Professional Documents
Culture Documents
Tutorial de MS Project 2007 2º Parte
Tutorial de MS Project 2007 2º Parte
Tutoriales
Taller de Proyectos
Microsoft Project 2007
(en inglés)
2º Parte
Objectives:
1. To learn how to add the resources and cost into tasks.
2. To learn how to track the project.
3. To learn how to select and display a report.
Sociocultural Project
http://sociocultural.mforos.com
ACE2090 Engineering Practice Tutorial 2
Objectives:
1. To learn how to add the resources and cost into tasks.
2. To learn how to track the project.
3. To learn how to select and display a report.
A. Resources
View → Resource Sheet
I. Terms:
Resources: People, equipment, and consumable items used to complete project tasks.
Resource Name: Assign the name of the resource. You will see this name beside the Gantt chart bar.
Material Label: Indentify the quantity of the material that will be consumed. This field is only workable
if the type is chosen as “Material”.
Max. Units: Is a percentage that indicates the resource’s allocation in daily scheduled work time.
Percentage Meaning
100% (default) Single Person – Full time (40 hrs / week)
<100% Single Person – Part time (Max. unit * 40 hrs / week)
100% > A team – Max. unit * 40 hrs / week
Std. Rate: The amount shows how much cost is added to the project for each hour of work assigned for
a material resource.
Accrue. At: Specifies how the Project accounts for the timing of resource costs in the budget for the
project.
- Prorated (By default): Project adds in costs at the time when work is scheduled.
- Start: Cost is paid before the work starts.
- End: Cost is paid after the work ends.
Base Calendar: Set the type of the calendar, standard (by default), 24 hours or night shift.
Now repeat Step 2 to 4 for the rest tasks according to the following table:
Note: You can keep the Assign Resources box open while you work.
Total Cost (Work * Std. Rate) + (Ovt. Work * Ovt. Rate) + (Per/Use Cost) + Task Fixed Cost
Baseline Total cost in baseline
Variance Total Cost – Baseline Cost
Actual (Actual Work * Std. Rate) + (Actual Ovt. Work * Ovt. Rate) + (Per/Use Cost) + Task Fixed Cost
Remaining (Remaining Work * Std. Rate) + Remaining Ovt. Cost
→
↓
B. Tracking Progress
Baseline: The original project plan used to track progress on a project, which includes information about
tasks, resources, and assignment.
I. Save Baseline
Tools → Tracking → Set Baseline
2. Progress
View → Tracking Gantt
The red/ blue bars shift to the right due to adding the holiday and the change of the overtime work.
II. Slack
Step 1: View → Gantt Chart
Step 2: View → Table → Schedule
Free Slack: The amount of time a task can slip without delaying other tasks.
Total Slack: The amount of time a task can slip without delaying the project finish date.
D. Reporting
Report → Reports…