02.07.13 02 GSM Wireless Network Moderniz - Off Revision CLAROV 13
02.07.13 02 GSM Wireless Network Moderniz - Off Revision CLAROV 13
TABLE OF CONTENTS
1.
Preface............................................................................................................3
2.
Modernization Principles...................................................................................4
2.2
Modernization Strategy.....................................................................................4
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.3
Modernization Process......................................................................................6
2.3.1
2.3.2
Solution Design...................................................................................................... 7
2.3.3
2.4
2.4.1
Engineering Services............................................................................................. 9
2.4.2
Implementation Services......................................................................................11
2.4.3
Network Analysis.................................................................................................. 12
2.5
Other Services................................................................................................14
2.5.1
2.6
Babysitting............................................................................................................ 14
Training........................................................................................................... 14
Local Trainings................................................................................................................... 14
2.6.1
2.6.2
International Trainings........................................................................................................ 22
Huawei Confidential
27/06/2013
Page 2 of 23
1.
Preface
As a leader in providing next-generation telecommunication network,
Huawei focus on customers market challenges and requirements. We
provide excellent communication network solutions and services in
order to consistently create maximum value for our customers. The key
values of the solution from Huawei offered to Conecel are listed as
below:
Modernize the legacy GSM radio network
Introduce new services and features, such as Gb over IP, etc
Smooth evolution to 3G and LTE
TCO saving solution reduces CAPEX & OPEX in the years to come in
different dimensions, such as power consumption, space
occupancy.
Future proof, advanced hardware platform ready for IP, LTE
This document describes Huaweis implementation solution of GSM
wireless network modernization for Conecel.
Huawei Confidential
27/06/2013
Page 3 of 23
2.
2.1
Modernization Principles
Reliability
Modernization
Principles
Smoothness
Low Cost
High Efficiency
2.2
Modernization Strategy
The most suitable modernization strategy contributes to the success of a modernization
project in terms of modernization effectiveness, modernization stability and cost-efficiency.
In practical projects, various factors come together to shape up the strategy. Based on our
modernization experience around the world, we recommend the bellowing modernization
strategy for this project.
2.2.1
High
Medium
Low
Cluster by
Cluster
Site by Site
Low
Huawei Confidential
27/06/2013
Medium
High
Project complexity
and risk
Page 4 of 23
Huawei recommends cluster modernization for this project. The detailed site number of
each cluster for the implementation works during maintenance window, will be discussed
with Conecel and mutually agreed by both parties.
2.2.2
Pilot
Network
Modernization
Modernization
before
Large-scale
Network
2.2.4
2.2.5
Huawei Confidential
27/06/2013
Page 5 of 23
2.3
Modernization Process
The process usually includes network information collection, network design, test system
deployment, live network modernization, network monitoring, network optimization,
network acceptance, etc.
Huawei Confidential
27/06/2013
Page 6 of 23
2.3.1
2.3.1.1
2.3.1.2
RF team
This team is responsible for the wireless planning and tunning in this wireless project. It
helps the project team to implement the modernization in clusters, and check the wireless
performance and key performance indicator (KPI) of the cluster set and network before
acceptance.
2.3.1.3
2.3.1.4
Solution team
This team is responsible for requirement research, technical proposals, solution design,
and correctness of the bill of quantity (BOQ).
2.3.1.5
2.3.2
Solution Design
2.3.2.1
2.3.2.2
Site Conditions:
Indoor BTS with space problem
Huawei Confidential
27/06/2013
Page 7 of 23
Modernization Strategy
Dismounting and Remove existing BTS Install new BTS
Modernization Process
1)
2)
3)
4)
5)
6)
Service test.
Above process, is a general one for sites that have restrictions of working hours,
space, etc. In case there are these type of scenarios, detailed process must be
discussed together with Conecel.
Scenario B
Site Conditions
Indoor BTS without space problem
Modernization Strategy
Install new BTS in extra space
2.3.3
Modernization Process
1)
2)
3)
4)
5)
Service test;
6)
Huawei Confidential
27/06/2013
Page 8 of 23
2.4
2.4.1
Engineering Services
2.4.1.1
Original network traffic statistical data (Statistcs for previous 15 das per hour per
sector)
Output documents:
2.4.1.2
For technical Site Survey scope according to review with CLARO EC, for GYE and UIO is require to
perform TSS Update scope described in attached document as Servicio de Technical Site Survey
(TSS). For Portoviejo cluster is required to perform TSS described in attached document as Servicio
de Levantamiento de Sitio
Output documents:
2.4.1.3
Huawei Confidential
27/06/2013
Page 9 of 23
Mapping
-
KPI mapping. The baseline for this mapping will be AMX KPI homologate for all
countries. Also should be consider SUPTEL/CONECEL KPIs, This should uploaded to
iManager M2000.
