Professional Documents
Culture Documents
Pow Anhawan (FMR) - Final
Pow Anhawan (FMR) - Final
Barangay of Anhawan
Municipality of Dauin
Province of Negros Oriental, Region VII
SUB-PROJECT PROGRAM-OF-WORK
Project Title
Category
Physical Target
Total Sub-Project Cost
: 0.30 KM
PHP 1,854,700.00
Mode of Implementation
: By Contract
Project Description:
Sub-Project Duration
: 90 Calendar Days
Equipment/Tools Needed
Technical Personnel
No. of Laborers
: 90 person days
Sub-Project Location:
Sub-Project Site Location is 8KM away from Town Proper
Item
Scope of Work
No.
%(Wt)
102
201
311
505
Quantity
Unit
233.33
cu.m.
238.55
55,660.00
24.87%
393.00
cu.m.
907.45
356,629.75
60.09%
1200.00
sq.m.
718.11
861,729.00
10.50%
45.00
cu.m.
3,345.36
150,541.00
0.66%
1.00
lot
9,425.00
9,425.00
3.88%
100.00%
658,761.60
Total (P)
1,433,984.75
SOURCE OF FUND
Breakdown of Estimated Project Cost
KALAHI Grant
Community
Barangay LGU
In-Kind
A.
Cash
Municipal LGU
In-Kind
Cash
Total
In-Kind
Direct Cost
Materials
983,805.09
Equipment
150,672.57
10,000.00
-
117,894.66
1,111,699.75
19,587.43
170,260.00
63,750.00
88,275.00
1,433,984.75
21,000.00
3,390.00
Labor
Skilled
63,750.00
Unskilled
64,200.00
24,075.00
1,262,427.65
24,075.00
Sub-Total A
B.
10,000.00
137,482.10
Indirect Cost
Overhead Cost
21,000.00
2,947.83
1,000.00
Project Supervision
442.17
8,500.00
1,000.00
2,000.00
4,000.00
12,500.00
3,130.43
469.57
3,600.00
Administrative Cost
34,782.61
5,217.39
40,000.00
Bidding Publication
6,521.74
978.26
7,500.00
Materials Testing
8,695.65
1,304.35
10,000.00
Treasurer's Bond
5,253.75
5,253.75
100,378.93
100,378.93
143,398.48
124,694.33
Sub-Total ( B )
201,772.59
TOTAL ( A+ B )
1,464,200.24
ADD: Contingency
141,248.57
5,000.00
349,021.16
5,000.00
1,783,005.91
24,075.00
10,000.00
1,000.00
278,730.67
24,075.00
10,000.00
1,000.00
291,550.00
5,000.00
1,523,075.00
82.12%
301,550.00
16.26%
30,075.00
1.62%
291,550.00
5,000.00
58,874.76
1,523,075.00
12,819.33
MCC Grant
Cost Sharing to TEPC
18,704.15
1,000.00
LCC Cash
LCC Inkind
71,694.09
1,854,700.00
100.00%
1,523,075.00
24,075.00
Prepared by :
10,000.00
1,000.00
1,854,700.00
Approved by :
JOY ALABAN
Service Provider
BSPMC Chairperson
Checked by:
Concurred by :
ORENCIO T. SARENSE
Recommending Approval:
Municipal Mayor
BILL OF QUANTITIES
COST SHARING
ITEM
NO.
Quantity Derivation
Computation
ITEM DESCRIPTION
QUANTI
UNIT
TY
233.33
233.33
cu.m.
cu.m.
233.33
cu.m.
Rate per
No. of
Day / Unit
Crew/
Cost
Add
Frieght &
Handling
Cost
Total Unit
Cost
2.00
3.00
2.00
Day/s
Day/s
Day/s
1.00
4.00
2.00
350.00
300.00
275.00
Sub-Total
C. Equipment
Preparation of fnish grade of item 200
including trench canal excavation
Mobilization & Demobilization
1-Backhoe (280 cu.m / day)
3-Dump Truck (240cu.m / day)
189.24/280 =
189.24/240 =
1.00
2.00
1.00
lot
Day/s
Day/s
10,000.00
16,880.00
6,500.00
1.00
3.00
393.00
cu.m.
(1.31*300) =
393.00
cu.m.
(1.31*300*1.15) =
451.95
cu.m.
451.95
cu.m.
A. Materials
Aggregate Subbase Course (Balastro Class "A" Type)
Sub-Total
B. Labor
Construction Foreman
*pls see equipment
Driver / Operator
*pls see equipment
Laborer
*pls see equipment
Sub-Total
C. Equipment
Mobilization & Demobilization
1-Road Roller (210cu.m/day)
227.7/210 =
1-Road Grader (400 cu.m / day)
227.7/400 =
3.00
5.00
3.00
Day/s
Day/s
Day/s
1.00
3.00
2.00
lot
Day/s
Day/s
550.00
55.00
605.00
1- Concrete Vibrator
180/7.82 =
700.00
3,600.00
1,100.00
5,400.00
700.00
3,600.00
800.00
5,100.00
10,000.00
33,760.00
6,500.00
50,260.00
8,849.56
29,876.11
5,752.21
44,477.88
55,660.00
49,577.88
273,429.75
273,429.75
241,973.23
241,973.23
350.00
300.00
275.00
1,050.00
3,000.00
1,650.00
5,700.00
1,050.00
3,000.00
1,200.00
5,250.00
1.00
1.00
6,500.00
13,800.00
14,800.00
6,500.00
41,400.00
29,600.00
77,500.00
5,752.21
36,637.17
26,194.69
68,584.07
356,629.75
315,807.30
445,500.00
62,700.00
155,925.00
21,164.00
4,752.00
14,256.00
1,221.00
715.00
13,750.00
396.00
1,250.00
721,629.00
394,247.79
55,486.73
137,986.73
18,729.20
4,205.31
12,615.93
1,080.53
632.74
12,168.14
350.44
1,106.19
638,609.73
bags
cu.m.
cu.m.
length
bdft
bdft
length
kgs.
bag
pcs
cu.m.
250.00
600.00
750.00
370.00
20.00
20.00
370.00
65.00
2,500.00
60.00
20.00
25.00
60.00
75.00
37.00
2.00
2.00
37.00
6.50
250.00
6.00
30.00
275.00
660.00
825.00
407.00
22.00
22.00
407.00
71.50
2,750.00
66.00
50.00
Day/s
5.00
300.00
6,000.00
Day/s
Day/s
Day/s
Day/s
Day/s
1.00
2.00
10.00
1.00
1.00
350.00
300.00
275.00
300.00
300.00
8,750.00
13,800.00
63,250.00
6,900.00
6,900.00
105,600.00
6,000.00
8,750.00
13,800.00
46,000.00
6,900.00
6,900.00
88,350.00
23,000.00
20,353.98
day
1.00
1,000.00
day
1.00
500.00
11,500.00
10,176.99
34,500.00
30,530.97
861,729.00
757,490.71
49,896.00
12,870.00
2,475.00
44,155.75
11,389.38
2,190.27
45.00
Length =
Total Volume =
300.00
300.00
300.00
450.00
450.00
450.00
BRGY.
CASH
IN-KIND
TOTAL
MUN.
CASH
IN-KIND
700.00
3,600.00
1,100.00
5,400.00
1,150.44
3,883.89
747.79
5,782.12
10,000.00
33,760.00
6,500.00
50,260.00
5,782.12
55,660.00
31,456.52
31,456.52
273,429.75
273,429.75
747.79
4,762.83
3,405.31
8,915.93
40,372.45
41,252.21
7,213.27
17,938.27
2,434.80
546.69
1,640.07
140.47
82.26
1,581.86
45.56
143.81
73,019.27
1,050.00
3,000.00
1,650.00
5,700.00
6,500.00
41,400.00
29,600.00
77,500.00
356,629.75
445,500.00
62,700.00
155,925.00
21,164.00
4,752.00
14,256.00
1,221.00
715.00
13,750.00
396.00
1,250.00
721,629.00
sq.m.
m
m
sq.m.
cu.m.
cu.m.
Sub-Total
505 Grouted Riprap
23.00
1.00
2.00
2.00
COMMUNITY
CONTRIBUTI
ON
KALAHI
GRANT
Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer
LGU
Total
10,000.00
10,000.00
6,000.00
17,250.00
17,250.00
3,969.03
34,500.00
76,988.29
861,729.00
2,646.02
23,000.00
1,323.01
17,250.00
8,750.00
13,800.00
63,250.00
6,900.00
6,900.00
105,600.00
10,000.00
11,500.00
cu.m.
300.00
45.00
cu.m.
189.00
18.00
3.00
bags
cu.m.
cu.m.
240.00
650.00
750.00
24.00
65.00
75.00
264.00
715.00
825.00
52.00
cu.m.
750.00
75.00
825.00
Sub-Total
42,900.00
37,964.60
108,141.00
95,700.00
5,740.25
1,480.62
284.73
49,896.00
12,870.00
2,475.00
4,935.40
-
12,441.00
42,900.00
-
108,141.00
2,800.00
7,200.00
2,400.00
22,000.00
34,400.00
8.00
8.00
8.00
8.00
Day/s
Day/s
Day/s
Day/s
1.00
3.00
1.00
10.00
350.00
300.00
300.00
275.00
2,800.00
7,200.00
2,400.00
22,000.00
34,400.00
2,800.00
7,200.00
2,400.00
16,000.00
28,400.00
8.00
day
1.00
1,000.00
Sub-Total
8,000.00
8,000.00
7,079.65
7,079.65
150,541.00
131,179.65
8,500.00
8,500.00
7,522.12
7,522.12
350.00
300.00
350.00
300.00
Sub-Total
C.Equipment
1- Concrete Mixer
SPL - 1 Billboard
1.00
lot
1.00
lot
6,000.00
6,000.00
6,000.00
920.35
920.35
8,000.00
8,000.00
13,361.35
150,541.00
977.88
977.88
8,500.00
8,500.00
Quantity: 1 unit
A. Materials
Project Billboard
8,500.00
Sub-Total
B. Labor
Contstruction Foreman
Carpenter
1.00
1.00
Day/s
Day/s
1.00
1.00
350.00
300.00
350.00
300.00
COST SHARING
ITEM
NO.
