Download as pdf or txt
Download as pdf or txt
You are on page 1of 41

SECURITY AND DIVERSIFICATION

OF SUPPLIES WITH THE TWIN


PRIORITIES OF IMPROVING SAFETY
AND ENVIRONMENTAL IMPACT

AGENDA

1. General presentation
2. Site location: connections to Belgium and French gas systems
3. Developing EPC strategy
4. Use of the cooling water discharged from Gravelines nuclear power
plant
5. Improving safety by demonstrating tanks ability to support overfilling
6. Improving safety by using state of the art sea protection
7. Erection status to date

I LNG Tech S. Ringot I 04 dcembre 2012

General presentation

I LNG Tech S. Ringot I 04 dcembre 2012

TERMINAL MAIN CHARACTERISTICS


Commercial capacity

Storage (m3)

Jetty

Emission flow rate

13 bcm/y (# 9.2 mtpa)

3 tanks of 190,000 m3
570,000 m3 total

0 1,9 Mm3/h

Ship sizes:
75,000 270,000 m3
flare

53 ha plateform

GRTgaz (French grid)


Fluxys (Belgian grid)

Re-gasification technology
ORVs using cooling water discharged
from the nearby nuclear power plant

I LNG Tech S. Ringot I 04 dcembre 2012

DUNKERQUE LNG STRUCTURATION

Dunkerque LNG : EDF subsidiary

65%

25%

10 %

Pacte dactionnaires

Fluxys

Belgium gas TSO

Zeebrugge LNG terminal operator

Total

8 Bcma

Main Oil & Gas player

2 Bcma

3 Bcma

Contrats de rservation de capacit

Gaz Opale

Dunkerque LNG & Fluxys subsidiary

Dedicated to terminal operation

I LNG Tech S. Ringot I 04 dcembre 2012

Disponibles

Dunkerque LNG participates with partners in INNOCOLD, Institute of LowTemperature Technology, for :

Research topics (materials, industrial safety, process efficiency)

Training in cold technologies

Test facility development

I LNG Tech S. Ringot I 04 dcembre 2012

Site location : connections to Belgium


and French gas systems

I LNG Tech S. Ringot I 04 dcembre 2012

CONNECTION OF DUNKERQUE LNG TERMINAL TO FRANCE

Has triggered 1,2 G investment on the


French gas network to connect the terminal
and reinforce the transmission system,
allowing to send out 520 GWh/d (13 bcma)

GRTgaz is thus laying down a 170 km


pipeline with a diameter of 1200 mm

The natural gas will not be odorized after


measuring and before being piped into the
transmission system

For the first time in France,


GRTgaz

a no odorized pipeline: a first step towards a


wider no odorized gas transmission system in
France ?

8
I LNG Tech S. Ringot I 04 dcembre 2012

CONNECTION OF DUNKERQUE LNG TERMINAL TO BELGIUM

Dunkerque LNG pushed GRTgaz and Fluxys


Belgium to extend the pipeline to Belgium and
thus create a direct connection of the terminal to
Belgium

In an European first, a new concept: a single


Fluxys contract for cross-border capacity
between Dunkirk terminal and the Belgian
system

GRTgaz and Fluxys Belgium will lay down a nearly 100 km pipeline offering thus a 8 bcma capacity
from France into the Belgian system on a firm basis

The new capacity is expected to be ready for use by late 2015, to coincide with the commissioning of
the LNG terminal in Dunkirk

Dunkerque LNG terminal offers through a direct connection to 2 major markets,


a gateway to supply gas to NW Europe
9
I LNG Tech S. Ringot I 04 dcembre 2012

Developping EPC strategy

I LNG Tech S. Ringot I 04 dcembre 2012

10

EPC STRATEGY
Reach a cost As Low As Possible is a common goal for all
project developers
Classical EPCC contracts all in one , despite some real
avantages, suffers

A limitation of competition (number of Tanks manufacturers / number of


engineering compagnies)
Mixing very different activities within only one contract (severability,
liabilities)
A huge amount, among wich any claims seems so little

Dunkerque LNG choice was to split on three homogenous


contracts :

Process, throught an engineering compagny :

Tanks, throught a consortium :

Tunnel, also throught a consortium :


I LNG Tech S. Ringot I 04 dcembre 2012

11

INDUSTRIAL ORGANISATION
Rseaux

Matrise
douvrage

Terminal mthanier

Installations portuaires

Dunkerque LNG

GPMD

GRT gaz

COFIVA :

Dpartement
Grands Projets

EDF Ingnierie
SOGREGAZ,

Lot 3 : GC Ctier

Lot 1 : Prparation

Lot 2 : Dragage

Lot 4 : Mesures Comp.

I LNG Tech S. Ringot I 04 dcembre 2012

ARCADIS

Lot Tunnel BRS

Lot Rservoirs EP-BY

Fourniture tubes

Pose tubes

Ralisation

TSLNG

MOE : Lot Process TS LNG

Matrise
duvre

Centre
dingnierie
GRTgaz

12

Use of the cooling water discharged from


Gravelines nuclear power plant

I LNG Tech S. Ringot I 04 dcembre 2012

13

Reach a 0 CHG emission goal


Zero CHG terminal was a major objective of Dunkerque project
since the begining
First decision was to collect every emission of LNG and gas to
flare systems

TSV and PSV on every lines

ORV and Tanks (hight flow-rate) are collected throught a specific system

Second challenge was to face the sea-water temperature in


winter (-4C as a minimum) :

