Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 63

OFFICE OF THE BRGY SUB-PROJECT MANAGEMENT COMMITTEE (BSPMC)

Barangay of Anhawan
Municipality of Dauin
Province of Negros Oriental, Region VII
SUB-PROJECT PROGRAM-OF-WORK
Project Title
Category

: Concreting of Access Road with Slope Protection


: Public Goods

Physical Target
Total Sub-Project Cost

: 0.30 KM
PHP 1,854,700.00

Mode of Implementation

: By Contract

Project Description:

Sub-Project Duration

: 90 Calendar Days

Surplus Common Excavation, Embankment, Aggregate Sub-Base Course,


PCCP, Grouted Riprap and Installation of Project Steel Billboard

Equipment/Tools Needed

Road Grader,Back Hoe, Road Roller, Concrete


Mixer and Vibrator

Technical Personnel

: Engineer, Foreman, Carpenter/Mason,


Instrument Man, Survey Aide and Riprapper

No. of Laborers

: 90 person days

Sub-Project Location:
Sub-Project Site Location is 8KM away from Town Proper
Item
Scope of Work
No.

%(Wt)

102

Surplus Common Excavation

201

Aggregate Base Course

311

Portland Cement Conrete Pavement (PCCP)

505

Grouted Riprap (Line Ditched Canal)

Quantity

Unit

Unit Cost (P)

233.33

cu.m.

238.55

55,660.00

24.87%

393.00

cu.m.

907.45

356,629.75

60.09%

1200.00

sq.m.

718.11

861,729.00

10.50%

45.00

cu.m.

3,345.36

150,541.00

0.66%

1.00

lot

9,425.00

9,425.00

3.88%

SPL 1 Project Steel Billboard


Total Direct Cost

100.00%

658,761.60

Total (P)

1,433,984.75

SOURCE OF FUND
Breakdown of Estimated Project Cost

KALAHI Grant

Community

Barangay LGU

In-Kind
A.

Cash

Municipal LGU

In-Kind

Cash

Total

In-Kind

Direct Cost
Materials

983,805.09

Equipment

150,672.57

10,000.00
-

117,894.66

1,111,699.75

19,587.43

170,260.00

63,750.00

88,275.00

1,433,984.75

21,000.00

3,390.00

Labor
Skilled

63,750.00

Unskilled

64,200.00

24,075.00

1,262,427.65

24,075.00

Sub-Total A
B.

10,000.00

137,482.10

Indirect Cost
Overhead Cost

21,000.00

2,947.83

Handtools and Prot. Equip. (PPE)


Pre-engineering

1,000.00

Project Supervision

442.17
8,500.00

1,000.00

2,000.00

4,000.00

12,500.00

3,130.43

469.57

3,600.00

Administrative Cost

34,782.61

5,217.39

40,000.00

Bidding Publication

6,521.74

978.26

7,500.00

Materials Testing

8,695.65

1,304.35

10,000.00

Environmental Metigating Cost

Treasurer's Bond

5,253.75

5,253.75

VAT (7% of Total Direct Cost)

100,378.93

100,378.93

143,398.48

124,694.33

Sub-Total ( B )

201,772.59

TOTAL ( A+ B )

1,464,200.24

Contractor Profit (10%)

ADD: Contingency

141,248.57

5,000.00

349,021.16

5,000.00

1,783,005.91

24,075.00

10,000.00

1,000.00

278,730.67

24,075.00

10,000.00

1,000.00

291,550.00

5,000.00

1,523,075.00

82.12%

301,550.00

16.26%

30,075.00

1.62%

291,550.00

5,000.00

58,874.76

Total Estimated Project Cost

1,523,075.00

12,819.33

MCC Grant
Cost Sharing to TEPC

18,704.15

1,000.00

LCC Cash
LCC Inkind

71,694.09

1,854,700.00

100.00%

Add: O and M (Other Amenities)


GRAND TOTAL

1,523,075.00

24,075.00

Prepared by :

10,000.00

1,000.00

1,854,700.00

Approved by :

ENGR. JERRY C. BALIOLA

JOY ALABAN

Service Provider

BSPMC Chairperson

Checked by:

Concurred by :

ENGR. RODSON R. ESCORA

ORENCIO T. SARENSE

Deputy Area Coordinator

Sanggunian Barangay Member

Recommending Approval:

ENGR. CARMEN A. GAUDIANO


Municipal Engineer - MCT DAC

HON. NEIL B. CREDO


Noted by:

ENGR. GEORGE S. ISULAT


Regional Community Infrastructure Specialist

Municipal Mayor

NAME OF SUB-PROJE: CONCRETING OF ACCESS ROAD with SLOPE PROTECTION


: Anhawan, Dauin, Negros Oriental
LOCATION:

BILL OF QUANTITIES
COST SHARING
ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION

102 Surplus Common Excavation


see vol. computation
A. Materials
Existing Ground Profile

QUANTI
UNIT
TY

233.33
233.33

cu.m.
cu.m.

233.33

cu.m.

Rate per
No. of
Day / Unit
Crew/
Cost

Add
Frieght &
Handling
Cost

Total Unit
Cost

* pls see equipment


* pls see equipment
* pls see equipment

2.00
3.00
2.00

Day/s
Day/s
Day/s

1.00
4.00
2.00

350.00
300.00
275.00

Sub-Total
C. Equipment
Preparation of fnish grade of item 200
including trench canal excavation
Mobilization & Demobilization
1-Backhoe (280 cu.m / day)
3-Dump Truck (240cu.m / day)

189.24/280 =
189.24/240 =

1.00
2.00
1.00

lot
Day/s
Day/s

10,000.00
16,880.00
6,500.00

1.00
3.00

Total for Item102


201

Aggregate Base Course (including 0.20m


width shouldering both sides)

Total Compacted Volume =


Total Loose Volume =

393.00

cu.m.

(1.31*300) =

393.00

cu.m.

(1.31*300*1.15) =

451.95

cu.m.

451.95

cu.m.

A. Materials
Aggregate Subbase Course (Balastro Class "A" Type)
Sub-Total
B. Labor
Construction Foreman
*pls see equipment
Driver / Operator
*pls see equipment
Laborer
*pls see equipment
Sub-Total
C. Equipment
Mobilization & Demobilization
1-Road Roller (210cu.m/day)
227.7/210 =
1-Road Grader (400 cu.m / day)
227.7/400 =

3.00
5.00
3.00

Day/s
Day/s
Day/s

1.00
3.00
2.00

lot
Day/s
Day/s

550.00

55.00

605.00

1- Concrete Vibrator

180/7.82 =

700.00
3,600.00
1,100.00
5,400.00

700.00
3,600.00
800.00
5,100.00

10,000.00
33,760.00
6,500.00
50,260.00

8,849.56
29,876.11
5,752.21
44,477.88

55,660.00

49,577.88

273,429.75
273,429.75

241,973.23
241,973.23

350.00
300.00
275.00

1,050.00
3,000.00
1,650.00
5,700.00

1,050.00
3,000.00
1,200.00
5,250.00

1.00
1.00

6,500.00
13,800.00
14,800.00

6,500.00
41,400.00
29,600.00
77,500.00

5,752.21
36,637.17
26,194.69
68,584.07

356,629.75

315,807.30

445,500.00
62,700.00
155,925.00
21,164.00
4,752.00
14,256.00
1,221.00
715.00
13,750.00
396.00
1,250.00
721,629.00

394,247.79
55,486.73
137,986.73
18,729.20
4,205.31
12,615.93
1,080.53
632.74
12,168.14
350.44
1,106.19
638,609.73

bags
cu.m.
cu.m.
length
bdft
bdft
length
kgs.
bag
pcs
cu.m.

250.00
600.00
750.00
370.00
20.00
20.00
370.00
65.00
2,500.00
60.00
20.00

25.00
60.00
75.00
37.00
2.00
2.00
37.00
6.50
250.00
6.00
30.00

275.00
660.00
825.00
407.00
22.00
22.00
407.00
71.50
2,750.00
66.00
50.00

Day/s

5.00

300.00

6,000.00

Day/s
Day/s
Day/s
Day/s
Day/s

1.00
2.00
10.00
1.00
1.00

350.00
300.00
275.00
300.00
300.00

8,750.00
13,800.00
63,250.00
6,900.00
6,900.00
105,600.00

6,000.00
8,750.00
13,800.00
46,000.00
6,900.00
6,900.00
88,350.00

23,000.00

20,353.98

day

1.00

1,000.00

day

1.00

500.00

11,500.00

10,176.99

34,500.00

30,530.97

Total for Item 311

861,729.00

757,490.71

49,896.00
12,870.00
2,475.00

44,155.75
11,389.38
2,190.27

45.00
Length =
Total Volume =

300.00
300.00

300.00

450.00
450.00

450.00

BRGY.
CASH

IN-KIND

TOTAL

MUN.

CASH

IN-KIND

700.00
3,600.00
1,100.00
5,400.00

1,150.44
3,883.89
747.79
5,782.12

10,000.00
33,760.00
6,500.00
50,260.00

5,782.12

55,660.00

31,456.52
31,456.52

273,429.75
273,429.75

747.79
4,762.83
3,405.31
8,915.93

40,372.45

41,252.21
7,213.27
17,938.27
2,434.80
546.69
1,640.07
140.47
82.26
1,581.86
45.56
143.81
73,019.27

1,050.00
3,000.00
1,650.00
5,700.00

6,500.00
41,400.00
29,600.00
77,500.00

356,629.75

445,500.00
62,700.00
155,925.00
21,164.00
4,752.00
14,256.00
1,221.00
715.00
13,750.00
396.00
1,250.00
721,629.00

sq.m.
m
m
sq.m.
cu.m.
cu.m.

Sub-Total
505 Grouted Riprap

23.00

1.00
2.00
2.00

Total for Item 200


311 Portland Cement Concrete Pavement
1,200.00
Length of PCCP =
300.00
Width =
4.00
Area =
300*4 = 1,200.00
Portland Cement Concrete Pavement =
300*4*0.15 = 180.00
Total Volume =
180.00
A. Materials
180.00*9 = 1,620.00
Portland Cement (40kgs), Type 1
180.00*0.5*1.05=
Fine Aggregates (Approved Source)
95.00
Gravel 2"-2-1/2" dia. (Approved Source)
180.00*1*1.05= 189.00
16mm dia. X 6m Def. Bars (Const. Joint)
((300/1)+1)/(6/.6)*1.7=
52.00
(((2"*2"*12')/12)*54= 216.00
2"x2"x8' Coco Lumber (Formworks)
(((2"*6"*12')/12)*54= 648.00
2"x6"x12' Coco Lumber (Formworks)
16mm dia. X 6.0 m Def. Bars (Formworks)
((10.8/1)+1)/(6-.3)=
3.00
(((6*3.6)/0.2)/5)*28)/58
Assorted CWN (2" & 3")
10.00
Hard Asphalt (Joint Filler)
5.00
Hack Saw Blade
6.00
Water (for mixing)
25.00
Sub-Total
B. Labor
During Installation of Forms: (150 sq.m./day)
Carpenter
4.00
During Concrete Pouring: Gang of 15 Workers (1.40 man-hour/sq.m)
Construction Foreman
25.00
Mason
((1.4*1200)/8)/15
23.00
Laborers
23.00
Concrete Mixer Operator
23.00
Concrete Mixer Vibrator
23.00
Sub-Total
C.Equipment
7.85 cu.m/day
1- Concrete Mixer
180/7.82 = 23.00

COMMUNITY
CONTRIBUTI
ON

KALAHI
GRANT

Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer

LGU

Total

10,000.00

10,000.00

6,000.00

17,250.00

17,250.00

3,969.03

34,500.00

76,988.29

861,729.00

2,646.02

23,000.00

1,323.01
17,250.00

8,750.00
13,800.00
63,250.00
6,900.00
6,900.00
105,600.00

10,000.00

11,500.00

cu.m.

300.00

45.00

cu.m.

Portland Cement (40kgs), Type 1


Fine Aggregates (Approved Source)
Gravel 2"-2-1/2" dia. (Approved Source)

189.00
18.00
3.00

bags
cu.m.
cu.m.

240.00
650.00
750.00

24.00
65.00
75.00

264.00
715.00
825.00

Cobble Class A stone (20cm - 30cm dia.)

52.00

cu.m.

750.00

75.00

825.00

Sub-Total

42,900.00

37,964.60

108,141.00

95,700.00

5,740.25
1,480.62
284.73

49,896.00
12,870.00
2,475.00

4,935.40
-

12,441.00

42,900.00
-

108,141.00

2,800.00
7,200.00
2,400.00
22,000.00
34,400.00

1.5 man lm per day


Construction Foreman
Mason
Concrete Mixer Operator
Laborers

8.00
8.00
8.00
8.00

Day/s
Day/s
Day/s
Day/s

1.00
3.00
1.00
10.00

350.00
300.00
300.00
275.00

2,800.00
7,200.00
2,400.00
22,000.00
34,400.00

2,800.00
7,200.00
2,400.00
16,000.00
28,400.00

8.00

day

1.00

1,000.00

Sub-Total

8,000.00
8,000.00

7,079.65
7,079.65

Total for Item 505

150,541.00

131,179.65

8,500.00
8,500.00

7,522.12
7,522.12

350.00
300.00

350.00
300.00

Sub-Total
C.Equipment
1- Concrete Mixer

SPL - 1 Billboard

1.00

lot

1.00

lot

6,000.00
6,000.00

6,000.00

920.35
920.35

8,000.00
8,000.00

13,361.35

150,541.00

977.88
977.88

8,500.00
8,500.00

Quantity: 1 unit
A. Materials
Project Billboard

8,500.00

Sub-Total
B. Labor
Contstruction Foreman
Carpenter

1.00
1.00

Day/s
Day/s

1.00
1.00

350.00
300.00

350.00
300.00

COST SHARING
ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION
Laborer

QUANTI
UNIT
TY
1.00

Day/s

Rate per
No. of
Day / Unit
Crew/
Cost
1.00

Add
Frieght &
Handling
Cost

Total Unit
Cost

LGU

Total

275.00

COMMUNITY
CONTRIBUTI
ON
200.00
75.00
850.00
75.00

KALAHI
GRANT

BRGY.

