Professional Documents
Culture Documents
David Rose Final Design Report
David Rose Final Design Report
David Rose Final Design Report
Government of Guyana
Basic Needs Trust Fund 7th Programme
Contract No. CA 124/GUY
Executive Summary
This report covers the final design of David Rose Street, Bagotville, West Coast Demerara which was identified by
Basic Needs Trust Fund (BNTF) for rehabilitation works under the BNTF Seventh Programme funded by the
Caribbean Development Bank (CDB) and Government of Guyana (GoG). This final design encompasses field
investigations inclusive of in-situ California Bearing Ratio (CBR) tests and engineering surveys. Condition surveys of
the two culverts were also conducted and proposed rehabilitation works are also presented in this report.
The pavement design for this project is based on the American Association of State Highway and Transportation
Officials (AASHTO) Guide for Design of Pavement Structures (1993). Flexible pavements were considered based on
the existing conditions, available materials, practicality and cost effectiveness for pavement rehabilitation and
reconstruction. The material selection, constructability, flexibility of future pavement rehabilitation, upgrades and long
term durability have also been taken into consideration during the pavement selection process. Based on the 24
hours traffic study, the projected traffic over the 15-year design life was less than 50,000 ESALs for this street. As
such, the minimum design traffic loads of 50,000 ESALs were used in the design as recommended in the AASTHO
Guide.
Based on our visual assessment, pavement testing and geotechnical investigation, pavement sections were
noticeably deteriorated with potholes, depressions and waterlogged. As such, rehabilitation strategies were proposed
for the various pavements. The works generally consist of rehabilitating the existing base course with white
sand/sand clay and crushed stone and sealing of the roads with a layer of asphaltic concrete. The western section of
the street will require full construction from sub-grade to wearing course.
Reinforced concrete head and wing walls are proposed at the entrance and also for the Glasgow road intersection.
Head and wing walls are proposed at the intersection since the roadway width is narrow and will continue to get
narrower if headwalls are not installed. All roadside drains are to be either de-silted or reshaped as appropriate.
Based on the calculated quantities and other estimated costs a final sum of US$178,949(GY$36,684,537) was
computed for construction works which is 99% of the total allocated budget of the project.
Utilities companies were also notified and provided feedback on existing water lines and wires/cables. The
construction phase will be completed within four (4) months. A Gantt chart of the consultants schedule is also
provided in
Appendix 7.
Table of Contents
Executive Summary .......................................................................................................................................................1
1.0
Introduction .......................................................................................................................................................1
2.0
Project Background...........................................................................................................................................2
2.1
2.2
Demographics ..............................................................................................................................................3
2.2.1
2.2.2
2.2
3.0
3.1
3.2
3.2.1
Methodology...........................................................................................................................................10
3.2.2
3.2.3
3.2.3
3.2.4.1
3.2.4.2
3.2.5
3.2.6
3.3
3.3.1
3.3.2
3.3.2.1
3.3.2.2
3.3.2.3
3.3.3
3.4
Appendices ..................................................................................................................................................................23
Appendix 1 Design Calculations & Condition Survey ............................................................................................24
Appendix 1A Traffic Survey & Analysis (Estimated ESAL Value .........................................................................25
Appendix 1B Dynamic Cone Penetration Test (DCP) & California Bearing Ratio ...............................................26
List of Figures
Figure 1-Showing a Satellite Image of the Project Area at an Altitude of 3781 ft...................................................2
Figure 2-Deteriorated Roadway Chainage 0+420m .................................................................................................. .8
Figure 3-Deteriorated Roadway- Chainage 0+280m................................................................................................. .8
Figure 4-Deteriorated Roadway ,Chainage 0+690m ................................................................................................. .9
Figure 5-Glasgow Road Intersection,Chainage 0+0590m ....................................................................................... .9
Figure 6- Showing gradient of finished road and clay shoulders..........................................................................15
Figure 7- Glasgow Intersection: Deteriorated carriageway, Chainage 0+615m ...................................................31
Figure 8- Deteriorated Carriageway with minor depressions, Chainage 0+690m ................................................31
Figure 9- Deteriorated Carriageway with depressions, Chainage 0+500m ...........................................................31
Figure 10-Test Pit at Chainage 0+710m ...................................................................................................................32
Figure 11-Garbage Along Side Roadway ................................................................................................................ .32
Figure 12-Deteriorated Carriageway showing large depressions .........................................................................32
List of Tables
Table 1-Diversification of skills amongst residents..................................................................................................3
Table 2-Population Disaggregated by sex (Source La-Grange/Nismes NDC) ........................................................4
Table 3-Social Development Profile to produce more marketable residents. ........................................................5
Table 4-Pavement Design Inputs ..............................................................................................................................17
Table 5-Proposed Scope of Works ...........................................................................................................................19
Table 6-Section 1:Chainage 0+000m - 0+615m (Road width 3.65m / 12ft.) ...........................................................20
Table 7-Section 2:Chainage 0+615m- 0+690m (Road width 2.43m / 8ft.) ..............................................................20
Table 8-Section 2:Chainage 0+690m - 0+745m (Road width 2.43m / 8ft.) .............................................................20
Table 9 - Summary of Final Estimate .......................................................................................................................21
Appendices
Appendix 1Design Calculations & Condition Survey
Appendix 1A Traffic Survey & Analysis (Estimated ESAL Value
Appendix 1B Dynamic Cone Penetration Test (DCP) & California Bearing Ratio (CBR)
Appendix 1C Existing Pavement Profile & Test Pits
Appendix 1D AASTHO 1993 - Algorithm Analysis (Structural Number)
Appendix 1E Interlayer Checks
Appendix 2- Photographs
Appendix 3- Final Design Drawings
Appendix 4-Final Estimate
Appendix 5-Correspondences
Appendix 6-Framework for Environmental and Social Assessment
Appendix 7-Consultant Work Schedule
1.0 Introduction
Caribbean Engineering and Management Consultants Inc (CEMCO) was engaged by the Caribbean Development
Bank (CDB) to produce engineering design, construction drawings and supervisory services for the improvement of
David Rose Street, located in Bagotville, West Bank Demerara, Region 3. The length and width of this street is 745
meters and 3.7 meters respectively. The roadway will directly benefit approximately 850 residents in the Bagotville
community.
The allocated CDB budget for end of construction cost is US$179,080 (GY$36,711,400) with a total budget utilization
of US$178,949(GY$36,684,537).
CEMCO is tasked with conducting all investigations and produce engineering designs and estimates for constructing
this roadway and supporting infrastructure within the Clients budget. Tender Documents is a deliverable of the Final
Design Phase.
An initial site visit was made to the sites by representatives of BNTF, [Mr. Utoh Project Engineer] and CEMCOs
design and supervision team, [Team Leader, Mr. P. Bonar Chief Engineer and others] and members of the
respective communities on the 23rd June 2015. Surveys and field work started on the 24th June 2015.
This report presents the findings of our assessment of the roads (condition survey), the sub-surface investigation and
analysis, the plans, profiles and cross sections obtained from the surveys, the required design interventions, the
proposed design for the pavements and associated infrastructure as well as final cost estimates and
recommendations.
This Report is intended to provide the Client with all the necessary information required to make an informed decision
on the preferred design option to be pursued as well as the scope of intervention and prioritization.
2.0
Project Background
2.1 Historical and Physical
Profle
Bagotville is located on the West Bank of Demerara; Administrative Region No. 3: approximately five (5) miles (8
Kilometres) from Georgetown and is accessible via the Demerara Harbour Bridge. In 1848 a group of slaves bought
the village from a proprietor known as Mr. Bagot, hence the name Bagotville. Residents normally hold an annual
village day fair to showcase cultural food, games and to appreciate a sense of community unity.
