PREFACE
This edition of the KALAHI-CIDSS Community Based Procurement Manual is
designed to be a user-friendly and comprehensive guide. Major revisions aim
to clarify some of the provisions and provide complete guidance to every
Community procurement activity.
The highlight of revisions include the following:
definition of terms,
elaboration on procedural steps, answers to frequently asked questions
(FAQs) and clarification to guidelines.
This manual is intended for the Barangay Sub-project Management
Committee (BSPMC) particularly the Procurement Team (PT) and the Bids
and Awards Committee (BAC) as guide in their procurement activities. This
manual will also be used by the Area/Municipal Coordinating Teams
(A/MCTs) and Regional Project Management Teams (RPMTs) in providing
Technical Assistance on Community Procurement to the BSPMC; likewise,
external monitors in conducting fiduciary reviews.
This edition has been made possible through the leadership and support of
Assistant Secretary Camilo G. Gudmalin, Deputy National Project Director of
KALAHI-CIDSS Project; Mr. Edgar G. Pato, National Project Manager;
technical inputs from Engr. Benito Cesario Tingson, Chief Infrastructure
Engineer, Engr. Abelardo Cea, Deputy NPMO Infra Engineer, and the
contributions of all the Regional Community Infrastructure Specialsists
(RCIS). The role of Engr. Alfredo D. Tucpi (KALAHI-CIDSS Procurement
Specialist July 200615 May 2011), who was responsible for putting
together the inputs from the various units, is also acknowledged.
CORAZON JULIANO-SOLIMAN
Secretary and National Project Director
KALAHI-CIDSS Project
01 June 2011
TABLE OF CONTENTS
DEFINITION OF TERMS
ABBREVIATIONS; ACRONYMS
4-9
10
CHAPTER 1: INTRODUCTION
Introduction
Scope, Coverage, and Application
Principles in Community-Based Procurement
11
12
12-13
13-14
18
20
20
20
20
19
20
21
22
25
26
32
32
36
39
40
41
41-42
43
44-46
22
23
32
47
48-59
60-65
66-67
68-85
86
LIST OF ANNEXES
INSTRUCTIONS TO BIDDERS
CONDITIONS OF CONTRACT
FORM OF BID
FORM OF CONTRACT AGREEMENT
BANK GUARANTEE FOR ADVANCE PAYMENT
G150
FORM OF BID SECURITY (BANK GUARANTEE)
EVALUATION FORM PROCUREMENT OF WORKS
RESOLUTION TO AWARD
NOTICE OF AWARD
NOTICE TO COMMENCE
PERFORMANCE SECURITY (BANK GUARANTEE)
BIDDING DATA
CANVASS FORM FOR GOODS
ABSTRACT OF QUOTATION/CANVASS
PURCHASE ORDER
INVITATION TO QUOTE-FOR WORKS UNDER LOCAL SHOPPING
ABSTRACT OF QUOTATION FOR WORKS
INVITATION FOR DIRECT CONTRACTING FOR LABOR
DIRECT CONTRACT AGREEMENT FOR LABOR
INVITATION TO BID-FOR WORKS UNDER LOCAL BIDDING
INVITATION TO BID-FOR GOODS
ABSTRACT OF CANVASS FOR LOCAL SHOPPING
EMPLOYMENT RECORD SHEET
SUPPLEMENTAL AGREEMENTS (LS Goods for fuel only)
CONTRACT AGRREMENT (LS for Works Fabrication Works)
CANVASS FORM FOR LEASE OF EQUIPMENT (Goods)
PURCHASE ORDER (For equipment services)
EQUIPMENT LEASE AGREEMENT (Works)
REQUEST FOR QUOTATION FOR TAF
SERVICE CONTRACT AGREEMENT
QUALIFICATION STANDARS FOR SERVICE PROVIDERS and TERMS OF
REFERENCE
PASS/FAIL CHECKLIST
NOL REVIEW REPORT (LOCAL SHOPPING FOR WORKS and
BIDDING GOODS AND WORKS)
SUGGESTED FORMAT IN PREPARING POST-QUALIFICATION REPORT
PLANNED COMMUNITY PROCUREMENT PACKAGING FORM
SCHEDULE OF IN-KIND LOCAL COUNTERPART CONTRIBUTION
ACTUAL COMMUNITY PROCUREMENT PACKAGING
PROCUREMENT ACTION PLAN and FORM
ANNEX A DIRECT CONTRACT AGREEMENT OF LABOR
BID BULLETIN SAMPLE FORMAT
ACKNOWLEDGMENT RECEIPT
SITE VISIT CERTIFICATE
CF PROCUREMENT RED FLAGS MONITORING FORMS
87-91
91-97
98
99-101
102
103
104
105
106
107
108
109-110
111
112
113
114-115
116
117-118
119-120
121-122
123-124
125
126
127
128
129-130
131
132-136
137-138
139-144
145-149
150
151-157
158-159
160
161
162
164
165
166-167
168
169
170
2-A
Local Bidding for Goods
2-B
Local Shopping for Goods
2-C
Local Shopping for Works
2-D
Local Bidding for Works
2-E
Direct Contracting for Works
2-F
Direct Contracting for Goods
RPMO No Objection Letter (Suggested Format)
DOCUMENTS FILING CHECKLISTS
1-A
Community Force Account
1-B
Direct Contracting of Works
1-C
Local Shopping of Works
1-D
Local Bidding of Goods
1-E
Local Bidding of Works
1-F
Direct Contracting of Goods
1-G
Direct Shopping of Goods
190
191
192
193
194
195
196
197
198-199
200
201
202
203-205
205-210
211-220
170-172
173-174
176-178
179-181
182-184
185-187
188
219-222
223-225
226-230
231-234
235-237
238
239-242
DEFINITION OF TERMS
Abstract of Bids/Record of Bid Opening The corresponding document prepared by
the BAC after all bids have been received, opened, examined, evaluated and ranked.
Advance payment Refers to any payment made prior to the delivery and acceptance of
Goods, Works, or Consulting Services.
BAC The Bids and Awards Committee.
Bid (Bid proposal) is a signed offer coming from a supplier/contractor interested to
provide goods or undertake infrastructure work for the community.
Bid Evaluation The process of determining the Bidder with the Lowest Calculated and
Responsive Bid/Quotation (LCRB/Q) or the Highest Rated Bid (HRB) in case of consultancy
services.
Bid Opening Date The date specified in the Invitation to Bid (ITB) for the opening of
bids.
Bid Security- is required to ensure that the successful bidder shall, within five calendar
days from receipt of the Notice of Award, sign the contract with the BSPMC. It
could be in the form of cash, check, bank draft, letter of credit or bank guarantee
that serves as a guarantee that the successful bidder shall not default on his offer,
and shall enter into contract with the BSPMC and furnish the performance security.
The bid security shall be returned to the bidders only after the successful
bidder has signed the Contract and posted the performance security, except
if the bidder fails to comply with all the requirements and the bid is marked
failed.
Bidder, who wants to present cash as bid security, shall be instructed to
deposit the amount to the communitys bank account and to attach the
machine validated deposit slip to the bid documents to be placed in a
sealed envelope.
Bid Validity A period indicated in the bidding documents, but in no case shall exceed
sixty (60) calendar days from the date of the opening of bids, wherein a Bid Security is
considered valid.
Bidder An individual or entity that submits a bid. The term includes anyone acting on
behalf of the individual or other entity that submits a bid, such as agents, employees, and
representatives. More specifically, a contractor, manufacturer, supplier, distributor and/or
consultant competing for the award of a contract in any government procurement.
Bidding Documents. The documents issued by the BAC as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the
infrastructure projects, goods and/or consulting services required by the procuring entity.
Blacklisting To place on, or as if on, a list of persons or organizations that have incurred
disapproval or suspicion or are to be boycotted or otherwise penalized.
Brand Name A trade name or product name, which identifies a product as having been
made by a particular manufacturer.
Calculated bid price The price of a bid, after taking into account minor arithmetical
corrections to consider computational errors, omissions and discounts, if allowed.
Collusion An agreement between two or more persons, to commit acts to accomplish a
fraudulent or deceitful purpose.
Competitiveness A principle in KC procurement that allows broad participation by
eligible and qualified suppliers, contractors, consultants to put forward offers for a
community project.
Competitive Bidding (Public Bidding) A method of procurement which is open to
participation by any interested party and which consists of the following processes:
advertisement, pre-bid conference, receipt and opening of bids, evaluation of bids, postqualification, and award of contract.
Communication costs mail, internet rental, and fax costs, plus cost of advertising,
meetings, internet/web posting, and other costs incurred for the dissemination of
information about the bidding.
Conference Notice A formal written communication sent to the participants of the
conference (such as the Pre-procurement, Pre-bid and Post-Award Conference) informing
them when and where the conference will be held.
Conflict of Interest a situation in which a public official's decisions are influenced by
the official's personal interests.
Consulting Services refer to services provided by external technical service providers 1
or professional expertise that are beyond the capacity of the BSPMC or Local Government
Unit (LGU) staff to undertake such as but not limited to feasibility studies; design;
construction supervision; services for capability building types of community projects; and,
special studies.
Consolidated Blacklisting Report A report issued by the GPPB that contains a list of
people and/or organizations that are barred from participating in any Government
procurement project.
Contract a meeting of minds between two persons whereby one binds himself, with
respect to the other, to give something or to render some service. Article 1305, New
Civil Code, Republic Act No. 386
A promise or a set of promises for the breach of which the law gives a
remedy, or the performance of which the law in some way recognizes a
duty.
An agreement, upon sufficient consideration, to do or not to do a particular
thing.
A promise enforceable by law.
Contract Completion Project sign-off or acceptance of the project/goods by the enduser.
Contract Implementation The execution of a contract, covering the following
milestones: effectivity of the contract; contractors performance of his contractual
obligations; procuring entitys performance of its contractual obligations, as specified in
1
Service providers referred to in these guidelines pertain to suppliers, contractors and consultants.
the Contract; final acceptance or project sign-off; all other related activities; and payment
by the Procuring Entity.
Contractor One who undertakes to perform a work or service, or supply goods for a
public or private entity.
Contract Termination Ending of a contract prior to its completion.
Corrupt practice the offering, giving, receiving, or soliciting of any thing of value to
influence the action of a public official in the procurement process or in contract execution.
Compare fraudulent practice.
Cost Recovery Component Direct and indirect costs accounted for in determining the
price of Bidding Documents to be sold to interested suppliers/contractors.
Defects Liability Period - refers to the period from the date of issuance of Certificate of
Completion of the works as certified by the BSPMC Chairman up to the date within
which, the contractor shall still be liable for defects, shrinkage or other faults as
determined by BSPMC. The contractor shall execute all such work needed to
amend, reconstruct, or remedy at his own cost.
Development Cost Costs incurred in developing the original content of the documents,
designs, plans and specifications. The design cost may be excluded if the same is to be
included in the capitalized cost of the project which is to be recovered from the usage of
the completed project facility.
Direct Costs - Costs directly incurred such as development, reproduction, and
communication costs allocated to the bidding activity.
Disclosure The act of disclosing, uncovering, or revealing.
Disqualification The act of barring a bidder from further participation in the
procurement at hand, even if, in some instances, it has initially been declared eligible or
post-qualified.
Eligible Bidder A contractor, manufacturer, supplier, distributor or consultant who
meets all the eligibility requirements issued by the BAC.
Eligibility Refers to the status of a Bidder in relation to its legal, technical and financial
competence to comply with the requirements of the contract to be bid, as shown by
eligibility documents submitted to and checked by the BAC.
Eligibility Requirements - refer to qualifications set by the BAC for participating bidders.
Some examples of qualifications are:
Suppliers must have a SEC Registration, mayors permit or municipal
license, or the Cooperative Development Authority, if a cooperative;
Contractors for works must be either a duly licensed Filipino citizen or a
sole proprietorship, or a duly registered partnership or corporation;
Estimated Budget for the Contract The budget for the contract duly approved by the
BSPMC which will serve as the agency estimate.
Evaluated Bid - refers to the corrected bid after evaluation has been completed.
Force Majeure see Fortuitous events.
Fortuitous events/Force majeure An event which could not be foreseen, or which
though foreseen, was inevitable.
and
Stipulates price adjustment when bid price should be fixed given the short
duration of the contract;
Proposed timeframe of implementation does not conform to the required
period
Bid contains provision to exempt the bidder from some critical provisions of
the contract.
Project Implementation Unit The unit created through an Executive Order that is
primarily responsible for implementing and managing a community project.
Procurement Package is a group of similar goods that can be purchased from one
supplier or work items that can be performed or implemented by a single contractor.
Protest A formal declaration made by a person interested or concerned in some act to
be done, or already performed, whereby he expresses his dissent or disapproval, or affirms
the act against his will. The object of such declaration is usually to save some right which
would be lost to him if his implied anent could be made nil, or to exonerate himself from
some responsibility which would attach to him unless he express negatively his assent.
(Blacks Law Dictionary, 5th Ed.)
Reproduction cost labor, supplies and equipment rental costs incurred in the
reproduction of the documents e.g. photocopying, blue printing, etc
Request for Clarification A written request submitted by the bidder to the BAC, asking
the latter to clarify a particular provision of the Bidding Documents.
Request for Proposal Bidding document for Consulting Services. Also called Request
for Quotation.
Responsive bid is a solicited bid is determined to be in substantial conformance with
the conditions, completion or delivery requirements, and specifications detailed in the
invitation-to-bid (ITB), request for proposals (RFP), request for quotations (RFQ), or
request for tenders.
Retention Money - refers to the amount retained from progress payment to cover
uncorrected discovered defects and third party liabilities. This is equivalent to 10%
of all progress payments. Upon issuance of Certificate of Completion by the BSPMC
through the recommendation of the Project Supervisor, 100% of the retention
money is returned to the contractor. It is understood that the Contractor is still
liable to BSPMC under Defects Liability Period provision of the contract.
For performance guarantees in the form of cash for contracts that are nearing thee
end of KALAHI-CIDSS project, such guarantee shall be replaced with a bank
guarantee from a reputable bank.
Spare parts Refer to extra components, equipment, tools, instruments or parts of
machinery or apparatus that replace the ones that are damaged or worn out.
Specification - A description of what the purchaser requires and what a bidder must offer.
- A detailed description of design criteria for a piece of work or
material.
Splitting of Contracts/Packages is the act of dividing or breaking up of contracts into
smaller quantities and amounts, or dividing contract implementation into sub-contracts but
it can be undertaken/procured as one contract to circumvent or subvert the procurement
method.
Standard The established and fixed measure used in assessing quality or performance.
Subcontractor One who takes a specific part of the work undertaken by the principal
contractor. (Blacks Law Dictionary, 5th Ed.)
Submitted bid price The bid price as indicated in the financial proposal submitted by
the bidder.
Supplemental/Bid bulletin A notice issued by the Procuring Entity to Prospective
Bidders with respect to any clarifications or modifications in the Bidding Documents,
including those affecting the technical specifications, eligibility requirements, procurement
schedule, and other similar matters.
Technical Bid One of two components comprising a bid, the other being Financial Bid.
Tender See Bid.
Warranty An undertaking by the supplier, manufacturer or distributor to guarantee that
it will correct any manufacturing defects of the goods procured by the BSPMC.
ACRONYMS; ABBREVIATIONS
AC
ACT
AIT
BA
BAC
BDC
BSPMC
CC
CD
DAC
DSWD
CERS
CF
CFA
CSO
DA
DAC
DC
DENR
DPWH
CPP
DC
GOP
KALAHI- CIDSS
KKB
LCCQ
LCRB
LGU
LS
LB
MAO
MCA-P
MCC
MIT
NOA
NOL
NPMO
NPMT
NRM
NTP
OR
PIT
PO
POs
POW
PT
TWG
RIE
RPM
RPMO
RTA
WB
WD
Area Coordinator
Area Coordinating Team
Audit and Inventory Team
Barangay Assembly
Bid and Award Committee
Barangay Development Council
Barangay Community Project Committee
Conditions of Contract
Calendar Days
Deputy Area Coordinator
Department of Social Welfare and Development
Community Employment Record Sheet
Community Facilitators
Community Force Account
Civil Society Organization
Department of Agriculture
Deputy Area Coordinator
Direct Contracting
Department of Environment and Natural Resources
Department of Public Works and Highways
Community Procurement Plan
Direct Contracting
Government of the Philippines
Kapit-bisig Laban sa Kahirapan-Comprehensive and Integrated
Delivery of Social Services
Kapangyarihan at Kaunlaran sa Barangay
Lowest Calculated and Complying Quotation
Lowest Calculated and Responsive Bid
Local Government Unit
Local Shopping
Local Bidding
Municipal Agricultural Officer
Millennium Challenge Account-Philippines
Millennium Challenge Corporation
Monitoring and Implementation Team
Notice of Award
No Objection Letter
National Project Management Office
National Project Management Team
Natural Resources Management
Notice to Proceed
Official Receipt
Project Implementation Team
Purchase Order
Peoples Organizations
Program of Works
Procurement Team
Technical Working Group
Regional Infrastructure Engineer
Regional Project Manager
Regional Project Management Office
Resolution to Award
World Bank
Working Days
CHAPTER 1 |
INTRODUCTION
Scope, Coverage, and Application
Principles in Community-Based Procurement
1. Introduction
Procurement is one of the most critical activities in
community project implementation. It refers to the
purchase of all the goods, supplies, and materials
needed by the community project. It also refers to
the contracting of the entire or a portion of the works
in an infrastructure community project.
It is the most sensitive
disbursement of funds.
because
it
involves
2.3. Application
The procurement procedures provided in this manual shall apply to the following:
1. Goods - These include supplies, materials, and purchase of
equipment, lease of equipment 2, trucking and hauling.
Examples: construction materials, seedlings/seeds (for prevention of
erosion), hand tools, and including office supplies for use by the
BSPMC in its operations.
2. Works refer to civil/infrastructure and all types of physical works
such as construction, improvement, upgrading, roads and bridges,
irrigation, flood control and drainage, water supply, electrification
facilities, buildings, fabrication of equipment and structural parts, Natural
Resources Management (NRM) activities, solid waste management
system and physical works that require labor.
3. Consulting Services refer to services provided by external
technical service providers 3 or professional expertise that are outside
the capacity of the BSPMC or Local Government Unit (LGU) staff to
undertake such as but not limited to feasibility studies; design;
construction supervision; services for capability building types of
community projects; and, special studies.
When leasing for equipment, the nature of the activities will define if it is categorized as goods or works. Categorization and
procedures are provided in the guidelines for Lease of Equipment to further understand the details when renting/leasing
equipment.
3
Service providers referred to in this manual pertain to suppliers, contractors and consultants.
4
The term Bid applies to thresholds under local bidding.
5
The term Quotation applies to thresholds under local shopping.
Working Group (TWG) to provide technical assistance. The BAC shall also invite
representatives from the LGU COA in the Municipality, Civil Society Organizations,
local government officials, Area Coordinator, Deputy Area Coordinator, Head of the
Barangay Audit and Inventory Committee and other interested members to observe
any or all stages of the procurement process. Finally, each procurement transaction
must be properly documented and such records must be maintained and made
available at the BSPMC office/s.
Accountability all officials directly or indirectly involved in the procurement
process as well as in the implementation of the contracts and the private parties
when warranted by circumstances, investigated and held liable for their actions
thereto.
CHAPTER 2 |
POSSIBLE TYPES OF COMMUNITY
PROJECTS REQUIRING
PROCUREMENT
Construction, repair and improvement
Common Service Facilities
Others
The following are some examples of community projects which would involve
procurement.
2.1
2.2
2.3
Others
1. All other approved community projects not mentioned above, provided it is not
within the negative list 6.
Negative list includes acquisition of land; building or repair of government offices, meeting halls and places of worship;
environmentally hazardous materials, such as, chainsaws, explosives, pesticides, herbicides, insecticides, asbestos and other
potentially dangerous materials; international travel; and maintenance and operation of infrastructure built from project funds;
assistance to, or training of, the military, police, national guard, or other quasi-military organization or unit; and to pay for the
performance of abortions as a method of family planning or to motivate or coerce any person to practice abortions, to pay for the
performance of involuntary sterilizations as a method of family planning or to coerce or provide any financial incentive to any
person to undergo sterilizations; or any activity or funds relating to trafficking of person/s. Note: Any proposed projects intended
to benefit commercial logging, (provided this shall not include tree removal incidental to the project), must be sent to the funding
donor for review prior to project approval.
CHAPTER 3 |
PROCUREMENT POLICIES
3.1 Procurement for the community project shall be the responsibility of the
community through the Barangay Community Project Management Committee
(BSPMC). A Procurement Team composed of at least three community volunteers
elected by the barangay assembly shall assist the BSPMC.
3.2
Transparency should be practiced in all stages of the procurement process.
From the public announcement of invitation to quote or to bid, awarding of
contracts, contract implementation to payment to suppliers, contractors and local
workers, the BSPMC should ensure that transparency is observed. This shall be
achieved through conduct of barangay assemblies and posting of notices and
reports in the Kalahi-CIDSS: KKB billboards or bulletin boards within the barangay.
3.3
The BSPMC shall use the Lowest Calculated and Responsive Bid/Quotation as
the criterion for selection of suppliers and contractors. This criterion shall be
publicly announced to the community and to all interested parties.
3.4
The Project prescribes the procurement methods and procedures to be used.
These are contained in this revised manual and should be followed strictly by
participating communities.
3.5 Section 4 of Government Procurement Reform Act, R.A. 9184 provides that any
treaty or international or executive agreement affecting the subject matter of this
Act to which the Government of the Philippines is a signatory shall be observed.
For MCC: The Compact Agreement signed between the funding donor (for MCC)
and the Government of the Philippines provides that Funding will be granted to
DSWD to plan and implement community-chosen sub-projects in accordance with
the Kalahi-CIDSS Project manuals approved by MCC. Thus, the procurement
procedures provided for in this Community Procurement Manual, as acceptable to
MCC shall be followed.
3.6
Participating communities which violate the prescribed procurement policies,
methods and procedures are liable for sanctions and will be penalized. Procurement
that does not follow guidelines will be disallowed and grant funds used will be
returned to the KC Project. Depending on the degree of violation, the sanctions can
range from disallowance, suspension of further fund releases, and withdrawal of the
community project. If there are anomalous transactions, persons responsible will be
charged with civil and/or criminal cases.
3.7 Blacklisted and suspended suppliers, contractors and consultants by private and
Government entities shall not be allowed to participate in KALAHI-CIDSS
procurement.
CHAPTER 4 |
COMMUNITY CAPABILITY
BUILDING ON PROCUREMENT
Orientation, Organization & Workshop
Skills Training & Preliminary Procurement
Coaching Jobs, Practicum
Community Procurement Technical Assistance
Procurement Monitoring of Red Flags
4.1
4.2
4.3
4.4
4.5
The Community Facilitators Red Flag Procurement Monitoring Form can be found in the procurement manuals annexes.
CHAPTER 5 |
PROCUREMENT ORGANIZATION
AND FUNCTIONS OF THE
PROCUREMENT TEAM
Procurement Team
Bids and Awards Committee
Functions of the BAC
Br g y.
Re p r es e n tatio n
T e am (B RT )
P roj.
P re pa ra tion
T ea m (P P T )
A u d it &
In ve n tor y
T e am
(A IT )
Bid s an d
A w ard s
C o m m ittee
(BA C )
O pe ra tion &
Ma inte na nc e
C om m ittee
(O & M)
B rg y. T rea sure r
S e c re ta ry
B ookke epe r
P roc ureme nt
T ea m (P T )
P roje c t
Im pleme nta tion
T ea m (P IT )
Monitoring &
Inspe c tion Tea m
(MIT )
This section elaborates on the formation of a Procurement Team within the BSPMC.
5.1
Procurement Team
The Barangay Assembly (BA) members elect at least three members of the
Procurement Team during the Second Barangay Assembly (2nd BA).
While the membership is elected 8, the minimum qualification should be at least
high school level or graduate. However, if there are elementary graduates that have
experience in local procurement, they are also welcome provided they are dedicated
to do the tasks. It is clarified that while the membership is elected, it does not
mean that any member of the community can be a PT member. Furthermore, it is
clarified that the selection with minimum qualification is not defeating the principle
of inclusion but rather ensuring that fiduciary requirements are complied in
accordance with this manual.
The Procurement Team shall be in charge of activities required to facilitate
acquisition of all supplies, materials, equipment, labor from suppliers and
contractors.
Specific Functions of the Project Procurement Team
Acts as Canvassers
Prepares and finalizes Planned Community Procurement Packaging (PCPP) & Community
Employment Record Sheet (CERS) with the assistance of DAC
Elected in this statement to mean chosen from at least high school level or graduate.
5.2
The BSPMC executive committee is composed of the BSPMC chairperson and heads of teams under the BSPMC.
5.3
10
Eligibility verification follows the existing KALAHI-CIDSS Project. This mean that Contractors or Suppliers and
Service Providers possessed the capacity to perform or deliver the Contract/s.
CHAPTER 6 |
PROCUREMENT PROCESS
Procurement Planning
Presentation to the Barangay Assembly
Finalization of Planned Community Procurement Packaging
Implementation of the Planned Community Procurement Packaging
Monitoring Procurement Compliance
Billboards
6.1
Procurement Planning
Procurement Planning starts after the Community Project Preparation Committee
has completed the detailed project proposal and budget, complete with technical
specifications, drawings and bill of materials (for infra community projects). The
BSPMC shall prepare a procurement package called Planned Community
Procurement Package (PCPP).
Procurement package is a group of similar goods, works or services that can be
purchased from one supplier or work items that can be performed or implemented
by a single contractor or a an activity that can be performed by a consultant.
A procurement action plan (PAP) shall also be prepared indicating the timeline to
complete the activity, responsible volunteers and project staff, venue of meeting
and place/s to conduct procurement, packages to be procured, and list of potential
service providers 11.
Procurement planning ensures that the overall goal of a particular community
project will be achieved effectively and efficiently. Through procurement plan, the
BSPMC is able to effectively manage and track procurement all the way to contract
implementation. The procurement will allow the BSPMC to be cost efficient in its
procurement.
Proper planning ensures that only goods, infrastructure projects, and consulting
services which have been included in the approved PCPP.
Procurement planning should be done within the approved estimated budget.
Prior to the conduct of actual procurement, the PCPP must be approved by the
RPMO. The A/MCT shall provide a copy of the PCPP to the Regional Community
Infrastructure Specialist (RCIS) for review. The A/MCT can submit the PCPP
electronically 12 to the RCIS for online review, comments and approval. Approval
and/or comments should be provided to the ACT before the conduct of the
procurement conference.