TOTAL

MUN.

Sub-Total

275.00
925.00

Total for Item SPL -1

9,425.00

8,372.12

75.00

275.00
925.00

977.88

9,425.00

Total Direct Cost

1,433,984.75

1,262,427.65

24,075.00

10,000.00

137,482.10

1,433,984.75

1,111,699.75

983,805.09

170,260.00

150,672.57

10,000.00
-

117,894.66

1,111,699.75

19,587.43

170,260.00

63,750.00

63,750.00

63,750.00

88,275.00

1,433,984.75

21,000.00
21,000.00

Direct Cost Summary


Materials
Equipment
Labor

1) Skilled
2)Unskilled
TOTAL DIRECT COST

88,275.00

64,200.00

24,075.00

1,433,984.75

1,262,427.65

24,075.00

INDIRECT COST:
OVERHEAD COST
Foreman/Leadman
Sub-total
HANDTOOLS AND PROTECTIVE EQUIPMENT
Hard Hat
Hand Glooves
Medicine Kit
Sub-total
PRE-ENGINEERING
Preparation of Plans (TAF)
Reproduction of Plans
Sub-total
PROJECT SUPERVISION
Municipal Engineer
BSPMC volunteers
Sub-total
ENVIRONMENTAL IMPACT

10,000.00

137,482.10

60.00

days

350.00

21,000.00
21,000.00

21,000.00
21,000.00
1,086.96
217.39
1,643.48
2,947.83

10.00
10.00
1.00

pcs.
pcs.
set

125.00
25.00
1,890.00

1,250.00
250.00
1,890.00
3,390.00

20.00

shts

100.00

2,000.00
2,000.00

4,000.00
8,500.00
12,500.00

163.04
32.61
246.52
442.17

5.00
17.00

days
days

800.00
250.00

2.00

1,000.00
1,000.00

8,500.00
8,500.00

5.00

pcs.

420.00

2,100.00

1,826.09

273.91

Barricades

5.00

pcs.

300.00

1,500.00

1,304.35

195.65

3,600.00
40,000.00
7,500.00
10,000.00
5,253.75
100,378.93
143,398.48
349,021.16
1,783,005.91
71,694.09
1,854,700.00

3,130.43
34,782.61
6,521.74
8,695.65

124,694.33
201,772.59
1,464,200.24
58,874.76
1,523,075.00

1,854,700.00

1,523,075.00

Prepared by:

ENGR. JERRY C. BALIOLA


Service Provider

1.00

posting

7,500.00

7,500.00

82.12%

Checked & Reviewed by:

RODSON R. ESCORA
Deputy Area Coordinator

Recommending Approval:

CARMEN A. GAUDIANO
Municipal Engineer

2,000.00
2,000.00

1,000.00
1,000.00
4,000.00

Warning Signs
Sub-total
ADMINISTRATIVE COST
BIDDING PUBLICATION
MATERIAL TESTING
TREASURER'S BOND
VAT (7% OF Total Direct Cost)
Contractor Profit (10%)
TOTAL INDIRECT COST
TOTAL (A+B)
Add: Contingency
TOTAL ESTIMATED PROJECT COST (TEPC)
Add: O and M (Other Amenities)
TOTAL CONSTRUCTION COST

1,250.00
250.00
1,890.00
3,390.00

24,075.00

10,000.00

1,000.00
1,000.00

24,075.00

10,000.00

1,000.00

469.57
5,217.39
978.26
1,304.35
5,253.75
100,378.93
18,704.15
141,248.57
278,730.67
12,819.33
291,550.00

24,075.00

10,000.00

1,000.00
17.88%

291,550.00
304,615.00

Approved by:

JOY ALABAN
BSPMC Chairperson

4,000.00
8,500.00
12,500.00

4,000.00

2,100.00
1,500.00
-

5,000.00
5,000.00
5,000.00
5,000.00

3,600.00
40,000.00
7,500.00
10,000.00
5,253.75
100,378.93
143,398.48
349,021.16
1,783,005.91
71,694.09
1,854,700.00
1,854,700.00

Noted by:

GEORGE S. ISULAT
RCIS

Department of Social Walfare and Development


KALAHI-CIDSS : MCC PROJECT
Dauin, Negros Oriental
Sub-Project :
CONCRETING OF BARANGAY ROAD
Location: ANHAWAN, DAUIN NEGROS ORIENTAL

Description of Work
Item No.
Location
Note
STATION
0+000
0+020
0+040
0+060
0+080
0+100
0+120
0+140
0+160
0+180
0+200
0+340
0+360
0+380
0+400
0+420
0+440
Total Area :
Ave. Area :

BARANGAY SUB-PROJECT
MANAGEMENT COMMITTEE

QUANTITY CALCULATION

Barangay Anhawan, Dauin


Negros Oriental

: SURPLUS COMMON EXCAVATION AND EMBANKMENT


: 102 & 104
: STA. 0-000.00 - STA. 0+200.00 & STA. 0+340.00 - STA. 0+440.00

: Computed Areas are taken from CAD File ( Poly Line Method)
AREA
DISTANCE
VOLUME
ITEM 102
ITEM 104
(m)
ITEM 102
0.020
0.460
20.00
0.660
0.550
20.00
6.800
0.000
3.840
20.00
6.600
11.120
0.000
20.00
111.200
0.150
0.630
20.00
112.700
0.140
0.740
20.00
2.900
0.210
0.350
20.00
3.500
0.150
0.750
20.00
3.600
0.330
0.180
20.00
4.800
1.630
0.160
20.00
19.600
1.400
0.510
20.00
30.300
1.990
0.060
20.00
1.470
0.200
20.00
34.600
1.410
0.200
20.00
28.800
0.050
2.370
20.00
14.600
1.410
0.200
20.00
14.600
0.190
0.270
20.00
16.000
22.330
1.314

11.470
0.675
Add: 15% Shrinkage Factor =
Total Loose Volume =

REMARKS /
LOCATION

ITEM 104

10.100
43.900
38.400
6.300
13.700
10.900
11.000
9.300
3.400
6.700

2.600
4.000
25.700
25.700
4.700

410.600

216.400

410.600

32.460
248.860

Total Volume of Item 104 to be procured:


* Assume 100% of the Excavated Materials will be utilized for it was found out
during site validation that some portion of existing road bed as good quality of
embankment materials/ common borrow)
Total Compact Volume to be hauled:
Total Loose Volume to be hauled:

410.60

194.200 cu.m
223.33 cu.m

Submitted by:

JERRY C. BALIOLA

Service Provider

BARANGAY SUB-PROJECT WORK SCHEDULE & PHYSICAL PROGRESS REPORT


Project Title

: CONCRETING OF BARANGAY ROAD

Sub-Project duration

: 90

Physical Target

:
:
:
:
:

Region
Province
Municipality
Barangay

Calendar Days

300 L.M.
VII CENTRAL VISAYAS
NEGROS ORIENTAL
DAUIN
MAGSAYSAY

Total Sub-Project Cost

: P

Direct Cost
Indirect Cost
Date Started
Target Completion
Mode of Implementation

: P
1,433,984.75
: P
420,715.25
:
:
: By Contract

1,854,700.00

LABOR

NO.

WEIGHT
DESCRIPTION

Surplus Common Excavation

II

Emabankment

III

IV

VI

QTY

233.33 cu.m.

Err:509

Aggregate Sub-Base Course


Portland Cement Conrete
Pavement (PCCP)

UNIT

cu.m.

393.00 cu.m.

1,200.00 sq.m.

Grouted Riprap

45.00 cu.m.

Project Steel Billboard

1.00

lot

T O T A L

AMOUNT

PHYSICAL

(%)

55,660.00

3.88%

Err:509

Err:509

356,629.75

24.87%

861,729.00

60.09%

150,541.00

10.50%

9,425.00

1,433,984.75

0.66%

100.00%

PHYSICAL
% PROGRESS (Actual)
PROGRESS (Planned)
FINANCIAL
PROGRESS (Actual)
Prepared by:

TOTAL
MONTH 2

WEEK 3

WEEK 4

WEEK 5

WEEK 6

MONTH 3
WEEK 7

WEEK 8

WEEK 9

WEEK 10

MONTH 4
WEEK 11

WEEK 12

WEEK 13

# # # # # # # # # # # # # # # # # # # # # # # # # # # #

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

PLANNED
ACTUAL
PLANNED

##########################################

ACTUAL
PLANNED

###################################################################################################################################################

ACTUAL
PLANNED

####################################################################################

ACTUAL
PLANNED

# #

ACTUAL
PLANNED

# # # # # # # # # # # # # # # # # # # # ###################################################################################################################################################################################################################

ACTUAL
1

PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
Concurred by:

JOCELYN ALAS-AS
PIT Chairperson

WEEK 2

275.00

ACTUAL

II. To be filled up by Deputy Area Coordinator


% PROGRESS (Planned)

WEEK 1

90

UNSKILLED

MONTH 1

TARGET
PLANNED

90

SKILLED

I. To be filled up by Deputy Area Coordinator

ITEM

Average
Rate/Day
300.00

No. of Days

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

43

44

45

46

47

48

49

50

51

52

53

54

55

56

65

66

67

68

69

70

71

72

73

74

75

76

77

85

86

87

88

89

90

91

99

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

0.97%

3.00%

Err:509

5.00%

15.00%

17.00%

18.00%

13.81%

12.00%

5.00%

3.00%

2.00%

1.63%

2.60%

5.60%

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

23,340.00

13,915.00

43,019.54

Err:509

23,340.00

37,255.00

80,274.54

Err:509

71,699.24
Err:509

215,097.71

243,777.41

258,117.26

198,033.29

172,078.17

Err:509

Err:509

Err:509

Err:509

Err:509

Checked by & Reviewed by:

SELVINO BULISID
MIT Team Leader

64

1.63%

GERUNDIO C. BAUTISTA JR.


Deputy Area Coordinator

Approved by:

CARMEN A. GAUDIANO
Municipal Engineer

71,699.24
Err:509

43,019.54
Err:509

119

28,679.70
1,433,984.75

Noted by:

GEORGE ALAS-AS
BSPMC

118

GEORGE S. ISULAT
RCIS

ENVIRONMENTAL MANAGEMENT PLAN


Sub-Project Title
:
Sub-Project Description :
Location
Total Approved Cost
Cost Sharing

Concreting of Barangay Road


Surplus Common Excavation, Embankment, Aggregate Sub-Base
Course, PCCP, Grouted Riprap & Project Steel Billboard
Barangay Magsaysay, Dauin, Negros Oriental
PHP 1,854,700.00

:
:
:

Local Counterpart :
KALAHI Grant
Community
Barangay LGU
Municipal LGU
TOTAL
SPI Stage / Activities
Conducted
ITEM 102 Surplus Common
Excavation

PHP
PHP
PHP
PHP
PHP

Negative Impact

1,523,075.00
24,075.00
1,000.00
296,550.00
1,844,700.00
Mitigating Measures

a.

Deep Excavation/Ground
Leveling

a-1.

Provide baricades and warning


signs to make aware of the
community of the on-going
activity. And Strickly follow the
desired elevation on plan.

b.

Presence of Heavy
Equipment in the project
Site

b-1.

Inform the community of the


presence of Heavy Equipment in
the area.

a.

Backfilling of Excavated
Materials

a-2.

Provide workers Dust Mask


during execution of work to
prevent workers from inhailing
dust particles.

b.

Presence of Heavy
Equipment in the project
Site

b-1.

Inform the community of the


presence of Heavy Equipment in
the area.

ITEM 200 Aggregate Sub-base a.


Course

Presence of Heavy
Equipment in the project
Site

a-1.

Inform the community of the


presence of Heavy Equipment in
the area.

ITEM 311 Portland Cement


a.
Concrete Pavement

Increase in noise level

a-1.

ITEM 104 Embankment

ITEM 505 Grouted Riprap


SPCL 1 Project Steel
Billboard

Inform the community about the


incoming activities and instruct
the workers to minimize the
noise during construction.

none

none

none

none
Reviewed by:

Prepared By:

GEORGE ALAS-AS

RICKY PANOY

BSPMC Chair

Community Facilitator

CARMEN A. GAUDIANO

RODSON R. ESCORA

Municipal Engineer

Deputy Area Coordinator

Concurred by:

OFFICE OF THE BRGY SUB-PROJECT MANAGEMENT COMMITTEE (BSPMC)


Barangay of Magsaysay
Municipality of Dauin
Province of Negros Oriental, Region VII
SUB-PROJECT PROGRAM-OF-WORK
Project Title

: Concreting of Barangay Road

Category
Physical Target

: Public Goods
: 0.30 KM

Total Sub-Project Cost


Mode of Implementation

PHP 2,027,337.65
: By Community Force Account (CFA)

Project Description:

Sub-Project Duration

: 90 Calendar Days

Surplus Common Excavation, Embankment, Aggregate Sub-Base Course,


PCCP, Grouted Riprap and Installation of Project Steel Billboard

Equipment/Tools Needed

Road Grader,Back Hoe, Road Roller, Concrete


Mixer and Vibrator

Technical Personnel

: Engineer, Foreman, Carpenter/Mason,


Instrument Man, Survey Aide and Riprapper

Sub-Project Location:
Sub-Project Site Location is 8KM away from Town Proper

No. of Laborers

Item
Scope of Work
No.

