Daily 081015

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 40

ifj;kstuk vuqoh{k.

k izdks"B
nSfud izxfr izfrosnu
No. : DGM(PMC)/DPR/2015/0747

Date : 09.10.15

Index

/ HIGHLIGHT OF THE DAY

/ Project Zone

A.

/ Coke Zone

B.

/ Mills Zone

C.

/ Steel Zone

D.

.. / OP Zone

E.

.. ... / SP & OHP Zone

F.

$ & / Blast Furnace Zone

G.

/ Power Zone

H.

.. ... / IATRS Zone

I.

Fabrication and Erection of Structural staircase for Ladle Furnace 1 at SMS III

Award letter issued to M/s Suprabhat Pal, Bhilai on 05.10.15 at the value of Rs. 98684
and completion period 3 months.
Review meeting held on 08.10.15

Instln. of By-Product Plant Complex & its integration with existing facilities for
COB#11 (Pkg. - 003A)

Illumination,Earthing & lighting protection system for SMS-3 (Pkg-127)

*, & /Civil services, Township & Mines Zone

J.

2 / Utility Zone

K.
L.

... / SPU Zone

Review meeting scheduled on 09.10.15

COB-9 Pkg.-8A: Replacement of Ammonia Saturators # 5 & 6 in ASP #2 of CO&CCD

Augmentation of Raw Material receipt & handling facilities with OHP, Part-B (Pkg. 061)

Stage-I approved schemes other than 7.0 MT expansion


Modernization & Expansion of BSP to 7.0 MT

M.

4-( )-...
* -4 ( )
4:

( )
4 -( )-

4 -( )-

4 - 4 ( )-

4 -( )- ... & .

4 - 4 ( )-

4 -( )-...3

4 -( )-2

4-( ) @B

4 -( )-<=-..&...3

* D .

All project reports available at Project Deptts website: Intranet

Depts Websites

. -( )-...

Projects (http://cmmsftp.sail-bhilaisteel.com/projects/index.htm)

ifj;kstuk vuqoh{k.k izdks"B


nSfud izxfr izfrosnu
SN
SCHEME / PACKAGE
A. COKE ZONE
A 1 Coke Oven Battery 11 Proper
(Pkg.-001-SE-01)
A2

Oven Machines & land based


Pushing Emission Control for Battery11 (Pkg. -001-SE-02)
Contract No. TK 2008/279
Consultant MECON

Total

Oven machines put into operation.


PEC system: Eqpt. Erection in progress.

Instln. of By-Product Plant Complex &


its integration with existing facilities
for COB#11 (Pkg. - 003A)
Contract No. TK 2011/344
Consultant MECON
Agency M/s MBE
Contract price - Rs. 353.52 Crs.
Contract signed on: 20.04.11,
Contr. Completion: 19.04.13
Likely completion : Mar16
(Proj. Mgr.- Puneet Sharma, DGM 21776)

Important activities completed / Highlights

BE (A)
BE ( I )
DE (A)
DE ( I )
TOTAL

124
14
125
244
507
Activity

Submtd.

121
26
97
242
486
Unit

Appd/KFR

90
24
87
230
431
Total vol.

AAN

Comntd

U/S

13
0
0
0
13

18
2
8
8
36

0
0
2
4
6
Cum. Prog.

Oct15

Plan

Important activities completed / Highlights

A4

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


PAC issued on 05.12.14 w.e.f 30.09.14.
Commissioning certificate issued on 23.07.15 w.e.f 03.10.14.
Coal charging in Oven started on 29.09.14 & Pushing started on 30.09.14.

Likely completion : Dec15


(Proj. Mgr. Shri U, Bhardwaj, DGM
20184)

Coke Dry Cooling Plant COB-11


(Pkg.-002)

Date : 08.10.15

DAILY PROGRESS REPORT

PROGRESS ON DATE

Agency M/s BEC- KBK


Contract price: Rs. 105.61 Crs.
Contract date : 19.09.08,
Contr. Completion : 18.09.10

A3

PROJECT MONITORING CELL

Review meeting held on 08.10.15.


Processing of Gas from COB#11 in ByProduct Plants - 3 started on 29.09.14.
(Exhauster, ETP, PGC & Decanter running
successfully).
Phase - II
Civil & Structural work in progress.
(Unit 800, 900, DM Plant, Maintenance
bldg.).

Review meeting held on 07.10.15.

Prog.

Mech. Eqpt. Ordering


T
1776
0
0
1776
Elect. Eqpt. Ordering
T
232
0
0
232
Mech. Eqpt. supply
T
1776
30
0
1746
Elect. Eqpt. supply
T
232
15
0
217
Mech. Eqpt. erection
T
1776
40
0
1683
Elect. Eqpt. Erection
T
232
0
0
139
Part PAC (for all oven machines) issued on 05.12.14 w.e.f 29.09.14.
PAC issued on 26.03.15 w.e.f 23.02.15.
Review meeting held on 07.10.15.
Hot Coke charging with module 3&4 started on 14.10.14, with Module
no-2 started on 22.10.14 & with module -1 started on 23.02.15.
Drawings
Total
Submtd.
Appd
AAN
Comntd
U/S
Review meeting held on 08.10.15.
BE (A)
106
BE I
76
DE (A)
624
DE I
1067
1873
TOTAL
Activity

112
73
681
1224
2090*
Unit

110
72
667
1214
2063
Total vol.

2
0
3
0
5

0
1
9
9
19
Oct15

Plan

0
0
2
1
3
Cum. Prog.

Prog.

Earthwork
M3
84000
500
0
81500
Concreting
M3
30200
198
0
29432
Structure supply
T
2250
4
0
2240
0
Structure erection
T
2250
25
2124
Mech. Eqpt. supply
T
8200
0
0
8116
Elect. Eqpt. supply
T
1500
0
0
1480
*- Includes additional drgs. as per
Mech. Eqpt. erection
T
8200
344
18
7401
MECON.
Elect. Eqpt. erection
T
1500
8
0
1426
Part PAC issued on 14.04.15 w.e.f 12.01.15.
Part Commissioning certificate issued on 27.08.15 w.e.f. 20.07.15.
Processing of Gas from COB#11 in By-Product Plant - 3 started on
29.09.14. (Exhauster, ETP, PGC & Decanter running successfully). Ordering
(Mech.-8200 T & Elect.-1500 T) completed.

10/9/2015

Page : 2

SN

SCHEME / PACKAGE

A 5 Instn. of Phenolic Effluent Treatment


Plant for COB-11 (Pkg. 003C)
Contract No. TK 2010/314
Consultant MECON
Agency UEM
Contract price - Rs. 21.19 Crs.
Contract signed on : 25.06.10,
Contr. Completion: 24.06.11,
Likely completion: Dec15
(Proj. Mgr. - Puneet Sharma, DGM 21776)

A 6 Installation of New Coal Handling


Plant (Pkg. 062)
Contract No. TK 2008/280
Consultant MECON
Agency HEC
Contract price: Rs. 463.8 Crs.
Contract signed on 20.09.08,
Contr. Completion : 19.03.11
Likely completion: Mar16
(Proj. Mgr. K Dikshitulu, DGM, 20403)

PROGRESS ON DATE

COMMITMENT AS PER LATEST


MOM

OVERALL STATUS AS ON DATE

Review meeting scheduled on 27.10.15.

Drawings

Total

Submtd.

Appd/KFR

AAN

Comntd

U/S

Nitrification tank II:


R&S for Wall in progress.

BE (A)
BE ( I )
DE (A)
DE ( I )
TOTAL
Activity

19
8
120
82
229

19
10
168
75
272*

16
7
144
60
227

0
1
11
10
22

2
2
6
1
11

1
0
7
4
12

Road & Drain work in progress.

7 M3 Concreting completed.
New Silos (CDI - 2 nos. & Boiler - 2 nos.):
Eqpt. erection in progress.
Stacker cum reclaimer 5,6,7:
Eqpt. erection in progress.
Wagon Tippler:
Elect. Eqpt. erection in progress.

Unit

Total vol.
Plan

Oct15
Prog.

Review meeting held on


19.09.15.

Cum. Prog.

Earthwork
M3
30000
1000
0
22800
Concreting
M3
10050
250
0
9700
*-Includes addition drgs.
Strl. supply
T
190
0
0
190
Strl. Erection
T
190
0
0
190
Mech. Eqpt. Ordering
T
509
0
0
459
Elect. Eqpt. Ordering
T
173
0
0
173
Mech. Eqpt. supply
T
509
2
2
459
Elect. Eqpt. supply
T
173
0
0
170
Mech. Eqpt. erection
T
509
0
0
459
Elect. Eqpt. erection
T
173
0
0
126
Nitrification tank I: Part commissioning activity completed on
29.11.14.Nitrification tank II: Raft concreting completed during 24 08.15 28.08.15.
Drawings
Total
Submtd
Appd/KFR
AAN
Comntd
U/S
Review meeting held on
BE (A)
145
145
142
0
2
1
06.10.15.
BE I
DE (A)
DE I
TOTAL
Activity

4
661
413
1223

4
661
413
1223

4
647
409
1202

Unit

0
0
0
0

Total vol.
Plan

M3

0
10
4
16

Oct15
Prog.

0
4
0
5

Cum. Prog.

Earthwork
250000
5000
0
242000
M3
Concreting
#52000
380
43
50443
T
Strl. supply
8070
50
0
7744
T
#- Scope revised.
Strl. Erection
8070
100
12
7484
T
Mech.Eqpt. ordering
7500
7
0
7493
T
Elect Eqpt. Ordering
2500
0
0
2500
T
Mech. Eqpt. Supply
7500
205
0
6593
T
Elec. Eqpt. Supply
2500
15
0
2478
T
Mech. Eqpt. Erection
7500
470
0
5700
T
Elec. Eqpt. Erection
2500
300
0
810
Part PAC issued on 19.03.15 (for Dispatcher Building D2, 15 nos. APDs).
SCR- 5, 6, 7: Eqpt. erection in progress
New Silo (CDI - 2 nos. & Boiler - 2 nos.): Eqpt. erection in progress..Wagon
Tippler#4: Mech. Eqpt. erection completed.
SCR-3, 4: Trial run with load completed by 22.07.15.

10/9/2015

Page : 3

SN

A7

SCHEME / PACKAGE
Augmentation of Fuel & Flux Crushing &
Screening Facilities (Pkg. 064)
Contr. No. TK 2011/337
Consultant MECON
Agency M/s EPI
Contract price Rs. 272.65 Crs.
Contract signed on: 15.02.11,
Contr. Completion: 14.12.12,
Likely completion Mar16
(Proj. Mgr.- A P Barnwal, DGM, 20131)

PROGRESS ON DATE

CHP Area:
Civil work for LTSS-1,Final crushing
station, Bldg. in progress.
Str. work for Y11-200 in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd.

Appd/KFR

AAN

Comntd

U/S

BE (A)
BE ( I )
DE (A)
DE ( I )
TOTAL

304
40
362
900
1606

266
38
455
520
1279

236
18
330
472
1056

10
0
42
0
52

16
19
56
14
105

4
1
27
34
66

Plan

Oct15
Prog.

Activity

Unit

Total vol.

Review meeting held on 05.10.15.

Cum. Prog.

