David Rose Final Design Report

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 99

Design Report

Caribbean Development Bank


&

Government of Guyana
Basic Needs Trust Fund 7th Programme
Contract No. CA 124/GUY

Provision of Design & Supervision


Services for the Rehabilitation of
Community Roads within Region No. 3 & 4
Final Design Report
For
David Rose Street, Bagotville, West Bank Demerara

16th September 2015

Caribbean Engineering & Management Consultants, Inc.


Lot 117, John Smith Street, Campbellville, Georgetown, Guyana, South America
Tel # - (592) 227-0481, 226- 2773, 226-2758. Fax (592) 226-3930

Executive Summary
This report covers the final design of David Rose Street, Bagotville, West Coast Demerara which was identified by
Basic Needs Trust Fund (BNTF) for rehabilitation works under the BNTF Seventh Programme funded by the
Caribbean Development Bank (CDB) and Government of Guyana (GoG). This final design encompasses field
investigations inclusive of in-situ California Bearing Ratio (CBR) tests and engineering surveys. Condition surveys of
the two culverts were also conducted and proposed rehabilitation works are also presented in this report.
The pavement design for this project is based on the American Association of State Highway and Transportation
Officials (AASHTO) Guide for Design of Pavement Structures (1993). Flexible pavements were considered based on
the existing conditions, available materials, practicality and cost effectiveness for pavement rehabilitation and
reconstruction. The material selection, constructability, flexibility of future pavement rehabilitation, upgrades and long
term durability have also been taken into consideration during the pavement selection process. Based on the 24
hours traffic study, the projected traffic over the 15-year design life was less than 50,000 ESALs for this street. As
such, the minimum design traffic loads of 50,000 ESALs were used in the design as recommended in the AASTHO
Guide.
Based on our visual assessment, pavement testing and geotechnical investigation, pavement sections were
noticeably deteriorated with potholes, depressions and waterlogged. As such, rehabilitation strategies were proposed
for the various pavements. The works generally consist of rehabilitating the existing base course with white
sand/sand clay and crushed stone and sealing of the roads with a layer of asphaltic concrete. The western section of
the street will require full construction from sub-grade to wearing course.
Reinforced concrete head and wing walls are proposed at the entrance and also for the Glasgow road intersection.
Head and wing walls are proposed at the intersection since the roadway width is narrow and will continue to get
narrower if headwalls are not installed. All roadside drains are to be either de-silted or reshaped as appropriate.
Based on the calculated quantities and other estimated costs a final sum of US$178,949(GY$36,684,537) was
computed for construction works which is 99% of the total allocated budget of the project.
Utilities companies were also notified and provided feedback on existing water lines and wires/cables. The
construction phase will be completed within four (4) months. A Gantt chart of the consultants schedule is also
provided in
Appendix 7.

Table of Contents
Executive Summary .......................................................................................................................................................1
1.0

Introduction .......................................................................................................................................................1

2.0

Project Background...........................................................................................................................................2

2.1

Historical and Physical Profile ......................................................................................................................2

2.2

Demographics ..............................................................................................................................................3

2.2.1

Economic Profile ..................................................................................................................................3

2.2.2

Social Profile ........................................................................................................................................4

2.2
3.0

Environmental and Social Assessment ........................................................................................................6


Final Design ......................................................................................................................................................8

3.1

Condition Surveys ........................................................................................................................................8

3.2

Design Approach & Proposed Design ........................................................................................................10

3.2.1

Methodology...........................................................................................................................................10

3.2.2

Materials Selection .................................................................................................................................12

3.2.3

Traffic Demand and Loading ..................................................................................................................13

3.2.3

Geotechnical Investigation .....................................................................................................................13

3.2.4.1

Test Pits & Boreholes ....................................................................................................................13

3.2.4.2

Dynamic Cone Penetrometer (DCP) .............................................................................................14

3.2.5

Road Structure and Drainage.................................................................................................................14

3.2.6

Road Marking & Signs............................................................................................................................14

3.3

Proposed Design ........................................................................................................................................15

3.3.1

Geometric Design ..............................................................................................................................15

3.3.2

Design Criteria .......................................................................................................................................17

3.3.2.1

Estimate ESAL AASTHO 1993...................................................................................................17

3.3.2.2

Subgrade Resilient Modulus..........................................................................................................18

3.3.2.3

Pavement Structural Number ........................................................................................................18

3.3.3
3.4

Proposed Scope of Works......................................................................................................................19


Recommended Design ...............................................................................................................................20

3.5 Cost Estimate & Procurement ...........................................................................................................................21


4.0

Limitations and Construction Issues ...............................................................................................................22

Appendices ..................................................................................................................................................................23
Appendix 1 Design Calculations & Condition Survey ............................................................................................24
Appendix 1A Traffic Survey & Analysis (Estimated ESAL Value .........................................................................25
Appendix 1B Dynamic Cone Penetration Test (DCP) & California Bearing Ratio ...............................................26

Appendix 1C Existing Pavement Profile & Test Pits............................................................................................27


Appendix 1D AASTHO 1993 - Algorithm Analysis (Structural Number) ..............................................................28
Appendix 1E Interlayer Checks ...........................................................................................................................29
Appendix 2- Photographs ........................................................................................................................................30
Appendix 3- Final Design Drawings.........................................................................................................................33
Appendix 4-Final Estimate.......................................................................................................................................34
Appendix 5-Correspondences .................................................................................................................................35
Appendix 6-Framework for Environmental and Social Assessment ........................................................................36
Appendix 7-Consultant Work Schedule ...................................................................................................................38
List of Tables
Appendices

List of Figures
Figure 1-Showing a Satellite Image of the Project Area at an Altitude of 3781 ft...................................................2
Figure 2-Deteriorated Roadway Chainage 0+420m .................................................................................................. .8
Figure 3-Deteriorated Roadway- Chainage 0+280m................................................................................................. .8
Figure 4-Deteriorated Roadway ,Chainage 0+690m ................................................................................................. .9
Figure 5-Glasgow Road Intersection,Chainage 0+0590m ....................................................................................... .9
Figure 6- Showing gradient of finished road and clay shoulders..........................................................................15
Figure 7- Glasgow Intersection: Deteriorated carriageway, Chainage 0+615m ...................................................31
Figure 8- Deteriorated Carriageway with minor depressions, Chainage 0+690m ................................................31
Figure 9- Deteriorated Carriageway with depressions, Chainage 0+500m ...........................................................31
Figure 10-Test Pit at Chainage 0+710m ...................................................................................................................32
Figure 11-Garbage Along Side Roadway ................................................................................................................ .32
Figure 12-Deteriorated Carriageway showing large depressions .........................................................................32

List of Tables
Table 1-Diversification of skills amongst residents..................................................................................................3
Table 2-Population Disaggregated by sex (Source La-Grange/Nismes NDC) ........................................................4
Table 3-Social Development Profile to produce more marketable residents. ........................................................5
Table 4-Pavement Design Inputs ..............................................................................................................................17
Table 5-Proposed Scope of Works ...........................................................................................................................19
Table 6-Section 1:Chainage 0+000m - 0+615m (Road width 3.65m / 12ft.) ...........................................................20
Table 7-Section 2:Chainage 0+615m- 0+690m (Road width 2.43m / 8ft.) ..............................................................20
Table 8-Section 2:Chainage 0+690m - 0+745m (Road width 2.43m / 8ft.) .............................................................20
Table 9 - Summary of Final Estimate .......................................................................................................................21

Appendices
Appendix 1Design Calculations & Condition Survey
Appendix 1A Traffic Survey & Analysis (Estimated ESAL Value
Appendix 1B Dynamic Cone Penetration Test (DCP) & California Bearing Ratio (CBR)
Appendix 1C Existing Pavement Profile & Test Pits
Appendix 1D AASTHO 1993 - Algorithm Analysis (Structural Number)
Appendix 1E Interlayer Checks
Appendix 2- Photographs
Appendix 3- Final Design Drawings
Appendix 4-Final Estimate
Appendix 5-Correspondences
Appendix 6-Framework for Environmental and Social Assessment
Appendix 7-Consultant Work Schedule

1.0 Introduction
Caribbean Engineering and Management Consultants Inc (CEMCO) was engaged by the Caribbean Development
Bank (CDB) to produce engineering design, construction drawings and supervisory services for the improvement of
David Rose Street, located in Bagotville, West Bank Demerara, Region 3. The length and width of this street is 745
meters and 3.7 meters respectively. The roadway will directly benefit approximately 850 residents in the Bagotville
community.
The allocated CDB budget for end of construction cost is US$179,080 (GY$36,711,400) with a total budget utilization
of US$178,949(GY$36,684,537).
CEMCO is tasked with conducting all investigations and produce engineering designs and estimates for constructing
this roadway and supporting infrastructure within the Clients budget. Tender Documents is a deliverable of the Final
Design Phase.
An initial site visit was made to the sites by representatives of BNTF, [Mr. Utoh Project Engineer] and CEMCOs
design and supervision team, [Team Leader, Mr. P. Bonar Chief Engineer and others] and members of the
respective communities on the 23rd June 2015. Surveys and field work started on the 24th June 2015.
This report presents the findings of our assessment of the roads (condition survey), the sub-surface investigation and
analysis, the plans, profiles and cross sections obtained from the surveys, the required design interventions, the
proposed design for the pavements and associated infrastructure as well as final cost estimates and
recommendations.
This Report is intended to provide the Client with all the necessary information required to make an informed decision
on the preferred design option to be pursued as well as the scope of intervention and prioritization.

2.0

Project Background
2.1 Historical and Physical
Profle

Bagotville is located on the West Bank of Demerara; Administrative Region No. 3: approximately five (5) miles (8
Kilometres) from Georgetown and is accessible via the Demerara Harbour Bridge. In 1848 a group of slaves bought
the village from a proprietor known as Mr. Bagot, hence the name Bagotville. Residents normally hold an annual
village day fair to showcase cultural food, games and to appreciate a sense of community unity.
Bagotville is bordered by La-grange to the south, Nismes to the north and Demerara River to the east. The
community is divided into residential housing and farmlands. It is accessible at all times by buses which traverse the
main roads from early in the morning to late in the evenings throughout the year. Most of the houses within Bagotville
are comprised of timber and concrete structures; that have readily access to potable water, electricity and garbage
disposal services (NDC and Private Sectors). Community Streets in Bagotville consist of a flexible pavement design
with a Double Bituminous Surface Treatment.

Figure 1-Showing a Satellite Image of the Project Area at an Altitude of 3781 ft.

Approximate GPS Coordinates (UTM)


Starting Point UTM Coordinates:
E 0367211, N 0747171 (Intersection at Public Road)
Glasgow Road Intersection UTM Coordinates:
E 0366614, N 0747231
Ending Point UTM Coordinates:
E 0366483, N 0747233
2

2.2

Demographics

2.2.1

Economic Profle

Based on the stakeholders meeting held on the 20th June, 2014 it was identified that most of the working population
are involved the following sectors:
Earning/Living

Occupation/Skills

Skills Needed

Men
Qualified

-Teachers
-Private and Public Sectors Employees
Craftsmen e.g.
-Carpenters

Skilled

-Welders
-Electricians
-Masons)

Unskilled

-Farmers

-Hydroponics

-Self-employed

Women
-Teachers
Qualified

-Nurses,
-Private and Public Sectors Employees

Skilled
Unskilled

-Self-employed

-Sewing

-Housewives

-Catering

Table 1-Diversification of skills amongst residents


The unemployment rate in the community is high even though farming is the major economic activity within the
village. Farmers usually take their produce to neighbouring markets to wholesale/retail; this in turn means residents
would have to travel to nearby markets such as Vreed-en-Hoop (two miles) away or utilize markets in the capital city
of Georgetown e.g. La Penitance, Bourda and Stabroek when travelling home after work. Residents also indicated
that persons would also seek employment outside of Bagotville in Georgetown and as far as the Hinterland and
would periodically visit/send remittance to family members.
The 2006 Household Income and Expenditure Survey (HIES) indicated in Region #3; Essequibo Islands/West
Demerara: that forty percent (40%) of the population currently lives in poverty.

