Professional Documents
Culture Documents
Site Assessment Report - For Study
Site Assessment Report - For Study
Site Assessment Report - For Study
WAPCOS LIMITED
(A Government of India UndertakingMinistry of Water Resources, River Development & Ganga Rejuvenation)
76-C, Institutional Area, Sector - 18, Gurgaon-122015
Gurgaon - 122015
FEBRUARY 2015
BACKGROUND
NTPC has recently taken up the execution of its coal based power project of
3x660 MW capacity at North Karanpura in Hazaribag district of Jharkhand. The
water for the project is envisaged to be drawn from river Garhi for the purpose of
Water Cooling requirements for the Thermal plant.
1|Page
Gondwanas
predominantly
comprise
Mahadevas,
Raniganj,
Barren
It is pertinent to make a mention of the coal deposits in the project area. Three
bore-holes have earlier been drilled in village Laranga on the right flank of Garhi
River downstream of the proposed dam site. These holes have been drilled to
depth of 300 m, 250 m and 200 m respectively. Coal seams are reported to have
been encountered in holes around 200 m depth. These holes are reported to have
Site Assessment Report
2|Page
started in Raniganj formation. The coal mines around Piparwar are mostly open
cast.
5.0 INVESTIGATIONS CARRIED OUT AT THE EARLIER DPR STAGE
Geological / Geo-Technical investigations
Since the depth of the bed rock is shallow, sufficient no. of boreholes were
made at DPR stage instead of relying on geophysical investigation.
The
boreholes along the dam axis have indicated that foundation rock, which is
generally semi-impervious in nature, is available at shallow depth within 8 m
and the overburden material is mostly pervious in nature. For the purpose of
the earth materials laboratory tests were conducted for the physical and
strength characteristics of the soils from various borrow areas. Borrow area
investigation indicated the sufficient availability of desired quality and quantity
of earth materials for construction purposes.
Hydrological Observations
No hydrological observations on the river Garhi was available for arriving at the
hydrological design parameters of the storage dam. A gauge-discharge site
was established by WAPCOS on the river Garhi and daily discharge
measurements were taken from 19.09.1999 to 19.12.1999. This actual
discharge observations were for supplementing the other existing hydrological
/river flow data in the upper Damodar river basin for assessing water availability
and other hydrological studies.
6.0 REVISED PROPOSAL FOR THE REDUCED WATER DEMAND
Due to the changes made in the plant cooling system (from water cooling to air
cooling), the consumptive water requirement of the plant has reduced from 90
cusecs to 20 cusecs (18 MCM approx.). NTPC has accordingly requested
WAPCOS to assess the possibility of constructing a low height weir / barrage for
storage of water and pumping the same to an in-plant storage reservoir for its
revised water requirement of 20 cusecs (18 MCM approx.). The structure is
proposed to be located at a close proximity to the high level road Bridge Site
across River GARHI. Water stored at the proposed barrage location shall be
Site Assessment Report
3|Page
conveyed thru a buried pipe line to the in-plant reservoir by pumping it from the
pump house envisaged close to the proposed weir/barrage location.
7.0
The proposed location of a low height weir/barrage near the road bridge site is
around 5Kms upstream of the Dam location proposed in the DPR prepared by
WAPCOS. Since no data/ details are available at the proposed location, the
existing reports prepared by RITES Ltd. for the Road Bridge as well as the Data
on the hydrological studies available in the earlier DPR prepared by WAPCOS
Ltd. have been referred for a preliminary assessment.
The Thermal Power Plant requires a sustained water supply and the sources like
Ground Water option and Surface Water through direct pumping or through a
system of infiltration galleries do not appear to provide an uninterrupted source of
supply throughout the project operation period.
4|Page
The team was also apprised that a Connecting road is proposed from the NH to
the Thermal Plant which crosses the river near the Tandwa village about 1.5 km
D/s of the existing road bridge near Surya Mandir. A bridge has already been
proposed at this location to cross the river. The River width at the proposed
location is about 200-250 m. The river alignment is almost straight up to about 1.5
km U/s where the confluence of two rivers converge. The river course at the
proposed location is well defined. The river slope is almost flat as in the plain
area. The Slope of the river appears to be in the range of 1 in 400-500. The
material on the river banks in the vicinity of the proposed structure appears to be
Silty clay type soil. The water level in the river during monsoon period was
observed to be about 3-4 m above the river bed. The river bed material similar to
silty sand type.
It was also informed that the River carries a lot of silt load during the monsoon
period. No sediment inflow data are available in the Garhi catchment. Some data
of adjoining catchment of the Barakar at Maithon reservoir are available. The
average rate of silting at Maithon reservoir is 1.02 mm/year. The Maithon reservoir
also lies in the Damodar river basin as that of Garhi river basin with almost similar
catchment characteristics. A long term average silt rate of 1 mm/year appears
reasonable and is therefore adopted for the present assessment studies.
Accordingly, it is suggested that adequate silt flushing arrangement need to be
explored and provided in the proposed Barrage after detailed investigations.
The Area plan of the Project demarcating the Proposed Barrage location as well
as the earlier Dam location is enclosed as Annexure-II.
8.0
CONCLUSIONS
The river Garhi, a tributary of the Damodar, is a non-perennial river. The flows in
the Garhi River are mainly dependent on monsoon precipitation. The average
annual rainfall in the region is around 1350 mm. The catchment is mostly rocky &
sandy interspersed with jungles & bushes.