CSP Area :
Emergency coke yard: Eqpt. Erection in
progress.
Civil work for LTSS #2, 3 in progress.
Structural work of JH Z -17 in progress.
Fuel & Flux area: Civil work for LTSS #4, 5 in
progress.

M3
Earthwork
#85000
3500
0
81000
M3
Concreting
#16000
600
130
13760
Structure supply
T
7250
250
10
4340
# - Scope revised
Structure Erection
T
7250
250
12
3263
Mech. Eqpt. ordering
T
2522
200
0
2186
Elect Eqpt. Ordering
T
526
0
0
210
Mech. Eqpt. supply
T
2522
100
38
1520
Elect Eqpt. supply
T
526
30
20
186
Mech. Eqpt. erection
T
2522
30
3
425
Elect Eqpt. erection
T
526
30
0
91
Important activities completed / Highlights
C-line conveyor: Integrated load trial run of new C-line conveyor taken
on 07.11.13. CHP area: Civil work for Final crushing station ,LTSS-1 Bldg. &
Str. work for Conveyor Y11-200 in progress. Coal feeding in Coal Tower
started on 27.09.14.
CSP area: Trial run of Conveyor K11-9B & K11-10B completed.
Emergency coke yard: Eqpt. Erection in progress.
Civil work for LTSS #2, 3 in progress. Structural work of JH Z -17 in
progress.Fuel & Flux area: Civil work for LTSS #4, 5 in progress.
A 8 Cold repair of Coke Oven Battery no. -9 of CO & CCD (Stage-II approved on 04.08.12) completion: 25 months, Approved cost: Rs. 332.65 Crs. (Consultant CET)
Pkg.-1: Battery Proper
Review meeting scheduled on 16.10.15. Erection of All 136 nos. Flash plate completed on 31.01.15.
Review meeting held on 22.09.15.
Contract No. TK 2012/ 365 Agency MECON
Erection of Door frame completed on 02.07.15.
Contract price - Rs. 150.09 Crs.
Temporary Heating in progress.
All 136 nos. WHB assembly erected by 21.07.15..
Contract signed on : 29.08.12,
All 136 nos. Buckstay erected by 02.04.15.
Contr. Completion: 28.08.14,
Quenching Tower: Civil & Structural work in Erection of temporary tie rods & charging hole completed.
Likely completion Oct15
progress.
Major Refractory erection for Battery proper completed on 13.03.15.
(Proj. Mgr. D K Dewangan, DGM,20134)
Eqpt. Erection in progress.
Chimney Heating started on 22.06.15.
Wharf: Civil work in progress.
Temporary Heating started on 28.08.15.
Pkg.-4: Instrumentation & Automation
Review meeting scheduled on 15.10.15. All 13 nos. BE drgs. & 49 out of 50 nos. DE drgs. Submitted.
Review meeting held on 23.09.15.
Contract No. TK 2012/ 374
Equipment erection in progress.
Agency M/s Instrumentation Ltd.
Equipment erection in progress.
Contract price - Rs. 4.43 Crs.
Contract signed : 18.10.12, Contr. Completion:
17.06.14, Likely completion Oct15
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-5: Electrics & Drive Automation


Contract No. TK 2013/376 Agency M/s
Sterling & Wilson Contract price - Rs. 6.93 Crs.
Contract signed : 12.02.13, Contr. Completion:
11.08.14, Likely completion Oct15
(Proj. Mgr. D K Dewangan, DGM,20134)

Review meeting scheduled on 14.10.15.

All 21 nos. BE drgs. & 87 out of 89 nos. DE drgs. submitted.


Equipment erection in progress.

Equipment erection in progress.

10/9/2015

Page : 4

Review meeting held on 24.09.15.

SN

A8

COMMITMENT AS PER LATEST MOM


PROGRESS ON DATE
OVERALL STATUS AS ON DATE
SCHEME / PACKAGE
Cold repair of Coke Oven Battery no. -9 of CO & CCD (Stage-II approved on 04.08.12) Completion: 25 months, Approved cost: Rs. 332.65 Crs. (Consultant CET)
Pkg.-6: Oven Machines
Review meeting scheduled on 13.10.15. All 44 nos. BE drgs. & 251 out of 256 nos. DE drgs. Submitted.
Review meeting held on 15.09.15.
Contract No. TK 2012/ 367Agency M/s BEC- CUI
Charging cars, Locos and Pusher car, Guide cars supplied.
Contract price - Rs. 64.08 Crs. & Euro 5000
Erection of 1st Charging car started on 02.05.15 & 2nd Charging car
Contract signed on : 03.09.12,
Erection of Both Charging car, Electric
on 15.07.15. Erection of 1st Guide car started on 04.08.15.
Contr. Completion: 02.05.14,
Locos, 1 no. guide car & Pusher car in
Erection of Electric Locos started on 19.05.15.
Likely completion Oct15
progress.
(Mechanical eqpt. Erection of both locos completed in May15)
(Proj. Mgr. D K Dewangan, DGM,20134)
Erection of Pusher car started on 27.05.15.
Pkg.-7: Expert Supervision during erection &
Refractory Expert deputed by M/s CUI at site from 29.07.13.
commissioning of 7 MT tall battery
Contract No. TK 2012/375
Agency M/s CUI Contract
price USD 766800, Contract signed : 07.11.12, Contr.
Completion: 06.02.15, Likely completion Oct15
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-8A:
Replacement
of
Ammonia Review meeting scheduled on 09.10.15.
Saturators # 5 & 6 in ASP #2 of CO&CCD
Contract No. TK 2012/364 Agency Beekay
Contract price - Rs. 5.40 Crs.
Contract signed on : 22.08.12 Cont Completion: 21.08.14,
Likely completion Oct15
(Proj. Mgr. D K Dewangan, DGM,20134)

All 45 nos. DE drgs. submitted.


Erection of 1st saturator started on 24.02.15.
Major supply of Both Saturators completed.

Review meeting held on 14.09.15.

All 31 nos. BE drgs. and all 78 nos. DE drgs. submitted.


ETP#8: All work completed.
PGC#1-4: Mech. Eqpt. Erection completed.

Review meeting held on 21.09.15.

PAC issued on 05.10.15 w.e.f. 06.08.15.

Review meeting held on 18.09.15.

Erection of 1st saturator is in progress.

Pkg.-8B: Re-tubing of PGC#1-4, Replacement


of ETP#8 in Gas Cleaning Plant #2

Review meeting scheduled on 19.10.15.

Contract No. TK 2012/ 372


Agency Bhilai Techneeds& Technovation
Contract price - Rs. 15.53 Crs.
Contract signed on : 26.09.12,
Contr. Completion: 25.06.14, Likely completion Oct15
(Proj. Mgr. D K Dewangan, DGM,20134)

PGC#1-4:
Gas Pipe line testing in progress .

Pkg.-8C: Replacement of Circular Tar Review meeting scheduled on 26.10.15.


Decanter #9 in CCD#2 Contract price - Rs. 2.08 Crs.
Contract No. TK 2012/ 368 Agency Bengal Tools.
Contract signed on : 05.09.12,
Contr. Completion: 04.12.13, Likely completion Oct15
(Proj. Mgr. D K Dewangan, DGM,20134)

Pkg.-8D: Repl. of Contaminated Water Cooling


Tower of Final Gas Coolers of BRP #2

A9

Contract price - Rs. 1.26 Crs.


Contract signed on : 11.09.12, Agency Koolaqua
Contract No. TK 2012/ 370, Contr. Completion:
10.12.13, (Proj. Mgr. D K Dewangan, DGM,20134)
Replacement of Benzol and Separating Columns
of Old Stream in Benzol Distillation Plant of CCD # 1
Contract no . TK- 2012/369
Consultant CET Agency : M/s Nuberg
Cost : Rs. 3.44 Crs. Contract Signed : 07.09.12
Cont. Completion : 06.09.13
(Proj. Mgr.- P Sharma, DGM -21776)

PAC issued on 24.03.15 w.e.f 18.03.15.


Commissioning certificate issued on 14.08.15 w.e.f. 30.06.15.

Major work completed & put into operation on 24.04.15.


PAC issued on 18.09.15 w.e.f. 24.07.15.

10/9/2015

Page : 5

SN
SCHEME / PACKAGE
B. MILLS ZONE
B 1 Civil works for Bar & Rod Mill
(Pkg-051A-01) (Works Pkg.)

Consultant-MECON
Agency: M/s HSCL
Contract Price: Rs 123.93 Crs.
Contract signed on : 30.12.10
Completion period : 29.08.12
Likely Completion: Oct.15
(Proj. Mgr. A K Singh, AGM) 21014

B2

Structural works for Bar & Rod Mill


(Pkg-051B-01)
Consultant-MECON
Agency: M/s HSCL
Contract price: Rs. 54.26 Crs.
Eff. dt. of Cont. : 07.09.10,
Cont. signed on : 16.09.10
Cont. Completion: 06.05.12
Likely compln: Oct.15
(Proj. Mgr. Ajay Kumar, DGM) 21772

PROGRESS ON DATE

Earthwork for flooring & drain in progress.


Civil work for Chiller Bldg. in progress.
Wall casting (R & S for slab at 4.3 m) in
Water Sump area of Pumphouse in
progress.
EW and R& S for pump foundation at 0-0
m level in Pump area of Pumphouse in
progress.
Waterproofing and anti-skid work in ECR
slabs, cable tunnel, pipe tunnel in Furnace
ECR, ECRs-1 & 2, Flooring for oil cellar in
Block-2 & ECR-3, CD Bay, Brickwork &
plaster for Welfare bldg. & final roof lift for
O/h tank above 23 m up to 25 m in
progress.
Finishing & Flooring work in Mill area (AB,
BC and CD bay of all Blocks) in progress.
5 M3 Concreting (done.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Concreting for Main Bldg. Column fd/ns (190 nos.) completed on 25.07.14.
Welfare Bldg. RCC work completed on 28.12.13.
Activity

Unit

M3
M3

Earthwork
Concreting

Total Scope
(*- Revised)

Plan

Oct.15
Prog.

325000 *
87000 $

3430
2500

200
321

Cum. Prog.

321770
85240 #

$ - Revised Scope as informed by Zone


# - RCC Figures reported by Zone after reconciliation

Casting for Chimney, Flue duct & Furnace proper completed.