Parameter mapping
Key parameters are 100% inherited to ensure smooth network transition; such as cell
basic parameters, Frequency plan, cell layer/Priority, Rx Access Min, etc; other
parameters will use Huawei parameter baseline.
Power mapping
Power mapping is to make sure radio coverage level/quality is same as before swap.
Considering that Huawei will use DBS site to replace original Macro site, so suggest
mapping EIRP. CLARO has to deliver current output power for calculate EIRP.
Site survey information, will considered in calculating EIRP of original power, such as
feeder/jumper/connecter information;
Feature mapping
Feature mapping is to make sure all current active features work well according the
feature description. The baseline for feature mapping is document deliver as part as
commercial proposal.
2.4.2
Implementation Services
A. Equipment Installation
2.4.2.1
Preparation (daytime)
After obtaining and delivering the installation design document:
-
Pre-installation Site Visit (PISM), in order to confirm that the site adaption is finished
based on TSS requirements.
MRF
Huawei Confidential
27/06/2013
Page 10 of 23
2.4.2.2
BTS Installation
Daytime:
-
Equipment Power On
maintenance windows.
BTS commissioning and integration (the cells will be blocked): Huawei BTS will load
software and configuration data from BSC automatically after the transmission is OK.
Output document:
2.4.2.3
Single Site Verification: Execution of voice and data functions test per cell, just after
the cutover process this test and report will be deliver per site. Include KPIs de
accessibility and retain ability . The SSV document will be deliver in next calendar
day.
KPIs Monitoring: After site on air should deliver 4 report within 7 days.
VSWR measurement: Feeder & antenna system test will be done with site master if
there is something wrong in the feeder & antenna system.
Huawei Confidential
27/06/2013
Page 11 of 23
2.4.2.4
BSC integration
-
TSS:
Visit to the site to get information of space location for BSC, civil works requirements,
etc. If there are modifications to the delivered TSS, these will be additional.
o Interface planning
o Datafill
o Equipment parameters
o Feature activation and testing
-
Installation,
o Equipment installation and cabling
o Equipment power up
o Commissioning and integration
o ATP that will be reviewed and agreed with CONECEL.
o BSC will be integrated to iManager M2000.
For power on and physical connection will be execute during windows maintenance.
2.4.2.5
Project follow up
Huawei Confidential
27/06/2013
Page 12 of 23
Resources coordination
2.4.3
Network Analysis
2.4.3.1
2.4.3.2
2.4.3.3
Tuning
After being successfully modernized a cluster enters the stage of tuning. During this
stage, performance monitoring team will continually monitor the associated BTSs of the
cluster and provide decision support for tuning activities that are aimed to further enhance
the network performance for Conecel. Huawei will complete the corresponding cluster
tunings and achieve the target KPIs (same KPIs as before the modernization process).
Huawei Confidential
27/06/2013
Page 13 of 23
2.4.3.4
Acceptances
HARDWARE and SOFTWARE Acceptances
Site Installation Provisional Acceptance Certificate (PAC)
This acceptance is to verify the running status and service functions of new
equipments and ensure smooth implementation of the subsequent cutover.
The procedures of the acceptance test are as follows:
Make the test scheme and fix the test items defined on the ATP.
Conecel and Huawei conduct the formal test and sign to confirm the test results;
After successful completion previous step, Huawei will initiate the Final
Acceptance Certificate (FAC) which will be based on site.
If there are no pending issues in PAC, the FAC will be signed directly after
Huawei deliver corresponding site folder.
After the successful acceptance test, Conecel will issue the Final Acceptance
Certificate to Huawei and the network will be handed over from Huawei to
Conecel.
RF Acceptances
For RF acceptance, KPIs should comply with Acceptance parameters document.
2.5
Other Services
Huawei Confidential
27/06/2013
Page 14 of 23
Babysitting
After the modernization of the first cluster, Huawei engineer will be at Conecel NOC for 2
(one) calendar month, in order to monitor the equipment status during labor hours (8x5)
and on call 7x24.
