Professional Documents
Culture Documents
Sp08 Q&A 1pupoyu Ploy Ploby Ploby
Sp08 Q&A 1pupoyu Ploy Ploby Ploby
com]
Sent: 28 April 2008 12:40
To: INDRAWANSA SAMARATUN
Subject: Clarification
Dear Professor Sam
Kindly clarify following:
Is there any requirement of giving notices for any variations by the contractor? Notice is
not required to value the direct value of the Variation. Notice is required only if the
Contractor requires a varied rate or price, (or extra payment for indirect costs such as
prolongation costs if the variation causes a delay/disruption). Also could we reject any
variation upon not providing such notices? No. The Contractor should be paid the value
of the Variation.
Please clarify this pursuant to clause 52.2(paragraph two) of FIDIC Conditions of
Contract. As explained during the Course, although the literal meaning of the words
requires a notice, the Courts (in the construction of the contract), would not permit an
Employer to rely on such words as the Employer would become unjustly enriched (which
is unlawful) if the Contractor is not paid for the variation.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
so much and I'm sure same with my batch mates and others. The effort and time we spent
is really worth. I can consider that the knowledge we learned is priceless.
May you stay young looking, healthy and strong and continue to touch more people's life
for more years and decades. I'm looking forward for the second part of this training.
Surely we will miss attending your lectures.
Best Regards,
Elisa Villalon
Many Thanks for your kind words.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Prof. Sam.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
regards
----- Original Message ----From: Lourdes Beato
To: Prof Sam <sam99@emirates.net.ae>
Date: Tue, 15 Apr 2008 00:37:40 -0700 (PDT)
Subject: [No Subject]
Dear Prof. Sam,
I would like to ask if the contractor is entitled for
an EOT due to adverse climatic condition (this was
during the rainy days happened last January) as per
FIDIC clause 44.1 (c)? Yes.
If No, why?
If yes, what documents are required to prove that he
is entitled for EOT? Weather reports from meteorological department to show that the
climatic condition was exceptional (out of the ordinary) when compared to the typical
climatic conditions over the past 15 - 20 years (or such other period stated in the contract)
and site records/photos proving that progress of the Works were adversely affected, plus a
delay impact analysis demonstrating cause and effect.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Kind regards,
Lourdes
Dear Mr. Karim,
----- Original Message -----
Planning Manager
EC HARRIS:
Dear Mr. Zafar,
Many Thanks.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668