The following are the activities of the Procurement Team:
Meet with the Project Implementation Team (PIT) to discuss the different
items that needs to be procured and their technical specifications and
financial requirements.
11
Service providers pertain to suppliers, contractors or individual or firms providing services to the BSPMC.
Either scanned copy for handwritten PCPPs or electronic copy. For Shopping and Bidding for works the POW
must also be submitted as basis for review. The electronic means could save use of papers.
12
Quantity
Unit
50
Cu.M.
40
Cu.M.
Sand
30
Cu.M.
Boulders
20
Cu.M.
Portland Cement
100
Bags
16 mm diameter RSB x 6M
110
Pieces
10 mm diameter RSB x 6M
150
Pieces
500
Bd. Ft.
12
Pieces
3 inches CWN
15
Kilos
50
Cu.M.
40
Cu.M.
Sand
30
Cu.M.
Boulders
20
Cu.M.
Portland Cement
100
Bags
16 mm diameter RSB x 6M
110
Pieces
10 mm diameter RSB x 6M
150
Pieces
12
Pieces
3 inches CWN
15
Kilos
Possible Packaging:
Package 1:
Package 2:
Package 3:
2"x3"x10' Coco Lumber
500
Bd. Ft.
In areas where all the required materials can be taken from one supplier
or if all suppliers in the locality can supply all the materials needed thus,
package it as one.
Case 2: For works, the first step is to define the items that can be undertaken
by community force account (CFA) and have it packaged as separate package.
For items that require heavy equipment, such items must be packaged
separately.
Example:
Prepare a package for a road community project with common work
items such as items 100 (Clearing and Grubbing), 105 (Sub-grade
Preparation), Item 200 (Aggregate Sub-Base Coarse), Item 201
(Aggregate Base Coarse), Item 311 (Portland Cement Concrete
Pavement), Item 500 (Reinforced Concrete Pipe Culvert), Item 505
(Grouted Riprap).
Option 1: Package all the items as one since all can be undertaken by
one contractor.
Package 1:
Item 105
Sub-grade Preparation
Item 200
Aggregate Sub-Base
Item 201
Item 311
Item 500
Item 505
Grouted Riprap
Option 2:
PACKAGE 1:
(It can be Shopping
or Bidding depending
on the threshold)
Item 105
Sub-grade Preparation
Item 200
Aggregate Sub-Base
PACKAGE 2: CFA
Item 311
PACKAGE 3: CFA
Item 500
PACKAGE 4: CFA
Item 505
Grouted Riprap
Item 201
Notes:
1. This is a combined method of procurement. Items 105, 200 and 201
are mechanized so it will be undertaken by contract. Items 311, 500
and 505 were separated since it can be undertaken by CFA with 1 or 2
Pakyaw groups.
Item
Item
Item
Item
Item
Item
storage and the distance as locations are in far flung areas, the
community can break the packaging for cement into several package
depending on the condition of the area to avoid spoilage. Likewise, for
fuel and oil, if the conditions of the contract agreement do not apply to
the condition of the area, several packages can be made for fuel and oil.
Splitting under the KALAHI-CIDSS procurement guidelines depends on
the purpose for which the contract is divided. If the purpose for the
division of the contract/packages into artificial phases or subcontracts is
to circumvent or evade the mandatory requirements as per Loan
Agreement, the BSPMC is guilty of contract splitting thus, sanctions shall
be imposed as per section 3.6 of the Procurement Policies. The service
provider involved in the preparation must ensure proper packaging to
avoid such sanctions.
1. Conduct resource assessment to find out which of the items are available within
the barangay or within the municipality. They can visit the towns commercial
center and check for possible suppliers. If not available within the municipality,
they inquire for other possible sources in the areas near the municipality or any
area within the province. They can also refer to the ACT and RPMT inventory of
resource institutions, TA providers and suppliers. The Officer may already have
a list of possible suppliers and the prevailing prices.
2. Review the Planned Community Procurement Packaging including the
Community Employment Record in consultation with the Project Preparation
Team. The Department of Social Welfare and Development (DSWD) will ensure
that Deputy Area Coordinator (DAC) assesses the overall feasibility of municipal
and other counterpart contributions during the detailed community project
preparation. Community Monitoring Teams will ensure a record is kept of
municipal inputs (cash, equipment and services) during the community project
implementation to verify actual delivery against commitment. They will present
this to the community during the fifth barangay assembly.
The Planned
Community Procurement Packaging will contain the following information:
A. For Community Projects to be Executed Under Community Force
Account (CFA) Mode
During updating of status, the date of actual request and date funds received
must be indicated in the Actual Community Procurement Packaging.
3. Update the Actual Community Procurement Packaging.
2. Functional Specifications
- defines the job to
be done rather than
the
method
by
which it is to be
accomplished;
do
not
limit
the
supplier/contractor
to providing specific
solution,
thus
enabling
the
supplier/contractor
to create the best
possible
solution;
used
to
solicit
suppliers/contracto
rs proposals for further evaluation by the BSPMC when a specific
solution is not known. (Definition from the Philippine Institute of Supply
Management-PISM)
3. Performance Specifications
- describes the parameters of actual performance the item or
service must meet; interested in results rather than method; can
be described by a virtually unlimited choice of criteria and must be
Developing Standards:
What are the considerations in setting the standards and technical
specifications?
1. The standards and technical specifications quoted in procurement
documents should promote the broadest possible competition, while
assuring the critical performance or other requirements for the goods
and/or works under procurement;
2. The BSPMC should specify accepted standards based on the Department
of Public Works and Highways (DPWH) with which the equipment or
materials or workmanship should comply, except if such standard/s are
unavailable or inappropriate, may be specified; and,
3. the procurement documents should state that equipment, material or
workmanship meeting other standards, which promise at least substantial
equivalent, should also be accepted.
The Use of Brand Name
-
Use of Brand Name/s is not allowed as it limits competition and thus, increases
likelihood of higher prices.
May or may not improve the chances of receiving better quality; nevertheless,
they typically cost more as a result of higher advertising cost to create the
brand name.
2. Draw out suggestions from the barangay members of possible suppliers and
contractors, which can be added to the list prepared by the Procurement Team.
All issues raised and agreements reached should be reflected in the minutes of the
Assembly Meeting. The Procurement Team should refer to this when finalizing the
Planned Community Procurement Packaging and Community Employment Record.
b.
c.
d.
e.
Items that are within the major item of work needed to accomplish that particular item e.g. Construction of
Concrete Pavement for a Drying Pavement requires formworks. The formwork is the subsidiary item.
Local Bidding Goods package with total estimated cost of more than P500,000.00.
Direct contracting package with total estimated cost of not more than P125,
000.00
5. If the proposed work items are not within the capacity of the community and
municipality to implement, a package for works will be prepared and will observe
the procurement method.
Local Shopping works package with an estimated cost not more than P 1,250,000.
Local Bidding works package with total estimated cost of more than P1,250,000.
Direct Contracting small package with total estimated cost not more than
P250,000.00
6. It is important that the specifications of required materials for purchase are clearly
indicated in the PCPP for the reason that other Procurement Team members that
will prepare the canvass form and/or Invitation to Quote/Bid will copy the
procurement packages.
7. Once the packages are determined, sum-up all the costs of each package to
determine the amount and percent of tranches to be requested. The normal
tranche is 50%-40%-10% of the total KC Grant for the community project. Flexible
tranches as a result of appropriate packaging are allowed by the Project; 60-30-10;
70-20-10; or 80-10-10 for community project that will require big initial
investment.
8. Schedules of local counterpart delivery must also be considered. If the community,
barangay and municipal LCC can be delivered on the first, second tranches, it must
be clearly indicated on the respective column and form (Cash and in-kind LCC).
9. Group the packages subject for shopping and bidding.
10. Based on the implementation schedule, determine the activities and corresponding
package/s that will be needed to immediately start and will provide significant
accomplishment (will result to more than 30% which is the minimum requirement
for the second tranche) that the community or the contractor can undertake in the
given timeline.
11.Check the total amount of the package/s for the first tranche (with consideration to
the implementation schedule/Gantt chart). The total amount of package/s
grouped packages will dictate the amount of the first tranche.
If the amount needed for the first tranche exceeded the regular tranching which is
50%-40%-10%, analyze the PCPP and draft a justification based on the PCPP when
requesting for open tranche.
12. If the total amount of packages needed for the first tranche is below the regular 5040-10 tranching, the regular tranching will be applied.
Shown in the succeeding page is an example in projecting the request for
tranching (Estimators Guide)
B A R
C H A R T
ITEM
NO.
DESCRIPTION
EARTHWORKS
QUANTITY
UNIT
S-CURVE
AMOUNT
WEIGHT
MONTH 1
WEEK 1
PESO
P
2,310.00
sq.m.
7,808.00
MONTH 2
WEEK
2
WEEK 3
WEEK
4
18.816
%
18.816%
18.816
%
0.346%
0.346%
WEEK
1
MONTH 3
WEEK
2
WEEK
3
WEEK
4
0.096%
0.096%
0.096%
0.183%
0.183%
1.001%
1.001%
WEEK
1
WEEK
2
0.183%
0.183%
WEEK
3
WEEK 4
0.831%
0.831%
II
FORMS
AND
SCAFOLDINGS
III
MASONRY
74.00
cu.m.
IV
CONCRETING
33.25
cu.m.
VI
ROOFING/ROO
F FRAMING
7,400.00
sq.m.
VII
PLUMBING
575.00
cu.m.
VIII
DOORS
AND
WINDOWS
IX
18,429.00
cu.m.
10.00
set
ELECTRICAL
1.00
lot
SEPTIC VAULT
1.00
unit
XI
PAINTING
TOTAL
150.00
sq,m,
530,432.00
9,760.00
3,600.00
6,896.00
94,700.00
37,634.50
69,047.00
27,593.00
152,225.00
939,695.50
56.447%
P
A
1.039%
0.346%
A
0.383%
0.096%
A
0.734%
P
A
10.078%
5.039%
5.039%
A
4.005%
1.001%
1.001%
A
7.348%
7.348%
A
2.936%
2.936%
A
16.199%
4.050%
4.050%
4.050%
4.050%
A
100.00%
P
A
CALENDAR
MONTHLY PROGRESS
CUMMULATIVE
PLANNED
ACTUAL
PLANNED
ACTUAL
WEEK 1
WEEK
2
WEEK 3
WEEK
4
WEEK
5
WEEK
6
WEEK
7
WEEK
8
WEEK
9
WEEK
10
WEEK
11
WEEK 12
0.83%
26.16%
24.20%
24.20%
1.44%
1.10%
1.28%
1.28%
7.17%
4.23%
4.05%
4.05%
0.83%
26.99%
75.40%
76.84%
77.94%
79.22%
80.50%
87.67%
91.90%
95.95%
100.00%
51.20%
In the given example, assuming that the community project can be completed
in 90 calendar days, based on the projection it may be noticed that at the end of
the first month the accomplishment is 75.40%. This will determine the first
tranche that will be requested. The first tranche request could either be 70 or
80%. It is safe to request 80% first tranche.
PROC.
STAGE
Planning
Stage
PreProcurement
Stage
Procurement
Stage
Contract
Review
Barangay
Treasurer
-attends
procurement
training
workshop
Certifies on Fund
availability
Prepares
disbursement
voucher and
check
PROC.
STAGE
Community BAC-TWG
Community
Facilitator
Planning
Stage
PreProcurement
Stage
-attend procurement
training workshop
Procurement
Stage
Contract
Review
- provide guidance to
the BSPMC in the
preparation of
minutes of meeting
and to ensure that
minutes are properly
prepared, in order
and filed.
-conduct contract
review by ensuring
completeness of
documents using
checklist
Roving
Book
keeper
-Maintain
copies of
procurement
documents
at ACTs.
Deputy Area
Coordinator
-assist in the
preparation of
CPP
-conduct
training on
procurement to
volunteers
-provide
technical
assistance
during bid
evaluation
-attend pre-bid
conference
-attend bid
opening
-provide action
regarding red
flag of
abnormalities
as per
instruction of
AC.
Area
Coordinat
or
-provide
action
regarding
red flag of
abnormaliti
es
-issue
clearance
to direct
contracting
for goods.
RIE/DRIE
/RPO
-conduct
coaching on
procurement to
ACTs
-attend all prebid conference
-attend all bid
opening.
-consolidation
of action taken
regarding red
flag of
abnormality
Regional
Project
Manager
-provide action
regarding red
flag of
abnormalities not
resolve in the
ACT.
-issue clearance
for direct
contracting for
works.
-issue no
objection letter
to contract above
P500,000.00
6.6
Billboards
It is a policy of the project that billboards should be installed for each community
project for transparency purposes.
It must be placed at least 5 meters away from any commercial or political
billboard/s.
No political names should be indicated.
The A/MCT will remind the BSPMC on monthly updating of billboards for
transparency purposes. Likewise, A/MCT should coach the volunteers on how to
present the rates of accomplishment for better understanding of all community
members and the public.
CHAPTER 7 |
MODE OF IMPLEMENTATION
By Contract
By Community Force Account
7.1
By Contract
One or more packages undertaken by one or more contractors using his available
resources will provide labor, materials and equipment in order to effect timely
completion of the works. The BSPMC the representative of the owner
community, will supervise the implementation of the community project.
7.2
14
Specialized community projects are those that requires structural analysis for infra community projects and
new technologies introduced by other agencies.
15
TAF eligibility and requirements shall be based on the guidelines set by the NPMO.
CHAPTER 8 |
PROCUREMENT METHODS
2. WORKS
Conditions
Recommended
Methods
Local Shopping
Local Bidding
Shopping for
Work
Direct
Contracting
Description
Community solicits at
least three separate price
canvass from suppliers.
Among the factors to be
considered in choosing
the potential suppliers
are quality, availability,
reliability and hauling
costs.
Simplified bidding
process.
Lone local supplier can
be chosen without any
shopping for goods,
provided cost are in line
with local market rates
as shown in the Regional
Project Management
Team Unit Cost
Database. The AC should
have a copy of this
database. Clearance from
AC is required prior to
contracting.
Written quotations from
at least three qualified
licensed local contractors
shall be obtained.
Direct
Contracting
Local Bidding
for Works
CHAPTER 9 |
PROCUREMENT PROCEDURES
Local Shopping
Direct Contracting
Community Force Account
Local Bidding
9.1
Local Shopping
This procurement method is adopted when there are several local suppliers or
contractors and the value of each contract or procurement is:
1. Less than PhP500,000.00 for purchase of goods (materials, supply and
equipment); and,
2. Less than or approximately PhP1.25 M for works {construction, NRM
contracts and services (hauling, trucking, and equipment rental) }.
Given the ceilings for this procurement method, local shopping for goods is
expected to be the most frequently used among the different methods.
9.1.1 Local Shopping Goods Contract Less Than or Approx. PhP
500,000.00)
PROCEDURES
1.
TIME FRAME
1 Calendar
Day (CD)
DISCUSSION
Discuss the items of materials for
procurement using the Planned
Community Procurement Packaging
b.
PREPARATION
The BSPMC will discuss the preparation
and filling up of the following forms:
RESPONSIBLE
UNIT
BSPMC
Procurement
Team, BAC &
PIT
same day
Procurement
Team, BAC &
PIT
same day
BSPMC
Chairperson
same day
Procurement
Team
Tip:
If the BSPMC has to procure goods with
different packages, it is best to hold just
one pre-procurement conference to save
time.
Things to remember in filling up the
canvass:
- Indicate Date (prepared & schedule of
opening)
- Indicate if the items will be procured
by package/pick up
- Date of canvassing & where to solicit
- Do not forget to write specifications of
the goods/ materials.
c.
ACT
PARTICIPATION
CF will facilitate
meeting. DAC will act
as resource person.
(Particularly if the
community are
situated on a far flung
areas.)
PROCEDURES
conference.
2.
RESPONSIBLE
UNIT
BSPMCBookkeeper
ACT
PARTICIPATION
2 CD
@ least 2
Procurement
Team members
CF should accompany
during the first serving
of canvass.
2 CD
Suppliers
w/ in 3 CD
upon signing
acknowledgem
ent receipt
Procurement
Team
1 CD
(On date and
time indicated
in the
BAC, PT
(Invited: TWG,
Audit
Committee
TIME FRAME
same day
5.
CF observes the
process.
PROCEDURES
of canvass. Open the padlock of the box
and open one by one the sealed envelopes
and read aloud in public the name of
supplier and the total amount of prices.
BAC to initial the canvass forms.
TIME FRAME
canvass.)
RESPONSIBLE
UNIT
Head if
necessary)
ACT
PARTICIPATION
6.
same day
PT
same day
1 CD
BSPMC
Bookkeeper
BAC, TWG
same day
PT
same day
BSPMCBookkeeper
a.
Evaluation
Evaluate if canvass is responsive, i.e.,:
Specifications
Delivery or pick up price
By package or by item
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
ACT
PARTICIPATION
7.
b.
1 CD
Procurement
Team
same day
BAC
same day
BSPMC
Chairperson
PROCEDURES
8.
9.
TIME FRAME
RESPONSIBLE
UNIT
BSPMCBookkeeper
Procurement
Team
same day
1 CD
same day
MIT
same day
14 CD
Barangay
Treasurer
1 CD
same day
1 CD
(As scheduled
in the PO)
same day
1 CD
BSPMC
Chairperson
Procurement
Team
Supplier
Procurement
Team
Procurement
Team
Supplier
BSPMCBookkeeper
MIT with
concerned TWG
member
(depends on the
type of items to
be inspected)
MIT
BSPMCBookkeeper
Storekeeper
same day
Storekeeper
same day
BSPMCBookkeeper
1 CD
Brgy Treasurer
& BSPMC
b.
same day
Chairperson
1 CD
Supplier
same day
BSPMCBookkeeper
1 CD
BSPMCBookkeeper
ACT
PARTICIPATION
MRB
MRB
AC
Community Facilitator
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
ACT
PARTICIPATION
Preparation of Documents
1. Conduct pre-procurement
conference. This is an internal
meeting with the BSPMC.
The
objective
of
the
Preprocurement Conference is to
ensure that the procurement is in
accordance with the approved
PCPP;
properly
schedule
the
succeeding procurement activities;
and, to determine the availability
of the approved budget for the
package. The activities involved
are:
A. Discussion.
Discuss the items of works for
procurement using the Planned
Community Procurement
Packaging.
TIME FRAME
2 CD
same day
PT
same day
BSPMC
Chairperson
B.
RESPONSIBLE
UNIT
BSPMC, PT &
BAC
Preparation.
The Procurement Team will
prepare the following forms:
Invitation to Quote
Abstract of Quotation
Notice of Award
Contract Agreement
Notice to Commence
Performance bank
Technical Specifications
Drawing (if applicable)
Bank Guarantee (Advance
Payment)
Things to remember:
- Indicate the date prepared & schedule
of opening
- Do not forget to attach the specification
ACT
PARTICIPATION
CF will facilitate
meeting. DAC will
act as resource
person.
PROCEDURES
2.
TIME FRAME
RESPONSIBLE
UNIT
ACT
PARTICIPATION
1 CD
@ least 2
members of
Procurement
Team
Contractors Conference
Required for all contracts under local
shopping for works. To be done at least 5
days before the deadline of submission of
quotation. The purpose of the contractors
conference is to discuss the details of the
contract and clarify documents.
1 CD
BSPMC,BAC &
PT
same day
PT
same day
5 CD
PT
Contractor
1 CD
3.
CF should
accompany during
first serving of
canvass. (For
communities that
are situated on farflung areas.)
DAC to act as
resource person
same day
1 CD
DAC to act as
resource person.
PROCEDURES
6.
TIME FRAME
RESPONSIBLE
UNIT
COA Auditor,
Mun. Engr.,
DAC,
Contractors)
ACT
PARTICIPATION
7.
same day
PT
same day
Document Examination
Examine documents using the pass/fail
criteria specified in the Instruction to
Bidders:
I.
Technical Documents;
II.
Legal Documents; and,
III.
Financial Documents except
Bid Security
1 CD
(Immediately
after the Bid
Opening)
BSPMCBookkeeper
BAC & TWG, PT
1 CD
Evaluation
Evaluate if quotation is responsive,
i.e.,:
Specifications
BAC
BAC, TWG
PROCEDURES
Pass/Fail Criteria
TIME FRAME
RESPONSIBLE
UNIT
ACT
PARTICIPATION
w/ in same
day
PT
same day
BSPMCBookkeeper
within 3 CD
after
completion of
bid evaluation
Procurement
Team
DAC to provide
assistance
1 CD
BAC
w/ in same
day
BAC
DAC to provide
technical assistance.
same day
BSPMC
Chairperson
of TWG.
C.
PROCEDURES
TIME FRAME
Contract Preparation
11. Drafts contract
1 CD
same day
RESPONSIBLE
UNIT
Procurement
Team
BSPMC
Chairperson
1 CD
BSPMC
Chairperson
3 CD
RPMT (Infra
Engr. for infra
contracts.)
1 CD
1 CD after
receipt of NOL
The Regional
Project Director
or the Regional
Project Manager
in case the RPD
is on official
travel or on
leave.
BSPMC
Chairperson
w/ in same
day
Procurement
Team
2 CD
5 CD
Contractor
contractor
2 CD
Contractor,
BSPMC
Chairperson
with Punong
Barangay &
Area
ACT
PARTICIPATION
DAC to act as
resource person.
DAC to provide
technical assistance
Contract Signing
21. Signs the contract
AC to provide
assistance
PROCEDURES
TIME FRAME
1 CD
Immediately
upon contract
signing
Within 7 CD
Advance Payment
25. Contractor has the option to claim advance
payment equivalent to 15% of the contract
price subject to compliance of the following
requirement:
Certification from DAC that equipment
and materials are already mobilized on
the jobsite.
Bank guarantee equivalent to the amount
requested.
A.
Processing @ Barangay
DV & cheque signing
B.
Contractor
Within 3 CD
Mun. Engr.,
DAC, Regional
Infra Engr.,
Area
Coordinating
Team.
2 CD
Brgy Treasurer
& BSPMC
Chairperson
same day
DAC to provide TA
DAC to certify
mobilization of
equipment, workers
and materials.
MRB
MRB
AC
1 CD
Contractor
same day
BSPMCBookkeeper
1 CD
BSPMCBookkeeper
ACT
PARTICIPATION
As frequent as
necessary
Payment
27. Process Payment on accomplishments
certified by the Project Supervisor noted by
the Project Implementation Team/Mun.
Engr.
Reviews the documents
RESPONSIBLE
UNIT
Coordinator as
witnesses
Project
Implementation
Team
BSPMC
Chairperson
Community
Facilitator
DEADLINE
Pre-procurement
Serving of Canvass
w/in 7 days
/ Invitation to
for works
Quote
5 days
Contractors
before
Conference
submission
Submission and
Opening of Bids
Evaluation of
Quotation
GOODS
WORKS
Min
Max
Min
Max
1 CD
1 CD
1 CD
1 CD
1 CD
2 CD
7 CD
14 CD
1 CD
1 CD
7 CD
7 CD
1 CD
3 CD
3 CD
5 CD
3 CD
7 CD
3 CD
5 CD
1 CD
2 CD
1 CD
1 CD
3 CD
1 CD
Post Qualification
Issuance of NOL
and Notice to
Award
Signing of PO/
Prepn of
Resolution to
Award /Contract
Preparation
Issuance of PO /
Notice to proceed
2 CD
2 CD
1 CD
TOTAL
7 CD
9 CD
27 CD
45 CD
9.2
DIRECT CONTRACTING
9.2.1 Direct Contracting for Goods shall be used using the following
procedures:
1.
2.
3.
4.
5.
Supporting documents:
1. DAC certification (that it is cheaper to purchase from a local supplier)
2. ACT unit cost data base.
a. Only one exclusive distributor of the good to be procured.
b. Repeat Order of additional goods of a similar nature previously
acquired through local shopping or bidding. Repeat Orders shall be
subject to the following conditions:
Unit prices of the repeat order must be the same as or lower than
those in the original contract, provided that such contract is still
the most advantageous to the BSPMC after price verification;
The repeat order may be availed of only within three (3) months
from the date of the original purchase; and
The quantity shall not exceed the quantity in the original contract
c. Purchase value under this method should not exceed PhP 125,000.
d. If after failure of canvass, direct contracting is allowed subject to
amount in the threshold.
9.2.1 Direct Contracting For Goods Detailed Procedures
PROCEDURES
1.
TIME FRAME
RESP. UNIT
B. Discussion
BSPMC to discuss items of materials for
procurement using the Planned Community
Procurement Package. The Municipal
Engineer and Deputy Area Coordinator will
certify that there is only one supplier in the
municipality.
1 CD
BSPMC,
BAC,PT,PIT
C.
same day
PT
Pre-procurement Conference
Conduct of pre-procurement conference.
This is an internal meeting with the BSPMC.
Preparation
The Procurement Team will prepare the
following:
D.
DAC to provide
technical assistance
Computation it is cheaper to
purchase from the lone supplier
compared to supplier outside the
municipality.
Canvass form
Purchase Order
ACT
PARTICIPATION
same day
BSPMC
PROCEDURES
TIME FRAME
2.
RESP. UNIT
Chairperson
PT
same day
same day
1 CD
BSPMCBookkeeper
PT
2 CD
Supplier
1 CD
Supplier
1 CD (On the
date & time
indicated in
the canvass)
BAC, PT
(Invited: TWG,
Audit
Committee
Head if
necessary)
same day
PT
same day
1 CD
Bookkeeper
BAC
w/assistance of
TWG
1 CDafter
receipt of NOL
BSPMC
Chairperson
1 CD
a.
b.
ACT
PARTICIPATION
5.
6.
7.
8.
9.
1 CD
Procurement
Team
Supplier
same day
PT
same day
PT
CF observe the
process
PROCEDURES
Keeping of all records
Delivery of Goods
10. Delivers the goods
11. Inspects the goods against the delivery
receipt and the purchase order.
TIME FRAME
RESP. UNIT
same day
As scheduled
in the PO
w/ in same
day
PT
Supplier
w/ in same
day
Storekeeper
w/ in same
day
1 CD
Storekeeper
One day
BSPMCBookkeeper
Processing @ Barangay
DV & Check signing of Treasurer &
BSPMC Chairperson
B.
ACT
PARTICIPATION
MIT with
concerned TWG
member
(depends on the
type of items to
be inspected)
MIT
Brgy Treasurer
Community
Facilitator
9.2.2.1 Direct Contracting for Works shall only be used under the
following cases
1.
TIME FRAME
Pre-procurement Conference
Conduct of pre-procurement conference.
This is an internal meeting with the BSPMC.
A.