Bagotville is bordered by La-grange to the south, Nismes to the north and Demerara River to the east. The
community is divided into residential housing and farmlands. It is accessible at all times by buses which traverse the
main roads from early in the morning to late in the evenings throughout the year. Most of the houses within Bagotville
are comprised of timber and concrete structures; that have readily access to potable water, electricity and garbage
disposal services (NDC and Private Sectors). Community Streets in Bagotville consist of a flexible pavement design
with a Double Bituminous Surface Treatment.
Figure 1-Showing a Satellite Image of the Project Area at an Altitude of 3781 ft.
2.2
Demographics
2.2.1
Economic Profle
Based on the stakeholders meeting held on the 20th June, 2014 it was identified that most of the working population
are involved the following sectors:
Earning/Living
Occupation/Skills
Skills Needed
Men
Qualified
-Teachers
-Private and Public Sectors Employees
Craftsmen e.g.
-Carpenters
Skilled
-Welders
-Electricians
-Masons)
Unskilled
-Farmers
-Hydroponics
-Self-employed
Women
-Teachers
Qualified
-Nurses,
-Private and Public Sectors Employees
Skilled
Unskilled
-Self-employed
-Sewing
-Housewives
-Catering
2.2.2
Social Profle
Population
During the Stakeholders meeting on the 20th June,2014 the following information was submitted by the LaGrange/Nismes Neighbourhood Democratic Council in relations to David Rose Street.
Number of Households 99
Approximately twenty-four percent (24%) or 200 persons of the population are children under the age of 14
years.
Approximately one percent (1%) of the households are headed by a single parent, who are mostly women.
Age
Males
Females
Adults ( 25 years)
140
200
131
179
Child ( 14 years )
119
81
Sub-Total
390
460
Total
850
African
- 90%
East Indian
- 10%
Some of the Community Infrastructure/ Social Services availability to residents in Bagotville are listed below:
Nursing/Medical Station/ Clinic
- NO
Childcare Centre
- YES
- YES
Library
- YES
Police Station
- YES
Womens Shelter
- NO
Children Services
- NO
According to the La-grange/Nismes NDC all of the social services within the community are adequately equipped and
staffed to meet the needs of the community. Residents have also indicated their availability to participate in
community
works from which youths can benefit; whether it be paid work or skills development.
Sex
Needs
Males
Recreational Facilities
Challenges
Skills Training
Females
Impact
training facilities
-Homecare
Becoming
equipped
with
-Parenting
themselves marketable.
-Sewing
Table 3-Social Development Profile to produce more marketable residents.
3.0
Final Design
3.1
Surveys
Condition
The existing condition of the timber bridge and existing HDPE pipe culvert and the need for
rehabilitation works.
2. Using the results of the data obtained pavement and geometric design drawings were done using the
American Association of State Highway and Transportation Officials (AASHTO) Guide for Design of
Pavement Structures (1993). This section incorporates the following parameters:
Material Properties (Load bearing characteristics of the various pavement materials and supporting
road bed soils)
Flexible pavements were considered based on the existing conditions, practicality and cost effectiveness for both
pavement rehabilitation and widening.
Under AASHTO 1993 pavement design protocol, the Design Structural Number (SNDesign) for every pavement is
determined to estimate the viability of the rehabilitation strategy over the design life of the pavement for a known
Equivalent Single Axle Load (ESAL). SNDesign for the various pavements is calculated using the following formulation:
.eq (1)
Where i = every layer in the proposed structural layer of the pavement after rehabilitation;
n = Number of material layers;
ai = Structural Coefficient of ith layer;
Di = Layer thickness of ith layer; and
mi = Drainage Coefficient of ith layer.
10
The basic concept of pavement design based upon AASHTO, 1993 protocol for flexible pavements requires firstly
determining the required thickness of the pavement based upon the level of traffic. The associated performance
period is then corrected for any environmental-associated losses (Pi = Initial Serviceability = 4.5 and Po =
Terminal Serviceability = 2.0) for a suitable pavement design over a design life of the pavement, the following
equation is used
to estimate the New Structural Number (called SNNew):
.eq(2)
Where
w18 = ESAL repetitions expected during the design life;
ZR and So= Reliability and Standard Deviation of the usage of pavement and type of structure
(75% and 0.44, respectively);
SNNew = New Structural Number that the pavement must satisfy;
Pi = Initial Serviceability =4.2;
Po= Terminal Serviceability = 2.0; and
MR = Subgrade Resilient Modulus (estimated form the back-calculation protocol).
Equation 2 was developed as a regression model and is the primary flexible pavement design protocol that is used by
AASHTO, 1993 pavement design manual. It relates the ESALs to Structural Number, serviceability drop and subgrade
resilient modulus using reliability concepts. The derivation of this equation is based upon AASHTO Road test that was
performed in USA in the 1960s. For a rehabilitation strategy to be activated, the following rationale has to satisfy:
eq(3)
Once the scenario presented in Eq. 2 is satisfied, a rehabilitation alternative will be chosen such that the following
condition is satisfied.
SNDes > SNReq.eq(4)
The various rehabilitation and reconstruction options being presented in the latter sections were based on the above
mentioned design criterion with the pertinent information obtained from our geotechnical investigation.
1. Design reinforced HDPE concrete culverts.
2. From the designs produced cost estimate were prepared using current prices.
11
3.2.2
Materials Selection
The following are typical materials available and used in road and highway construction in Guyana:
Bitumen: Typically imported and is used during the hot mix asphalt production.
Crushed Gravel (1st Grade Crushed Stone): Crushed stone used in road construction in Guyana comes
from the Essequibo county with the Highland natural region and is delivered to Georgetown via barges and
trucks. The use of this material as a road base or aggregate for asphaltic concrete is extensive throughout
Guyana. There are basically two types of material available, Gabbro and Granite; the former is the preferred
choice for both road base and asphaltic concrete applications. The California Bearing Ratio (CBR) for this
material ranges from 60% to 100%.
White Sand (WS): This natural sand is fine to medium grained and is readily available along the hilly sand
and clay natural region. White sand is extensively used locally for road construction and is mainly used as an
improved subgrade, drainage layer or as a component for blending with other materials to be mentioned
below.
White Sand/ Sand Clay (WS/SC): It is one of the most extensively used road construction materials
throughout Guyana. It is readily available from open pits at Timehri, East Bank Demerara. Historically the
sand clay is typically mixed with white sand in ratios of 75:25 to 60:40 depending on the plasticity derived
during material sampling and testing. The moisture content of the material can be difficult to control due to
the local climatic and ground conditions in the pits. The CBR for the WS/SC typically ranges from 25%-50%
and
the common practice is to utilize it in the base of low volume local roads and sub-base on primary roads.
12
3.2.3
The predicted loading is simply the predicted number of 80 kN (18,000 lbs) along with the ESALs that the pavement
will experience over its design lifetime, which is 15 years for this project. The traffic study was for a continuous 24
hours period which was conducted for each of the roadway. (See Appendix I). The formula below represents the
ESAL and is used in to estimate the ESAL value for each roadway (See Appendix I). AASTHO 1993 recommended,
when the ESAL value is less than the minimum value, 50,000 ESAL should be used for low volume community roads.
This scenario was applicable for David Rose Street.
..Eq(5)
Where:
ADT Annual Daily Traffic
T Percentage of Trucks
Tf Truck Factor
G (1+r)0.58y
D - Directional Distribution Factor
L - Lane Distribution Factor
Y Design Years
These pavement parameters are explained in Appendix 1.
3.2.3
Geotechnical Investigation
13
3.2.5
The existing HDPE pipe culvert at the entrance to this street will be upgraded with wing and head walls. The existing
900 mm diameter HDPE pipe will be cleaned and reused. Also, head and wing walls will be installed at the Glasgow
road intersection and the 900 mm diameter existing steel barrel pipe will be cleaned and reused. All roadside earthen
drains will be de-silted and reshaped.
