties
where production rates and oil prices both vary stochastically over time and, at any time, the decision-maker may terminate the production or accelerate production by drilling
additional wells. Markov Decision Processes (MDPs) have
been applied to a wide range of stochastic control problems
including inspection-maintenance-replacement systems, inventory management, and economic planning and consumption models. A link between MDPs and options can
be seen through Tsitsiklis work: Tsitsiklis and Van Roy
Nembhard et al.
(1999) developed a theory characterizing optimal stopping
times for discrete-time ergodic Markov processes with discounted rewards; Marbach and Tsitsiklis (2001) proposed
a simulation-based algorithm for optimizing the average
reward in a nite-state Markov reward process that depends on a set of parameters; and Tsitsiklis and Van Roy
(2001) introduced and analyzed a simulation-based approximate dynamic programming method for pricing American
options. Focusing more specically on manufacturing systems, Nembhard et al. (2002) valued real options associated
with the exibility to apply statistical process control charts
to monitor quality in a production process. Nembhard et al.
(2003) studied the option value of being able to switch between the states of producing or outsourcing an item using
Monte Carlo simulation.
In this paper, we extend our research application to value
the real options encompassing the exibility to switch between global manufacturing options for a rm that has
operations in different countries and there may be an implementation time lag for the supply chain operations. The
rm maximizes its expected discounted value through the
exercise of the manufacturing options in an environment
of uncertain exchange rates. The remainder of this paper
is organized as follows. We present the problem formulation in Section 2. Valuation procedures that can be used to
solve the problem, and the proposed solution techniques
for the problem are presented in Section 3. Section 4 gives
the numerical results. We make some concluding remarks
in Section 5.
947
+ er t Vt+1 (et+1 , Ot ).
(1)
p
es as xsp WOt1 Ot
(2)
+e
Vt+1 (et , Ot ).
(3)
(4)
where i is the drift of the exchange rate changes for foreign country i, i is the volatility of the exchange rate
for foreign country i, dz is a standard Wiener disturbance
term. The expected changes in the exchange rates are set to
i = exp[(r ri )t], where t is the length of each time
interval, and r and ri are the risk-free rate of return in the
home country and country i, respectively.
In the next section, we discuss two option valuation methods that can be used to model the state variable movements
for this problem, and we present our procedures that use
these two methods for valuation of the problem with the
feature of implementation time lag.
948
Nembhard et al.
t
949
+ er t
n
(5)
j=1
+e
j=1
r t
(6)
j=1
(7)
n
pj et+1,j .
j=1
Therefore, apart from a discount factor of a possible switching cost, the expected prot due to the optimum decision
given at time t and implemented with a time lag at t+1,
and the prot due to the optimum decision given at time t
and implemented immediately at time t, are in fact equal.
Hence, the optimum strategy that will be implemented at
time t+1 in the time lag problem, and the resulting prot
value can both be determined by nding the optimum decision for time t in the original lattice without time lags. Prot
at the rst time interval for the time lag problem can be calculated using the given strategy that must be implemented
at the rst time interval.
With lattice methods, calculation effort increases dramatically with an increasing number of state variables, which
makes them impractical and difcult to use when there are
more than two state variables in a model. In Section 3.2,
we propose a Monte Carlo simulation technique, which
simplies valuing exibility in models with multiple state
variables.
3.2. The Monte Carlo simulation technique
Boyle (1977) introduced a Monte Carlo simulation method
for asset pricing of European options. This approach,
however, cannot be used for problems with switching
costs since the problem cannot be treated as a bundle of
European options with different expiration dates. Broadie
and Glasserman (1997) developed a simulation algorithm
for estimating the prices of American-style assets. In order to develop valid error bounds on the true option value,
they introduced two estimators, one biased high and one
biased low, but both asymptotically unbiased as the computational effort increases. These estimators are based on
simulated lattices. The simulated lattices are parameterized
by b, the number of branches per node. State variables are
simulated at a nite number of possible decision points, i.e.,
exercise times.