Discussion
Discuss items of works for procurement
using the Planned Community
Procurement Package. The
Procurement Team should submit
certification to the BAC that there is
only one contractor in the municipality.
B.
Preparation
The Procurement Team will prepare the
following:
RESPONSIBLE
UNIT
1 CD
BSPMC, BAC,
PIT, PT
same day
Procurement
Team
same day
BSPMC
Chairperson
same day
PT
same day
BSPMCBookkeeper
a. Computation it is cheaper to
purchase from the lone contractor
compared to supplier outside the
municipality.
b. Invitation to Quote
c. Notice of Award
d. Contract Agreement
e. Technical Specifications
f. Drawing (if applicable)
C.
2.
1 CD
Procurement
Team assisted
by DAC
ACT
PARTICIPATION
CF will facilitate
meeting. DAC will
act as resource
person.
PROCEDURE
TIME FRAME
RESPONSIBLE
UNIT
ACT
PARTICIPATION
Name of Contractor
Address
Quotation
for:________________________
KALAHI-CIDSS: Barangay Community
Project Management Committee
Address of Barangay
3.
1 CD
Contractor
2 CD (As
provided in the
request)
Procurement
Team
1 CD (on the
date & time
indicated in
the Invitation
to Quotation)
BAC, PT
(Invited: TWG,
Audit
Committee
Head if
necessary)
same day
1 CD
PT
BAC
w/assistance of
TWG
DAC to provide
assistance
3 CD after
completion of
bid evaluation
Procurement
Team
DAC to provide
assistance
8. Drafts contract
1 CD
9. Reviews contract
same day
Procurement
Team
BSPMC
Chairperson
DAC to act as
resource person.
Review by RPMT
11. Review the documents and recommend
issuance of No Objection Letter
1 CD
BSPMC
Chairperson
ACT to provide
assistance
3 CD
ACT to follow up
NOL
2 CD
Regional Infra
Engr /
concerned staff
Regional Project
Manager
CF observe the
process
6.
7.
Evaluation of quotation.
Evaluate quotation if it is responsive, i.e.,:
a. Specification
b. Pass/Fail Criteria
Conducts post-qualification of the lowest
calculated responsive quotation by
validating contractors documents. Submits
post-qualification report to BAC
PROCEDURE
TIME FRAME
RESPONSIBLE
UNIT
1 CD after
receipt of NOL
BSPMC
Chairperson
w/ in same
day
Procurement
Team
2 CD
Contractor
5 CD
Contractor
b.
Contract Signing
15. Signs the contract
16. Furnishes copy of signed contract to LGU
COA Auditor and RPMO
Payment
20. Processes payment based on
accomplishments certified by the Project
Supervisor noted by Project
Implementation Team.
A.
Processing @ Barangay
DV & Check signing
B.
2 CD
same day
1 CD upon
contract
signing
Contractor,
BSPMC
Chairman,
witnesses
Procurement
Team
BSPMC
Chairperson
Within 7 CD
Contractor
As frequent as
necessary
Mun. Engr.,
DAC, RIE, Area
Coordinating
Team.
2 CD
Brgy Treasurer
1 CD
MRB
MRB
AC
Immediately
upon payment
Contractor
ACT
PARTICIPATION
PROCEDURE
TIME FRAME
1 CD
RESPONSIBLE
UNIT
BSPMCBookkeeper
ACT
PARTICIPATION
Community
Facilitator
PAYMENT
1.Before commencing the work, the barangay treasurer has to certify the
availability of funds.
2.Payment will be made after the completion of the work only as certified
by the Project Supervisor.
DIRECT CONTRACT DOCUMENTS.
1.Proposal
2.Direct Contract Agreement
3.List of Tools to the provided to the Group
PROCEDURES
1.
2.
3.
4.
5.
Pre-procurement Conference
Convene and discuss the details of the
project to be implemented by the
community under CFA.
a.
b.
c.
d.
TIME FRAME
1 CD
RESPONSIBLE
UNIT
BAC, PT, PIT,
MIT, AIT
Invited: Project
Supervisor,
Mun. Engineer,
DAC
Procurement
Team
BSPMC
Chairperson
BAC
Awarded 2 wks
before the
work starts
Delivered 1 wk
before the
work starts
PIT, PT
As scheduled
Project
Supervisor/
Group Leader
As frequent as
necessary
Mun. Engr.
DAC, Area
Coordinating
Team, RIE
Frequency as
agreed by the
community
Brgy Treasurer
ACT
PARTICIPATION
CF to facilitate the
meeting. DAC as
resource person
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
ACT
PARTICIPATION
Brgy Treasurer
7.
Brgy Treasurer
8.
Workers
Group Leader
9.
Brgy.
Bookkeeper
1.
TIME FRAME
Pre-Procurement Conference
Conduct of pre-procurement conference .
This is an internal meeting with the BSPMC.
RESPONSIBLE
UNIT
A.
Discussion
BSPMC will discuss the items of
materials for procurement using the
Planned Community Procurement
Package.
1 CD
B.
Preparation
The procurement team will prepare the
following forms.
a. Invitation to Bid
b. Abstract of Bids
c. Form of Bid
d. Purchase Order
e. Form of Bid Security (Bank
Guarantee)
same day
PT
ACT
PARTICIPATION
CF to facilitate
meeting. DAC to act
as resource person.
PROCEDURES
TIME FRAME
2.
3.
4.
RESPONSIBLE
UNIT
same day
BSPMC
Chairperson
same day
Procurement
Team
same day
BSPMC Bookkeeper
2 CD
It must be
posted for two
weeks
Procurement
Team
CF to ensure wider
circulation
For a period of
two weeks
from date of
posting of
Invitation to
Bid
Procurement
Team
DAC to provide TA
1 CD
DAC to act as
resource person
same day
Procurement
Team
same day
Bookkeeper
same day
ACT
PARTICIPATION
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
6.
7.
w/ in 7 CD
Contractor
On or before
the date and
time specified
on the
Invitation to
Bid.
Procurement
Team
1 CD (Send
written
invitation one
(1) week
before bid
opening)
A day before
bid opening
On the date
specified in
the invitation
to bid.
1 CD
BAC
same day
BAC Chairman
same day
PT
same day
BSPMC
a.
b.
c.
d.
8.
9.
16
Procurement
Team
Procurement
Team
BAC Chairman
ACT
PARTICIPATION
PROCEDURES
Keeping of all documents
same day
RESPONSIBLE
UNIT
Chairperson
Bookkeeper
Procurement
Team
1 CD
(Immediately
after the Bid
Opening)
TIME FRAME
ACT
PARTICIPATION
BAC
w/assistance of
TWG
same day
PT
same day
Bookkeeper
2 CD (after
completion of
bid evaluation)
Procurement
Team
BAC
1 CD
DAC to provide
technical assistance.
PROCEDURES
Calculated and Responsive Bid (LCRB).
Review and signs the RTA
Contract Preparation
16. Drafts Purchase Order
TIME FRAME
RESPONSIBLE
UNIT
W/ in same
day
1 CD
BSPM
Chairperson
Procurement
Team
a.
1 CD
BSPMC
Chairperson
b.
2 CD
NPMO Staff
c.
1 CD
National Project
Manager
1 CD
(Immediately
upon receipt of
NOL)
w/ in same
day
Procurement
Team
w/ in same
day
BSPMC
Chairperson
Procurement
Team
Supplier
Monitoring
23. Monitors delivery of goods
1 CD
w/ in 5 CD
from receipt of
NOA
Supplier
Upon
submission of
Performance
Security
BSPMC
Chairperson
w/ in 1 CD
upon receipt of
PO
Supplier
1 CD
Procurement
Team
1 CD
Brgy
Bookkeeper
2 CD
Procurement
Team
As provided in
the delivery
schedule.
Supplier
As scheduled
MIT with
ACT
PARTICIPATION
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
assistance from
Mun. Engr.,
concerned MIAC
member, DAC
(if necessary)
As often as
necessary
Mun. Engr.
DAC, AC Reg.
Infra Engineer
ACT
PARTICIPATION
Processing @ Barangay
DV & Check signing of Treasurer &
BSPMC Chairperson
2 CD
Brgy. Treasurer
B.
same day
Contractor
Immediately
upon payment
1 CD
Brgy Treasurer
Community
Facilitator
BSPMCBookkeeper
1.
TIME FRAME
Pre-Procurement Conference
Conduct pre-procurement conference. This
is an internal meeting with the BSPMC.
A.
B.
Discussion.
Discuss the item of works for
procurement using the Planned
Community Procurement Packaging
(PCCP).
Preparation
Prepare the following:
Invitation to Bid for works
Instruction to Bidders
Bidding Data
Conditions of Contract
Contract Agreement
Engineering Drawings
Technical Specifications
Form of Bid
Form of Bank Guarantee for
Advance Payment
Form of Bid Security(Bank
Guarantee)
RESPONSIBLE
UNIT
1 CD
BAC,BSPMC,PT,
TWG
same day
Procurement
Team
ACT
PARTICIPATION
CF will facilitate
meeting. DAC will
act as resource
person.
PROCEDURES
2.
3.
4.
TIME FRAME
RESPONSIBLE
UNIT
same day
BSPMC
Chairperson
same day
PT
same day
BSPMC Bookkeeper
@ least 2
Procurement
Team members
For a period of
two weeks
from date of
posting of
Invitation to
Bid
Procurement
Team
1 CD
same day
Procurement
Team
same day
same day
BSPMCBookkeeper
free of charge
5.
ACT
PARTICIPATION
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
DAC, Bidders
same day
Procurement
Team
w/ in 7 CD
bidders
1 wd (On or
before the
date and time
specified on
the invitation
of bid.)
Procurement
Team
1 CD (Send
written
invitation one
(1) week
before bid
opening)
1 CD (One day
before bid
opening)
1 CD (Right
after the
deadline for
submission of
bid)
1 CD (w/ in
same day)
BAC
same day
BAC
same day
PT
same day
BSPMC
Chairperson
same day
BSPMCBookkeeper
Procurement
Team
6.
7.
8.
9.
Procurement
Team
BAC
ACT
PARTICIPATION
PROCEDURES
b.
c.
d.
TIME FRAME
Bid Examination
13. Examines bids using the pass/fail criteria.
check the technical, legal and
financial documents indicated in the
Instructions to bidders
RESPONSIBLE
UNIT
1 CD (Right
after the Bid
Opening)
same day
TWG
1 CD
BAC
same day
Procurement
Team
same day
BSPMCBookkeeper
2 CD after
completion of
bid evaluation
Procurement
Team with the
assistance of
TWG
same day
BAC
W/ in same
day
BSPM
Chairperson
ACT
PARTICIPATION
PROCEDURES
TIME FRAME
RESPONSIBLE
UNIT
Post-qualification
Contract Preparation
16. Drafts Contract (use proforma contract for
works)
Prior Review by NPMT
17. Required for all contracts regardless of the
amount for all Local bidding for Works.
a. Request for NOL from NPMO. To be
attached to the request are: RTA, draft
contract, form of bids, bidding
documents and all other supporting
documents (send only photo copy
except for request letter).
b.
b.
c.
1 CD
Procurement
Team with
assistance from
DAC
1 CD
BSPMC
Chairperson
1 CD
NPMO Staff
5 CD
NPM
1 CD upon
receipt of NOL
Procurement
Team
w/ in same
day
1 CD
BSPMC
Chairman
Procurement
Team
2 CD
Contractor
5 CD from
receipt of NOA
Contractor
5 WD upon
receipt of NOA
Contractor
witness
1 CD
BSPMC Chair
Note:
If security is in the form of cash or check, then
it should be deposited in the BSPMC account by
the winning bidder and submit to BSPMC the
deposit slip with bank validation.
1 CD
ACT
PARTICIPATION
PROCEDURES
Advance Payment
23. Contractor has the option to claim advance
payment equivalent to 15% of the contract
price subject to compliance of the ff:
requirement:
a. Certification from DAC that equipment
and materials are already on the
jobsite.
b. Bank guarantee equivalent to the
amount requested.
Payment
26. Process payment based on accomplishment
approved by BSPMC Chairperson as
recommended by PIT noted by Municipal
Engineer
TIME FRAME
1 CD
1 CD
w/ in same
day
1 CD
w/ in 7 days
from receipt of
Notice To
Commence
Within 3 CD
RESPONSIBLE
UNIT
ACT
PARTICIPATION
Procurement
Team
BSPMC
Chairperson
Procurement
Team
Procurement
Team
Contractor
Barangay
Treasurer
daily
PIT, MIT
As often as
necessary
Mun. Engr.
DAC, RIE, AC
A.
Processing @ Barangay
DV & Check signing of Treasurer &
BSPMC Chairperson
2 CD
Brgy. Treasurer
MRB
B.
same day
Contractor
MRB
AC
Immediately
upon payment
One day
BSPMCBookkeeper
Community
Facilitator
DEADLINE
ACTIVITIES
WORKS
Min
Max
Min
Max
1 CD
1 CD
1 CD
1 CD
7 CD
14 CD
7 CD
14 CD
1 CD
1 CD
1 CD
1 CD
7 CD
7 CD
7 CD
7 CD
1 CD
1 CD
7 CD
7 CD
1 CD
1 CD
1 CD
3 CD
1 CD
3 CD
1 CD
3 CD
21 CD
28 CD
27 CD
38 CD
5 (RPMO)
5 (NPMO)
15 (WB)
26 CD
5 (RPMO)
5 (NPMO)
15 (WB)
38 CD
5 (RPMO)
5 (NPMO)
15 (WB)
37 CD
5 (RPMO)
5 (NPMO)
15 (WB)
48 CD
3 CD
7 CD
3 CD
7 CD
2 CD
5 CD
2 CD
5 CD
Issuance of Notice to
Proceed
1 CD
3 CD
1 CD
3 CD
TOTAL
32 CD
53 CD
43 CD
53 CD
Pre-procurement
Advertisement/Posting
of Invitation
Pre-bid Conference and
Site visit
Issuance of bidding
documents
Submission and Opening
of Bids
7 CD before
deadline of
submission of
bids
Bid Evaluation
Post Qualification
SUB- T O T A L
Issuance of NOL
SUB- T O T A L
Issuance of Notice of
Award
Contract Preparation and
Signing
b. The bid security shall be returned to the bidders only after the
successful bidder has signed the Contract and posted the performance
security, except if the bidder fails to comply with all the requirements and
the bid is marked failed.
c. Bidder, who wants to present cash as bid security, shall be instructed to
deposit the amount to the communitys bank account and to attach the
machine validated deposit slip to the bid documents to be placed in a
sealed envelope.
4. Defects Liability Period
This refers to the period from the date of issuance of Certificate of
Completion of the works as certified by the BSPMC Chairman up to the
date within which, the contractor shall still be liable for defects, shrinkage
or other faults as determined by BSPMC. The contractor shall execute all
such work needed to amend, reconstruct, or remedy at his own cost.
5. Eligibility Requirements
These refer to qualifications set by the BAC for participating bidders.
Some examples of qualifications are:
a. Suppliers must have a SEC Registration, mayors permit or municipal
license, or the Cooperative Development Authority, if a cooperative;
b. Contractors for works must be either a duly licensed Filipino citizen or
a sole proprietorship, or a duly registered partnership or corporation.
6. Minor Deviations
These are deviations in the bid that can be corrected. Some examples are
the following:
a. Computational error such as when the total amount is not equal to the
unit cost times the number of units. In this case, it is the unit cost,
which should be taken as the correct amount, and the total price
should be corrected.
b. Discounts which do not have pre-conditions should be applied to the
total price to get the net amount.
c. Minor deviations shall be corrected and
computed to determine the calculated price.
adjustments
shall
be
a. Bid contains a different design that does not respond to the contract
plans and specifications;
b. Stipulates price adjustment when bid price should be fixed given the
short duration of the contract;
c. Proposed timeframe of implementation does not conform to the
required period;
d. Bid contains provision to exempt the bidder from some critical
provisions of the contract.
8. Retention Money
Retention fee refers to the 10% amount retained from all progress billings
to cover uncorrected discovered defects and third party liabilities. This is
mandatory for all contracts with PhP 1M or more in addition to
performance Security. For contracts with less than PhP 1M, retention fee
is only deducted from the progress billing when there is no Performance
Security posted. The retention fee, if not called shall be refunded to the
contractor after the expiration of the warranty period. The refund shall not
be subjected to Withholding Tax.
In case where closing of community account is mandated by the project,
the BSPMC shall require the Contractor to convert to Bank Guarantee or
Managers Check or Cashiers Check from a reputable bank. Upon
receipt of the Bank Guarantee or Managers Check or Cashiers Check,
the treasurer shall prepare a Disbursement Voucher and issue a check
equal to the amount of retention.
9.4.4 ADDITIONAL GUIDELINES ON LOCAL BIDDING (also applies to
Shopping for Works)
1. On receiving sealed bids
a. The BSPMC Chairperson authorizes the Procurement Team members to
receive the sealed bids.
b. At least one Procurement Team member shall be stationed at the
barangay hall to receive the bids.
c. Receiving Procurement Team member should be advised to accept
only bid documents that are contained in one sealed envelope with the
name of the bidder written outside. Furthermore, that he/she is not
authorized to open the envelope.
d. Bids received after the deadline set shall automatically be rejected.
2. Modification and Withdrawal of Bids
a. No bid shall be changed after the deadline for submission of bids.
b. Withdrawal of bid between the deadline for submission and of bids and
the expiration of the validity of bid will result in the contractor being
disqualified from participating in any KALAHI-CIDSS Project for two
(2) years.
3. Bid Opening (On the same day just after the time set as deadline
for submission of bids)
a. The Procurement Team prepares a checklist of all the documents
required to be submitted. There should be as many copies of the
checklist as the number of participating bidders.
b. Bidders or their representatives and interested barangay residents
may observe the bid opening.
c. Bids with incomplete requirements specified in the Invitation to Bid
shall be marked failed. All bids with complete requirements shall be
marked passed and shall be considered for evaluation.
d. Bid security submitted by bidders whose bids were marked failed
should be returned.
Let us clarify things:
What if a calamity such as typhoon or flash flood or other fortuitous event
happened during the scheduled submission opening of bids?
In such cases, postponing or re-scheduling is allowed for all methods of procurement.
However, a certification coming from the A/MCT signed by the Area/Municipal
Coordinator shall be attached to minutes during the re-scheduled opening stating the
reasons for postponement/re-scheduling. The BAC should give at least 2 days for
shopping for goods, at least 5 calendar days to a maximum of 7 calendar days for
bidding for goods, shopping for works and bidding for goods as allowance before the rescheduled opening. The BSPMC Chair should then prepare a Supplemental or Bid
Bulletin following the procedures for publication (for bidding for works), posting,
personal dissemination to bidders or other possible means to inform service providers
of the postponement/re-scheduling.
4. Bid Evaluation
a. The TWG shall assist the BAC in the evaluation of bids. The TWG
should explain fully every step in the evaluation process as part of the
capacity building of the BSPMC.
b. The following shall be considered in the evaluation:
The bid must be complete. This means that all the required
items in the bidding documents should be addressed.
qualification evaluation.
If he passed in the post qualification evaluation , he will be declared as the Lowest
Calculated and Responsive Bidder.
If the request for reconsideration is denied and the next in rank bidder
passes the post qualification, the latter shall be declared the bidder
with the Lowest Calculated and Responsive Bid.
g. If the second lowest bidder fails in the post qualification, the process
will be repeated for the bidder with the next lowest calculated bid and
again be repeated until a bidder is declared as the bidder with the
LCRB.
h. If no bidder passes the post qualification, the bidding shall be declared
a failure. Re-bidding will be conducted. If the same situation results
from the second bidding, the BSPMC can enter into negotiated
contract.
A: Postqualification involves the BAC verifying, validating and ascertaining that the bidder satisfies the
following:
1. LEGAL Requirements. The post-qualification process under this criterion involves the verification, validation
and ascertaining of the contractors claim that ii is not included in any government blacklist, as well as all the
licenses, permits and other documents it submitted, including the following: a. PCAB License; SEC registration
or the DTI name registration; Mayors permit; BIR Certification which contains the TIN; Authority of the
Signatory; contracts for the last 2 years, and, Affidavit of compliance with the Disclosure Provision and other
documents specified in the invitation to bid.
2. TECHNICAL Requirements. The BAC would have to verify, validate and ascertain the veracity of the
documents submitted by a contractor to prove compliance of the infra project it offered with the requirements
of the contract and bidding documents. This involves the following:
a. Verification of the bidders stated competence and experience, as well as the competence
and experience of its key personnel to be assigned to the project, to ensure that these
meet the minimum requirements;
b. Verification of availability and commitment, and/or inspection and testing, of equipment
units to be owned or leased by the bidder, as well as checking the performance of the
bidder in its ongoing govt or private contracts, e.g. examine the Construction Schedule,
Construction Methods, Equipment Utilization Schedule, List of projects undertaken or
ongoing and to be started.
c. Verification if any bidders on-going contracts show:
A reported negative slippage of at least 15%;
Substandard quality of work per contract plans and specifications;
Unsatisfactory performance of his obligations as per contract terms and conditions, at
the time of inspection; or
That the minimum required experience of the bidders key personnel were not met;
All of which will be grounds for disqualification if found by the BAC to be due to the
bidders fault or negligence.
d. Ascertain of the sufficiency of the Bid Security as to type, amount, form and wording, and
validity period.
e. other documents specified in the invitation to quote.
3. FINANCIAL Requirements. The BAC ought to verify, validate and ascertain the bid price proposal of the
bidder and, whenever applicable, the required bank commitment to provide a credit line to the bidder in the
amount specified and over the period stipulated. It also means verifying, validating and ascertaining, the
bidders stated net worth and liquid assets, net working capital , the value of all outstanding or unfinished works
under ongoing contracts, and the bidders NFCC, as recalculated considering developments in the bidders other
projects. This is also done to ensure that the bidder can sustain the operating cash flow of the transaction. The
process involves:
a. Examination of the Bill of Quantities, Detailed Estimates and Cash Flow;
b. Ascertaining of the sufficiency of the Bid Security (if required) as to type, amount, form and
wording, and validity period;
Ascertain the NFCC, credit line, or cash deposit; and,
c.
d. Examination of the BIR-audited financial statement.
CHAPTER 10 |
PROCUREMENT FORMS and
MONITORING FORMS
The Barangay Sub-Project Management Committee Chairman shall submit
to the Area Coordinating Team the Actual Community Procurement
Packaging and Community Employment Record status on a monthly basis
or when making a request for the release of funds. This shall be prepared
by the Procurement Team, noted by SP Implementation Team and Brgy.
Treasurer and approved by the BSPMC Chairperson. As part of enhanced
oversight and support mechanisms, the Regional Project Management
Office will also be conducting unannounced visits to barangays to ensure
that the ACTs have sufficient support for any issues that may arise, and to
conduct spot reviews to ensure correct implementation of KALAHI-CIDSS
procedures, particularly with regard to procurement.
I. TECHNICAL DOCUMENTS
Form of Bid (in prescribe form)
Program of Works
Plans
Detailed Estimates including summary sheet showing unit prices of
materials, labor rates and rentals
List of equipment owned/leased
Official Receipt (to support owning the equipment for equipment proposed
for use for the contract only)
Certificate of registration (to support owning the equipment for proposed
equipment for use for the contract only)
Schedule of utilization of equipment
List of similar projects undertaken for the last 2 years
Certification that each document submitted is an original or true copy of
the original
Certification from the bidder under oath of its compliance to labor laws
and standards and to utilize unskilled labor in the area
Notarized Affidavit for Defect Liability Commitment
List of Technical personnel
Site Visit Certificate
Detailed Construction method indicating the detailed methodology in
complying with Environmental Laws for the each Item of Work
involved, Safety measures
Bidding data sheet
Product Standard Certification Mark PS Mark License (for pipe materials)
II. FINANCIAL DOCUMENTS
Latest Income Tax Return w/ audited statement with Taxpayers
Identification Number
NFCC
Bid Security form, amount and validity period; only the following are
acceptable:
Cash, cashiers check, managers check, bank draft or irrevocable letter of
credit - 2 % of bid price
Bank Guarantee 2% of bid price
III. LEGAL DOCUMENTS
Contractors License or Temporary Certificate of Renewal (for expired
License)
SEC registration w/ articles of Incorporation (for Corporations)
Authority of the signatory
Contracts (similar contracts for the last two years only)
Certificate of Acceptance (contracts for the last 2 years only)
Affidavit of Undertaking
7. Price Bid:
The Contract shall be for the whole works as described in the Invitation and shall
be based on the unit and total price on portion of work items indicated in the Bill
of Quantities. The Contractor shall fill in the rates and prices for all items of the
Works described in the drawings and specifications listed in the Bill of Quantities.
The Owner will not pay for items, which were left blank by the Contractor, if
executed. They shall be deemed covered by the other rates and prices in the Bill
of Quantities. All fees and taxes payable by the Contractor under the Contract
shall be included in the rates, prices, and total price bid submitted by the
Contractor. The contract price quoted by the Contractor shall be fixed for the
duration of the Contract and shall not be subject to any price adjustment.
8. Bid Security:
The Bidder shall furnish as part of the Bid, a Bid Security in local currency or in a
freely convertible currency, in the amount specified in the Bidding Data.
The Bid Security shall, at the Bidders option, be in the form of a certified
check, bank draft, or bank guarantee from a reputable bank located in the
region of the BSPMC.
The Bid Security of the successful Bidder will be discharged when the Bidder
has signed the Agreement and furnished the required Performance Security.
9. Validity of Bid:
The price bid shall remain valid for the period of sixty (60) calendar days
counted from the date of the Bid. The BSPMC may request in writing the
Contractor/s to extend the period of validity for a specified additional period. The
Owners request and the Contractors responses shall be made in writing. A
Contractor may refuse the request for extension of bid validity in which case he
may withdraw his Bid without any penalty. A Contractor agreeing to the request
will not be required or permitted to change its Bid.
10. Preparation and Sealing of Bids:
The Contractor shall prepare one original and one duplicate copy of the
documents comprising the Price Bid. The contractor or person duly authorized by
the contractor shall sign the original and duplicate copy of the Price Bid.
The person or persons signing the Price Bid shall initial all the pages of the Bid
where entries or amendments or corrections have been made. The Contractor
shall seal the documents in one envelope addressed to the BSPMC at the
specified address and shall provide a warning not to open before the specified
time and date for Price Bids opening.
On the upper left-hand corner of the envelope, the contractor shall indicate
his/her name and full address. If the envelope is not sealed and marked as
above, the Owner will assume no responsibility for the misplacement or
premature opening of the Price Bid.
