Onshore Civil and Buildings (Contract No.

----)
Main Contractor:
Subcontractor:

Project name
ITP for Block works

LOGO OF CLIENT

LOGO OF
ENGINEER

Name of Project

Inspection and Test Plan for Block Works

Rev

Date

001

Date:

Comments

Prepared By

Initial Issue

Noel V. Mades

Page 1 of 3

Reviewed By

Approved By

Inspection and Test Plan Number

Onshore Civil and Buildings (Contract No. ----)


Main Contractor:
Subcontractor:

Project name
ITP for Block works

Inspection & Test Plan


LOGO
OF
ENGR.

Title/Description

Block works

Unit Area: All buildings

Discipline: Block work

Inspection Test Requirements


Activi
ty No.

1
1.1

ITP No. :

LOGO OF COMP.

Rev. 00

Reference Documentation

Verifying Documents
/Demonstrated Evidence
Report Checklist
(Reference Number)

Inspections / Verification

Activity / Description
Test or
Inspection
Performed

Stage/Frequency

Code/Spec/etc

Acceptance Criteria

Contrac
to

Engr.

Employ
er

Approval / Permits/Preliminaries
Preparation of

ITP,

Method Statement

Material Submittals

Drawings

Approval

Prior to Start of
Work

Specification Section
Number

Code 1/ 2

Approved Submittals

Material Inspections (Delivery on Site)

2.1

Materials

Visual

Material Arrival on
Site

Specification Section
Number

Material Receiving Inspection Rep


(MRIR)

2.2

Accessories

Visual

Material Arrival on
Site

Specification Section As per approved Material


Number
Submittals Code 1/2

Material Receiving Inspection Re


(MRIR)

Visual

One Wall Panel


with all required
accessories used

IRF
Method Statement Checklist:
Checklist number

3
3.1

Work Process
Prior to Start Blockwork

3.1.1

3.2

Mock up

As per approved IRF


Approved Drawings
As per approved shop drawing
Specification Section
All required accessories
Number
included in the mock up

Blocks Laying/ Installation

Date:

Page 2 of 3

Inspection and Test Plan Number

Onshore Civil and Buildings (Contract No. ----)


Main Contractor:
Subcontractor:

3.2.1

3.2.2

3.2.3

3.2.4

4.0

Setting out & Surface


Preparation

First Course

Block layer installation

Final Inspection

As - built Drawings

Project name
ITP for Block works

Visual

Prior to laying of
every first course

Approved Shop
Drawing for Block work
layout

As per approved survey layout


No unsatisfactory condition

Checklist:
Checklist number

Visual

Every 18 bays for


CFS bldg.
For other buildings
every completed
First course

Approved Shop
Drawing for block work
layout

Dimension is correct as per


approved block work layout
drawing

Method Statement
Approved Shop Drawing

Visual

During block laying


works

Approved shop
drawings for block
work layout

Checklist:
Checklist number

Checklist:
Checklist number

Approved As-Built Drawings

Visual

Approval

Every 18 bays for


CFS Bldg.
For other buildings
every completed
First Course

Approved Shop
Drawings block work
layout
Specification Section
Number

Progressively

All accessories required are


installed and verified.
All MEP required
embedment's and openings
are placed and verified
Construction Tolerances:
1. For Vertical lines. Plumb
shall not vary by more than
6mm in 6m height.
2. For vertical alignment of
exposed head joints, do not
vary from plumb by more than
6mm by 3m, nor 12mm max.
3. For horizontal line, do not
vary from level by more than
6mm in 6m, nor 12mm max.
4. For exposed bed joints, do
not vary from thickness by
more than +/- 3mm & adjacent
course with a max. thickness
limited to 12mm.
5. For exposed head joints, do
not vary from thickness by
more than +/- 3mm.

Code 1

Legend: I-Inspection, T-Test, W-Witness Point, H-Mandatory Hold Point for Inspection, R-Document Review, S-Surveillance, E-Execution, RE-Records

Date:

Page 3 of 3

Inspection and Test Plan Number