In this section, we develop a Monte Carlo simulation procedure that can be used to value the problem in Section 3.1
which has nonzero switching costs, multiple decision points
to switch between the options, and time lags between the
decision and the implementation. There are signicant
differences between the American stock option and the
given manufacturing strategy planning problem with supply chain network: a stock option is exercised instantly, but
950
Nembhard et al.
itm =
t 1 is i:
gijt (s) = E[hijt (s) + eR fj,t+1 (St+1 ) | St = s],
fit (s) = max {gilt (s)} .
l=1,...,k
b
b
b
1
n
n
n
1
1
R
R
hilt St + e l,t+1 =
hiit St + eR i,t+1 ,
hiit St + e i,t+1 if max
l=1,...,k
b n=1
b1 n=1
b1 n=1
n = m
n = m
b
b
b
1
n
n
n
1
1
R
R
S
+
e
h
S
+
e
hijt St + eR j,t+1 ,
=
h
if
max
ijt
j,t+1
ilt
l,t+1
t
t
l=1,...,k
b n=1
b1 n=1
b 1 n = 1,
n = m
Figure 4 shows the effect of decisions in a two-step simulated tree for b = 3, where et,j is the vector of exchange
rates at time interval t and node order j.
We use the following notation for the procedure:
t
= 0, 1, . . . , T and is the time index;
{St : t = 0, 1, . . . , T} = a risk-neutralized Markov chain
recording all state variables;
= a discount factor for one time
eR
interval.
Also, hijt (s) is the prot in time interval t by exercising option j in state s, if the previously exercised option in time
n = m
for m = 1, . . . , b. Then let it = (1/b) bm=1 itm for t =
0, . . . ,T 1. To simulate the path followed by ei , we approximate Equation (4) as:
i2
t + i t . (8)
ei (t + t) = ei (t) exp i
2
Now, we give a example for the application of our procedure. Assume that we only have two manufacturing options
and two decision points. W12 = $4.0 is the switching cost
from option 1 to option 2, and W21 = $3.0 is the switching
cost from option 2 to option 1. Assume that by running
a single simulation run, we have generated the values of
the state variables at each node in the tree, and using the
generated values, we have calculated the prots for each
node as given in Fig. 5. The values in parentheses are the
prots in the home countrys currency for option 1 and option 2, respectively. For simplicity of the calculations, we
assume that the risk-free rate of return is zero.
Assume that the current strategy is option 1, i.e., the option that is applied in the initial node is option 1. Figure 6
shows the high estimates in the tree, and the options that
yield the high estimates. We begin to work on the tree from
the last time interval. To nd the high estimate, we calculate
the expected prot of b branches to select the best manufacturing option to be implemented in those branches.
As a sample calculation, let us use the top three branches
in the last time interval. If we apply option 1, the average
prot is (80 + 120 + 90)/3 = 96.67. If we apply option 2, the
average prot is (70 + 100 + 110)/3 = 93.33. If the previous
option was option 2, and if we decide to switch to option 1,
then the average prot is 96.67 3 = 93.67 > 93.33. Then,
switching to option 1 gives a larger prot value than keeping
951
option 2. Therefore, whatever the previous option is, we
should select option 1. In Fig. 6, the values (96.67, 93.67)
represent the prot estimates for the previous options 1
and 2, respectively. After completing the calculations for all
branches in the last time interval, we move to the previous
time interval. If we apply option 1, the prot estimate is
[(110 + 96.67) + (90 + 96.67) + (95 + 100)]/3 = 196.11. If
we apply option 2, the prot estimate is [(100 + 93.67) +
(110 + 100) + (90 + 97)]/3 = 196.89. The difference between
the two prot estimates is 196.89 196.11 = 0.78, which is
smaller than W21 . This means that we must continue with
the previous option. Then, for the three time intervals, we
get a total prot estimate of 100 + 196.11 = 296.11, which
is the high estimate.
Figure 7 shows the low estimates and the options that
yield the low estimates. In order to calculate a low estimate,
we use b 1 branches to determine a policy, and we apply
that policy in all b branches. We repeat this process for the
b possible combinations of b 1 branches. Then, we take
the average of prot estimates obtained from these b combinations. As a sample calculation, let us use the top three
branches in the last time interval. If we apply option 1 to
the rst and second branches, the prot estimate is (80 +
120)/2 = 100. If we apply option 2 to those branches, the
prot estimate is (70 + 100)/2 = 85. Since the difference
between the prot estimates is 100 85 = 15 >W21 , we
select option 1 whatever is the previous option. If we apply
option 1 to the rst and third branches, the prot estimate
is (80 + 90)/2 = 85. If we apply option 2 to those branches,
the prot estimate is (70 + 110)/2 = 90. We see that the difference between the prot estimates is 90 85 = 5 > W12 .