Quantity Derivation
Computation
ITEM DESCRIPTION
Laborer
QUANTI
UNIT
TY
1.00
Day/s
Rate per
No. of
Day / Unit
Crew/
Cost
1.00
Add
Frieght &
Handling
Cost
Total Unit
Cost
LGU
Total
275.00
COMMUNITY
CONTRIBUTI
ON
200.00
75.00
850.00
75.00
KALAHI
GRANT
BRGY.
TOTAL
MUN.
Sub-Total
275.00
925.00
9,425.00
8,372.12
75.00
275.00
925.00
977.88
9,425.00
1,433,984.75
1,262,427.65
24,075.00
10,000.00
137,482.10
1,433,984.75
1,111,699.75
983,805.09
170,260.00
150,672.57
10,000.00
-
117,894.66
1,111,699.75
19,587.43
170,260.00
63,750.00
63,750.00
63,750.00
88,275.00
1,433,984.75
21,000.00
21,000.00
1) Skilled
2)Unskilled
TOTAL DIRECT COST
88,275.00
64,200.00
24,075.00
1,433,984.75
1,262,427.65
24,075.00
INDIRECT COST:
OVERHEAD COST
Foreman/Leadman
Sub-total
HANDTOOLS AND PROTECTIVE EQUIPMENT
Hard Hat
Hand Glooves
Medicine Kit
Sub-total
PRE-ENGINEERING
Preparation of Plans (TAF)
Reproduction of Plans
Sub-total
PROJECT SUPERVISION
Municipal Engineer
BSPMC volunteers
Sub-total
ENVIRONMENTAL IMPACT
10,000.00
137,482.10
60.00
days
350.00
21,000.00
21,000.00
21,000.00
21,000.00
1,086.96
217.39
1,643.48
2,947.83
10.00
10.00
1.00
pcs.
pcs.
set
125.00
25.00
1,890.00
1,250.00
250.00
1,890.00
3,390.00
20.00
shts
100.00
2,000.00
2,000.00
4,000.00
8,500.00
12,500.00
163.04
32.61
246.52
442.17
5.00
17.00
days
days
800.00
250.00
2.00
1,000.00
1,000.00
8,500.00
8,500.00
5.00
pcs.
420.00
2,100.00
1,826.09
273.91
Barricades
5.00
pcs.
300.00
1,500.00
1,304.35
195.65
3,600.00
40,000.00
7,500.00
10,000.00
5,253.75
100,378.93
143,398.48
349,021.16
1,783,005.91
71,694.09
1,854,700.00
3,130.43
34,782.61
6,521.74
8,695.65
124,694.33
201,772.59
1,464,200.24
58,874.76
1,523,075.00
1,854,700.00
1,523,075.00
Prepared by:
1.00
posting
7,500.00
7,500.00
82.12%
RODSON R. ESCORA
Deputy Area Coordinator
Recommending Approval:
CARMEN A. GAUDIANO
Municipal Engineer
2,000.00
2,000.00
1,000.00
1,000.00
4,000.00
Warning Signs
Sub-total
ADMINISTRATIVE COST
BIDDING PUBLICATION
MATERIAL TESTING
TREASURER'S BOND
VAT (7% OF Total Direct Cost)
Contractor Profit (10%)
TOTAL INDIRECT COST
TOTAL (A+B)
Add: Contingency
TOTAL ESTIMATED PROJECT COST (TEPC)
Add: O and M (Other Amenities)
TOTAL CONSTRUCTION COST
1,250.00
250.00
1,890.00
3,390.00
24,075.00
10,000.00
1,000.00
1,000.00
24,075.00
10,000.00
1,000.00
469.57
5,217.39
978.26
1,304.35
5,253.75
100,378.93
18,704.15
141,248.57
278,730.67
12,819.33
291,550.00
24,075.00
10,000.00
1,000.00
17.88%
291,550.00
304,615.00
Approved by:
JOY ALABAN
BSPMC Chairperson
4,000.00
8,500.00
12,500.00
4,000.00
2,100.00
1,500.00
-
5,000.00
5,000.00
5,000.00
5,000.00
3,600.00
40,000.00
7,500.00
10,000.00
5,253.75
100,378.93
143,398.48
349,021.16
1,783,005.91
71,694.09
1,854,700.00
1,854,700.00
Noted by:
GEORGE S. ISULAT
RCIS
Description of Work
Item No.
Location
Note
STATION
0+000
0+020
0+040
0+060
0+080
0+100
0+120
0+140
0+160
0+180
0+200
0+340
0+360
0+380
0+400
0+420
0+440
Total Area :
Ave. Area :
BARANGAY SUB-PROJECT
MANAGEMENT COMMITTEE
QUANTITY CALCULATION
: Computed Areas are taken from CAD File ( Poly Line Method)
AREA
DISTANCE
VOLUME
ITEM 102
ITEM 104
(m)
ITEM 102
0.020
0.460
20.00
0.660
0.550
20.00
6.800
0.000
3.840
20.00
6.600
11.120
0.000
20.00
111.200
0.150
0.630
20.00
112.700
0.140
0.740
20.00
2.900
0.210
0.350
20.00
3.500
0.150
0.750
20.00
3.600
0.330
0.180
20.00
4.800
1.630
0.160
20.00
19.600
1.400
0.510
20.00
30.300
1.990
0.060
20.00
1.470
0.200
20.00
34.600
1.410
0.200
20.00
28.800
0.050
2.370
20.00
14.600
1.410
0.200
20.00
14.600
0.190
0.270
20.00
16.000
22.330
1.314
11.470
0.675
Add: 15% Shrinkage Factor =
Total Loose Volume =
REMARKS /
LOCATION
ITEM 104
10.100
43.900
38.400
6.300
13.700
10.900
11.000
9.300
3.400
6.700
2.600
4.000
25.700
25.700
4.700
410.600
216.400
410.600
32.460
248.860
410.60
194.200 cu.m
223.33 cu.m
Submitted by:
JERRY C. BALIOLA
Service Provider
Sub-Project duration
: 90
Physical Target
:
:
:
:
:
Region
Province
Municipality
Barangay
Calendar Days
300 L.M.
VII CENTRAL VISAYAS
NEGROS ORIENTAL
DAUIN
MAGSAYSAY
: P
Direct Cost
Indirect Cost
Date Started
Target Completion
Mode of Implementation
: P
1,433,984.75
: P
420,715.25
:
:
: By Contract
1,854,700.00
LABOR
NO.
WEIGHT
DESCRIPTION
II
Emabankment
III
IV
VI
QTY
233.33 cu.m.
Err:509
UNIT
cu.m.
393.00 cu.m.
1,200.00 sq.m.
Grouted Riprap
45.00 cu.m.
1.00
lot
T O T A L
AMOUNT
PHYSICAL
(%)
55,660.00
3.88%
Err:509
Err:509
356,629.75
24.87%
861,729.00
60.09%
150,541.00
10.50%
9,425.00
1,433,984.75
0.66%
100.00%
PHYSICAL
% PROGRESS (Actual)
PROGRESS (Planned)
FINANCIAL
PROGRESS (Actual)
Prepared by:
TOTAL
MONTH 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
MONTH 3
WEEK 7
WEEK 8
WEEK 9
WEEK 10
MONTH 4
WEEK 11
WEEK 12
WEEK 13
# # # # # # # # # # # # # # # # # # # # # # # # # # # #
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
PLANNED
ACTUAL
PLANNED
##########################################
ACTUAL
PLANNED
###################################################################################################################################################
ACTUAL
PLANNED
####################################################################################
ACTUAL
PLANNED
# #
ACTUAL
PLANNED
# # # # # # # # # # # # # # # # # # # # ###################################################################################################################################################################################################################
ACTUAL
1
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
Concurred by:
JOCELYN ALAS-AS
PIT Chairperson
WEEK 2
275.00
ACTUAL
WEEK 1
90
UNSKILLED
MONTH 1
TARGET
PLANNED
90
SKILLED
ITEM
Average
Rate/Day
300.00
No. of Days
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
43
44
45
46
47
48
49
50
51
52
53
54
55
56
65
66
67
68
69
70
71
72
73
74
75
76
77
85
86
87
88
89
90
91
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
0.97%
3.00%
Err:509
5.00%
15.00%
17.00%
18.00%
13.81%
12.00%
5.00%
3.00%
2.00%
1.63%
2.60%
5.60%
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
23,340.00
13,915.00
43,019.54
Err:509
23,340.00
37,255.00
80,274.54
Err:509
71,699.24
Err:509
215,097.71
243,777.41
258,117.26
198,033.29
172,078.17
Err:509
Err:509
Err:509
Err:509
Err:509
SELVINO BULISID
MIT Team Leader
64
1.63%
Approved by:
CARMEN A. GAUDIANO
Municipal Engineer
71,699.24
Err:509
43,019.54
Err:509
119
28,679.70
1,433,984.75
Noted by:
GEORGE ALAS-AS
BSPMC
118
GEORGE S. ISULAT
RCIS
:
:
:
Local Counterpart :
KALAHI Grant
Community
Barangay LGU
Municipal LGU
TOTAL
SPI Stage / Activities
Conducted
ITEM 102 Surplus Common
Excavation
PHP
PHP
PHP
PHP
PHP
Negative Impact
1,523,075.00
24,075.00
1,000.00
296,550.00
1,844,700.00
Mitigating Measures
a.
Deep Excavation/Ground
Leveling
a-1.
b.
Presence of Heavy
Equipment in the project
Site
b-1.
a.
Backfilling of Excavated
Materials
a-2.
b.
Presence of Heavy
Equipment in the project
Site
b-1.
Presence of Heavy
Equipment in the project
Site
a-1.
a-1.
none
none
none
none
Reviewed by:
Prepared By:
GEORGE ALAS-AS
RICKY PANOY
BSPMC Chair
Community Facilitator
CARMEN A. GAUDIANO
RODSON R. ESCORA
Municipal Engineer
Concurred by:
Category
Physical Target
: Public Goods
: 0.30 KM
PHP 2,027,337.65
: By Community Force Account (CFA)
Project Description:
Sub-Project Duration
: 90 Calendar Days
Equipment/Tools Needed
Technical Personnel
Sub-Project Location:
Sub-Project Site Location is 8KM away from Town Proper
No. of Laborers
Item
Scope of Work
No.
%(Wt)
: 90 person days
Quantity
Unit
Total (P)
102
8.54%
410.60
cu.m.