18. BSPMCs Right to Accept Any Bid and to Reject any or all Bids:
The BSPMC has the right to accept or reject any bid/quotation, and to cancel the
bidding process and reject all bids, at any time prior to the award of the
Contract. The affected Contractor(s) will not hold the BSPMC liable. It is not
also obliged to inform the affected Contractor(s) of the grounds for its decision.
19. Notification of Award and Signing of Contract:
The BSPMC shall notify the Contractor of the award in writing prior to the
expiration of the validity period of the Bid. This Notice, together with a contract
will state the amount that the BSPMC will pay the Contractor in consideration of
the execution, completion, and maintenance of the Works by the Contractor as
prescribed by the Contract.
20. Performance Security
20.1 Within 21 days after receipt of the Letter of Acceptance the successful
Bidder shall deliver to the BSPMC a Performance Security in the amount
stipulated in the Contract data and in the form stipulated in the bidding
Data.
20.2
20.3
j)
A Defect is any part of the Works not completed in accordance with the
Contract.
k) The Defects Liability Period for infrastructure projects shall be one year
from project completion up to final acceptance by the BSPMC. During this
period the contractor shall undertake the repair work at his own expenses, of
any damage to the infrastructure projects on the account of the use of
materials of inferior quality within 45 days from the time the BSPMC
Chairperson has issued an order to undertake repair. In case of failure or
refusal to comply with this mandate, the BSPMC shall undertake the repair
works and shall be entitled to full reimbursement of expenses incurred
thereon upon demand.
Any contractor who fails to comply with the preceding paragraph shall be
perpetually disqualified from participating in any public bidding and his
property or properties will be subjected to attachment or garnishment
proceedings to recover the costs. All payable of the BSPMC, in the
contractors favor shall be offset to recover the costs.
l)
m) Materials are all supplies, including consumables, used by the Contractor for
incorporation in the Works.
n)
uncorrected. Every time notice of a defect is given, the Contractor shall correct
the notified defect within the length of time specified in the Project Supervisors
notice.
If the Contractor has not corrected a defect within the time specified by the
Project Supervisors notice, the Project Supervisor will assess the cost of having
the defect corrected. The Contractor will pay this amount. BSPMC shall recover
these amounts by deducting from the amounts due to the Contractor. Failure by
the Contractor to pay the BSPMC will be a ground to disqualify him from
participating from other KALAHI-CIDSS community project.
After final acceptance of the project, the contractor shall be held responsible for
structural defects and/or failure of the completed project within the warranty
period (as provided in Sec 62 of the Revised IRR 9184) from final acceptance,
except those occasioned by force majeure and those caused by other parties.
10. Program:
Within seven (7) days of the written notification of award, the Contractor shall
submit to the Project Supervisor for approval a Program showing the general
methods, arrangements, order, and timing for all activities of the Works. The
BSPMC approval of the Program shall not change the Contractors obligations.
The Contractor may revise the Program and submit it to the Project Supervisor
again at any time. A revised Program will show the effect of the changes.
11. Activity Schedule:
The Contractor shall provide updated Activity Schedules within ten (10) days of
being instructed by the Project Supervisor. The activities on the Activity
Schedule will be coordinated with the activities of the Program.
12. Changes in Quantities:
The Contractor shall carry out all the activities and complete them in accordance
with the scope of works specified in the Contract as part of the prices in the
Activity Schedule, which shall not be subject to any change. In the case of unit
rate contracts no adjustment in the unit rate shall be made if the variation in
quantity does not exceed 25% of the entire estimated quantity. If the variation
exceeds 25%, the Project Supervisor will determine if there is any justification to
revise the unit price, based on information provided by the Contractor, and will
fix such rate as he deems appropriate with the approval of the BSPMC. The BSPM
shall secure clearance from RPMO prior to any changes in quantities.
13.
Payment Certificate:
The Project Supervisor shall check the Contractors executed work and certify the
amount to be paid to the Contractor. The value of work executed shall comprise
the value of completed items of work or activities in the Activity Schedule.
14. Payments:
Payments shall be adjusted for deductions on account of advance payments and
retention money. The BSPMC shall pay the Contractor the amounts certified by
the Project Supervisor within thirty (30) days of the date of each certificate. The
Contractor may request payment every substantial accomplishment not below
20% of total contract amount.
15. Retention:
Retention fee refers to the 10% amount retained from all progress billings to
cover uncorrected discovered defects and third party liabilities. This is mandatory
for all contracts with PhP 1M or more in addition to performance Security. For
contracts with less than PhP 1M, retention fee is only deducted from the progress
billing when there is no Performance Security posted. The retentionfee, if not
called shall be refunded to the contractor after the expiration of the warranty
period. The refund shall not be subjected to Withholding Tax.
In case where closing of community account is mandated by the project, the
BSPMC shall require the Contractor to convert to Bank Guarantee or
Managers Check or Cashiers Check from a reputable bank. Upon receipt of
the Bank Guarantee or Managers Check or Cashiers Check, the treasurer shall
prepare a Disbursement Voucher and issue a check equal to the amount of
retention.
16. Taxes:
The Contractor is responsible for all taxes in accordance with Philippine laws and
ordinances of the local government units.
17. Advance Payment:
The BSPMC may make advance payment to the Contractor in the amount up to
fifteen (15) percent of the Initial Contract Price only after the DAC had certified
materials and equipment presence on site and the Contractor has provided Bank
Guarantee of equal amount. If there is no Bank Guarantee posted by the
Contractor, at his request the BSPMC may make payment directly to the supplier
after the delivery and acceptance of materials.
The advance payment shall be repaid by making deductions for every progress
billing with consideration that it is fully recoup upon reaching 80% physical
accomplishment. The first recoupment shall start when accomplishment has
reached 20% of the total contract price.
18. Completion and Taking Over:
The Contractor shall request the BSPMC to issue a certificate of completion of the
Works. The Project Supervisor will recommend such a certificate when he
determines that the work is satisfactorily completed. The BSPMC shall take
possession of the site within seven (7) days upon issuance of certificate of
completion of the Works.
19. Final Account:
The Contractor shall supply the Project Supervisor with a detailed account of the
total amount that the Contractor considers payable under the Contract before the
end of the Defects Liability Period. The Project Supervisor shall issue a Defects
Liability Certificate after the Contractor has fulfilled its obligation under the
Contract to this end and certify any final payment that is due to the Contractor
within fifteen (15) days of receiving the Contractors account if it is correct and
complete.
If it is not, the Project Supervisor shall issue within fifteen (15) days a schedule
that states the scope of the corrections or changes that are necessary. If the
Final Account is still unsatisfactory after it has been resubmitted, the Project
Supervisor shall decide on the amount payable to the Contractor and issue a
payment certificate.
20. Suspension:
The Contractor may suspend the Contract if a payment certified by the Project
Supervisor is not paid by the BSPMC to the Contractor within thirty (30) days of
the date of the Project Supervisors Certificate
21. Termination:
The BSPMC or the Contractor may terminate the Contract if the either party
causes a fundamental breach of the Contract. Fundamental breaches of Contract
shall include, but shall not be limited to, the following:
a) The Contractor stops work for ten (10) days when the stoppage has not been
authorized by the Project Supervisor;
b) The Project Supervisor gives notice that the Contractor has failed to correct a
Defect within twenty one (21) days as determined by the Project Supervisor;
and
c) The Contractor has delayed the completion of the works by thirty (30)
calendar days.
d) If payment certified by the Project Supervisor is not paid by BSPMC within
ninety (90) days.
e) If the contractor incurred a minimum of negative fifteen percent (-15%)
slippage but remains dormant for 21 calendar days despite receipt of the
warning letter from the BSPMC.
the performance security will be forfeited and shall be used by the BSPMC
for the remaining works or for further improvement of the community
project.
24. Property:
All materials and construction equipment on the site, temporary works, and
Works shall be deemed to be the property of the BSPMC if the Contract is
terminated because of the Contractors default.
25. Penalties:
Failure by the Contractor to complete the works within the implementation
period or any extended period approved by the BSPMC shall render the
Contractor liable to forfeit 1/10 of 1% of the value of uncompleted works per
calendar day of delay. Total penalty shall not exceed 10% of the total contract
price.
26. Resolution of Disputes:
The BSPMC and the Contractor shall make every effort to resolve amicably by
direct negotiations any disagreement or dispute arising between them under or
in connection with the Contract. The disagreement may also be presented to
appropriate Grievance Officer/Unit of KALAHI-CIDSS. In case of further
disagreement either party can take the matter to arbitration in accordance with
the Law governing the Contract.
SECTION 3 DRAWINGS TO ATTACH DRAWINGS
SECTION 4 TECHNICAL SPECIFICATION TO ATTACH SPECIFICATIONS
SECTION 5 PROGRAM OF WORKS /SCOPE OF WORK
_________________________
Authorized Signature:
_________________________
_________________________
Name of Firm:
_________________________
Address:
_________________________
Phone Number:
_________________________
Fax number
_________________________
_________________________
Group Leader
Funds Available
_________________________
Barangay Treasurer
_________________________
BSPMC Chairperson
ACKNOWLEDGEMENT
NOTARY PUBLIC
Until December ___, 200___
PTR NO.
______________
Issued at
______________
Issued on
______________
Doc. No.
Page No.
Book No.
Series of
______________
______________
______________
______________
(Name of Owner)
(Address of Owner)
(Name of Contract)
Gentlemen:
1. In accordance with the provisions of the above mentioned Contract,
___________________________ {name and address of the Contractor}(hereinafter
called the Contractor) shall deposit in favor of ________________________
{name of BSPMC} a Bank Guarantee to guarantee his proper and faithful
performance under the said Clause of the Contract in an amount of
__________{amount of Guarantee} _______________________{amount in
words}.
2. We, the _______________________ {Bank or Financial Institution}, as instructed
by the Contractor, agree unconditionally and irrevocable to guarantee as primary
obligator
and
not
as
Surety
merely,
the
payment
to
___________________________ {name of BSPMC} on his first demand without
whatsoever right of objection on our part and without his first claim to the
Contractor, in the amount not exceeding _______________________ {amount of
Guarantee}______________________________ {amount in words}.
3. We further agree that no change or addition to or other modification of the terms of
the Contract or of the Works to be performed under the Contract which may be
made between ______________________ {name of BSPMC} and the Contractor,
shall in any way release us from any liability under this Guarantee, and we hereby
waive notice of any such change, addition, or modification.
4. The Guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until ___________________{name of BSPMC} receives
full payment of the same amount from the Contractor.
Yours truly,
SIGNATURE AND SEAL
_________________________
_________________________
_________________________
_________________________
NOTED:
Authorized Signature of the Firm
_________________________
Name of Contractor
_________________________
Date
_________________________
Bank
Letterhead
ANNEX 7
FORM OF BID SECURITY (BANK GUARANTEE)
WHEREAS, ___________________________________ (hereinafter called the
Bidder) has submitted his bid dated _____________________ for the execution of
_________________________________________ (name of contract) (hereinafter
called the Bid)
KNOW ALL MEN by these presents that We _________________________ (name of
bank)
having
our
registered
office
at
________________________________________________ (hereinafter called the
Bank) are bound unto the __________________ Barangay Community Project
Management Committee (hereinafter called the Owner) in the sum of
_____________________________________ (P__________) for which payment well
and truly to be made to the said Owner, the Bank binds himself, his successors and
assigns by these presents.
SEALED with the Common Seal of the said Bank this _____day of ________, 200_.
THE CONDITIONS of this Obligation are:
1. If the Bidder withdraws his Bid during the period of bid validity specified in the Bid
Form; or
2. If the bidder having been notified of the acceptance of his Bid by the Owner during
the period of bid validity:
a. fails or refuses to execute the Contract in accordance with the Bidding
Documents, if required; or
b. fails or refuses to furnish the Performance Security, in accordance with the
Bidding Documents.
3. If the bidder refuses to accept the correction of error in his bid;
We undertake to pay to the Owner up to the above amount upon receipt of his first
written demand, without the Owner having to substantiate his demand, provided that in
his demand, the Owner will note that the amount claimed by him is due to him owing to
the occurrence of one or both of the two conditions, specifying the occurred condition or
conditions.
This Guarantee will remain in force up to and including the date, ____________ 28
days after the closing date for submission of bids as stated in the Bidding Documents or
as extended by you at any time prior to this date, notice of which extension to the Bank
being hereby waived, and any demand in respect thereof should reach the Bank not
later than the above date.
Date:
_________________________
_________________________
Address:
_________________________
Witness:
_________________________
ANNEX 8
KALAHI-CIDSS PROJECT
PROCUREMENT OF WORKS EVALUATION FORM
Barangay:
___________________________
Municipality:
Province:
1. Community Project Title:
2. Name Contract:
___________________________
___________________________
_________________________
_________________________
_________________________
5. Bidders
CONTRACTORS NAME
SUBMITTED BID
PRICE
EVALUATED
BID PRICE
RANKING
6. Any issues (to be) discussed or clarified with the bidder before finalization of
contract. Give details.
Signatures of Evaluators:
TWG Members Present
_________________________ _________________________
_________________________ _________________________
_________________________ _________________________
Date: ___________________
ANNEX 9
KALAHI-CIDSS PROJECT
BIDS AND AWARDS COMMITTEE
Barangay:
___________________________
Municipality:
Province:
___________________________
___________________________
Date: ___________________
RESOLUTION TO AWARD
WHEREAS, the Invitation to Bid for this contract has been issued to interested bidders.
WHEREAS, in response to the invitation, ___________ (number of contractors)
submitted their bids.
WHEREAS, the result of the evaluation is as follows:
NAME OF BIDDERS
BID AMOUNT
AS EVALUATED
1.
2.
3.
WHEREAS,
the
indicative
estimate
for
this
contract
_____________________________________________ (P_________).
is
WHEREAS,
in
the
evaluation
of
the
BAC,
the
bid
of
_______________________________
in
the
amount
of
____________________________________ (P _________) is found to be the lowest
calculated and responsive bid, and is the most advantageous to the Barangay.
WHEREAS, this community project is partly financed by the __________________
(state name of donor e.g. World Bank, Millennium Challenge Corporation, PODER,
etc..).
NOW, THEREFORE, THE BIDS AND AWARDS COMMITTEE AFTER A THOROUGH
DELIBERATION, RESOLVED TO RECOMMEND AS IT HEREBY RECOMMENDS TO ACCEPT
THE
BID
AND
AWARD
THE
CONTRACT
TO:
______________________________________________________________________
_______________________________________
IN THE TOTAL AMOUNT OF
____________________________________________ PESOS (P__________).
Done in the Barangay of __________________________ this _________ day of
200_.
BIDS AND AWARDS COMMITTEE
_________________________
BAC Chairperson
Approved By:
_________________________
BSPMC Chairperson
Date: ___________________
ANNEX 10
KALAHI-CIDSS PROJECT
Barangay:
___________________________
Municipality:
Province:
___________________________
___________________________
Date: ___________________
NOTICE OF AWARD
Sir/Madam:
Contract Title: ___________________________
The above contract is hereby awarded to you according to the terms and conditions of
your bid as contained in your proposal submitted to us in the of amount of
_______________________________________________ (P________).
In accordance with the provisions of the Tender Documents, you are instructed to enter
into and execute the Contract Agreement with us and to furnish us the following
documents, which will form part of the Contract Agreement within five (5) calendar
days upon receipt of this Notice of Award.
(If contract price is P1Million or more)
a. Performance Security shall be callable on demand, co-terminus with the
community project and shall either be in the form prescribed as follows:
i.
CONFORME:
_________________________
_________________________
Chairperson,
Barangay Community Project
Management Committee
ANNEX 11
KALAHI-CIDSS PROJECT
BARANGAY COMMUNITY PROJECTS MANAGEMENT COMMITTEE
Barangay:
___________________________
Municipality:
Province:
___________________________
___________________________
Date: ___________________
NOTICE TO COMMENCE
Sir/Madam:
Community Project Title: _________________________
Pursuant to your Contract Agreement dated ____________________ with the
____________________________
Barangay
Community
Project
Management
Committee for the _________________(Name of Community Project__________ under
the Kalahi-CIDSS: KKB Project, you are hereby directed to start the work within 7 days
upon receipt of this notice in accordance with the provisions of the Contract Documents.
Please acknowledge receipt of this Notice to Commence.
_________________________
BSPMC Chairperson
Date: ___________________
By: ________________________________________________
(Name, Signature and Position of authorized representative)
ANNEX 12
PERFORMANCE SECURITY
BANK GUARANTEE
To: The __________________________
Barangay Community Project Management Committee
______(Address of BSPMC)_______
__________________________
WHEREAS ________________________________ (Name and Address of Contractor),
hereinafter called the Contractor has undertaken, in pursuance of Contract No.
__________
dated
_________________
to
execute
______________________________________________________________ (Name of
Contract and brief description of works), hereinafter called the Contract;
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor
shall furnish you with a Bank Guarantee by a recognized bank for the sum specified
therein as security for compliance with his obligation in accordance with the Contract;
AND WHEREAS we have agreed to give the Contract such a Bank Guarantee;
NOW THEREFORE, we hereby affirm that we are the Guarantor and responsible to you,
on
behalf
of
the
Contractor,
up
to
a
total
of
____________________________________
____________________ (amount of Guarantee in words), such sum being payable in
the types and proportions of currencies in which the Contract Price is payable, and we
undertake to pay you, upon your first written demand and without cavil or argument,
any sum or sums within the limits of ________________________________ (amount
of Guarantee) as aforesaid without your needing to prove or to show grounds or
reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor
before presenting us with the demand.
We further agree that no change or addition to or other modifications of the terms of
the Contract or of the Works to be performed hereunder or of any of the Contract
documents which may be made between you and the Contractor shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any
such change, addition or modification.
This guarantee shall be valid until the date of issue of the Defects Liability Certificate.
Signature and Seal of Guarantor
_________________________
Name of Bank
_________________________
Address
_________________________
Bidding Data
Name of Community Project:
_____________________________________________
The Grantee is the Government of the Philippines
The Owner is the (Barangay Community Project Committee)
III.b.2
III.a.1(a),
III.a.1(b)
III.b.1(b)
III.b.1
III.b.4
III.b.6
III.c.2
III.c.3
III.c.4
[ ] No
III.c.5
III.c.6
III.d.1
III.d.4(a)
III.c.2; IV.a.4
III.f.3;
IV.d.6(b)
III.f.5(a)
III.Doc.#6(4)
Bill of Quantity
and IV.d.1(a)
KALAHI-CIDSS Project
CANVASS FORM/Request for Quotation
(for GOODS)
Barangay: ___________________________
Municipality: _________________________
Province: ____________________________
DATE: ______________
To: _______________________ (Name of Supplier/Store)
Address:______________________________
Tel. No. :______________________________
May we request you to indicate your prices for the items listed below? Please
return this form to the canvasser in sealed envelope or submit it to the Barangay
Community Project Management Committee at the Barangay hall on or before
_______ (time), _____________ (date).Immediately after the deadline of
submission, canvass will be opened.
Item
Description
QTY
Unit
Unit
Total
No.
Price
Price
TOTAL AMOUNT
MODE OF PAYMENT
DELIVERY PERIOD : __________ cal. Days
Canvassers Names and Signatures
1. _________________________________
2. _________________________________
Note:
1. Quotation must be valid for 15 calendar days.
2. Prices quoted must include taxes and other incidental expenses.
3. Price quoted must be fixed for 15 calendar days.
4. Cost of delivery:
to include
not to include
5. Award shall be made: on per item basis on per package basis
________________
BSPMC Chairperson
Canvass Submitted by:
______________________
Signature over Printed Name
Owner/Manager
Date: __________
Kalahi-CIDSS Project
ABSTRACT OF CANVASS/Quotation
(Local Shopping for Goods)
Barangay: ___________________________
Municipality: _________________________
Province: ____________________________
Ite
m
No.
1.
2.
3
4
5
6
7
Description/Specifications
Qty.
Unit
Name of Supplier
Unit
Total
Price
Name of Supplier
Unit Price
Total
Name of Supplier
Unit
Total
Price
TOTAL
Encircled is/are the price/s evaluated to be the lowest calculated and responsive quotations/s Award is hereby
recommended to this/these supplier/s.
BIDS AND AWARDS COMMITTEE
____________________________
____________________________
____________________________
BAC Chairman
APPROVED BY:
_________________________
BSPMC CHAIRPERSON
DATE: ___________________
KALAHI-CIDSS PROJECT
Barangay: ____________________________
Municipality: ___________________________
Province: _____________________________
PURCHASE ORDER
Name of Supplier:
P.O. No.
_________________
Address:
Date:___________________
In accordance
with the canvass dated ___________, the Community Project
Management Committee (BSPMC) off Barangay
______________________________
requests you to supply and deliver the items detailed below:
Item
No.
Description / Specification
Quantity
Conforme:
Date ________
Date
________
___________________________________________ Date
________
Treasurer
______________________________________________
(Name and signature of Supplier)
Inspected/Tested
by:
___________________________________________ Date
Received by:
___________________________________________ Date
Scope of Works
Qty
Unit
Unit
Cost
Total
TOTAL
To assist you in the preparation of your price quotation, we enclosed the necessary
drawings and specifications. Your quotation should be sealed in an envelope and
addressed to the undersigned at the following address:
The Barangay Community Project Management Committee
Attention: Bids and Awards Committee
Barangay Hall, Barangay ______________________
________________________
Signature over Printed Name
Owner/Manager
Date
AMOUNT
REMARKS
1.
2.
3.
4.
Based on the quotations opened on _________________ (date). The quotation
submitted by ___________________________ (name of contractor) in the
amount of ____________________________________________ (amount in
words) P ______ (in figures) was determined after evaluation to be the lowest
calculated complying quotation. Therefore, award of the contract is hereby
recommended to the said contractor.
BIDS AND AWARDS COMMITTEE
__________________________
__________________________
__________________________
BAC Chairperson
APPROVED BY:
__________________________
BSPMC CHAIRPERSON
Date: __________
CFA
KALAHI-CIDSS Project
INVITATION
FOR DIRECT CONTRACTING OF LABOR
Barangay: ___________________________
Municipality: _________________________
Province: ____________________________
Date: __________________
To:
_____________________________________________
_____________________________________________
Sir/Madam:
Our community has received a grant from the Department of Social Welfare and
Developments KALAHI-CIDSS Project.
The Barangay Community Project Management Committee invites you to submit a
proposal to construct and complete, on behalf of the community and according to the
conditions of this Invitation, the whole of the work items for said community project
broken down as follows:
Name of Project:
________________________________________________________
Work
Item
No.
Description of Works
Qty
Unit
Unit
Cost
Total
TOTAL
To assist you in the preparation of your proposal quotation, we enclosed the necessary
drawings and specifications. Your quotation should be sealed in an envelope and
addressed to the undersigned at the following address:
The Barangay Community Project Management Committee
Attention: Bids and Awards Committee
Barangay Hall, Barangay ______________________
Municipality of _________________, Province of ________________
Your proposal shall be valid for a period of forty five (45) days from the date of
submission. Proposal shall be fixed for four (4) months. Price quoted must include taxes
and other incidental expenses. It is understood that the Group shall complete all works
enumerated at the total quoted price. Minor works not listed therein but are necessary
to execute the work items are deemed part of these work items.
A Group who withdraws his proposal during the validity period and/or refuses to accept
award or complete the contract will be disqualified from participating in any KalahiCIDSS: KKB funded community project for two years.
Attached for your information and guidance is the Draft Contract.
Your proposal should be received by the BSPMC on or before _______________ (date
and time). The proposal shall be opened in public in your or your representatives
presence if you choose to attend, on ___________________ (same date as deadline for
proposal submission) at ____ (time) (same as the deadline for bid submission) at the
given address:
The Contract Time for this contract is _____________ calendar days
Please attach to your proposal the following documents:
Composition of Group (with their names and signature, address, work
assignment, rate per day)
It is understood that the Group shall coordinate with the BSPMC in the execution of the
works herein indicated
Very truly yours,
_________________________
BAC Chairman
Proposal Submitted by:
____________________
____________
Name of Group Leader
________________________
Signature
Date
Recommended by:
BIDS AND AWARDS COMMITTEE
__________________
Member
Approved by:
__________________
Member
__________________
BSPMC Chairperson
Date: ___________
____________________
BAC Chairman
In Witness whereof the parties thereto have caused this Agreement to be executed
this _____ day of _____________ 200_.
For the Contract Group
___________________________
Group Leader
____________________________
Witness
Funds Available
___________________________
Barangay Treasurer
Items of Work/Description of
Work
TOTAL
Amount in Words:
Qty
Unit
Unit
Cost
Total
We will only accept an offered price that is fixed and is not subject to any adjustment.
Bid shall be valid for a period of sixty (60) days from the date of submission.
Bidding documents may be obtained from the Barangay Treasurer in the Barangay Hall
after payment of a non-refundable fee in the amount of ____________.
A pre-bid conference will be held at the Barangay Hall on (date) ___________ at
_________ (time).
All bids must be accompanied by a bid security in any of the following forms:
Cash, Cashiers check, managers check, bank draft or bank guarantee = 2 % of bid
price.
All bids must be received on _________________ (date and time) and will be opened
in public in the presence of bidders representatives who choose to attend at the
following address:
Kalahi-CIDSS: KKB Project
Barangay Community Project Management Committee
Barangay Hall
Barangay ____________, Municipality of ________________
Province of _________________________________________
Please attach to your quotation with the requirements provided in the Instructions to
Bidders containing the following:
I.
II.
III.
Technical Documents;
Legal Documents; and,
Financial Documents
The community reserves the right to reject any bid or waive any defect or formality.
The lowest calculated and responsive bid shall be used as the criterion in the selection
of the contractor. The community will not reimburse any expenses related to the
preparation of bids.
(SGD.) ____________________________________
Chairperson, Barangay Community Project Management Committee
Description/Specs of Items
TOTAL
Amount in Words:
Qty
Unit
Unit
Cost
Total
We will only accept an offered price that is fixed and is not subject to any adjustment.
Bid shall be valid for a period of sixty (60) days from the date of submission.
Bidding documents may be obtained from the Barangay Treasurer in the Barangay Hall
after payment of a non-refundable fee in the amount of ____________.
A pre-bid conference will be held at the Barangay Hall on (date) ___________ at
_________ (time).
The Bid shall include the following documents:
All bids must be received on _________________ (date and time) and will be
immediately opened in public in the presence of bidders representatives who choose to
attend at the following address:
Kalahi-CIDSS Project
Barangay Community Project Management Committee
Barangay ____________, Municipality of ________________
Province of _________________________________________
The community reserves the right to reject any bid or waive any defect or formality.
The lowest calculated and responsive bid shall be used as the criterion in the award.
The community will not reimburse any expenses related to the preparation of bids.