During hollidays or weekends, or non labor hours, Conecel NOC must monitor and inform
to Huawei in case network alarms appear.
Also, it includes 8 (eight) hours of competence transfer during babysitting period, date and
trainees to be defined by Conecel.
alarms and
between parties.
Output document:
2.6
Training
Local Trainings
Duracin
(das hbiles)
Number of
trainees
Number
of classes
Training
Location
12
Onsite
12
Onsite
12
Onsite
12
Onsite
12
Onsite
13ECWR035ECOOS00
2.6.1
2.6.1.1
Training Route
Huawei Confidential
27/06/2013
Page 15 of 23
Lecture
1d
3d
Objective Group
BSS technical people. O&M first line maintenance.
Prerequirements
-
Objetives
After finish the training, trainees will be have knowledge about:
-
Time
4 labor days
Participants
Min 6max 12
2.6.1.2
Training Route
Huawei Confidential
27/06/2013
Page 16 of 23
4d
1d
Objective Group
Field BSS technicians,engineers of O&M first line maintenance.
Prerequirements
-
Objetives
After finish the training, trainees will be have knowledge about:
-
Huawei Confidential
27/06/2013
Page 17 of 23
Time
5 labor days
Participants
Min 6max 12
2.6.1.3
Training Route
MBTS GU V1R7 Product Description
OMT99
Lecture
0.5d
2d
1d
1d
Lecture
0.5d
Objective Group
Field BSS technicians,engineers of O&M first line maintenance.
Prerequirements
-
Objetives
After finish the training, trainees will be have following knowledge :
Huawei Confidential
27/06/2013
Page 18 of 23
Time
5 labor days
Participants
Min 6max 12
2.6.2
2.6.2.1
Training Route
Huawei Confidential
27/06/2013
Page 19 of 23
1.5d
2.75
d
Objectives
Describir la funcin de cada tipo de canal lgico.
Describir el proceso general de seales de radiofrecuencia en la interfaz Um.
Especificar las tcnicas utilizadas en la interfaz Um.
Describir el flujo tpico de comunicaciones sobre GSM.
Realizar la operacin correspondiente al rastreo de mensajes de interfaz.
Identificar los mensajes en las interfaces A y Abis.
Analizar los mensajes en las interfaces A y Abis.
Explicar los parmetros de mensajes relevantes.
Identificar fallas mediante el anlisis de flujos de sealizacin.
Enumerar los comportamientos de la MS en modo inactivo.
Describir los parmetros asociados con los comportamientos de la MS en modo inactivo.
Enumerar los tipos de saltos de frecuencia.
Describir las funciones del algoritmo de saltos de frecuencia.
Describir los parmetros de saltos de frecuencia.
Describir el flujo general del algoritmo de control de energa en GSM.
Interpretar el algoritmo de control de energa II de Huawei.
Interpretar el algoritmo de control de energa III de Huawei.
Describir otras funciones de control de energa.
Describir el flujo general del algoritmo del handover en GSM.
Interpretar el algoritmo de handover I/II de Huawei.
Describir el algoritmo mejorado de velocidad mxima.
Describir el algoritmo de velocidad media.
Huawei Confidential
27/06/2013
Page 20 of 23
Time
8 das hbiles (6 horas diarias dependiendo el requerimiento del cliente)
Participants
Min 6max 12
2.6.2.2
2d
1.5d
Lecture
1d
Lecture
0.5d
Objective Group
Objectives
Huawei Confidential
27/06/2013
Page 21 of 23
Describe the structure of GPRS / EDGE and functions of the entities in the GPRS network
Describe the operational flow of the network planning GPRS / EDGE Radio
Time
5 labor days
Participants
Min 6max 12
International Trainings
METC: Mexico Training Center
*Note: 1 training day = 6 hours per day
Duracin
(das hbiles)
GSM O&M Training
GSM&UMTS SingleRAN7.0 BSC Operation and
4
Maintenance Training
GSM&UMTS SingleRAN7.0 BSC Configuration
8
Training
GSM&UMTS SingleRAN7.0 BTS Operation and
7
Maintenance Training
GSM RNO&RPO Training
GSM Radio Network Optimization Training
8
Training Program
Huawei Confidential
27/06/2013
Number of
trainees
Number
of classes
Training
Location
METC
METC
METC
METC
Page 22 of 23
METC
13ECWR035ECOOS00
Huawei Confidential
27/06/2013
Page 23 of 23