367.27
150,800.00
104
Embankment
-9.57%
-194.20
cu.m.
869.88
(168,931.50)
200
22.42%
393.00
cu.m.
1,007.60
395,987.00
311
51.49%
1200.00
sq.m.
757.85
909,418.00
505
26.52%
216.00
cu.m.
2,168.26
468,345.00
0.59%
1.00
lot
10,425.00
100.00%
990,820.35
10,425.00
1,766,043.50
SOURCE OF FUND
Breakdown of Estimated Project Cost
KALAHI Grant
Community
Barangay LGU
In-Kind
A.
Cash
Municipal LGU
In-Kind
Cash
Total
In-Kind
Direct Cost
Materials
Equipment
1,096,691.50
236,927.00
1,333,618.50
190,075.00
44,425.00
234,500.00
Labor
Skilled
82,150.00
82,150.00
Unskilled
84,050.00
31,725.00
115,775.00
1,452,966.50
31,725.00
281,352.00
1,766,043.50
Sub-Total A
B.
Indirect Cost
Overhead Cost
25,200.00
6,300.00
31,500.00
13,432.00
3,358.00
16,790.00
Pre-engineering
Project Supervision
2,000.00
4,000.00
12,500.00
720.00
3,600.00
10,100.00
50,500.00
6,000.00
1,500.00
7,500.00
12,000.00
3,000.00
15,000.00
6,000.00
1,500.00
7,500.00
5,253.75
1,000.00
40,231.75
5,000.00
152,143.75
1,000.00
321,583.75
5,000.00
1,918,187.25
Sub-Total ( B )
105,912.00
TOTAL ( A+ B )
1,558,878.50
31,725.00
89,618.50
1,648,497.00
19,531.90
31,725.00
1,000.00
MCC Grant
Cost Sharing to TEPC
8,500.00
1,000.00
2,880.00
40,400.00
Treasurer's Bond
ADD: Contingency
1,000.00
341,115.65
5,253.75
5,000.00
1,648,497.00
81.31%
LCC Cash
341,115.65
16.83%
LCC Inkind
37,725.00
1.86%
109,150.40
2,027,337.65
100.00%
1,648,497.00
31,725.00
Prepared by :
1,000.00
341,115.65
5,000.00
2,027,337.65
Approved by :
ELSA A. TRUNO
GEORGE ALAS-AS
MEO Staff
BSPMC Chairperson
Checked by:
Concurred by :
Recommending Approval:
Municipal Mayor
BILL OF QUANTITIES
ITEM
NO.
Quantity Derivation
Computation
ITEM DESCRIPTION
QUANTI
UNIT
TY
Rate per
No. of
Day / Unit
Crew/
Cost
410.60
410.60
cu.m.
cu.m.
410.60
cu.m.
4.00
7.00
4.00
Day/s
Day/s
Day/s
1.00
2.00
2.00
1.00
4.00
3.00
lot
Day/s
Day/s
1.00
1.00
194.20
194.20
223.33
cu.m.
cu.m.
cu.m.
223.33
cu.m.
2.00
3.00
2.00
Day/s
Day/s
Day/s
1.00
2.00
2.00
1.00
1.00
2.00
lot
Day/s
Day/s
1.00
1.00
393.00
cu.m.
(1.31*300) =
393.00
cu.m.
(1.31*300*1.15) =
451.95
cu.m.
451.95
cu.m.
A. Materials
Existing Ground Profile
Add
Frieght &
Handling
Cost
Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer
C. Equipment
Preparation of fnish grade of item 200
including trench canal excavation
Mobilization & Demobilization
1-Backhoe (119 cu.m / day)
1-Road Grader (175 cu.m / day)
358/119 =
358/175 =
500.00
50.00
600.00
60.00
Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer
C. Equipment
Mobilization & Demobilization
1-Road Roller (250 cu.m/day)
1-Road Grader (175 cu.m / day)
472.06/250 =
472.06/175 =
Magsaysay BOQ
Page 9 of 63
ITEM
NO.
Quantity Derivation
Computation
ITEM DESCRIPTION
QUANTI
UNIT
TY
Rate per
No. of
Day / Unit
Crew/
Cost
Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer
3.00
5.00
3.00
Day/s
Day/s
Day/s
1.00
2.00
2.00
1.00
2.00
3.00
lot
Day/s
Day/s
1.00
1.00
Add
Frieght &
Handling
Cost
Sub-Total
C. Equipment
Mobilization & Demobilization
1-Road Roller (250 cu.m/day)
1-Road Grader (175 cu.m / day)
451.95/250 =
451.95/175 =
(180*9.5)/122
15.00
sq.m.
m
m
sq.m.
cu.m.
cu.m.
bags
cu.m.
cu.m.
length
bdft
bdft
length
kgs.
bag
cu.m.
261.50
750.00
850.00
370.00
20.00
20.00
370.00
65.00
2,500.00
20.00
Day/s
2.00
Day/s
Day/s
Day/s
Day/s
Day/s
1.00
4.00
10.00
1.00
1.00
day
1.00
day
1.00
26.15
75.00
85.00
37.00
2.00
2.00
37.00
6.50
250.00
30.00
Sub-Total
Total for Item 311
505 Grouted Riprap
Length =
Cross-sectional Area of canal =
0.3*1.2 =
(0.36*2*300)=
Class A stone
2"x2"x8' Coco Lumber (Batterboards)
# 4 CWN
Magsaysay BOQ
cu.m.
300.00
0.36
cu.m.
216.00
cu.m.
(two sides)
216.00
cu.m.
(1.620*216)
(0.143*216)
350.00
62.00
bags
cu.m.
261.50
750.00
26.15
75.00
(0.48*2*216)=
208.00
cu.m.
850.00
85.00
240.00
5.00
bdft
kgs.
20.00
65.00
2.00
6.50
Total Volume =
Portland Cement (40kgs), Type 1
Fine Aggregates (Approved Source)
216.00
((2"*2"*8')/12)*15 =
Page 10 of 63
ITEM
NO.
Quantity Derivation
Computation
ITEM DESCRIPTION
Water (for mixing)
QUANTI
UNIT
TY
6.00
cu.m.
27.00
27.00
27.00
Day/s
Day/s
Day/s
1.00
lot
1.00
lot
1.00
1.00
1.00
Day/s
Day/s
Day/s
90.00
days
10.00
10.00
10.00
10.00
10.00
1.00
pcs.
pcs.
pcs
pairs
pcs
set
20.00
shts
5.00
17.00
days
days
Warning Signs
5.00
pcs.
Barricades
5.00
pcs.
Sub-total
ADMINISTRATIVE COST
BIDDING PUBLICATION
1.00
posting
Rate per
No. of
Day / Unit
Crew/
Cost
20.00
Sub-Total
1.5 man lm per day
Construction Foreman
Mason
Laborers
(600/1.5)/15=
1.00
4.00
10.00
Sub-Total
Total for Item 505
SPL - 1Billboard
Quantity: 1 unit
A. Materials
Project Billboard
Sub-Total
B. Labor
Contstruction Foreman
Carpenter
Laborer
1.00
1.00
1.00
Sub-Total
Total for Item SPL -1
Total Direct Cost
Direct Cost Summary
Materials
Equipment
Labor
1) Skilled
2)Unskilled
TOTAL DIRECT COST
INDIRECT COST:
OVERHEAD COST
Foreman/Leadman
Sub-total
HANDTOOLS AND PROTECTIVE EQUIPMENT
Hard Hat
Hand Glooves
Face Mask
Safety Boots
Shovel w/ handle
Medicine Kit
Sub-total
PRE-ENGINEERING
Preparation of Plans (TAF)
Reproduction of Plans
Sub-total
PROJECT SUPERVISION
Municipal Engineer
BSPMC volunteers
Sub-total
ENVIRONMENTAL IMPACT
Magsaysay BOQ
Page 11 of 63
2.00
7,500.00
Add
Frieght &
Handling
Cost
30.00
ITEM
NO.
ITEM DESCRIPTION
Quantity Derivation
Computation
MATERIAL TESTING
BSPMC FILLING CABINET
TREASURER'S BOND
TOTAL INDIRECT COST
TOTAL (A+B)
Add: Contingency
TOTAL ESTIMATED PROJECT COST (TEPC)
Add: O and M (Other Amenities)
TOTAL CONSTRUCTION COST
Prepared by:
1.00
Rate per
No. of
Day / Unit
Crew/
Cost
unit
Add
Frieght &
Handling
Cost
7,500.00
82.12%
ELSA A. TRUNO
MEO Staff
Magsaysay BOQ
QUANTI
UNIT
TY
RODSON R. ESCORA
Deputy Area Coordinator
Page 12 of 63
Recommending Approval:
CARMEN A. GAU
Municipal Engi
L OF QUANTITIES
COST SHARING
Total Unit
Cost
LGU
Total
KALAHI
GRANT
350.00
300.00
275.00
15,000.00
18,500.00
18,000.00
550.00
350.00
300.00
275.00
10,000.00
16,500.00
18,000.00
660.00
Magsaysay BOQ
COMMUNITY
CONTRIBUTI
ON
BRGY.
CASH
IN-KIND
1,400.00
4,200.00
2,200.00
7,800.00
1,400.00
4,200.00
1,600.00
7,200.00
15,000.00
74,000.00
54,000.00
143,000.00
12,000.00
59,200.00
43,200.00
114,400.00
150,800.00
121,600.00
(122,831.50)
(122,831.50)
(103,235.49)
(103,235.49)
(700.00)
(1,800.00)
(1,100.00)
(3,600.00)
(700.00)
(1,800.00)
(1,100.00)
(3,600.00)
10,000.00
(16,500.00)
(36,000.00)
(42,500.00)
8,500.00
(14,025.00)
(30,600.00)
(36,125.00)
(168,931.50)
(142,960.49)
298,287.00
268,458.30
600.00
600.00
600.00
TOTAL
MUN.