(SGD.) _______________________
Chairperson, BSPMC
BID SUBMITTED BY:
___________________________________
Signature Over Printed Name of Supplier
Date: _______________
KALAHI-CIDSS PROJECT
ABSTRACT OF BIDS
Barangay:
___________________________
Municipality:
___________________________
Province:
___________________________
Community Project:
ITEMS
NO.
DESCRIPTION
QTY
1.
2.
3.
4.
5.
6.
Total
UNIT
NAME OF BIDDER
BID
BID SECURITY
AMOUNT
TYPE
AMOUNT
___________________________
BID
AMOUNT
NAME OF BIDDER
BID SECURITY
TYPE
AMOUNT
BID
AMOUNT
NAME OF BIDDER
BID SECURITY
TYPE
APPROVED BY:
_________________________
_________________________
BSPMC CHAIRPERSON
_________________________
_________________________
BAC Chairman
DATE : ___________________
AMOUNT
MALE
FEMALE
Municipality: ___________________
TYPE:
SKILLED
___________________________
UNSKILLED
RATE PER
HOUR
DAY
Province: ___________________
NO. OF WORKING
TOTAL
HOURS
LABOR
DAYS
PLAN PAYMENT
CASH
BAYANIHAN
ACTUAL PAYMENT
(ACCUM.)
CASH
BAYANIHAN
1
2
3
4
5
6
7
8
9
10
TOTAL
NOTE:
Rate - Is the rate per day or per hour of the community worker (cash plus "bayanihan" monetized)
Cash - Is the cash amount to be paid to community members for labor
Bayanihan- Cost of Labor not to be paid (Community Equity)
Noted:
_________________________
Head, Procurement Team
Brgy. Treasurer
Approved by:
_________________________
Head, Project Implementation Team
BSPMC Chairperson
SIGNATURE
to the CONSUMER
described in the
And the CONSUMER has accepted the proposal of the DEALER for the supply of the diesel fuel and
remedying of any defects therein.
Now this agreement witnesseth as follows:
1. In this agreement, words and expressions shall have the same meanings as respectively
assigned to them.
2. The following document shall be deemed to form and be read and construed as part of this
agreement:
Canvass form
Abstract of Canvass
Minutes of evaluation of Canvass
Purchase Order
3. In consideration of the payments to be made in full amount by the consumer and of the
fact that the CONSUMER does not have a safe depository tank for the flammable materials,
the
DEALER hereby covenants with the CONSUMER to supply and take custody of the
stocks of diesel fuel and be held liable for whatever damages it may incur during its
custody.
4. The DEALER allows partial withdrawal of stocks using withdrawal slip duly signed by the
BSPMC Chairperson and inspected by the Monitoring and Inspection Team (MIT) and
accepted by the storekeeper.
5. The DEALER allows on the spot reconciliation and checking of stocks by the Monitoring and
Inspection Team (MIT).
In witness whereof the parties thereto have caused this Agreement to be executed this _______
day of _______ 200__.
FOR THE CONSUMER
______________________
BSPMC Chairperson
______________________
Gasoline Dealer
Funds Available
______________________
Barangay Treasurer
Witnesses
______________________
Invitation to Quote
Abstract of Quotation
Minutes of evaluation of quotation
Contract Agreement
KALAHI-CIDSS Project
CANVASS FORM FOR LEASE OF EQUIPMENT
(GOODS)
Barangay: ___________________________
Municipality: _________________________
Province: ____________________________
To:
(Name of Contractor/Supplier/Owner)
DATE: ______________
Address:_________________________________________
Tel. No. : ______________
May we request you to indicate your quotations for the rental of equipment indicated
below. Please return this form to the canvasser in sealed envelope or submit it to the
Barangay Community Project Management Committee at the Barangay hall on or before
_______ (time), _____________ (date).Immediately after the deadline of submission,
canvass will be opened.
Item No.
/
Package
No.
TOTAL AMOUNT
MODE OF PAYMENT
DELIVERY PERIOD : __________ cal. Days
Canvassers Names and Signatures
1. _________________________________
2. _________________________________
3._________________________________
Number of No. of
Unit
equipment (Days / Rate Per
/ No. of Hours) (Day /
Unit
Hour)
Total
Rental
Cost
EQUIPMENT LEASE
Terms and Conditions:
1. In case of unacceptable/unreasonable delay in delivery of services as
required, 1/10 of 1% of the rental will be deducted from the total amount
due for each day of delay (weekends, and holidays included)
2. Quotation must be valid and fixed for 30 calendar days.
3. Prices quoted must include taxes and other incidental expenses.
4. The Equipment Operators wages cost of equipment maintenance and repairs
shall be for the account of the lessor.
5. The lessor shall ensure that the equipment is in operating condition at all
times during the duration of the contract agreement.
6. Fuel, oil and lubricants shall be supplied by the LESSOR. The lessor shall
ensure the equipment for third party liability and for total loss or partial
damage to the equipment while on transport or at the designated area of
operation.
7. The lessor binds itself to protect and immune the LESSEE from any suit or
liability resulting from claims of any nature, whether for death, injuries or
damages that maybe suffered by the LESSORS Operator and/or third
parties, arising from or in connection with the transport of the equipment or
performance of the work.
8. Damages caused by the lessors party shall be charged/deducted from the
lessor.
9. Payment shall be through CHECK.
____________________
BSPMC Chairperson
Date: __________
Canvass Submitted by:
______________________
Signature over Printed Name
Owner/Manager
Date: __________
In accordance with the canvass dated ___________, the Community Project Management
Committee (BSPMC) off
Barangay
____________________ requests you to provide
services as stated below:
Item No. /
Package No.
___________________________________________
Treasurer
Conforme:
________
______________________________________________
Date
________
Date
foregoing,
1.2
The LESSOR shall ensure that the equipment is in operating condition at all
times during the duration of the contract agreement.
1.3
1.4
The LESSOR shall insure the equipment for third party liability and for total loss
or partial damage to the equipment while on transport or at the designated area
of operation.
1.5
The LESSOR binds itself to protect and immune the LESSEE from any suit or
liability resulting from claims of any nature, whether for death, injuries or
damages that maybe suffered by the LESSORS Operator and/or third parties,
arising from or in connection with the transport of the equipment or performance
of the work.
1.6
Utilization
of
the
equipment
for
the
community
project,
the
________________________________ (name of community project) shall
be under the supervision of the LESSEE; therefore, the LESSEE shall be
responsible for the scope of work of the equipment.
1.7
The LESSOR shall have the right at any time to inspect his equipment. For this
purpose, the LESSEE agrees to provide free access and facilities to the LESSOR
to accomplish such inspection.
1.8
The LESSEE shall not sublease, pledge, encumber, dispose or place the
equipment in the possession and/or use and supervision of any other person
other than his duly authorized representative.
1.9
The Equipment Operator shall maintain a Daily Time Record to be checked and
signed by the PIT/BSPMC at the end of each day. This shall be part of the
attachments for payment.
SECTION 2.0. SCOPE OF WORKS TO BE DONE BY THE EQUIPMENT/S:
Scope of Works
Item
Qty
Unit
Description
SECTION 3.0.
3.1
Equipment
Needed
Total Rental
Cost
CONTRACT AMOUNT:
The total contract amount shall be Pesos, not to exceed the amount of
____________________________________________________ pesos
(PhP: ______________).
SECTION 4.0.
TERMS OF PAYMENT
5.1 The LESSOR may request for partial payments up to fifteen (15) percent of the
Contract Price only after the DAC and/or Municipal Engineer had certified that the
equipment is delivered at the project site; the equipment is in good running
condition; and, the Lessor has submitted to the BSPMC a Bank Guarantee of equal
amount. The advance payment shall be repaid by making deductions for every
progress billing with consideration that it is fully recoup upon reaching 80% physical
accomplishment. The first recoupment shall start when accomplishment has reached
20% of the total contract price.
5.2. Total Rental cost of the contracted equipment shall be based on the total actual
quantity accomplished in the project specified herein.
SECTION 6.0. TERMINATION
6.1 The LESSOR shall have the right to terminate the Agreement and withdraw the
equipment for the following reasons:
a. If in LESSORS opinion continued operation will result in accelerated damage
to the equipment.
b. If the LESSEE has violated any provision(s) of the Lease Agreement and/or
due to non-payment of the stipulated rental fees.
6.2 The LESSEE shall have the right to terminate this Agreement after giving for any of
the following causes:
a. The LESSOR fails to mobilize the contracted equipment as instructed by the
BSPMC.
b. Failure of the LESSOR to fulfill its obligations such as non-operation due to
breakdown, absence of POL, or upon assessment of the lessee, the LESSOR
cannot deliver the work on time;
c. Assignment of the equipment by the LESSOR to any job site other than the
_________________________________________ (name of the community
project).
d. The LESSOR is willfully violating any of the material conditions, stipulations
and covenants of this Agreement.
6.3 In case of termination of this agreement due to the above stated causes, the cost of
returning the equipment to the yard of the LESSOR shall be for the account of the
LESSOR.
6.4 In cases where the Scope Works in the community project have been completed
ahead of the contract period and the equipment is not any more of use to the
LESSEE, or where community project has to be terminated for reasons beyond its
control, the LESSEE has the option to terminate this Agreement.
SECTION 7.0.
7.1 A material breach by either party of any of the warranty, representation of covenant
herein made entitle the aggrieved party, at its option, to rescind the Agreement upon
written notice to this effect. Any suit or legal proceeding which either party may in
virtue of, or in relation to, or in any way connected with this Agreement, shall be filed
with the proper courts of ___________________, _________________________.
SECTION 8.0.
EFFECTIVITY
8.1 This Lease Agreement shall take effect immediately upon signing of the Agreement.
8.2 The Notice to Commence shall be issued within three (3) calendar days upon
signing of the contract agreement.
____________________________
Bspmc Chairperson
_____________________
Lessor
______________________
Witness
ACKNOWLEDGEMENT
REPUBLIC OF THE PHILIPPINES
MUNICIPALITY OF _____________, ______________
BEFORE ME, a Notary Public for and in the above jurisdiction, personally
appeared this ____ day of __________, 20____ at ______________, ____________,
Philippines.
Name
___________________
______________
_______________
____________________
______________
_______________
__________________
______________
_______________
Known to me to be the same persons who executed the foregoing LEASE AGREEMENT
consisting of five (5) pages including this page on which the Acknowledgement appears
and they acknowledged to me that the same is their free and voluntary act and deed
and those of the principals they respectfully represent.
IN WITNESS WHEREOF, I have hereunto set my hand and seal on the date and
at the place first above- mentioned.
_____________________
Notary Public
PTR No.______________
Until December 31, 200___
Doc. No. ____________;
Page No. ____________;
Book No. ____________;
Series of ____________.
bid submission) at ____ (time) (same as the deadline for bid submission) at the given
address:
Please attach to your quotation with the breakdown of your quotations and attach proof
of your experience in similar activity.
Very truly yours,
____________________________
BSMPC Chairperson
Quotation Submitted by:
____________________________________
Signature over Printed Name of Consultant
_______________
Date
1. The Service provider agrees and binds itself to fully and faithfully provide for its
account all needed materials, instruments necessary or required to finish, and
complete the work, based on the given timeframe to complete the community
project/s (Section II, Clause 2) and requirements stipulated in the Terms of
Reference attached to this contract.
2. The work called for under this contract shall be completed and submitted on or
before _________________, 2010. Failure to comply with the said date shall cause
the Owner to impose the necessary penalty.
3. The Service provider shall provide and do everything necessary to conform to its
obligation under the Agreement to the true intent and meaning of the other
Agreement documents taken together, whether the same may or may not be shown
or described particularly in the supporting documents as part of this contract
(Section 1), provide that the same shall be informed there from. Should the Service
Provider find any discrepancy in the said documents, he shall immediately refer the
same to the Owner whose decision shall be followed.
4. The Service provider guarantees the quality of the workmanship of all its work under
the Agreement and shall undertake at his own expense all revisions, adjustments as
a result of the technical review of the Deputy Area Coordinator and Municipal
Engineer relative to the work.
SECTION III
CONTRACT PRICE
The Owner and in consideration of the faithful performance by the service provider of
the terms and conditions of this agreement, agrees to pay the service provider in a
manner provided under Section IV of this Service Agreement, the amount of
______________________________________ (PhP _________). It is understood that
any increase in the cost related to the service contract shall be the sole account of the
service provider.
SECTION IV
MANNER OF PAYMENT
1. Upon satisfactory completion and submission of the required documents by the
Service Provider as supported by the final acceptance of Project Preparation
Team full payment will be released to the service provider.
2. It is the intention of the parties that there shall be no employer-employee
relationship between the owner and the service provider, and between the
service providers employees and / or laborers, it being understood that the
relationship between the parties hereto shall be one of an independent
contractor. In the event or any official or legislated increase in the minimum
wage and / or compulsory allowances during the contract period, the same shall
be likewise be for the account of the service provider.
SECTION V
PERIOD OF COMPLETION
1. The work stipulated in the Agreement shall be completed within the given period
as provided in the Scope of Works (Section III)
In case the service provider encounters any justifiable cause or reason for delay,
the same shall within two (2) days after encountering such cause of delay submit
to the Owner in writing a request for time extension. Failure by the service
provider to comply with this requirement will be considered an express waiver by
the service provider for the owner not to grant the time extension.
2. Since time is of the essence in this Agreement, the completion period herein
stipulated may be extended only for any of the following causes not attributable
to the fault of negligence of the service provider, namely:
SECTION VII
COMPLETION AND FINAL ACCEPTANCE
1. When the work required and called for under this contract is totally completed,
the service provider shall submit to the Owner through the Area/Municipal
Coordinating Team for review and evaluation of the Deputy Area Coordinator and
/ or Municipal Engineer of the documents. The review shall be completed within
two (2) days upon submission of the complete documents by the service
provider.
2. Should the work be found satisfactory with the agreements, the Owner shall
within five (5) calendar days from the last day of review by the DAC, issue the
Certificate of Final Acceptance of the submitted documents and the dull payment
due to the service provider shall be paid immediately. Provided that no such
certificate shall be issued the service provider has first submitted an affidavit
attesting that any and all obligations /liabilities incumbent upon it have been
fully satisfied and settled.
3. If the work is found unsatisfactory however, the first party shall within two (2)
working days from the last day of review, advice the service provider of the
revisions to be done.
4. Upon the correction of the items, the service provider shall again submit to the
Owner the corrected documents.
5. Should the correction made by the service provider of the items be found
satisfactory, payment found to be due to the service provider shall be paid
immediately and the Owner shall not later than three (3) working days after the
last day of submission issue the certificate of final acceptance.
SECTION VIII
ASSIGNMENT AND SUB-CONTRACTING
The service provider shall not assign, transfer or make any other disposition of the
agreement any part or interest therein except with the written approval of the Owner.
Approval of the sub-contract shall not relieve the service provider from any liability or
obligation under its agreement with the Owner, nor shall it create any contractual
relation between the sub-contractor and the Owner.
SECTION IX
SERVICE PROVIDERS DUTIES AND RESPONSIBILITIES
The service providers duties and responsibilities are found in the TOR in connection to
this agreement to include the following:
1. Conduct site validation and survey
The service provider shall solely responsible for all expenses to be incurred
during the preparation of all pertinent required documents as stipulated in this
contract agreement.
2. Supplies, Materials, Equipment, etc.
The service provider shall be solely responsible in the provision of all required
supplies, materials, equipment, machineries, transportation and or among others
for the proper and satisfactory completion of the work in accordance to the
content of this agreement.
3. Assistance to the Project Preparation Team (PPT)
The service provider shall be assisting the PPT during the preparation of the
attachments for the package proposed by his/her attendance to the following:
a.
b.
c.
d.
e.
The service provider shall also assist the Owner explain the content and details of
the POW and design of the community project in the barangay assemblies to be
conducted prior to the conduct of project approval.
4. Indemnification and Hold Harmless Agreement
The service provider agrees to indemnify and hold harmless the Owner and its
constituents including the KALAHI-CIDSS employees from and against all claims,
damages, losses and expenses including reasonable attorneys fees in case any
litigation arising out of the performance of the works herein.
SECTION X
GENERAL PROVISIONS
The parties have herein agrees that the present agreement does not create any
obligations, legal, financial or otherwise on the part of the Owner to any persons
claiming entitlement to compensation or other remedies relating to personal injuries,
economic-harm or otherwise including but not limited to any contractor, sub-contractor
or beneficiary and / or other project users before, during and after the completion of
the contract. In the event any claim is asserted against the Owner, the service provider
shall defend the Owner from all costs occasioned thereby, including any assessment of
damages or imposition of legal; obligations.
SECTION XI
ARBITRATION
The parties hereto agree to settle any dispute arising from this agreement amicably in
accordance to the Grievance Redress System of the KALAHI-CIDSS project. In the event
that any judicial proceedings brought by either party against the other arising out from
this agreement, the venue of the same shall be the appropriate Court in the area.
IN WITNESS WHEREOF, the parties have hereunto signed this SERVICE AGREEMENT
this _________________ of _______ 2010.
BARANGAY ___________ COMMUNITY
The First Party
_________________________
BSPMC Chairperson
CTC No. _______________
Issued On _____________
Issued at ______________
SERVICE PROVIDER
Second Party
______________________
Service Provider
CTC No. ________________
Issued On ______________
Issued at _______________
_____________________
Area Coordinator
CTC No. ________________
Issued On _____________
Issued at ______________
Issued on ______________
Issued at _______________
TERMS OF REFERENCE
SERVICE PROVIDER
(Pre-Engineering Works for Water System)
: 1 Months
(1-week survey works and data gathering;
1 week preliminary design consideration/consultation;
3 weeks drafting of plans;
1 week preparation/finalization of cost estimates)
TERMS OF REFERENCE
SERVICE PROVIDER
(Pre-Engineering for Road Construction community project)
An Individual or Engineering/Consulting Firm that can provide technical assistance in
the implementation of rural road access in KALAHI-CIDSS areas. Technical assistance
shall include specialized advice to implementers along preparation of appropriate
designs and engineering plans, cost estimates and Program of Works.
Specifically, the Service Provider will assist the project municipal staffs and community
volunteers in the following areas:
1. Provide guidance and assistance to Project Preparation Team (PPT) on the
conduct of the following specific activities to come-up with the project
requirements for the approval of proposed improvement of barangay road, to
wit:
Execute detailed field survey using instruments such as engineers transit,
theodolite, total station and other appropriate instruments to establish
horizontal and vertical controls;
Preparation of engineering designs, technical drawings/plans drawn on a
500mm x 1000mm appropriate paper, with the following outputs;
i.
Location plan showing the vicinity map of the proposed road section
ii.
Traverse and Profile plan drawn on a half-section drawing paper
scaled at 1:100 vertical and 1:1000 horizontal. Plans must indicate
the existing and proposed structures with corresponding station
limits. The elements of curves, bench marks and match line of
traverse plan must equal to the length of profile plan. Elevations of
ground and design grade must be indicated on the profile plan.
iii.
Cross-section plan at every 20 meter station interval drawn on full
cross section with a scale of 1:100 (preferably). Actual ground
elevation shall be indicated and inked. Designed ground elevation
shall be indicated and penciled
iv.
Detailed plans of road structures e.g. reinforced concrete pipe
culverts (RCPC), reinforced concrete box culvert (RCBC) headwalls
and cross-drains. At critical slope, provision of portland cement
concrete pavement (PCCP) and slope protection as may be required;
v.
Detailed cost estimates showing quantity take-off and capability
outputs of labor and equipment, bill of materials for materials
vi.
Materials specifications and method of construction;
vii.
Others that may be specified in the contract depending on the need
of the community.
Type and traffic volume should be considered in the choice of design
options;
2. Submit draft designs for review and approval before the finalization of
engineering drawings and plans.
3. Prepare billing request together with the acceptable outputs as stated in parag. 1
for payment.
4. Payment/s will be made upon submission of acceptable outputs, checked and
reviewed by the DAC/Mun. Engineer and approved by the PPT Head and noted by
the Area Coordinator.
QUALIFICATIONS STANDARD
1. A Civil Engineer or Geodetic Engineer with 3 years minimum relevant work
experience on the survey works and implementation of rural roads, preferably
with formal training and knowledgeable road project design.
2. Preferably with skills in computer operation such as CAD operations and
spreadsheet
DURATION
: 1 Months
(1-week survey works and data gathering;
1 week preliminary design consideration/consultation;
3 weeks drafting of plans;
1 week preparation/finalization of cost estimates)
TERMS OF REFERENCE
SERVICE PROVIDER
(Pre-Engineering for Road Improvement community project)
KALAHI-CIDSS: KKB Project is assisting various rural communities to improve their
governance through active participation to reduce poverty. One of the basic needs of
these communities is access. The project allows the improvement of rural access to
improve the delivery of services. Road improvement involves the implementation of
selected work items only. This will not cover entire works for the rural road access
(construction) but only those work items that will make the rural road access passable
for vehicular traffic the whole year round. This can be applied on all roads that already
exist and can be implemented in all types of terrain.
The Project is looking for an Individual or Engineering/Consulting Firm that can provide
technical assistance in the improvement of rural barangay road access in KALAHI-CIDSS
areas. Technical assistance shall include specialized advice to implementers along
preparation of appropriate designs and engineering plans, cost estimates and Program
of Works.
Specifically, the Service Provider will assist the project municipal staffs and community
volunteers in the following areas:
1. Provide guidance and assistance to Project Preparation Team (PPT) on the
conduct of the following specific activities to come-up with the study, design
options and plans required for the proposed improvement of barangay road, to
wit:
Execute detailed field survey using instruments such as engineers transit,
theodolite, total station and other appropriate instruments to establish
horizontal and vertical controls;
Assess the existing road and evaluate the possible improvement,
extension or expansion needed for the road to be passable for vehicular
traffic year round. Since the proposed road section will only requires
improvement, it is expected that no major earthworks will be made.
Preparation of engineering designs, technical drawings/plans drawn on a
500mm x 1000mm appropriate paper, with the following outputs;
i. Location plan showing the vicinity map of the proposed road section
ii. Traverse and Profile plan drawn on a half-section drawing paper
scaled at 1:100 vertical and 1:1000 horizontal. Plans must indicate
the existing and proposed structures with corresponding station
limits. The elements of curves, bench marks and match line of
traverse plan must equal to the length of profile plan. Elevations of
existing ground and design grade must be indicated on the profile
plan.
iii. Cross-section plan for selected stations that may require earth
moving activities have to be drawn on full cross section with a scale
of 1:100. Actual ground elevation shall be indicated and inked.
Designed ground elevation shall be indicated and pencilled.
iv. Schedules and detailed plans of road structures e.g. reinforced
concrete pipe culverts (RCPC), reinforced concrete box culvert
(RCBC) headwalls and cross-drains. At critical slope, provision of
portland cement concrete pavement (PCCP) and slope protection as
may be required;
v. Detailed cost estimates showing quantity take-off and capability
outputs of labor and equipment, bill of materials for materials
vi. Materials specifications and method of construction;
vii. Others that may be specified in the contract depending on the need
of the community.
Type and traffic volume should be considered in the choice of design
options;
Close coordination with project technical staff as to the format of POW
and other project standards.
5. Submit draft designs for review and approval before the finalization of
engineering drawings and plans.
6. Prepare billing request together with the acceptable outputs as stated in parag. 1
for payment.
7. Payment/s will be made upon submission of acceptable outputs, checked and
reviewed by the DAC/Mun. Engineer and approved by the PPT Head and noted by
the Area Coordinator.
QUALIFICATIONS STANDARD
2. A Civil Engineer or Geodetic Engineer with 3 years minimum relevant work
experience on the survey works and implementation of rural roads, preferably
with formal training and knowledgeable road project design.
3. Skilled in computer operation with some knowledge on CAD operations and
spreadsheet
DURATION
: 1 Months
(1-week survey works and data gathering;
1 week preliminary design consideration/consultation;
3 weeks drafting of plans;
1 week preparation/finalization of cost estimates)
TERMS OF REFERENCE
SERVICE PROVIDER
(Pre-Engineering for Barangay Electrification community project)
An Individual or Engineering/Consulting Firm that can provide technical assistance in
the implementation of rural electrification in KALAHI-CIDSS areas. Technical assistance
shall include specialized advice to implementers along preparation of appropriate
designs and engineering plans, cost estimates and Program of Works.
Specifically, the Service Provider will assist the project municipal staffs and community
volunteers in the following areas:
4. Provide guidance and assistance to Project Preparation Team (PPT) on the
conduct of the following specific activities to come-up with the project
requirements for the approval of proposed improvement of barangay road, to
wit:
a. Execute detailed field survey using instruments such as engineers transit,
theodolite, total station and other appropriate instruments;
b. Preparation of engineering designs, technical drawings/plans drawn on a
500mm x 800mm appropriate paper, with the following outputs;
i.
Location plan showing the vicinity map of the proposed site
ii.
Traverse plan or schematic plan drawn on a drawing paper scaled at
1:1000 horizontal. Plans must indicate the existing and proposed
households with corresponding station limits.
The elements of
curves, bench marks and match line of traverse plan must equal to
the length of profile plan. Elevations of ground and design grade
must be indicated on the profile plan.
iii.
Cross-section plan with a scale of 1:100 (preferably). Actual ground
elevation shall be indicated and inked. Designed ground elevation
shall be indicated and penciled
iv.
Detailed plans of road structures e.g. reinforced concrete pipe
culverts (RCPC), reinforced concrete box culvert (RCBC) headwalls
and cross-drains. At critical slope, provision of portland cement
concrete pavement (PCCP) and slope protection as may be required;
v.
Detailed cost estimates showing quantity take-off and capability
outputs of labor and equipment, bill of materials for materials
vi.
Materials and construction specifications;
vii.
Others that may be specified in the contract depending on the need
of the community.
c. Operation and maintenance activities should be considered in the choice
of design options;
d. Consultation with community members and project staffs as to the
existing cultural practices and users preference must be properly
coordinated.
Close coordination with project technical staff as to the format of
POW and other project standards.
5. Submit draft of design considerations before the finalization of engineering
drawings and plans.
6. Prepare billing request together with the acceptable outputs as stated in parag. 1
for payment.
QUALIFICATIONS STANDARD
8. A Civil Engineer or Geodetic Engineer with 3 years minimum relevant work
experience on the survey works and implementation of rural roads, preferably
with formal training and knowledgeable road project design.