3.2.6
This is a community access road; lane marks and edge marks will not be included in this contract except for the
junction linking the roadway with the West Bank Demerara Main Public Road (30m from the WBD Main Road).
Painting of speed humps, stop marking, stop lines and installation of STOP signs are included for installation and as
detailed on drawings.
Four (4) speed humps are included in the scope of works at chainages 0+30m, 0+245m, 0+590m and 0+615m.
14
Geometric Design
The existing road width from 0+00m to 0+615m is 3.05m (10ft.) while 0+615m to 0+745m has an existing road width
of 2.44m. Follow field data analysis which comprised of boreholes and test pits; there was visible evidence of existing
sub base layers which allowed for the expansion of the current roadway from 3.1m to 3.67m (12ft). This expansion is
only scheduled for the first section of the roadway as this is the most trafficked region and due to the limitations of the
budget. However there will an extension of the roadway from 0+690m to 0+745m which requires full reconstruction
as there is no existing sub base layer (trial test pit dug at 0+710m only indicating clay layer); This further extension of
the 2.44m (8ft.) roadway is to incorporate a more easily flow of access to the burial ground. The entire roadway will
have a cambered of 2% to accommodate rainfall runoff and a graded shoulder slope of 3% as shown in cross
sectional figure below. For Average Daily Traffic (ADT) of 2000 to 4000 for residential access roads; a width of
3.05m 3.6m is recommended. Road widths may be reduced by 0.3m to 0.6m based on the engineers judgement
regarding space available as what was done for chainage 0+590m to 0 + 745m. (AASHTO Geometric Standards
Green Book).
15
There is currently large earthen drains located on northern side of the roadway spanning a width of 3.05m with a
slope gradient of approximately 1:2. The flow direction is from west to east and outflows into the West Bank
Demerara Public Road main drain which discharges into Canal Polder No. 1 main canal. The proposed drainage
work includes the desilting and reshaping of the drains but the depth and slope gradient will be maintained as there is
no visible signs of slope failures along the carriageway. The current width of the clay shoulders exceeds 1.22m
(4ft.) and will not present any future slippage of the roadway. At Glasgow road intersection the radius of the transition
zone was determined in relation to the width of the existing and proposed road carriageways hence for the 2.44m
width road a transition radius of 3.05m (10ft.) was utilized. Likewise a transition radius of 4.57m (15ft.) was used at
the entrance of the roadway i.e. the junction of David Rose Street and West Bank Demerara Main Public Road (The
2011 AASHTO Green Book for Geometric Standards was considered).
16
3.3.2
Design Criteria
Design parameter
Value
4.2
Terminal Serviceability, Pt
2.0
2.2
15
Reliability, R %
75
Standard Deviation, So
0.4
(3000) 2% CBR
0.44
0.25
0.08
0.141
0.11
0.07
0.42
Pulverized materials
0.12
Burnt Earth
0.05
17
18
3.3.3
The table below highlights the proposed scope of works with alterations made to maximize the usage of the budget
without comprising the durability of the road.
Description
Comments
i.
ii.
iii.
iv.
v.
vi.
vii.
from
i)
19
38 mm Asphalt Concrete
38 mm Asphalt Concrete
Clay
20
General Summary
Bill No.A: Preliminaries
8,220.00
Amount
(GYD)
1,685,000.00
136,926.00
28,069,837.00
4,181.00
857,200.00
29,622.00
6,072,500.00
Sub-total of Bills
178,949.00
36,684,537.00
179,080.00
36,711,400.00
21
4.0
There will be several issues which will arise during the construction phase; some of which are listed below.
During construction of the reinforced concrete headwalls and wing walls of the culvert there will be minor
inconvenience caused from the rerouting of traffic at the junction of David Rose Street and WBD Public
Road i.e. there will be one way flow of traffic at the head of the roadway during construction.
Structures to be removed include a side shop located at 0+015m and an abandoned car on the edge of the
roadway.
GWI The underground water utility line will be temporarily relocated to remove the possibility of rupturing
any pipelines which may cause further distress to residents. A lump sum (Bill D-Structures; Item D1.2.1) has
been included in the Final Estimates to accommodate for this.
GPL- The existing power utility poles are located within a close proximity of the proposed roadway.
Most of the residential entrances are timber bridges and out of the proposed road carriageway hence no
problems during construction.
22
Appendic
es
23
24
Appendix
1A
Traffic Survey & Analysis (Estimated ESAL Value)
25
Project Name:
Client
Description:
Prepared By:
Checked By:
Reference:
ESAL Definition
The 1993 AASHTO Guide for Design of Pavement Structures states that "the damage effect of the passage of an axle of any mass (commonly called load) can be represented by a number of 18-kip equivalent single axle loads or ESAL's."
Variables in ESAL Calculations
According to the AASHTO Guide, several variables can impact the load equivalency factors and therefore will impact the calculated ESAL's. The variables are: pavement type (rigid or flexible), thickness, and terminal serviceability used for design. This spreadsheet program only calculates ESAL's
for flexible pavements. The thickness and terminal serviceability variables are accounted for at the bottom of the AASHTO ESAL calculation sheets with notes on suggest input values for various applications.
Axle Load and Type
Vehicles - (24 Hrs Traffic)
Passenger Cars
Passenger Buses
Small Canters/Vans/ Jeeps / Pick Ups
Large Canters
Sand Trucks
Garbage Trucks (Full)
West to East
East to West
Axle 1 (k)
46
12
6
0
0
1
50
10
6
0
0
1
2S
2S
2S
2S
8S
8S
Axle 2 (k)
2S
4S
4S
4S
24 T
24 T
Gross
Weight
Axle 3 (k)
S
4
S
6
S
6
S
S
32
S
32
Comments on Variables
Equivalency Factor
Axle 1
Axle 2
0.002
0.002
0.002
0.002
0.613
1.56
0.002
0.02
0.02
0.02
1.08
1.23
Axle 3
ADT
132
Typical ranges are 50-800 vehicles for residential streets, 700-5,000 vehicles for collectors, and 3,000-50,000+ vehicles for arterials.
Number of Years
YRS
15
Pavement designs typically have a design life ranging from 15-30+ years.
GR
Growth rates typically range from 1 to 3 percent per year; this growth rate is applied to all traffic, not just trucks.
Growth Factor
1.40666296
GF
20.02358764
DD
100
A 50-50 split between traffic going in each direction on the roadway typically is used (e.g., a Directional Distribution of 50%). In some cases, however, a difference in traffic patterns
may necessitate a directional distribution other than 50%, such as a particular area generating more trips over a long period of time than the number of trips that it attracts. AASTHO
recommended that the factor can vary from 30 % to 70 %. Since the vehicle will be traversing on the same wheel path most of the time (road with 12 ft), the factor is taken as 100%.
Design lane distribution refers to the percent of vehicles in one direction that use one lane of the roadway the most. For example, on 4-lane divided highways (e.g., 2 lanes in each
direction), 90% of the traffic on average uses the right (or driving lane) and 10% of the traffic uses the left lane (or passing lane). Indian Roads Congress (IRC - 37-2001)
recommended that for a single laneroad, the factor is 1; for a two -lane road with single carriagewa, the factor is 0.75, for a four lane single carriageway it is 0.40. Clause 2.2.1 in the
AASTHO under Taffic provide a table to estimate the Lane Factor.
LD
100
TP
1.515151515
TF
1.2
Function of the Growth Rate and the design live of the pavement.
Typical ranges include 1-3% for residential streets, 3-15% for collectors, and 5-30% for arterials.