%(Wt)

: 90 person days
Quantity

Unit

Unit Cost (P)

Total (P)

102

Surplus Common Excavation

8.54%

410.60

cu.m.

367.27

150,800.00

104

Embankment

-9.57%

-194.20

cu.m.

869.88

(168,931.50)

200

Aggregate Sub-Base Course

22.42%

393.00

cu.m.

1,007.60

395,987.00

311

Portland Cement Conrete Pavement (PCCP)

51.49%

1200.00

sq.m.

757.85

909,418.00

505

Grouted Riprap (Line Ditched Canal)

26.52%

216.00

cu.m.

2,168.26

468,345.00

0.59%

1.00

lot

10,425.00

SPL 1 Project Steel Billboard


Total Direct Cost

100.00%

990,820.35

10,425.00
1,766,043.50

SOURCE OF FUND
Breakdown of Estimated Project Cost

KALAHI Grant

Community

Barangay LGU

In-Kind
A.

Cash

Municipal LGU

In-Kind

Cash

Total

In-Kind

Direct Cost
Materials
Equipment

1,096,691.50

236,927.00

1,333,618.50

190,075.00

44,425.00

234,500.00

Labor
Skilled

82,150.00

82,150.00

Unskilled

84,050.00

31,725.00

115,775.00

1,452,966.50

31,725.00

281,352.00

1,766,043.50

Sub-Total A
B.

Indirect Cost
Overhead Cost

25,200.00

6,300.00

31,500.00

Handtools and Prot. Equip. (PPE)

13,432.00

3,358.00

16,790.00

Pre-engineering

Project Supervision

Environmental Metigating Cost


Administrative Cost
Bidding Publication
Materials Testing
BSPMC Filling Cabinet

2,000.00

4,000.00

12,500.00

720.00

3,600.00

10,100.00

50,500.00

6,000.00

1,500.00

7,500.00

12,000.00

3,000.00

15,000.00

6,000.00

1,500.00

7,500.00

5,253.75

1,000.00

40,231.75

5,000.00

152,143.75

1,000.00

321,583.75

5,000.00

1,918,187.25

Sub-Total ( B )

105,912.00

TOTAL ( A+ B )

1,558,878.50

31,725.00

89,618.50

1,648,497.00

19,531.90

31,725.00

1,000.00

MCC Grant
Cost Sharing to TEPC

8,500.00

1,000.00

2,880.00

Total Estimated Project Cost

40,400.00

Treasurer's Bond

ADD: Contingency

1,000.00

341,115.65

5,253.75

5,000.00

1,648,497.00

81.31%

LCC Cash

341,115.65

16.83%

LCC Inkind

37,725.00

1.86%

109,150.40

2,027,337.65

100.00%

Add: O and M (Other Amenities)


GRAND TOTAL

1,648,497.00

31,725.00

Prepared by :

1,000.00

341,115.65

5,000.00

2,027,337.65

Approved by :

ELSA A. TRUNO

GEORGE ALAS-AS

MEO Staff

BSPMC Chairperson

Checked by:

Concurred by :

ENGR. RODSON R. ESCORA

HON. LIBRADO TUALA

Deputy Area Coordinator

Sanggunian Barangay Member

Recommending Approval:

ENGR. CARMEN A. GAUDIANO


Municipal Engineer - MCT DAC

HON. NEIL B. CREDO


Noted by:

Municipal Mayor

ENGR. GEORGE S. ISULAT


Regional Community Infrastructure Specialist

NAME OF SUB-PROJE: Concreting of Barangay Road


: Magsaysay, Dauin, Negros Oriental
LOCATION:

BILL OF QUANTITIES

ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION

102 Surplus Common Excavation


to include Earth Canal Ditching and Reshaping see vol. computation

QUANTI
UNIT
TY

Rate per
No. of
Day / Unit
Crew/
Cost

410.60
410.60

cu.m.
cu.m.

410.60

cu.m.

4.00
7.00
4.00

Day/s
Day/s
Day/s

1.00
2.00
2.00

1.00
4.00
3.00

lot
Day/s
Day/s

1.00
1.00

194.20
194.20
223.33

cu.m.
cu.m.
cu.m.

223.33

cu.m.

2.00
3.00
2.00

Day/s
Day/s
Day/s

1.00
2.00
2.00

1.00
1.00
2.00

lot
Day/s
Day/s

1.00
1.00

393.00

cu.m.

(1.31*300) =

393.00

cu.m.

(1.31*300*1.15) =

451.95

cu.m.

451.95

cu.m.

A. Materials
Existing Ground Profile

Add
Frieght &
Handling
Cost

Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer

* pls see equipment


* pls see equipment
* pls see equipment
Sub-Total

C. Equipment
Preparation of fnish grade of item 200
including trench canal excavation
Mobilization & Demobilization
1-Backhoe (119 cu.m / day)
1-Road Grader (175 cu.m / day)

358/119 =
358/175 =

Total for Item102


104 Embankment
Total Compacted Volume = see vol. comp.
Total Loose Volume = see vol. comp.
A. Materials
Embankment (Fill) Materials

500.00

50.00

600.00

60.00

Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer

* pls see equipment


* pls see equipment
* pls see equipment
Sub-Total

C. Equipment
Mobilization & Demobilization
1-Road Roller (250 cu.m/day)
1-Road Grader (175 cu.m / day)

472.06/250 =
472.06/175 =

Total for Item104


Aggregate Subbase Course (including 1.0m
200
width shouldering both sides)

Total Compacted Volume =


Total Loose Volume =
A. Materials
Aggregate Subbase Course (Balastro Class "A" Type)

Magsaysay BOQ

Page 9 of 63

ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION

QUANTI
UNIT
TY

Rate per
No. of
Day / Unit
Crew/
Cost

Sub-Total
B. Labor
Construction Foreman
Driver / Operator
Laborer

*pls see equipment


*pls see equipment
*pls see equipment

3.00
5.00
3.00

Day/s
Day/s
Day/s

1.00
2.00
2.00

1.00
2.00
3.00

lot
Day/s
Day/s

1.00
1.00

Add
Frieght &
Handling
Cost

Sub-Total
C. Equipment
Mobilization & Demobilization
1-Road Roller (250 cu.m/day)
1-Road Grader (175 cu.m / day)

451.95/250 =
451.95/175 =

Total for Item 200


311 Portland Cement Concrete Pavement
1,200.00
Length of PCCP =
300.00
Width =
4.00
Area =
300*4 = 1,200.00
300*4*0.15 = 180.00
Portland Cement Concrete Pavement =
Total Volume =
180.00
A. Materials
180.00*9 = 1,620.00
Portland Cement (40kgs), Type 1
180.00*0.7 = 126.00
Fine Aggregates (Approved Source)
180.00*1 = 180.00
Gravel 3/4" dia. (Approved Source)
((300/1)+1)/(6/.6)*1.5=
16mm dia. X 6m Def. Bars (Const. Joint)
46.00
(((2"*2"*8')/12)*54= 144.00
2"x2"x8' Coco Lumber (Formworks)
(((2"*6"*12')/12)*54= 648.00
2"x6"x12' Coco Lumber (Formworks)
((10.8/1)+1)/(6-.3)=
16mm dia. X 6.0 m Def. Bars (Formworks)
2.00
(((6*3.6)/0.2)/5)*28)/58
# 4 CWN
10.00
Hard Asphalt (Joint Filler)
7.00
Water (for mixing)
25.00
Sub-Total
B. Labor
During Installation of Forms: (150 sq.m./day)
Carpenter
4.00
During Concrete Pouring: Gang of 15 Workers (1.40 man-hour/sq.m)
Construction Foreman
14.00
Mason
((1.4*1200)/8)/15
14.00
Laborers
14.00
Concrete Mixer Operator
14.00
Concrete Mixer Vibrator
14.00
Sub-Total
C.Equipment
122 bags/day
1- Concrete Mixer
(180*9.5)/122
15.00
1- Concrete Vibrator

(180*9.5)/122

15.00

sq.m.
m
m
sq.m.
cu.m.
cu.m.
bags
cu.m.
cu.m.
length
bdft
bdft
length
kgs.
bag
cu.m.

261.50
750.00
850.00
370.00
20.00
20.00
370.00
65.00
2,500.00
20.00

Day/s

2.00

Day/s
Day/s
Day/s
Day/s
Day/s

1.00
4.00
10.00
1.00
1.00

day

1.00

day

1.00

26.15
75.00
85.00
37.00
2.00
2.00
37.00
6.50
250.00
30.00

Sub-Total
Total for Item 311
505 Grouted Riprap
Length =
Cross-sectional Area of canal =

0.3*1.2 =

Grouted Riprap trinch canal =

(0.36*2*300)=

Class A stone
2"x2"x8' Coco Lumber (Batterboards)
# 4 CWN

Magsaysay BOQ

cu.m.

300.00

0.36

cu.m.

(one side only)

216.00

cu.m.

(two sides)

216.00

cu.m.

(1.620*216)
(0.143*216)

350.00
62.00

bags
cu.m.

261.50
750.00

26.15
75.00

(0.48*2*216)=

208.00

cu.m.

850.00

85.00

240.00
5.00

bdft
kgs.

20.00
65.00

2.00
6.50

Total Volume =
Portland Cement (40kgs), Type 1
Fine Aggregates (Approved Source)

216.00

((2"*2"*8')/12)*15 =

Page 10 of 63

ITEM
NO.

Quantity Derivation
Computation

ITEM DESCRIPTION
Water (for mixing)

QUANTI
UNIT
TY
6.00

cu.m.

27.00
27.00
27.00

Day/s
Day/s
Day/s

1.00

lot

1.00

lot

1.00
1.00
1.00

Day/s
Day/s
Day/s

90.00

days

10.00
10.00
10.00
10.00
10.00
1.00

pcs.
pcs.
pcs
pairs
pcs
set

20.00

shts

5.00
17.00

days
days

Warning Signs

5.00

pcs.

Barricades

5.00

pcs.

Sub-total
ADMINISTRATIVE COST
BIDDING PUBLICATION

1.00

posting

Rate per
No. of
Day / Unit
Crew/
Cost
20.00

Sub-Total
1.5 man lm per day
Construction Foreman
Mason
Laborers

(600/1.5)/15=

1.00
4.00
10.00

Sub-Total
Total for Item 505
SPL - 1Billboard
Quantity: 1 unit
A. Materials
Project Billboard
Sub-Total
B. Labor
Contstruction Foreman
Carpenter
Laborer

1.00
1.00
1.00

Sub-Total
Total for Item SPL -1
Total Direct Cost
Direct Cost Summary
Materials
Equipment
Labor
1) Skilled
2)Unskilled
TOTAL DIRECT COST

INDIRECT COST:
OVERHEAD COST
Foreman/Leadman
Sub-total
HANDTOOLS AND PROTECTIVE EQUIPMENT
Hard Hat
Hand Glooves
Face Mask
Safety Boots
Shovel w/ handle
Medicine Kit
Sub-total
PRE-ENGINEERING
Preparation of Plans (TAF)
Reproduction of Plans
Sub-total
PROJECT SUPERVISION
Municipal Engineer
BSPMC volunteers
Sub-total
ENVIRONMENTAL IMPACT

Magsaysay BOQ

Page 11 of 63

2.00

7,500.00

Add
Frieght &
Handling
Cost
30.00

ITEM
NO.

ITEM DESCRIPTION

Quantity Derivation
Computation

MATERIAL TESTING
BSPMC FILLING CABINET
TREASURER'S BOND
TOTAL INDIRECT COST
TOTAL (A+B)
Add: Contingency
TOTAL ESTIMATED PROJECT COST (TEPC)
Add: O and M (Other Amenities)
TOTAL CONSTRUCTION COST

Prepared by:

1.00

Rate per
No. of
Day / Unit
Crew/
Cost

unit

Add
Frieght &
Handling
Cost

7,500.00

82.12%

Checked & Reviewed by:

ELSA A. TRUNO
MEO Staff

Magsaysay BOQ

QUANTI
UNIT
TY

RODSON R. ESCORA
Deputy Area Coordinator

Page 12 of 63

Recommending Approval:

CARMEN A. GAU
Municipal Engi

L OF QUANTITIES
COST SHARING
Total Unit
Cost

LGU

Total

KALAHI
GRANT

350.00
300.00
275.00

15,000.00
18,500.00
18,000.00

550.00

350.00
300.00
275.00

10,000.00
16,500.00
18,000.00

660.00

Magsaysay BOQ

COMMUNITY
CONTRIBUTI
ON

BRGY.
CASH

IN-KIND

1,400.00
4,200.00
2,200.00
7,800.00

1,400.00
4,200.00
1,600.00
7,200.00

15,000.00
74,000.00
54,000.00
143,000.00

12,000.00
59,200.00
43,200.00
114,400.00

150,800.00

121,600.00

(122,831.50)
(122,831.50)

(103,235.49)
(103,235.49)

(700.00)
(1,800.00)
(1,100.00)
(3,600.00)

(700.00)
(1,800.00)
(1,100.00)
(3,600.00)

10,000.00
(16,500.00)
(36,000.00)
(42,500.00)

8,500.00
(14,025.00)
(30,600.00)
(36,125.00)

(168,931.50)

(142,960.49)

298,287.00

268,458.30

600.00
600.00

600.00

TOTAL

MUN.