CASH
IN-KIND
1,400.00
4,200.00
2,200.00
7,800.00
3,000.00
14,800.00
10,800.00
28,600.00
15,000.00
74,000.00
54,000.00
143,000.00
28,600.00
150,800.00
(19,596.02)
(19,596.02)
(122,831.50)
(122,831.50)
(700.00)
(1,800.00)
(1,100.00)
(3,600.00)
1,500.00
(2,475.00)
(5,400.00)
(6,375.00)
10,000.00
(16,500.00)
(36,000.00)
(42,500.00)
(25,971.02)
(168,931.50)
29,828.70
Page 13 of 63
298,287.00
COST SHARING
Total Unit
Cost
Total
298,287.00
350.00
300.00
275.00
LGU
COMMUNITY
KALAHI
CONTRIBUTI
GRANT
ON
268,458.30
-
BRGY.
-
TOTAL
MUN.
-
29,828.70
298,287.00
1,050.00
3,000.00
1,650.00
5,700.00
5,000.00
33,000.00
54,000.00
92,000.00
395,987.00
465,993.00
103,950.00
168,300.00
18,722.00
3,168.00
14,256.00
814.00
715.00
19,250.00
1,250.00
796,418.00
1,050.00
3,000.00
1,650.00
5,700.00
1,050.00
3,000.00
1,200.00
5,250.00
5,000.00
33,000.00
54,000.00
92,000.00
4,250.00
28,050.00
45,900.00
78,200.00
395,987.00
351,908.30
465,993.00
103,950.00
168,300.00
18,722.00
3,168.00
14,256.00
814.00
715.00
19,250.00
1,250.00
796,418.00
372,698.81
83,160.00
134,640.00
14,977.60
2,534.40
11,404.80
651.20
572.00
15,400.00
1,000.00
637,038.81
300.00
2,400.00
350.00
300.00
275.00
300.00
300.00
4,900.00
16,800.00
38,500.00
4,200.00
4,200.00
71,000.00
2,400.00
4,900.00
16,800.00
28,150.00
4,200.00
4,200.00
60,650.00
1,600.00
24,000.00
19,200.00
4,800.00
24,000.00
1,200.00
18,000.00
14,400.00
3,600.00
18,000.00
5,000.00
16,500.00
18,000.00
287.65
825.00
935.00
407.00
22.00
22.00
407.00
71.50
2,750.00
50.00
450.00
450.00
450.00
750.00
4,950.00
8,100.00
13,800.00
43,628.70
93,294.19
20,790.00
33,660.00
3,744.40
633.60
2,851.20
162.80
143.00
3,850.00
250.00
159,379.19
2,400.00
10,350.00
10,350.00
42,000.00
33,600.00
909,418.00
731,288.81
287.65
825.00
100,677.50
51,150.00
85,575.88
40,920.00
15,101.63
10,230.00
100,677.50
51,150.00
935.00
194,480.00
155,584.00
38,896.00
194,480.00
22.00
71.50
5,280.00
357.50
4,224.00
286.00
1,056.00
71.50
5,280.00
357.50
Magsaysay BOQ
4,900.00
16,800.00
38,500.00
4,200.00
4,200.00
71,000.00
10,350.00
8,400.00
42,000.00
167,779.19
909,418.00
Page 14 of 63
COST SHARING
Total Unit
Cost
50.00
350.00
300.00
275.00
9,500.00
350.00
300.00
275.00
LGU
Total
300.00
352,245.00
KALAHI
GRANT
240.00
286,829.88
COMMUNITY
CONTRIBUTI
ON
-
BRGY.
-
TOTAL
MUN.
-
60.00
65,415.13
300.00
352,245.00
9,450.00
32,400.00
74,250.00
116,100.00
9,450.00
32,400.00
54,000.00
95,850.00
20,250.00
20,250.00
9,450.00
32,400.00
74,250.00
116,100.00
468,345.00
382,679.88
20,250.00
65,415.13
468,345.00
9,500.00
9,500.00
7,600.00
7,600.00
1,900.00
1,900.00
9,500.00
9,500.00
350.00
300.00
275.00
925.00
350.00
300.00
200.00
850.00
75.00
75.00
350.00
300.00
275.00
925.00
10,425.00
8,450.00
75.00
1,900.00
10,425.00
1,766,043.50
1,452,966.50
31,725.00
281,352.00
1,766,043.50
1,333,618.50
1,096,691.50
236,927.00
1,333,618.50
234,500.00
190,075.00
44,425.00
234,500.00
82,150.00
82,150.00
82,150.00
115,775.00
84,050.00
31,725.00
115,775.00
1,766,043.50
1,452,966.50
31,725.00
281,352.00
1,766,043.50
6,300.00
6,300.00
31,500.00
31,500.00
350.00
31,500.00
31,500.00
25,200.00
25,200.00
370.00
35.00
35.00
450.00
600.00
1,890.00
3,700.00
350.00
350.00
4,500.00
6,000.00
1,890.00
16,790.00
2,960.00
280.00
280.00
3,600.00
4,800.00
1,512.00
13,432.00
100.00
2,000.00
2,000.00
740.00
70.00
70.00
900.00
1,200.00
378.00
3,358.00
800.00
250.00
4,000.00
8,500.00
12,500.00
1,000.00
1,000.00
1,000.00
1,000.00
4,000.00
8,500.00
8,500.00
420.00
2,100.00
1,680.00
420.00
300.00
1,500.00
1,200.00
300.00
7,500.00
3,600.00
50,500.00
7,500.00
2,880.00
40,400.00
6,000.00
Magsaysay BOQ
3,700.00
350.00
350.00
4,500.00
6,000.00
1,890.00
16,790.00
Page 15 of 63
720.00
10,100.00
1,500.00
4,000.00
2,000.00
2,000.00
4,000.00
8,500.00
12,500.00
2,100.00
1,500.00
3,600.00
50,500.00
7,500.00
COST SHARING
Total Unit
Cost
7,500.00
Total
15,000.00
7,500.00
5,253.75
152,143.75
1,918,187.25
109,150.40
2,027,337.65
2,027,337.65
commending Approval:
CARMEN A. GAUDIANO
Municipal Engineer
Magsaysay BOQ
LGU
KALAHI
GRANT
12,000.00
6,000.00
COMMUNITY
CONTRIBUTI
ON
BRGY.
105,912.00
1,558,878.50
89,618.50
1,648,497.00
31,725.00
1,000.00
1,000.00
31,725.00
1,000.00
3,000.00
1,500.00
5,253.75
40,231.75
321,583.75
19,531.90
341,115.65
1,648,497.00
31,725.00
1,000.00
341,115.65
Approved by:
TOTAL
MUN.
5,000.00
5,000.00
5,000.00
5,000.00
15,000.00
7,500.00
5,253.75
152,143.75
1,918,187.25
109,150.40
2,027,337.65
2,027,337.65
Noted by:
GEORGE ALAS-AS
BSPMC Chairperson
Page 16 of 63
GEORGE S. ISULAT
RCIS
: Ocotber 9, 2013
Barangay
Municipality
Province
: Magsaysay
: Dauin
: Negros Oriental
PACKAGES
PACKAGE ITEMS
QTY
UNIT
UNIT COST
TOTAL
PROC
METHOD
1st Tranche
KC Grant
Package 1-A
Package 1
Hardware:
0
1470
bags
287.65
48
length
407.00
15
kg
71.50
bags
2,750.00
Sub-Total :Hardware:Package 1
Hardware:
0
500
bags
287.65
422,845.50
LOCAL
19,536.00 SHOPPING
1,072.50 FOR GOODS
(LSG)
359,418.68
16,605.60
911.63
19,250.00
16,362.50
462,704.00
393,298.40
LOCAL
SHOPPING
FOR GOODS
143,825.00
(LSG)
143,825.00
Package 2
Base Aggregates
0
-223.33
cu.m
550.00
451.95
cu.m
660.00
Package 5
Package 4
Package 3-A
Package 3
Sub-Total Package 2
Aggregates
0
0
188
180
cu.m
cum
825.00
935.00
(122,831.50)
LOCAL
SHOPPING
298,287.00 FOR GOODS
(LSG)
238,629.60
175,455.50
134,222.83
LOCAL
155,100.00 SHOPPING
168,300.00 FOR GOODS
(LSG)
323,400.00
131,835.00
143,055.00
274,890.00
Aggregates
Class A Stone
208
cum
935.00
384
bd.ft
22.00
648
bd.ft
22.00
Sub-Total Package 4
Water
31
Sub-total Package 5
194,480.00
Form Lumber
194,480.00
cu.m
50.00
165,308.00
165,308.00
LOCAL
SHOPPING
FOR GOODS
14,256.00
(LSG)
12,117.60
22,704.00
19,298.40
8,448.00
LOCAL
1,550.00 SHOPPING
FOR GOODS
(LSG)
1,550.00
(104,406.78)
LOCAL
SHOPPING
FOR GOODS
(LSG)
7,180.80
1,240.00
1,240.00
Package 6
lot
30,000.00
30,000.00
Backhoe
Road Grader
Road Roller
4
4
1
days
days
days
18,500.00
18,000.00
16,500.00
74,000.00 SHOPPING
FOR GOODS
72,000.00
(LSG)
16,500.00
Package 10
Package 9
Package 8
Package 7
Sub-Total Package 6
192,500.00
days
days
1,600.00
1,200.00
lot
lot
82,150.00
84,050.00
unit
9,500.00
pcs.
370.00
35.00
600.00
35.00
450.00
pairs
pcs.
pcs.
pairs
1.00
Package 11
1,890.00
set
sub-total
Package 12
163,625.00
LOCAL
24,000.00 SHOPPING
18,000.00 FOR GOODS
(LSG)
42,000.00
82,150.00
84,050.00
166,200.00
9,500.00
9,500.00
1,734,318.50
62,900.00
61,200.00
14,025.00
19,200.00
14,400.00
33,600.00
13,612.84
11,153.12
24,765.96
7,600.00
7,600.00
1,217,848.59
LSG
3,700.00
350.00
6,000.00
LOCAL
350.00
SHOPPING
4,500.00 FOR GOODS
2,960.00
280.00
4,800.00
280.00
3,600.00
(LSG)
Package 13
25,500.00
LOCAL
ok
1,890.00
1,512.00
16,790.00
13,432.00
1.00
pcs.
7,500.00
sub-total
Environmental Mitigating Cost:
Warning Sign
Barricade
sub-total
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
Materials Testting
Treasurer Bond
Contingency Cost
sub-total
Total Indirect Cost
GRAND TOTAL CASH
7,500.00
7,500.00
5.00
5.00
pcs.
pcs.