Site Assessment Report
5|Page
It was observed at site and also appraised by the NTPC site officers accompanying the
team that sound rock may be available at a depth of around 4-5 meters below the NSL at
the proposed road bridge location. Accordingly, it is opined that a raised crested barrage
adjoining the road bridge would be most suitable proposal for storage of water. The
barrage could be raised over a RCC raft with a u/s and d/s cut off for achieving a safe exit
gradient of seepage flow. Consolidation Grouting below the foundation of the Barrage
need to be adequately planned.
NTPC apprised to provide the guide embankment on either bank of the River as close to
the river course as possible to minimize the submergence area. The river banks on either
side of the river at the proposed Barrage site are proposed to be treated with stone
pitching or boulders in wire crates up to the required height & length for containing the
water within the guide banks. It is preliminary estimated that the embankment length may
be around 1.50 Kms and more on each bank which can be confirmed after detailed
topographical surveys.
The WAPCOS team members are of the view that the Road Bridge can be located on the
proposed Barrages Piers thereby omitting the requirement of Bridge sub-structure (i.e.
deep Pile foundations & Pile cap etc.).
The barrage is planned to be provided with vertical lift fixed wheel type hydraulic gates
electrically operated by means of rope drum hoists for storage of water u/s of barrage.
The rope drum hoists shall be placed on a raised platform over steel trestles. One set of
stop log units operated by means of a monorail crane placed on the extended arm from
the hoist bridge shall suffice for any emergency gate requirements (Refer sketch
enclosed as Annexure-IV.)
Site Assessment Report
6|Page
Since, the SEDIMENT LOAD of the river appears to be quiet high, it would be desirable
to restrict the entry of silt into the pump intake. The River slope is almost flat at the
proposed barrage location, it is apprehended that suspended silt would settle down at a
fast rate after the structure is raised. The heavy suspended silt load shall enter the pump
intake and may choke the suction sump and pipes. Since provision of a de-sander with a
flushing arrangement would be a costlier option, the following alternatives are being
proposed for removal of silt and its flushing so as to optimize the pumping operations.
The structural arrangement as well as all other design details / parameters shall be
worked out after further investigations including the river silt studies, in-plant reservoir
simulation studies etc.
1. Alternative. 1.
invert. The Intake for the pump house shall be located very close to the silt
flushing bays at the right bank of the river towards the thermal plant. A raised
crest with its top level below MDDL and above the Sluice invert is proposed all
around the intake to the pump house for reducing the entry of silt. (Sketch 1
enclosed as Annexure IV)
2. Alternative .2.
towards the U/s and adjoining the raised crest all around the pump intake. The
invert of the cunnette shall have a steep slope and connected to a pipe having a
control valve for flushing operations towards the d/s of barrage. (Sketch 2
enclosed as Annexure V)
3. Alternative .3. The suction chamber below the riser pipes of the pumps could be a
hopper shaped with provisions of flushing the silt via pipe line equipped with a
control valve. This alternative could be planned in combination with the measures
listed at alternative 1&2 above (Sketch 3 enclosed as Annexure VI)
4. Alternative .4. A geotextile filter membrane could also be installed in the trash rack
units or separately in order to restrict the entry of suspended silt load along with
trash. Or else a system of pipes wrapped in geotextile filter material could be
installed at various levels around an intake well for water diversions. Arrangement
shall be provided to clean the choked geo-filter at regular intervals by back water
7|Page
8|Page
Annexure-I
List of team members during the site visit on 8th January, 2015 to North Karanpura Super Thermal
Power Project site
NTPC
WAPCOS
ANNEXURE-II
Annexure - III
Preliminary Assessment of Water Availability at the Proposed Barrage
1
2
3
4
5
6
7
8
9
Inputs/Assumptions
Details
River bed level
Barrage U/s Raft top level
Barrage Crest level
Undersluice Invert El
MDDL
FRL
Top El of Gate
Deck EL of Bridge
Top of Barrage Piers at Crest location
10
11
Priliminary Assessment
Volume of 90% dependable flow in Garhi River at Old
Dam Axis
Refered from
M/s RITES bridge documents
Unit
m
m
m
m
m
m
m
m
m
Value
433.00 approx.
433
434.5
433
434.5
437.5
439
441.00 approx.
444
200
1 in
500
MCM
67.00
As per DPR
assuming the Catchment area of the Proposed
Barrage Axis is 80% of the Catchment area of the
old dam location
MCM
53.60
MCM
18.00 Approx.
assumed
assumed
M/s RITES bridge documents
assumed as per visual observations during site
visit
assumed as per M/s RITES Document & Visual
Observations during Site Visit
FRL-MDDL
MDDL-River Bed Level
Live storage
m
m
MCM
3
1.5
0.9
750.00 m
1500.00 m
FRL Line
3.00 m
Flow
Barrage Axis
MDDL Line
Pumping Requirement
Assuming that The in plant Reservoir is filled up with 18 MCM in two months (considering the uncertainty if occurred during any year),
although water flow is available for five months
days
60
3
4
5
MCM
hrs
cumec
cusec
cumec
nos.
0.3
16
5.21
50.00
1.42
3.68
6
7
Note : The priliminary computaions provided above are based on the observations during Site Visit & limited data. The Computed design
parameters may undergoes changes and other Design Parameters shall be assessed after Detail Investigations/Survey
Annexure-IV
Annexure-V
Annexure-VI
Annexure-VII
Annexure-VIII