ECRs-1, 2,3 & Furnace ECR RCC work completed.
Work Roll shop RCC work completed on 10.06.14.
Slab at 5.0 m of BC Bay b/w Columns 3 to 23 (Furnace Exit area, Roughing,
Intermediate, Finishing mill & Finishing Block exit area) cast.
Cooling Bed and Bar lineRCC work completed.
Civil work for all Transformers foundations in all ECRs completed.
RCC work for Product Forming area, Coil Storage area and Cut length
area completed. RCC work for MCC room (Block-1) completed.
RCC for coil evacuation area 98 % comp., balance is cable trench.
RCC work for Rail track parallel to A row of Blocks-3 & 4 completed and for
rail track parallel to D row 99 % completed.
Earthwork for Scale pit started on 03.03.15 & completed on 28.05.15.
Drgs. issued:
Raft casting for Pumphouse started on 16.06.15 and completed for Water
Concreting 88123 M3
Sump area, wall casting is in progress.
Raft casting for Chiller Bldg comp. on 19.06.15. Slab at 5 M cast on 07.10.15.
Fabrication & erection of strs. incl. sheeting Cum. 18360 T steel collected by M/s HSCL for both the pkgs (incl. 955 T for 27th Review Meeting held
in Axis-X, Y & Z, Blocks-1 to 4 in progress.
sheets). Assembly of all 190 columns & 242 Crane Girders (related to Axis X, on 14.02.13.
2 T Strs. fabricated and 3 T Strs. erected.
Y & Z and Blocks-1 to 4) completed. Cum. 186 out of 190 Columns & 237
out of 242 Crane girders (related to Axis X, Y & Z and Blocks-1 to 4) erected.
Erection of roof truss completed except for 4 columns in X, Y & Z axis.
Activity
Unit
Oct.15
Cum. Prog.
Total Scope
Status of Drgs.:
Plan
Prog.
(*- Revised)
DE drgs Approved by MECON 15148 T
Strl. Fabrication
T
8500 *
8500
# - Structure erection data
(combined for both the pkgs.)
Strl. erection
T
8500 *
0
0
8253
reconciled by Zone on
Scope increased to 13500 T by MECON, awarded in Octarate pkg. no. (051-B- 30.11.14.
1A), further scope increased to 14200 T and further increased to 15500 T.

B3

Additional Structural Works of BRM


(Pkg No. 051-B-1A) Consultant MECON

Agency: M/s HSCL

26th Review Meeting held


on 14.02.13.

Pkg. covers fabrication & erection of structures for Block-3 (partly) and
Block-4 (complete). ie. from Axis- 29 to 47.
Activity

Unit

Total Scope

Oct.15
Plan
Prog.

Cum.
Prog.

Awarded on : 24.11.12,
Contract signed on 15.02.13
Award value: Rs. 47.11 Crs.
Contr. Completion: 23.05.13

Strl. fabrication

7000 *

200

6390

Likely compln: Oct.15

Strl. erection

7000 *

500

16.5

5495.5

(*- Revised)

(Proj. Mgr. Ajay Kumar, DGM) 21772

10/9/2015

Page : 6

SN

B4

B5

SCHEME / PACKAGE

PROGRESS ON DATE

Reheating Furnaces for Bar & Rod Mill Design Engg., ordering, supply &
(Pkg.-049-1)
erection of eqpts. in progress.
Contract No.- TK/2011/335
Rod bending and shuttering for
Consultant - MECON
Concreting of basin of Cooling tower
Agency: M/s Fives Stein, Spain
at 7.4 M level in progress.
Fives Stein, India Beekay
Alignment of all Roller tables & of
Contract price: Rs. 54.23 Crs.
Furnace actuator without damper
Cont. signed on : 09.02.11
completed.
Cont. Completion: 08.11.12
Erection of Elect.eqpts. restarted on
Likely compln: Oct.15
21.04.15 and in progress.
(Proj. Mgr. J Gopi Krishnan, DGM)
21151

Installation of Bar & Rod Mill (Pkg.-046) Shifting, placement and erection of
Contract No.- TK/2010/323
equipments in Rolling Mill area, Rolling
Consultant - MECON
Mill exit area, Cooling bed area,
Agency: M/s Danieli & C SpA, ItalyCutting to length area, Product
Danieli India, Kolkata - Beekay
Forming area, Product Collecting area,
Contract price: Rs. 406.09 Crs.
Hyd. Cellars, Oil Cellars, etc in progress.
Cont. Signed on : 25.08.10
Elect. Erection work (on-field cable
Cont. Completion : 24.08.12
tray work in BC bay, cable laying from
Likely Completion : Oct.15
Switchgear to ECR-1, bus duct erection
(Proj. Mgr. - K D Prasad, DGM) 22183
in ECR-3) in progress.
Testing of balc 9 transformers of ECR-1
almost completed, oil filtration i/p.
2 T Mech. eqpts. & 0.5 T Elect. eqpts.
erected.

COMMITMENT AS PER LATEST


MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd

Appd/KFR

AAN

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

74
211
241
287
813

71
210
227
280
788

67
204
215
270
756

0
0
4
0
4

Unit

Total Scope
(*- Revised)

Activity

Comtd.

U/S

4
6
8
10
28

0
0
0
0
0

Oct.15

Plan

Cum. Prog.
Prog.

Concreting
M3
324
50
0
182
Mech. Eqpt. (Imp.)Supply
T
62*
Comp.
Elect. Eqpt. (Imp.) Supply
T
7*
0
0
6.5
Mech. Eqpt. (Ind.) Supply
T
1048*
0
0
1040
Elect. Eqpt. (Ind.) Supply
T
195*
0
0
167
Refractory (Imp.) Supply
T
190*
0
0
Comp.
Refractory (Ind.) Supply
1090*
0
0
561
Mech. Eqpt. Erection
T
1110*
10
0
858
Elect. Eqpt. Erection
T
202*
30
0
82.5
Erection of lifting frame assly., Chimney & lateral wall of Furnace completed & of
Flue duct 96 % completed Erection of all burners & roof beam of Furnace Proper
completed. Alignment of Skid & posts, Charge wall & DA fan completed. All
Imported Refractory received at site on 07.09.15. Pressure testing of indirect
cooling water piping for Furnace completed on 14.09.15.
Drawings

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Submtd

36
231
268
1280
1815

Appd/KFR

36
231
268
1280
1815

Activity

Unit

AAN

35
231
268
1279
1813

0
0
0
0
0

Total
Scope

Plan

Comntd

1
0
0
1
2
Oct.15

U/S

0
0
0
0
0

T
2300*
10
0
T
1857
0
0
T
1650
2
0
T
5500*
220
13
T
1824
30
3
Charging of Transformers in ECR-1 started on 05.09.15, 9 out of 18 charged.
Mech. Eqpt(Ind.) SupplyM/s Beekay
Mech. Eqpt. (Ind.) Supply M/S DIL
Elect. Eqpt. (Ind.) Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Ordering of all 190 T


Refactory (Imp.) & all
1090 T Refractory (Indig.)
completed.
9th Review meeting held
on 03.10.13.

2290
1069 #
1648
2869.5
1386.5

# - 788 T 1st Fill Oil

Ordering & supply of All


Imported Eqpts.(Mech. 1343 T & Elect. -174 T)
completed.Ordering of
All
4157
T
Mech
Testing of transformers of ECR-1 started on 10.8.15 and testing/charging in progress.
Eqpt.(Indig.) & All 1650 T
PCC and MCC erection in ECRs-1 & 2 (at 5 m and 16 m) & in ECR-3 (at 0 m) completed. Elect.
Eqpt.(Indig.)
HT cable laying from Switchgear to Primary side of transformers in ECR-1 completed. All
completed.

Diversion of Nallah passing through Concreting for slab of Manhole no.-17 Laying/jointing of pipes for manholes nos. 5 to 9 & 11 to 24 completed.
Universal Rail Mill layout (Pkg-118 S)
Activity
Unit
Total
Oct.15
completed on 30.09.15.
Agency-M/s Kulkarni & Sahu Buildcon
Contract price: Rs 9.68 Crs.
Cont. Signed on: 09.02.12
Completion period : 02.06.12
Likely Completion : Nov.15
(Proj. Mgr. - A S P Sarma, DGM) 22187

# Ordering of all 62 T
Mech. Eqpt. (Imp.) , all
1048 T Mech. Eqpt.
(Indig.), all 195 T Elect.
Eqpt. (Indig.) & all 7 T
Elect. Eqpt. (Imp.)
completed.

Cum. Prog.
Prog.

18 Transformers of ECR-1, 12 transformers of ECR-2 & 6 Transformers of ECR-3 erected.


Cable tray work in ECRs-1 & 2 and connecting tunnel completed.
Erection of eqpts. of Charging area, Furnace entry & exit area completed.

B6

15th Review meeting held


on 11.12.14.

Earthwork
Concreting
Supply of RCC Pipes
Laying/jointing of Pipes

10/9/2015

Page : 7

M3
M3
RM
RM

Scope

Plan

42000
9500
2450
2450

0
200
25
25

Prog.

0
0
0
0

Cum.
Prog.

39200
5320
1900
1900

SN

B7

SCHEME / PACKAGE
Civil works for Universal Rail Mill
(Pkg-052A) (Works Pkg.)
Consultant-MECON
Agency: M/s HSCL
Contract price: Rs. 289.51 Crs.
Eff. dt. of Cont. : 07.09.10,
Cont. signed on : 15.09.10
Cont. Completion: 06.03.12
Likely compln: Dec.15
(Proj. Mgr. A S P Sarma, DGM)
22187

B8

Strl. Works for Universal Rail Mill


(Pkg-052B) (Works Pkg.)
Consultant-MECON
Agency: M/s HSCL
Contract price: Rs 200.02 Crs.
Cont. signed on : 10.12.10
Completion period : 09.08.12
Likely compln: Nov.15
(Proj. Mgr. J P Pandey, DGM)
22171

B9

OVERALL STATUS AS ON DATE


Cum. 321 nos. Main Shop Bldg. fdns of Blocks-1 to 7 cast up to bolt lift (at -1 M level). Civil work
for ECR-1 to 4, 6 including Furnace ECR completed RCC work of ECR-5 85 % completed. Brick
work & plaster for ECR- 7 & 8 comp. Eqpt. fdn. of Areas-1 to 19, 24 to 35, 42, 44 to 47 comp & in
progress for Areas-36 to 39 & 43. RCC work for MVSWG room and Eqpt fd/n for all 4 CNC Lathe
M/cs completed. Piling work for Drop test area completed. Drain work parallel to D & E row in
progress.Welfare Bldg. Wing -1, 2 & 3 RCC work completed, Finishing work i/p.RCC work of
Cooling Bed-1 (14 to 19) completed on 11.07.14. Raft & wall casting in CB-2 completed
Overhead water tank RCC work completed Furnace Conc. for Furnace proper & Chimney
completed Slab for flue tunnel roof cover cast on 03.03.14.
RWL-: RCC, flooring & rail fixing work for DT, FT &TT completed RCC, finishing & flooring work for
all bldgs.{Brushing Bldg, Grinding & Drilling Bldgs.-7,8,9, Grinding Bldg. 10 Feeding Control Bldg.
6, Welding Bldg, Finishing, Transfer & S/s Bldgs.} completed. Drain and apron work in progress.
Oct.15
Activity
Unit
Total Scope
Cum. Prog
Plan
Prog.
(*- Revised)

Earthwork
Concreting (#)

M3
M3

500000*
230000 $

6000

493

& erection for Blocks-1 to 7 (Cols, CGs, roof truss, girders,


lighting walkway, staircase, etc) i/p.

Cum. 58 nos. long trusses (45 m) at BC bay erected.


5 T Strs. fabricated & 5 T Strs. erected.

27th Review Meeting


held on 14.02.13.

500000
207046 #

$ - Revised Scope as informed by Zone # - RCC Figures reported by Zone after reconciliation

Strl. Fabrication for roof truss, supports & lighting walkway Cum. 32148 T steel collected by M/s HSCL. Strl. fabrication for Cols. & CGs for Blks-1 to 7 completed.
Assembly of all 342 columns & all 466 Crane Girders completed.
Cum. all 342 columns & 466 Crane girders erected.
342 Cols (Blk-152 nos,Blk-242 nos, Blk-355 nos, Blk-459 nos,Blk-545 nos,Blk-644 nos,Blk-7-45 nos)

26 th Review Meeting
held on 14.02.13.