420.00
300.00
LOCAL
SHOPPING
FOR GOODS
(LSG)
LOCAL
6,000.00
2,100.00 SHOPPING
1,500.00 FOR GOODS
1,680.00
1,200.00
3,600.00
2,880.00
31,500.00
8,500.00
50,500.00
7,500.00
15,000.00
5,253.75
109,150.40
(LSG)
7,491.42
CFA
8,000.00
227,404.15
15,491.42
255,294.15
1,989,612.65
SAY
1,989,612.65
6,000.00
0.00
Checked & Reviewed by:
37,803.42
1,255,652.01
1,318,797.60
80.00%
AIDEAH SILVA
RODSON R. ESCORA
PPT
of Barangay Road
:
:
1,989,612.65
90 C.D
SOURCES OF FUNDS
TOTAL
.
PERCENTAGE WEIGHT
TO KC
GRANT
KC Grant:
LCC:
1,318,797.60
272,892.52
1,591,690.12
80.00%
164,849.70
164,849.70
1,648,497.00
34,111.57
34,111.57
341,115.65
198,961.27
198,961.27
1,989,612.65
10.00%
10.00%
100%
TO LCC
CASH
FUND SOURCE
LEGEND:
KC GRANT
1,648,497.00
80%
TOTAL LCC
378,840.65
10.00%
10.00%
100%
LCC - In-kind
LCC - Cash
TOTAL
37,725.00
341,115.65
2,027,337.65
REMARKS
TRANCHING SCHEDULE
TOTAL
1st Tranche
2nd Tranche
LCC Cash
KC Grant
3rd Tranche
LCC Cash
KC Grant
TOTAL
LCC Cash
KC Grant
LCC Cash
359,418.68
63,426.83
422,845.50
2,930.40
16,605.60
2,930.40
19,536.00
160.88
911.63
160.88
1,072.50
2,887.50
115,060.00
28,765.00
115,060.00
28,765.00
16,362.50
2,887.50
19,250.00
393,298.40
69,405.60
462,704.00
115,060.00
28,765.00
143,825.00
115,060.00
28,765.00
143,825.00
(18,424.73)
(104,406.78)
(18,424.73)
(122,831.50)
59,657.40
238,629.60
59,657.40
298,287.00
134,222.83
41,232.68
175,455.50
131,835.00
143,055.00
23,265.00
25,245.00
155,100.00
168,300.00
274,890.00
48,510.00
323,400.00
41,232.68
23,265.00
25,245.00
48,510.00
29,172.00
29,172.00
165,308.00
29,172.00
194,480.00
165,308.00
29,172.00
194,480.00
1,267.20
7,180.80
1,267.20
8,448.00
2,138.40
12,117.60
2,138.40
14,256.00
19,298.40
-
3,405.60
-
22,704.00
-
1,240.00
310.00
1,550.00
1,240.00
310.00
1,550.00
3,405.60
310.00
310.00
MONTHS
1
63,426.83
69,405.60
PROPOSED
IMPLEMENTATION
SCHEDULE
4,500.00
25,500.00
4,500.00
30,000.00
11,100.00
10,800.00
2,475.00
62,900.00
61,200.00
14,025.00
11,100.00
10,800.00
2,475.00
74,000.00
72,000.00
16,500.00
163,625.00
28,875.00
192,500.00
28,875.00
4,800.00
3,600.00
8,400.00
19,200.00
14,400.00
33,600.00
75,700.00
74,026.98
149,726.98
7,600.00
7,600.00
1,292,561.61
4,800.00
3,600.00
8,400.00
10,500.00
11,823.02
22,323.02
1,900.00
1,900.00
253,126.90
24,000.00
18,000.00
42,000.00
86,200.00
85,850.00
172,050.00
9,500.00
9,500.00
1,740,168.50
740.00
70.00
1,200.00
70.00
900.00
2,960.00
280.00
4,800.00
280.00
3,600.00
740.00
70.00
1,200.00
70.00
900.00
3,700.00
350.00
6,000.00
350.00
4,500.00
378.00
1,512.00
378.00
1,890.00
13,432.00
3,358.00
16,790.00
6,000.00
1,500.00
7,500.00
6,000.00
1,500.00
7,500.00
1,680.00
1,200.00
420.00
300.00
2,100.00
1,500.00
2,880.00
720.00
3,600.00
12,151.42
1,500.00
13,008.58
1,500.00
3,000.00
5,253.75
15,000.00
31,500.00
8,500.00
50,500.00
7,500.00
15,000.00
5,253.75
109,150.40
4,000.00
2,163.02
6,163.02
40,000.00
39,340.00
79,340.00
4,000.00
3,835.00
7,835.00
22,087.16
23,533.86
45,621.02
2,500.00
5,825.00
8,325.00
1,900.00
1,900.00
237,373.90
194,400.00
36,600.00
45,621.02
8,325.00
3,358.00
1,500.00
1,500.00
420.00
300.00
720.00
5,860.00
3,442.50
8,000.00
3,000.00
5,253.75
13,488.58
7,000.00
30,000.00
6,000.00
4,000.00
8,708.92
1,500.00
5,008.58
1,500.00
94,150.40
15,000.00
19,348.58
7,000.00
37,491.42
6,000.00
12,000.00
94,150.40
16,253.75
5,860.00
3,442.50
154,638.98
31,717.50
175,990.40
51,413.75
227,404.15
21,831.75
5,860.00
3,442.50
154,638.98
31,717.50
198,302.40
56,991.75
255,294.15
259,205.65
200,260.00
40,042.50
200,260.00
40,042.50
1,490,864.01
310,118.65
1,995,462.65
272,892.52
164,849.70
34,111.57
164,849.70
34,111.57
1,490,864.01
310,118.65
1,995,462.65
63,145.60
10.00%
(35,410.30)
10.00%
(35,410.30)
Recommending Approval:
Submitted by:
Noted by:
CARMEN A. GAUDIANO
VERONICA ALCORIZA
GEOGRE S. ISULAT
Municipal Engineer
BSMPC
AMOUNT
(PESO)
1,648,497.00
378,840.65
37,725.00
341,115.65
2,027,337.65
PROPOSED
IMPLEMENTATION
SCHEDULE
MONTHS
2
4
-
(4,050.00)
(1,800.00)
(5,850.00)
(5,850.00)
-
(5,850.00)
: Ocotber 9, 2013
Barangay
Municipality
Province
: Magsaysay
: Dauin
: Negros Oriental
:
:
SOURCES OF FUNDS
DESCRIPTION
PACKAGES
PACKAGE ITEMS
QTY
UNIT COST
TOTAL
KC Grant:
LCC:
1,318,797.60
272,892.52
164,849.70
164,849.70
1,648,497.00
34,111.57
34,111.57
341,115.65
PROC
METHOD
TRAN
1st Tranche
KC Grant
2nd Tranche
LCC Cash
KC Grant
Hardware:
Package 1 - A
Package 1
1470
bags
245.00
360,150.00
306,127.50
54,022.50
48
length
340.00
16,320.00
13,872.00
2,448.00
# 4 CWN
15
kg
bags
46.50
1,950.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Hardware:
Portland Cement (40kgs) Type 1
500
bags
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
LOCAL
697.50 SHOPPING
13,650.00 FOR GOODS
(LSG)
592.88
104.63
11,602.50
2,047.50
390,817.50
332,194.88
58,622.63
71,886.50
462,704.00
61,103.52
10,782.98
393,298.40
69,405.60
-
LOCAL
SHOPPING
- FOR GOODS
(LSG)
143,825.00
115,060.00
143,825.00
115,060.00
Package 3
Package 2
Base Aggregates
Embankment (Fill) Materials
363.15
cu.m
550.00
199,732.50
451.95
cu.m
550.00
248,572.50
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Aggregates
Fine Aggregates (Approved Source)
188
Gravel 3/4" dia. (Approve Source)
180
cu.m
cum
640.00
790.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
LOCAL
SHOPPING
FOR GOODS
(LSG)
448,305.00
169,772.63
29,959.88
198,858.00
49,714.50
368,630.63
79,674.38
272,849.50
175,455.50
234,407.80
134,222.83
38,441.70
41,232.68
120,320.00
LOCAL
142,200.00 SHOPPING
262,520.00 FOR GOODS
(LSG)
60,880.00
323,400.00
102,272.00
120,870.00
18,048.00
21,330.00
223,142.00
39,378.00
51,748.00
274,890.00
9,132.00
48,510.00
121,992.00
21,528.00
121,992.00
21,528.00
43,316.00
165,308.00
7,644.00
29,172.00
Package 3-A
Aggregates
Class A Stone
208
Sub-Total (Actual)
cum
690.00
LOCAL
SHOPPING
143,520.00 FOR GOODS
(LSG)
50,960.00
143,520.00
194,480.00
Package 4
Form Lumber
2"x2"x8' Coco Lumber (Formworks)
384
bd.ft
21.00
648
bd.ft
21.00
Sub-Total (Actual)
Package 5
8,064.00
6,854.40
1,209.60
13,608.00
11,566.80
2,041.20
18,421.20
3,250.80
877.20
19,298.40
154.80
3,405.60
LOCAL
SHOPPING
FOR GOODS
21,672.00
(LSG)
1,032.00
22,704.00
31
cu.m
LOCAL
SHOPPING
- FOR GOODS
(LSG)
1,550.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
1,550.00
1,240.00
1,240.00
310.00
310.00
Package 6
lot
45,000.00
45,000.00
38,250.00
6,750.00
Backhoe
Road Grader
Road Roller
4
4
1
days
days
days
20,000.00
15,000.00
15,000.00
80,000.00
LOCAL
60,000.00 SHOPPING
15,000.00 FOR GOODS
68,000.00
51,000.00
12,750.00
12,000.00
9,000.00
2,250.00
170,000.00
30,000.00
7,500.00
192,500.00
6,375.00
163,625.00
1,125.00
28,875.00
10,500.00
7,800.00
8,400.00
6,240.00
2,100.00
1,560.00
14,640.00
3,660.00
18,960.00
33,600.00
4,740.00
8,400.00
Sub-Total (Actual)
200,000.00
(LSG)
Package 10
Package 9
Package 8
Package 7
15
15
days
days
700.00
520.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Labor
Skilled
1.00
Unskilled
1.00
23,700.00
42,000.00
lot
lot
82,150.00
84,050.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Project Billboard
Project Steel Billboard
1.00
unit
8,450.00
1.00
pcs.