2.2.2

Social Profle

Population
During the Stakeholders meeting on the 20th June,2014 the following information was submitted by the LaGrange/Nismes Neighbourhood Democratic Council in relations to David Rose Street.

The population is approximately 850 residents (Males 390, Females 460)

Number of Households 99

Approximately twenty-four percent (24%) or 200 persons of the population are children under the age of 14
years.

Approximately one percent (1%) of the households are headed by a single parent, who are mostly women.
Age

Males

Females

Adults ( 25 years)

140

200

Youths (14-24 years)

131

179

Child ( 14 years )

119

81

Sub-Total

390

460

Total

850

Table 2-Population Disaggregated by sex (Source La-Grange/Nismes NDC)


Residents within Bagotville have access to potable water, electricity and garbage disposal services via NDC and the
private sector; however only fifty percent (50%) of the households have indoor toilets.
The ethnic composition of this community is approximately:

African

- 90%

East Indian

- 10%

Some of the Community Infrastructure/ Social Services availability to residents in Bagotville are listed below:
Nursing/Medical Station/ Clinic

- NO

Childcare Centre

- YES

Schools (Nursery, Primary & Secondary)

- YES

Library

- YES

Police Station

- YES

Womens Shelter

- NO

Children Services

- NO

According to the La-grange/Nismes NDC all of the social services within the community are adequately equipped and
staffed to meet the needs of the community. Residents have also indicated their availability to participate in
community
works from which youths can benefit; whether it be paid work or skills development.
Sex

Needs

Males

Recreational Facilities

Challenges

The males will be more


socially rounded.
Do not have access to

Skills Training
Females

Impact

training facilities

-Homecare

Becoming

equipped

with

necessary skills to make

-Parenting

themselves marketable.

-Sewing
Table 3-Social Development Profile to produce more marketable residents.

2.2 Environmental and Social Assessment


To achieve the main objectives of this consultancy TOR, the following methodology has been used thus far to conduct
the Environmental and Social Impact Assessment for the selected roads and to prepare the initial Environmental
assessment (ES).This has provided information that is required to identify the issues and recommendations for the
proposed roads respectively.
The pertinent environmental and social issues regarding environmental impacts of the project, establishing the need
for the project, specific features of the rehabilitated roadway as well as willingness of community to support project
and dealing with temporary inconveniences of such works, are based largely on views expressed by stakeholders in
the specific areas where the roads are to be constructed. On June 23rd 2015, a site inspection of the David Rose
Street, Bagotville site, was undertaken by representatives of BNTF and CEMCO Inc. to discuss the proposed roads
and future implications with community residents, NDC and PMC members. The stakeholders (villagers) were
engaged during the Initial BNTF/Consultant visit where detailed discussion based on critical issues highlighted in the
TOR was undertaken. The key points listed below guided the discussions with the community.
1. Description of Project Funding activities.
2. Description of field and design works to be carried out as part of consultancy.
3. Description of likely designs.
4. Community involvement in discussion regarding specific features of the roadway.
5. Discussion of mitigation measures to be implemented through the contract documents and technical
specification as well as supervision of project.
6. Discussions with community to garner their views on environmental impacts such as dust, noise, oil spills etc.
Recommendation for best management of these impacts.
7. Identification of point person to provide feedback and liaison services for the community.
Key issues identified by stakeholders in Bagotville in relation to David Rose Street:
1. David Rose Street has 1 private school and approximately 5 shops, residents raised concerns whether these
facilities will be affected and requested that access be maintained at all times during construction.
2. Speed humps should be included in designs.
3. Area is prone to flooding and a culvert located in the last street (Glasgow Road Intersection) is sinking and
should also be fixed.
4. Residents should be consulted to fill vacancies for labourer positions during construction.
5. Barriers should be placed on the road to prevent Puran Bros waste collection and other larger trucks from
accessing the area.
6. Road should be built to accommodate the extensive thru - traffic.
6

7. Workers and contractors should adhere to safety practices.


8. Will de-silting of canal be part of project?
9. Residents recommended that parking on the roadway should be discouraged.
In addition an Environmental Reconnaissance focused on the following key areas:
1. Proximity of schools, places of worship and other social services to the existing roadways.
2. Proximity of residences to the roadway to be rehabilitated and likely social impacts.
3. Dust noise and other construction phase impacts.
4. Identification of alterative diversions for traffic where applicable.
5. Best construction methods to allow safe access of public during construction.
6. Placement of construction signs and other safety equipment.
7. Waste management practices during construction.
8. Proximity of waterways to the site; is construction likely to impact water quality? Best construction methods
to deal with such impacts.
9. Possibility of project affecting flora and fauna.
10. General public safety.
This process will underpin the success of the overall project through contributing to build a consensus for the
recommended roadway design and through recommendations for best construction practices to minimize
environmental impacts. In keeping with the TOR, an Environmental Management Guideline document will be
prepared that would deal with the following.
1. Identification of environmental and social impacts of the project.
2. Best Construction Practices/Recommendation to minimize Environmental and Social Impacts
3. Monitory and Management recommendations for Construction Phase Impacts.
4. Reporting Framework for environmental monitoring.
5. Measures to evaluate environmental performance and compliance.
The Environmental Management Recommendations and guidelines will follow international best practices and will
meet or exceed EIA guidelines outlined by the Guyana EPA and the Project TOR.

3.0

Final Design

3.1
Surveys

Condition

Chainage 0+000m to 0+590m


The pavement between 0+000m to 0+590m is a Double Bituminous Surface Treatment (DBST) and a crushed stone
base which is found to be in a poor condition with medium to high severity of pavement distress. The subgrade
consists of an average of 200mm white sand and 125mm white sand/sand clay. The pavement distresses
predominately found as depressions and potholes. HDPE culvert exists at the entrance but doesnt have headwalls
nor wingwalls and there is a failed timber revetment at this location.
Drains appear to be partially functioning.
There are currently one roadside shop and an abandoned car which needs to be removed to accommodate scarifying
and grading of road materials.

Figure 2-Deteriorated Roadway Chainage 0+420m

Figure 3-Deteriorated Roadway- Chainage 0+280m

Chainage 0+590m to 0+690m


The pavement between 0+590m to 0+690m is a Double Bituminous Surface Treatment (DBST) and a white
sand/sand clay base which is found to be in a poor condition with high severity of pavement distress. The subgrade
consists of an average of 250mm white sand. There is no crusher run base existing. The pavement distresses
predominately found as depressions and potholes. Steel pipe culvert exists at chainage 0+600m but doesnt have
headwalls nor wingwalls and the road width is narrow over the culvert.
Between chainage 0+690m to 0+745m there isnt any existing road materials hence full road construction has to be
done.
Drains appear to be partially functioning.

Figure 4-Deteriorated Roadway ,Chainage 0+690m

Figure 5-Glasgow Road Intersection,Chainage 0+0590m

3.2 Design Approach & Proposed Design


3.2.1 Methodology
1. Field Investigation and surveys were conducted over the period 24th June 2015 to 30th June 2015.
To collect inventory information related to the roadway, lengths, widths, existing cross sections,
grade profiles, and structures type and sizes, drainage, safety issues and data related to any
special use issues that should be attended to during road design. Information of the direct
beneficiaries and businesses along the three roadways were also collected.

Geotechnical Investigation to obtain soil strata and CBR of sub grade.

The existing condition of the timber bridge and existing HDPE pipe culvert and the need for
rehabilitation works.

Continuous 24 hours traffic survey.

2. Using the results of the data obtained pavement and geometric design drawings were done using the
American Association of State Highway and Transportation Officials (AASHTO) Guide for Design of
Pavement Structures (1993). This section incorporates the following parameters:

Design Variables (traffic; time constraints; reliability and environmental impacts)

Performance criteria (level of service expected during design life)

Material Properties (Load bearing characteristics of the various pavement materials and supporting
road bed soils)
Flexible pavements were considered based on the existing conditions, practicality and cost effectiveness for both
pavement rehabilitation and widening.
Under AASHTO 1993 pavement design protocol, the Design Structural Number (SNDesign) for every pavement is
determined to estimate the viability of the rehabilitation strategy over the design life of the pavement for a known
Equivalent Single Axle Load (ESAL). SNDesign for the various pavements is calculated using the following formulation:

.eq (1)
Where i = every layer in the proposed structural layer of the pavement after rehabilitation;
n = Number of material layers;
ai = Structural Coefficient of ith layer;
Di = Layer thickness of ith layer; and
mi = Drainage Coefficient of ith layer.

10

The basic concept of pavement design based upon AASHTO, 1993 protocol for flexible pavements requires firstly
determining the required thickness of the pavement based upon the level of traffic. The associated performance
period is then corrected for any environmental-associated losses (Pi = Initial Serviceability = 4.5 and Po =
Terminal Serviceability = 2.0) for a suitable pavement design over a design life of the pavement, the following
equation is used
to estimate the New Structural Number (called SNNew):

.eq(2)
Where
w18 = ESAL repetitions expected during the design life;
ZR and So= Reliability and Standard Deviation of the usage of pavement and type of structure
(75% and 0.44, respectively);
SNNew = New Structural Number that the pavement must satisfy;
Pi = Initial Serviceability =4.2;
Po= Terminal Serviceability = 2.0; and
MR = Subgrade Resilient Modulus (estimated form the back-calculation protocol).
Equation 2 was developed as a regression model and is the primary flexible pavement design protocol that is used by
AASHTO, 1993 pavement design manual. It relates the ESALs to Structural Number, serviceability drop and subgrade
resilient modulus using reliability concepts. The derivation of this equation is based upon AASHTO Road test that was
performed in USA in the 1960s. For a rehabilitation strategy to be activated, the following rationale has to satisfy:

SNreq > SNeffective

eq(3)

Once the scenario presented in Eq. 2 is satisfied, a rehabilitation alternative will be chosen such that the following
condition is satisfied.
SNDes > SNReq.eq(4)
The various rehabilitation and reconstruction options being presented in the latter sections were based on the above
mentioned design criterion with the pertinent information obtained from our geotechnical investigation.
1. Design reinforced HDPE concrete culverts.
2. From the designs produced cost estimate were prepared using current prices.

11

3.2.2

Materials Selection

The following are typical materials available and used in road and highway construction in Guyana:

Bitumen: Typically imported and is used during the hot mix asphalt production.

Crushed Gravel (1st Grade Crushed Stone): Crushed stone used in road construction in Guyana comes
from the Essequibo county with the Highland natural region and is delivered to Georgetown via barges and
trucks. The use of this material as a road base or aggregate for asphaltic concrete is extensive throughout
Guyana. There are basically two types of material available, Gabbro and Granite; the former is the preferred
choice for both road base and asphaltic concrete applications. The California Bearing Ratio (CBR) for this
material ranges from 60% to 100%.

White Sand (WS): This natural sand is fine to medium grained and is readily available along the hilly sand
and clay natural region. White sand is extensively used locally for road construction and is mainly used as an
improved subgrade, drainage layer or as a component for blending with other materials to be mentioned
below.
White Sand/ Sand Clay (WS/SC): It is one of the most extensively used road construction materials
throughout Guyana. It is readily available from open pits at Timehri, East Bank Demerara. Historically the
sand clay is typically mixed with white sand in ratios of 75:25 to 60:40 depending on the plasticity derived
during material sampling and testing. The moisture content of the material can be difficult to control due to
the local climatic and ground conditions in the pits. The CBR for the WS/SC typically ranges from 25%-50%
and
the common practice is to utilize it in the base of low volume local roads and sub-base on primary roads.

12

3.2.3

Traffic Demand and Loading

The predicted loading is simply the predicted number of 80 kN (18,000 lbs) along with the ESALs that the pavement
will experience over its design lifetime, which is 15 years for this project. The traffic study was for a continuous 24
hours period which was conducted for each of the roadway. (See Appendix I). The formula below represents the
ESAL and is used in to estimate the ESAL value for each roadway (See Appendix I). AASTHO 1993 recommended,
when the ESAL value is less than the minimum value, 50,000 ESAL should be used for low volume community roads.
This scenario was applicable for David Rose Street.

