Professional Documents
Culture Documents
Solutions To Questions
Solutions To Questions
3.25"
.71
3.1
1.18
3.22
1.43
3.39
1.26
3.07
1.17
2.86
.32
3.05
.53
2.65
1.13
3.02
.71
10
2.85
1.33
11
2.83
1.17
12
2.97
.4
13
3.11
.85
14
2.83
1.31
15
3.12
1.06
16
2.84
.50
17
2.86
1.43
18
2.74
1.29
HOUR
19
3.41
1.61
20
2.89
1.09
21
2.65
1.08
22
3.28
.46
23
2.94
1.58
24
2.64
.97
The Bill of materials for a finished product "E', inventory status, and other
relevent information are given below. Compute the planned order releases
and projected on-hand balances for parts E, F, and M.
E
A
B
F
2 required
3 required
2 required
L
M
Part E
20
20
40
Projected On-hand 20
Inventory
20
20
40
40
40
80
Gross Requirements
Scheduled Receipts
Part F
Gross Requirements
Scheduled Receipts
50
80
130
90
90
10
Inventory
80
130
130
90
10
40
40
80
Part M
Gross Requirements
40
40
80
Scheduled Receipts
60
Projected On-hand 10
30
30
40
Inventory
30
40
40
80
gross reqmnts
scheduled receipts
projected
available
net reqmnts
planned order
receipts
planned order
releases
gross reqmnts
scheduled receipts
projected
available
net reqmnts
planned order
receipts
planned order
releases
gross reqmnts
scheduled receipts
projected
available
net reqmnts
planned order
receipts
planned order
releases
1
20
2
0
3
0
4
20
5
0
6
40
20
30
30
40
20
10
50
50
120
50
50
40
0
50
40
80
80
80
130
90
90
60
0
50
50
10
40
60
40
80
30
30
30
50
50
30
60
10
30
60
60
60
Explanation is as follows:
For part E,
Given, lot size = 50, Lead time = 2 periods, Safety stock = 0
On October 10, 2015 you could buy Colombian Pesos for 1$ = 2806
On August 13, 2015 the rate was $1 = 2762
On September 1, 2015 the rate was $1 = 3200 pesos [these were the actual
rates]
Assuming you have a time machine and a million dollars to play with. What
would you do? How much money could you make?
Assume banks are open on Columbus Day in the US.
The demand of the winter jacket varies over the week (7 days). The
average demand per week is 50 items. Given that the retailers order
lead time is two days, the average lead time demand is 16 items and the
standard deviation during lead time is 3 items. Acceptable stock-out risk
during is considered 4% (96% service level).
[Hints: for 95% service level, z = 1.64, you need to find Z value for 96%
service level]
What amount of safety stock is appropriate?
When should this item be reordered (ROP)?
Assuming the retailers order interval is one week and lead time is same
as two days. The average on-hand inventory is five items at the end of
each week.
[Hints: You will need to determine the standard deviation for the time
period between order placement (i.e., one week) using the standard
deviation for lead time period.]
Determine the order quantities using fixed order interval model
Determine the reorder point (ROP) using variable demand model
Z value for 96% service level from service level and Z value table is 1.751
Safety stock = z*Std. dev = 1.751*3 = 5.253 = 5 items
ROP = Demand during lead time + Safety stock = 16+5 = 21 items