466 CGs(Blk-1- 70 nos, Blk-2- 54 nos, Blk-3 76 nos, Blk-4- 86 nos,Blk-562 nos,Blk-660 nos &Blk-7-58 nos)

Cum. 481 out of 494 nos. Roof truss erected. 2 no. Long Crane girders at Blk-5 (A row) & 4 no. Long
Crane girders Blk-7 (B, B row) of 36 m erected. Erection of 58 long trusses (45 m) completed by
BE drgs. (Scope) 30000 T (Blk-1-4497 T, Blk-2-3354 T, Blk-3-4441 May.15. 1 no. long Roof girder at AB bay of Block-7 erected.

Status of Drgs. :-

Activity

T,Blk-44415 T,Blk-54271 T, Blk-64500 T, Blk-73600 T, Misc922 T)

BE drgs Released by MECON 29898 T


DE drgs Submitted by M/s HSCL - 30336 T
DE drgs Approved by MECON 30336 T
Reheating
Furnaces
for Design Engg., ordering, supply and erection of
Universal Rail Mill
Mech. and Elect. Eqpts. (cable laying for CA fan,
(Pkg. 049-3)
cable laying from Pumphouse MCC to cable tray
Contract no. TK/ 2011 / 346
support work, erection/ earthing of Isolator,
Consultant - MECON
busduct, PLC & LCSS, transformer, VFD panels,
Agency M/s Gillander Arbuthnot
etc) in progress.
(MICCO), Kolkata AndritzBric

Piping work for mixed gas started on 01.02.14 and


MontInc, USA &BricMont, India)
in progress.
Contract price: Rs. 75.81 Crs.
Concreting for column lift at and above 12m in
Contract Signed on: 13.07.11
Cooling tower area in progress.
Cont. Completion: 12.04.13
Erection of Indigenous refractory in Combustion
Likely Completion : Oct.15
air pipe & in Furnace Proper area in progress.
(Proj. Mgr.-T B Kulkarni, AGM)
21013
Erection of eqpts. in Pumphouse started on
02.02.15 and in progress.
2 T Mech. eqpts. erected.
10 T Refractory erected.

Imp. activities completed/ Highlights

COMMITMENT AS PER LATEST MOM

PROGRESS ON DATE

Concreting for Col. fdns. in URM {Areas-36,37, 38,


39, 43}, ECR-5 (RCC work), Drain work parallel to
D & E row, Rail Welding Line {Apron, drain in
various area in progress).
Ramp in Finishing Bldg completed, Screeding in
Grinding Bldg. 7 to 9 completed.
Garland drain of different bldgs. of RWL i/p.
Concreting for railway track for Axis -1 to 20
completed and in progress for Axis 54 to 82.
Civil work for Chiller Bldg. 80 % comp., balc i/p.
RCC work of ECR-5 in progress.
Flooring work in various Areas in progress.
142 M3 Concreting completed.
Drgs. issued: Concreting 2,30,000 M3

Unit

Structural fabrication
Structural erection
Drawings

Total

50
40
240
954
1284

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Activity

Oct.15

Total Scope
(*- Revised)

Plan

Prog.

Cum.
Prog.

T
T

30513 $
30513 $

380
1500

22
30

30155
28013

Submtd.

Appd/KFR

AAN

Comtd.

U/S

50
40
238
930
1258

49
39
222
912
1222

0
1
3
8
12

1
0
9
10
20

0
0
4
0
4

Total Scope
Oct.15
Cum.
(*-Revised)
Prog.
Plan
Prog.
Concreting (incl. precast slabs)
M3
475*
34
0
441
Elect. Eqpt. (Ind.) Ordering
T
170*
6
0
164
Refractories (Indig.) Supply
T
1520 $
20
0
1500 $
Refractories (Imp.) Supply
T
325 $
0
0
Comp.
Mech. Eqpt. (Imp.) Supply
T
190
26
0
164
Mech. Eqpt. (Ind.) Supply
T
1800*
20
0
1780
Elect. Eqpt. (Imp.) Supply
T
5
3.5
0
1.5
Elect. Eqpt. (Ind.) Supply
T
170*
36
0
134
Mech. Eqpt. Erection
T
1990*
150
5
1646
Elect. Eqpt. Erection
T
175
20
5
114
Refractories Erection
T
1845
400
41
1181
Column lift in CT at 12 m i/p. Erection of moving ducts, Flue tunnel & Chimney comp.
Erection of ref. in Combustion air pipe started on 19.11.14 & in Furnace Proper started
on 19.03.15. Alignment of moving skids & welding for fixed skids completed. Erection of
Indigenous refractory in Chimney area comp. & for flue tunnel 98% completed. Supply
of Elect. (Imp.) eqpts. started on 10.07.15. Supply of Imported refractory started on
06.08.15 and completed on 19.09.15. Erection of Indigenous refractory in Unfired Zone
of Furnace Proper area completed on 19.09.15.

10/9/2015

Page : 8

$ - Revised Scope
informed by Zone

as

12th Review meeting held


during 02.04-03.04.15.

Unit

$ - Excluding spares
Ordering of all 190 T Mech
Eqpt.(Imp.). all 1800 T
Mech Eqpt.(Indig.), all 5 T
Elect.
Eqpt.(Imp.),
completed.
Ordering of all 325 T Imp.
Refractory and 1520 T
Indig.
Refractory
completed.

SN

SCHEME / PACKAGE
B 10 Installation of Universal Rail Mill
(Pkg.-047)
Contract No. - TK/2010/322
Consultant - MECON
Agency - M/s SMS Meer GmbH,
Germany - SMS Meer India,
Kolkata -ABB, Bangalore
Contract price: Rs. 1174.46 Crs.
Contract Signed on: 23.08.10
Cont. Completion: 22.06.13
Likely Completion : Oct.15
(Proj. Mgr. -B K Dey, DGM) 20008

PROGRESS ON DATE
Erection & alignment of Mech. eqpts. in
various areas (Areas- 1 to 12, 14 to 19, 24
to 34) in progress.
Grouting of major eqpts. of Areas -1 to 9 &
Area-24 completed and in progress for
Areas 14 to 19 & 20 to 27.
Erection of Elect. eqpts. (RTDB, MCC
panel, LTSS, bus duct erection in ECR-2 &3,
cable laying, cable tray work in various
areas, HT cable laying up to ECR-3) in
progress.
Motor testing work of Area-1 (except
megger test for cable) and of Area-4 & 5
comp., of Areas-6 & panel wiring of LV
drive-1 i/p,
Testing work & other jobs for charging of
LTSS-13 in ECR-1 in progress.

2 T Elect. eqpts. erected.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd.

Appd/KFR

AAN

Comtd.

U/S

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

285
321
685
169

285
320
680
158

264
317
629
151

15
3
32
1

6
0
19
3

0
0
0
3

1460

1443
Unit

1361
Total
Scope
1808
6750*
5800
163
1808
12550
1971

51

Activity
Elect. Eqpt. (Ind.) Ordering
Mech. Eqpt. (Imp.) Supply
Mech. Eqpt. (Ind.) Supply
Elect. Eqpt. (Imp.) Supply
Elect. Eqpt. (Ind.) Supply
Mech. Eqpt. erection
Elect. Eqpt. erection

T
T
T
T
T
T
T

28
Oct.15

Plan
28
0
550
66
1000
60

Prog.
28
0
0
0
26
12

3
Cum. Prog.
1808
6750
5250
Completed
1742
6709
1237

Erection activities of Areas- 1 to 12, 14 to 19, 24 to 34, Hyd. Cellars and Oil cellars i/p. Erection of
Housing in all Mill Stands completed. Placement of eqpts. in 1st module of Cooling Bed area
completed on 31.07.15. Erection of Cold Carbide saw started on 14.09.15 Bus duct erection &
HT cable laying in ECR- 3 and grid earthing in ECR-2, LCSS and panel erection in ECR-3 i/p. One
Transformer of LTSS-13 of ECR-1 charged on 12.09.15 & another on 14.09.15.

B 11 Installation of Rail Welding Line for Parameters


setting
of
Welding Drawings
Basic Engg. (A)
Long Rails (Pkg.-121)
machine for approval of RDSO i/p.
Contract no. TK/ 2011 / 338
Testing
and
automation
work Basic Engg. (I)
Detail Engg. (A)
Consultant - MECON
completed in Transfer and Delivery Detail Engg. (I)
Agency M/s Railtech International,
Telpher area and in progress for TOTAL
France - Maco Corp., Kolkata
Activity
Feeding Telpher area.
Contract price: Rs. 263.16 Crs.
Testing/trial of Telpher systems & motors
Contract Signed on: 18.02.11
Mech. Eqpt. Erection
in various areas in progress.

Total

Submtd.

Appd/KFR

AAN

37
12
88
253
390

37
12
88
253
390

34
12
86
251
383

1
0
2
0
3

Unit

Total Scope
*- Revised

Plan

B 12 Hoisting and Handling Facilities Equipment erection with Crane-413,


in Bar & Rod Mill and Universal 416, 418 & 421 in URM & with Crane-106
in BRM in progress.
Rail Mill (Pkg. 030)
Design Engg., ordering, manufacturing,
Contract no. TK/ 2012 / 356
ConsultantMECON
supply & erection of equipments (101,
Agency-M/s HEC Ltd, Ranchi
105, 116, 114, 406, 109, etc) in progress.

Drawings

Total

Submtd.

Appd/KFR

AAN

Comtd

U/S

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)

203
48
270
761
1282

203
48
262
754
1267

203
48
262
754
1267

0
0
0
0
0

0
0
0
0
0

0
0
0
0
0

Unit

Total Scope
(*-Revised)

Imp. activities completed/ Highlights

B 13 Drop Test Facility for URM (Pkg.047-01)


Consultant-MECON Price: Rs97.79 Lakhs
Agency M/s Pragya Equipments Pvt. Ltd.,
Indore Contract Signed on: 13.09.13
Compln: 12.06.14 Contract no. TK/2013/389

Likely Compln Dec.15


(Proj. Mgr.- B K Dey, DGM) 20008

2
0
0
2
4
Oct.15
Prog.

U/S

0
0
0
0
0

TOTAL
Activity

Oct.15
Plan
Prog.

Ordering of All 6750 T


Mech Eqpt.(Imp.). all
5800
T
Mech
Eqpt.(Indig.) & All 163 T
Elect.
Eqpt.(Imp.)
completed.

8th Review meeting


held on 29.10.13.

Cum. Prog.

T
3463
20
0
3443
Elect. Eqpt. Erection
T
703*
3
0
700
Hot trials of Welding Machine no.-1 taken and 1st weld joint of 60 Kg rails (7.5 M) was done successfully
on 14.11.14. Both Brushing machines erected. Testing of motors of Roller table of Transfer Telpher area
completed. All 5 Xmers in S/s bldg.and 3 Xmers in Welding Bldg. charged. All ECRs-1 to 5 charged.