Dual system (ORV / SCV et ORV / sea-water heater) has been designed

A tunnel solution, from Western to Eastern part of harbour, associated


with ORV, has been designed

Economical comparison has been carried out

TUNNEL (5km) was the optimum solution


Tender result has confirmed this choice
I LNG Tech S. Ringot I 04 dcembre 2012

14

OVERVIEW OF TUNNEL

I LNG Tech S. Ringot I 04 dcembre 2012

15

FULLY BORED IN FLANDER CLAY


Terminal platform
(+10 m CMG)

Tunnel (-40 m CMG)

Exhaust pit ( 16m)

CNPE pits
I LNG Tech S. Ringot I 04 dcembre 2012

16

GRAVELINES POWER : WATER INTAKE

Sea-water
intake (during
unit
maintenance)
inlet pits

EXHAUST PIT : D-WALL OVER 65 METER DEPTH


Main challenge was the verticality, with a requested deviation
of less than 260 mm at -65 m from top.

The result is better than


110 mm
Including for the part
digged in clay (30 m)

I LNG Tech S. Ringot I 04 dcembre 2012

18

EXHAUST PIT : D-WALL OVER 65 METER DEPTH


Waterstop CWS welding technique was used at -55m (first of a
kind)

I LNG Tech S. Ringot I 04 dcembre 2012

19

Improving safety by demonstrating tanks ability to


support overfilling

I LNG Tech S. Ringot I 04 dcembre 2012

20

TANK ABILITY TO SUPPORT OVERFILLING


French regulation request that the consequences of any
danger that cannot be demonstrated as impossible must be
studied in detail
Despite all the safety barriers, an overfilling cannot be
qualified of impossible
Tank design has been slightly modified to take into account
this accidental case
This has been achieved by designing a frangible dome roof

The roof is set to fail at a predetermined over pressure,

The slab and wall are set to remain structurally able to hold the liquid

I LNG Tech S. Ringot I 04 dcembre 2012

21

SEQUENCE OF EVENTS
t=0: start of overfilling

From 0 to 40 s after start of overfilling:


Total evaporation of LNG in contact with the
warmer elements of the annular space
Internal gas pressure increases quickly
dome frangibility happens at 757 mbarg (safe
margin / operation : 2.5 x design pressure)
I LNG Tech S. Ringot I 04 dcembre 2012

22

DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (1/4)


Overview of dome roof structure arrangement

I LNG Tech S. Ringot I 04 dcembre 2012

23

DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (2/4)


Welds failure happens first

I LNG Tech S. Ringot I 04 dcembre 2012

24

DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (3/4)


Welds failure leads to large displacement

P2 = 757 mbarg weld failure


Tension redistributed in rebars
Rebar plastification; large rebar deformation
Separation dome / rafter

I LNG Tech S. Ringot I 04 dcembre 2012

25

DESCRIPTION OF HOW IS TANK FRANGIBILITY ACHIEVED (4/4)


Large displacements leads to dome cracking

P2 = 757 mbarg weld failure


Tension redistributed in rebars
Rebar plastification; large rebar deformation
Separation dome / rafter
Cracking of dome
Gas flow => overpressure evacuated
I LNG Tech S. Ringot I 04 dcembre 2012

26

Improving safety by using state of the art


sea protection

I LNG Tech S. Ringot I 04 dcembre 2012

27

STATE OF THE ART SEA PROTECTION


During the 1990s, and beginning of 2000s, several bad
weather conditions leads to industrial damage in France
LNG Terminal took into account sea-water protection from the
early design, regarding :

Static level of plateform,

Wave protection.

Static protection was achieved with a plateform level of +10 m


CMG (Gravelines Coastal Level), including some provision for
climate change
Methodology for wave protection is not define nor requested
by regulation or standard.

I LNG Tech S. Ringot I 04 dcembre 2012

28

DEFINITION OF PROJECT CRITERIA


Criteria for dike design :

Stability for W100 / L100 (stands for 100 years return period)

Limited (less than 5%) disorders for W100 / L1000

No overtopping for W10 / L10 (stands for 10 years return period)

Additionnal protection (sea walls) have been designed to


obtain a level of protection defined per :

a wave climate of W100 / L100


a protection level :

LNG pipes : no over-topping

Gangways : < 3 l/s/ml

Roads : 10-50 l/s/ml

Protection efficiency has been checked under W100 / L1000 wave


climate.

I LNG Tech S. Ringot I 04 dcembre 2012

29

SPECIFICATION FOR SEA PROTECTION

I LNG Tech S. Ringot I 04 dcembre 2012

30

RESULTS
DIKE

I LNG Tech S. Ringot I 04 dcembre 2012

31

Erection Status to date

I LNG Tech S. Ringot I 04 dcembre 2012

32

DUNKERQUE WESTERN HARBOUR

I LNG Tech S. Ringot I 04 dcembre 2012

33

21 octobre 2007
I LNG Tech S. Ringot I 04 dcembre 2012

34

16 septembre 2011
I LNG Tech S. Ringot I 04 dcembre 2012

35

9 dcembre 2011
I LNG Tech S. Ringot I 04 dcembre 2012

36

20 avril 2012
I LNG Tech S. Ringot I 04 dcembre 2012

37

25 mai 2012
I LNG Tech S. Ringot I 04 dcembre 2012

38

24 aot 2012
I LNG Tech S. Ringot I 04 dcembre 2012

39

27 septembre 2012
I LNG Tech S. Ringot I 04 dcembre 2012

40

TERMINAL
MTHANIER
DE DUNKERQUE

THANKS FOR YOUR KIND


ATTENTION

You might also like