Thus, if the previous option is option 1, and if we switch to
option 2, the estimated prot is 90 4 = 86 > 85. Then,
whatever is the previous option, we select option 2. If
we apply option 1 to the second and third branches, the
average prot is (120 + 90)/2 = 105. If we apply option 2 to
those branches, the average prot is (100 + 110)/2 = 105. We
952
Nembhard et al.
4. Numerical results
In this section, we present the results of the lattice and
Monte Carlo simulation approaches using a case example.
A rm wants to maximize its prot from the operations on
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
953
next time interval. The lower line shows the expected prots
when there is no switching between the options. The horizontal axis shows which manufacturing option has been
used prior to the rst time interval in the problem.
If the decisions can only be implemented with a time lag,
and if we ignore this limitation and solve the problem as
if there is no time lag for the implementation, then we will
overestimate the value of exibility. The amount of overestimation is the distance between the upper line and the middle
line in Fig. 9. When a decision cannot be implemented in
the rst time interval immediately, we must implement the
strategy that was selected before the decision time horizon,
whereas a strategy can be selected and implemented immediately in the rst time interval when there is no time lag.
Therefore, if the strategy selected before the rst time interval is not the optimal strategy for the rst time interval,
then there is a prot loss because of implementation time
lag. At the same time, the best strategy can be selected and
implemented at the last time interval when there is no time
lag, but a strategy which was selected earlier without observing the last state will be implemented in the last time
954
Nembhard et al.
955
Lattice
Simulation
Percentage difference
10
11
12
1587
1588
0.11
1740
1701
2.23
1795
1785
0.57
1949
1905
2.28
1472
1469
0.21
1620
1585
2.17
1670
1661
0.58
1819
1778
2.27
1735
1735
0.03
1939
1897
2.16
2044
2035
0.43
2248
2230
0.78
5. Conclusions
Flexibility allows rms to compete more effectively in an
environment of uncertainty. A real options approach estimates the value of exibility and is used to determine the
optimum strategy to manage the exibility. In this study,
we incorporated the practical operational concerns of
decision-making in manufacturing enterprises into the existing real options framework by considering the case where
there may be an implementation time lag. The main purposes were to capture the difference between immediate implementation and the time lag into the framework, and to
analyze the effect on the outcome and hence the managerial
course of action. We adapted current solution procedures
to address this problem. We found that when there is a
time lag, the option value is smaller than the case of immediate implementation. However, the ratio of the option
value decrease to the total option value becomes smaller
when the number of time intervals in the analysis increases.
Therefore, the necessity to analyze the effect of the implementation at the time lag decreases with an increasing number of decision points in the analysis time horizon.
The real options valuation procedures discussed in this
paper give decision-makers a way to choose the appropriate
manufacturing enterprise strategy based on an integrated
view of the market dynamics. We have presented the application of the procedures to a supply chain network with
uncertain exchange rates, where costly switching decisions
for the suppliers, production plants, and market regions require a time lag to be implemented. Overall, the manufacturing enterprise maximizes its expected discounted prot
through effective decisions to exercise real manufacturing
options across the supply chain. In such problems, there
are multiple options. At each time interval, switching between options is possible, and each switch results in a switching cost. A comparison of the results for the Monte Carlo
simulation procedure and the lattice procedure has shown
Acknowledgement
This research has been partially supported by the National
Science Foundation under award #135-8459.
References
Amin, K.I. and Khanna, A. (1994) Convergence of American option values from discrete to continuous-time nancial models. Mathematical
Finance, 4, 289304.
Boyle, P.P. (1977) Options: a Monte Carlo approach. Journal of Financial
Economics, 4, 323338.
Boyle, P.P. (1988) A lattice framework for option pricing with two state
variables. Journal of Financial and Quantitative Analysis, 23(1), 112.
Boyle, P.P., Evnine, J. and Gibbs, S. (1989) Numerical evaluation of multivariate contingent claims. The Review of Financial Studies, 2(2),
241250.
Brach, M. (2003) Real Options in Practice, Wiley, Hoboken, NJ.