Cont. Completion: 17.10.12


Likely Completion : Oct.15
(Proj. Mgr.- M M Gadre, DGM) 21146

Contract price: Rs. 150.42 Crs.


Contract Signed on: 21.01.12
Cont. Completion: 20.07.13
Likely Completion : Dec.15
(Proj. Mgr.- S K Jain, DGM) 21058

Comtd

Review meeting held


on 15.01.14.

Ordering & Supply of All


Eqpt. completed.(Mech.
Imp-438 T,Mech. Indig.3025 T, Elect. Imp-100 T,
Elect. Indig.-603 T )

13th Review meeting held


on 17.01.15.

to
be
commissioned for BRM
1100
17 Cranes, 3 Transfer
275
cars & 21 Electric Hoist.
Completed
Eqpt.
to
be
1319.5
commissioned for URM
1042.7
24 Cranes & 21 Elect.
1054
Hoist)
691
Cum. Prog.

(Eqpt.

Mech. (Manufacturing)
T
2636*
400
0
Mech. (B/o items) Ordering
T
464*
189
0
Elect. (B/o items) Ordering
T
1300*
Mech. Eqpt. Supply
T
3100*
100
0
Elect. Eqpt. Supply
T
1300*
50
0
Mech. Eqpt. Erection
T
3100*
100
0
Elect. Eqpt. Erection (incl DSL)
T
1300*
50
0
Eqpt. erection with Crane-106 in BRM & Crane-413, 416, 418 & 421 in URM i/p. LT mechanism with trolley
of Crane -101, 105 & 116 in BRM area erected. LT mechanism of Crane -406 of URM area erected.
Drawings
Drawing list KFR on 05.09.14.
Basic Engg. (A)
GA drgs for civil foundation plan KFR.
GA of Drop Test Area, Feeding Roller Basic Engg. (I)

Total

Table, Rail Transfer Mechanism, Ram & Detail Engg. (A)


Grip Mechanism & of Anvil Block Detail Engg. (I)
TOTAL
approved.

10/9/2015

Page : 9

Appd/KFR

AAN

Comtd

8
6
6

Submtd.

8
4
0

7
3
0

1
0
0

0
1
0

U/s

0
0
0

10

30

12

10

1st Review meeting held


on 21.09.15.
Scope of Mech eqpts.
33 T & Elect. eqpts. 2 T

SN
SCHEME / PACKAGE
B 14 Illumination System for URM, BRM & RWL

(Pkg-128) Consultant MECON


Contract no. TK/ 2013 / 382
AgencyM/s Traansrect Industries, Raipur
Cont. price: Rs 11.60 Crs.
Contract Signed on: 21.05.13
Contract Completion : 20.02.14
Likely Completion : Oct.15
(Proj. Mgr.- Tirumal Rao, DGM) 20055

PROGRESS ON DATE

Illumination work in BC bay of URM


started on 26.09.13 and in progress.
Illumination work in BC bay of BRM
started on 10.06.14 and in progress.
Illumination work in RWL area in progress.

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)

20
0
350
71
441

TOTAL

Activity

Elect. Eqpt. (Ind.) Supply


Elect. Eqpt. (Ind.) Erection
Drawings

B 15 CNC Roll Turning Lathes for URM


(Pkg-142-01)

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL
Activity

Consultant- MECON
Contract no. TK/ 2013 / 385
Cont. price: Rs 22.84 Crs.
AgencyM/s Hankook-Sanmathi
Contract Signed on: 21.06.13
Contract Completion : 20.06.14
Likely Completion : Oct.15
(Proj. Mgr.- Rakesh Kumar, DGM) 21143

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

9
8
15
31
63

Submtd.
20
0
330
67
417
Unit

Appd/KFR

AAN

Comtd

16
0
160
65
241
Total
Scope

2
0
156
0
158
Plan

Prog.

T
T

448
448

50
50

0
0

Submtd.

Appd/KFR

AAN

Comtd

0
0
0
0
0

0
2
0
3
5

9
8
15
31
63
Unit

1
0
8
0
9
Oct.15

9
6
15
28
58
Total
Scope

Plan

Prog.

354
50

23
15.3

0
0

Oct.15

U/S
1
0
6
2
9
Cum. Prog.

358
183
U/S
0
0
0
0
0
Cum. Prog.

18th Review meeting held on


23.09.15.

Ordering of all 448 T eqpts.


completed.
8th Review meeting held on
05.05.15.
Ordering & supply of all
Imported Eqpts. (330 T Mech.
& 43.5 T Elect.) completed.

Ordering & supply of all


Indigenous eqpts. (24 T
Mech. & 6.5 T Elect.)
All Imported Eqpts. (330 T Mech. & 43.5 T Elect.) supplied during 30.07.14-05.08.14. completed.
Mech. Eqpt. Erection
Elect. Eqpt. Erection

T
T

331
34.7

Alignment work of all 4 nos. CNC lathe machines completed. Cable laying work comp.

Total
Submtd.
Appd/KFR
AAN
Comtd
U/S
B 16 Air Conditioning System and Ventilation Design Engg., ordering,
supply & Drawings
Basic Engg. (A)
29
29
29
0
0
0
System for BRM, URM & RWL (Pkg.-125-02)
erection of eqpts. in progress.
Basic Engg. (I)
6
6
6
0
0
0
Consultant-MECON
Fabrication & erection of ducts (ECRs-1, Detail Engg. (A)
294
277
250
8
9
10
Contract price: Rs 47.92 Crs.
2 & 3 of BRM & ECRs-1 to 3 & 6 of URM) in Detail Engg. (I)
50
49
47
1
1
0
Contract no. TK/ 2013 / 387
TOTAL
379
361
332
9
10
10
progress.
Agency M/s Sterling & Wilson Ltd., Kolkata
Activity
Unit
Total Revised
Oct.15
Cum. Prog.
Placement of eqpts. in various area of
Contract Signed on: 25.06.13
Scope
Plan
Prog.
BRM and URM(Mech. eqpts., Elect. Mech. Eqpt (Ind.) supply
Contract Completion : 24.09.14
T
969 #
49
31
951
eqpts. like PDB, insulation work, cable Elect. Eqpt. (Ind.) Supply
Likely Completion : Oct.15
T
316 #
22
0
294
(Proj. Mgr.- J Gopi Krishnan, DGM) 21151
tray work & cable laying) in progress.
Mech. Eqpt (Ind.) erection
T
969 #
100
0
313
T
316 #
15
0
164
Piping work, welding, alignment, hydro Elect. Eqpt. (Ind.) erection
test and piping insulation work in Mech. eqpts.(VRF, ACs, pipes, GI sheets Chillers, valves, AHUs, FCUs, fans, Airwashers,
louvyers, desert cooler, pipes, plates, humid stats, pkg ACs, Cooling tower, dampers, etc)
progress.

18th Review meeting held on


16.07.15.

B 17 Roll & Repair Shop Equipment for Universal Design Engg., ordering & supply of
Rail Mill (Pkg-142-02)
eqpts. in progress.
Contract no. TK/2013/391
Welding rectifier & m/cs, Radial drilling

5th Review meeting held on


22.04.15.

supplied. Elect. eqpts (Cables, steel supports,cable tray, PDBs, SDBs, etc) supplied. Testing
of all AC and ventilation systems of Rail Welding Line area successfully comp. on 06.05.15.

Consultant-MECON
Cont. price: Rs 23.90 Crs.
Agency M/s MACO Corporation, Kolkata
Contract Signed:26.09.13
Contract Compln: 25.09.14

Likely Completion : Dec.15

m/cs, hack saw, band saw m/cs, lathes,


universal milling m/c, Column drilling m/c,
grinding, brazing & welding m/cs, profile
redressal m/c, PDBs, etc supplied.

(Proj. Mgr.- Rakesh Kumar, DGM) 21143

B 18 Air Drying Plant for Universal Rail Mill and Air Design Engg. in progress.
Drying and Filtration Plant for BRM (Pkg. -114A)
QAP of Strl. & Mech. eqpts. approved on
Consultant-MECON
Cont. price: Rs 1.34 Crs.
08.09.15.
Agency M/s Mellcon Engineers Pvt. Ltd, New Delhi

Contract Signed:31.03.15
Contract Compln: 30.11.15
(Proj. Mgr.- K V S Prakash Rao, DGM) 21374

Drawings

Total

Basic Engg. (A)


Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL
Activity

14
14
13
62
103

Mech. Eqpt Supply


Elect. Eqpt. Supply
Drawings
Basic Engg. (A)
Basic Engg. (I)
Detail Engg. (A)
Detail Engg. (I)
TOTAL

Total
5
0
31
44
80

Submtd.
14
13
10
59
96
Unit

Appd/KFR

AAN

Comtd

Plan

T
T

420
20

117.5
10

0
0

302.5
10

Submtd.

Appd/KFR

AAN

Comtd

U/S

3
0
15
3
21

2
0
0
2
4

5
0
21
8
34

0
0
1
0
1

1
3
1
5
10

U/S

13
10
8
54
85
Total
Scope

Oct.15

0
1
0
0
1
Cum. Prog.

Prog.

0
0
2
3
5

0
0
4
0
4

Engg. meeting held at MECON, Ranchi during 01.07-04.07.15. List of drawings & datasheets for
air filter and air dryer KFR on 17.07.15.P & ID diagrams, eqpt. list and foundation drawing for air
filtration plant and assembly for BRM KFR. P & ID diagrams and foundation drawing for air dryer
for URM KFR. Electrical load list KFR and Power supply scheme approved. GA drg. & foundation
drg. for air receiver for BRM and URM KFR.

10/9/2015

Page : 10

All Eqpts. (969 T Mech. & 316 T


Elect.) ordered.

All Eqpts. (420 T Mech. & 20 T


Elect.) ordered.

1st Review meeting held on


21.09.15.

C. STEEL ZONE
SN

C1

PROGRESS ON DATE
SCHEME / PACKAGE
Instn. of Desulphurisation Unit at SMS-II (Consultant-CET) Sanction Cost: Rs 83.90 Crs.
Drawings
Pkg.-IV 180T+50T Ladle Crane
Critical Issue
BE (A)
Contract No TK- 2006/221
Supply of Main Trolley.
DE (A)
Consultant-CET
Start erection of eqpt. by M/s DE I
Agency -M/s Jessop
TOTAL
Jessop.
Cost : Rs. 13.18 Crs
Contr. date : 10.03.06
Contr. comp : 09.06.07
Project Mgr- S.K.Jain, DGM- 1058

Total

Subm.

40
26
113
179

37
22
68
127

36
17
56
109

1
5
1
7

Unit

Total
vol.
385
*52
*385
*52

Plan
-

Activity

Mech. eqpt. supply


Elect. Eqpt. supply
Mech. eqpt. erection
Elect. eqpt. erection

Pkg.-V LT S/S & DC S/S for Ladle Crane


Contract No TK- 2006/223
Agency M/s Siemens
Cost ; Rs. 10.99 Crs ; Contract date: 10.04.06
Contr. Comln: 09.06.07
Proj. Mgr -MP Singh, DGM- 2678

C2
2.1

OVERALL STATUS AS ON DATE

T
T
T
T

Appd/KFR

COMMITMENT AS PER LATEST MOM

AAN

Comnt
4
4

U/S
7
7

Oct15

Cum. Prog.
Prog.
206
22
24
7

Commissioning certificate issued on 16.06.12. PG will be done after


commissioning of 180T +50T ladle crane by M/s Jessop.