The truck factor characterizes the average number of ESALs per truck. FHWAs Traffic Monitoring Guide (TMG) provides guidance on such characterizations. Vehicles such as
motorcycles, passenger cars, vans and pickup trucks have negligible impact on the truck factor. Buses can truck factors ranging from 0.57 ESALs/bus for a typical-length, empty bus to
up to 6.17 ESALs/bus for articulated buses with all seats filled and standing passengers. Similarly, the truck factor for trucks can have a very large range, depending on configuration and
weight restrictions. Passenger car equivalent for trucks = 1.2 (Which was used for WCD and EBB Road esign Project since Since overloaded truck is common and was encountered
during the axle load tests, an average truck factor of 1.2 ESAL/truck is utilised to address this issue.). The safety factor incorporated would also future truck upgrades to satisfy the
request of local residents.
18,484
Since the ESAL Value is less than the minimum recommended by AASTHO 1993, 50,000 ESAL will be use in this design
Recommended ESAL
Appendix
1B
Dynamic Cone Penetration Test (DCP) & California Bearing Ratio
26
Name
of
Project:
BNTF
Roads
Upgrade
Project
Road:
David Rose Street, Bagotville, WBD
Borehole No. 1
:
Chainage:
0+010 m
Lane:
Northern Lane @ 450mm offset from edge (Northern)
No. Of
Blows
(1)
0
Accumulative Penetration
Per
Penetration/
Blow Set/mm
mm (2)
(3)
10
Penetration
Per
Blow/mm (4)
Hammer Blow
Factor
(5)
CBR % (7)
94
84
16.8
17
12.4
147
53
10.6
11
20.8
188
41
8.2
27.7
240
52
10.4
10
21.2
294
54
10.8
11
20.3
355
61
12.2
12
17.7
411
56
18.7
19
11.0
445
34
34.0
34
5.6
467
22
22.0
22
9.2
500
33
33.0
33
5.8
525
25
25.0
25
7.9
560
35
35.0
35
5.4
580
20
20.0
20
10.2
652
72
72.0
72
2.4
1
1
1
1
729
786
830
870
77
57
44
40
77.0
57.0
44.0
40.0
1
1
1
1
77
57
44
40
2.3
3.2
4.2
4.7
907
37
37.0
37
5.1
937
30
30.0
30
6.5
1
1
955
980
18
25
18.0
25.0
1
1
18
25
11.5
7.9
1
1
1
1
100
5
103
0
105
3
107
5
109
25
25
23
22
25.0
25.0
23.0
22.0
1
1
1
1
25
25
23
22
7.9
7.9
8.7
9.2
22
23
22.0
23.0
1
1
22
23
9.2
8.7
23
22
20
23.0
22.0
20.0
1
1
1
23
22
20
8.7
9.2
10.2
1
1
1
1
1
7
112
0
114
3
116
5
118
5
Name
BNTF Roads Upgrade Project
of
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 2
:
Chainage:
0+060 m
Lane:
Southern Lane 450mm offset from edge
No. OfName
Accumulative
Penetration
Penetration
Hammer Blow
DCP Index (6)
CBR % (7)
of
BNTF Roads
Blows Projec
Per Upgrade Project
Per
Factor
Penetration/
(1) t:
Blow Set/mm
Blow/mm (4)
(5)
mm (2)
(3)
Road: 19
David Rose Street, Bagotville, WBD
0
Borehole
5
65No. 3
46
9.2
1
9
24.3
:
5
106
41
8.2
1
8
27.7
Chainage:
0+120 m
5
146
40
8.0
1
8
28.4
Lane:
Center of Roadway
5
188
42
8.4
1
8
26.9
No. Of
Accumulative Penetration
Penetration
Hammer Blow
DCP Index (6)
CBR % (7)
5
9.0 Per
1
9
24.9
Blows233 Penetration/45 Per
Factor
(1) 287
(5)
5
10.8 Blow/mm (4)1
11
20.3
mm (2) 54 Blow Set/mm
4
152(3)
38.0
1
38
5.0
0 439
0
1
5 541
43
56
43
56.0
8.6
56
3.2
26.2
76
46
33
46.0
6.6
46
4.0
35.3
578
110
37
34
37.0
6.8
37
5.1
34.1
605
145
27
35
27.0
7.0
27
7.3
33.0
633
183
28
38
28.0
7.6
28
7.0
30.1
658
221
25
38
25.0
7.6
25
7.9
30.1
680
273
22
52
22.0
10.4
22
10
9.2
21.2
1
1
1
1
1
700
718
736
755
771
340
20
18
18
19
16
67
20.0
18.0
18.0
19.0
16.0
33.5
1
1
1
1
1
34
10.2
11.5
11.5
10.8
13.1
5.7
10
20
18
18
19
16
787
625
16
38
16.0
38.0
13
16
38
13.1
5.0
1
1
803
819
655
16
16
30
16.0
16.0
30.0
1
1
14
16
16
30
13.1
13.1
6.5
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
495
834
849
863
872
891
906
920
934
948
960
973
986
100
0
101
3
102
6
104
1
105
6
107
2
111
5
426
496
545
587
680
703
724
745
764
782
799
815
832
847
863
877
892
905
920
934
949
963
975
990
100
5
101
9
103
3
104
7
106
0
107
4
108
9
15
15
14
9
19
15
14
14
14
12
13
13
14
13
13
15
15
16
43
86
70
49
42
25
23
21
21
19
18
17
16
17
15
16
14
15
13
15
14
15
14
12
15
15
14
14
14
13
14
15
15.0
15.0
14.0
9.0
19.0
15.0
14.0
14.0
14.0
12.0
13.0
13.0
14.0
13.0
13.0
15.0
15.0
16.0
14.3
86.0
70.0
49.0
42.0
25.0
23.0
21.0
21.0
19.0
18.0
17.0
16.0
17.0
15.0
16.0
14.0
15.0
13.0
15.0
14.0
15.0
14.0
12.0
15.0
15.0
14.0
14.0
14.0
13.0
14.0
15.0
Name
David Rose Street, Bagotville, WBD
of
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 4
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
9
11
12
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
15
15
14
9
19
15
14
14
14
12
13
13
14
13
13
15
15
16
14
86
70
49
42
25
23
21
21
19
18
17
16
17
15
16
14
15
13
15
14
15
14
12
15
15
14
14
14
13
14
15
14.1
14.1
15.2
24.9
10.8
14.1
15.2
15.2
15.2
18.1
16.5
16.5
15.2
16.5
16.5
14.1
14.1
13.1
14.8
2.0
2.5
3.7
4.4
7.9
8.7
9.6
9.6
10.8
11.5
12.2
13.1
12.2
14.1
13.1
15.2
14.1
16.5
14.1
15.2
14.1
15.2
18.1
14.1
14.1
15.2
15.2
15.2
16.5
15.2
14.1
:
Chainage:
0+180 m
Lane:
Southern lane 450mm offset from edge
No. OfName
Accumulative
Penetration
Penetration
Hammer Blow
of
David Rose Street, Bagotville, WBD
Blows Projec
Per
Per
Factor
Penetration/
(1) t:
Blow Set/mm
Blow/mm (4)
(5)
mm (2)
(3) Rose Street, Bagotville, WBD
Road: 10
David
0
Borehole
5
60No. 5
50
10.0
1
:
5
99
39
7.8
2
Chainage:
0+240 m
5
138
39
7.8
3
Lane:
Northern Lane 450mm offset from edge
5
183
45
9.0
4 Blow
No. OfName
Accumulative
Penetration
Penetration
Hammer
of
David Rose 120
Street, Bagotville,
WBD
5
303
24.0
5
Blows Projec
Per
Per
Factor
Penetration/
(1)
Blow
Set/mm
Blow/mm
(4)
(5)
1
355
52
52.0
6
t:
mm (2)
(3)
Road:
David
Rose
Street,
Bagotville,
WBD
1
405
50
50.0
7
0
10
Borehole
1
450
45
45.0
8
5
73No. 6
63
12.6
11
:
1
495
45
45.0
9
5
115
42
8.4
12
Chainage:
0+300 m
1
537
42
42.0
10
5
153
38
7.6
13
Lane:
Center of Roadway
1 Of
570
33
33.0
11 Blow
187
34
6.8
14
No.5
Accumulative
Penetration
Penetration
Hammer
Name of
Blows
Per Street,
Per 32.0
Factor
Bagotville,
Penetration/
1
602 David Rose
32
12
5
221
34
6.8WBD
15
Projec
(1)
Blow Set/mm
Blow/mm
(5)
mm
(2)
1
627
25
25.0
13
5
262
41
8.2 (4)
16
t:
(3)
0
10
11
0
5
7
1
1
650
23 Street, Bagotville,
23.0
14
5
48
9.6
17
Road: 310
David Rose
WBD
5
50No. 7
53
45
59
55
48
53
40
52
54
10.6
10.4