CASH

IN-KIND

1,400.00
4,200.00
2,200.00
7,800.00

3,000.00
14,800.00
10,800.00
28,600.00

15,000.00
74,000.00
54,000.00
143,000.00

28,600.00

150,800.00

(19,596.02)
(19,596.02)

(122,831.50)
(122,831.50)

(700.00)
(1,800.00)
(1,100.00)
(3,600.00)

1,500.00
(2,475.00)
(5,400.00)
(6,375.00)

10,000.00
(16,500.00)
(36,000.00)
(42,500.00)

(25,971.02)

(168,931.50)

29,828.70

Page 13 of 63

298,287.00

COST SHARING
Total Unit
Cost

Total
298,287.00

350.00
300.00
275.00

LGU
COMMUNITY
KALAHI
CONTRIBUTI
GRANT
ON
268,458.30
-

BRGY.
-

TOTAL

MUN.
-

29,828.70

298,287.00

1,050.00
3,000.00
1,650.00
5,700.00

5,000.00
33,000.00
54,000.00
92,000.00

395,987.00

465,993.00
103,950.00
168,300.00
18,722.00
3,168.00
14,256.00
814.00
715.00
19,250.00
1,250.00
796,418.00

1,050.00
3,000.00
1,650.00
5,700.00

1,050.00
3,000.00
1,200.00
5,250.00

5,000.00
33,000.00
54,000.00
92,000.00

4,250.00
28,050.00
45,900.00
78,200.00

395,987.00

351,908.30

465,993.00
103,950.00
168,300.00
18,722.00
3,168.00
14,256.00
814.00
715.00
19,250.00
1,250.00
796,418.00

372,698.81
83,160.00
134,640.00
14,977.60
2,534.40
11,404.80
651.20
572.00
15,400.00
1,000.00
637,038.81

300.00

2,400.00

350.00
300.00
275.00
300.00
300.00

4,900.00
16,800.00
38,500.00
4,200.00
4,200.00
71,000.00

2,400.00
4,900.00
16,800.00
28,150.00
4,200.00
4,200.00
60,650.00

1,600.00

24,000.00

19,200.00

4,800.00

24,000.00

1,200.00

18,000.00

14,400.00

3,600.00

18,000.00

5,000.00
16,500.00
18,000.00

287.65
825.00
935.00
407.00
22.00
22.00
407.00
71.50
2,750.00
50.00

450.00
450.00

450.00

750.00
4,950.00
8,100.00
13,800.00

43,628.70

93,294.19
20,790.00
33,660.00
3,744.40
633.60
2,851.20
162.80
143.00
3,850.00
250.00
159,379.19

2,400.00

10,350.00

10,350.00

42,000.00

33,600.00

909,418.00

731,288.81

287.65
825.00

100,677.50
51,150.00

85,575.88
40,920.00

15,101.63
10,230.00

100,677.50
51,150.00

935.00

194,480.00

155,584.00

38,896.00

194,480.00

22.00
71.50

5,280.00
357.50

4,224.00
286.00

1,056.00
71.50

5,280.00
357.50

Magsaysay BOQ

4,900.00
16,800.00
38,500.00
4,200.00
4,200.00
71,000.00

10,350.00

8,400.00

42,000.00

167,779.19

909,418.00

Page 14 of 63

COST SHARING
Total Unit
Cost
50.00

350.00
300.00
275.00

9,500.00

350.00
300.00
275.00

LGU

Total
300.00
352,245.00

KALAHI
GRANT

240.00
286,829.88

COMMUNITY
CONTRIBUTI
ON
-

BRGY.
-

TOTAL

MUN.
-

60.00
65,415.13

300.00
352,245.00

9,450.00
32,400.00
74,250.00
116,100.00

9,450.00
32,400.00
54,000.00
95,850.00

20,250.00
20,250.00

9,450.00
32,400.00
74,250.00
116,100.00

468,345.00

382,679.88

20,250.00

65,415.13

468,345.00

9,500.00
9,500.00

7,600.00
7,600.00

1,900.00
1,900.00

9,500.00
9,500.00

350.00
300.00
275.00
925.00

350.00
300.00
200.00
850.00

75.00
75.00

350.00
300.00
275.00
925.00

10,425.00

8,450.00

75.00

1,900.00

10,425.00

1,766,043.50

1,452,966.50

31,725.00

281,352.00

1,766,043.50

1,333,618.50

1,096,691.50

236,927.00

1,333,618.50

234,500.00

190,075.00

44,425.00

234,500.00

82,150.00

82,150.00

82,150.00

115,775.00

84,050.00

31,725.00

115,775.00

1,766,043.50

1,452,966.50

31,725.00

281,352.00

1,766,043.50

6,300.00
6,300.00

31,500.00
31,500.00

350.00

31,500.00
31,500.00

25,200.00
25,200.00

370.00
35.00
35.00
450.00
600.00
1,890.00

3,700.00
350.00
350.00
4,500.00
6,000.00
1,890.00
16,790.00

2,960.00
280.00
280.00
3,600.00
4,800.00
1,512.00
13,432.00

100.00

2,000.00
2,000.00

740.00
70.00
70.00
900.00
1,200.00
378.00
3,358.00

800.00
250.00

4,000.00
8,500.00
12,500.00

1,000.00
1,000.00

1,000.00
1,000.00
4,000.00

8,500.00
8,500.00

420.00

2,100.00

1,680.00

420.00

300.00

1,500.00

1,200.00

300.00

7,500.00

3,600.00
50,500.00
7,500.00

2,880.00
40,400.00
6,000.00

Magsaysay BOQ

3,700.00
350.00
350.00
4,500.00
6,000.00
1,890.00
16,790.00

Page 15 of 63

720.00
10,100.00
1,500.00

4,000.00

2,000.00
2,000.00
4,000.00
8,500.00
12,500.00
2,100.00
1,500.00

3,600.00
50,500.00
7,500.00

COST SHARING
Total Unit
Cost
7,500.00

Total
15,000.00
7,500.00
5,253.75
152,143.75
1,918,187.25
109,150.40
2,027,337.65
2,027,337.65

commending Approval:

CARMEN A. GAUDIANO
Municipal Engineer

Magsaysay BOQ

LGU
KALAHI
GRANT

12,000.00
6,000.00

COMMUNITY
CONTRIBUTI
ON

BRGY.

105,912.00
1,558,878.50
89,618.50
1,648,497.00

31,725.00

1,000.00
1,000.00

31,725.00

1,000.00

3,000.00
1,500.00
5,253.75
40,231.75
321,583.75
19,531.90
341,115.65

1,648,497.00

31,725.00

1,000.00

341,115.65

Approved by:

TOTAL

MUN.

5,000.00
5,000.00
5,000.00
5,000.00

15,000.00
7,500.00
5,253.75
152,143.75
1,918,187.25
109,150.40
2,027,337.65
2,027,337.65

Noted by:

GEORGE ALAS-AS
BSPMC Chairperson

Page 16 of 63

GEORGE S. ISULAT
RCIS

ENHANCED PLANNED COMMUNITY PROCUREME


Date Prepared

: Ocotber 9, 2013

Name of Proposed Sub-Project

Barangay
Municipality
Province

: Magsaysay
: Dauin
: Negros Oriental

Total Cash (Php)


Sub-project Duration
DESCRIPTION
1st Tranche (Php)
2nd Tranche (Php)
3rd Tranche (Php)
TOTAL CASH (Php)

PACKAGES

Mode of Implementation : Community Force Account (CFA)

PACKAGE ITEMS

QTY

UNIT

UNIT COST

TOTAL

PROC
METHOD

1st Tranche
KC Grant

Package 1-A

Package 1

Hardware:
0

1470

bags

287.65

16mm dia x 6.0m def. Bars

48

length

407.00

15

kg

71.50

bags

2,750.00

Sub-Total :Hardware:Package 1
Hardware:
0

500

bags

287.65

Sub-Total: Hardware: Package 1-A

422,845.50

LOCAL
19,536.00 SHOPPING
1,072.50 FOR GOODS
(LSG)

359,418.68
16,605.60
911.63

19,250.00

16,362.50

462,704.00

393,298.40

LOCAL
SHOPPING
FOR GOODS
143,825.00
(LSG)

143,825.00

Package 2

Base Aggregates
0

-223.33

cu.m

550.00

451.95

cu.m

660.00

Package 5

Package 4

Package 3-A

Package 3

Sub-Total Package 2
Aggregates
0
0

188
180

cu.m
cum

825.00
935.00

Sub-Total: Aggregates Package 3

(122,831.50)

LOCAL
SHOPPING
298,287.00 FOR GOODS
(LSG)

238,629.60

175,455.50

134,222.83

LOCAL
155,100.00 SHOPPING
168,300.00 FOR GOODS
(LSG)
323,400.00

131,835.00
143,055.00
274,890.00

Aggregates
Class A Stone

208

cum

935.00

Sub-Total: Aggregates Package 3-A

384

bd.ft

22.00

648

bd.ft

22.00

Sub-Total Package 4
Water
31

Sub-total Package 5

194,480.00

Form Lumber

194,480.00

cu.m

50.00

165,308.00
165,308.00

LOCAL
SHOPPING
FOR GOODS
14,256.00
(LSG)

12,117.60

22,704.00

19,298.40

8,448.00

LOCAL
1,550.00 SHOPPING
FOR GOODS
(LSG)
1,550.00

Equipment Rental (Heavy)


Package 6

(104,406.78)

LOCAL
SHOPPING
FOR GOODS
(LSG)

7,180.80

1,240.00
1,240.00

Package 6

lot

30,000.00

30,000.00

Backhoe
Road Grader
Road Roller

4
4
1

days
days
days

18,500.00
18,000.00
16,500.00

74,000.00 SHOPPING
FOR GOODS
72,000.00
(LSG)
16,500.00

Package 10

Package 9

Package 8

Package 7

Sub-Total Package 6

192,500.00

Equipment Rental (Light)


Concrete Mixer
15
Concrete Vibrator
15
Sub-Total Package 7
Labor
Skilled
1.00
Unskilled
1.00
Sub-Total Package 8
Project Billboard
Project Steel Billboard
1.00
Sub-Total Package 9
Total Direct Cost
Handtools & Personal Protective Equipment (PPE)
Hard Hat
10.00
Hand Glooves
10.00
Shovel w/ handle
10.00
Face Mask
10.00
Safety boots
10.00

days
days

1,600.00
1,200.00

lot
lot

82,150.00
84,050.00

unit

9,500.00

pcs.

370.00
35.00
600.00
35.00
450.00

pairs
pcs.
pcs.
pairs

1.00

Package 11

1,890.00

set

sub-total

Package 12

163,625.00
LOCAL

24,000.00 SHOPPING
18,000.00 FOR GOODS
(LSG)
42,000.00
82,150.00
84,050.00
166,200.00
9,500.00
9,500.00
1,734,318.50

62,900.00
61,200.00
14,025.00

19,200.00
14,400.00
33,600.00
13,612.84
11,153.12
24,765.96
7,600.00
7,600.00
1,217,848.59

LSG

3,700.00
350.00
6,000.00
LOCAL
350.00
SHOPPING
4,500.00 FOR GOODS

2,960.00
280.00
4,800.00
280.00
3,600.00

(LSG)

Package 13

25,500.00

LOCAL

ok

1,890.00

1,512.00

16,790.00

13,432.00

BSPMC Filing Cabinet


BSPMC Filing Cabinet

1.00

pcs.

7,500.00

sub-total
Environmental Mitigating Cost:
Warning Sign
Barricade
sub-total
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
Materials Testting
Treasurer Bond

Contingency Cost
sub-total
Total Indirect Cost
GRAND TOTAL CASH

7,500.00
7,500.00

5.00
5.00

pcs.
pcs.