Segment repair & mould repair shop for new slab caster at SMS-II, Consultant-CET
Instaln. of EOT Crane ,Wire Rope Hoist & Jib
All Mechanical & electrical equipments erection completed. Individual
Crane for Segment & Mould Repair Shop at
trial of mechanism completed. PAC issued on 03.01.14. Load test
SMS-II Contract no. TK/2010/305
completed and certificate issued by competent authority on 19.05.14.
Agency- M/s Grip Engnrs., Faridabad
Commissioning certificate issued w.e.f 09.08.2014.
Cost : Rs.1.77 Crs,;
Contr. Sign dt. 06.04.10,
Cont. Completion : 05.04.11,
Likely compl: Oct15
Proj. Mgr -K. Rajasekhar, AGM- 0518

2.2

Aug. of power supply facility for


segment repair & mould repair shop
Contract no. TK/2010/302
Agency-Hindustan Control & Eqpt., Kolkata
Cost : Rs. 2.63 Crs
Contract signed on : 23.02.10,
Cont. Completion : 22.02.11
Likely Compl- Oct15
Proj. Mgr- MP Singh, DGM- 2678

2.3

CNC Lathe M/c for Segment Repair


Shop

Drawing

Total

BE (A)
DE (A)
DE I
TOTAL

15
21
20
56

Activity

Earthwork
Concrete
Elect. Eqpt. Ord
Elect. Eqpt. Supply
Elect. Eqpt Erection

Submtd.
15
21
19
55

Appd/KFR
13
19
19
51

Unit

Total Vol.

M3
M3
MT
MT
MT

125
75
32
32
32

AAN

Comtd.

2
2
0
4

0
0
0
0
Oct15

Plan

Progress

U/S
0
0
0
0

Cum.
Prog

125
75
32
32
32

Testing of PCC panels compl. On 02.08.13 .LT substation- 27Q charged on


16.09.13. PAC given on 14.01.14. Both transformers (of S/S 27Q) charged on
15.03.14.
CNC Lathe erection completed on 10.07.12. PAC issued with effect from
12.07.12.

Contract no . TK/2010/320
Agency- M/s Texllence CNC, Pune
Cost : Rs 87.63 Lakhs
Contract signed : 06.08.10,
Cont. Compl. : 05.08.11
Likely Completion Oct15
Proj. Mgr K. Rajshekhar, AGM- 0518

10/9/2015

Page : 11

Review Meeting held on 10.06.14

SN

2.4

SCHEME / PACKAGE
Provision of Roll Cladding facilities &
other Auxiliaries in SRS

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

COMMITMENT AS PER LATEST MOM

PAC issued with effect from 02.03.15

Review meeting held on 30.05.14.

Contract no . TK/2010/328
Agency : Welding Alloys , Mumbai
Cost : Rs 1.92 Crs. Contract Signed : 11.11.10
Effective Dt. of contract : 02.11.10
Cont. Completion : 01.11.11
Likely Completion : Oct15
Proj. Mgr K. Rajshekhar, AGM- 0518

2.5

Installation of Machine Tools in


Segment Repair Shop and Mould
repair shop
Award No. NTK-5(2919)/12/184
Agency- M/s DK Saha Cost Rs. 47.73 Lakhs.
Date of Award : 06.02.12 Cont. compl. 05.08.12
Likely Completion: Oct15
Proj. Mgr - K. Rajshekhar, AGM - 0518

C3

BOF Shop Technological Package


(Pkg.-025)
Contract No. TK-2008/285
Consultant MECON
Agency-M/s Siemens VAI
Cost Rs. 1335.72 Crs
Contract signed : 24.10.08,
Cont. Completion : Aug.11
Likely Compl: Jun16
(Conv.1-Mar16, Conv.2-May16)
Proj. Mgr V.K. Rai, DGM - 0563

Radiography completed
line). Charging balance.

(Oxygen Roll grinding machine erection started on 11.07.12 & completed in


Aug.12. Universal cutter grinder m/c positioned in their respective
locations. Erection of hydraulic press completed. Erection of centre lathe
completed. Horizontal boring m/c erection completed. Oxygen pipeline
erection completed. Water pipeline erection completed.

Drawing
BE (A)
BE I
DE (A)
DE I
TOTAL
Addl. Drawings
BE (A)
BE I
DE (A)
DE I
TOTAL
Activity

Total
598
282
103
286
1269
-

Appd/KFR

AAN

Comntd

U/S

597
277
108
279
1261

586
270
102
249
1207

3
1
1
8
13

5
5
5
16
31

3
1
0
6
10

270
215
156
647
1288
Total vol.

7
0
1
30
38

4
11
9
139
163

0
0
1
9
10
Cum.
Prog.

281
226
167
825
1499
Unit

Oct15
Plan

Mech. Eqpt. Ord. (Imp)


Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. (Imp.)
Elect. Eqpt. Ord. (Indg.)
Refractory Ord.
Mech. Eqpt. Supply (Indg.)
Mech. Eqpt. Supply (Imp.)
Elect. Eqpt. Supply. (Imp.)
Elect. Eqpt. Supply. (Indg.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection
Important activities completed / Highlights

Subtd.

T
T
T
T
T
T
T
T
T
T
T

2426
21562
349.2
1870.1
4212
21562
2426
349.2
1870.1
2059
1081

0
150
0
0
30.4
0
40.21

Prog.

2426
21463
349
1856
0
20950
2412
349.2
1825.6
2058.5
418.3

Mechanical test for travel of piston of Gas Holder, to its operating limit
conducted on 18.01.14 along with EMD & SMS-II. Standard leak test of
Gas Holder conducted during 04-07.02.14 along with EMD & SMS-II and
joint inspection recorded for 24, 48 & 72 hrs. Electrical equipment
erection started on 04.11.14.

10/9/2015

Page : 12

Review meeting held on 15.09.15.

SN

C4

PROGRESS ON DATE
SCHEME / PACKAGE
Instln. Of Secondary Refining Unit for Erection of Storage Bunker is in
SMS-III (Pkg.-025A)
progress.
Cont. No. 2010/303
1.5 T tech strl erected.
Consultant MECON
43.5 T tech strl supplied.
Agency-M/s WISDRI, China
131 T mech eqpt supplied (imp.)
Cost : Rs. 205.56 Crs
80 T elect eqpt supplied (imp.)
Contract signed on 08.03.10,
Cont. Completion : : 22.09.12,
Likely Compl: Jun16
(LF1 - Nov'15, ARS1 - Feb'16,
LF 2 & 3, ARS 2 & 3 - Jun'16,
RH - Jun'16)
Proj. Mgr V.K. Rai, DGM - 0563

OVERALL STATUS AS ON DATE


Total
BE (A)
BE I
DE (A)
DE I
TOTAL

179
173
146
523
1021
Total

BE (A)

BE (I)

DE (A)

DE ( I )
TOTAL

Submtd.
179
173
146
509
1007
Submtd.

3
4
10
69

Activity
Mech. Eqpt.Ord. (Imp.)
Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. Imp.)
Elect.Eqpt. Ord. (Indg.)
Tech. Strl Fabrication
Refractory ordering (Imp.)
Refractory ordering (Indig.)
Mech. Eqpt.Supply. (Imp.)
Mech. Eqpt. Supply. (Indg.)
Tech. Strl Supply
Tech. strrl. erection
Elect. Eqpt. supply. (Imp.)
Elect. Eqpt. supply. (Indg.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Appd/KFR

COMMITMENT AS PER LATEST MOM

AAN

176
171
145
489
981

3
1
1
0
5

Appd/KFR

0
1
0
2
3

86

73

Total
Vol.

T
T
T
T
T
T
T
T
T
T
T
T
T
T
T

1698
1652
303
873
2150
353
480
1698
1652
2150
2150
303
873
3350
1176

U/S

0
0
0
14
14

AAN

3
3
9
58

Unit

Comntd

Review meeting held on 27.05.15.

0
1
0
6
7

Comntd

U/S

0
0
0
6

0
0
1
3

6
Oct15
Progress
Plan
0
0
180
131
270
200
119.5
34
4
57
80
130
70
24
42

4
Cum.
Prog.
1698
1652
303
873
2150
353
0
491.1
147.88
640.5
186.74
120
325
7.5
75

Mechanical (imp.) equipment supply started on 27.01.15. Tech. strl erection started for LF
area on 30.03.15. 35 MVA Ladle furnace transformer supplied in Apr.15. Electrical eqpt.
Erection started on 27.05.15. 35 MVA Ladle furnace transformer at LF-1 erected on 27.05.15.
35 MVA Transformer (for LF) received at site on 12.06.15. Mech. eqpt. Erection started on
25.08.15. 3rd and last 35 MVA trans. Supplied on 03.10.15.

C6

Instln. Of Continuous Casting Plant


Complex (Pkg.-026)
Contract No. TK-2009/289
Consultant MECON
Agency-M/s Siemens VAI
Cost :781.01 Crs
Contract signed on: 18.04.09
Contr. Compln. : 17.12.11
Likely Compl: Jun16
(CK1 - Nov'15, CK2 - Dec'15,
CV1 - Feb'16, CV2 - Jun'16)
Proj. Mgr - MP Singh, DGM -2678

Erection of JBs, earthing strip and


earthing is in progress.
Cable laying from MCP to hydraulic
motor JB completed (400 mtr.).

Drawings

Total

BE (A)
BE I
DE (A)
DE I
TOTAL

723
108
266
937
2034

Submtd

722
108
265
908
2003

Appd/KFR

706
108
258
902
1974

AAN

16
0
6
1
23

Comntd.

0
0
1
5
6

U/S

0
0
0
0
0

232
518
59
1843
2652

231
496
59
1814
2600

1
0
0
3
4

0
20
0
12
32

0
2
0
14
16

Addl. Drawings

BE (A)
BE I
DE (A)
DE I
TOTAL
Activity
Mech. Eqpt. Ord. (Imp.)
Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. (Imp.)
Elect. Eqpt. Ord. (Indg.)
Mech. Eqpt. Supply (Imp.)
Mech. Eqpt. Supply (Indg.)
Elect. Eqpt. Supply (Imp.)
Elect. Eqpt. Supply (Indg.)
Refractory Ord.
Elect. Eqpt. erection

Unit

Total Vol.

T
T
T
T
T
T
T
T
T
T

3299
10791
240
1176
3299
10791
240
1176
2200
971

Oct15
Plan
Prog
0
0
0
0
50
0
0
0
23.8

Cum. Prog.
3294
10380
239
1100
3294
10198
239
1097
0
138.8

Elect. Eqpt erection started on 27.12.14. Cable laying started in Caster-1 on 06.08.15.

10/9/2015

Page : 13

Review meeting held on 04.02.13.

SN

C7

SCHEME / PACKAGE
Instln. of Hot Metal De-sulphurisation
Unit for SMS-III (Pkg.-027)
Contract No. TK-2008/283
Consultant MECON
Agency-M/s ESM USA-Beekay Engg.
Cost Rs. 37.73 Crs
Contract signed: 06.10.08 (Eff. date
06.03.09)
Contr. completion : 05.03.11,
Likely Compl: Mar16
Proj. Mgr -. N.V.Joshi, DGM-0799

PROGRESS ON DATE

Design Engg. in progress.