10.8
9.6
8.0
22
31
43
51
1
673
23
23.0
15
Borehole
4
422
112
28.0
18
5
1
1
1
5
1
1
5
1
1
5
1
1
2
5
3
1
1
5
1
2
1
1
5
3
1
5
1
1
4
1
1
1
1
1
1
1
1
1
1
104
101
113
87
98
78
37
45
33
42
58
11.6
7.4
9.0
6.6
8.4
23
32
44
52
:
694
21
21.0
16
486
64
64.0
19
Chainage:
0+360
m
713
19
19.0
17
122
147
109
140
172
35
43
42
31
39
59
11.8
7.0
8.6
8.4
6.2
7.8
24
33
45
53
545
59
59.0
20
Lane:
Northern 51
Lane @ 450mm
offset from edge
732
19
19.0
18
165
193
182
140
180
223
43
46
42
31
40
10.2
8.6
9.2
8.4
6.2
8.0
25
34
46
54
589
44
44.0
21
18
18.0
19
Name of 750
202
252
223
172
224
277
37
59
41
32
44
54
11.8
10.8
7.4
8.2
6.4
8.8
26
35
47
55
Bagotville,
626 David Rose Street,
37
37.0WBD
22
Projec 767
17
17.0
20
245
320
261
208
293
365
43
68
38
36
69
88
34.0
13.8
29.3
8.6
7.6
7.2
27
36
48
56
659
33
33.0
23
t:
783
16
16.0
21
349
375
372
297
255
435
104
55
36
47
79
70
20.8
55.0
39.5
70.0
7.2
9.4
28
49
37
57
Road: 800
David Rose
WBD
17 Street, Bagotville,
17.0
22
390
440
424
41
65
52
41.0
65.0
52.0
29
50
335
341
520
38
86
85
28.7
85.0
7.6
38
58
Borehole
No. 8
814
14
14.0
23
505
65
65.0
432
380
385
480
600
42
45
44
56
80
42.0
44.0
56.0
80.0
9.0
30
39
51
59
:
831
17
17.0
24
475
565
450
429
540
665
43
70
44
60
65
43.0
17.5
44.0
60.0
65.0
31
40
52
60
Chainage:
0+420 m
845
14
14.0
25
Lane:
Southern 55
Lane @ 450mm
offset from edge
513
611
483
472
595
38
46
33
43
38.0
46.0
33.0
43.0
55.0
32
41
53
860
15
15.0
26
Name of 637
547
522
513
34
39
41
42
34.0
39.0
41.0
42.0
33
42
54
879 David Rose Street,
19
19.0WBD
27
Bagotville,
Projec 551
579
560
32
38
32.0
38.0
34
43
888
9
9.0
28
t:
607
599
585
28
39
34
28.0
39.0
34.0
35
44
902
14
14.0
29
Road:
David Rose Street, Bagotville, WBD
637
614
38
29
38.0
29.0
36
45
916
14
14.0
30
Borehole No. 9
680
639
43
25
43.0
25.0
37
46
930
14
14.0
31
:
1
943
13
13.0
Chainage:
0+480 m
1 Lane:
956
13
13.0
Center of Roadway
1 Name of 970
14
14.0
David Rose Street,
Bagotville,
1
982
12
12.0WBD
Projec
1
996
14
14.0
t:
1
12 Street, Bagotville,
12.0
Road: 100
David Rose
WBD
8 No. 10
1
102
12
12.0
Borehole
0
:
3
105
35
11.7
5
Chainage:
0+540 m
Lane:
32
33
34
35
36
37
38
39
Name of
David Rose Street, Bagotville, WBD
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 11
:
Chainage:
0+600 m
Lane:
Northern Lane @ 450mm offset from edge
Name of
David Rose Street, Bagotville, WBD
Projec
t:
Road:
David Rose Street, Bagotville, WBD
Borehole No. 12
:
CBR % (7)
10
22.2
29.3
29.3
9
DCP Index
(6)
24
52
24.9
CBR
% (7)
8.3
3.5
50
3.7
45
13
45
8
4.1
17.1
4.1
26.9
42
8
7
DCP 33
Index
(6)
32
7
25
8
23
10
10
11
8
23
28
12
9
7
8
21
64
19
12
7
9
6
8
59
19
10
9
6
8
44
18
12
11
7
8
6
9
37
17
34
14
29
9
8
7
33
16
21
55
40
70
7
9
17
41
65
52
29
85
8
14
65
42
44
56
80
9
17
43
18
44
60
65
14
38
46
33
43
55
15
34
39
41
42
19
32
38
9
28
39
34
14
38
29
14
43
25
14
13
13
14
12
14
12
12
12
4.4
30.1
5.8% (7)
34.1
CBR
6.0
34.1
7.9
27.7
8.7
23.2
23.2
20.8
28.4
21.2
20.3
8.7
7.0
18.8
31.0
24.9
35.3
26.9
9.6
2.8
10.8
33.0
26.2
26.9
37.8
29.3
18.4
3.0
10.8
26.2
24.3
26.9
37.8
28.4
21.7
4.2
11.5
31.0
18.4
27.7
36.5
25.6
20.3
5.1
12.2
26.2
30.1
32.0
15.4
5.6
6.6
5.8
13.1
32.0
23.7
9.8
3.3
4.8
2.5
12.2
4.6
2.7
3.5
30.1
6.8
2.0
15.2
2.7
24.9
4.4
4.2
3.2
2.2
12.2
11.8
4.3
4.2
3.0
2.7
15.2
5.0
4.0
5.8
4.3
3.3
14.1
5.6
4.8
4.6
4.4
10.8
6.0
5.0
24.9
7.0
4.8
5.6
15.2
5.0
6.7
15.2
4.3
7.9
15.2
16.5
16.5
15.2
18.1
15.2
18.1
18.1
18.6
Chainage:
0+660 m
Lane:
Southern Lane @ 450mm offset from edge
No. Of
Accumulative Penetration
Penetration
Hammer Blow
Blows
Per
Per
Factor
Penetration/
(1)
Blow Set/mm
Blow/mm (4)
(5)
mm (2)
(3)
0
0
CBR % (7)
54
54
10.8
53
11
20.3
107
53
10.6
54
11
20.8
165
58
11.6
55
12
18.8
222
57
11.4
56
11
19.1
318
96
24.0
57
24
8.3
385
67
67.0
58
67
2.6
446
61
61.0
59
61
2.9
504
58
58.0
60
58
3.1
550
46
46.0
61
46
4.0
587
37
37.0
62
37
5.1
617
30
30.0
63
30
6.5
643
26
26.0
64
26
7.6
Appendix
1C
Existing Pavement Profile & Test Pits
27
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+010 m
Northern Lane @ 450mm offset from edge (Northern)
Material
Asphaltic Concrete
Crusher Run (Base)
Thickness (mm)
None
70
105
White Sand
200
Clay
Continuous
Remarks:
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+060 m
Southern Lane 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
90
60
70
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) Insitu CBR (%) = 292/ (DCP^1.12)
(iii.) Insitu CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+120 m
Center of Roadway
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
80
140
260
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+180 m
Southern lane 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
70
70
190
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+240 m
Northern Lane 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
50
90
190
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+300 m
Center of Roadway
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
40
120
250
Continuous
Remarks:
Done in Failure Zone
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+360 m
Northern Lane @ 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
70
140
210
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+420 m
Southern Lane @ 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
80
170
270
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+480 m
Center of Roadway
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
100
100
240
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+540 m
Southern Lane @ 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
90
120
180
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+600 m
Northern Lane @ 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
None
130
270
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Name of Project:
Road:
Borehole No. :
Chainage:
Lane:
0+660 m
Southern Lane @ 450mm offset from edge
Material
Asphaltic Concrete
Crusher Run (Base)
White Sand/ Sand Clay
White Sand
Clay
Thickness (mm)
None
None
120
275
Continuous
Remarks:
(i) DCP started on the White Sand / Sand Clay Layer.