pairs
pcs.
pcs.
pairs
set
82,150.00
LOCAL
84,050.00 SHOPPING
166,200.00 FOR GOODS
(LSG)
0.00
166,200.00
8,450.00
13,612.84
11,153.12
4,000.00
2,163.02
40,000.00
39,340.00
24,765.96
6,163.02
79,340.00
0.00
24,765.96
0.00
6,163.02
0.00
79,340.00
6,760.00
1,690.00
6,760.00
1,690.00
9,500.00
1,659,784.50
840.00
7,600.00
1,280,546.66
210.00
1,900.00
243,966.82
85.00
35.00
225.00
8.50
280.00
850.00
350.00
2,250.00
85.00
2,800.00
680.00
280.00
1,800.00
68.00
2,240.00
170.00
70.00
450.00
17.00
560.00
1,750.00
1,750.00
1,400.00
350.00
8,085.00
6,468.00
1,617.00
8,705.00
6,964.00
1,741.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Total Direct Cost
Handtools & Personal Protective Equipment (PPE)
Hard Hat
10.00
Hand Glooves
10.00
Shovel w/ handle
10.00
Face Mask
10.00
Safety boots
10.00
LOCAL
SHOPPING
18,300.00 FOR GOODS
(LSG)
LOCAL
SHOPPING
8,450.00 FOR GOODS
(LSG)
1,050.00
LOCAL
SHOPPING
FOR GOODS
(LSG)
79,340.00
Package 13
Package 12
Package 11
1.00
pcs.
6,400.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Environmental Mitigating Cost:
Warning Sign
5.00
Barricade
5.00
16,790.00
13,432.00
6,400.00
5,120.00
1,280.00
5,120.00
1,280.00
880.00
6,000.00
220.00
1,500.00
1,120.00
1,120.00
280.00
280.00
2,240.00
560.00
640.00
2,880.00
160.00
720.00
LOCAL
SHOPPING
6,400.00 FOR GOODS
(LSG)
1,100.00
7,500.00
pcs.
pcs.
280.00
280.00
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
1,400.00
1,400.00
LOCAL
SHOPPING
2,800.00 FOR GOODS
(LSG)
800.00
3,600.00
31,500.00
8,500.00
50,500.00
7,500.00
3,358.00
5,860.00
7,491.42
8,000.00
8,000.00
3,000.00
5,253.75
118,253.75
15,491.42
16,253.75
5,860.00
109,150.40
227,404.15
135,538.75
194,289.40
0.00
15,491.42
29,319.42
(54,214.07)
0.00
16,253.75
19,710.75
(4,471.93)
0.00
5,860.00
5,860.00
115,060.00
1,795,323.25
1,309,866.08
263,677.57
85,200.00
2,403,025.00
1,602,080.00
320,340.00
200,260.00
97.18%
292,213.92
12.15%
Materials Testting
15,000.00
5,253.75
Treasurer Bond
CFA
Contingency Cost
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Total Indirect Cost
TOTAL SAVINGS DETERMINED AFTER PROCUREMENT
SAY
%
1,795,323.25
0.00
Checked & Reviewed by:
Recommending Approval:
FELIX ABELLANO
TEODOLO T. BULISID
RODSON R. ESCORA
PPT
CARMEN A
Municipa
.
PERCENTAGE WEIGHT
TO KC
GRANT
TO LCC
CASH
AMOUNT
(PESO)
FUND SOURCE
LEGEND:
KC GRANT
1,648,497.00
1,591,690.12
80.00%
80%
TOTAL LCC
378,840.65
198,961.27
198,961.27
1,989,612.65
10.00%
10.00%
100%
10.00%
10.00%
100%
LCC - In-kind
LCC - Cash
TOTAL
37,725.00
341,115.65
2,027,337.65
REMARKS
TRANCHING SCHEDULE
TOTAL
2nd Tranche
3rd Tranche
LCC Cash
KC Grant
LCC Cash
TOTAL
KC Grant
LCC Cash
54,022.50
360,150.00
13,872.00
2,448.00
16,320.00
592.88
104.63
697.50
11,602.50
2,047.50
13,650.00
332,194.88
58,622.63
390,817.50
61,103.52
10,782.98
71,886.50
393,298.40
69,405.60
462,704.00
28,765.00
115,060.00
28,765.00
143,825.00
28,765.00
115,060.00
28,765.00
143,825.00
169,772.63
29,959.88
199,732.50
198,858.00
49,714.50
248,572.50
368,630.63
79,674.38
448,305.00
234,407.80
134,222.83
102,272.00
120,870.00
38,441.70
41,232.68
18,048.00
21,330.00
272,849.50
175,455.50
120,320.00
142,200.00
223,142.00
39,378.00
262,520.00
9,132.00
48,510.00
60,880.00
323,400.00
51,748.00
274,890.00
-
121,992.00
21,528.00
143,520.00
121,992.00
21,528.00
143,520.00
7,644.00
29,172.00
50,960.00
194,480.00
43,316.00
165,308.00
MONTHS
1
306,127.50
PROPOSED
IMPLEMENTATION
SCHEDULE
6,854.40
1,209.60
8,064.00
2,041.20
13,608.00
18,421.20
3,250.80
21,672.00
8,325.00
0.00
7,835.00
0.00
45,621.02
0.00
8,325.00
7,835.00
45,621.02
8,325.00
1,550.00
1,550.00
-
6,750.00
45,000.00
68,000.00
51,000.00
12,750.00
12,000.00
9,000.00
2,250.00
80,000.00
60,000.00
15,000.00
170,000.00
30,000.00
200,000.00
1,125.00
28,875.00
7,500.00
192,500.00
45,621.02
310.00
310.00
38,250.00
6,375.00
163,625.00
7,835.00
1,032.00
22,704.00
-
2,500.00
5,825.00
154.80
3,405.60
-
1,240.00
1,240.00
22,087.16
23,533.86
11,566.80
877.20
19,298.40
-
4,000.00
3,835.00
8,400.00
6,240.00
2,100.00
1,560.00
10,500.00
7,800.00
14,640.00
3,660.00
18,300.00
18,960.00
33,600.00
75,700.00
74,026.98
4,740.00
8,400.00
10,500.00
11,823.02
23,700.00
42,000.00
86,200.00
85,850.00
22,323.02
172,050.00
0.00
149,726.98
0.00
22,323.02
0.00
172,050.00
6,760.00
1,690.00
8,450.00
6,760.00
1,690.00
8,450.00
149,726.98
840.00
7,600.00
1,405,507.68
210.00
1,900.00
260,126.82
1,050.00
9,500.00
1,665,634.50
680.00
280.00
1,800.00
68.00
2,240.00
170.00
70.00
450.00
17.00
560.00
850.00
350.00
2,250.00
85.00
2,800.00
1,400.00
350.00
1,750.00
6,468.00
1,617.00
8,085.00
6,964.00
1,741.00
8,705.00
13,432.00
3,358.00
5,120.00
1,280.00
6,400.00
5,120.00
1,280.00
6,400.00
880.00
6,000.00
220.00
1,500.00
13,488.58
7,000.00
30,000.00
6,000.00
8,708.92
1,500.00
5,008.58
1,500.00
4,000.00
1,100.00
7,500.00
1,120.00
1,120.00
280.00
280.00
1,400.00
1,400.00
2,240.00
560.00
2,800.00
640.00
2,880.00
3,442.50
16,790.00
160.00
720.00
800.00
3,600.00
19,348.58
7,000.00
37,491.42
6,000.00
12,151.42
1,500.00
13,008.58
1,500.00
31,500.00
8,500.00
50,500.00
7,500.00
12,000.00
-
3,000.00
5,253.75
-
15,000.00
5,253.75
-
3,442.50
60,488.58
16,717.50
81,840.00
36,413.75
118,253.75
0.00
3,442.50
3,442.50
28,765.00
94,150.40
154,638.98
60,488.58
94,150.40
15,000.00
31,717.50
16,717.50
15,000.00
94,150.40
175,990.40
95,668.00
154,996.33
15,000.00
51,413.75
39,870.75
39,293.08
109,150.40
227,404.15
135,538.75
194,289.40
11,277.50
106,109.60
25,042.50
1,501,175.68
299,997.57
1,801,173.25
40,042.50
200,260.00
40,042.50
1,837,292.00
371,253.00
2,403,025.00
115,060.00
12.15%
94,150.40
(336,116.32)
(71,255.43)
Submitted by:
Noted by:
CARMEN A. GAUDIANO
GEORGE A. ALAS-AS
GEOGRE S. ISULAT
Municipal Engineer
BSMPC
Sub-Project duration
: 90
Physical Target
:
:
:
:
:
Region
Province
Municipality
Barangay
Calendar Days
300 L.M.
VII CENTRAL VISAYAS
NEGROS ORIENTAL
DAUIN
MAGSAYSAY
Direct Cost
Indirect Cost
Date Started
Target Completion
Mode of Implementation
ITEM
NO.
I
DESCRIPTION
QTY
II
Emabankment
III
IV
Grouted Riprap
VI
UNIT
233.33 cu.m.
Err:509
PHYSICAL
(%)
TARGET
150,800.00
8.54%
(168,931.50)
-9.57%
393.00 cu.m.
395,987.00
22.42%
1,200.00 sq.m.
909,418.00
51.49%
45.00 cu.m.
468,345.00
26.52%
10,425.00
0.59%
1.00
cu.m.
