Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 17

ITEM

DESCRIPTION
Site Clearance & Demolition Cont'd

QUANTITY

UNIT

RATE

SUM

Allow for avoiding any damage whatsoever to


all existing electrical poles, trees, fire hydrants
and drainage manholes located along the
route of the walls.

AMOUNT

500,000.00

Earthworks
B

Remove 150mm thickness of top soil from


unpaved ground along route of new walls and
store in spoil heaps.

659

m2

150

98,850.00

Supply, place and compact in layers not


exceeding 200mm compacted thickness granular limestone (marl) to form level
embankment to the dimensions shown - each
layer to be compacted to achieve 95% Proctor
Dry Density.

231

m2

150

98,850.00

Extra over item "C" for shaping and grading


top and sloping surfaces of embankment.

554

m2

100

55,400.00

Take from spoil heaps - selected top soil


material, then place on top of embankment
slope and top - 100mm thick along outside of
Walls A, B, C and D.

369

m2

200

73,800

Sow, water and establish Bahamia grass on


top of top soil embankment surface.

369

m2

1,000

369,000

Dispose of surplus top soil in spoil heaps from


site.

69

m2

500

34,500

ITEM

DESCRIPTION

QUANTITY

UNIT

RATE

294

m3

800

235,200

Retaining Walls, Security Walls "A", "B",


"C" & "D" and Gate Columns
A

Excavate not exceeding 1.5m deep below top


of new embankment, average 1.05m deep for
strip foundation to new boundary walls A, B, C
& D and get out and store in spoil heaps.

Ditto, existing ground level of outside grassed


verge for strip foundations below three new
short retaining walls, ditto.

m3

800

3,200

Ditto - average 1.2 deep for two (2) 1.4m x


1.4m x 0.6m deep foundations to 450 x 450
reinforced concrete gate columns for gate #1,
ditto.

m3

800

4,000

Demolish portion of existing 20mm thick x


2.54m high reinforced blockwork security wall
separating the North Terminal and the Old Zinc
Factory premises to forms 6.1m wide gate in including removing &-arms, six (6) strands of
barbed wire and 760mm 0 razor wire and
disposed of spoils from site.

3,000

21,000

Excavate not exceeding 2m deep, average


1.65m deep for two(2) 1.4m x 1.4m x 0.6m
deep foundations to 450 x 450 reinforced
concrete gate columns for gate #2, ditto.

6.5

m3

800

5,200

Extra over Items A, C, & E for excavating to


break up using pneumatic breakers, existing
150 and 200 thick stup walls and reinforced
concrete foundations and dispose of spoils
from site.

55

m3

3,500

192,500

ITEM

DESCRIPTION

QUANTITY

UNIT

RATE

Retaining Walls, Security Walls "A", "B",


"C" & "D" and Gate Columns Cont'd.
Rates for precast concrete walls are to include
for all equipment needed to lift, transport,
place and secure wall panels during erection.
A

Extra over Items 2/3B, 2/3C and 2/3E for saw


cutting, scarifying and disposing of asphaltic
concrete surface from site.

10

m2

1,000

10,000

Supply, mix, place and compact 28 N/mm


(4000#/in2 ) reinforced concrete in foundation
for retaining walls, security walls and gated
columns.

131.5

m3

10,800

1,420,200

Ditto for precast security wall panels, insitu


retaining wall stems and gate columns.

154

m3

14,200

2,186,800

Supply and place wrought vertical shuttering to


the sides of security walls and at ends where
expansion joints occur.

Ditto for retaining walls and for gate columns.

Extra for foriming shaped groove at ends of


pre-cast wall panels.

44

m2

Reinforcement
G

Supply, cut, bend and fix 12mm m.s. 0


reinforcing bards in Foundations for Security
Walls and Gate Columns.

kg.

Ditto, 10mm in Security Walls and columns.

kg.

Ditto 16mm in Security Walls and Columns.

kg.

Ditto, 12mm in Security Walls and Gate


Columns.

kg.

Ditto 10mm m.s. - as horizontal bars in ditto.

kg.

Ditto 10mm m.s. links in columns.

kg.

Ditto, 10mm - Foundation and stems of


Retaining Walls.

kg.

ITEM

DESCRIPTION

QUANTITY

Retaining Walls, Security Walls "A", "B",


"C" & "D" and Gate Columns Cont'd.
A

Level tops of Retaining Walls, Security Walls


A, B, C & D and Gate Columns with integral
steel floated finish.

m2

Supply and install on top of Security Walls A,


B, C & D, 900mm galvanized razor wire
included galvanized 14 guage pipe Y-arms
cast into tops of insitu portions of walls,
secured by (6) strands of galvanized steel
barbed wires.

Supply and install at expansion joints in


No.
security walls - 20mm thick and 152mm wide x
3.75 high flexcell (or other approved alternative
filler).

Return selected excavated material to backfill m3


on top of foundations to Retaining Walls,
Security Walls A, B, C & D and gate columns compacting in layers not exceeding 250mm
compacted thickness to achieve 95% Proctor
Dry Density.

Dispose of surplus excavated material from


site.

m3

Extra over Item 2/3A for breaking off portions

SUM

of existing wall foundations to facilitate casting


foundations under ends of walls "A" and "D".

UNIT

RATE

Ditto, Item 2/3E for excavating beneath


existing wall foundation to enable casting
column foundations beneath wall foundations.

SUM

ITEM

DESCRIPTION

QTY

UNIT

1048.5

DEMOLITION AND ALTERATION

Demolition and Alterations


A

Carefully demolish damaged concrete wall panels and remove


to spoil heaps , leaving existing foundation in place. Carefully
remove existing galvanized steel Y-members holding razor wire
and store for re-use.

RATE

DESCRIPTION

ITEM

Carried to collection

DEMOLITION AND ALTERATIONS


COLLECTION
Carried from page RW-D1
Demolition and Alterations carried to GS

QTY

UNIT

RATE

DESCRIPTION

ITEM

QTY

UNIT

EXCAVATION AND EARTHWORKS


Excavation and Earthworks

Excavation strip footing commencing at strip site level not


exceeding 1.5m and get out

287.47

Level and compact bottom of foundation excavations and


trenches to receive concrete

282.95

Return fill and ram with selected refused excavated material


around foundation trenches.

158.11

Load up excavated material and cart away from site to a spoil


heap not exceeding457.3m where directed

129.36

39.757

Filling

Approved quality imported marl filling as specified, spread,


levelled and compacted to CBR of 30, in layers not exceeding
150mm thick under the foundation

RATE

ITEM

DESCRIPTION

Carried to collection

QTY

UNIT

RATE

DESCRIPTION

ITEM

DEMOLITION AND ALTERATIONS


COLLECTION
Carried from page RW-D3
Excavation and Earthworks carried to GS

QTY

UNIT

RATE

DESCRIPTION

ITEM

REINFORCED CONCRETE
Reinforced Concrte (1;2:3) 28MPA
A

Supply, mix, place and compact 28 MPA reinforced concrete in


foundation for boundary wall

Ditto for precast boundary wall panel (28MPA)

Steel Reinforcement
Steel reinfoorcment bars cut, tied and erected as specified,
included all coating of steel bars

QTY

UNIT

RATE

AMOUNT

AMOUNT

AMOUNT

AMOUNT

AMOUNT

AMOUNT

You might also like