9. Skilled in computer operation with some knowledge on softwares related to
community water supply system design
10. Skilled in computer operation involving spreadsheet and other related softwares
11. Experience in foreign-assisted projects is an advantage
MONTHLY RATE :
DURATION
: 1 Months
(1-week survey works and data gathering;
1 week preliminary design consideration/consultation;
3 weeks drafting of plans;
1 week preparation of cost estimates)
PASS/FAIL CHECKLIST
Form to be used in conducting Preliminary Examination of Bidding Documents
(For shopping for works and bidding of works)
Name of Contractor: ________________________________
REQUIREMENTS
I.
i.
ii.
iii.
PASS or
FAIL?
Remarks
TECHNICAL DOCUMENTS
Form of Bid (in prescribe form)
Program of Works of the bidder
Plans
NFCC
Affidavit of Undertaking
Note: In case one is missing based on the checklist, verification can be done
during the post-qualification evaluation. If the missing requirement is the bid
security, it will be a ground for automatic disqualification.
Date
submitted @
ACT
DOCUMENTS
TECHNICAL
Approved POW, DE & Approved Engineering Plans
Minutes of the Pre-Procurement Conference
Invitation to Quote/Bid (Newspaper clippings or a
copy of the posted invitation)
Official Receipt (Of the Publication)
Affidavit of Publication (From the Newspaper
Company)
Minutes of Pre-Bid Conference
Minutes of Bid Opening
Abstract of Bids
Minutes of the Evaluation of Bids
Post qualification Report
Form of bid
Program
of
Works
of
Recommended
Contractor/Bidder to include summary sheet
showing unit prices of materials, labor rates and
rentals
Plans
Official Receipt (equipment proposed to be used for
the contract)
Certificate of registration (to support owning the
equipment for proposed equipment to be used)
Schedule of Utilization of Equipment
List of similar projects undertaken for the last two
years
Certification that each document submitted is an
original or true copy of the original
Certification from the bidder under oath of its
compliance to labor laws and standards and to
utilize unskilled labor in the area
Notarized Affidavit for Defects Liability Commitment
Certificate of Site Inspection (Of the bidder
recommended for award)
List of Technical Personnel
Construction Methods (itemized and wwith with
safety procedures)
Bidding Data Sheet
PS Mark License (for Pipes)
FINANCIAL
ITR Audit Statement( Of the bidder recommended
for award )
Bid Security (of the bidder recommended for award
)
NFCC (Prepared by the bidder recommended for
award )
REMARKS
Quantit
y
P __________
Unit
RPMO NOL
NPMO NOL
WB/MCA-P NOL
of
Bid Offered
Bid Security
Amount
REMARKS
Form
of
Price
Corrected
Pass/Fail
Criteria
Conclusion
Bid Evaluation
Remarks
Note:
_______________
Deputy Area Coordinator/LGU Engineer
Date: ______________
________________________
Area Coordinator
Date: ___________________
DRCIS/RCIS SECTION:
VALIDATION REPORT:
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
RECOMMENDATION:
______________________________________________________________________
______________________________________________________________________
Reviewed:
__________________
RCIS
Date: ______________
Endorsed by:
_________________________________
Community Procurement Specialist
Date: ______________
I.
II
a. Indicate the title of the community project and its project type
b. Describe the physical aspect of the community project and its indicators
(How many units, what is the length, thickness, width, etc.)
c. Indicate the barangay, municipality and province.
d. Indicate the item number, Description of the Items of Work, Quantity and
Unit of the package/s procured subject for NOL.
e. Indicate the method of procurement used
f. Indicate the approved budget for the package/s subject for NOL
g. Indicate the name of the bidder recommended for award
h. Indicate the amount in this contract
i. Indicate the aggregate amount (Total amount of contracts of the bidder
recommended for award from the previous KALAHI contracts within the
municipality to include this contract subjected for NOL.
j. Indicate if the NOL issuance is for RPMO, NPMO or World Bank.
Extract from the minutes of the Pre-Procurement Conference useful
information such as items to be procured, method of procurement, dates for
the publication of the ITB, dates of the pre-bid conference, dates of the
opening of bids, etc )
III
IV
Extract from the minutes of the pre-bid conference useful information such
as date, time and place of the bid opening, technical requirements of the
bidding, agreement made, criteria for the award, etc.
Extract from the minutes of the bid opening useful information such as late
bidders, bid offered, bid security, complaints, date and time of actual
bidding, etc..
Fill up in the matrix with the name of bidders, bid offered, bid security
(amount & form), remarks (other information not found in the matrix)
VI
VII
Make a conclusion regarding the process and result of the bid evaluation.
Post-Qualification
Examples:
Documents
I.TECHNICAL
a. List of
Community
Projects
undertaken
b. List of
Technical
Personnel
c. List of
Equipment
Owned
d. List of
equipment lease
II. FINANCIAL
a. Income Tax
Return
Based on
Documentary
Review
Based on PostQualification.
Status ( Pass/fail )
Check if the
community projects
undertaken are
supported with
contract and
certificate of
acceptance
Interview the
client if it is true
that the bidder has
a project with
them and what is
his performance.
Check if there is a
deed of sale, Official
Receipt and
Certificate of
Registration ( For
dump trucks and
other equipment
which is registered
in the LTO )
Check if supported
with lease contract
and Official Receipt
and Certificate of
Registration.
Check if supported
with Financial Audit
Statement
Check if it is
supported with
affidavit of
undertaking from
the persons listed in
the Technical
Personnel
Interview the
lessor if the rental
is true.
b. Bid Security
c. Net Financial
Contracting
Capacity ( NFCC
)
Check the
computation, if his
NFCC is equal or
more than the
contract for bid.
d. Credit Line
III. LEGAL
a. Contractors
License
Check if the
contractors license
is expired and if
expired did he
attach certificate of
temporary renewal
of license.
Check if bidder
has license and if
expired license he
has certificate of
temporary
renewal.
b. SEC
Registration
Check if supported
with articles of
incorporation
c. Authority of
the signatory
Check if the
authority of the
signatory is signed
by the owner if
owned by the
individual or board
resolution if it is a
corporation.
Check if in the
articles of
incorporation its
business is within
their primary and
secondary
purpose.
Validate if the
owner has issued
an authority or if
corporation has
issued a board
resolution allowing
its employee to
represent the
corporation.
INTRODUCTION (optional)
II. METHODOLOGY
A. Satisfy the ff:
1. WHO?
2. WHEN?
3. HOW?
RESULTS OF INVESTIGATION
A. Test of Contractors Qualification
REQUIREMENTS
I. TECHNICAL DOCUMENTS
i. Form of Bid (in prescribe form)
ii. Program of Works
iii. Plans
iv. Detailed Estimates including summary
sheet showing unit prices of materials, labor
rates and rentals (submitted by the bidder)
v. List of equipment owned/leased
vi. Official Receipt (to support owning the
equipment)
vii. Certificate of registration (to support
owning the equipment)
viii. Schedule of utilization of equipment
ix. List of similar projects undertaken for the
last 2 years
x. Certification that each document submitted
is an original or true copy of the original
xi. Certification from the bidder under oath of
its compliance to labor laws and standards and
to utilize unskilled labor in the area
xii. Notarized Affidavit for Defects Liability
Commitment
xiii. Certificate of Site Inspection
xiv. List of Technical personnel
xv.
Construction method
xvi.
NFCC
Bid Security
Affidavit of Undertaking
POST-QUALIFICATION
(Review computation,
validate the submitted
documents at the office
who issued the documents,
and others)
PASS or
FAIL?
PACKA
GE
ITEMS
QTY.
UNIT
BY CONTRACT
TOTAL
PROC.
METH
OD
LCC
Cash
2ND Tranche
LCC
Grant
Cash
3RD Tranche
LCC
Grant
Cash
TOTAL
Gran
LCC
t
Cash
PROPOSED
IMPLEMENTATI
ON SCHEDULE
Month/Weeks
1
2 3 4
Package 2
Package 1
PACKAGES
TOTAL
Reviewed by:
________________________
DAC/Municipal Engineer
Submitted by:
___________________
BSPMC Chairperson
PACKA
GE
ITEMS
UNI
T
TOT
AL
PROC.
METHOD
1ST Tranche
2nd
Tranche
3rd
Tranche
In-Kind
In-Kind
In-Kind
PROPOSED
IMPLEMENTATION
SCHEDULE
Month/Weeks
TOTAL
1
2 3
4 5 6 7
Package 2
Package 1
PACKAGES
TOTAL
Workshop output of:
_____________________
Procurement Team Head
Reviewed by:
_______________
DAC/Municipal Engineer
Submitted by:
_______________
BSPMC Chairperson
KC Cost: ______________
LCC: _________________
In-kind: _________
Cash:
_________
QT
Y.
UNIT
TOTAL
PROC.
METHOD
1ST Tranche
LCC
Grant
Cash
2ND Tranche
Grant
LCC Cash
3RD Tranche
LCC
Grant
Cash
TOTAL
Gran
LCC
t
Cash
PROPOSED
IMPLEMENTAT
ION
SCHEDULE
Month/Weeks
1
2 3 4
Package 2
Package 1
PACKAGES
TOTAL
Workshop output of:
_____________________________
Procurement Team Head
Name and Signature
Reviewed by:
________________________
DAC / Municipal Engineer
Submitted by:
________________
BSPMC Chairperson
Procurement Activities
Timeline to Complete
the Activity (Inclusive
Dates )
Responsible Volunteers
& Project Staff
Name of Potential
Suppliers &
Contractors
Resource
Requirement
Expected Outputs/
Remarks
1.
2.
3.
4.
5.
6.
Preparation of PCPP
Finalization of Packages & PCPP
Conduct of Pre-procurement Conference
Preparation of Minutes of Meeting
Preparation of Procurement Documents
Serving of Canvass
- Package # 1
- Package # 2
- Package # 3
7. Opening of Canvass and Quotation
8. Preparation of Minutes of Opening
9. Evaluation of Canvass
10. Preparation of minutes of Evaluation
11. Conduct of Post Qualification Evaluation
(LSW , LBG)
12. Prepn of Minutes of Evaluation (Post-qua)
13. Issuance of RPMT NOL
14. Preparation of Purchase Order
15. Serving of PO/s or Award (Package #)
16. Delivery of Materials
Prepared by:
____________________________
Procurement Team Head
Checked by:
_____________________
Deputy Area
Coordinator
Approved by:
Municipal Engineer
BSPMC Chairman
Noted by:
Area Coordinator
ANNEX
ITEM
Axe *
Bolo (multi-purpose) *
Brush Hook*
Grass Cutting Bolo*
Grass Cutter *
Crow Bar *
Shovel *
Hoe *
Forked Hoe*
Pick Mattock*
Pickaxe*
Sledge Hammer&*
Rake Spreader*
Hand Rammer*
Wheel Barrow*
QUANTITY
* Including Handles
I certify that the above tools have been received by me in behalf of the CONTRACT
GROUP.
________________________
GROUP LEADER
I certify that the above tools have been returned by the PAKYAW GROUP in acceptable
condition.
________________________
Project Supervisor
KALAHI-CIDSS Project
Office of the Barangay Community Project Management Committee
Barangay _________________
Municipality of _____________
Date: ____________
BID BULLETIN
Bid Bulletin No. _____ for the ________________________ (Name of Community
Project)
To: All concerned participating prospective bidders:
The BSPMC-BAC of ____________________________________ (name of Barangay)
hereby announces the postponement of opening of bids on _______________ (date)
and hereby rescheduled the same on __________________ (date) at ______________
(time) at ____________________________________ (venue).
All other provisions not herein modified shall remain in full force and effect.
For guidance and information of all concerned.
Truly yours,
_____________________________
BSPMC Chairperson
Description
Unit
Original
(Quantity /
Specifications)
Revised
(Quantity /
Specifications)
This BID BULLETIN NO. ___ shall form an integral part of the bid documents for this
public bidding.
All other provisions not herein modified shall remain in full force and effect.
For guidance and information of all concerned.
Truly yours,
_____________________________
BSPMC Chairperson
Date: __________________
ACKNOWLEDGEMENT RECEIPT
This is to acknowledge receipt of the canvass form/Invitation to Quote served by
______________,
______________,
_________________
Procurement
Team
members of BSPMC ______________________________________ (Name of Barangay
/Municipality).
________________________
Name & Signature of Contractor / Supplier
Date Served _________________
_________________________
Name & Signature of Contractor /Supplier
Date Served_________________
_________________________
Name & Signature of Contractor /Supplier
Date Served_________________
_________________________
Name & Signature of Contractor /Supplier
Date Served _________________
___________________________
Name & Signature of Contractor /Supplier
Date Served _________________
_________________________
Name & Signature of Contractor /Supplier
Date Served ________________
_________________________
Name & Signature of Contractor /Supplier
Date Served _________________
_________________________
BSPMC Chairperson
Date: __________________
ANNEX 2-A
(To be filled up by CF in two (2) copies of which one copy to be retained @ BSPMC and
the other copy to be kept in ACT. RPMT will be furnished a photocopy.)
Name of Community Project:
Location:
_________________________
_________________________
NO
OBSERVATIONS
Estimate within prevailing local prices
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
B. PACKAGING1
PACKAGE
ITEMS
Package #1
TOTAL COST
W/IN THRESH
HOLD
ABOVE THRESH
HOLD
REMARKS
Package #2
Package #3
Package #4
Package #5
Package #6
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C. BID DOCUMENTS PREPARATION
YES
NO
OBSERVATIONS
Invitation to Bid prepared
Invitation to Bid posted in Barangay Hall
Bidding Documents prepared using pro-forma
Pre-bid conference conducted
OBSERVATIONS
D. SUBMISSION OF BIDS
YES
NO
OBSERVATIONS
Bids submitted place on sealed envelope
Sealed envelope place on bid box
REMARKS
E. BID OPENING
YES
NO
OBSERVATIONS
REMARKS
F. SCRUTINY OF BIDS
YES
NO
OBSERVATIONS
Bid securities conform to the requirements
Bids are initialed by BAC members
Specifications conform to the requirements
Bids that comply are ranked from lowest to highest
Abstract of Bids was prepared
REMARKS
G. AWARDING
YES
NO
OBSERVATIONS
REMARKS
H. DELIVERY OF GOODS
YES
NO
OBSERVATIONS
REMARKS
I. PAYMENT
YES
NO
OBSERVATIONS
Payment made after the delivery of goods
Checks were prepared before the delivery of goods.
REMARKS
NO
OBSERVATION
Request for the release of 1st Tranche has been
received by the ACT from BSPMC ten (10) days
after 2nd MIBF approval of the community project.
RFR has stayed in particular station based on the
standard period for review.
Grant fund balance is 10% of the amount released
and RFR has been prepared and/or submitted by the
BSPMC within 5 days.
Actual delivery of LCC committed and reflected in
the detailed POW meet at least 50% when
requesting for the release of the 2nd tranche.
There is fund utilization one month after the release
of grant funds.
Variance of physical and financial accomplishment
did not exceeds 15%
Prepared by:
Noted by:
_________________________
Community Facilitator
Date: ___________________
REMARKS
_________________________
Area Coordinator
* Barangays certification need not have AC notation
Note: DAC to fill up this portion in the copy of report for the region.
_________________________
_________________________
NO
OBSERVATIONS
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
B. PACKAGING1
PACKAGE
Package
Package
Package
Package
Package
Package
ITEMS
#1
#2
#3
#4
#5
#6
TOTAL COST
W/IN THRESH
ABOVE THRESH
HOLD
HOLD
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C. CANVASSING
YES
NO
OBSERVATIONS
Canvass forms served to at least three separate
supplier for one package
Technical specifications is specified instead of
brand
Canvass served by designated canvasser of the
Procurement Team
D. SUBMISSION OF CANVASS2
REMARKS
YES
NO
OBSERVATIONS
Canvasses are sealed prior to opening.
Canvasses are placed inside bid box with lock or
makeshift box sealed or lock inside the cabinet.
Canvasses are personally hand carried by at least
two(2) PT members.
Canvasses are submitted by owner or
representative.
REMARKS
E. OPENING OF CANVASS.
YES
NO
OBSERVATIONS
Opening of canvass was conducted with the BAC in
quorum and presence of witnesses
Opening was conducted the day after the deadline
of submission except on Saturday, Sunday, &
Holidays
REMARKS
F. SCRUTINY OF CANVASS
YES
NO
OBSERVATIONS
Erasures of Canvass are initialed
Canvass Forms are signed by at least two PT
members
Canvass Forms are signed at least three copies per
package
Canvass Forms are initialed by BAC members
REMARKS
G. AWARDING OF CANVASS
YES
NO
OBSERVATIONS
Awarded to lowest calculated responsive canvass.
Winner conforms to specifications
Is the material to be supplied tested for quality?
For material to be supplied by informal suppliers,
they should also be tested for quality.
Awards are made to legitimate supplier3 (w/
business permit). If no, explain in remarks why?
REMARKS
H. DELIVERY OF GOODS
YES
NO
OBSERVATIONS
Goods are completely delivered on site as per
purchase order
Goods delivered in accordance to specification
Goods delivered are used in the project
Goods delivered are inspected by MIT
Goods delivered are accepted by storekeeper
REMARKS
OBSERVATIONS
Payment is on time
Payment made only to goods delivered
Signatories of check are BSPMC, Brgy. Treasurer &
Area Coordinator
Is the penalty observed for late deliveries? (1/10 of
1% per day)
REMARKS
I. PAYMENT
YES
NO
NO
OBSERVATIONS
Request for the release of 1st tranche has been
received by the ACT from BSPMC ten (10) after 2nd
MIBF approval of the community project
RFR has stayed in particular station based on the
standard period for review.
Grant fund balance is 10% of the amount released
and RFR has been prepared and/or submitted by
the BSPMC within 5 days.
Actual delivery of LCC committed and reflected in
the detailed POW meet at least 50% when
requesting for the release of 2nd tranche.
There is fund utilization one month after the
release of grant funds.
Variance of physical and financial accomplishment
did not exceeds 15%.
Prepared by:
Noted by:
_________________________
Community Facilitator
Date: ___________________
Note:
REMARKS
_________________________
Area Coordinator
DAC to fill up this portion in the copy of report for the region.
ANNEX 2-C
(To be filled up by CF in two (2) copies of which one (1) copy to be retained @ BSPMC
other copy to be kept in ACT. RPMT will be furnished one (1) photocopy.)
Name of Community Project:
Location:
_________________________
_________________________
NO
OBSERVATIONS
Estimates within prevailing local prices
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
B. PACKAGING1
PACKAGE
Package #1
ITEMS
TOTAL COST
W/IN THRESH
HOLD
ABOVE THRESH
HOLD
REMARKS
Package #2
Package #3
Package #4
Package #5
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C. QUOTATION
YES
NO
OBSERVATIONS
Quotations served to at least three (3) contractors.
Technical specifications are specified on the plans.
REMARKS
D. SUBMISSION OF QUOTATIONS2
YES
NO
OBSERVATIONS
Quotations are sealed during submission
Quotations are submitted by owner or
representative
Quotations are placed inside bid box with lock or
makeshift box sealed or locked inside cabinet
REMARKS
E. OPENING OF QUOTATION
YES
NO
OBSERVATIONS
Opening of quotation was conducted with BAC in
quorum and presence of witnesses
Opening was conducted immediately after the
deadline of submission
Quotations are sealed prior to opening
Open sealed envelopes and read aloud in public the
name of contractor and the documents attached.
REMARKS
F. SCRUTINY OF QUOTATION
YES
NO
OBSERVATIONS
Erasures of quotations are initialed
Quotations are signed by BSPMC Chairperson
Quotations are initialed by BAC
Documents are complete as per checklist
Quotations of at least three (3) contractors.
REMARKS
G. AWARDING OF QUOTATION
YES
NO
OBSERVATION
Abstract of Quotation prepared
Awarded to lowest calculated responsive quotation.
Winner conforms to specifications
Award made to legitimate (with license) contractor 3
REMARKS
H. CONTRACT PREPARATION
YES
NO
OBSERVATIONS
No Objection Letter (NOL) secured if required (RPMT
threshold is above P 500,000.00)4
Notice of Award issued
Required Performance Security posted.
REMARKS
I. CONTRACT IMPLEMENTATION
YES
NO
OBSERVATIONS
Notice to Proceed issued by BSPMC
Retention money withheld
Bank Guarantee for Advance Payment appropriate
form
Technical assistance provided by RIE and DAC
Payments made based in actual percentage of
physical accomplishment
Payments are made w/complete supporting
documents attached.
REMARKS
NO
OBSERVATIONS
Request for the release of 1st tranche has been
received by the ACT from BSPMC ten (10) after 2nd
MIBF approval of the community project
RFR has stayed in particular station based on the
standard period for review.
Grant fund balance is 10% of the amount released
and RFR has been prepared and/or submitted by the
BSPMC within 5 days.
Actual delivery of LCC committed and reflected in
the detailed POW meet at least 50% when
requesting for the release of 2nd tranche.
There is fund utilization one month after the release
of grant funds.
Variance of physical and financial accomplishment
did not exceeds 15%.
Prepared by:
Noted by:
_________________________
Community Facilitator
Date: __________________
REMARKS
_________________________
Area Coordinator
* Barangays certification need not have AC notation
Note: DAC to fill up this portion in the copy of report for the region.
_________________________
NO
OBSERVATIONS
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
B. PACKAGING1
TOTAL COST
PACKAGE
ITEMS
Package #1
W/IN THRESH
HOLD
ABOVE THRESH
HOLD
REMARKS
Package #2
Package #3
Package #4
Package #5
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C. PRE PROCUREMENT
YES
NO
OBSERVATIONS
Pre-procurement conference conducted by the
Procurement Team
Bidding documents prepared by PT
Invitation to Bid posted at the Barangay Hall
REMARKS
billboards
Pre-bid conference conducted
Letters sent to COA inviting them to attend
Invitation to Bid announced at local radio stations.
D. SUBMISSION OF BIDS
YES
NO
OBSERVATIONS
All bids are submitted on or before the deadline
All bids are placed inside bid box with lock
All bids are placed in sealed envelopes
REMARKS
E. OPENING OF CANVASS
YES
NO
OBSERVATIONS
Opening was made when BAC is in quorum
Bids are sealed prior to opening deadline
Opening was done in the place stipulated in the
Invitation to Bid.
Opening was done in public
All bids are complete as per checklist of documents
Bid security is in acceptable form
REMARKS
F. EVALUATION
YES
NO
OBSERVATIONS
Erasures of bid are initialed by concerned
contractor.
Bid documents are initialed by BAC
Technical Working Group (TWG) provided technical
assistance
Abstract of Bids prepared
Specification conforms to the requirement
Complying Bids were ranked from lowest to highest
REMARKS
G. CONTRACT
YES
NO
OBSERVATIONS
Award of contract was given to the lowest calculated
responsive bidder
NOL secured/issued
Performance Security posted acceptable
Notice to Proceed issued
H. IMPLEMENTATION
YES
NO
OBSERVATIONS
Bank Guarantee for Advance Payment posted is
acceptable
Technical assistance provided by DAC and RIE
Progress report made base by actual physical
accomplishment
Payments were made with complete documents.
REMARKS
NO
OBSERVATIONS
Request for the release of 1st tranche has been
received by the ACT from BSPMC ten (10) after 2nd
MIBF approval of the community project
RFR has stayed in particular station based on the
standard period for review.
Grant fund balance is 10% of the amount released
and RFR has been prepared and/or submitted by the
REMARKS
Prepared by:
Noted by:
_________________________
Community Facilitator
Date: __________________
_________________________
Area Coordinator
* Barangays certification need not have AC notation
Note: DAC to fill up this portion in the copy of report for the region.
ANNEX 2-E
(To be filled up by CF in two (2) copies of which one copy to be retained @ BSPMC and
the other copy to be kept in ACT. RPMT will be furnished a photocopy.)
Name of Community Project:
Location:
_________________________
_________________________
NO
OBSERVATIONS
Estimate within prevailing local prices
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
B. PACKAGING
PACKAGE
Package
Package
Package
Package
ITEMS
1
2
3
4
TOTAL COST
W/IN
ABOVE
THRESHHOLD
THRESHHOLD
C.QUOTATION
YES
NO
OBSERVATIONS
Quotation served to lone supplier
Technical Specifications are specified
REMARKS
D. SUBMISSION OF QUOTATIONS
YES
NO
OBSERVATIONS
Quotation is sealed during submission
Quotation is submitted by owner
Quotation is placed inside bid box
REMARKS
E. OPENING OF QUOTATION
YES
NO
OBSERVATIONS
Opening of Quotation was conducted with BAC in
quorum and presence of witnesses
Opening was conducted immediately after the
deadline of submission
REMARKS
REMARKS
G. SCRUTINY OF QUOTATIONS
YES
NO
OBSERVATIONS
Quotations are signed by BSPMC Chairperson
Quotations are initialed by BAC
Documents are complete as per checklist
REMARKS
H. AWARDING OF QUOTATION
YES
NO
OBSERVATIONS
Awarded to lowest calculated responsive quotation
Winner conforms to specifications
Award made to legitimate (with license) contractor.
REMARKS
I. CONTRACT PREPARATION
YES
NO
OBSERVATIONS
RPMT Clearance secured
REMARKS
J. CONTRACT IMPLEMENTATION
YES
NO
OBSERVATIONS
Notice to Proceed issued by BSPMC
Retention money withheld
Bank guarantee for Advance Payment in appropriate
form
Technical Assistance provided by RIE and DAC
Payments made based in actual percentage of
physical accomplishment
Payments are made with complete supporting
documents attached.
REMARKS
NO
OBSERVATIONS
Request for the release of 1st tranche has been
received by the ACT from BSPMC ten (10) after 2nd
MIBF approval of the community project
RFR has stayed in particular station based on the
standard period for review.
Grant fund balance is 10% of the amount released
and RFR has been prepared and/or submitted by the
BSPMC within 5 days.
Actual delivery of LCC committed and reflected in
the detailed POW meet at least 50% when
requesting for the release of 2nd tranche.
There is fund utilization one month after the release
of grant funds.
Variance of physical and financial accomplishment
did not exceeds 15%.