WEIGHT
AMOUNT
lot
T O T A L
1,766,043.50
100.00%
PLANNED
PHYSICAL
% PROGRESS (Actual)
PROGRESS (Planned)
FINANCIAL
PROGRESS (Actual)
Prepared by:
WEEK 2
WEEK 3
# # # # # # # # # # # # # # # # # # #
ACTUAL
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
# #
ACTUAL
PLANNED
# # # # # # # # # # # # # # # # # # #
ACTUAL
1
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
Concurred by:
JOCELYN ALAS-AS
PIT Chairperson
WEEK 1
PLANNED
MONTH 1
10
11
12
13
14
15
16
17
18
19
2.73%
2.13%
3.00%
2.73%
4.86%
7.86%
48,125.00
37,700.00
52,981.31
48,125.00
85,825.00
138,806.31
SELVINO BULISID
MIT Team Leader
RODSON
Deputy Area
: P
1,854,700.00
LABOR
: P 1,766,043.50
: P
88,656.50
:
:
: By Community Force Account (CFA)
No. of Days
90
SKILLED
90
UNSKILLED
TOTAL
MONTH 2
EEK 3
WEEK 4
WEEK 5
WEEK 6
MONTH 3
WEEK 7
WEEK 8
WEEK 9
WEEK 10
WEEK 11
WEEK
# # # # # # # # #
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
##########################################
###############################################################################################################
################################################
# # # # # # # # ######################
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
43
44
45
46
47
48
49
50
51
52
53
54
55
56
64
65
66
67
68
69
70
71
72
73
74
75
76
77
85
86
87
88
89
90
91
99
100
101
102
103
104
105
106
107
.00%
0.22%
5.00%
15.00%
17.00%
18.00%
13.81%
12.00%
5.00%
3.00%
.86%
8.08%
13.08%
28.08%
45.08%
63.08%
76.89%
88.89%
93.89%
96.89%
52,981.31
3,913.70
88,302.18
264,906.53
300,227.40
317,887.83
243,890.61
211,925.22
88,302.18
52,9
38,806.31
142,720.01
231,022.18
495,928.71
796,156.10
1,114,043.93
1,357,934.54
1,569,859.76
1,658,161.93
1,711,1
ewed by:
RODSON R. ESCORA
Deputy Area Coordinator
Approved by:
CARMEN A. GAUDIANO
Municipal Engineer
Noted by:
GEORGE ALAS-AS
BSPMC
GEORG
RT
Average
Rate/Day
300.00
No. of Days
90
90
275.00
MONTH 3
MONTH 4
WEEK 12
WEEK 13
####################################
####################################
108
109
110
111
112
113
114
115
116
117
3.00%
2.00%
96.89%
98.89%
118
119
52,981.31
35,320.87
1,711,143.24
1,766,043.50
GEORGE S. ISULAT
RCIS
March 4, 2014
March 7, 2014
-do-
Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF
Procurement Activities
Package 1: Hardware
Package 3: Aggregates
Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF
Procurement Activities
Timeline to complete
the activity (Inclusive
Dates)
Package 5: Water
Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF
Package 7: Equipment Rental (Light)
7: Opening of Canvass
Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF
Procurement Activities
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices
Timeline to complete
the activity (Inclusive
Dates)
Procurement Activities
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices
Timeline to complete
the activity (Inclusive
Dates)
-do-
Procurement Activities
Procurement Activities
Timeline to complete
the activity (Inclusive
Dates)
Prepared by:
Reviewed & Checked by:
PT Chairperson
Name of Potential
Suppliers Contractors
Resources
Requirement
Expected outputs/
Remarks
POW/Detailed
Estimates
Draft PCPP
Final PCPP
Final PCPP
Conference Conducted
Office supplies
Minutes of Conference
Invitation to Bid/Bid
Documents
Supplier's Office,
Establishment
Supplier's: Zenith
Commercials, Golden Rule,
New Bian Yek Commercials,
Dgte. YY Trading,
Duplamilco
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Supplier's: Gold
Enterprises, Lucky
Enterprises, JM
Commercials
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Name of Potential
Suppliers Contractors
Resources
Requirement
Expected outputs/
Remarks
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Suppliers's: Gold
Enterprises, Maureze
Construction, Duplamilco
Inc., Alagasi's Construction
Supply
Supplier's Office,
Establishment
Suppliers: Resident of
Barangay Tunga-Tunga
Supplier's Office,
Establishment
Supplier's:Uymatiao
Construction, HLJ
Construction, Big Foot,
Philsouth Contractors
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Supplier's: Alagasi's
Construction Supply,
Rejoice Hardware, LKC
Hardware
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Supplier's: Alagasi's
Welding Shop, Zamora
Welding Shop, Orient Pearl
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Supplier's: Rejoice
Hardware, Premium
Hardware, Gold Enterprises,
LKC Hardware
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Supplier's: Zipline
Commercial, I Concept,
ADS Unlimited, Sun Signs
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Supplier's Office,
Establishment
Supplier's: Zenith
Commercials, Golden Rule,
New Bian Yek Commercials,
Dgte. YY Trading,
Duplamilco
Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt
Canvass Form/Request
for Qoutation Served,
Signed AR
Name of Potential
Suppliers Contractors
Resources
Requirement
Expected outputs/
Remarks
Submitted Canvass
Form/Request for
Qoutation
Abstract of Canvass
Name of Potential
Suppliers Contractors
Resources
Requirement
Expected outputs/
Remarks
Office Supplies
Minutes of Opening
Office Supplies
Submitted Canvass
Form/Request for
Quotation
Minutes of Evaluation
Submitted Canvass
Form/Request for
Quotation
Minutes of Evaluation
Submitted Canvass
Form/Request for
Quotation
Abstract of Canvass
Submitted Canvass
Form/Request for
Quotation
Abstract of Canvass
Abstract of Canvass
Purchased Order
Venue
of meetingOffice
and
Brgy.
Hall/BSPMC
place/s to conduct
procurement
Abstract
of Canvass
Resources
Requirement
Purchased
Order
Expected
outputs/
Remarks
Abstract of Canvass
Purchased Order
Purchased Order
Approved Purchased
Order
Purchased Order
Approved Purchased
Order
Supplier's Office,
Establishment
Name of Potential
Suppliers Contractors
Supplier's Office,
Establishment
Project Site
Delivery
Receipt/Delivered
Goods
Goods Received
Project Site
Delivery
Receipt/Delivered
Goods
Goods Received
Project Site
Notice to Commence
Mobilization Started
Name of Potential
Suppliers Contractors
Noted by:
Resources
Requirement
Expected outputs/
Remarks
Approved by:
BSPMC Chairperson
: October 9, 2013
: Concreting
Barangay
Municipality
: Magsaysay
: Dauin
:
:
Province
: Negros Oriental
SOURCES OF FUNDS
TOTAL
74,772.40
56,407.25
PACKAGES
PACKAGE ITEMS
QTY
UNIT
UNIT COST
LCC:
AMOUNT
(PESO)
FUND SOURCE
LEGEND:
TO KC
GRANT
TO LCC CASH
KC GRANT
1,523,075.00
1,218,460.00
241,240.00
1,459,700.00
80.00%
80%
TOTAL LCC
331,625.00
152,307.50
152,307.50
1,523,075.00
30,155.00
30,155.00
301,550.00
182,462.50
182,462.50
1,824,625.00
10.00%
10.00%
100%
10.00%
10.00%
100%
LCC - In-kind
LCC - Cash
TOTAL
30,075.00
301,550.00
1,854,700.00
TRANCHING SCHEDULE
PROC
METHOD
TOTAL
TOTAL
1st Tranche
KC Grant
2nd Tranche
LCC Cash
KC Grant
3rd Tranche
LCC Cash
KC Grant
TOTAL
LCC Cash
KC Grant
LCC Cash
REMARKS
131,179.65
.
PERCENTAGE WEIGHT
DESCRIPTION
KC Grant:
of Barangay Road
Err:509
120 C.D
PROPOSED
IMPLEMENTATION
SCHEDULE
MONTHS
1
233.33
Err:509
393.00
1,200.00
45.00
1.00
cu.m.
cu.m.
cu.m.
sq.m.
cu.m.
lot
ok
10.00
10.00
1.00
pcs.
pcs.
set
1.00
pcs.
Package 4
Package 4
sub-total
package 5
237.26
Err:509
906.31
695.40
3,212.02
9,350.00
125.00
25.00
1,890.00
ok
55,360.00
49,577.88
5,782.12
Err:509
Err:509
Err:509
356,179.75
315,807.30
40,372.45
LOCAL
834,479.00 BIDDING FOR
757,490.71
76,988.29
144,541.00 WORKS (LBW)
1,607.47
3,861.35
9,350.00
8,372.12
977.88
124,694.33
(49,428.95)
100,378.93
75,883.66
Err:509
Err:509
Err:509
1,250.00
250.00
1,890.00
3,390.00
sub-total
Environmental Mitigating Cost:
Warning Sign
Barricade
sub-total
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
Materials Testting
5.00
5.00
pcs.
pcs.
6,000.00
420.00
300.00
7,500.00
7,500.00
2,100.00
1,500.00
3,600.00
Contingency Cost
sub-total
20,766.88
26,766.88
121,246.79
91,246.79
163.04
32.61
246.52
1,086.96
217.39
1,643.48
-
1,250.00
250.00
1,890.00
1,680.00
1,200.00
2,880.00
420.00
300.00
720.00
32,000.00
6,000.00
8,000.00
8,500.00
8,000.00
1,500.00
2,000.00
5,253.75
58,874.76
46,000.00
25,253.75
20,311.33
59,563.43
Err:509
Err:509
200,260.00
26,766.88
180,810.22
22,547.72
Err:509
Err:509
Err:509
1,218,460.00
241,240.00
152,307.50
30,155.00
152,307.50
30,155.00
Err:509
Err:509
Err:509
Err:509
10.00%
Err:509
Recommending Approval:
(47,952.50)
3,388.12
10.00%
(28,502.71)
7,607.28
Submitted by:
Err:509
Err:509
80.00%
163.04
32.61
246.52
442.17
Err:509
PPT
179,948.67
20,311.33
SAY
30,000.00
1,500.00
1,500.00
LOCAL
SHOPPING FOR
GOODS (LSG)
1,824,625.00
Err:509
Checked & Reviewed by:
6,000.00
82,876.49
6,000.00
6,000.00
163,947.84
GRAND TOTAL CASH
97,072.18
49,577.88
5,782.12
55,360.00
Err:509
Err:509
Err:509
315,807.30
40,372.45
356,179.75
757,490.71
76,988.29
834,479.00
6,000.00
128,679.65
15,861.35
144,541.00
8,372.12
977.88
9,350.00
124,694.33
124,694.33
3,728.39
100,378.93
100,378.93
9,728.39 Err:509
Err:509
Err:509
2,947.83
LOCAL
SHOPPING FOR
GOODS (LSG)
21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
71,694.09
Treasurer Bond
1,086.96
217.39
1,643.48
LOCAL
SHOPPING
FOR GOODS
(LSG)
CFA
Package 3
Package 1
Direct Cost:
2,947.83
442.17
3,390.00
6,000.00
6,000.00
1,500.00
1,500.00
7,500.00
7,500.00
1,680.00
1,200.00
2,880.00
420.00
300.00
720.00
2,100.00
1,500.00
3,600.00
12,819.33
21,000.00
32,000.00
6,000.00
8,000.00
58,874.76
8,500.00
8,000.00
1,500.00
2,000.00
5,253.75
12,819.33
21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
71,694.09
12,819.33
125,874.76
38,073.08
163,947.84
688.67
Noted by:
CARMEN A. GAUDIANO
GEORGE ALAS-AS
GEORGE S. ISULAT
Municipal Engineer
BSMPC
Destination/Description
Fare/
Allowance/
Unit Price
Qty.