(ii.) In-situ CBR (%) = 292/ (DCP^1.12)
(iii.) In-situ CBR equation is recommended by the ARMY Corps of Engineers. (ASTM D6951/D6951M )
Appendix
1D
AASTHO 1993 - Algorithm Analysis (Structural Number)
28
5.19
log10W18
4.7
0.2 PSI/2.
7
0.2 0.81481
5
5.19
2.32*log10M 8.07
8.06692131 8.0
R
1
7
MR
300
0
9.36*log10
(SN+1)
3.21
0.2 PSI/2.
7
0.2 0.81481
5
5.19
2.32*log10M 8.07
9.68853172 8.0
R
1
7
MR
1500
0
9.36*log10
(SN+1)
2.39
0.2 PSI/2.
7
0.2 0.81481
5
5.19
2.32*log10M 8.07
10.3869213 8.0
R
1
7
MR
3000
0
9.36*log10
(SN+1)
1.37
0.2 PSI/2.
7
0.2 0.81481
5
5.19
2.32*log10M 8.07
11.4938426 8.0
R
2
7
MR
9000
0
ZR
s0
ZR s0 SN
SN+1 9.36*log10
0.67
0.4 0.2 2.2
3.2 (SN+1)
4.73
4
7
0
4.8 Must be Greater than Log10 W18
log10W18
4.7
ZR
s0
ZR s0 SN
SN+1
0.67
0.4 0.2 1.2
2.2
4
7
0
Must be Greater than Log10 W18
log10W18
4.7
ZR
s0
ZR s0 SN
SN+1
0.67
0.4 0.2 0.8
1.8
4
7
0
Must be Greater than Log10 W18
log10W18
4.7
4.9
ZR
s0
ZR s0 SN
0.67
0.4 0.2 0.4
4
7
0
Must be Greater than Log10
W18
SN+1
1.4
Appendix
1E
Interlayer
Checks
29
SN1
Layer Coefficient
Propose
d
(inche
s)
Existing
(Inches)
0.4
0.6
0.4
AC
SN2
0.8
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
Existing
SN
Values
1.5
C.R
1.53
0.131
0.524
WS/SC
0.76
0.1
4.2
4.2
WS
7.3
0.09
0.42
SN3
1.2
SN4
2.2
0.42
0.72
0.72
Total SN (Actual)
2.264
Materials
AC
SN1
C.R
0.4
SN2
Proposed
SN
Values
Chainage
0+060 m
Propose
Layer Coefficient
d
Existing
(inche
(Inches)
s)
0.4
1.5
0.131
3.6
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
1.14
Existing
SN
Values
Proposed
SN
Values
0.6
1.53
0.4716
0.7
6
0.9
0.524
0.8
SN3
WS/SC
9
0.1
2.4
WS
2.8
0.09
2.8
0.9
1.2
SN4
2.2
2
0.252
0.252
Total SN (Actual)
2.276
1.6236
Chainage
0+120 m
Materials
Coefficient
SN
0.4
Layer
Existing
(Inches)
AC
0.4
C.R
0.131
3.15
Interlayer
Proposed
Checks (Inches);
(inches)
Greater than
(Minimum
1.5
Existing
SN
Values
Proposed
SN
Values
0.6
SN
2
0.8
1.53
0.41265
0.524
SN
1.2
WS/S
C
0.1
5.51
5.51
0.76
0.551
0.551
SN
2.2
Total SN
(Actual)
1.88435
2.5957
Materials
Coefficient
SN
Layer
AC
1.5
Chainage
0+180 m
Existin
Propose
g
d
(Inche
(inche
s)
s)
0.4
Existing
SN
Values
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
Proposed
SN
Values
0.6
0.4
C.R
0.36156
SN2
0.8
WS/SC
6
SN3
1.2
WS
0.6732
SN4
2.2
0.131
2.76
0.524
0.1
2.76
0.09
0.6732
7.48
1.53
0.76
0.6
7.48
Total SN (Actual)
Materials
SN1
AC
Layer Coefficient
0.4
C.R
0.262
SN2
0.8
WS/SC
5
SN
Chainage
0+240 m
Propose
Existing
d
(Inches)
(inche
s)
0.4
1.5
0.131
0.524
0.1
0.6
5.3
2.3972
1.63476
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
Existing
SN
Values
Proposed
SN
Values
0.6
2
3.54
1.53
0.76
0.5
0.5
1.2
WS
0.6732
SN4
2.2
0.09
0.6732
7.48
7.48
6.4
Total SN (Actual)
2.2972
Materials
Layer Coefficient
Chainage 0+300 m
Propose
Interlayer
d
Checks (Inches);
Existing
(inche
Greater than
(Inches)
s)
(Minimum
Thickness)
1.4352
Existing
SN
Values
Proposed
SN
Values
SN1
AC
SN2
0.8
SN3
1.2
SN4
2.2
0.4
0.4
1.5
C.R
0.20567
WS/SC
4.72
WS
0.8856
0.131
0.524
0.1
0.09
0.8856
0.6
1.57
4.72
9.84
1.53
0.76
0.472
9.84
Total SN (Actual)
2.4816
0.472
6.7
1.56327
Materials
SN1
AC
Layer Coefficient
0.4
1.5
0.4
C.R
0.36156
SN2
0.8
Existing
SN
Values
0.6
2.76
1.53
0.1
5.51
0.09
0.8343
9.27
0.76
0.551
9.27
0.551
5.8
Total SN (Actual)
2.5093
Materials
SN1
AC
Layer Coefficient
C.R
0.41265
SN2
0.8
Existing
SN
Values
6.69
0.09
0.9567
10.63
3.15
1.53
1.8735
0.669
10.63
0.669
5.8
Total SN (Actual)
2.63835
Materials
SN1
AC
0.4
Layer Coefficient
0.4
1.5
Proposed
SN
Values
0.6
3.15
0.1
WS
0.9567
SN4
2.2
1.74686
0.131
0.41265
WS/SC
6.69
SN3
1.2
Chainage 0+420 m
Propose
Interlayer
d
Checks (Inches);
Existing
(inche
Greater than
(Inches)
s)
(Minimum
Thickness)
0.4
1.5
0.4
Proposed
SN
Values
0.524
WS
0.8343
SN4
2.2
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
0.131
WS/SC
5.51
SN3
1.2
Chainage
0+360 m
Propose
d
Existing
(inche
(Inches)
s)
Chainage 0+480 m
Propose
Interlayer
d
Checks (Inches);
Existing
(inche
Greater than
(Inches)
s)
(Minimum
Thickness)
-
2.03835
Existing
SN
Values
Proposed
SN
Values
0.6
SN2
0.8
SN3
1.2
SN4
2.2
C.R
0.524
WS/SC
4
WS
0.8505
0.131
0.524
0.1
0.09
0.8505
9.45
1.53
0.76
0.4
9.45
Total SN (Actual)
2.3745
0.4
7.5
1.7745
SN1
AC
0.4
C.R
0.46374
SN2
0.8
0.4
1.5
0.131
Existing
SN
Values
Proposed
SN
Values
0.6
3.54
0.1
WS
0.9567
SN4
2.2
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
1.53
0.524
WS/SC
7.09
SN3
1.2
7.09
0.09
0.9567
0.76
0.709
10.63
10.63
0.709
4.1
Total SN (Actual)
2.7897
2.12944
Chainage 0+600 m
Materials
SN1
AC
Layer Coefficient
0.4
1.5
0.4
C.R
0
SN2
0.8
SN3
1.2
Interlayer
Checks (Inches);
Greater than
(Minimum
Thickness)
Existing
SN
Values
0.6
0.131
0.524
0.1
WS
0.9
0.09