..Eq(5)

Where:
ADT Annual Daily Traffic
T Percentage of Trucks
Tf Truck Factor
G (1+r)0.58y
D - Directional Distribution Factor
L - Lane Distribution Factor
Y Design Years
These pavement parameters are explained in Appendix 1.

3.2.3

Geotechnical Investigation

3.2.4.1 Test Pits & Boreholes


Several boreholes were taken on the streets identified under this project. The results of these boreholes are given in
Appendix 1C. The chip sealed (DBST) surfaces can be considered non existing since it is badly damage throughout
the entire roadway. The sub-base layers are in excess of 150 mm in thickness. Based on the material types, their
recommended structural coefficients were utilized to produce the structural design of the pavement. Test-pits were
also executed to determine the immediate and 24 hours water table. The immediate water table was recorded as
1.2 m
below the road level likewise the 24 hours depth measured as 0.7 m below the surface.

13

3.2.4.2 Dynamic Cone Penetrometer (DCP)


The U.S. Army Corps developed the DCP and the correlation between the test results (DCP index) and CBR. The
CBR value can be related to the subgrade resilient modulus relationship developed by the American Association of
State Highway and Transportation (AASHTO). The subgrade resilient modulus is essential in the AASHTO pavement
design method and could be determined by multiple methods including Benkelman Beam, DCP/CBR and laboratory
testing. The geotechnical investigation program incorporates the DCP/CBR method, coupled with AASHTO
correlation of subgrade resilient modulus is preferred. It is because Benkelman Beam testing is not possible in
severely deteriorated sections.
A total of one twelve (12) tests were conducted in the open borehole through the existing base/subbase/subgrade
layer where possible. The test results were analyzed with CBR values ranging from 2% to 11%, with an average of
4.8%. It is entirely possible that localized pockets of fill and excessive moisture have affected the test results and
such anomalies were exempted from the data set. The DCP testing results are summarized in the boreholes
summary tables and field notes are enclosed in Appendix 1C of this report. Equation (6) represents the relationship
with the CBR and DCP values and is recommended by the ARMY Corps of Engineers with respect to ASTM
D6951/D6951M.
In Situ CBR (%) = 292/ (DCP1.12) ..Eq(6)

3.2.5

Road Structure and Drainage

The existing HDPE pipe culvert at the entrance to this street will be upgraded with wing and head walls. The existing
900 mm diameter HDPE pipe will be cleaned and reused. Also, head and wing walls will be installed at the Glasgow
road intersection and the 900 mm diameter existing steel barrel pipe will be cleaned and reused. All roadside earthen
drains will be de-silted and reshaped.

3.2.6

Road Marking & Signs

This is a community access road; lane marks and edge marks will not be included in this contract except for the
junction linking the roadway with the West Bank Demerara Main Public Road (30m from the WBD Main Road).
Painting of speed humps, stop marking, stop lines and installation of STOP signs are included for installation and as
detailed on drawings.
Four (4) speed humps are included in the scope of works at chainages 0+30m, 0+245m, 0+590m and 0+615m.

14

3.3 Proposed Design


3.3.1

Geometric Design

The existing road width from 0+00m to 0+615m is 3.05m (10ft.) while 0+615m to 0+745m has an existing road width
of 2.44m. Follow field data analysis which comprised of boreholes and test pits; there was visible evidence of existing
sub base layers which allowed for the expansion of the current roadway from 3.1m to 3.67m (12ft). This expansion is
only scheduled for the first section of the roadway as this is the most trafficked region and due to the limitations of the
budget. However there will an extension of the roadway from 0+690m to 0+745m which requires full reconstruction
as there is no existing sub base layer (trial test pit dug at 0+710m only indicating clay layer); This further extension of
the 2.44m (8ft.) roadway is to incorporate a more easily flow of access to the burial ground. The entire roadway will
have a cambered of 2% to accommodate rainfall runoff and a graded shoulder slope of 3% as shown in cross
sectional figure below. For Average Daily Traffic (ADT) of 2000 to 4000 for residential access roads; a width of
3.05m 3.6m is recommended. Road widths may be reduced by 0.3m to 0.6m based on the engineers judgement
regarding space available as what was done for chainage 0+590m to 0 + 745m. (AASHTO Geometric Standards
Green Book).

Figure 6- Showing gradient of finished road and clay shoulders

15

There is currently large earthen drains located on northern side of the roadway spanning a width of 3.05m with a
slope gradient of approximately 1:2. The flow direction is from west to east and outflows into the West Bank
Demerara Public Road main drain which discharges into Canal Polder No. 1 main canal. The proposed drainage
work includes the desilting and reshaping of the drains but the depth and slope gradient will be maintained as there is
no visible signs of slope failures along the carriageway. The current width of the clay shoulders exceeds 1.22m
(4ft.) and will not present any future slippage of the roadway. At Glasgow road intersection the radius of the transition
zone was determined in relation to the width of the existing and proposed road carriageways hence for the 2.44m
width road a transition radius of 3.05m (10ft.) was utilized. Likewise a transition radius of 4.57m (15ft.) was used at
the entrance of the roadway i.e. the junction of David Rose Street and West Bank Demerara Main Public Road (The
2011 AASHTO Green Book for Geometric Standards was considered).

16

3.3.2

Design Criteria
Design parameter

Value

Initial Serviceability Index, P0

4.2

Terminal Serviceability, Pt

2.0

Total Change in Serviceability, PSI

2.2

Design Life, years

15

Reliability, R %

75

Standard Deviation, So

0.4

Subgrade Resilient Modules, MR (Mpa)

(3000) 2% CBR

Pavement Layer Coefficients


New Asphalt

0.44

Old Asphalt layer

0.25

Existing (old) base

0.08

Crushed gravel base (1st grade crushed stone)

0.141

Sand and clay sub-base layer (white sand/sand clay)

0.11

White Sand Layer

0.07

Existing Asphalt (Fair to Good condition)

0.42

Pulverized materials

0.12

Burnt Earth

0.05

Table 4-Pavement Design Inputs


Note: The Design Parameters based on Chapter 4 of AASHTO Pavement Design Guide, 1993 and the Pavement
Layer Coefficients are from AASHTO 1993 and MI-183 Adaption and Verification of AASHTO Pavement Design
Guide for Ontario Conditions. Other Pavement Layer Coefficients of local materials are based on the previous test
done.
3.3.2.1 Estimate ESAL AASTHO 1993
A 24 hours traffic survey was conducted at the entrance to David Rose Street on the 15th June 2015 and is
summarized in Appendix 1A. The 15 years design ESAL traffic analysis with an annual compound growth rate of 4%
is also presented in Appendix 1A. The design lane and directional distribution factor were taken as 100 % since the
roadway is one-carriageway with two directions of traffic: Equation 5 was utilized in the estimation of the ESAL value.
The estimated 15 years ESAL value calculated is 18,484 hence, a design ESAL value of 50,000 was used in this
design. AASTHO guide recommended that the minimum ESAL should be 50,000 for secondary community access
roads.

17

3.3.2.2 Subgrade Resilient Modulus


The subgrade resilient modulus was found to range from 2 % to 11.0 % hence, the minimum CBR value was used to
determine the Structural Pavement Number. The field testing data, test pits and calculation sheet for the CBR is
attached to Appendix 1B of this report.
3.3.2.3 Pavement Structural Number
The pavement structural number was computed as 2.25 for David Rose Street. (See Appendix 1D). The structural
number was calculated from equation 2 by a trial and error method which is presented in Appendix 1D. After the
structural numbers were generated, interlayer checks were required to estimate the minimum thickness for each
layer. Interlayer checks are enclosed in Appendix 1E.

18

3.3.3

Proposed Scope of Works

The table below highlights the proposed scope of works with alterations made to maximize the usage of the budget
without comprising the durability of the road.

Description

Comments

i.

Construction of asphalt concrete surface


and upgrade base course for the entire
roadway.

ii.

Concrete culvert head and wing walls will


be constructed at the entrance and at the
Glasgow intersection.

iii.

The width of the road is 3.67m (12ft) from


chainage 0+000 to 0+615 m and 2.44m
(8 ft) from 0+615m to 0+745m.

iv.

Full reconstruction is required


chainage 0+690m to 0+ 745m.

v.

Earthen drains will be reshaped and desilted.

vi.

Construction of clay shoulders both sides of


carriageway.

vii.

4 painted speed humps remains

from

i)

HDPE pipe at the entrance will be reused


likewise steel pipe at the Glasgow
intersection. Headwalls and wing walls at
the intersection are necessary since the
road width is extremely narrow.

ii) Test pits shows that there is existing road


material from chainage 0+ 615m to
0+690m; hence full reconstruction will not
be required.
iii) The western section the roadway width will
be constructed to an 8ft finished
carriageway and the base layer will be 10
ft because of the shoulder width and depth
of the drains. If the 12ft roadway is
maintained at this location revetment will
be necessary and will have significant cost
increase.

viii. Road markings are introduced. (e.g STOP


signs at the entrance)
Table 5-Proposed Scope of Works

19

3.4 Recommended Design


The tables below highlight the proposed road profile layers and the existing layers.

Existing Pavement Structure

Proposed Pavement Structure

Deteriorated DBST Removed

38 mm Asphalt Concrete

50 mm Crusher Run (Avg Remaining)

100 mm Crusher Run

150 mm WWS/SC(Avg Remaining)

50 mm Crusher Run (Avg Remaining)

200 mm WS(Avg Remaining)

150 mm WWS/SC(Avg Remaining)


200 mm WS

Table 6-Section 1:Chainage 0+000m - 0+615m (Road width 3.65m / 12ft.)

Existing Pavement Structure

Proposed Pavement Structure

125 mm WS/SC(Avg Remaining)

38 mm Asphalt Concrete

225 mm WS(Avg Remaining)

100 mm Crusher Run


120 mm WWS/SC(Avg Remaining)
225 mm WS(Avg Remaining)

Table 7-Section 2:Chainage 0+615m- 0+690m (Road width 2.43m / 8ft.)

Existing Pavement Structure

Proposed Pavement Structure

Clay

38mm Asphalt Concrete


100 mm Crusher Run
125 mm WS/SC(Avg Remaining)
300 mm WS(Avg Remaining)

Table 8-Section 2:Chainage 0+690m - 0+745m (Road width 2.43m / 8ft.)

Drainage & Structures


Reinforced concrete head and wing walls are proposed at the entrance and same for the Glasgow road intersection.
The 900 mm diameter HDPE pipe will be used likewise for steel pipe at the intersection. Road-sides earthen drains
will
be desilted and reshaped.

20

3.5 Cost Estimate & Procurement


The table below presents a summary of the estimated cost. Based on the calculated quantities and anticipated
variations, a cost of US$8,220(GY$1,685,000) was estimated for Preliminaries and Miscellaneous;
US$136,926 (GY$28,069,837) for Incidental Roadworks; US$4,181(GY$857,200) for Drainage Works, and
US$29,622(GY$6,072,500) for Structural and Incidentals, resulting in an overall subtotal of
US$178,949(GY$36,684,537).
The complete estimate is provided in Appendix 4.
BILL OF QUANTITIES GRAND SUMMARY
Contract Name: Basic Needs Trust Fund Seventh Programme
Contract - David Rose Street, Bagotville, WBD
Contract No.:
Amount
(USD)

General Summary
Bill No.A: Preliminaries

8,220.00

Bill No. B : Incidental Road Works

Amount
(GYD)
1,685,000.00

136,926.00

28,069,837.00

4,181.00

857,200.00

29,622.00

6,072,500.00

Sub-total of Bills

178,949.00

36,684,537.00

CBD's Allocated End of Construction Cost

179,080.00

36,711,400.00

Bill No. C: Drainage Works


Bill No. D: Structures and Incidential Works

Note: 1 USD = 205 GYD

Table 9 - Summary of Final Estimate

21

4.0

Limitations and Construction Issues

There will be several issues which will arise during the construction phase; some of which are listed below.

During construction of the reinforced concrete headwalls and wing walls of the culvert there will be minor
inconvenience caused from the rerouting of traffic at the junction of David Rose Street and WBD Public
Road i.e. there will be one way flow of traffic at the head of the roadway during construction.

Structures to be removed include a side shop located at 0+015m and an abandoned car on the edge of the
roadway.