Prepared by:
Noted by:
_________________________
Community Facilitator
Date: __________________
REMARKS
_________________________
Area Coordinator
* Barangays certification need not have AC notation
Note: DAC to fill up this portion in the copy of report for the region
_________________________
_________________________
NO
OBSERVATIONS
Estimates within prevailing local prices
REMARKS
Others:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
B. PACKAGING
PACKAGE
Package
Package
Package
Package
ITEMS
1
2
3
4
TOTAL COST
W/IN
ABOVE
THRESHOLD
THRESHHOLD
C. CANVASSING
YES
NO
OBSERVATIONS
Canvass form serve to lone supplier
Technical Specification is specified instead of brand
Canvass served by designated canvasser of the
Procurement Team
REMARKS
D.SUBMISSION OF CANVASS
YES
NO
OBSERVATIONS
Canvass are sealed prior to opening
Canvass are placed inside bid box
Canvass are personally hand carried by at least two
(2) PT members
Canvass are submitted by the owner representative
REMARKS
OBSERVATIONS
Opening of canvass was conducted with the BAC in
quorum and presence of witnesses
Opening was conducted on the date specified in the
canvass forms
REMARKS
E. OPENING OF CANVASS
YES
NO
REMARKS
F. SCRUTINY OF CANVASS
YES
NO
OBSERVATIONS
Erasures of canvass are initialed
Canvass form is signed by at least two (2) PT
members
Canvass form is initialed by BAC members
REMARKS
G. AWARDING OF CANVASS
YES
NO
OBSERVATIONS
Awarded to the lowest calculated responsive
canvass
Winner conforms to specifications
Is the material to be supplied tested for quality? For
materials to be supplied by informal suppliers, they
also be tested for quality.
Awards are made to legitimate supplier(with
business permit). If no, explain in remarks why?
REMARKS
H. DELIVERY OF GOODS
YES
NO
OBSERVATIONS
Goods are completely delivered on site as per
Purchase Order
Goods delivered are in accordance to specifications
Goods delivered are used in the project
Goods delivered are inspected by MIT
REMARKS
OBSERVATIONS
Payment is on time
Payment made only to goods delivered
Signatories of check are BSPMC Chair, Brgy
Treasurer & Area Coordinator
Is the penalty observed for the late deliveries?
(1/10 of 1% per day)
REMARKS
I. PAYMENT
YES
NO
NO
OBSERVATIONS
Request for the release of 1st tranche has been
received by the ACT from BSPMC ten (10) after 2nd
MIBF approval of the community project
RFR has stayed in particular station based on the
standard period for review.
Grant fund balance is 10% of the amount released
and RFR has been prepared and/or submitted by the
BSPMC within 5 days.
Actual delivery of LCC committed and reflected in
the detailed POW meet at least 50% when
requesting for the release of 2nd tranche.
There is fund utilization one month after the release
of grant funds.
Variance of physical and financial accomplishment
did not exceeds 15%.
Prepared by:
REMARKS
Noted by:
_________________________
Community Facilitator
Date: __________________
_________________________
Area Coordinator
* Barangays certification need not have AC notation
Note: DAC to fill up this portion in the copy of report for the region
Director ________________________
Regional Project Director or Manager
KALAHI-CIDSS Project
___________________________
Location:
DATE
OF
FILING
___________________________
CHECK
MARKS
DOCUMENTS
Daily Rate Basis Laborers
Disbursement Voucher
Employment Record Sheet
Daily Time Record
Pakyaw Contracts
Disbursement Voucher
List of Workers
Certification of Accomplishment
Honoraria To Committee Members
Disbursement Voucher
Employment Record Sheet
Time Sheets
Training Expenses
Disbursement Voucher
Training Completion Report
Contract with the trainers(if applicable)
Training Design and Budget
Petty Cash Fund (Establishment)
Disbursement Voucher
Minutes of BSPMC Executive Committee
Meeting
Reimbursement of Petty Cash Fund
Disbursement Voucher
Petty Cash Liquidation Summary
Petty Cash Voucher w/supporting documents
Payment of Goods to Non-registered
Suppliers
Reimbursement Expense Receipt
Disbursement Voucher
Certification from the Project Engineer.
(Materials delivered on site and in accordance
to specs.
Certification from Punong Barangay(a.) No
legitimate or registered supplier in the area; b.)
Buying the materials from legitimate suppliers
in other areas would entail additional cost not
provided in the POW)
Purchase Order
Abstract of Canvass
Canvass Forms
PERSON
RESPONSIBLE
REMARKS
___________________________
Location:
DATE
OF
FILING
CHECK
MARKS
DOCUMENTS
Notice of Award
Conditions of Contract
Contract of Agreement
Performance Security
Drawing/Plan/Specifications
PERSON
RESPONSIBLE
BSPMC
Chairperson/Co
m. Bookkeeper
(CB)
Procurement
Team/CB
Procurement
Team/CB
DAC/CB
PT/CB
PT/CB
PT/CB
PT/CB
PT/CB
BSPMC
Chairperson/CB
PT/CB
DAC/CB
PT/CB
PT/CB
DAC/CB
BSPMC
Chairperson/CB
DAC/CB
Barangay
Treasurer
PIT/CB
Barangay
Treasurer
Barangay
Treasurer
REMARKS
Note: 1. Items 1-15 to be attached to first payment only (or refer to finance manual)
2. Second and succeeding payments require items 17-21 only(or refer to Finance
manual)
___________________________
Location:
DATE
OF
FILING
CHECK
MARKS
DOCUMENTS
1. Approved Program of Works
2 . Planned Community Procurement Packaging
3. Actual Community Procurement Packaging
4. Pre-Procurement Conference (Minutes)
5. Invitation to Quote
6. Abstract of Quotation
7. Minutes of Opening of Quotation
8. Contractors License
9. Minutes of Evaluation of Quotation
10. RPMT NOL (If applicable)
11. Notice of Award
12. Condition of Contract
13. Contract of Agreement
14. Performance Security
15. Notice to Commence
16. Bank Guarantee for Advance Payment
17. Drawing/Plan/Specification
18. CF Proc Red Flag Monitoring Form
19.Contractors Billing
20.Joint Inspection Report
21. Disbursement Voucher w/ photocopy of
cheque
22. Official Receipt
Note:
PERSON
RESPONSIBLE
BSPMC
Chairperson/CB
Procurement
Team /CB
Procurement
Team/CB
Procurement
Team /CB
Procurement
Team/CB
Procurement
Team/CB
PT/CB
DAC/CB
PT/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
PT/CB
PT/CB
BSPMC
Chairperson/CB
Barangay
Treasurer/CB
PT/CB
PT/CB
Barangay
Treasurer
DAC/CB
Barangays
Treasurer/CB
Barangay
Treasurer/CB
REMARKS
___________________________
Location:
DATE
OF
FILING
___________________________
CHECK
MARKS
DOCUMENTS
Finance Documents
1. Official Receipt
2. Disbursement Voucher
3. Sales/Charge Invoice or Statement of
Accounts
4. Delivery Receipts
5. Contract
6. Abstract of Quotation
7. Invitation to Quote
Procurement Documents
1
Approved Program of Works
2
Invitation to Quote
5
6
7
8
9
Instruction to Bidders
Conditions of Contract
Drawings/Plan
Technical Specification
Contractor's License
10
11
Abstract of Quotation
12
13
14
15
16
Contract Agreement
No Objection Letter
Notice to Proceed
Performance Security
17
18
19
20
PERSON
RESPONSIBLE
BSPMC Chairman
Procurement
Team (PT)
Procurement
Team (PT)
Procurement
Team (PT)
DAC/PPT/PT
DAC/PPT/PT
DAC
DAC
DAC
Procurement
Team (PT)
BAC/PT
Procurement
Team (PT)
BSPMC Chairman
BSPMC Chairman
BSPMC Chairman
BSPMC Chairman
Barangay
Treasurer
CF
BSPMC Chairman
PIT
REMARKS
___________________________
Location:
DATE
OF
FILING
CHECK
MARK
DOCUMENTS
1 Approved Program of Works
2 Planned Community Procurement Packaging
3. Actual Community Procurement Packaging
4. Minutes of Pre-Procurement Conference
5 Invitation To Bid
6 Minutes of Pre-Bid Conference
7 Minutes of Bid Opening
8 Forms of Bid
9 Bid Security
10 Certificate of Business Registration
11. Minutes of Evaluation of Bids
12. Abstract of Bid
13.Post qualification Report
14.Resolution to Award
15. MCA-Philippines Eligibility Verification
Letter; No Objection Letter (NPMT)
16. Performance Security
17. Notice of Award
18. CF Proc Red Flag Monitoring Form
19. Purchase Order
20. Sales/Charge Invoice or Statement of
Accounts and/or Delivery Receipt
21. Certificate of Inspection and Acceptance*
22. Disbursement Voucher w/ attached
photocopy of cheque
23.Official Receipt
PERSON
RESPONSIBLE
REMARKS
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
PT/CB
Procurement
Team /CB
Procurement
Team/CB
Procurement
Team /CB
Procurement
Team /CB
Barangay
Treasurer/CB
Procurement
Team/CB
Procurement
Team/CB
Procurement
Team/CB
PT/CB
PT/CB
BSPMC
Chairperson/CB
Procurement
Team/CB
BSPMC
Chairperson/CB
Procurement
Team/CB
PIT/CB
Barangay
Treasurer/CB
MIT/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
CHECK
MARK
DOCUMENTS
Finance Documents
1. Approved Program of Works
2.Planned Community Procurement Packaging
3. Actual Community Procurement Packaging
4 Minutes of Pre-Procurement Conference
5 Invitation To Bid
6. Minutes of Pre-bid conference
7. Minutes of Bid Opening
8. Instruction to Bidders
9. Drawings/Plan
10. Technical Specifications
11. Forms of Bid
12. Bid Security
13 Minutes of Bid Evaluation
14 Abstract of Bids
15. Contractors License
16 Post Qualification Report
17 Resolution to Award
18 No objection Letter (NPMT);
19 Notice of Award
20. Contract Agreement/Conditions of Contract
21. Performance Security
22. Notice to Commence
23. Bank Guarantee for Advance Payment
24. CF Proc Red Flag Monitoring Form
25. Contractors Billing
26. Joint Inspection Report
27. Disbursement Voucher w/ photocopy of
cheque
28.Officicial Receipt
PERSON
RESPONSIBLE
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
Procurement
Team /CB
Procurement
Team/CB
Procurement
Team/CB
Procurement
Team/CB
PT/CB
PT/CB
PT/CB
Procurement
Team/CB
Barangay
Treasurer/BCB
PT/CB
PT/CB
PT/CB
PT/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
BSPMC
Chairperson/CB
Barangay
Treasurer/CB
CF/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
REMARKS
___________________________
Location:
DATE
OF
FILING
CHECK
MARK
DOCUMENTS
1. Approved Program of Works
2. Planned Community Procurement Packaging
3. Actual Community Procurement Packaging
4. Data Base Price( Regional Office)
5. Minutes of Pre-Proc Conference
6. Certification from Procurement Team that no
other supplier is available in the area
7. Canvass form
8. Minutes of Opening of Canvass
9.Minutes of Evaluation of Canvass
10. No Objection Letter (RPMT)
11. Purchase Order
12. CF Proc Red Flag Monitoring Form
13. Sales/Charge Invoice and/or Delivery
Receipt
14. Certificate of Inspection and Acceptance*
15. Disbursement Voucher w/ attached
photocopy of cheque
16. Official Receipt
PERSON
RESPONSIBLE
BSPMC
Chairperson/CB
Procurement
Team/CB
Procurement
Team/CB
DAC/CB
PT/CB
Barangay
Treasurer/CB
PT/CB
PT/CB
PT/CB
BSPMC
Chairperson/CB
PIT/CB
CF/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
Barangay
Treasurer/CB
REMARKS
___________________________
Location:
DATE
OF
FILING
CHECK
MARK
DOCUMENTS
1. Approved Program of Works
2.
3.
4.
5.
6.
7.
7.
PERSON
RESPONSIBLE
BSPMC
Chairperson/CB
PT/CB
PT/CB
PT/CB
PT/CB
PT/CB
PT/CB
PT/CB
BSPMC
Chairperson/CB
Barangay
Treasurer/CB
CF/CB
Barangay
Treasurer/CB
MIT/CB
Barangay
Treasurer/CB
Barangay
Treasure/CB
REMARKS
*Certificate of Inspection and Acceptance could be indicated in the Purchase Order and
Delivery Receipt
CHAPTER 11 |
GUIDELINES AND
CLARIFICATIONS
ANNEX
QUANTITY
* Including Handles
I certify that the above tools have been received by me in behalf of the CONTRACT
GROUP.
______________________
GROUP LEADER
I certify that the above tools have been returned by the PAKYAW GROUP in acceptable
condition.
______________________
Project Supervisor
1. The Lessor has the option to claim for advance payment up to fifteen (15)
2. The Lessor can claim partial payment if the accomplishment is at least twenty
(20) percent without submitting a bank guarantee provided the DAC or the Municipal
Engineer (if there is no DAC in the Municipality) certified that the equipment is
being utilized on the date claimed.
Equipment Rental as Works - if the utilization of the equipment is based on the
quantity of the item/s of work/s. Payment for rental under works is based on an
output that the equipment will complete. Similar with Equipment Rental as Goods,
equipment should be fully operated. The procurement form to be used in renting any
equipment categorized as works shall be Invitation to Lease Equipment and
Equipment Lease Agreement for Works (please see attached format).
For contract amounting to PhP. 30,000.00 and below, payment shall be made upon
completion of the contract. For contract amounting to more than PhP. 30,000.00 and
above, the BSPMC may make advance payment to the Lessor in the amount up to
fifteen (15) percent of the Contract Price only after the DAC had certified that the
equipment is delivered at the project site and the Lessor has submitted to the BSPMC a
Bank Guarantee of equal amount. The advance payment shall be repaid by making
deductions for every progress billing with consideration that it is fully recoup upon
reaching 80% physical accomplishment. Progress payment is allowed. The first
recoupment shall start when accomplishment has reached 20% of the total contract
price.
Full payment shall be made only upon completion of the services with certification of
the DAC and approval of the BSPMC.
There shall be no retention money withheld on any progress billing for rental of
equipment.
It is reiterated that the detailed procedures as provided in the manual shall be strictly
followed.
The threshold for the issuance of No Objection Letter shall also be strictly followed.
9. Show Cause refers to a notice which the BSPMC is required to issue prior to
terminating a contract. The purpose of a show cause notice is to enable the contractor
to present its position why the contract should not be terminated.
10. Verified Report refers to the report submitted by the Technical Working Group to
the BSPMC Chairperson setting forth its findings as to the existence of grounds or
causes for termination and explicitly stating its recommendation for the issuance of a
Notice to Terminate.
IV. GROUNDS FOR TERMINATION OF CONTRACTS
A. Termination for Default
1. In contracts for Goods:
The BSPMC shall terminate a contract for default when any of the following
conditions attend its implementation:
a) Outside of force majeure 17, the Supplier fails to deliver or perform any or all
of the Goods within the period(s) specified in the contract, or within any
extension thereof granted by the BVSPMC pursuant to a request made by the
Supplier prior to the delay, and such failure amounts to at least ten percent
(10%) of the contact price;
b) As a result of force majeure, the Supplier is unable to deliver or perform any
or all of the Goods, amounting to at least ten percent (10%) of the contract
price, for a period of not less than sixty (60) calendar days after receipt of the
notice from the BSPMC stating that the circumstance of force majeure is deemed
to have ceased; or
c) The Supplier fails to perform any other obligation under the Contract.
2. In contracts for Infrastructure Projects (Works):
The BSPMC may terminate the Contract for breach of contract. Fundamental
breaches of Contract shall include, but shall not be limited to, the following:
(a)
The Contractor stops work for ten (10) days when the stoppage has not
been authorized by the Project Supervisor;
(b) The Project Supervisor gives notice that the Contractor has failed to
correct a Defect within twenty one (21) days as determined by the Project
Supervisor;
(c) The Contractor has delayed the completion of the works by thirty (30)
calendar days;
(d) If the contractor incurred a minimum of negative fifteen percent
(15%) slippage but remains dormant for almost two months despite
receipt of the warning letter from the BSPMC; and,
(e) The Contractor:
17
Force majeure (French for "greater force") is a common clause in contracts which essentially frees one or both parties from
liabilities when an extraordinary event beyond the control of the parties, such as flood, war, riots, acts of God, et cetera prevents
one or both parties from fulfilling their obligations under the contract.
Verification
Issuance of Notice of
Termination
Show Cause Order (The
Supplier/Contractor will
submit to the BSPMC a
position paper why the
contract should not be
terminated)
Rescission of Notice of
Termination (The BSPMC may, at
anytime before receipt of the
Suppliers/Contractors verified
position paper to withdraw the
Notice to Terminate if it is
determined that certain items or
works subject of the notice had
been completed, delivered, or
performed before the
Suppliers/Contractors receipt of
the notice.
The
Supplier/Contractor
The BSPMC
Chairperson to be
delivered by the
Procurement
Team
The BSPMC
Chairperson
The BSPMC
Chairperson or
the RPD/RPM
The BSPMC
Max.
GOODS
Min.
Max.
WORKS
1 CD
1 CD
1 CD
1 CD
Within
2 CD
Within
5 CD
Within
2 CD
Within
5 CD
1 CD
1 CD
1 CD
1 CD
Within
7 CD
Within
7 CD
Within
7 CD
Within
7 CD
1 CD
1 CD
1 CD
1 CD
Within 2
CD
Within
7 CD
Within
2 CD
Within
7 CD
Within
2 CD
Within
2 CD
Within
2 CD
1 CD
1 CD
1CD
Within
CD
1 CD
17 CDs
17 CDs
25
CDs
25 CDs
This guideline shall govern the blacklisting of manufacturers, suppliers, distributors and
contractors involved in KALAHI-CIDSS: KKB Project for offenses or violations committed
during competitive bidding and contract implementation.
This guideline shall apply to all KALAHI-CIDSS: KKB FUNDED Projects.
5. PROHIBITION ON BLACKLISTED PERSONS/ENTITIES TO PARTICIPATE IN
THE BIDDING OF KALAHI-CIDSS: KKB PROJECTS/CONTRACTS
A person/entity that is blacklisted by a procuring entity and/or included in the
Government Procurement Policy Board (GPPB) Consolidated Blacklisting Report shall not
be allowed to participate in the bidding of all KALAHI-CIDSS: KKB funded projects
during the period of disqualification unless it is delisted as provided for in these
guidelines.
6. DEFINITION OF TERMS
6.1 Appellate Authority. The BSPMC with concurrence of the RPMO.
6.2 Award. A written notice from the BSPMC accepting a bid or proposal.
6.3 Blacklisting. An administrative penalty disqualifying a person or an entity from
participating in any KALAHI-CIDSS: KKB procurement for a given period.
6.4 Suspension. The administrative penalty imposed for infractions 21 committed by a
contractor during the competitive bidding stage, whereby such contractor is prohibited
from further participation in the bidding process of an agency.
6.5 Consolidated Blacklisting Report. A report prepared by the GPPB containing the
list of suppliers, manufacturers, distributors, contractors or consultants blacklisted by
procuring entities.
6.6 Contract Implementation. A process of undertaking a project or contract in
accordance with the contract documents.
6.7 Termination of Contract. Extinction of contract by reason of resolution or
rescission under Articles 1191, 1380, 1381 of the Civil Code, Section 68 of the Revised
IRR of R.A. 9184 and provision of the Community-Based Procurement Manual and
other applicable laws arising from the default of the contractor.
6.8 Delist. Removal of a person/entity from the Consolidated Blacklisting Report.
6.9 Blacklisted Person/Entity. A person/entity who was disqualified by an agency
and/or is included in the GPPB Consolidated Blacklisting Report.
7. SANCTIONS AND GROUNDS FOR BLACKLISTING
7.1 Competitive Bidding Stage
During the competitive bidding stage, the BSPMC shall impose on bidders or
prospective bidders the penalty of suspension for one (1) year for the first offense,
suspension for two (2) years for the second offense from participating in KALAHICIDSS bidding process, without prejudice to the imposition of additional
administrative sanctions as the internal rules of the BSPMC may provide and/or further
criminal prosecution, as provided by applicable laws, for the following violations:
21
iii. Stockpiling in proper places of all materials and removal from the project site
of waste and excess materials, including broken pavement and excavated debris
in accordance with approved plans and specifications and contract provisions;
iv. Deployment of committed equipment, facilities, support staff and manpower;
and
v. Renewal of the effectivity dates of the performance security after its
expiration during the course of contract implementation.
c) For the procurement of goods, unsatisfactory progress in the delivery of the
goods by the manufacturer, supplier or distributor arising from his fault or
negligence and/or unsatisfactory or inferior quality of goods, as may be provided in
the contract;
f) For the procurement of infrastructure projects, poor performance by the contractor
or unsatisfactory quality and/or progress of work arising from his fault or negligence
as reflected in the Constructor's Performance Evaluation System (CPES) rating
sheet provide by the GPPB. In the absence of the CPES rating sheet, the existing
performance monitoring system of the KALAHI-CIDSS shall be applied. Any of the
following acts by the constructor shall be construed as poor performance:
i. Negative slippage of 15% and above within the critical path of the project due
entirely to the fault or negligence of the contractor; and
ii. Quality of materials and workmanship not complying with the approved
specifications arising from the contractor's fault or negligence.
g) Willful or deliberate abandonment or non-performance of the project or contract
by the contractor resulting to substantial breach thereof without lawful and/or just
cause.
In addition to the penalty of suspension, the performance security posted by the
contractor shall also be forfeited.
8. PROCEDURE FOR SUSPENSION
COMPETITIVE BIDDING STAGE
AND
BLACKLISTING
DURING
THE
22
Prima Facie - is a Latin word meaning at first sight, a fact presumed to be true until disproved.
b) he has the opportunity to show cause why he should not be suspended and
blacklisted;
c) a hearing shall be conducted before the BAC, upon his request, where he may
present documentary evidence, verbal testimony and cross-examine the
witnesses presented against him; and
d) the consequences of being suspended and blacklisted.
Within seven (7) calendar days from receipt of notification, the contractor shall submit
its written answer with documentary evidence to the BAC with a manifestation for
request of hearing to determine questions of fact, if he so desires. No time extension
shall be allowed. Should the contractor fail to answer within the same period, the BAC
shall issue a resolution recommending to the BSPMC Chair to be assisted by
Area Coordinating Team or the Municipal Inter-Agency Committee to be
concurred by the RPMO thru the Regional Director or Regional Project Manager
the immediate suspension of the contractor from participating in any bidding process in
any KALAHI-CIDSS funded project and the forfeiture of his bid security.
8.3 Hearings
If a hearing is requested, the BAC shall immediately set the date and time for hearing.
The hearing shall be non-litigious and shall be terminated within five (5) calendar
days. The BAC may also invite a representative from a duly recognized private group,
NGOs, NGAs, religious group or discipline relevant to the procurement at hand as an
observer for each hearing. If no request is made, the BAC shall make a determination of
the case based on the complaint, answer, documentary evidence submitted and facts
verified. If the BAC is convinced that the contractor is at fault, it shall issue a resolution
recommending to the BSPMC Chairperson (assisted by Area Coordinating Team or
the Municipal Inter-Agency Committee) to be concurred by the RPMO thru the
Regional Director or Regional Project Manager the suspension of the contractor
from participating in any bidding process of the agency and the forfeiture of his bid
security.
8.4 Decision
The BSPMC Chairperson shall, within five (5) calendar days from receipt of the
resolution and the records of the BAC proceedings, determine whether reasonable cause
exists for the suspension of the contractor and the forfeiture of the latters bid security.
If the BSPMC Chairperson determines that such reasonable cause exists, he shall issue
a decision suspending the contractor from participating in any bidding process of the
KALAHI-CIDSS project, and further declaring that his bid security is forfeited.
Otherwise, he shall dismiss the case.
The decision shall clearly and distinctly state the facts, evidence and the law on which it
is based, as well as the date of effectivity of the penalty, if any.
The BSPMC Chairperson may delegate to the BAC the authority to impose the
corresponding sanction(s) provided for in these guidelines. In case a contractor commits
more than one offense or a combination of offenses for the same project/contract in a
particular KALAHI-CIDSS area, each violation shall be meted the corresponding penalty.
8.5 Notice of Decision
The BSPMC Chairperson shall furnish the suspended Contractor, Manufacturer, Supplier
and Distributor a copy of the decision immediately from its promulgation.
But if Blacklisting Order is issued prior to the date of the notice of award (NOA), the
blacklisted person/entity shall not be qualified for award and such project/contract shall
be awarded to another bidder pursuant to Community-Based Procurement Guidelines. If
the Blacklisting Order is issued after award of a government project/contract to the
blacklisted person/entity, the awarded project/contract shall not be prejudiced by the
said order. Provided, however, that the said offense(s) committed by the blacklisted
person/entity is/are not connected with the awarded project/contract.
11. DELISTING
11.1 A blacklisted person/entity shall be automatically delisted after the period for the
penalty shall have elapsed, unless the blacklisting agency requests the GPPB to
maintain the blacklisted person/entity in the GPPB Consolidated Blacklisting Report due
to justifiable reasons. In the latter case, the blacklisted person/entity shall be delisted
only upon the blacklisting agencys issuance of a Delisting Order.
ACTIVITIES
Initiation of
Action
Notification
Hearings
(NonLitigious)
Decision
Notice of
Decision
Responsible Person
The BAC commence the proceedings to
determine the grounds for blacklisting
The BAC to notify the contractor,
manufacturer, supplier or distributor
The BAC (can invite duly recognized
groups, NGOs NGAs, religious group)
If the BAC is convinced that the
contractor/supplier/distributor is at
fault, it shall issue resolution
recommending to the BSPMC
Chairperson the suspension. The
ACT/MIAC shall assist the BAC and
BSPMC.
The BSPMC to decide of the
suspension and declare forfeiture of
the bid security/performance
security. Otherwise, he shall dismiss
the case.
The BSPMC Chairperson may
delegate to the BAC the authority to
impose corresponding sanctions.
The BSPMC Chairperson shall furnish the
suspended contractor / manufacturer /
supplier / distributor
The contractor / manufacturer / supplier
/ distributor is suspended upon receipt of
the notice of decision prohibiting him in
participating in the bidding process in
any KC project
Effect of
Decision
Protest
from
Decision
Finality of
Decision and
submission to
the GPPB/CIAP
1 CD
Within 3 CD
to deliver the notice
Within 2 CD
Within 2 CD
Within 1 CD
Within 1 CD
10 Cal. Days
MAXIMUM
1 CD
Within 7 CD
Within 5 CD
Within 5 CD
Within 1 CD
Within 1 CD
20 Cal. Days
Within 7 CD from
filing + 5 Calendar
days to resolve from
the filing date
Within 7 CD from
filing + 5 Calendar
days to resolve
from the filing
date
Within 7 CD from
receipt of the
resolution on the
motion for
reconsideration
Within 7 CD from
receipt of the
resolution on the
motion for
reconsideration
30 Cal. Days
40 Cal. Days
supplier / distributor from participating in the bidding in all KALAHI-CIDSS Projects. The
performance security of said contractor shall also be forfeited.
3. An Extra Work Order may be issued by the BSPMC Chairperson to cover the
4.