5.11
0.9
1.53
0.76
0.511
10
10
0.511
6.3
Total SN (Actual)
2.535
Materials
Coefficient
Proposed
SN
Values
WS/SC
5.11
SN4
2.2
Propose
d
(inche
s)
Existing
(Inches)
Layer
Chainage 0+660 m
Existin
Propose
Interlayer
g
d
Checks (Inches);
(Inche
(inche
Greater than
s)
s)
(Minimum
Thickness)
SN1
0.4
1.411
Existing
SN
Values
Proposed
SN
Values
AC C.R
0.4
0.6
SN2
0.8
1.5
WS/SC
4.72
0.131
0
0.1
0
0.524
4.72
1.53
0.76
0.472
0.472
SN3
1.2
SN4
2.2
WS
0.81
0.09
6.7
0.81
Total SN (Actual)
2.406
1.282
Materials
SN1
AC
SN2
0.8
Layer Coefficient
0.4
Full
Reconstructio
n
Propose
Interlayer
Existing
d
Checks (Inches);
(Inches)
(inche
Greater than
s)
(Minimum
Thickness)
0.4
0.131
0.393
C.R
0
WS/SC
0.09
1.53
2.07
10
7.9
0.5
0
0
SN4
2.2
0
WS
Proposed
SN
Values
1.5
0.6
0.1
SN3
1.2
Existing
SN
Values
0.9
Total SN (Actual)
2.393
Appendix 2- Photographs
30
31
32
33
Statio
Sch
Bagostown
Cemetery
Sch
Health Centre
Nandy
Park
CANAL #1
Greenfiel
Park
Ch
Nismes
Nismes
Ch
Sluice
Gate
Healt
Centre
Sluice
Gate
Factory
Ch
Oilmill
Sch
Ch
Ch
Ch
Stanleytown
Sluice
Gate
L. Long
Notes
No.
Revision
Date
Initials
Legend
Drawn
L. Long
Designed
P. Deodat
Checked
P. Deodat
Approved
RB Latchmansingh
Consultant:
Client:
Title:
Date:
Dwg. No.:
Scale:
--
Status:
Sheet:
1 of 1
ML 1-1
-
ML 2-2
ML 1-1
ML 3-3
ML 2-2
-
ML 4-4
ML 3-3
ML 5-5
ML 4-4
-
ML 7-7
ML 6-6
ML 5-5
ML 6-6
-
ML 8-8
ML 7-7
ML 8-8
-
Longitudinal Profile
Longitudinal Profile
Longitudinal Profile
CH0+030 TO
0+615
CH0+615 TO
0+690
CH0+690 TO 0+745
34
Amount
(USD)
Amount
(GYD)
8,220.00
1,685,000.00
136,926.00
28,069,837.00
4,181.00
857,200.00
29,622.00
6,072,500.00
Sub-total of Bills
178,949.00
36,684,537.00
179,080.00
36,711,400.00
Item
Number
A.1
Item Description
Unit
Quantity
Rate GYD
Amount
GYD
PRELIMINARIES
A.1.1
LS
275,000
A.1.2
LS
450,000
A.1.3
Temporary Works
LS
75,000
A.1.4
LS
40,000
A.1.5
LS
85,000
A.1.6
LS
125,000
A.1.9
LS
185,000
A.2
Contractor's Facilities
A.2.1
Contractor's Welfare
LS
50,000
A.2.2
LS
40,000
LS
150,000
A.3
A.3.1
Engineer's Facilities
Allow a sum for rental of a site office for the Engineer (10'-0" x 10'-0")
with furniture, appliances and janitorial services. Engineer must be
supplied with drinking water on a daily basis. Site office should be
maintained during the project life.
Sub-Total Carried Forward
1,475,000
Item Description
Quantity
Brought Forward
A.4
Unit
Rate
(GYD)
Amount
(GYD)
1,475,000
Miscellaneous
A.4.1
Contractor's Programe
LS
35,000
A.4.2
LS
50,000
A.4.3
Progress photographs
LS
25,000
A.4.4
LS
100,000
PRELIMINARIES TOTAL
1,685,000
Bill B - Roadworks
Item Description
ROADWORKS
B.1
B.1.1
B.2
B.2.1
B.2.2
B.3
B.3.1
B.4
B.4.1
B.5
B.5.1
B.6
B.6.1
General Excavation
Scarify existing carriageway; average 150mm deep and compact to
95% of the maximum dry proctor density. As per Specifications
Section 5 Earthwork and Related Operations.
Excavation to Subgrade Level. As indicated in Profile Drawings. Subgrade should be compacted to design levels. As per Specifications
Section 5 Earthwork and Related Operations.
Surface Preparation
Grade, shape and compact existing shoulders to falls.As per
Specifications Section 5 Earthwork and Related Operations.
Imported Clay
Supply, place and compact in shoulders.As per Specifications As
per Specifications Section 5 Earthwork and Related Operations.
Sub Base - White Sand
Supply, place and compact White Sand in 150mm single layers.
Layers shall be compacted to a density of at least 95% of the
maximum density as determined by ASTM D- 1557 method A. As
per Specifications Section 7 White Sand Sub-base.
Lower Sub Base - White Sand / Sand Clay
Include the cost of all materials, multiple handling, stockpiling,
blending, placing, dewatering, pumping, compaction and trimming at
optimum moisture content, all clearing and grubbing of materials
pits, all stripping of overburden from the pits, if required, and all
incidentals necessary to complete the work. Layers shall be
compacted to a density of at least 95% of the maximum density as
determined by ASTM D- 1557 method A. A. As per Specifications
Section 8 Sand Clay/White Sand Sub base.
Sub-Total Carried Forward
Quantity
2,750
2,544
137
1,363
277
67
25
Unit
Rate
(GYD)
Amount
(GYD)
120
330,000
200
508,878
1,200
164,634
100
136,280
200
55,399
4,550
305,183
10,000
251,524
1,751,899
Bill B - Roadworks
Item Description
Quantity
Rate
(GYD)
Unit
Brought Forward
B.7
B.7.1
B.8
B.8.1
B.9
B.9.1
B.10
Speed Humps
Construction of Speed humps according to drawings or as directed
by Engineer. Rate should include for painting of humps. As per
Specifications Section 18.
B.11
Provisional Sum
Provisional Sum to be used as directed by the Engineer.
