Professional Documents
Culture Documents
Doc
Doc
CERTIFICATE
(2011 specification)
Candidates observation
sheet
of _____
Observations
Control measures
Timescale
3 days
1 month
2 weeks
1 week
1 month
3 days
3 days
a. Burns
b. Frostbite
c. Explosion / Fire
d. Intoxication
9. Inadequate work supervision while
doing repair of damaged cylinders.
a. Fire / Explosion
b. Skin allergies /dermatitis
c. Death
d. Burns
10. Ignoring Rules and safety signs
(Standards and Company Rules)
a. Product damaged
b. Increase accidents
c. Injury to others
11. Poor construction of landing bay.
a. fall from the ground
b. explosion
12. Exposure to high frequency of noise
during filling of cylinders and the 4
pressure vessels.
a. Hearing loss
b. Speech interference
c. Annoyance
d. Deficiency in concentration
1 week
3 days
6 weeks
3 days
Observations
Control measures
a. Explosion / Fire
b. Death
14. Dangling and unprotected electrical
cable wire in the filling area, passing to
the piping.
a. Electrocution
b. Fire / Explosion / Burns
c. Death
15. Wet floors in the filling of the
acetylene cylinder area.
a. slip / trip and fall
b. hematoma
16. Damaged cylinders are not labelled
and separated.
a.
Human
error,
might
accidentally used for filling
causing personal injury.
17. Pedestrian for people and vehicle
marking are no longer visible.
a. Hit by moving vehicle.
Timescale
2 weeks
2 weeks
1 week
3 days
1 week