Brennan, M.J. and Schwartz, E.S. (1985) Evaluating natural resource
investments. Journal of Business, 58(2), 135157.
Broadie, M. and Glasserman, P. (1997) Pricing American-style securities
using simulation. Journal of Economic Dynamics and Control, 21,
13231352.
Cox, J.C., Ross, S.A. and Rubinstein, M. (1979) Option pricing: a simplied approach. Journal of Financial Economics, 7, 229263.
Dasu, S. and Li, L. (1997) Optimal operating policies in the presence of
exchange rate variability. Management Science, 43(5), 705722.
Hodder, J.E. and Triantis, A.J. (1993) Valuing exibility: an impulse control framework. Annals of Operations Research, 45, 109130.
Huchzermeier, A. and Cohen, M.A. (1996) Valuing operational exibility
under exchange rate risk. Operations Research, 44(1), 100113.
Kamrad, B. and Ritchken, P. (1991) Multinomial approximating models for options with k state variables. Management Science, 37(12),
16401653.
Kogut, B. and Kulatilaka, N. (1994) Operating exibility, global manufacturing, and the option value of a multinational network. Management Science, 40(1), 123139.
Majd, S. and Pindyck, R.S. (1987) Time to build, option value, and investment decisions. Journal of Financial Economics, 18, 727.
Marbach, P. and Tsitsiklis, J.N. (2001) Simulation-based optimization of
Markov reward processes. IEEE Transactions on Automatic Control,
46(2), 191209.
McDonald, R. and Siegel, D. (1985) Investment and the valuation of
rms when there is an option to shut down. International Economic
Review, 26(2), 331349.
956
Nembhard, H.B., Shi, L. and Aktan, M. (2002) A real options design for
quality control charts. The Engineering Economist, 47(1), 2859.
Nembhard, H.B., Shi, L. and Aktan, M. (2003) A real options design for
product outsourcing. The Engineering Economist, 48(3), 199217.
Nembhard, H.B., Shi, L. and Park, C.S. (2000) Real option models for
managing manufacturing system changes in the new economy. The
Engineering Economist, 45(3), 232258.
Smith, J.E. and McCardle, K.F. (1998) Valuing oil properties: integrating option pricing and decision analysis approaches. Operations Research, 46(2), 198217.
Trigeorgis, L. (1999) Real Options, MIT Press, Cambridge, MA.
Tsitsiklis, J.N. and Van Roy, B. (1999) Optimal stopping of Markov
processes: Hilbert space theory, approximation algorithms, and an
application to pricing nancial derivatives. IEEE Transactions on
Automatic Control, 44(10), 18401851.
Van Roy, B. and Tsitsiklis, J.N. (2001) Regression methods for pricing
complex American-style options. IEEE Transactions on Neural Networks, 12(4), 694703.
Biographies
Harriet Black Nembhard is an Associate Professor and Bashore Career
Professor in the Harold and Inge Marcus Department of Industrial and
Manufacturing Engineering at The Pennsylvania State University. She is
Nembhard et al.
also the Principal Investigator of the Laboratory for Quality Engineering
and System Transitions (QUEST). Her research interests are in the areas
of applied statistics and nancial engineering with applications to manufacturing, health care, and global sustainability. She received her Ph.D. in
Industrial and Operations Engineering from the University of Michigan
in 1994. She is a member of IIE, INFORMS, ASQ, and a past president
of the Engineering Economy Division of IIE.
Leyuan Shi is a Professor in the Department of Industrial Engineering at
the University of Wisconsin-Madison. She received her Ph.D. in Applied
Mathematics from Harvard University in 1992. Her research interests
include simulation modeling and large-scale optimization with applications to operation planning and scheduling, supply chain management,
transportation, and health care systems. She is serving on the Editorial
Boards of the Journal of Discrete Event Dynamic Systems, INFORMS
Journal on Computing, and Journal of Methodology and Computing in
Applied Probability. She also chairs the Outstanding Publication Award
Committee for the INFORMS College on Simulation.
Mehmet Aktan is an Assistant Professor in the Department of Industrial
University, Turkey. He received his Ph.D. from
Engineering at Ataturk
The University of Wisconsin-Madison, his M.S. from The University of
Iowa, and his B.S. from Bogazici University. He is the co-author of several
research publications in the nancial engineering area.