Total
Amount
(GYD)
1,751,899
324
3,200
2,557
PS
30,000
9,732,591
1,150
3,679,860
4,250
10,865,488
No
60,000
240,000
1,800,000
28,069,837
Bill C - Drainage
Item
Item Description
Nr
Quantity
Drainage
C.1.1
Provisional Sum
Provisional Sum to be used as directed by the Engineer.
Total
PS
C.2
Unit
1,520
Rate
(GYD)
235
Amount
(GYD)
357,200
500,000
857,200
Amount
Quantity
Unit
Amount
(GYD)
Rate (GYD)
D.1
D.1.1
CULVERTS - Type 1
Temporary Works
D.1.1.1
LS
150,000
D.1.1.2
LS
75,000
LS
100,000
LS
150,000
D.1.1.3
D.1.2
D.1.2.1
D.1.3
Section 5- Earthworks/Excavation
D.1.3.1
50
500
25,000
D.1.3.2
50
300
15,000
D.1.4
18
4,500
80,222
29
4,500
130,500
15,000
30,000
1.80
40,000
72,000
16
50,000
775,000
1,700
kg
400
680,000
55
1200
66,000.00
6.0
80000
480,000.00
D.1.4.1
D.1.5
2.00
D.1.5.2
D.1.5.3
D.1.6
D.1.7
2,233,500
STRUCTURES
Item
Number
Item Description
Quantity
Unit
Rate (GYD)
Amount
(GYD)
D.2
CULVERT - Type 2
D.2.1.
Temporary Works
D.2.1.1
L.S
150,000
D.2.1.2
LS
100,000
D.2.2
Relocation of Utilities
D.2.2.1
Allow for GWI to relocate water line. Include for all bends,etc.
LS
200,000
D.2.3
Section 5- Earthworks/Excavation
D.2.3.1
50
550
27,500
D.2.3.2
50
150
7,500
D.2.4
D.2.4.1
12
4,500
54,000
28
4,500
126,000
8,000
24,000
40,000
40,000
D.2.5
D.2.5.1
D.2.6
(cube strength)
D.2.6.2
10
50,000
500,000
D.2.6.3
1,360
kg
400
544,000
D.2.6.4
55
1,200
66,000
D.2.7
Provisional Sum
Provisional Sum to be used as directed by the Engineer.
PS
2,000,000
1,839,000
6,072,500
Appendix 5-Correspondences
35
July 15 2015
The
Chief
ExecutiveOfficer
GuyanaTelephone& TelegraphCo.,
69 Brickdam,
Georgetown,
Guyana.
Dear Sir/Madam,
<:>
BNTF Seventh Programme for the improvement of access roads and drainage in communities.
We have been engaged by the Bank to provide engineering services to the following access roads:
David Rose Street, Bagotville, West Bank Demerara.
Mahagony Street, Samatta Point, Golden Grove, East Bank Demerara.
Market Street, Beterverwagting, East Coast Oemerara.
We are requesting
underground
may have to take careful Consideration during the construction period. It will be
mutually beneficial if plans can be provided beforehand showing the actual location of these infrastructures so as to
afford a smooth construction programme and prevent any damages and disruptions.
We would appreciate receiving such information and guidance by July 20 2015.
Sincerely you'W
:
.................. !
..
~
R. B.
Latchmb h
Managing Director
New address-117 John Smith Street, Campbellville,
Georgetown Tel:223-8823
CE.MCOinc.
Tel: (+592) 226-2758, 226-2773 & 227-0481, 227-0542 Facsimile: 226-3930. E-mail: info@cemcoguyana.com
Registered Office@above address. Registered # 2820
July152015
The Chief Executive Officer
Corporate Complex,
Guyana Water Inc.,
Vllissengen Road and Church Street,
. Bel Air Park,
Georgetown,
Guyana.
Dear Sir/Madam,
Re: Basic Needs Trust Fund - Seventh Programme
REHABILITATION OF ACCESS ROADS AND DRAINAGE
The Basic Needs Trust Fund Office has received funding from the Caribbean Development Bank (COB) under the
BNTF Seventh Programmefor the improvement of access roads and drainage in communities.
We have been engaged by the Bank to provide engineering services to the following access roads:
'
David Rose Street, Bagotville, West Bank Demerara.
'----"
Contractor may have to take careful consideration during the construction period. It will be mutually beneficial if plans
can be provided beforehand showing the actual location of these infrastructures so as to afford a smooth
construction programme and prevent any damages and disruptions.
Attached are pictures showing existing GWI mains that are of concern to the
Bagotvilleproject. We would appreciate receiving such information and guidance by July 20
2015.
Sincerely yours,
cc:
. '-....,.,'
CE.MCO Inc.
Tel: (+592) 226-2758, 226-2773 & 227-0481, 227-0542 Facsimile: 226-3930. E-mail: info@cemcoguyana.com
Registered Office@above address. Registered # 2820
Figure 2-Showing
July152015
The
ProjectManager
CommercialOffice,
Guyana Power & Light,
Middle Street
Georgetown,
Guyana.
Dear Sir/Madam,
. The Basic Needs Trust Fund Office has received funding from the Caribbean Development Bank (COB) under the.
BNTF Seventh Programme for the improvement of access roads and drainage in communities.
We have been engaged by the Bank
to provide
l:~
whl
~l ..
R. B. Latchma~sing
Managing Directs
cc:
CEMCOhic.
Tel: ( +592) 226-2758, 226-2773 & 227-0481, 227-0542 Facsimile: 226-3930. E-mail: info@cemcoguyana.com
Registered Office@above address. Registered # 2820
36
Disposal of Waste
Traffic Management
Social Impacts
Reporting requirement
Monitoring Framework
37
38
Task Name
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Duration
Start
383 days
Tue 23-06-15
0 days
Tue 23-06-15
62 days
31 days
1 day
Wed 24-06-15
5 days
Wed 24-06-15
14 days
4 days
4 days
30 days
0 days
30 days
Wed 01-07-15
Tue 21-07-15
Wed 01-07-15
Wed 24-06-15
Tue 04-08-15
Mon 07-09-15
Mon 07-09-15
Mon 07-09-15
Mon 07-09-15
Mon 07-09-15
Tue 15-09-15
Wed 07-10-15
Wed 07-10-15
Mon 16-11-15
Tue 24-11-15
Fri 04-12-15
Fri 04-12-15
Fri 04-12-15
Fri 04-12-15
25 days
Fri 15-01-16
7 days
8 days
4 days
7 days
0 days
35 days
28 days
7 days
0 days
265 days
3 days
87 days
Qtr 2, 2015
Apr May Jun
Qtr 3, 2015
Jul
Aug Sep
Qtr 4, 2015
Oct Nov Dec
23-06
Tue 23-06-15
Tue 23-06-15
Tue 23-06-15
4 days
8 days
15
Mar
04-08
15-09
24-11
Qtr 1, 2016
Jan Feb Mar
Qtr 2, 2016
Apr May Jun
Qtr 3, 2016
Jul
Aug Sep
Qtr 4, 2016
Oct Nov Dec
28
32 days
Fri 19-02-16
64 days
34
30 days
14 days
Wed 06-01-16
Wed 06-01-16
Wed 10-02-16
Fri 25-03-16
Fri 04-12-15
Tue 05-04-16
35
Submission of Final Reports, Asbuilt Drawings, Financials and Maintenance Plans etc.
45 days
Tue 05-04-16
36
0 days
133 days
0 days
Mon 06-06-16
Tue 07-06-16
Thu 08-12-16
29
30
31
32
33
37
38
David Rose Street-Bagotville Phase 3- Place and Compact C.R base and lay asphaltic surface
7 days
7 days
7 days
Task
Project Summary
Inactive Milestone
Progress
Split
External Tasks
Inactive Summary
Manual Summary
Deadline
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 1