420.00
300.00

LOCAL
SHOPPING
FOR GOODS
(LSG)
LOCAL

6,000.00

2,100.00 SHOPPING
1,500.00 FOR GOODS

1,680.00
1,200.00

3,600.00

2,880.00

31,500.00
8,500.00
50,500.00
7,500.00
15,000.00
5,253.75
109,150.40

(LSG)

7,491.42
CFA
8,000.00

227,404.15

15,491.42

255,294.15
1,989,612.65
SAY
1,989,612.65

Workshop Output by:

6,000.00

0.00
Checked & Reviewed by:

37,803.42

1,255,652.01
1,318,797.60
80.00%

AIDEAH SILVA

MARLE GRACE VENTULA

RODSON R. ESCORA

Procurement Team Head

PPT

Deputy Area Coordinator

ANCED PLANNED COMMUNITY PROCUREMENT PACKAGING


: Concreting

of Barangay Road

:
:

1,989,612.65
90 C.D

SOURCES OF FUNDS
TOTAL

.
PERCENTAGE WEIGHT
TO KC
GRANT

KC Grant:

LCC:

1,318,797.60

272,892.52

1,591,690.12

80.00%

164,849.70
164,849.70
1,648,497.00

34,111.57
34,111.57
341,115.65

198,961.27
198,961.27
1,989,612.65

10.00%
10.00%
100%

TO LCC
CASH

FUND SOURCE
LEGEND:

KC GRANT

1,648,497.00

80%

TOTAL LCC

378,840.65

10.00%
10.00%
100%

LCC - In-kind
LCC - Cash
TOTAL

37,725.00
341,115.65
2,027,337.65

REMARKS

TRANCHING SCHEDULE
TOTAL
1st Tranche

2nd Tranche

LCC Cash

KC Grant

3rd Tranche

LCC Cash

KC Grant

TOTAL

LCC Cash

KC Grant

LCC Cash

359,418.68

63,426.83

422,845.50

2,930.40

16,605.60

2,930.40

19,536.00

160.88

911.63

160.88

1,072.50

2,887.50

115,060.00

28,765.00

115,060.00

28,765.00

16,362.50

2,887.50

19,250.00

393,298.40

69,405.60

462,704.00

115,060.00

28,765.00

143,825.00

115,060.00

28,765.00

143,825.00

(18,424.73)

(104,406.78)

(18,424.73)

(122,831.50)

59,657.40

238,629.60

59,657.40

298,287.00

134,222.83

41,232.68

175,455.50

131,835.00
143,055.00

23,265.00
25,245.00

155,100.00
168,300.00

274,890.00

48,510.00

323,400.00

41,232.68

23,265.00
25,245.00
48,510.00

29,172.00
29,172.00

165,308.00

29,172.00

194,480.00

165,308.00

29,172.00

194,480.00

1,267.20

7,180.80

1,267.20

8,448.00

2,138.40

12,117.60

2,138.40

14,256.00

19,298.40
-

3,405.60
-

22,704.00
-

1,240.00

310.00

1,550.00

1,240.00

310.00

1,550.00

3,405.60

310.00
310.00

MONTHS
1

63,426.83

69,405.60

PROPOSED
IMPLEMENTATION
SCHEDULE

4,500.00

25,500.00

4,500.00

30,000.00

11,100.00
10,800.00
2,475.00

62,900.00
61,200.00
14,025.00

11,100.00
10,800.00
2,475.00

74,000.00
72,000.00
16,500.00

163,625.00

28,875.00

192,500.00

28,875.00

4,800.00
3,600.00
8,400.00

19,200.00
14,400.00
33,600.00
75,700.00
74,026.98
149,726.98
7,600.00
7,600.00
1,292,561.61

4,800.00
3,600.00
8,400.00
10,500.00
11,823.02
22,323.02
1,900.00
1,900.00
253,126.90

24,000.00
18,000.00
42,000.00
86,200.00
85,850.00
172,050.00
9,500.00
9,500.00
1,740,168.50

740.00
70.00
1,200.00
70.00
900.00

2,960.00
280.00
4,800.00
280.00
3,600.00

740.00
70.00
1,200.00
70.00
900.00

3,700.00
350.00
6,000.00
350.00
4,500.00

378.00

1,512.00

378.00

1,890.00

13,432.00

3,358.00

16,790.00

6,000.00

1,500.00

7,500.00

6,000.00

1,500.00

7,500.00

1,680.00
1,200.00

420.00
300.00

2,100.00
1,500.00

2,880.00

720.00

3,600.00

12,151.42
1,500.00
13,008.58
1,500.00
3,000.00
5,253.75
15,000.00

31,500.00
8,500.00
50,500.00
7,500.00
15,000.00
5,253.75
109,150.40

4,000.00
2,163.02
6,163.02

40,000.00
39,340.00
79,340.00

4,000.00
3,835.00
7,835.00

22,087.16
23,533.86
45,621.02

2,500.00
5,825.00
8,325.00

1,900.00
1,900.00
237,373.90

194,400.00

36,600.00

45,621.02

8,325.00

3,358.00

1,500.00
1,500.00
420.00
300.00
720.00

5,860.00

3,442.50

8,000.00
3,000.00
5,253.75

13,488.58
7,000.00
30,000.00
6,000.00
4,000.00

8,708.92
1,500.00
5,008.58
1,500.00

94,150.40

15,000.00

19,348.58
7,000.00
37,491.42
6,000.00
12,000.00
94,150.40

16,253.75

5,860.00

3,442.50

154,638.98

31,717.50

175,990.40

51,413.75

227,404.15

21,831.75

5,860.00

3,442.50

154,638.98

31,717.50

198,302.40

56,991.75

255,294.15

259,205.65

200,260.00

40,042.50

200,260.00

40,042.50

1,490,864.01

310,118.65

1,995,462.65

272,892.52

164,849.70

34,111.57

164,849.70

34,111.57

1,490,864.01

310,118.65

1,995,462.65

63,145.60

10.00%

(35,410.30)

10.00%

(35,410.30)

Recommending Approval:

Submitted by:

Noted by:

CARMEN A. GAUDIANO

VERONICA ALCORIZA

GEOGRE S. ISULAT

Municipal Engineer

BSMPC

Regional Community Infra. Specialist

AMOUNT
(PESO)
1,648,497.00
378,840.65
37,725.00
341,115.65
2,027,337.65
PROPOSED
IMPLEMENTATION
SCHEDULE

MONTHS
2

4
-

(4,050.00)
(1,800.00)
(5,850.00)
(5,850.00)
-

(5,850.00)

unity Infra. Specialist

ACTUAL COMMUNITY PROCUREMENT PACKAGIN


Date Prepared

: Ocotber 9, 2013

Name of Proposed Sub-Project

Barangay
Municipality
Province

: Magsaysay
: Dauin
: Negros Oriental

Total Cash (Php)


Sub-project Duration

:
:
SOURCES OF FUNDS

DESCRIPTION

PACKAGES

Mode of Implementation : Community Force Account (CFA)

PACKAGE ITEMS

QTY

UNIT COST

TOTAL

KC Grant:

LCC:

1st Tranche (Php)

1,318,797.60

272,892.52

2nd Tranche (Php)


3rd Tranche (Php)
TOTAL CASH (Php)

164,849.70
164,849.70
1,648,497.00

34,111.57
34,111.57
341,115.65

PROC
METHOD

TRAN
1st Tranche
KC Grant

2nd Tranche

LCC Cash

KC Grant

Hardware:

Package 1 - A

Package 1

Portland Cement (40kgs) Type 1

1470

bags

245.00

360,150.00

306,127.50

54,022.50

16mm dia x 6.0m def. Bars

48

length

340.00

16,320.00

13,872.00

2,448.00

# 4 CWN

15

kg

Hard Asphalt (Joint Filler)

bags

46.50
1,950.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Hardware:
Portland Cement (40kgs) Type 1
500

bags

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)

LOCAL
697.50 SHOPPING
13,650.00 FOR GOODS
(LSG)

592.88

104.63

11,602.50

2,047.50

390,817.50

332,194.88

58,622.63

71,886.50
462,704.00

61,103.52

10,782.98

393,298.40

69,405.60
-

LOCAL
SHOPPING
- FOR GOODS
(LSG)
143,825.00

115,060.00

143,825.00

115,060.00

Package 3

Package 2

Base Aggregates
Embankment (Fill) Materials

363.15

cu.m

550.00

199,732.50

Aggregate Subbase Course (Balastro


Class "A" Type)

451.95

cu.m

550.00

248,572.50

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Aggregates
Fine Aggregates (Approved Source)
188
Gravel 3/4" dia. (Approve Source)
180

cu.m
cum

640.00
790.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)

LOCAL
SHOPPING
FOR GOODS
(LSG)
448,305.00

169,772.63

29,959.88

198,858.00

49,714.50

368,630.63

79,674.38

272,849.50
175,455.50

234,407.80
134,222.83

38,441.70
41,232.68

120,320.00
LOCAL
142,200.00 SHOPPING
262,520.00 FOR GOODS
(LSG)
60,880.00
323,400.00

102,272.00
120,870.00

18,048.00
21,330.00

223,142.00

39,378.00

51,748.00
274,890.00

9,132.00
48,510.00

121,992.00

21,528.00

121,992.00

21,528.00

43,316.00
165,308.00

7,644.00
29,172.00

Package 3-A

Aggregates
Class A Stone

208
Sub-Total (Actual)

Savings amount determined after procurement


Sub Total for Package (Plan)

cum

690.00

LOCAL
SHOPPING
143,520.00 FOR GOODS
(LSG)
50,960.00
143,520.00

194,480.00

Package 4

Form Lumber
2"x2"x8' Coco Lumber (Formworks)

384

bd.ft

21.00

2"x6"x12' Coco Lumber (Formworks)

648

bd.ft

21.00

Sub-Total (Actual)

Package 5

Savings amount determined after procurement


Sub Total for Package (Plan)
Water
Water (for mixing)

8,064.00

6,854.40

1,209.60

13,608.00

11,566.80

2,041.20

18,421.20

3,250.80

877.20
19,298.40

154.80
3,405.60

LOCAL
SHOPPING
FOR GOODS
21,672.00
(LSG)

1,032.00
22,704.00

31

cu.m

LOCAL
SHOPPING
- FOR GOODS
(LSG)
1,550.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)

1,550.00

1,240.00
1,240.00

310.00
310.00

Package 6

Equipment Rental (Heavy)


Mobilization & Demobilization

lot

45,000.00

45,000.00

38,250.00

6,750.00

Backhoe
Road Grader
Road Roller

4
4
1

days
days
days

20,000.00
15,000.00
15,000.00

80,000.00
LOCAL
60,000.00 SHOPPING
15,000.00 FOR GOODS

68,000.00
51,000.00
12,750.00

12,000.00
9,000.00
2,250.00

170,000.00

30,000.00

7,500.00
192,500.00

6,375.00
163,625.00

1,125.00
28,875.00

10,500.00
7,800.00

8,400.00
6,240.00

2,100.00
1,560.00

14,640.00

3,660.00

18,960.00
33,600.00

4,740.00
8,400.00

Sub-Total (Actual)

200,000.00

Savings amount determined after procurement


Sub Total for Package (Plan)

(LSG)

Package 10

Package 9

Package 8

Package 7

Equipment Rental (Light)


Concrete Mixer
Concrete Vibrator

15
15

days
days

700.00
520.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Labor
Skilled
1.00
Unskilled
1.00

23,700.00
42,000.00

lot
lot

82,150.00
84,050.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Project Billboard
Project Steel Billboard
1.00

unit

8,450.00

Medicine kit box to include Betadine


100ml, Agua Oxinada 100ml, cotton
5grams, bandage 5pcs, & 1st aide tape
1 roll
Sub-Total (Actual)
Savings amount determined after procurement

1.00

pcs.
pairs
pcs.
pcs.
pairs

set

82,150.00
LOCAL
84,050.00 SHOPPING
166,200.00 FOR GOODS
(LSG)
0.00
166,200.00
8,450.00

13,612.84
11,153.12

4,000.00
2,163.02

40,000.00
39,340.00

24,765.96

6,163.02

79,340.00

0.00
24,765.96

0.00
6,163.02

0.00
79,340.00

6,760.00

1,690.00

6,760.00

1,690.00

9,500.00
1,659,784.50

840.00
7,600.00
1,280,546.66

210.00
1,900.00
243,966.82

85.00
35.00
225.00
8.50
280.00

850.00
350.00
2,250.00
85.00
2,800.00

680.00
280.00
1,800.00
68.00
2,240.00

170.00
70.00
450.00
17.00
560.00

1,750.00

1,750.00

1,400.00

350.00

8,085.00

6,468.00

1,617.00

8,705.00

6,964.00

1,741.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Total Direct Cost
Handtools & Personal Protective Equipment (PPE)
Hard Hat
10.00
Hand Glooves
10.00
Shovel w/ handle
10.00
Face Mask
10.00
Safety boots
10.00

LOCAL
SHOPPING
18,300.00 FOR GOODS
(LSG)

LOCAL
SHOPPING
8,450.00 FOR GOODS
(LSG)
1,050.00

LOCAL
SHOPPING
FOR GOODS
(LSG)

79,340.00

Package 13

Package 12

Package 11

Sub Total for Package (Plan)


BSPMC Filing Cabinet
BSPMC Filing Cabinet

1.00

pcs.

6,400.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Environmental Mitigating Cost:
Warning Sign
5.00
Barricade
5.00

16,790.00

13,432.00

6,400.00

5,120.00

1,280.00

5,120.00

1,280.00

880.00
6,000.00

220.00
1,500.00

1,120.00
1,120.00

280.00
280.00

2,240.00

560.00

640.00
2,880.00

160.00
720.00

LOCAL
SHOPPING
6,400.00 FOR GOODS
(LSG)
1,100.00

7,500.00
pcs.
pcs.