GWI The underground water utility line will be temporarily relocated to remove the possibility of rupturing
any pipelines which may cause further distress to residents. A lump sum (Bill D-Structures; Item D1.2.1) has
been included in the Final Estimates to accommodate for this.

GPL- The existing power utility poles are located within a close proximity of the proposed roadway.

Most of the residential entrances are timber bridges and out of the proposed road carriageway hence no
problems during construction.

22

Appendic
es

23

Appendix 1 Design Calculations & Condition Survey

24

Appendix
1A
Traffic Survey & Analysis (Estimated ESAL Value)

25

Project Name:
Client
Description:
Prepared By:
Checked By:
Reference:

Community Roads Improvement


BNTF - CDB & GoG
Estimate ESAL - David Rose Street, Bagotville, WBD
K. Rajana
P. Deodat
AASHTO Guide for Design of Pavement Structures 1993

ESAL Definition
The 1993 AASHTO Guide for Design of Pavement Structures states that "the damage effect of the passage of an axle of any mass (commonly called load) can be represented by a number of 18-kip equivalent single axle loads or ESAL's."
Variables in ESAL Calculations
According to the AASHTO Guide, several variables can impact the load equivalency factors and therefore will impact the calculated ESAL's. The variables are: pavement type (rigid or flexible), thickness, and terminal serviceability used for design. This spreadsheet program only calculates ESAL's
for flexible pavements. The thickness and terminal serviceability variables are accounted for at the bottom of the AASHTO ESAL calculation sheets with notes on suggest input values for various applications.
Axle Load and Type
Vehicles - (24 Hrs Traffic)
Passenger Cars
Passenger Buses
Small Canters/Vans/ Jeeps / Pick Ups
Large Canters
Sand Trucks
Garbage Trucks (Full)

West to East

East to West

Axle 1 (k)

46
12
6
0
0
1

50
10
6
0
0
1

2S
2S
2S
2S
8S
8S

Axle 2 (k)
2S
4S
4S
4S
24 T
24 T

Gross
Weight

Axle 3 (k)
S
4
S
6
S
6
S
S
32
S
32
Comments on Variables

Equivalency Factor
Axle 1

Axle 2

0.002
0.002
0.002
0.002
0.613
1.56

0.002
0.02
0.02
0.02
1.08
1.23

Axle 3

Two-Way Average Daily Traffic

ADT

132

Typical ranges are 50-800 vehicles for residential streets, 700-5,000 vehicles for collectors, and 3,000-50,000+ vehicles for arterials.

Number of Years

YRS

15

Pavement designs typically have a design life ranging from 15-30+ years.

Growth Rate (%)

GR

Growth rates typically range from 1 to 3 percent per year; this growth rate is applied to all traffic, not just trucks.

Growth Factor

1.40666296

Total Growth Factor

GF

20.02358764

Directional Distribution Factor (%):

DD

100

A 50-50 split between traffic going in each direction on the roadway typically is used (e.g., a Directional Distribution of 50%). In some cases, however, a difference in traffic patterns
may necessitate a directional distribution other than 50%, such as a particular area generating more trips over a long period of time than the number of trips that it attracts. AASTHO
recommended that the factor can vary from 30 % to 70 %. Since the vehicle will be traversing on the same wheel path most of the time (road with 12 ft), the factor is taken as 100%.
Design lane distribution refers to the percent of vehicles in one direction that use one lane of the roadway the most. For example, on 4-lane divided highways (e.g., 2 lanes in each
direction), 90% of the traffic on average uses the right (or driving lane) and 10% of the traffic uses the left lane (or passing lane). Indian Roads Congress (IRC - 37-2001)
recommended that for a single laneroad, the factor is 1; for a two -lane road with single carriagewa, the factor is 0.75, for a four lane single carriageway it is 0.40. Clause 2.2.1 in the
AASTHO under Taffic provide a table to estimate the Lane Factor.

Design Lane Distribution Factor (%)

LD

100

Percentage of Trucks (%)

TP

1.515151515

Truck Factor (ESALs/Truck)

Final Design ESAL's

TF

1.2

Function of the Growth Rate and the design live of the pavement.

Typical ranges include 1-3% for residential streets, 3-15% for collectors, and 5-30% for arterials.
The truck factor characterizes the average number of ESALs per truck. FHWAs Traffic Monitoring Guide (TMG) provides guidance on such characterizations. Vehicles such as
motorcycles, passenger cars, vans and pickup trucks have negligible impact on the truck factor. Buses can truck factors ranging from 0.57 ESALs/bus for a typical-length, empty bus to
up to 6.17 ESALs/bus for articulated buses with all seats filled and standing passengers. Similarly, the truck factor for trucks can have a very large range, depending on configuration and
weight restrictions. Passenger car equivalent for trucks = 1.2 (Which was used for WCD and EBB Road esign Project since Since overloaded truck is common and was encountered
during the axle load tests, an average truck factor of 1.2 ESAL/truck is utilised to address this issue.). The safety factor incorporated would also future truck upgrades to satisfy the
request of local residents.

18,484

Since the ESAL Value is less than the minimum recommended by AASTHO 1993, 50,000 ESAL will be use in this design
Recommended ESAL

50,000 (50,000 ESALs for low volume access roads)

Appendix
1B
Dynamic Cone Penetration Test (DCP) & California Bearing Ratio

26
Name
of

Project:

BNTF
Roads
Upgrade
Project
Road:
David Rose Street, Bagotville, WBD
Borehole No. 1
:
Chainage:
0+010 m
Lane:
Northern Lane @ 450mm offset from edge (Northern)
No. Of
Blows
(1)
0

Accumulative Penetration
Per
Penetration/
Blow Set/mm
mm (2)
(3)
10

Penetration
Per
Blow/mm (4)

Hammer Blow
Factor
(5)

DCP Index (6)

CBR % (7)

94

84

16.8

17

12.4

147

53

10.6

11

20.8

188

41

8.2

27.7

240

52

10.4

10

21.2

294

54

10.8

11

20.3

355

61

12.2

12

17.7

411

56

18.7

19

11.0

445

34

34.0

34

5.6

467

22

22.0

22

9.2

500

33

33.0

33

5.8

525

25

25.0

25

7.9

560

35

35.0

35

5.4

580

20

20.0

20

10.2

652

72

72.0

72

2.4

1
1
1
1

729
786
830
870

77
57
44
40

77.0
57.0
44.0
40.0

1
1
1
1

77
57
44
40

2.3
3.2
4.2
4.7

907

37

37.0

37

5.1

937

30

30.0

30

6.5

1
1

955
980

18
25

18.0
25.0

1
1

18
25

11.5
7.9

1
1
1
1

100
5
103
0
105
3
107
5
109

25
25
23
22

25.0
25.0
23.0
22.0

1
1
1
1

25
25
23
22

7.9
7.9
8.7
9.2

22
23

22.0
23.0

1
1

22
23

9.2
8.7

23
22
20

23.0
22.0
20.0

1
1
1

23
22
20

8.7
9.2
10.2

1
1

1
1
1

7
112
0
114

3
116
5
118
5

Name
BNTF Roads Upgrade Project
of
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 2
:

Chainage:
0+060 m
Lane:
Southern Lane 450mm offset from edge
No. OfName
Accumulative
Penetration
Penetration
Hammer Blow
DCP Index (6)
CBR % (7)
of
BNTF Roads
Blows Projec
Per Upgrade Project
Per
Factor
Penetration/
(1) t:
Blow Set/mm
Blow/mm (4)
(5)
mm (2)
(3)
Road: 19
David Rose Street, Bagotville, WBD
0
Borehole
5
65No. 3
46
9.2
1
9
24.3
:
5
106
41
8.2
1
8
27.7
Chainage:
0+120 m
5
146
40
8.0
1
8
28.4
Lane:
Center of Roadway
5
188
42
8.4
1
8
26.9
No. Of
Accumulative Penetration
Penetration
Hammer Blow
DCP Index (6)
CBR % (7)
5
9.0 Per
1
9
24.9
Blows233 Penetration/45 Per
Factor
(1) 287
(5)
5
10.8 Blow/mm (4)1
11
20.3
mm (2) 54 Blow Set/mm
4
152(3)
38.0
1
38
5.0
0 439
0
1

5 541

43

56

43

56.0

8.6

56

3.2

26.2

76

46

33

46.0

6.6

46

4.0

35.3

578

110

37

34

37.0

6.8

37

5.1

34.1

605

145

27

35

27.0

7.0

27

7.3

33.0

633

183

28

38

28.0

7.6

28

7.0

30.1

658

221

25

38

25.0

7.6

25

7.9

30.1

680

273

22

52

22.0

10.4

22

10

9.2

21.2

1
1
1
1
1

700
718
736
755
771

340

20
18
18
19
16

67

20.0
18.0
18.0
19.0
16.0

33.5

1
1
1
1
1

34

10.2
11.5
11.5
10.8
13.1

5.7

10

20
18
18
19
16

787

625

16

38

16.0

38.0

13

16

38

13.1

5.0

1
1

803
819

655

16
16

30

16.0
16.0

30.0

1
1

14

16
16

30

13.1
13.1

6.5

1
1
1
1
1
1
1
1

1
1
1
1
1
1
1
1
1
1
3

1
1
1
1

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

1
1
1
1
1
1
1
1
1
1
1

495

834
849
863
872
891
906
920
934

948
960
973
986
100
0
101
3
102
6
104
1
105
6
107
2
111
5

426
496
545
587

680
703
724
745
764
782
799
815
832
847
863
877
892
905
920
934

949
963
975
990
100
5
101
9
103
3
104
7
106
0
107
4
108
9

15
15
14
9
19
15
14
14

14
12
13
13
14
13
13
15
15
16
43

86
70
49
42

25
23
21
21
19
18
17
16
17
15
16
14
15
13
15
14

15
14
12
15
15
14
14
14
13
14
15

15.0
15.0
14.0
9.0
19.0
15.0
14.0
14.0

14.0
12.0
13.0
13.0
14.0
13.0
13.0
15.0
15.0
16.0
14.3

86.0
70.0
49.0
42.0

25.0
23.0
21.0
21.0
19.0
18.0
17.0
16.0
17.0
15.0
16.0
14.0
15.0
13.0
15.0
14.0

15.0
14.0
12.0
15.0
15.0
14.0
14.0
14.0
13.0
14.0
15.0

Name
David Rose Street, Bagotville, WBD
of
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 4

1
1
1
1
1
1
1
1

1
1
1
1
1
1
1
1
1
1
1

9
11
12

15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30

31
32
33
34
35
36
37
38
39
40
41

15
15
14
9
19
15
14
14

14
12
13
13
14
13
13
15
15
16
14

86
70
49
42

25
23
21
21
19
18
17
16
17
15
16
14
15
13
15
14

15
14
12
15
15
14
14
14
13
14
15

14.1
14.1
15.2
24.9
10.8
14.1
15.2
15.2

15.2
18.1
16.5
16.5
15.2
16.5
16.5
14.1
14.1
13.1
14.8

2.0
2.5
3.7
4.4

7.9
8.7
9.6
9.6
10.8
11.5
12.2
13.1
12.2
14.1
13.1
15.2
14.1
16.5
14.1
15.2

14.1
15.2
18.1
14.1
14.1
15.2
15.2
15.2
16.5
15.2
14.1

:
Chainage:
0+180 m
Lane:
Southern lane 450mm offset from edge
No. OfName
Accumulative
Penetration
Penetration
Hammer Blow
of
David Rose Street, Bagotville, WBD
Blows Projec
Per
Per
Factor
Penetration/
(1) t:
Blow Set/mm
Blow/mm (4)
(5)
mm (2)
(3) Rose Street, Bagotville, WBD
Road: 10
David
0
Borehole
5
60No. 5
50
10.0
1
:
5
99
39
7.8
2
Chainage:
0+240 m
5
138
39
7.8
3
Lane:
Northern Lane 450mm offset from edge
5
183
45
9.0
4 Blow
No. OfName
Accumulative
Penetration
Penetration
Hammer
of
David Rose 120
Street, Bagotville,
WBD
5
303
24.0
5
Blows Projec
Per
Per
Factor
Penetration/
(1)
Blow
Set/mm
Blow/mm
(4)
(5)
1
355
52
52.0
6
t:
mm (2)
(3)
Road:
David
Rose
Street,
Bagotville,
WBD
1
405
50
50.0
7
0
10
Borehole
1
450
45
45.0
8
5
73No. 6
63
12.6
11
:
1
495
45
45.0
9
5
115
42
8.4
12
Chainage:
0+300 m
1
537
42
42.0
10
5
153
38
7.6
13
Lane:
Center of Roadway
1 Of
570
33
33.0
11 Blow
187
34
6.8
14
No.5
Accumulative
Penetration
Penetration
Hammer
Name of
Blows
Per Street,
Per 32.0
Factor
Bagotville,
Penetration/
1
602 David Rose
32
12
5
221
34
6.8WBD
15
Projec
(1)
Blow Set/mm
Blow/mm
(5)
mm
(2)
1
627
25
25.0
13
5
262
41
8.2 (4)
16
t:
(3)
0
10
11
0
5
7
1
1
650
23 Street, Bagotville,
23.0
14
5
48
9.6
17
Road: 310
David Rose
WBD
5
50No. 7
53
45
59
55
48
53
40
52
54
10.6
10.4
10.8
9.6
8.0
22
31
43
51
1
673
23
23.0
15
Borehole
4
422
112
28.0
18
5
1
1
1
5
1
1
5
1
1
5
1
1
2
5
3
1
1
5
1
2
1
1
5
3
1
5
1
1
4
1
1
1
1
1
1
1
1
1
1