Strl fabrication under progress.

Total

Submtd

Appd/KFR

AAN

Comtd

U/S

BE (A)

55
61
74
348

55
61
67
322

42
58
55
315

2
0
0
0

10
3
12
6

1
0
0
1

BE I
DE (A)
DE I
TOTAL

538

BE (A)
BE I
DE (A)
DE I
TOTAL

Activity

Mech. Eqpt. Ord. (Imp.)


Mech. Eqpt. Ord. (Indg.)
Elect. Eqpt. Ord. (Imp.)
Elect. Eqpt. Ord. (Indg.)
Structural supply
Structural Erection
Mech Eqpt. Supply (Imp.)
Mech Eqpt. Supply (Indg)
Elect. Eqpt. supply. (Imp.)
Elect. Eqpt. supply. (Indg.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection

C8

Lime Calcinations & Dolomite Plant at


RMP-III (Pkg.-028)
Contract No. TK-2009/298
Consultant-MECON
Agency-M/s Shapoorji Pallonji
Cost : Rs. 263.99 Crs
Contract signed on : 09.12.09,
Cont. Completion : 08.03.12,
Likely Compl : Mar16
(Kiln 1 - Nov'15 ; Kiln 2 - Dec'15 ;
Kiln 3 - Jan'16 ; Kiln 4 - Feb'16 ;
Kiln 5 - Mar'16)

Proj. Mgr MP Singh, DGM- 2678

Important activities completed / Highlights

HT Cable route trusel erection


completed.
Laying of LT power cable in progress.
2 T Strl erected.
1 T electrical eqpt erected.
1 T mech. eqpt erected.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Drawings

Total

BE (A)
BE I
DE (A)
DE I
TOTAL

73
95
186
280
634
Activity

505
470
Addl. Drawings
3
3
1
1
10
9
14
13
Unit

Total Vol.

T
T
T
T
T
T
T
T
T
T
T
T

15
300
2
60
420
420
15
300
2
60
315
62

Submtd.

73
95
186
277
631
Unit

Appd/KFR

0
0
1
1
Oct15
Plan
Progress

10
10

AAN

72
95
184
277
628

M3
Nos.
M3
T
T
T
T
T
T
T
T
T
T
T

108000
792
21195
4000
8364
2750
11114
21
2047
1.5
1000
4000
2068
1001.5

Comtd

1
0
0
0
1

Total vol.

2
0
0
Cum.
Prog.

15
290
2
60
410
0
15
290
2
5.5

0
0
0
0

Plan

Earthwork
Pilling (Scope revised)
Concreting
Refractory ordering
Tech. Structures Supply
Bldg. Structures supply
Structures erection
Mech. Eqpt. Supply. (Imp.)
Mech. Eqpt. Supply. (Indg.)
Elect. Eqpt. supply. (Imp.)
Elect. Eqpt. Supply. (Indg.)
Refractory supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

31

0
0
1
1
2

Oct15
Prog.

4000
40
59
130
29
23
0
45
25

6300
416
33
12
22
13
9
6

U/S

0
0
0
0
0
Cum Prog

105682
792
20929
4000
8306
2750
9925
21
2032
1.5
985
0
1639
657.8

Trial run taken for Conv-2A on 25.05.15. Trial run taken for Conv-2B on 30.05.15. 2MVA Transformer 1
C charged for Kiln-1 on 03.06.15. Conveyor 3 B trial run taken successfully on 06.06.15. Kiln Feed
Building-1 screen trial taken on 12.06.15. Chilled water line testing done at ECR Building on
03.07.15. 2 nos. transformer (2 MVA) charged for Kiln no.2 on 04.07.15. Kiln Feed Building-2 screen
trial taken on 09.07.15. No load trial taken for 2 nos. blowers of
Kiln 2 on 13.07.15. 2 nos.
transformer (2 MVA) charged for Kiln no.3 on 14.07.15. No load trial taken for 2 more blowers of
Kiln 2 on 17.07.15. 1 no. & 2 nos transformer (2 MVA), of Kiln 4 & 5 respectively, charged on
24.07.15. PCC charged at Kiln-1 on 25.07.15. No load trial taken for 3 nos. blowers of Kiln 1 on
27.07.15. 1 no. transformer (2 MVA) charged for Kiln no.1 on 25.08.15. Total 9 out 12 nos trans.
charged.Trial run taken for vibro feeder of Kiln no.2 on 25.08.15. MCC of Kiln1 & 2 Charged on
28.08.15.

10/9/2015

Page : 14

Review meeting held on 26.08.14

Review meeting held on 13.02.15

SN

C9

Activity

Drawing

Total

BE (A)
BE I
DE (A)
DE I
TOTAL

Submtd.

34
4
64
182
284

Total
vol.

Oct15 Plan -Progress

Appd/KFR

34
4
63
175
276

Activity

Unit

Mech. BO item Ordering


Elect. BO item Ordering
DSL ordering
Mechanical eqpt. Supply
Electrical eqpt. Supply
DSL Supply
Mech. eqpt. Erection

Important activities completed / Highlights

C 11 Installation of Cranes for BOF & CCP


(Pkg.-029B1) (Consultant- MECON)
(Pkg retendered after RPN)

Unit

Cum. Prog.

Review Meeting held on 11.06.15.

Mech. BO item Ordering


T
553
553
Elect. BO item Ordering
T
599
599
DSL ordering
T
561
561
DSL Supply
T
561
561
Mech Eqpt supply
T
3756
200
3210
Electrical eqpt. supply
T
599
100
423
Mech Eqpt erection
T
3756
100
601
Electrical eqpt. erection
T
599
50
Main girder of 1st crane for I-J bay with balancer erected. 1st Main girder of 2nd crane
for I-J bay with balancer erected on 07.06.13 & 2nd Main girder on 12.06.13. 2 Nos.
Aux. end girders erected on 13.04.15.

Contract No. TK-2009/293


Consultant MECON
Agency-M/s HEC
Cost : Rs. 146.10 Crs
Contract signed: 29.06.09,
Contractual Compln : 28.06.11,
Likely Compl: Feb16 (Priority Cranes)
Project Mgr- S.K.Jain, DGM- 1058
Important activities completed / Highlights

C 10 Instln. Of 10 Nos. Cranes above 100 T


capacity (Pkg.-029-A-2)
Contract no. TK/2011/336
Consultant-MECON
Agency-M/s HEC
Cost Rs. 149.55 Crs
Contract signed: 12.02.11
Contractual Compln : 11.02.13
Likely Compl : Feb16 (Priority Cranes)
Project Mgr- S.K.Jain, DGM- 1058

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE

SCHEME / PACKAGE
Installation of Cranes for BOF & CCP
(Pkg.-029A) (7Nos 300T + 80 T Cap.)

T
T
T
T
T
T
T

AAN

34
4
62
169
269

0
0
0
0
0

Total
vol.
507
494
760
3686
494
760
3686

Plan
9
200
100
50
10

Comntd.
0
0
1
6
7

Oct15
Progress

50

U/S

Review Meeting held on 11.06.15.

0
0
0
0
0
Cum.
Prog.
498
173
760
1101
106
749.3
0

Mech. eqpt. Supply started on 11.01.14. Elect. Eqpt. Supply started on 27.05.14.

Design engg. in progress.


Equipment ordering in pogress.

Agency M/s Mukand


Contract signed: 19.06.15; Contr. Compln. :
18.12.16; Cost Rs.176.08 Crs.

Drawing

Total

BE (A)
BE I
DE (A)
DE I
Total

Submtd.

85
79
246
436

40
44
50
55

846

189

Activity

Priority Cranes : Feb16 (Priority Cranes)


Proj. Mgr SK Jain, DGM

Appd/KFR

27
19
50
55
Unit

Mech. BO item Ordering


Elect. BO item Ordering
Mech. eqpt. Supply
Electrical eqpt. Supply
Mech. eqpt. Erection
Elect. eqpt. Erection

T
T
T
T
T
T

151
Total vol.
3484
233
3484
233
3484
233

AAN

2
0
0
0

Comntd.

1
1
0
0

2
Oct15
Plan
Progress
200
761.5
100
0
0
0
0

U/S

Review meeting held on 15.09.15

10
24
0
0
34
Cum.
Prog.
761.5
0
0
0
0
0

Important activities completed / Highlights

C 12 Installation of Cranes for BOF & CCP


(Pkg.-029B2)
Consultant-MECON
Agency- M/s Mukand Ltd
Cost :Rs 53.75 Crs
Contract signed: 08.08.12
Contractual Compln : 07.02.14
Likely Compl: Feb16
Project Mgr- S.K.Jain, DGM- 1058

Important activities completed / Highlights

Drawing

Total

Submtd.

201
52
210
508
971

201
52
210
505
968

BE (A)
BE I
DE (A)
DE I
Total
Activity

Appd/KFR

Unit

Mech. BO item Ordering


Elect. BO item Ordering
Mech. eqpt. Supply
Electrical eqpt. Supply
Mech. eqpt. Erection
Elect. eqpt. Erection

T
T
T
T
T
T

200
51
205
501
957
Total vol.
704
329
704
329
704
329

AAN
1
0
0
1
2
Plan
14
50
20

Comntd.
0
0
4
0
4
Oct15
Progress
-

U/S
0
1
1
3
5
Cum.
Prog.
704
329
690
329
255
20

Mech equipment started on 01.08.14. Elect. eqpt erection started on 18.08.15.

10/9/2015

Page : 15

Review meeting held on 15.09.15

SN
PROGRESS ON DATE
SCHEME / PACKAGE
C 13 Cast in situ bored piling work in SMS-III Piles-Nil.
complex (Pkg.-033-A 1)

Total Vol.

Award No.PCC/NTK/19/09
Consultant-MECON
Agency -M/s HSCL
Cost Rs 191.37 Crs (Revised)
Award Dt. 10.02.11. Cont. Signed: 21.02.11
Cont. compl. 20.10.12.

Unit

Earth work
Concreting For BOF
-For CCP
Total Concreting

Total Vol.

M3
M3
M3
M3

250000
99138
95025
194213*

Important activities completed / Highlights

Review meeting held on 09.05.14

Oct15

Cum. Prog.

Plan

Prog

5000
588
1108
1696

642
81
136
217

Review meeting held on 06.05.14

239122
82482
90333
172815

*Scope revised as per MECON (confirmed by Zone)

RCC work started on 10.04.13


Strl Fabn 35 T for BOF, 15 T for CCP.
Strl Ertn 49 T for BOF, 21 T for CCP.

Activity

Unit

Total Procurement of steel


Structural Fabr -For BOF
-For CCP
Total fabrication
Structural Erection
- For BOF
-For CCP
Total Erection
Area

MT
MT
MT
MT
MT
MT
MT

Total Vol.

106947
57349
42601
99950
57349
42601
99950

Status of Detail drgs


Submtd
Appd/KFR

Scope

1100
550
1650
1690
890
2580

240
110
350
290
156
446

96000
49277
37334
86611
41764.11
33947.89
75712

47721
39870

0
0

1432
0

2555
292

Submtd

Appd/KFR

AAN

Comntd

U/S

21
27
38
86
Unit

21
27
38
86
Total vol.