280.00
280.00

Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication

1,400.00
1,400.00

LOCAL
SHOPPING
2,800.00 FOR GOODS
(LSG)

800.00
3,600.00

31,500.00
8,500.00
50,500.00
7,500.00

3,358.00

5,860.00
7,491.42

8,000.00

8,000.00

3,000.00
5,253.75

118,253.75

15,491.42

16,253.75

5,860.00

109,150.40
227,404.15
135,538.75
194,289.40

0.00
15,491.42
29,319.42
(54,214.07)

0.00
16,253.75
19,710.75
(4,471.93)

0.00
5,860.00
5,860.00
115,060.00

GRAND TOTAL CASH (Actual)

1,795,323.25

1,309,866.08

263,677.57

85,200.00

GRAND TOTAL CASH (Plan)

2,403,025.00

1,602,080.00

320,340.00

200,260.00

97.18%

292,213.92

12.15%

Materials Testting

15,000.00
5,253.75

Treasurer Bond

CFA

Contingency Cost
Sub-Total (Actual)
Savings amount determined after procurement
Sub Total for Package (Plan)
Total Indirect Cost
TOTAL SAVINGS DETERMINED AFTER PROCUREMENT

SAY
%

1,795,323.25
0.00
Checked & Reviewed by:

Workshop Output by:

Recommending Approval:

FELIX ABELLANO

TEODOLO T. BULISID

RODSON R. ESCORA

Procurement Team Head

PPT

Deputy Area Coordinator

CARMEN A

Municipa

NITY PROCUREMENT PACKAGING

Concreting of Barangay Road


1,989,612.65
90 C.D
TOTAL

.
PERCENTAGE WEIGHT
TO KC
GRANT

TO LCC
CASH

AMOUNT
(PESO)

FUND SOURCE
LEGEND:

KC GRANT

1,648,497.00

1,591,690.12

80.00%

80%

TOTAL LCC

378,840.65

198,961.27
198,961.27
1,989,612.65

10.00%
10.00%
100%

10.00%
10.00%
100%

LCC - In-kind
LCC - Cash
TOTAL

37,725.00
341,115.65
2,027,337.65

REMARKS

TRANCHING SCHEDULE
TOTAL
2nd Tranche

3rd Tranche

LCC Cash

KC Grant

LCC Cash

TOTAL
KC Grant

LCC Cash
54,022.50

360,150.00

13,872.00

2,448.00

16,320.00

592.88

104.63

697.50

11,602.50

2,047.50

13,650.00

332,194.88

58,622.63

390,817.50

61,103.52

10,782.98

71,886.50

393,298.40

69,405.60

462,704.00

28,765.00

115,060.00

28,765.00

143,825.00

28,765.00

115,060.00

28,765.00

143,825.00

169,772.63

29,959.88

199,732.50

198,858.00

49,714.50

248,572.50

368,630.63

79,674.38

448,305.00

234,407.80
134,222.83
102,272.00
120,870.00

38,441.70
41,232.68
18,048.00
21,330.00

272,849.50
175,455.50
120,320.00
142,200.00

223,142.00

39,378.00

262,520.00

9,132.00
48,510.00

60,880.00
323,400.00

51,748.00
274,890.00
-

121,992.00

21,528.00

143,520.00

121,992.00

21,528.00

143,520.00

7,644.00
29,172.00

50,960.00
194,480.00

43,316.00
165,308.00

MONTHS
1

306,127.50

PROPOSED
IMPLEMENTATION
SCHEDULE

6,854.40

1,209.60

8,064.00

2,041.20

13,608.00

18,421.20

3,250.80

21,672.00

8,325.00

0.00
7,835.00

0.00
45,621.02

0.00
8,325.00

7,835.00

45,621.02

8,325.00

1,550.00
1,550.00
-

6,750.00

45,000.00

68,000.00
51,000.00
12,750.00

12,000.00
9,000.00
2,250.00

80,000.00
60,000.00
15,000.00

170,000.00

30,000.00

200,000.00

1,125.00
28,875.00

7,500.00
192,500.00

45,621.02

310.00
310.00

38,250.00

6,375.00
163,625.00

7,835.00

1,032.00
22,704.00
-

2,500.00
5,825.00

154.80
3,405.60
-

1,240.00
1,240.00

22,087.16
23,533.86

11,566.80
877.20
19,298.40
-

4,000.00
3,835.00

8,400.00
6,240.00

2,100.00
1,560.00

10,500.00
7,800.00

14,640.00

3,660.00

18,300.00

18,960.00
33,600.00
75,700.00
74,026.98

4,740.00
8,400.00
10,500.00
11,823.02

23,700.00
42,000.00
86,200.00
85,850.00

22,323.02

172,050.00

0.00
149,726.98

0.00
22,323.02

0.00
172,050.00

6,760.00

1,690.00

8,450.00

6,760.00

1,690.00

8,450.00

149,726.98

840.00
7,600.00
1,405,507.68

210.00
1,900.00
260,126.82

1,050.00
9,500.00
1,665,634.50

680.00
280.00
1,800.00
68.00
2,240.00

170.00
70.00
450.00
17.00
560.00

850.00
350.00
2,250.00
85.00
2,800.00

1,400.00

350.00

1,750.00

6,468.00

1,617.00

8,085.00

6,964.00

1,741.00

8,705.00

13,432.00

3,358.00

5,120.00

1,280.00

6,400.00

5,120.00

1,280.00

6,400.00

880.00
6,000.00

220.00
1,500.00

13,488.58
7,000.00
30,000.00
6,000.00

8,708.92
1,500.00
5,008.58
1,500.00

4,000.00

1,100.00
7,500.00

1,120.00
1,120.00

280.00
280.00

1,400.00
1,400.00

2,240.00

560.00

2,800.00

640.00
2,880.00
3,442.50

16,790.00

160.00
720.00

800.00
3,600.00

19,348.58
7,000.00
37,491.42
6,000.00

12,151.42
1,500.00
13,008.58
1,500.00

31,500.00
8,500.00
50,500.00
7,500.00

12,000.00
-

3,000.00
5,253.75
-

15,000.00
5,253.75
-

3,442.50

60,488.58

16,717.50

81,840.00

36,413.75

118,253.75

0.00
3,442.50
3,442.50
28,765.00

94,150.40
154,638.98
60,488.58
94,150.40

15,000.00
31,717.50
16,717.50
15,000.00

94,150.40
175,990.40
95,668.00
154,996.33

15,000.00
51,413.75
39,870.75
39,293.08

109,150.40
227,404.15
135,538.75
194,289.40

11,277.50

106,109.60

25,042.50

1,501,175.68

299,997.57

1,801,173.25

40,042.50

200,260.00

40,042.50

1,837,292.00

371,253.00

2,403,025.00

115,060.00

12.15%

94,150.40

(336,116.32)

(71,255.43)

Submitted by:

Noted by:

CARMEN A. GAUDIANO

GEORGE A. ALAS-AS

GEOGRE S. ISULAT

Municipal Engineer

BSMPC

Regional Community Infra. Specialist

BARANGAY SUB-PROJECT WORK S


Project Title

: CONCRETING OF BARANGAY ROAD

Sub-Project duration

: 90

Physical Target

:
:
:
:
:

Region
Province
Municipality
Barangay

Calendar Days

Total Sub-Project Cost

300 L.M.
VII CENTRAL VISAYAS
NEGROS ORIENTAL
DAUIN
MAGSAYSAY

Direct Cost
Indirect Cost
Date Started
Target Completion
Mode of Implementation

I. To be filled up by Deputy Area Coordinator

ITEM
NO.
I

DESCRIPTION

QTY

Surplus Common Excavation

II

Emabankment

III

Aggregate Sub-Base Course

IV

Portland Cement Conrete


Pavement (PCCP)

Grouted Riprap

VI

Project Steel Billboard

UNIT

233.33 cu.m.

Err:509

PHYSICAL

(%)

TARGET

150,800.00

8.54%

(168,931.50)

-9.57%

393.00 cu.m.

395,987.00

22.42%

1,200.00 sq.m.

909,418.00

51.49%

45.00 cu.m.

468,345.00

26.52%

10,425.00

0.59%

1.00

cu.m.

WEIGHT
AMOUNT

lot

T O T A L

1,766,043.50

100.00%

PLANNED

PHYSICAL
% PROGRESS (Actual)
PROGRESS (Planned)
FINANCIAL
PROGRESS (Actual)
Prepared by:

WEEK 2

WEEK 3

# # # # # # # # # # # # # # # # # # #

ACTUAL

ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED

# #

ACTUAL
PLANNED

# # # # # # # # # # # # # # # # # # #

ACTUAL
1

PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
PERIODIC
COMMULATIVE
Concurred by:

JOCELYN ALAS-AS
PIT Chairperson

WEEK 1

PLANNED

II. To be filled up by Deputy Area Coordinator


% PROGRESS (Planned)

MONTH 1

10

11

12

13

14

15

16

17

18

19

2.73%

2.13%

3.00%

2.73%

4.86%

7.86%

48,125.00

37,700.00

52,981.31

48,125.00

85,825.00

138,806.31

Checked by & Reviewed by:

SELVINO BULISID
MIT Team Leader

RODSON
Deputy Area

WORK SCHEDULE & PHYSICAL PROGRESS REPORT

: P

1,854,700.00

LABOR

: P 1,766,043.50
: P
88,656.50
:
:
: By Community Force Account (CFA)

No. of Days
90

SKILLED

90

UNSKILLED
TOTAL

MONTH 2
EEK 3

WEEK 4

WEEK 5

WEEK 6

MONTH 3
WEEK 7

WEEK 8

WEEK 9

WEEK 10

WEEK 11

WEEK

# # # # # # # # #

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
##########################################

###############################################################################################################

################################################

# # # # # # # # ######################

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

43

44

45

46

47

48

49

50

51

52

53

54

55

56

64

65

66

67

68

69

70

71

72

73

74

75

76

77

85

86

87

88

89

90

91

99

100

101

102

103

104

105

106

107

.00%

0.22%

5.00%

15.00%

17.00%

18.00%

13.81%

12.00%

5.00%

3.00%

.86%

8.08%

13.08%

28.08%

45.08%

63.08%

76.89%

88.89%

93.89%

96.89%

52,981.31

3,913.70

88,302.18

264,906.53

300,227.40

317,887.83

243,890.61

211,925.22

88,302.18

52,9

38,806.31

142,720.01

231,022.18

495,928.71

796,156.10

1,114,043.93

1,357,934.54

1,569,859.76

1,658,161.93

1,711,1

ewed by:

RODSON R. ESCORA
Deputy Area Coordinator

Approved by:

CARMEN A. GAUDIANO
Municipal Engineer

Noted by:

GEORGE ALAS-AS
BSPMC

GEORG

RT
Average
Rate/Day
300.00

No. of Days
90
90

275.00

MONTH 3

MONTH 4
WEEK 12

WEEK 13

####################################

####################################

108

109

110

111

112

113

114

115

116

117

3.00%

2.00%

96.89%

98.89%

118

119

52,981.31

35,320.87

1,711,143.24

1,766,043.50

GEORGE S. ISULAT
RCIS

PROPOSED PROCUREMENT ACTIO


Sub-project Name : Concreting of Barangay Road
Location : Magsaysay, Dauin, Negros Oriental
Timeline to complete
the activity (Inclusive
Dates)

Responsible Volunteer/s and Project Staff


( Complete Name)

1. Preparation of Planned Community


Procurement Packages

March 4, 2014

George alas-as BSPMC Chair, Teodolo Bulisid


-BAC,-PT,Engr. Rodson R. Escora - DAC, Ricky
T. Panoy -CF and Name-Engr. Carmen A.
GaudianoM.E.

2. Finalization of Packages & PCPP

March 7, 2014

-do-

3. Conduct of Pre-procurement Conference

March 11, 2014

George Alas-as-BSPMC Chair, Teodolo


Bulisid ,Benadeth Tuala-BAC, Jocelyn Alas-asPIT,Felix Avellano-PT, Engr. Rodson R. Escora DAC, Ricky T. Panoy-CF and Carmen A.
Gaudiano-M.E.

4. Preparation of Minutes of Conference

March 11, 2014

Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF

Procurement Activities

5. Preparation of Procurement Documents

March 11-13, 2014

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

6. Serving of Canvass/Request for Qoutation

Package 1: Hardware

March 14, 2015

Package 2: Base Aggregate

March 14, 2015

Package 3: Aggregates

March 14, 2015

Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF

Procurement Activities

Timeline to complete
the activity (Inclusive
Dates)

Package 4: Form Lumber

March 14, 2015

Package 5: Water

March 14, 2015

Package 6: Equipment Rental (Heavy)

March 14, 2015

Responsible Volunteer/s and Project Staff


( Complete Name)

Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF
Package 7: Equipment Rental (Light)

March 14, 2015

Package 9: Project Steel Billboard

March 14, 2015

Package 10: Personal Protective Equipment

March 14, 2015

Pckage 11: BSPMC Filing Cabinet

March 14, 2015

Package 1A: Hardware

April 18, 2014

Package 3A: Aggregates

April 18, 2014

7: Opening of Canvass

Felix Savillano, Erick Adora, Cristituta Rigon PT, Ricky T. Panoy- ACT-CF

Procurement Activities
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices

Package 1A: Hardware, Package 3A: Aggregates


8. Preparation of Minutes of Opening

Timeline to complete
the activity (Inclusive
Dates)

March 17, 2014

Responsible Volunteer/s and Project Staff


( Complete Name)

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

April 21, 2014


-do-

Procurement Activities
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices

Package 1A: Hardware, Package 3A: Aggregates


9. Evaluation of Canvass
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices

Package 1A: Hardware, Package 3A: Aggregates


10. Preparation of Abstract of Canvass
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices
Package 1A: Hardware, Package 3A: Aggregates

11. Preparation of Purchased Order

Package 1: Hardware, Package 2: Base Aggregate,


Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices

Timeline to complete
the activity (Inclusive
Dates)

March 17, 2014

Responsible Volunteer/s and Project Staff


( Complete Name)

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

April 21, 2014


March 27, 2014

March 17, 2014

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

April 21, 2014


March 27, 2014

-do-

March 17, 2014

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

April 21, 2014

March 27, 2014

March 18, 2014

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

Procurement Activities

Package 1A: Hardware, Package 3A: Aggregates

George Alas-as-BSPMC Chair,Felix AvellanoTimeline to complete


PT,Engr. Rodson
R. Escora
- DAC,Ricky
T.
Responsible
Volunteer/s
and
Project Staff
the activity (Inclusive Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.
( Complete Name)
Dates)
April 22, 2014
George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.
Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

12. Approving of Purchased Order


Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices

Package 1A: Hardware, Package 3A: Aggregates

13. Serving of Purchased Order to Winning


Suppliers
Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices
Package 1A: Hardware, Package 3A: Aggregates

March 18, 2014


Hazley Lanfie,Teodulo Bulisid, Bernadita Tuala

April 22, 2014

March 28, 2014

Hazley Lanfie,Teodulo Bulisid, Bernadita Tuala

March 18-19, 2014

George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.


Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

April 22-23, 2014


George Alas-as-BSPMC Chair,Felix AvellanoPT,Engr. Rodson R. Escora - DAC,Ricky T.
Panoy-CF and -Engr. Carmen A. Gaudiano-M.E.

14. Delivery of Goods


Package 1: Hardware, Package 2: Base Aggregate,
Package 3: Aggregates, Package 4 Form Lumber,
Package 5: Water, Package 6: Heavy Equipment
(Heavy), Package 7: Light Equipment, Package 9:
Project Steel Billboard, Package 10: Personal
Protective Equipment; Package 11: BSPMC Filing
Cabinet, Package 12: Environmental Mitigating
Devices
Package 1A: Hardware, Package 3A: Aggregates

March 24-28, 2014

April 27-29, 2014


April 28-May 3, 2014

15. Mobilization and Start of SPI

Selvino Bulisid - MIT Chair, MIT Members, Ricky


T. Panoy- ACT-CF, Rodson Escora-ACT-DAC

Selvino Bulisid - MIT Chair, MIT Members, Ricky


T. Panoy- ACT-CF, Rodson Escora-ACT-DAC
BSPMC, Jocelyn Alas-as- PIT Chair and PIT
Members, Community Workers

Procurement Activities

Timeline to complete
the activity (Inclusive
Dates)

Responsible Volunteer/s and Project Staff


( Complete Name)

Prepared by:
Reviewed & Checked by:

PT Chairperson

ENGR. CARMEN A. GAUDIANO


MCT-DAC

ENGR. RODSON R. ESCORA


ACT-DAC

EMENT ACTION PLAN (PAP)

Venue of meeting and


place/s to conduct
procurement

Name of Potential
Suppliers Contractors

Resources
Requirement

Expected outputs/
Remarks

Brgy. Hall/BSPMC Office

POW/Detailed
Estimates

Draft PCPP

Brgy. Hall/BSPMC Office

POW & Draft PCPP

Final PCPP

Brgy. Hall/BSPMC Office

Final PCPP

Conference Conducted

Brgy. Hall/BSPMC Office

Office supplies

Minutes of Conference

Brgy. Hall/BSPMC Office

POW & Final PCPP

Invitation to Bid/Bid
Documents

Supplier's Office,
Establishment

Supplier's: Zenith
Commercials, Golden Rule,
New Bian Yek Commercials,
Dgte. YY Trading,
Duplamilco

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Gold
Enterprises, Lucky
Enterprises, JM
Commercials

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Sugar Hills


Agricultural Corp., Solon
Construction, Lucky
Construction

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Venue of meeting and


place/s to conduct
procurement

Name of Potential
Suppliers Contractors

Resources
Requirement

Expected outputs/
Remarks

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Suppliers's: Gold
Enterprises, Maureze
Construction, Duplamilco
Inc., Alagasi's Construction
Supply

Supplier's Office,
Establishment

Suppliers: Resident of
Barangay Tunga-Tunga

Supplier's Office,
Establishment

Supplier's:Uymatiao
Construction, HLJ
Construction, Big Foot,
Philsouth Contractors

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Alagasi's
Construction Supply,
Rejoice Hardware, LKC
Hardware

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Alagasi's
Welding Shop, Zamora
Welding Shop, Orient Pearl

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Rejoice
Hardware, Premium
Hardware, Gold Enterprises,
LKC Hardware

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Alice Furniture,


Lindeys Furniture, BL
Furniture

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Zipline
Commercial, I Concept,
ADS Unlimited, Sun Signs

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Supplier's Office,
Establishment

Supplier's: Zenith
Commercials, Golden Rule,
New Bian Yek Commercials,
Dgte. YY Trading,
Duplamilco

Canvass
Form/Request for
Qoutation,
Acknowledgement
Receipt

Canvass Form/Request
for Qoutation Served,
Signed AR

Venue of meeting and


place/s to conduct
procurement

Brgy. Hall/BSPMC Office

Name of Potential
Suppliers Contractors

Resources
Requirement

Expected outputs/
Remarks

Submitted Canvass
Form/Request for
Qoutation

Abstract of Canvass

Venue of meeting and


place/s to conduct
procurement

Name of Potential
Suppliers Contractors

Resources
Requirement

Expected outputs/
Remarks

Brgy. Hall/BSPMC Office

Office Supplies

Minutes of Opening

Brgy. Hall/BSPMC Office

Office Supplies

Brgy. Hall/BSPMC Office

Submitted Canvass
Form/Request for
Quotation

Minutes of Evaluation

Brgy. Hall/BSPMC Office

Submitted Canvass
Form/Request for
Quotation

Minutes of Evaluation

Brgy. Hall/BSPMC Office

Submitted Canvass
Form/Request for
Quotation

Abstract of Canvass

Brgy. Hall/BSPMC Office

Submitted Canvass
Form/Request for
Quotation

Abstract of Canvass

Brgy. Hall/BSPMC Office

Abstract of Canvass

Purchased Order

Venue
of meetingOffice
and
Brgy.
Hall/BSPMC
place/s to conduct
procurement

Abstract
of Canvass
Resources
Requirement

Purchased
Order
Expected
outputs/
Remarks

Brgy. Hall/BSPMC Office

Abstract of Canvass

Purchased Order

Brgy. Hall/BSPMC Office

Purchased Order

Approved Purchased
Order

Brgy. Hall/BSPMC Office

Purchased Order

Approved Purchased
Order

Supplier's Office,
Establishment

Name of Potential
Suppliers Contractors

Approved Purchased Conformed Purchased


Order
Order by Suppliers

Supplier's Office,
Establishment

Project Site

Delivery
Receipt/Delivered
Goods

Goods Received

Project Site

Delivery
Receipt/Delivered
Goods

Goods Received

Project Site

Notice to Commence

Mobilization Started

Venue of meeting and


place/s to conduct
procurement

Name of Potential
Suppliers Contractors

Noted by:

Resources
Requirement

Expected outputs/
Remarks

Approved by:

ENGR. HELEN C. YBANEZ


Area Coordinator

BSPMC Chairperson

ENHANCED PLANNED COMMUNITY PROCUREMENT PACKAGING


Date Prepared

: October 9, 2013

Name of Proposed Sub-Project

: Concreting

Barangay
Municipality

: Magsaysay
: Dauin

Total Cash (Php)


Sub-project Duration

:
:

Province

: Negros Oriental

SOURCES OF FUNDS
TOTAL

74,772.40
56,407.25

PACKAGES

Mode of Implementation : By Contract

PACKAGE ITEMS

QTY

UNIT

UNIT COST

LCC:

AMOUNT
(PESO)

FUND SOURCE
LEGEND:

TO KC
GRANT

TO LCC CASH

KC GRANT

1,523,075.00

1st Tranche (Php)

1,218,460.00

241,240.00

1,459,700.00

80.00%

80%

TOTAL LCC

331,625.00

2nd Tranche (Php)


3rd Tranche (Php)
TOTAL CASH (Php)

152,307.50
152,307.50
1,523,075.00

30,155.00
30,155.00
301,550.00

182,462.50
182,462.50
1,824,625.00

10.00%
10.00%
100%

10.00%
10.00%
100%

LCC - In-kind
LCC - Cash
TOTAL

30,075.00
301,550.00
1,854,700.00

TRANCHING SCHEDULE

PROC
METHOD

TOTAL

TOTAL
1st Tranche
KC Grant

2nd Tranche

LCC Cash

KC Grant

3rd Tranche

LCC Cash

KC Grant

TOTAL

LCC Cash

KC Grant

LCC Cash

REMARKS

131,179.65

.
PERCENTAGE WEIGHT

DESCRIPTION
KC Grant:

of Barangay Road

Err:509
120 C.D

PROPOSED
IMPLEMENTATION
SCHEDULE

MONTHS
1

Surplus Common Excavation


Emabankment
Aggregate Sub-Base Course
Portland Cement Conrete Pavement (PCCP)
Grouted Riprap
Project Steel Billboard
CONTRACTOR'S PROFIT (10% of DC)
VAT (7% of TDC)
sub-total
Handtools & Personal Protective Equipment (PPE)
Hard Hat
Hand Glooves
Medicine Kit

233.33
Err:509
393.00
1,200.00
45.00
1.00

cu.m.
cu.m.
cu.m.
sq.m.
cu.m.
lot

ok
10.00
10.00
1.00

pcs.
pcs.
set

1.00

pcs.

Package 4

Package 4

sub-total

package 5

237.26
Err:509
906.31
695.40
3,212.02
9,350.00

125.00
25.00
1,890.00
ok

55,360.00
49,577.88
5,782.12
Err:509
Err:509
Err:509
356,179.75
315,807.30
40,372.45
LOCAL
834,479.00 BIDDING FOR
757,490.71
76,988.29
144,541.00 WORKS (LBW)
1,607.47
3,861.35
9,350.00
8,372.12
977.88
124,694.33
(49,428.95)
100,378.93
75,883.66
Err:509
Err:509
Err:509
1,250.00
250.00
1,890.00
3,390.00

BSPMC Filling Cabinet


BSPMC Filling Cabinet

sub-total
Environmental Mitigating Cost:
Warning Sign
Barricade
sub-total
Indirect Cost:
Overhead Cost
Project Supervision
Administrative Cost
Bidding Publication
Materials Testting

5.00
5.00

pcs.
pcs.

6,000.00

420.00
300.00

7,500.00
7,500.00
2,100.00
1,500.00
3,600.00

Contingency Cost
sub-total

20,766.88
26,766.88

121,246.79

91,246.79

163.04
32.61
246.52

1,086.96
217.39
1,643.48
-

1,250.00
250.00
1,890.00

1,680.00
1,200.00
2,880.00

420.00
300.00
720.00

32,000.00
6,000.00
8,000.00

8,500.00
8,000.00
1,500.00
2,000.00
5,253.75
58,874.76

46,000.00

25,253.75

20,311.33

59,563.43

Err:509

Err:509

200,260.00

26,766.88

180,810.22

22,547.72

Err:509

Err:509

Err:509

1,218,460.00

241,240.00

152,307.50

30,155.00

152,307.50

30,155.00

Err:509

Err:509

Err:509

Err:509
10.00%
Err:509
Recommending Approval:

(47,952.50)
3,388.12

10.00%

(28,502.71)
7,607.28
Submitted by:

Err:509

Err:509

80.00%

163.04
32.61
246.52

442.17

Err:509

PPT

179,948.67

20,311.33

SAY

Procurement Team Head

30,000.00

1,500.00
1,500.00

LOCAL
SHOPPING FOR
GOODS (LSG)

1,824,625.00
Err:509
Checked & Reviewed by:

6,000.00

82,876.49

6,000.00
6,000.00

163,947.84
GRAND TOTAL CASH

97,072.18

49,577.88
5,782.12
55,360.00
Err:509
Err:509
Err:509
315,807.30
40,372.45
356,179.75
757,490.71
76,988.29
834,479.00
6,000.00
128,679.65
15,861.35
144,541.00
8,372.12
977.88
9,350.00
124,694.33
124,694.33
3,728.39
100,378.93
100,378.93
9,728.39 Err:509
Err:509
Err:509

2,947.83
LOCAL
SHOPPING FOR
GOODS (LSG)

21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
71,694.09

Treasurer Bond

1,086.96
217.39
1,643.48

LOCAL
SHOPPING
FOR GOODS
(LSG)

CFA

Package 3

Package 1

Direct Cost:

2,947.83

442.17

3,390.00

6,000.00
6,000.00

1,500.00
1,500.00

7,500.00
7,500.00

1,680.00
1,200.00
2,880.00

420.00
300.00
720.00

2,100.00
1,500.00
3,600.00

12,819.33

21,000.00
32,000.00
6,000.00
8,000.00
58,874.76

8,500.00
8,000.00
1,500.00
2,000.00
5,253.75
12,819.33

21,000.00
8,500.00
40,000.00
7,500.00
10,000.00
5,253.75
71,694.09

12,819.33

125,874.76

38,073.08

163,947.84

688.67

Noted by:

GERUNDIO C. BAUTISTA JR.

CARMEN A. GAUDIANO

GEORGE ALAS-AS

GEORGE S. ISULAT

Deputy Area Coordinator

Municipal Engineer

BSMPC

Regional Community Infra. Specialist

ADMINISTRATIVE COST DERIVATION


Sub-project Activities

Destination/Description

Fare/
Allowance/
Unit Price

Qty.