104
101
113
87
98
78
37
45
33
42
58
11.6
7.4
9.0
6.6
8.4
23
32
44
52
:
694
21
21.0
16
486
64
64.0
19
Chainage:
0+360
m
713
19
19.0
17
122
147
109
140
172
35
43
42
31
39
59
11.8
7.0
8.6
8.4
6.2
7.8
24
33
45
53
545
59
59.0
20
Lane:
Northern 51
Lane @ 450mm
offset from edge
732
19
19.0
18
165
193
182
140
180
223
43
46
42
31
40
10.2
8.6
9.2
8.4
6.2
8.0
25
34
46
54
589
44
44.0
21
18
18.0
19
Name of 750
202
252
223
172
224
277
37
59
41
32
44
54
11.8
10.8
7.4
8.2
6.4
8.8
26
35
47
55
Bagotville,
626 David Rose Street,
37
37.0WBD
22
Projec 767
17
17.0
20
245
320
261
208
293
365
43
68
38
36
69
88
34.0
13.8
29.3
8.6
7.6
7.2
27
36
48
56
659
33
33.0
23
t:
783
16
16.0
21
349
375
372
297
255
435
104
55
36
47
79
70
20.8
55.0
39.5
70.0
7.2
9.4
28
49
37
57
Road: 800
David Rose
WBD
17 Street, Bagotville,
17.0
22
390
440
424
41
65
52
41.0
65.0
52.0
29
50
335
341
520
38
86
85
28.7
85.0
7.6
38
58
Borehole
No. 8
814
14
14.0
23
505
65
65.0
432
380
385
480
600
42
45
44
56
80
42.0
44.0
56.0
80.0
9.0
30
39
51
59
:
831
17
17.0
24
475
565
450
429
540
665
43
70
44
60
65
43.0
17.5
44.0
60.0
65.0
31
40
52
60
Chainage:
0+420 m
845
14
14.0
25
Lane:
Southern 55
Lane @ 450mm
offset from edge
513
611
483
472
595
38
46
33
43
38.0
46.0
33.0
43.0
55.0
32
41
53
860
15
15.0
26
Name of 637
547
522
513
34
39
41
42
34.0
39.0
41.0
42.0
33
42
54
879 David Rose Street,
19
19.0WBD
27
Bagotville,
Projec 551
579
560
32
38
32.0
38.0
34
43
888
9
9.0
28
t:
607
599
585
28
39
34
28.0
39.0
34.0
35
44
902
14
14.0
29
Road:
David Rose Street, Bagotville, WBD
637
614
38
29
38.0
29.0
36
45
916
14
14.0
30
Borehole No. 9
680
639
43
25
43.0
25.0
37
46
930
14
14.0
31
:

1
943
13
13.0
Chainage:
0+480 m
1 Lane:
956
13
13.0
Center of Roadway
1 Name of 970
14
14.0
David Rose Street,
Bagotville,
1
982
12
12.0WBD
Projec
1
996
14
14.0
t:
1
12 Street, Bagotville,
12.0
Road: 100
David Rose
WBD
8 No. 10
1
102
12
12.0
Borehole
0
:
3
105
35
11.7
5
Chainage:
0+540 m
Lane:

32
33
34
35
36
37
38
39

Southern Lane @ 450mm offset from edge

Name of
David Rose Street, Bagotville, WBD
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 11
:
Chainage:
0+600 m
Lane:
Northern Lane @ 450mm offset from edge
Name of
David Rose Street, Bagotville, WBD
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 12
:

DCP Index (6)

CBR % (7)

10

22.2

29.3

29.3

9
DCP Index
(6)
24
52

24.9
CBR
% (7)
8.3
3.5

50

3.7

45
13
45
8

4.1
17.1
4.1
26.9

42
8
7
DCP 33
Index
(6)
32
7
25
8
23
10
10
11
8
23
28
12
9
7
8
21
64
19
12
7
9
6
8
59
19
10
9
6
8
44
18
12
11
7
8
6
9
37
17
34
14
29
9
8
7
33
16
21
55
40
70
7
9
17
41
65
52
29
85
8
14
65
42
44
56
80
9
17
43
18
44
60
65
14
38
46
33
43
55
15
34
39
41
42
19
32
38
9
28
39
34
14
38
29
14
43
25
14

13
13
14
12
14
12
12
12

4.4
30.1
5.8% (7)
34.1
CBR
6.0
34.1
7.9
27.7
8.7
23.2
23.2
20.8
28.4
21.2
20.3
8.7
7.0
18.8
31.0
24.9
35.3
26.9
9.6
2.8
10.8
33.0
26.2
26.9
37.8
29.3
18.4
3.0
10.8
26.2
24.3
26.9
37.8
28.4
21.7
4.2
11.5
31.0
18.4
27.7
36.5
25.6
20.3
5.1
12.2
26.2
30.1
32.0
15.4
5.6
6.6
5.8
13.1
32.0
23.7
9.8
3.3
4.8
2.5
12.2
4.6
2.7
3.5
30.1
6.8
2.0
15.2
2.7
24.9
4.4
4.2
3.2
2.2
12.2
11.8
4.3
4.2
3.0
2.7
15.2
5.0
4.0
5.8
4.3
3.3
14.1
5.6
4.8
4.6
4.4
10.8
6.0
5.0
24.9
7.0
4.8
5.6
15.2
5.0
6.7
15.2
4.3
7.9
15.2

16.5
16.5
15.2
18.1
15.2
18.1
18.1
18.6

Chainage:
0+660 m
Lane:
Southern Lane @ 450mm offset from edge
No. Of
Accumulative Penetration
Penetration
Hammer Blow
Blows
Per
Per
Factor
Penetration/
(1)
Blow Set/mm
Blow/mm (4)
(5)
mm (2)
(3)
0
0

DCP Index (6)

CBR % (7)

54

54

10.8

53

11

20.3

107

53

10.6

54

11

20.8

165

58

11.6

55

12

18.8

222

57

11.4

56

11

19.1

318

96

24.0

57

24

8.3

385

67

67.0

58

67

2.6

446

61

61.0

59

61

2.9

504

58

58.0

60

58

3.1

550

46

46.0

61

46

4.0

587

37

37.0

62

37

5.1

617

30

30.0

63

30

6.5

643

26

26.0

64

26

7.6

Appendix
1C
Existing Pavement Profile & Test Pits

27

Name of Project:

BNTF Roads Upgrade Project

Road:
Borehole No. :

David Rose Street, Bagotville, WBD

Chainage:
Lane:

0+010 m
Northern Lane @ 450mm offset from edge (Northern)

Existing Pavement Profile :

Material
Asphaltic Concrete
Crusher Run (Base)

Thickness (mm)
None
70

White Sand/ Sand Clay

105

White Sand

200

Clay

Continuous

Remarks:

(i) DCP started on the White Sand / Sand Clay Layer.


(ii.) Insitu CBR (%) = 292/ (DCP^1.12)
(iii.) Insitu CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

BNTF Roads Upgrade Project

Road:
Borehole No. :

David Rose Street, Bagotville, WBD

Chainage:
Lane:

0+060 m
Southern Lane 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
90
60
70
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) Insitu CBR (%) = 292/ (DCP^1.12)
(iii.) Insitu CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

BNTF Roads Upgrade Project

Road:
Borehole No. :

Chainage:
Lane:

David Rose Street, Bagotville, WBD

0+120 m
Center of Roadway

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
80
140
260
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

David Rose Street, Bagotville, WBD

Chainage:
Lane:

0+180 m
Southern lane 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
70
70
190
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

David Rose Street, Bagotville, WBD

Chainage:
Lane:

0+240 m
Northern Lane 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
50
90
190
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

Chainage:
Lane:

David Rose Street, Bagotville, WBD

0+300 m
Center of Roadway

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
40
120
250
Continuous

Remarks:
Done in Failure Zone
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

Chainage:
Lane:

David Rose Street, Bagotville, WBD

0+360 m
Northern Lane @ 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
70
140
210
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

Chainage:
Lane:

David Rose Street, Bagotville, WBD

0+420 m
Southern Lane @ 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
80
170
270
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

Chainage:
Lane:

David Rose Street, Bagotville, WBD

0+480 m
Center of Roadway

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
100
100
240
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

David Rose Street, Bagotville, WBD


10

Chainage:
Lane:

0+540 m
Southern Lane @ 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
90
120
180
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

David Rose Street, Bagotville, WBD


11

Chainage:
Lane:

0+600 m
Northern Lane @ 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
None
130
270
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Name of Project:

David Rose Street, Bagotville, WBD

Road:
Borehole No. :

David Rose Street, Bagotville, WBD


12

Chainage:
Lane:

0+660 m
Southern Lane @ 450mm offset from edge

Existing Pavement Profile:

Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay

Thickness (mm)
None
None
120
275
Continuous

Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )

Appendix
1D
AASTHO 1993 - Algorithm Analysis (Structural Number)

28

AASHTO FLEXIBLE PAVEMENT DESIGN


SN Determination - References: AASTHO 1993
The tables below solve the AASHTO Equation for Flexible Pavement Design: Log10 W18 = ZR S0 + (9.36 log10 (SN+1)) - 0.2 + log10 (PSI/(4.2-1.5)/[(0.4+(1094/
(SN+1)
W18 = estimated traffic load over design life (expressed as an 18Kip Equivalent Single Axel Load) 50,000 ESALs for low volume access roads
Soil Resilient Modus (Mr) = 1,500 * CBR
Materials
Resilient Modulus (Mr) = 1500 x CBRvalue
Reliability R = 75%
Crushed Stone
1500x (60% ) = 90,000psi
ZR - Standard normal deviate = 0.674 (Table 4.1 p i.62)
White Sand/ Sand Clay 1500 x(20% ) = 30,000psi
Standard deviation = 0.4
Present serviceability index (P0) = 4.2
White sand
1500 x (10 % ) = 15,000psi
Clay Subgrade
1500 x (2% ) = 3000psi
Terminal Serviceability (Pt) = 2
Change in Serviceability Index (PSI) = (P0-Pt) = 2.2