Unit
pesos
No of
transactions
1 times
persons x
1 times
persons x
2 times
130.00
persons x
8 times
80.00
persons x
8 times
130.00
persons x
8 times
meals
80.00
persons x
8 times
Supplies
Snacks
50.00
20.00
12
20
meetings
persons x
15 times
130.00
persons x
15 times
80.00
persons x
15 times
130.00
persons x
30 times
80.00
persons x
30 times
350.00
300.00
2.00
1.00
30.00
685.00
50.00
35.00
20.00
3.00
20.00
30.00
x
x
x
x
x
x
x
x
x
x
x
x
6
6
2250
1190
8
1
4
1
3
40
2
1
reams
reams
sheets
pc
boxes
pc
pcs
ps
pc
pcs
box
pc
Log book
80.00
pcs
Fastener
50.00
box
meals
1,500.00
130.00
80.00
Sub-Total
2. TE for procurement
transactions of CVs
BSPMC office to Dgte. (vice
versa)
Serving of Canvass
meals
Serving of PO & Payments
Sub-Total
3. Project Meetings
Sub-Total
4. MCT-Initiated Meetings
BSPMC office to MCT Office
(vice versa)
Meals
Sub-Total
5. Treasurer Payroll Processing
BSPMC office to Dauin (vice
versa)
Meals
Sub-Total
6. Forms/Supplies and Reproduction
Bondpaper long
Bondpaper short
Reproduction
Petty Cash Box
Staple Wire
Calculator
Columnar Book
Liquid Eraser
Paste/Glue
Folder long
Paper clip
Pentil pen
Sub-Total
TOTAL FOR ADMIN COST
Prepared by :
Approved by :
ELSA A. TRUNO
GEORGE ALAS-AS
MEO Staff
BSPMC Chairperson
Checked by:
Concurred by :
RODSON R. ESCORA
Deputy Area Coordinator
Recommending Approval:
Municipal Mayor
Noted by:
GEORGE S. ISULAT
Regional Community Infrastructure Specialist
Amount
1,500.00
260.00
320.00
2,080.00
3,120.00
1,920.00
2,080.00
1,280.00
8,400.00
=
=
600.00
6,000.00
6,600.00
9,750.00
6,000.00
15,750.00
3,900.00
2,400.00
6,300.00
=
=
=
=
=
=
=
=
=
=
=
=
2,100.00
1,800.00
4,500.00
1,190.00
240.00
685.00
200.00
35.00
60.00
120.00
40.00
30.00
320.00
50.00
11,370.00
50,500.00
GEORGE ALAS-AS
BSPMC Chairperson
Negros Oriental
Mode of Implementation:
By Contract
PACKAGE ITEMS
Direct Cost:
Materials
Package 1
Unskilled labor
Contract
Indirect Cost:
Hand tools/PPE
Pre-engineering
Project Supervision
CFA
In - Kind
In - Kind
25,260.00
3,157.50
3,157.50
2,000.00
3,200.00
400.00
400.00
### 3,557.50
3,557.50
TOTAL
Workshop output of:
Checked by:
Reviewed by:
FELIX AVELLANO
Procurement Team Head
CARMEN A. GAUDIANO
RODSON R. ESCORA
Municipal Engineer
TERPART CONTRIBUTION
ED and SCHEDULE OF
RY
PROPOSED
IMPLEMENTATION
TOTAL
SCHEDULE
31,575.00
2,000.00
4,000.00
ESCORA
ordinating Team
###
Submitted by:
GEORGE ALAS-AS
BSPMC Chairperson
1st Tranche
CHECKLIST OF DOCUMENTARY REQUIREMENTS
Barangay MAGSAYSAY
Municipality of Dauin
Sub-Project Title: Concreting of Barangay Road
Phase/Cycle: 2
RFR REVIEW SHEET
Item #
1st TRANCHE
Requirements
Comments
Actions Taken
For Asec. CGG/ NPM's Signature
For regional compliance
For Transmittal to Finance Unit
Returned to Region
Unit used
No. of
Units
Per Unit
Cost
Total Sub-Project
Cost
I. Administrative Cost
TE for opening of BSPMC DBP Account of CV's
TE for procurement transactions of CV's
Project Meetings
MCT-Initiated Meetings
Treasurer Payroll Processing
Forms/Supplies and Reproduction
Sub Total
II. Other Indirect Costs
Overhead Cost
Handtools
Pre-engineering
Project Supervisions
Bidding Publication
Environmental Mitigating Cost
BSPMC Filing Cabinet
Material Testing
Treasurer's Bond
VAT ( 7% of Total Direct Cost)
Contractors Profit (10%)
Contingency
Sub Total
III. Direct Cost
Labor
Materials
Equipment Rental
Sub Total
TOTAL PROJECT COST
IV. Operations & Maintenance
Other Amenities
Sub Total
GRAND TOTAL
Prepared by:
BERNADITA TUALA
Barangay Treasurer
2,800.00
7,140.00
5,400.00
9,900.00
6,000.00
8,760.00
40,000.00
21,000.00
3,390.00
2,000.00
12,500.00
7,500.00
3,600.00
7,500.00
10,000.00
5,253.75
133,567.97
190,811.39
95,363.05
492,486.16
198,825.00
1,526,348.84
182,940.00
1,908,113.84
2,440,600.00
0.00
0.00
2,440,600.00
Pro-posed
Amount of Grant
Mun LGU
2,240.00
560.00
560.00
5,712.00
4,320.00
7,920.00
4,800.00
7,008.00
32,000.00
1,428.00
1,080.00
1,980.00
1,200.00
1,752.00
8,000.00
0.00
1,428.00
1,080.00
1,980.00
1,200.00
1,752.00
8,000.00
18,500.00
1,632.00
2,500.00
1,758.00
1,000.00
8,500.00
1,500.00
720.00
1,500.00
2,000.00
5,253.75
133,567.97
0.00
2,500.00
1,758.00
2,000.00
12,500.00
1,500.00
720.00
1,500.00
2,000.00
5,253.75
133,567.97
0.00
17,038.50
180,338.22
6,000.00
2,880.00
6,000.00
8,000.00
190,811.39
78,324.55
312,147.94
17,038.50
175,338.22
0.00
0.00
1,000.00
4,000.00
5,000.00
0.00
167,250.00
1,336,828.06
154,374.00
1,658,452.06
2,002,600.00
31,575.00
189,520.78
28,566.00
218,086.78
401,425.00
0.00
5,000.00
31,575.00
31,575.00
0.00
0.00
31,575.00
189,520.78
28,566.00
249,661.78
438,000.00
0.00
2,002,600.00
0.00
401,425.00
0.00
5,000.00
0.00
31,575.00
0.00
0.00
0.00
0.00
438,000.00
Approved by:
GEORGE ALAS-AS
BSPMC Chairperson
Target Date of
Delivery of LCC
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
KALAHI-CIDSS:MCC
As of October 31, 2
PA
C
KA
G
ES
Barangay :
MAGSAYSAY
Municipality : Dauin
Sub-Project : Concreting of Barangay Road
Package Items
Cash
In-Kind
SCHEDULE OF LOCAL
2nd Tranche
Cash
1st Tranche
Cash
Planned
In-Kind
Actual
Planned
Actual
Planned
DIRECT COST:
I# 102-Surplus Common
I# 104-Embankment
I# 200-Aggregate Sub-ba
I# 311-PCCP
I# 505-Grouted Riprap
I# 500-Installation of RCPC
Project Steel Billboard
Unskilled Worker
TOTAL DIRECT COST
INDIRECT COST:
Overhead Cost
Bidding Publication
Administrative Cost
Package 5
Materials Testing
Treasurer's Bond
Contingency
Handtools / PPE
Package 2
Pre-Engineering
Project Supervision
Environmental Impact
Package 4
BSPMC Filing Cabinet
Package 3
VAT (7 % of Direct Cost
Package 1
TOTAL INDIRECT COST
GRAND TOTAL
Package 1
Prepared by:
11,766.00
25,013.09
35,732.85
81,221.35
53,353.50
6,000.00
1,500.00
208,586.79
31,575.00
0.00 31,575.00
0.00
6,000.00
0.00
0.00
34,042.50
34,042.50
40,042.50
1,500.00
8,000.00
2,000.00
5,253.75
1,758.00
8,500.00
720.00
1,500.00
82,521.46
111,753.21
320,340.00
2,000.00
4,000.00
0.00 6,000.00
0.00 37,575.00
Verified by:
ARLENE P. GESULGA
Municipal Financial Analyst
ALAHI-CIDSS:MCC PROJECT
438,000.00
:
:
400,425.00
37,575.00
0.00
0.00
0.00
Planned
Actual
Planned
Actual
Planned
TOTAL
Cash
Actual
0.00
0.00
6,000.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,500.00
8,000.00
2,000.00
5,253.75
17,038.50
1,758.00
0.00
8,500.00
720.00
1,500.00
133,567.96
179,838.21
400,425.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
17,038.50
0.00
0.00
0.00
0.00
Verified by:
17,004.00
0.00 34,042.50
0.00 40,042.50
0.00
0.00
0.00
0.00
Actual
11,766.00
25,013.09
35,732.85
81,221.35
65,353.50
0.00
1,500.00
0.00
220,586.79
6,000.00
0.00
Planned
Noted by:
JOEL A. EREDIANO
Area Coordinator
TOTAL
In-Kind
Planned
Actual
0.00
0.00
0.00
0.00
0.00
0.00
0.00
31,575.00
31,575.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,000.00
4,000.00
0.00
0.00
0.00
6,000.00
37,575.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
oordinator (RFFP-Coordinator)