5. In claiming for any Variation Order, the contractor shall, within seven (7)
calendar days after such work has been commenced or after the
circumstances leading to such condition(s) leading to the extra cost, and
within fifteen days (15) calendar days deliver a written communication giving
full and detailed particulars of any extra cost in order that it may be
2. Request for payment by the contractor for any extra work shall be accompanied
by a statement, with the approved supporting forms, giving a detailed
accounting and record of amount for which he claims payment. Said request for
payment shall be included with the contractor's statement for progress payment.
1. Once a month, the contractor may submit a request for payment for work
accomplished. Such request for payment shall be verified and certified by the
PIT, DAC and RIE concerned. Except as otherwise stipulated in the Instruction to
Bidders, materials and equipment delivered on the site but not completely put in
place shall not be included for payment.
2. The procuring entity shall have the right to deduct from the contractor's progress
billing such amount as may be necessary to cover third party liabilities, as well
as uncorrected discovered defects in the project.
VI. RETENTION MONEY FOR VARIATION/CHANGE ORDER
1. Progress payments are subject to retention of ten percent (10%) referred to as
the "retention money." Such retention shall be based on the total amount due to
the contractor prior to any deduction and shall be retained from every progress
payment until fifty percent (50%) of the value of works, as determined by the
BSPMC, are completed. If, after fifty percent (50%) completion, the work is
satisfactorily done and on schedule, no additional retention shall be made;
otherwise, the ten percent (10%) retention shall be imposed.
2. The total "retention money" shall be due for release upon final acceptance of the
works. The contractor may, however, request the substitution of the retention
money for each progress billing with irrevocable standby letters of credit of from
a commercial bank, or bank guarantees callable on demand, of amounts
equivalent to the retention money substituted for and acceptable to the BSPMC,
provided that the project is on schedule and is satisfactorily undertaken.
Otherwise, the ten percent (10%) retention shall be made. Said irrevocable
standby letters of credit or bank guarantees, to be posted in favor of the BSPMC
shall be valid for a duration to be determined by the concerned BSPMC and will
answer for the purpose for which the ten percent (10%) retention is intended,
i.e., to cover uncorrected discovered defects and third party liabilities.
VII. CONTRACT COMPLETION
Once the project reaches an accomplishment of ninety five (95%) of the total contract
amount, the inspectorate team to make preliminary inspection and submit a punch-list
to the contractor in preparation for the final turnover of the project. Said punch-list will
contain, among others, the remaining works, work deficiencies for necessary
corrections, and the specific duration/time to fully complete the project considering the
approved remaining contract time. This, however, shall not preclude the procuring
entity's claim for liquidated damages.
The BSPMC thru the BAC shall directly invite or get quotations/bid
proposals from at least three or more licensed contractors within the
municipality or adjacent municipalities that has satisfactorily completed a
contract of the same nature. This procedure will exempt the requirement
23
Appropriate authorities to mean the Sanggunian in the Municipality or Province declaring state of calamity inn the area where
the sub-project is located.
1.2.
1.3.
1.4.
2.
2.3
3.
The contract may be negotiated starting from the second lowest rated
bidder under consideration at the bidders original price.
If negotiation fails, then negotiation shall be done with the third lowest
calculated rated bidder at his original price. If the negotiation fails again,
a short list of at least three (3) eligible contractors shall be invited to
submit their bids, and negotiation shall be made starting with the lowest
calculated rated bidder.
The BSPMC shall allow at least 7 calendar days for bidders to prepare a
detailed bid proposal and thereafter, the timelines specified in each
procurement activity from opening to award of contract shall be strictly
followed to facilitate immediate implementation.
In the preceding guidelines, a procedure for variation order is provided. In the event
of a change order e.g. Extra Work order, the guidelines on undertaking change order
shall be followed. Limits and conditions shall also be referred to said guidelines.
Negotiation with the same contractor may be allowed in the following instances:
24
Mobilization cost for extra work orders should not be considered since it is assumed to be incorporated in the original
contract.
Any cumulative Variation Order beyond ten percent (10%) shall be subject
of another contract to be bid out if the works are separable from the original
contract. In exceptional cases where it is urgently necessary to complete the
original scope of work, the BSPMC may authorize the variation order beyond
ten percent (10%) but not more than twenty percent (20%) subject to the
guidelines to be determined by the NPMO: Provided, however, That
appropriate sanctions shall be imposed on the designer, service provider,
consultant or official responsible for the original detailed engineering design
which failed to consider the Variation Order beyond ten percent (10%).
GUIDELINES IN
CONTRACTORS
EVALUATING
PERFORMANCE
of
SUPPLIERS
and
Rationale
The KALAHI-CIDSS is a fast-paced/time-bounded project. Community community
projects are funded as these are immediate needs of the communities. Therefore, in the
provision of goods and services, service providers such as suppliers and contractors
should comply strictly with the provisions of the contract to immediately expedite the
completion of the community projects.
In order to facilitate management of suppliers and contractors doing business with the
communities, the project shall establish procedures for evaluating, documenting, and
reporting the supplier/contractors performance under a contract for purchase of goods,
performance of services, consulting, construction or improvement of facilities. These
procedures shall include a process for performance appraisal, communication of
feedback to vendors, forms and documentation requirements.
Why Evaluate the Supplier/Contractor?
1. To improve communication and relationship with suppliers/contractors;
2. To improve supplier performance by way of awareness and feedback on key
performance criteria and service improvement areas;
3. To have more reliable material quality and availability and/or better service;
4. To document supplier performance to be used as basis for future transactions
and discussions with the supplier
Purposes
1. To provide the BSPMC with objective information on which judgments relating to
source selection can be based; and,
2. To enable the BSPMC to provide the supplier with an indication of his
performance rating and where improvements, if any, are required.
Criteria for Evaluation
1.
2.
3.
4.
5.
Quality
Delivery
Price
Technical Support
Management Attitude
Assigned Points:
Criteria
Quality
Delivery
Price
Compliance to Environmental Laws
Technical Support
Management Attitude
Total
Points
40
20
20
10
5
5
100
Categorical Rating:
Very Good - 90-100
Satisfactory- 50-89
Unsatisfactory
- 0-49
Blacklisting
The purpose of blacklisting is to protect the project from risks associated with awarding
contracts to persons or firms having exhibited an inability or unwillingness to fulfill
contractual obligations, and to protect the projects interests and the integrity of the
procurement process by preventing individuals or firms who have displayed improper
conduct from participating on project requirements for specific periods of time.
Sanction/s
1. Any supplier/contractor that has incurred an UNSATISFACTORY rating in a
particular barangay shall not be allowed to participate in any procurement in
that barangay;
2. Any supplier/contractors that has incurred two (2) UNSATISFACTORY ratings
in a particular Municipality shall not be allowed to participate in any KALAHICIDSS procurement in that Municipality; and,
3. Any supplier/contractors that has incurred three (3) UNSATISFACTORY ratings
in a particular region shall not be allowed to participate in any DSWD - KALAHICIDSS procurement in any region.
Discussion
The evaluation procedures must be discussed with the suppliers and or contractors
during contractors conference/meeting or pre-bidding conferences.
The Form and Guides in Filling-up
The evaluation form and guides is found on the succeeding page.
: ___________________
Barangay : ___________________
Municipality
Province
Region
: ___________________
Contract for
: _________________
: _________________
Points
40
20
20
10
5
5
100
Categorical Rating:
Very Good - 90-100
Satisfactory - 50-89
Unsatisfactory
- 0-49
Rated by:
__________________________________________
Head, Procurement Team (Name & Signature)
__________________________________________
Head, Project Implementation Team (Name & Signature)
___________________________________________
Head, Monitoring & Inspection Team (Name & Signature)
Approved by:
___________________________________________
BSPMC Chairperson
Rating
Guides in Rating:
1. Quality = 40 points
A. FOR GOODS:
BASIS
BASIS
Corresponding
Points
40
35
25
20
0
Corresponding
Points
40
35
30
20
0
2. Delivery
A. GOODS
If
If
If
If
If
the
the
the
the
the
goods
goods
goods
goods
goods
B. WORKS
BASIS
are delivered within schedule
were delivered but 1 3 days delayed
were delivered but 3-5 days delayed
were delivered but more than 6 days delayed
were not delivered
BASIS
Corresponding
Points
20
15
10
5
0
Corresponding
Points
20
15
10
5
0
Corresponding Points
20
15
10
Corresponding Points
10
5
5. Technical Support
BASIS
Did the owner show concern with the BSPMC on the
immediate delivery?
Did the workers of the supplier or contractor assisted the
volunteers in terms of handling, proper installation, or
provided instructions in the usage of materials
If during the delivery there were no efforts shown by
the owner and their workers
Corresponding Points
5
6. Management Attitude
BASIS
Is the owner or their personnel provided quality service
by to the volunteers? Are they humble enough? If yes,
give the maximum score.
Do they give importance to the volunteers when they
are transacting business with the firm/company/office?
If they show less concern to the volunteers
Corresponding Points
5
After Bid Opening, evaluate all bid item prices, as submitted by the Bidders, for
unreasonable deviations from the Engineers Estimate. The BSPMC deserves the right to
review all Bids for material unbalancing regardless of the deviation from the Engineers
Estimate.
If bid item prices deviate more than a reasonable amount from the Engineers Estimate,
re-check the bid item quantities.
Example:
Name of Community Project: Improvement of Farm to Market Road
Per Approved POW and PCPP
Item
No.
102
105
200
201
Description
Roadway &
Drainage
Excavation
Sub-Grade
Preparation
Aggregate
Sub-Base
Coarse
Aggregate
Base Coarse
TOTAL
Cost
Difference
Percenta
ge (Cost
Differenc
e)
Qty
Unit
Unit
Price
6,762.39
Cu.
m.
70.39
476,004.63
625,000.00
148,995.37
-31.30%
9,812.00
Sq.
M.
14.69
144,138.28
221,000.00
-76,861.72
-53.32%
1,417.80
Cu.
m.
225.81
320,153.42
224,000.00
94,153.42
29.41%
1,471.00
Cu.
m.
253.36
372,692.56
242,000.00
130,692.56
35.07%
Total
1,312,988.89
1,312,000.00
In the above example, assuming that profit, overhead costs and other considerations
were incorporated, it is clear that the bid is unbalanced as unit bid prices are front
loaded in Items 102 and 105 of the contract with minimal unrealistic costs attributed
to work required for Items 200 and 201 of the contract.
The risk in the above example is: What if the contractor abandoned the contract
after completing Item 102 and 105? Can the remaining amount complete the
remaining items of work?
Accuracy of Estimated Quantities:
When items are bid unusually high or low in relationship to the engineer's estimate, the
accuracy of the estimated quantities should be checked. If, after examination, the
estimated quantities are determined to be a reasonably accurate representation of
actual anticipated needs, then the low bid should be further evaluated for unbalancing.
On the other hand, in cases where it is concluded, after examination, that the estimated
quantities are not a reasonably accurate representation of actual anticipated needs, the
BAC with assistance of TWG should consider rejecting all bids, correcting the quantities,
and re-advertising. However, an error in estimated quantities should not cause an
automatic rejection of bids. Two factors need to be considered: (1) whether the
communitys interest would be best served by making the award and, (2) whether any
bidder would be treated in an unfair manner if the award were made.
Bid Analysis:
An analysis of unbalanced bids should be properly undertaken by the BAC and TWG.
However, the final analysis should not preclude the use of engineering judgment
especially at the RPMO who will issue NOL or in some cases endorsing procurement
documents for issuance of NOL at the NPMO or MCA-Philippines.
In analyzing bids, the following should be considered:
1. Is the bid mathematically unbalanced? Are the unit bid prices in reasonable
conformance with the engineer's estimate and other bids?
2. If awarded, what effect will unbalanced bid items have on the total contract
amount?
3. If quantities are incorrect, will the contract cost be increased when the quantities
are corrected?
4. On items where the quantities may vary, will the lower bidder remain as low
bidder?
5. If the bid is unbalanced, will the unbalance have a potential detrimental effect
upon the competitive process or cause contract administration problems after
award?
In cases where obvious unbalanced bid items exist, the BAC's recommendation to award
or reject a bid needs to be supported by written justification or stating clearly in the
minutes of evaluation. The justification should include the detrimental effect or lack of
detrimental effect. However, prior to concurrence in the award of any mathematically
unbalanced bid which is not materially unbalanced, the RPMO or NPMO, as the case
maybe, should determine the reason for the unbalancing and, when warranted, take
appropriate steps to protect the project. Hence, it is important that details of the
evaluation is clearly indicated in the minutes of evaluation. The action may take the
form of concurrence or no objection whether or not to award the contract to the
submitter of the unbalanced low bid.
A unbalanced bid analysis will be performed under two circumstances:
1. If the BSPMC becomes aware of an error in a quantity of an item shown in the
bidding documents; and,
2. If an item is found to be both significant to the contract and significantly
unbalanced.
The Unbalanced Bid Analysis shall consist of the following steps:
The estimated unit price for all items identified as being significantly
unbalanced will be reviewed for correctness. Corrections will be made as
needed and the low bidders unit price will re-evaluated to determine if the item
remains significantly unbalanced.
Quantities for all items found to be significant to the contract will be checked
and verified. Quantities will be determined based upon the bidding documents
and the construction methodologies depicted in the plan. These quantities will
be used only for the purpose of performing the Unbalanced Bid Analysis.
Proposals will be considered irregular and may be rejected if the TWG or RPMO
determines that any of the unit bid prices are significantly unbalanced to the potential
detriment of the KALAHI-CIDSS project.
BAC and TWG performing bid analysis should be aware that signs of apparent
unbalancing in bidding may be an indication of more serious criminal activities such as
collusion and bid rigging. Studies of collusion and bid rigging show that such activities
are often accompanied by suspicious bidding patterns such as bids: "front loading,"
"identical bidding," "complimentary bidding."
An item will be considered significantly unbalanced if the following are observed:
1. The quotation/bid is higher by 25% against the approved engineers estimate;
or, if the quotation/bid is lower by 75% against the approved engineers
estimate.
2. During evaluation, a comparison of the calculated gross sum totals show that
the calculated gross sum for the contract low bid is found to be higher than
the calculated gross sum of another bidder, the low contract bid proposal
shall be determined to be materially unbalanced. If the calculated gross sum
of the contract low bid proposal is found to be less than the calculated gross
some of all other bidders, that bid shall be determined to be not materially
unbalanced.
3. If the initial contract low bid proposal is found to be not materially
unbalanced, the contract will be considered for award at the bid contract
amount in accordance to the Standard Specifications. The contract will be
based upon the bid amount and the quantities shown in the bidding
documents.
4. If the initial low bid contract proposal is found to be materially unbalanced it
will be considered irregular and will be rejected as non-responsive as
reasonable doubt exists that the bid does not represent the lowest cost to the
BSPMC.
5. If the initial low bid contract proposal is found to be materially unbalanced
and rejected, the BSPMC may award to the next low bid contract proposal at
the bid contract amount or may elect to reject all bids and re-let/re-bid.
Decisions will be made in the communitys interest and will consider
consequences of re-letting/re-bidding the project.
The warranty security shall be stated in Philippine Pesos, shall remain effective
during the applicability warranty period and shall be returned only after the
lapse of warranty period.
2. Liability (under contract)
The defects liability period for infrastructure projects shall be one year from
project completion up to final acceptance by the community. During this
period, the contractor shall undertake the repair works, at his own expense of
any damage to the infrastructure projects on account of the use of materials of
inferior quality within ninety (90) days from the time the BSPMC has issued
order to undertake repair. In case of failure or refusal to comply with this
mandate, the BSPMC shall undertake such repair works shall be entitled to full
reimbursement of expenses incurred therein upon demand.
Any contractor who fails to comply with the preceding paragraph shall suffer
perpetual disqualification from participating in any public bidding and his
property shall be subject to attachment or garnishment proceedings to recover
the costs. All payables of the BSPMC in his favor shall be offset to recover the
costs.
3. Sanctions against Bidders
3.1. The BSPMC being the representative of the barangay as the lowest political
structure in the government should impose administrative penalties to the
prospective bidders. The sanctions of one (1) year suspension for the first
offense, suspension of two (2) years for second offense from participating in
the public bidding process as well as disqualification from further participating
in the public bidding being undertaken by the project, for the following
violations:
2 Submission
of
eligibility
requirements
containing
false
information or falsified documents.
3
Submission of Bids that contain false information or falsified
documents, or the concealment of such information in the Bids in
order to influence the outcome of eligibility screening or any
stage of public bidding.
4 Withdrawal of a bid, or refusal to accept award, or enter into
contract with the BSPMC without justifiable cause, after he had
been adjudged as having submitted the Lowest Calculated
Responsive Bid.
5
Refusal or failure to post the required performance security
within the prescribed time.
6 Termination of the contract due to the default of the bidder.
7 Any documented unsolicited attempt by a bidder to unduly
influence the outcome of the bidding in his favor.
8 All other acts that tend to defeat the purpose of the competitive
bidding, such as an eligible contractor participating in the pre-bid
conference which does not buy bid documents and contractors
habitually withdrawing from bidding or submitting letters of nonparticipation for at least three (3) times within a year, except for
valid reasons.
3.3
3.4
3.5
Listed below are some of the common mistakes that the BSPMC may commit
and must be address by the concerned ACTs or Procurement Officers to avoid
penalties and sanctions.
Under the Local Bidding/Shopping Method
a. Sets of Canvass Form were served or given to only one (1) or two
suppliers.
b. Opening of canvass without proper quorum of the BAC.
c. The awarding of contract or Purchase Order (PO) with only one (1) or two
(2) canvass received during the opening.
d. Payment was made before the delivery of materials and works.
e. Non-observance of the penalty to be imposed to supplier/contractor for
delayed delivery of materials and works.
f. Payroll padding of Labor payment.
g. Favoring supplier or contractor.
h. Awarding contract without posting the required performance security.
i. Purchasing without following our prescribed procurement method and its
detailed procedures.
ON
COMMUNITY
PROJECTS
Incessant price increases maybe experienced anytime and may have effect to approved
community projects. These include prices of construction materials resulting to high
quotations/bids of suppliers/contractors exceeding the programmed cost. The 5% markup in the estimates and 10% contingency costs may not be able cover such escalation.
To somehow address the above, a revised the readiness filter replacing the procurement
requirements into a procurement action plan (PAP) to eliminate cases on nonconformance of suppliers when the purchase order is served. This is effective when the
procurement benchmark/timeline (within 7-9 calendar days) is observed when shopping
for goods.
For shopping of works, bidding of goods and works, that will need 27-35 calendar days
to complete the procurement process that are affected by price escalation and the
resultant quotations or bids exceeds the approved estimated cost, automatic rebidding should NOT be the immediate action. There is a need to review whether the
bids are reasonable, i.e. within market ranges. If the BAC and TWG are convinced that
the prices are within market ranges and that the increase is based on the current trend,
the following shall be undertaken to augment the difference:
i. Use the savings/balance from other packages (if there are);
ii. Use the allotted contingency;
iii. If there are no savings/balances from other package/s and no allotted
contingency or if the contingency is not enough to cover the deficit, supplement
the budget by sourcing out additional LCC;
iv. If no LCC is produced, the last resort will be to reduce the scope of works to
fit within available budget. In reducing the scope of works below are suggested
considerations:
a. For buildings: Deletion of painting works, amenities such as chairs
and tables or other possible items that will not affect stability of the building;
b. For Roads: Reduction of the physical length may be necessary or
deletion of items of works that may be covered by future operation and
maintenance like provision of Item 201 (Aggregate Base Coarse) if Item 200
(Aggregate Sub-Base Coarse) will be provided, Item 311-Portland Cement
Concrete Pavement (PCPP), Item 504 (Grouted Riprap) in non-critical sections,
etc
c. For Water System: the engineer/s to review the hydraulic analysis
to check possible reduction of pipes that were overly designed and possible
reduction of overly designed reservoir or other structures, otherwise, increase
labor counterpart contribution; and,
d. For other type of community projects where there are no scope of work/s
to be reduced, reduction of programmed labor to be paid is
recommended.
It is reiterated that whenever there is reduction in scope of works, it should be
properly deliberated with the Barangay Assembly for transparency
purposes. The community must also agree to shoulder reduced scope of works as
part of the operation and maintenance activities. It should be considered that
25
The evaluation mentioned is based on the process in checking the required Technical, Financial and Legal documents and
other requirements indicated in the invitation for bids.
Item no.
Description
Qty
Unit
Unit
Price
Total
102
6,762.39
Cu.m.
70.39
476,004.63
105
Sub-Grade Preparation
9,812.00
Sq.M.
14.69
144,138.28
200
1,417.80
Cu.m.
225.81
320,153.42
201
Total
1,471.00
Cu.m.
253.36
372,692.56
1,312,988.89
The above data can be linked to the abstract of bids from the PCPP. Since the above
data are fixed and to avoid retyping during the evaluation, it is suggested that during
the programming the abstract of canvass and abstract bid form should prepared. It can
also be copied from the file to be uploaded thru the KC yahoo group
(superries@yahoo.com) 26 used by the project staff.
The second column is the bid/quotation offered by the contractor/supplier (as the case
maybe) with 4 sub columns namely: Unit Price, Amount, Type of Bid Security and
Amount of Bid Security. Below is the cut out columns and rows:
ABC DEVELOPMENT CONSTRUCTION
Bid Security
Unit price
Amount
Type
Amount
47.36
320,250.00
10.86
106,558.32
280.42
397,579.48
288.47
424,339.37
Cash
12,500.00
1,248,727.17
The figures found under the column amount was easily be taken using the excel formula
by pressing the equal sign (=) in each cell then multiplying the quantity (from the
PCPP) times the unit price in each row then press enter.
The third column is the cost analysis with 3 columns namely: within or above budget,
Percentage (cost difference) and Remarks as shown below:
COST ANALYSIS
Within or Above
Budget?
Percentage (Cost
Difference)
Remarks ( in
terms of cost)
Within Budget
48.64%
Responsive
Within Budget
35.27%
Responsive
Above Budget
Above Budget
-19.47%
-12.17%
Not Responsive
Not Responsive
Within Budget
5.15%
The result in each column has formula to automatically state whether it is within or
above budget, Percentage difference based on the approved cost and the remarks will
say if each item cost is responsive or not in terms of cost. It is however clarified that
the term responsive or not responsive as being evaluated in the abstract
sheet/form is only limited to the cost and not pertaining to the whole
26
evaluation process. It is further clarified that when we say RESPONSIVE, to mean that
the solicited bid is determined to be in substantial conformance with the conditions,
completion or delivery requirements, and specifications detailed in the invitation-to-bid
(ITB).
For better understanding of the formula, please proceed to the example presented and
click in each cell. The formula will be shown what column and row is involved. There are
limitations however in cases where a blank cell is not filled up especially the unit price.
If this is the case, the answer could either be error or may accept the formula and will
show a positive result which is wrong!
Description
Qty
Unit
Unit
Price
Total
Unit
price
Amount
COST
Bid Security
Type
Amount
ANALYSIS
Within or
Above
Budget?
Percentag
e (Cost
Difference
)
Remarks
Selected
Borrow
335
cu.m.
650
217,750.00
575.00
192,625.00
Within Budget
13.04%
Responsive
Ready Mixed
Aggregates
(Item 201)
1630
cu.m.
800
1,304,000.00
750.00
1,222,500.00
Within Budget
6.67%
Responsive
77
cu.m.
700
53,900.00
770.00
59,290.00
Above Budget
-9.09%
Not Responsive
139
cu.m.
850
118,150.00
1,450.00
201,550.00
Above Budget
-41.38%
Not Responsive
36
pcs
850
30,600.00
1,750.00
63,000.00
Above Budget
-51.43%
Not Responsive
1260
bags
230
289,800.00
240.00
302,400.00
Above Budget
-4.17%
Not Responsive
230
20
18
30
8
pcs
kilos
kilos
kilos
kilos
315
70
60
60
60
72,450.00
1,400.00
1,080.00
1,800.00
480.00
130.00
90.00
85.00
85.00
88.00
29,900.00
1,800.00
1,530.00
2,550.00
704.00
Within Budget
Above Budget
Above Budget
Above Budget
Above Budget
142.31%
-22.22%
-29.41%
-29.41%
-31.82%
Responsive
Not Responsive
Not Responsive
Not Responsive
Not Responsive
pcs
325
2,600.00
300.00
2,400.00
Within Budget
8.33%
Responsive
2,080,249.00
Within
Budget
0.66%
3
4
5
6
7
8
9
10
11
12
Washed
Sand
Washed
Gravel (G-1)
24" RCPC
Portland
Cement
10 MM RSB
#16 Tie wire
3" CWN
4" CWN
1 1/2" CWN
11/4 Thick
Ord.
plywood
Total
2,094,010.00
Managers
Check
20,805.00
Items
No.
1
2
3
4
Description
Selected
Borrow
Ready Mixed
Aggregates
(Item 201)
Washed
Sand
Washed
Gravel (G-1)
Qty
Unit
Unit
Price
335
cu.m.
650
1630
cu.m.
800
77
cu.m.
700
139
cu.m.
850
24" RCPC
36
pcs
850
Portland
Cement
1260
bags
230
10 MM RSB
230
pcs
315
20
kilos
70
3" CWN
18
kilos
60
10
4" CWN
30
kilos
60
11
1 1/2" CWN
kilos
60
12
11/4 Thick
Ord.
plywood
pcs
325
Total
Unit
price
Amount
217,750.00
450.00
1,304,000.00
760.00
53,900.00
800.00
61,600.00
118,150.00
1,200.00
166,800.00
30,600.00
1,500.00
54,000.00
289,800.00
250.00
315,000.00
72,450.00
165.00
37,950.00
1,400.00
104.00
2,080.00
1,080.00
75.00
1,350.00
1,800.00
75.00
2,250.00
480.00
75.00
600.00
340.00
2,720.00
2,600.00
2,094,010.00
Bid Security
Type
Amount
150,750.00
1,238,800.00
Managers
Check
20,339.00
2,033,900.00
COST
Within or
Above
Budget?
ANALYSIS
Percentage
(Cost
Difference)
Remarks
Within Budget
44.44%
Responsive
Within Budget
5.26%
Responsive
Above Budget
-12.50%
Not Responsive
Above Budget
-29.17%
Not Responsive
Above Budget
-43.33%
Not Responsive
Above Budget
-8.00%
Not Responsive
Within Budget
90.91%
Responsive
Above Budget
-32.69%
Not Responsive
Above Budget
-20.00%
Not Responsive
Above Budget
-20.00%
Not Responsive
Above Budget
-20.00%
Not Responsive
Above Budget
-4.41%
Not Responsive
Within Budget
2.96%
__________________________ ________________________
BAC Member
BAC Member
_________________________
BAC Chairperson
___________________________
BSPMC Chairperson