5.19

+ 2.32 log10MR 8.07

Min Value from


DCP

Minimum SN Required for clay sub grade


W18
5000
0
Solution

log10W18
4.7

0.2 PSI/2.
7
0.2 0.81481
5

log10(PSI/2.7 0.4 0.4+1097/


(SN+1)
)-0.088941083 0.4
3.02

5.19

2.32*log10M 8.07
8.06692131 8.0
R
1
7

MR
300
0

9.36*log10
(SN+1)
3.21

0.2 PSI/2.
7
0.2 0.81481
5

log10(PSI/2.7 0.4 0.4+1097/


(SN+1)
)-0.088941083 0.4
18.7
2

5.19

2.32*log10M 8.07
9.68853172 8.0
R
1
7

MR
1500
0

9.36*log10
(SN+1)
2.39

0.2 PSI/2.
7
0.2 0.81481
5

log10(PSI/2.7 0.4 0.4+1097/


(SN+1)
)-0.088941083 0.4
52.3
2

5.19

2.32*log10M 8.07
10.3869213 8.0
R
1
7

MR
3000
0

9.36*log10
(SN+1)
1.37

0.2 PSI/2.
7
0.2 0.81481
5

log10(PSI/2.7 0.4 0.4+1097/


(SN+1)
)-0.088941083 0.4
191.7
4

5.19

2.32*log10M 8.07
11.4938426 8.0
R
2
7

MR
9000
0

ZR
s0
ZR s0 SN
SN+1 9.36*log10
0.67
0.4 0.2 2.2
3.2 (SN+1)
4.73
4
7
0
4.8 Must be Greater than Log10 W18

Minimum SN Required for White Sand Base


W18
5000
0
Solution
4.9

log10W18
4.7

ZR
s0
ZR s0 SN
SN+1
0.67
0.4 0.2 1.2
2.2
4
7
0
Must be Greater than Log10 W18

Minimum SN Required for White Sand Base/Sand Clay


W18
5000
0
Solution
4.8

log10W18
4.7

ZR
s0
ZR s0 SN
SN+1
0.67
0.4 0.2 0.8
1.8
4
7
0
Must be Greater than Log10 W18

Minimum SN Required for Crusher Run - Base


W18
5000
0
Solution

log10W18
4.7
4.9

ZR
s0
ZR s0 SN
0.67
0.4 0.2 0.4
4
7
0
Must be Greater than Log10
W18

SN+1
1.4

Appendix
1E
Interlayer
Checks

29

Project: Basic Needs Trust Fund (Seventh Programme)


Inter -layer Checks
Note: Structural Number computations were performed with imperial units because the layer coefficient derived by AASTHO Guide are in imperial units and
computations must be performed in imperial units.
Chainage
0+010 m
Materials

SN1

Layer Coefficient

Propose
d
(inche
s)

Existing
(Inches)

0.4
0.6

0.4

AC
SN2
0.8

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

Existing
SN
Values

1.5

C.R
1.53

0.131

0.524

WS/SC
0.76

0.1

4.2

4.2

WS
7.3

0.09

0.42

SN3
1.2

SN4
2.2

0.42

0.72

0.72

Total SN (Actual)
2.264

Materials

AC

SN1

C.R

0.4

SN2

Proposed
SN
Values

Chainage
0+060 m
Propose
Layer Coefficient
d
Existing
(inche
(Inches)
s)
0.4
1.5
0.131

3.6

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

1.14

Existing
SN
Values

Proposed
SN
Values
0.6

1.53

0.4716

0.7
6

0.9

0.524

0.8

SN3

WS/SC
9

0.1

2.4

WS
2.8

0.09

2.8

0.9

1.2

SN4
2.2

2
0.252

0.252

Total SN (Actual)
2.276

1.6236

Chainage
0+120 m
Materials
Coefficient
SN

0.4

Layer

Existing
(Inches)

AC

0.4

C.R

0.131

3.15

Interlayer
Proposed
Checks (Inches);
(inches)
Greater than
(Minimum
1.5

Existing
SN
Values

Proposed
SN
Values
0.6

SN
2

0.8

1.53

0.41265

0.524

SN

1.2

WS/S
C

0.1

5.51

5.51

0.76

0.551

0.551

SN

2.2

Total SN
(Actual)

1.88435

2.5957

Project: Basic Needs Trust Fund (Seventh Programme)


Inter -layer Checks
Note: Structural Number computations were performed with imperial units because the layer coefficient derived by AASTHO Guide are in imperial units and
computations must be performed in imperial units.

Materials
Coefficient

SN

Layer

AC
1.5

Chainage
0+180 m
Existin
Propose
g
d
(Inche
(inche
s)
s)

0.4

Existing
SN
Values

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

Proposed
SN
Values

0.6

0.4
C.R
0.36156

SN2
0.8

WS/SC
6

SN3
1.2

WS
0.6732

SN4
2.2

0.131

2.76

0.524

0.1

2.76

0.09
0.6732

7.48

1.53

0.76
0.6

7.48

Total SN (Actual)

Materials

SN1
AC

Layer Coefficient

0.4
C.R
0.262

SN2
0.8

WS/SC
5

SN

Chainage
0+240 m
Propose
Existing
d
(Inches)
(inche
s)

0.4
1.5
0.131
0.524

0.1

0.6

5.3

2.3972

1.63476

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

Existing
SN
Values

Proposed
SN
Values

0.6
2

3.54

1.53

0.76
0.5

0.5

1.2
WS
0.6732

SN4
2.2

0.09
0.6732

7.48

7.48

6.4

Total SN (Actual)
2.2972

Materials

Layer Coefficient

Chainage 0+300 m
Propose
Interlayer
d
Checks (Inches);
Existing
(inche
Greater than
(Inches)
s)
(Minimum
Thickness)

1.4352

Existing
SN
Values

Proposed
SN
Values

SN1
AC
SN2
0.8
SN3
1.2

SN4
2.2

0.4

0.4
1.5
C.R
0.20567

WS/SC
4.72

WS
0.8856

0.131

0.524

0.1

0.09
0.8856

0.6
1.57

4.72

9.84

1.53

0.76
0.472

9.84

Total SN (Actual)
2.4816

0.472

6.7

1.56327

Project: Basic Needs Trust Fund (Seventh Programme)


Inter -layer Checks
Note: Structural Number computations were performed with imperial units because the layer coefficient derived by AASTHO Guide are in imperial units and
computations must be performed in imperial units.

Materials

SN1
AC

Layer Coefficient

0.4
1.5

0.4
C.R
0.36156

SN2
0.8

Existing
SN
Values

0.6

2.76

1.53

0.1

5.51

0.09
0.8343

9.27

0.76
0.551

9.27

0.551

5.8

Total SN (Actual)
2.5093

Materials

SN1
AC

Layer Coefficient

C.R
0.41265

SN2
0.8

Existing
SN
Values

6.69

0.09
0.9567

10.63

3.15

1.53

1.8735
0.669

10.63

0.669

5.8

Total SN (Actual)
2.63835

Materials

SN1
AC

0.4

Layer Coefficient

0.4
1.5

Proposed
SN
Values

0.6

3.15

0.1

WS
0.9567

SN4
2.2

1.74686

0.131
0.41265

WS/SC
6.69

SN3
1.2

Chainage 0+420 m
Propose
Interlayer
d
Checks (Inches);
Existing
(inche
Greater than
(Inches)
s)
(Minimum
Thickness)

0.4
1.5

0.4

Proposed
SN
Values

0.524

WS
0.8343

SN4
2.2

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

0.131

WS/SC
5.51

SN3
1.2

Chainage
0+360 m
Propose
d
Existing
(inche
(Inches)
s)

Chainage 0+480 m
Propose
Interlayer
d
Checks (Inches);
Existing
(inche
Greater than
(Inches)
s)
(Minimum
Thickness)
-

2.03835

Existing
SN
Values

Proposed
SN
Values

0.6

SN2
0.8
SN3
1.2

SN4
2.2

C.R
0.524

WS/SC
4

WS
0.8505

0.131
0.524

0.1

0.09
0.8505

9.45

1.53

0.76
0.4

9.45

Total SN (Actual)
2.3745

0.4

7.5

1.7745

Project: Basic Needs Trust Fund (Seventh Programme)


Inter -layer Checks
Note: Structural Number computations were performed with imperial units because the layer coefficient
computations must be performed in imperial units.
Chainage
0+540 m
Propose
Existing
d
Materials
Layer Coefficient
(Inches)
(inche
s)

SN1
AC

0.4
C.R
0.46374

SN2
0.8

0.4
1.5
0.131

Existing
SN
Values

Proposed
SN
Values

0.6
3.54

0.1

WS
0.9567

SN4
2.2

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

1.53

0.524

WS/SC
7.09

SN3
1.2

derived by AASTHO Guide are in imperial units and

7.09

0.09
0.9567

0.76
0.709

10.63

10.63

0.709

4.1

Total SN (Actual)
2.7897

2.12944

Chainage 0+600 m
Materials

SN1
AC

Layer Coefficient

0.4
1.5

0.4
C.R
0

SN2
0.8
SN3
1.2

Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)

Existing
SN
Values

0.6

0.131
0.524

0.1

WS
0.9

0.09

5.11

0.9

1.53

0.76
0.511

10

10

0.511

6.3

Total SN (Actual)
2.535

Materials
Coefficient

Proposed
SN
Values

WS/SC
5.11

SN4
2.2

Propose
d
(inche
s)

Existing
(Inches)

Layer

Chainage 0+660 m
Existin
Propose
Interlayer
g
d
Checks (Inches);
(Inche
(inche
Greater than
s)
s)
(Minimum
Thickness)

SN1

0.4

1.411

Existing
SN
Values

Proposed
SN
Values

AC C.R

0.4
0.6
SN2
0.8

1.5
WS/SC
4.72

0.131
0
0.1

0
0.524
4.72

1.53
0.76
0.472

0.472

SN3
1.2

SN4
2.2

WS
0.81

0.09

6.7

0.81
Total SN (Actual)
2.406

1.282

Project: Basic Needs Trust Fund (Seventh Programme)


Inter -layer Checks
Note: Structural Number computations were performed with imperial units because the layer coefficient derived by AASTHO Guide are in imperial units and
computations must be performed in imperial units.

Materials

SN1
AC
SN2
0.8

Layer Coefficient

0.4

Full
Reconstructio
n
Propose
Interlayer
Existing
d
Checks (Inches);
(Inches)
(inche
Greater than
s)
(Minimum
Thickness)

0.4
0.131
0.393

C.R
0
WS/SC

0.09

1.53

2.07

10

7.9

0.5
0

0
SN4
2.2

0
WS

Proposed
SN
Values

1.5
0.6

0.1

SN3
1.2

Existing
SN
Values

0.9
Total SN (Actual)
2.393

Appendix 2- Photographs

30

Figure 7-Glasgow Intersection: Deteriorated carriageway, Chainage 0+615m


(Taken: 23/06/2015)

Figure 8- Deteriorated Carriageway with minor depressions, Chainage 0+690m


(Taken:23/06/2015)

Figure 9-Deteriorated Carriageway with depressions, Chainage 0+500m


(Taken: 23/06/2015)

31

Figure 10-Test Pit at Chainage 0+710m


(Taken: 25/06/2015)

Figure 11-Garbage Along Side Roadway


(Taken: 23/06/2015)

Figure 12-Deteriorated Carriageway showing large depressions


(Taken: 23/06/2015)

32

Appendix 3- Final Design Drawings

33

Tel. # - (592)-227-0481, 226-2773, 226-2758


Fax. # - (592)-226-3930
Email - cemco@networksgy.com

DAVID ROSE STREET


BAGOTVILLE
WEST BANK DEMERARA (REG.3 )

Statio

Sch

Bagostown

Cemetery
Sch

Health Centre

Nandy
Park

CANAL #1

Greenfiel
Park

Ch
Nismes

Nismes

Ch
Sluice
Gate

Healt
Centre

Sluice
Gate

Factory
Ch
Oilmill

Sch
Ch
Ch

Ch

Stanleytown
Sluice
Gate

L. Long

Notes

No.