Unit

pesos

No of
transactions

1. TE for Opening of BSPMC LBP Bank Account of CVs


x

1 times

persons x

1 times

persons x

2 times

130.00

persons x

8 times

80.00

persons x

8 times

130.00

persons x

8 times

meals

80.00

persons x

8 times

Supplies
Snacks

50.00
20.00

12
20

meetings
persons x

15 times

130.00

persons x

15 times

80.00

persons x

15 times

130.00

persons x

30 times

80.00

persons x

30 times

350.00
300.00
2.00
1.00
30.00
685.00
50.00
35.00
20.00
3.00
20.00
30.00

x
x
x
x
x
x
x
x
x
x
x
x

6
6
2250
1190
8
1
4
1
3
40
2
1

reams
reams
sheets
pc
boxes
pc
pcs
ps
pc
pcs
box
pc

Log book

80.00

pcs

Fastener

50.00

box

DBP Initial Deposit


BSPMC office to Dgte. (vice
versa)

meals

1,500.00

130.00

80.00

Sub-Total
2. TE for procurement
transactions of CVs
BSPMC office to Dgte. (vice
versa)

Serving of Canvass

meals
Serving of PO & Payments

BSPMC office to Dgte. (vice


versa)

Sub-Total
3. Project Meetings

Sub-Total
4. MCT-Initiated Meetings
BSPMC office to MCT Office
(vice versa)

Meals
Sub-Total
5. Treasurer Payroll Processing
BSPMC office to Dauin (vice
versa)

Meals
Sub-Total
6. Forms/Supplies and Reproduction
Bondpaper long
Bondpaper short
Reproduction
Petty Cash Box
Staple Wire
Calculator
Columnar Book
Liquid Eraser
Paste/Glue
Folder long
Paper clip
Pentil pen

Sub-Total
TOTAL FOR ADMIN COST

Prepared by :

Approved by :

ELSA A. TRUNO

GEORGE ALAS-AS

MEO Staff

BSPMC Chairperson

Checked by:

Concurred by :

RODSON R. ESCORA
Deputy Area Coordinator

HON. LIBRADO TUAL


Sanggunian Barangay Mem

Recommending Approval:

ENGR. CARMEN A. GAUDIANO

HON. NEIL B. CREDO

Municipal Engineer - MCT DAC

Municipal Mayor

Noted by:

GEORGE S. ISULAT
Regional Community Infrastructure Specialist

RATIVE COST DERIVATION


No of
transactions

Amount

1,500.00

260.00

320.00
2,080.00

3,120.00

1,920.00

2,080.00

1,280.00
8,400.00

=
=

600.00
6,000.00
6,600.00

9,750.00

6,000.00
15,750.00

3,900.00

2,400.00
6,300.00

=
=
=
=
=
=
=
=
=
=
=
=

2,100.00
1,800.00
4,500.00
1,190.00
240.00
685.00
200.00
35.00
60.00
120.00
40.00
30.00

320.00

50.00
11,370.00
50,500.00

GEORGE ALAS-AS
BSPMC Chairperson

HON. LIBRADO TUALA


Sanggunian Barangay Member

HON. NEIL B. CREDO


Municipal Mayor

SCHEDULE OF IN - KIND LOCAL COUNTERPART CO


Date Prepared
###
Barangay:
MAGSAYSAY
Municipality: Dauin
Province:

Name of proposed community project:Concreting of Barang


Total Estimated Cost:
Php2,440,600.00

Negros Oriental

Mode of Implementation:

Community Project Duratio90 Calendar Days


Estimated Cost1st Tranche
###
2nd Tranche 3,557.50
3rd Tranche 3,557.50
CFA

By Contract

ESTIMATED COST INVOLVED and SCHEDULE


PROC.
DELIVERY
PACKAGES

PACKAGE ITEMS

METHOD 1st Tranche2nd Tranche3rd Tranche


In - Kind

Direct Cost:
Materials
Package 1
Unskilled labor

Contract

Indirect Cost:
Hand tools/PPE
Pre-engineering
Project Supervision

CFA

In - Kind

In - Kind

25,260.00

3,157.50

3,157.50

2,000.00
3,200.00

400.00

400.00

### 3,557.50

3,557.50

TOTAL
Workshop output of:

Checked by:

Reviewed by:

FELIX AVELLANO
Procurement Team Head

CARMEN A. GAUDIANO

RODSON R. ESCORA

Municipal Engineer

DAC - Area Coordinating Team

TERPART CONTRIBUTION

ncreting of Barangay Road


0.00
LCC ( In - Kind) :Php 37,575.00

ED and SCHEDULE OF
RY

PROPOSED
IMPLEMENTATION

TOTAL

SCHEDULE

31,575.00

January, 2014 -April, 2014

2,000.00
4,000.00

January, 2014 -April, 2014


January, 2014 -April, 2014

ESCORA

ordinating Team

###
Submitted by:

GEORGE ALAS-AS
BSPMC Chairperson

1st Tranche
CHECKLIST OF DOCUMENTARY REQUIREMENTS
Barangay MAGSAYSAY
Municipality of Dauin
Sub-Project Title: Concreting of Barangay Road
Phase/Cycle: 2
RFR REVIEW SHEET
Item #

1st TRANCHE

Requirements

Comments

1. Request for Fund Release (RFR)


2. POW
3. Colored Photographs of Proposed Project
Site/Plan
4. Guide for the Technical Review
5. Certification of Review by RIE, RFA, CPS &
RPM
6. MDC/ MIBF Resolution
7. Detailed Estimates/Work Schedule &
Physical Progress Report
8. Hydraulic Analysis for Water Supply System
9. Project Proposal
10. Planned Comm. Procurement Packaging
(PCPP)
11. Procurement Action Plan (PAP)
12. LCC for SPI Monitoring Report
13. DBP Certification/Bank Snapshot
14. Schedule of In-kind LCC
15. O&M Action Plan signed by Brgy. Chairman
16. Certification from the Regional Director

17.For SPs amounting to P 1.5 million and above, submit


PSA result, approved technical plans ( for roads indicate critical sections subject for concreting) and
approved specifications

18.Barangay Council Resolution


19.Sub Project Agreement
20.Local Counterpart Contribution Plan/Admis cost
21.Certification on Local Contributions
22.Bond Premium of Treasurer
23. Economic Analysis
24.Notarized Deed of Lot Donation for Titled
Lot or Quit Claim for non Titled lots
Reviewed By: ______ Date: _____

For Further Review of :______________ Date:____________


Other Comments/ Findings/ Recommendation

Reviewed By: ________ _____


Reviewed By: ________ _____

Actions Taken
For Asec. CGG/ NPM's Signature
For regional compliance
For Transmittal to Finance Unit
Returned to Region

Date/ Date Returned


___________________
___________________
___________________
___________________

BSPMC Form No. 3


KALAHI-CIDSS: MCC PROJE
LOCAL COUNTERPART CONTRIBUT
Barangay MAGSAYSAY
Municipality of Dauin
Province of Negros Oriental, Region V
Sub-Project Title: Concreting of Barangay Road
Budget Item

Unit used

No. of
Units

Per Unit
Cost

Total Sub-Project
Cost

I. Administrative Cost
TE for opening of BSPMC DBP Account of CV's
TE for procurement transactions of CV's
Project Meetings
MCT-Initiated Meetings
Treasurer Payroll Processing
Forms/Supplies and Reproduction
Sub Total
II. Other Indirect Costs
Overhead Cost
Handtools
Pre-engineering
Project Supervisions
Bidding Publication
Environmental Mitigating Cost
BSPMC Filing Cabinet
Material Testing
Treasurer's Bond
VAT ( 7% of Total Direct Cost)
Contractors Profit (10%)
Contingency
Sub Total
III. Direct Cost
Labor
Materials
Equipment Rental
Sub Total
TOTAL PROJECT COST
IV. Operations & Maintenance
Other Amenities
Sub Total
GRAND TOTAL
Prepared by:

BERNADITA TUALA
Barangay Treasurer

2,800.00
7,140.00
5,400.00
9,900.00
6,000.00
8,760.00
40,000.00
21,000.00
3,390.00
2,000.00
12,500.00
7,500.00
3,600.00
7,500.00
10,000.00
5,253.75
133,567.97
190,811.39
95,363.05
492,486.16
198,825.00
1,526,348.84
182,940.00
1,908,113.84
2,440,600.00
0.00
0.00
2,440,600.00

BSPMC Form No. 3


ALAHI-CIDSS: MCC PROJECT
OUNTERPART CONTRIBUTION PLAN
Barangay MAGSAYSAY
Municipality of Dauin
Negros Oriental, Region VII, Philippines

Pro-posed
Amount of Grant

Mun LGU

Local Counterpart Contribution (LCC) Sources


Brgy LGU
Community
DepEd
Total of LCC

2,240.00

560.00

560.00

5,712.00
4,320.00
7,920.00
4,800.00
7,008.00
32,000.00

1,428.00
1,080.00
1,980.00
1,200.00
1,752.00
8,000.00

0.00

1,428.00
1,080.00
1,980.00
1,200.00
1,752.00
8,000.00

18,500.00
1,632.00

2,500.00
1,758.00
1,000.00
8,500.00
1,500.00
720.00
1,500.00
2,000.00
5,253.75
133,567.97

0.00

2,500.00
1,758.00
2,000.00
12,500.00
1,500.00
720.00
1,500.00
2,000.00
5,253.75
133,567.97
0.00
17,038.50
180,338.22

6,000.00
2,880.00
6,000.00
8,000.00

190,811.39
78,324.55
312,147.94

17,038.50
175,338.22

0.00

0.00

1,000.00
4,000.00

5,000.00

0.00

167,250.00
1,336,828.06
154,374.00
1,658,452.06
2,002,600.00

31,575.00
189,520.78
28,566.00
218,086.78
401,425.00

0.00
5,000.00

31,575.00
31,575.00

0.00
0.00

31,575.00
189,520.78
28,566.00
249,661.78
438,000.00

0.00
2,002,600.00

0.00
401,425.00

0.00
5,000.00

0.00
31,575.00

0.00
0.00

0.00
0.00
438,000.00

Approved by:

GEORGE ALAS-AS
BSPMC Chairperson

Target Date of
Delivery of LCC
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014

January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014
January, 2014

January, 2014
January, 2014
January, 2014

Department of Social Welfare a

KALAHI-CIDSS:MCC

LCC FOR SUB-PROJECT IMPLEMENTA

As of October 31, 2

PA
C
KA
G

ES

Barangay :
MAGSAYSAY
Municipality : Dauin
Sub-Project : Concreting of Barangay Road

Package Items

Total LCC Committed

Cash
In-Kind

SCHEDULE OF LOCAL
2nd Tranche
Cash

1st Tranche
Cash
Planned

In-Kind
Actual

Planned

Actual

Planned

DIRECT COST:
I# 102-Surplus Common

I# 104-Embankment
I# 200-Aggregate Sub-ba

I# 311-PCCP
I# 505-Grouted Riprap
I# 500-Installation of RCPC
Project Steel Billboard
Unskilled Worker
TOTAL DIRECT COST
INDIRECT COST:
Overhead Cost
Bidding Publication
Administrative Cost
Package 5
Materials Testing
Treasurer's Bond
Contingency
Handtools / PPE
Package 2
Pre-Engineering
Project Supervision
Environmental Impact
Package 4
BSPMC Filing Cabinet
Package 3
VAT (7 % of Direct Cost
Package 1
TOTAL INDIRECT COST
GRAND TOTAL
Package 1

Prepared by:

11,766.00
25,013.09
35,732.85
81,221.35
53,353.50

6,000.00

1,500.00
208,586.79

31,575.00
0.00 31,575.00

0.00

6,000.00

0.00
0.00

34,042.50
34,042.50
40,042.50

1,500.00
8,000.00
2,000.00
5,253.75
1,758.00
8,500.00
720.00
1,500.00
82,521.46
111,753.21
320,340.00

2,000.00
4,000.00

0.00 6,000.00
0.00 37,575.00

Verified by:

ARLENE P. GESULGA
Municipal Financial Analyst

partment of Social Welfare and Development

ALAHI-CIDSS:MCC PROJECT

JECT IMPLEMENTATION MONITORING REPORT


As of October 31, 2013
:

438,000.00

:
:

400,425.00

Total LCC Delivered :


Cash
In-Kind

37,575.00

0.00
0.00
0.00

SCHEDULE OF LOCAL COUNTERPART CONTRIBUTION DELIVERED


2nd Tranche
3rd Tranche
Cash
In-Kind
Cash
In-Kind
Actual

Planned

Actual

Planned

Actual

Planned

TOTAL
Cash

Actual

0.00

0.00

6,000.00

0.00

0.00

0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00

0.00
1,500.00
8,000.00
2,000.00
5,253.75
17,038.50
1,758.00
0.00
8,500.00
720.00
1,500.00
133,567.96
179,838.21
400,425.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

17,038.50

0.00
0.00

0.00
0.00

Verified by:

17,004.00
0.00 34,042.50
0.00 40,042.50

0.00
0.00

0.00
0.00

Actual

11,766.00
25,013.09
35,732.85
81,221.35
65,353.50
0.00
1,500.00
0.00
220,586.79

6,000.00

0.00

Planned

Noted by:

JOEL A. EREDIANO
Area Coordinator

ANTONIO R. DOLAOTA, CPA


Regional Finance Focal Person Coordinator (RFFP-Coordinator)

TOTAL
In-Kind
Planned

Actual

0.00
0.00
0.00
0.00
0.00
0.00
0.00
31,575.00
31,575.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,000.00
4,000.00
0.00
0.00
0.00
6,000.00
37,575.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

oordinator (RFFP-Coordinator)

You might also like