Revision

Date

Initials

Legend

Drawn

L. Long

Designed

P. Deodat

Checked

P. Deodat

Approved

RB Latchmansingh

Consultant:

Client:

BASIC NEEDS TRUST FUND(BNTF)


Project:

Title:
Date:

LOCATION PLAN DAVID ROSE STREET

Dwg. No.:

SEPTEMBER, 2015 CM/BNTF7/DRAR/DES/00

Scale:

--

Status:
Sheet:

1 of 1

ML 1-1
-

BASIC NEEDS TRUST FUND(BNTF)

PLAN - DAVID ROSE STREET

ML 2-2

ML 1-1

ML 3-3

ML 2-2
-

BASIC NEEDS TRUST FUND(BNTF)

PLAN - DAVID ROSE STREET

ML 4-4

ML 3-3

ML 5-5

ML 4-4
-

BASIC NEEDS TRUST FUND(BNTF)

PLAN - DAVID ROSE STREET

ML 7-7

ML 6-6

ML 5-5
ML 6-6
-

BASIC NEEDS TRUST FUND(BNTF)

PLAN - DAVID ROSE STREET

ML 8-8

ML 7-7
ML 8-8
-

BASIC NEEDS TRUST FUND(BNTF)

PLAN - DAVID ROSE STREET

Longitudinal Profile

Longitudinal Profile

BASIC NEEDS TRUST FUND(BNTF)

PROFILE OF DAVID ROSE STREET

Longitudinal Profile

Typical Design Cross SectionRehabilitation

CH0+030 TO
0+615
CH0+615 TO
0+690

Typical Design Cross Section-Re-Construction


-

CH0+690 TO 0+745

BASIC NEEDS TRUST FUND(BNTF)

PROFILE & CROSS


SECTIONS OF DAVID ROSE
STREET

BASIC NEEDS TRUST FUND(BNTF)

DOUBLE 900MM CULVERT#1: PLAN


& SECTIONOF DAVID ROSE STREET

BASIC NEEDS TRUST FUND(BNTF)

900mm CULVERT#2: PLAN &


SECTIONOF DAVID ROSE STREET

BASIC NEEDS TRUST FUND(BNTF)

ROAD MARKINGS - DAVID ROSE


STREET

Appendix 4-Final Estimate

34

Basic Needs Trust Fund


David Rose Street, Bagotville, WBD

BILL OF QUANTITIES GRAND SUMMARY


Contract Name: Basic Needs Trust Fund Seventh Programme
Contract - David Rose Street, Bagotville, WBD
Contract No.:
General Summary
Bill No.A: Preliminaries

Amount
(USD)

Amount
(GYD)

8,220.00

1,685,000.00

136,926.00

28,069,837.00

4,181.00

857,200.00

29,622.00

6,072,500.00

Sub-total of Bills

178,949.00

36,684,537.00

CBD's Allocated End of Construction Cost


Note: 1 USD = 205 GYD

179,080.00

36,711,400.00

Bill No. B : Incidental Road Works


Bill No. C: Drainage Works
Bill No. D: Structures and Incidential Works

BNTF - Seventh Programme


David Rose Street, Bagotville, WBD

Bill No. A - Preliminaries

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)

Item
Number
A.1

Item Description

Unit

Quantity

Rate GYD

Amount

GYD

PRELIMINARIES

A.1.1

Mobilisation and Demobilisation.

LS

275,000

A.1.2

Surveys and Setting out

LS

450,000

A.1.3

Temporary Works

LS

75,000

A.1.4

Allow for coordinating with utility companies for the location/relocation


of utility services and all related works

LS

40,000

A.1.5

Testing of materials. As directed by engineer

LS

85,000

A.1.6

Testing of the Works . As directed by engineer

LS

125,000

A.1.9

Pavement markings (STOP and Lane marking at entrance from


Public Road) and road signs ( 1Nr "STOP") . These should be
according to drawings and final location as directed by Engineer.

LS

185,000

A.2

Contractor's Facilities

A.2.1

Contractor's Welfare

LS

50,000

A.2.2

Provision for Contractor's Office, Plant, Yard and Store

LS

40,000

LS

150,000

A.3

A.3.1

Engineer's Facilities
Allow a sum for rental of a site office for the Engineer (10'-0" x 10'-0")
with furniture, appliances and janitorial services. Engineer must be
supplied with drinking water on a daily basis. Site office should be
maintained during the project life.
Sub-Total Carried Forward

1,475,000

BNTF - Seventh Programme


David Rose Street, Bagotville, WBD

Bill No. A - Preliminaries

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)
Item
Nr

Item Description

Quantity

Brought Forward
A.4

Unit

Rate
(GYD)

Amount
(GYD)
1,475,000

Miscellaneous

A.4.1

Contractor's Programe

LS

35,000

A.4.2

Safety and Traffic Management

LS

50,000

A.4.3

Progress photographs

LS

25,000

A.4.4

Provided and erect project sign board having a diemension of 1.5m x


1.5m. Details and location will be provided in the final construction
drawings.

LS

100,000

PRELIMINARIES TOTAL

1,685,000

Bill B - Roadworks

BNTF Seventh Programme


David Rose Street, Bagotville, WBD

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)
Item
Nr

Item Description

ROADWORKS

B.1

Clearing and grubbing


Clearing and grubbing of roadway and shoulder. As per
Specifications Section 4 Site Clearance.

B.1.1
B.2
B.2.1

B.2.2

B.3
B.3.1
B.4
B.4.1
B.5
B.5.1

B.6

B.6.1

General Excavation
Scarify existing carriageway; average 150mm deep and compact to
95% of the maximum dry proctor density. As per Specifications
Section 5 Earthwork and Related Operations.
Excavation to Subgrade Level. As indicated in Profile Drawings. Subgrade should be compacted to design levels. As per Specifications
Section 5 Earthwork and Related Operations.
Surface Preparation
Grade, shape and compact existing shoulders to falls.As per
Specifications Section 5 Earthwork and Related Operations.
Imported Clay
Supply, place and compact in shoulders.As per Specifications As
per Specifications Section 5 Earthwork and Related Operations.
Sub Base - White Sand
Supply, place and compact White Sand in 150mm single layers.
Layers shall be compacted to a density of at least 95% of the
maximum density as determined by ASTM D- 1557 method A. As
per Specifications Section 7 White Sand Sub-base.
Lower Sub Base - White Sand / Sand Clay
Include the cost of all materials, multiple handling, stockpiling,
blending, placing, dewatering, pumping, compaction and trimming at
optimum moisture content, all clearing and grubbing of materials
pits, all stripping of overburden from the pits, if required, and all
incidentals necessary to complete the work. Layers shall be
compacted to a density of at least 95% of the maximum density as
determined by ASTM D- 1557 method A. A. As per Specifications
Section 8 Sand Clay/White Sand Sub base.
Sub-Total Carried Forward

Quantity

2,750

2,544

137

1,363

277

67

25

Unit

Rate
(GYD)

Amount
(GYD)

120

330,000

200

508,878

1,200

164,634

100

136,280

200

55,399

4,550

305,183

10,000

251,524

1,751,899

Bill B - Roadworks

BNTF Seventh Programme


David Rose Street, Bagotville, WBD

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)
Item
Nr

Item Description

Quantity

Rate
(GYD)

Unit

Brought Forward
B.7

B.7.1

B.8
B.8.1

Granular base course


Supply, place and compact crushed stone (CBR 60%) in single layer
100 mm thick. Base course should be placed and compact 300 mm
both sides of the road to allow for vehicles wheels on shoulder. As
per Specifications Section 10 Graded Aggregate Material for Base
Course.
Bituminous prime coat
Bituminous prime coat material applied to a prepared base course
surface at a rate of 0.25 Imp. Gal/yd2. Base extends 300 mm both
side into the shoulder must be prime coated. As per Specifications
Section 11 Prime and Tack Coats.

B.9

Bituminous surface dressing

B.9.1

Supply, spread and compact hot mix asphaltic concrete wearing


course 38mm thick using refinery bitumen. As per Specifications
Section 18.

B.10

Speed Humps
Construction of Speed humps according to drawings or as directed
by Engineer. Rate should include for painting of humps. As per
Specifications Section 18.

B.11

Provisional Sum
Provisional Sum to be used as directed by the Engineer.
Total

Amount
(GYD)
1,751,899

324

3,200

2,557

PS

30,000

9,732,591

1,150

3,679,860

4,250

10,865,488

No

60,000

240,000

1,800,000
28,069,837

Basic Needs Trust Fund


David Rose Street, Bagotville, WBD

Bill C - Drainage

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)

Item

Item Description

Nr

Quantity

Drainage

C.1.1

Desilt and reshape existing earthen drain and dispose of


all excavated materials.As per Specifications Section 5
Earthwork and Related Operations.

Provisional Sum
Provisional Sum to be used as directed by the Engineer.
Total

PS

C.2

Unit

1,520

Rate
(GYD)

235

Amount
(GYD)

357,200

500,000
857,200

BNTF - Seventh Programme


David Rose Street, Bagotville, WBD

Bill D- Structures Incidential Works

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)
STRUCTURES
Item
Item Description
Number
D
STRUCTURES AND INCIDENTAL CONSTRUCTION

Amount
Quantity

Unit

Amount
(GYD)

Rate (GYD)

D.1
D.1.1

CULVERTS - Type 1
Temporary Works

D.1.1.1

Allow for construction of cofferdams, de-watering site and


removal of cofferdams after completion of construction works

LS

150,000

D.1.1.2

Allow for the removal of all timber revetments work in way of


construction and stockpile for NDC

LS

75,000

LS

100,000

LS

150,000

D.1.1.3
D.1.2
D.1.2.1

Allow for cleaning and de-silting existing culvert and disposing


of all materials. Include for cleaning ends of culvert to receive
concrete works.
Relocation of Utilities
Allow for GWI to relocate water line. Include for all bends,etc.

D.1.3

Section 5- Earthworks/Excavation

D.1.3.1

Excavation for foundation slabs, both sides of existing HDPE


pipe.

50

500

25,000

D.1.3.2

Load up and transport surplus excavated material from site to


an approved location

50

300

15,000

D.1.4

Section 5-White Sand Embankment

18

4,500

80,222

29

4,500

130,500

15,000

30,000

1.80

40,000

72,000

16

50,000

775,000

1,700

kg

400

680,000

55

1200

66,000.00

6.0

80000

480,000.00

Filling to make up levels over 450mm thick spread level and


compact to not less than 95% of the Standard Proctor Dry
Density
Additional Sand Fill
Filling to make up levels over culvert and wing walls spread
D.1.4.2 level and compact to not less than 95% of the Standard
Proctor Dry Density

D.1.4.1

Imported granular backfill; 2" diameter boulder


D.1.4.3

Filling to make up levels; at inlet and outlet. 2m width

D.1.5

Section 20: Concrete for Structures and other Uses

2.00

Plain in-situ concrete 15N/mm (cube strength)


D.1.5.1

Blinding beds 75mm thick; poured against white sand


Reinforced in-situ concrete 25N/mm2 (cube strength)

D.1.5.2

Concrete for Structure including headwall,wingwalls and toe.


Rates should include for form works.
Reinforcement bars; deformed high yield steel; BS 4449

D.1.5.3

Bar reinforcement; 12mm diameter (foundation, headwall,


wingwall and toe)
Finishes

D.1.6

Supply and apply two coats of oil paint to headwalls and


wing walls.
HDPE Pipe

D.1.7

Supply, transport and install HDPE - Pipe 900 mm


Grand Total for Type 1 Culvert

2,233,500

BNTF - Seventh Programme


David Rose Street, Bagotville, WBD

Bill D- Structures Incidential Works

Basic Needs Trust Fund (BNTF) - Seventh Programme


Funded By: Caribbean Development Bank (CDB) & Governement of Guyana (GoG)
Estimated Amount

STRUCTURES
Item
Number

Item Description

Quantity

Unit

Rate (GYD)

Amount

(GYD)

D.2

CULVERT - Type 2

D.2.1.

Temporary Works

D.2.1.1

Allow for construction of cofferdams, de-watering site and


removal of cofferdams after completion of construction works

L.S

150,000

D.2.1.2

Allow for cleaning and de-silting existing culvert and disposing


of all materials. Include for cleaning ends of culvert to receive
concrete works.

LS

100,000

D.2.2

Relocation of Utilities

D.2.2.1

Allow for GWI to relocate water line. Include for all bends,etc.

LS

200,000

D.2.3

Section 5- Earthworks/Excavation

D.2.3.1

Excavating trenched for foundations; not exceeding 5.00


feet deep starting from built- up ground level

50

550

27,500

D.2.3.2

Load up and transport surplus excavated material from site to


an approved location

50

150

7,500

D.2.4

Section 5-White Sand Embankment

D.2.4.1

Filling to make up levels over 12" thick spread level and


compact to not less than 95% of the Standard Proctor Dry
Density

12

4,500

54,000

28

4,500

126,000

8,000

24,000

40,000

40,000

Additional Sand Fill


D.2.4.2

Filling to make up levels over culvert and wing walls spread


level and compact to not less than 95% of the Standard
Proctor Dry Density

D.2.5

Imported granular backfill; 2" diameter boulder

D.2.5.1

Filling to make up levels; at inlet and outlet

D.2.6

Section 20: Concrete for Structures and other Uses

Plain in-situ concrete 15N/mm


D.2.6.1

(cube strength)

Blinding beds 75mm thick; poured against white sand


2

D.2.6.2

Reinforced in-situ concrete 25N/mm (cube strength)


Concrete for Structure including headwall,wingwalls and toe.
Rate should include for form works.

10

50,000

500,000

D.2.6.3

Reinforcement bars; deformed high yield steel; BS 4449


Bar reinforcement; 12mm diameter (foundation, headwall,
wingwall and toe)
Finishes

1,360

kg

400

544,000

D.2.6.4

Supply and apply two coats of oil paint to headwalls and


wing walls.

55

1,200

66,000

D.2.7

Provisional Sum
Provisional Sum to be used as directed by the Engineer.

PS

2,000,000

Grand Total for Type 2 Culvert

1,839,000

Grand Total for both Culverts

6,072,500

Appendix 5-Correspondences

35

July 15 2015

The
Chief
ExecutiveOfficer
GuyanaTelephone& TelegraphCo.,
69 Brickdam,
Georgetown,
Guyana.

Dear Sir/Madam,

Re: Basic Needs Trust Fund - Seventh Programme


REHABILITATION OF ACCESS ROADS AND DRAINAGE
The Basic Needs Trust Fund Office has received funding from the Caribbean Development Bank (COB) under the
I

<:>

BNTF Seventh Programme for the improvement of access roads and drainage in communities.
We have been engaged by the Bank to provide engineering services to the following access roads:
David Rose Street, Bagotville, West Bank Demerara.
Mahagony Street, Samatta Point, Golden Grove, East Bank Demerara.
Market Street, Beterverwagting, East Coast Oemerara.
We are requesting

your kind assistance to alert us of any infrastructure,

with which the Contractor

underground

cables and otherwise,

may have to take careful Consideration during the construction period. It will be

mutually beneficial if plans can be provided beforehand showing the actual location of these infrastructures so as to
afford a smooth construction programme and prevent any damages and disruptions.
We would appreciate receiving such information and guidance by July 20 2015.

Sincerely you'W
:

.................. !

..

~
R. B.
Latchmb h
Managing Director
New address-117 John Smith Street, Campbellville,

Georgetown Tel:223-8823

CE.MCOinc.
Tel: (+592) 226-2758, 226-2773 & 227-0481, 227-0542 Facsimile: 226-3930. E-mail: info@cemcoguyana.com
Registered Office@above address. Registered # 2820

July152015
The Chief Executive Officer

Corporate Complex,
Guyana Water Inc.,
Vllissengen Road and Church Street,
. Bel Air Park,
Georgetown,
Guyana.

Dear Sir/Madam,
Re: Basic Needs Trust Fund - Seventh Programme
REHABILITATION OF ACCESS ROADS AND DRAINAGE
The Basic Needs Trust Fund Office has received funding from the Caribbean Development Bank (COB) under the
BNTF Seventh Programmefor the improvement of access roads and drainage in communities.
We have been engaged by the Bank to provide engineering services to the following access roads:
'
David Rose Street, Bagotville, West Bank Demerara.
'----"

Mahagony Street, Samatta Point, Golden Grove, East Bank


Demerara.
Market Street, Beterverwagting, East Coast Demerara.
We are requesting your kind assistance to alert us of any infrastructure, pipelines and otherwise, with which the
'

Contractor may have to take careful consideration during the construction period. It will be mutually beneficial if plans
can be provided beforehand showing the actual location of these infrastructures so as to afford a smooth
construction programme and prevent any damages and disruptions.
Attached are pictures showing existing GWI mains that are of concern to the
Bagotvilleproject. We would appreciate receiving such information and guidance by July 20
2015.
Sincerely yours,

cc:
. '-....,.,'

Mr. M. Singh, Project Manager, BNTF


New address 117 John Smith Street, Campbellville, Georgetown Tel:223-8823

CE.MCO Inc.

Tel: (+592) 226-2758, 226-2773 & 227-0481, 227-0542 Facsimile: 226-3930. E-mail: info@cemcoguyana.com
Registered Office@above address. Registered # 2820

Figure 1- Showing GWI main relatively

Figure 2-Showing

close to proposed road construction

Proposed Road Upgrade Site, David Rose Street-Bagotville.

site. {Source: CEMCO- 23rd June, 2015, Bogotvil/e)

{Source: CEMCO- 23rd June, 2015, Bagotville)

July152015

The
ProjectManager
CommercialOffice,
Guyana Power & Light,
Middle Street
Georgetown,
Guyana.

Dear Sir/Madam,

Re: Basic Needs Trust Fund - Seventh Programme


REHABILITATION OF ACCESS ROADS AND DRAINAGE

. The Basic Needs Trust Fund Office has received funding from the Caribbean Development Bank (COB) under the.
BNTF Seventh Programme for the improvement of access roads and drainage in communities.
We have been engaged by the Bank

to provide

engineering services to the following access roads:

David Rose Street, Bagotville, West Bank Demerara.


Mahagony Street, Samatta Point, Golden Grove, East Bank Demerara.
Market Street, Beterverwagting, East Coast Demerara.
We are requesting your kind assistance to alert us of any infrastructure with which the Contractor may have to take
careful consideration during the construction period. It will be mutually beneficial if plans can be provided beforehand
showing the actual location of these infrastructures so as to afford a smooth construction programme and prevent
any damages and disruptions.
We would appreciate receiving such information and guidance by July 20 2015.
Sincerely your(:\

l:~

whl

~l ..

R. B. Latchma~sing
Managing Directs
cc:

Mr. M. Singh, Project Manager, BNTF

Mr. B. Dyndayll, Guyana Power& Lights


New address 117 John Smith Street, Campbe\lvi\le, Georgetown Tel:223-8823

CEMCOhic.
Tel: ( +592) 226-2758, 226-2773 & 227-0481, 227-0542 Facsimile: 226-3930. E-mail: info@cemcoguyana.com
Registered Office@above address. Registered # 2820

Appendix 6-Framework for Environmental and Social Assessment

36

Framework for Environmental and Social Assessment.


The Environmental and Social Assessment (EA) will be conducted to satisfy the requirements of the TOR and
guidelines as outlined in the Environmental Protection Act, 1996. The assessment will encompass the various stages
of the project (Design, Construction and Post construction) to identify and document the environmental and social
impacts of the project.
The Environmental Reconnaissance will focus on the following key areas:
1. Proximity of schools and other social services to the proposed sites.
2. The types of impacts likely to be generated by the implementation of the project.
3. Situational analysis of traffic scenario within the area.
4. Proximity of nearest waterway to the site, is construction likely to impact water quality.
5. Utilities
6. Waste management and general health and safety.
Social Assessment
The details of the stakeholder concerns during the initial engagement will form part of the assessment. This includes:
1. Discussions with community to garner their views on environmental impacts such as dust, noise, oil spills
etc. Recommendation for best management of these impacts.
2. Identification of point person to provide feedback and liaison services for the community.
Environmental Management Plan.
Mitigation measures will provided and tailored to reduce the potential adverse impacts of the project to the point
where the impacts are insignificant or within acceptable limits through effective best practices. The plan will cover the
following areas:

Vegetation & Biodiversity

Wildlife & Impact on Threatened or Endangered Species

Prevention of Water and Soil Pollution

Prevention of Air Pollution and Hazards

Prevention of Noise Pollution and Hazards

Disposal of Waste

Traffic Management

Social Impacts

Reporting requirement

Monitoring Framework
37

Appendix 7-Consultant Work Schedule

38

Basic Needs Trust Fund (BNTF)- Seventh Programme


David Rose Street,Bagotville,WBD
ID

Task Name

CONSULTANT'S WORK PROGRAMME

2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27

Commencement of Consultancy Services


Design Services
Preliminary Design Services
General Project Meeting
Initial Survey: setting out, Elevation of Existing structures i.e. drainage, roadways, culverts and
utilities
Pertinent Data Collection (e.g. DCP, Traffic Survey, Test Pits, Condition Survey of Culverts)
Engineering Design for Culverts and Carriageway
Preliminary Design Drawings
Preliminary Estimates of Cost
Preparation and Submission of Preliminary Design Report
End of Preliminary Design Services
Final Design Services
Preparation and Submission of Final Designs and Construction Drawings
Preparation and Submission of Technical Specifications
Final Cost Estimates
Preparation of Tender Documents
End of Final Design Services
Pre-construction Services
Tender Period
Evaluation of Tenders Received - Procurement Process
End of Pre-construction Services
Technical Inspection of Construction Services
Provision of Requsite Technical Personnels - Engineers, Site Inspectors etc.
Monitoring of Construction Works, Environmental and Social Aspects.
David Rose Street-Bagotville Phase 1- Culverts Construction
David Rose Street-Bagotville Phase 2- Desilting & Reshaping of drains, Excavation of Carriageway,
Place WS/SC to bring up formation levels

Duration

Start

383 days

Tue 23-06-15

0 days

Tue 23-06-15

62 days
31 days
1 day

Wed 24-06-15

5 days

Wed 24-06-15

14 days
4 days
4 days
30 days
0 days

30 days

Wed 01-07-15
Tue 21-07-15
Wed 01-07-15
Wed 24-06-15
Tue 04-08-15
Mon 07-09-15
Mon 07-09-15
Mon 07-09-15
Mon 07-09-15
Mon 07-09-15
Tue 15-09-15
Wed 07-10-15
Wed 07-10-15
Mon 16-11-15
Tue 24-11-15
Fri 04-12-15
Fri 04-12-15
Fri 04-12-15
Fri 04-12-15

25 days

Fri 15-01-16

7 days
8 days
4 days
7 days
0 days

35 days
28 days
7 days
0 days

265 days
3 days

87 days

Qtr 2, 2015
Apr May Jun

Qtr 3, 2015
Jul
Aug Sep

Qtr 4, 2015
Oct Nov Dec

23-06

Tue 23-06-15
Tue 23-06-15
Tue 23-06-15

4 days

8 days

15
Mar

04-08

15-09

24-11

Qtr 1, 2016
Jan Feb Mar

Qtr 2, 2016
Apr May Jun

Qtr 3, 2016
Jul
Aug Sep

Qtr 4, 2016
Oct Nov Dec

28

32 days

Fri 19-02-16

64 days

34

Assessment, Preparation and Submission of Monthly Progress Reports etc.


David Rose Street-Bagotville-Phase 1
David Rose Street-Bagotville-Phase 2
David Rose Street-Bagotville-Phase 3
Preparation and processing of Interim Payment Certificates.
Final Inspection, Assessment of Completed Works, Issuance of Take Over Certificate

30 days
14 days

Wed 06-01-16
Wed 06-01-16
Wed 10-02-16
Fri 25-03-16
Fri 04-12-15
Tue 05-04-16

35

Submission of Final Reports, Asbuilt Drawings, Financials and Maintenance Plans etc.

45 days

Tue 05-04-16

36

End of Technical Inspection of Construction Services


Defects Correction Period
End of Consultancy Services

0 days
133 days
0 days

Mon 06-06-16
Tue 07-06-16
Thu 08-12-16

29
30
31
32
33

37
38

David Rose Street-Bagotville Phase 3- Place and Compact C.R base and lay asphaltic surface

Project: Access and Drainage Infra-structure


Sub-projects
Date: Wed 16-09-15

7 days
7 days
7 days

Task

Project Summary

Inactive Milestone

Manual Summary Rollup

Progress

Split

External Tasks

Inactive Summary

Manual Summary

Deadline

Milestone

External Milestone

Manual Task

Start-only

Summary

Inactive Task

Duration-only

Finish-only

Page 1

You might also like