0
0
0
0

0
0
0
0

0
0
0
0
Cum.
Prog.

51708
40162

BE (A)
DE (A)
DE ( I)
TOTAL

Cum. Prog.

Comntd.

50000
40000
Total

Prog

Drawing

Oct15
Plan

AAN

412 / 513 column erected.

Agency- M/s Anupam Industires


Cost :Rs 8.83 Crs
Contract signed: 15.03.11
Contractual Compln : 14.12.11
Likely Compl: Oct15
Proj. Mgr -V.K.Rai, AGM- 0563

Prog

Nos.
Nos.
Nos.

Activity

BOF
CCP

Augmentation facilities of Material


Handling system in SMS-II (Pkg No.
038-01) Contract no . TK/2011/339
Consultant-MECON

Cum. Prog.

Plan

Excavation 104 m3 completed.


Concreting -31 m3 completed.

Consultant MECON
Agency-M/s Simplex Infrastructures
Cost : Rs. 330.06 Crs (Revised)
Award Dt. 11.02.13
Contract signed: 28.02.13
Cont. Compl. : 30.04.14.
Likely Completion: Jan16
Proj. Mgr

C 17

Oct15

8425
8425
7520
7499
15945
15924
Earth Work
M3
233500
239490
Concreting(PCC)
M3
3000
2538.5
Concreting(RCC)
M3
2000
733
Pile drgs.- Total 15945 drgs. Issued (8425 for BOF & 7520 for CCP)
13320 m3 / 300000 m3 earthwork done & 54680 m3 / 180000 m3
concreting completed. Contract terminated on 09.02.13. Balance work
awarded to M/s Simplex Infrastructures on 11.02.13.

C 14 Civil works for BOF & CCS (Pkg-033A)

C 16 Strl. Works for BOF & CCS (Pkg-033B)


Award No. NTK-5(2787)/09/1554
Consultant MECON
Agency-M/s Era Infra Structure
Cost : Rs. 611.66 Crs (Revised)
Contract signed: 30.09.09,
Cont. Completion : 29.09.11
Likely Compl: Feb16
Proj. Mgr Alok Rai, DGM- 0792

Unit

Piles for BOF


Piles for CCP
Total Pilling

Award No. PCC/NTK/ 23/10


Consultant-MECON
Agency-M/s Era Infra Structure, Delhi
Cost Rs 84.92 Crs. (Revised)
Contract signed on: 23.01.10,
Cont. Completion : 22.10.10,
Likely Completion: Oct15
Proj. Mgr.

C 15 Balance civil works for BOF & CCP at


BSP Bhilai (Pkg - 033A2)

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Activity

21
27
41
89
Activity

*Revised Scope is 99950

Oct15
Plan

Mech. Eqpt. Ordering


Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

U/S

T
T
T
T
T
T

187.3
44.5
187.3
44.5
187.3
44.5

7.3
2.5
17.3
9
50
20

Prog.

180
42
170
35
125
15

All parts of 75/15 T crane erected and load test completed on 04.07.15.

10/9/2015

Page : 16

Review meeting held on 24.06.14.

Drgs. of 89962 T design drawing issued by


MECON.
H-I bay (Secondary refining unit), I-J bay
(Casting Bay), J-K bay (tundish bay), K-L
bay (Segment bay), L-M bay (Storage
bay), M-N bay (Storage bay) G-H (Ladle
preparation bay).

Review meeting held on 13.11.14.

SN

C 18

SCHEME / PACKAGE
Inter Plant Pipe Conveyor from RMP-3
to RMP-2 (Pkg.-140)
Contract no . TK/2011/334
Consultant- MECON
Agency : M/s FL Smidth Pvt. Ltd
Cost- Rs 58.11 Crs
Contract Signed : 04.02.11,
Cont. Completion : 03.05.12
Likely Completion : Nov15

PROGRESS ON DATE

Power cavble laying in


Fire Hydrant laying work in progress.
Equipment
alignment
Mech.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawing

in

progress.
Conveyor belt laying in progress.

BE (A)
BE I
DE (A)
DE I
TOTAL

Total

Submtd

Appd/KFR

AAN

50
27
145
60
282

50
21
142
53
266

48
19
141
53
261

0
0
0
0
0

Activity

Earthwork
Concreting
Mech. equipment Ord
Elect. equipment Ord
Bldg Strl Fab
Bldg Strl Supply
Tech. Strl Supply
Strl Erection
Mech. Eqpt supply
Elect. equipment Supply
Mech. Eqpt erection
Electrical Eqpt erection

Proj. Mgr MP Singh, DGM- 2678

Unit

Total vol.

M3
M3
T
T
T
T
T
T
T
T
T
T

9700
5100
558
200
1600
1600
55
1655
558
200
558
200

Comntd.
0
2
0
0
2
Oct15

Plan

Prog.

25
0.5
2
10
3

U/S

Review meeting held on 29.08.15

2
0
1
0
3
Cum Prog.

9700
5000
558
200
1600
1600
55
1654.5
556
200
546
197

All 133 nos. gallery erection completed on 05.02.15.Electrical eqpt supply


completed on 11.03.15. Conveyor belt laying in RMP-2 started on 28.04.15. 2
nos. transformer (2 MVA) charged at S/S of RMP-2 end on 03.07.15 & 04.07.15.
No load trial taken for 2 nos. motors at tail end on 11.07.15 & another 1 no. on
14.07.15.MCC Panel of RMP-III end charged on 13.07.15. No load coupled trial
(motor with gear) of 2 nos motors at head end (RMP-II) taken on 15.07.15. &
no motor at tail end (RMP-III) taken on 16.07.15.

C 19

Erection, testing & commissioning of


plant & eqpt. of BOF & CCP complex
(Pkg.-131) Consultant MECON

Out of total 37323 T, 400 T equipments erected. The package is


Foreclosed as terminated.

Agency- M/s Bridge & Roof, Kolkata


Cost : Rs. 53.02 Crs. Contract signed : 03.11.11
Compl Dt: 28.02.13

C 20

Erection, Testing & Commissioning of


Plant & Equipment of BOF and CCP
complex (Pkg. 131 A)
(Consultant MECON)
Agency-M/s Essar Projects (I) Ltd.
Contract signed: 12.0314;
Contr. Compln. : 11.05.15
Likely Completion : Jun16
(CK1 - Nov'15, CK2 - Dec'15, CV1 - Feb'16,
CV2 - Jun'16, Converter 1 - Mar'16,
2 - May'16, 3 - Jun'16)
Cost: Rs 84.59 Crs.
Proj. Mgr K. Rajsekhar, AGM- 0518

C21 Pneumatic Sample Transport System


for BOF, CCP & SRU in SMS-III (Pkg.134)

BOF: SRU dedusting system erection in


progress. Secondary dedusting raw gas duct
erection in progress.
4 T mech eqpt erected. 0 T Elect. Eqpt.
Erected.
CCP:
CK1- Pump house, hydraulic room, water
room piping erection work in progress.
Finishing activity in roller table in progress.
CV1- Alignment of roller table and cooling
bed is in progress.
Erection of mould oscillator and tundish
relining stand erection of CK1 & CK2 in
progress.
1 T mech. Eqpt erected. 1 T Elect. Eqpt.
Erected.

Design Engg. in progress.

Activity

Unit

Total vol.

Oct15
Plan

Mech. Eqpt. Erection

Cum Prog
Prog.

Review meeting held on 25.05.15

34535.6
21293.03
13242.57
2460.74
1605.93
854.81
10495.21
5700
4795.21

33
14040
729
BOF
T
24
8628.5
459
CCP
T
9
5411.5
270
Elect. Eqpt. erection
T
43
8
1235
BOF
T
13
2
650
CCP
T
30
6
585
Refractory
T
0
BOF
T
0
CCP
0
T
Converter-2- Top cone erected on 30.01.15. Converter-3- Erection of Trunnion ring
assembly completed on 16.02.15. Converter-3 bottom Shell erection completed on
28.02.15. Finfan Cooler erected at Pump house on 17.03.15. Converter-2 tilting
device installation done on 14.09.15.

Contract signed with M/s Kerry Engg, Visakhapatnam on 25.06.13.

Consultant- MECON. Agency- M/s Kerry Engg


Cost Rs 2.90 Crs.. Contract Signed on 25.06.13.
Cont.Compl. 24.03.14. Likely cmpn. : Mar16
Proj. Mgr.- Alok Rai, DGM-0792

10/9/2015

Page : 17

Review meeting held on 25.07.15

SN
SCHEME / PACKAGE
C 22 Illumination,Earthing & lighting protection system

PROGRESS ON DATE

Design Engg. in progress.

for SMS-3 (Pkg-127) (Consultant- MECON);


Agency M/s ETA Engg., Kolkata.
Contract signed: 26.11.14; Contr. Compln. :
Review meeting held on 08.10.15.
25.02.16; Cost Rs.15.47 Crs.
Likely Completion : Mar16
Proj. Mgr MP Singh, DGM- 2678

Total

Submtd

BE (A)

Propane storage & handling system (Pkg.032)

Design Engg. in progress.

Design Engg. in progress.

DE I
TOTAL

47
72

27
44
Unit

9
19
Total vol.

0
0

10
12

Activity

Cost: Rs 39.92 Crs.


Contract Signed on 31.08.12.

Drawing

Total
14
7
54
41
116

Drawing

Total

299.15

299.15

Appd/KFR

12
5
28
11
56
Unit

5
1
15
6
27
Total vol.

M3
M3
T
T
T

3400
1070
300
50
50

Submtd

Appd/KFR

AAN

Comtd.

1
0
0
0
1

6
3
5
2
16

Oct15
Plan

Prog.

AAN

6
92
75

0
1
0

221

188
Unit

173
Total vol.

Activity

Mech. Eqpt. Ordering


Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply

T
T
T
T

885

Prog.
0

6
103
79

Likely Completion : Mar16


Proj. Mgr Alok Rai, DGM- 0792

Submtd

299.15

9
116
96

DE I
TOTAL

Compl.Dt. 28.02.14

T
T
T

8
13
Cum Prog

Oct15
Plan
0

Comntd.

Plan
0

885

175

U/S

Review meeting held on 01.09.15

0
1
8
1
10
Cum
Prog

2700
200
200
10
0
U/S

0
6
2

0
4
2

6
Cum Prog

Oct15

175

Review meeting held on 08.10.15

DE (A)

Consultant MECON

BE (A)

Agency- M/s Voltas, Jamshedpur.

U/S

Earthwork
Concreting
Mech. equipment Ord
Elect. equipment Ord
Bldg Strl Fabrication

C 24 Air Conditioning and Ventilation System For


BOF & CCP Complex (Pkg.125-01)

Comntd.

13

Activity

Proj. Mgr - N.V.Joshi, DGM-0799

AAN

DE (A)

BE (A)
BE I
DE (A)
DE I
Total

Contract no . TK/2011/343
Consultant- MECON
Agency M/s OGPE
Cost : Rs. 9.18 crs
Cont. signed: 19.04.11
Effective Dt. of contract: 16.03.11
Contl. completion: 15.03.12
Likely Completion : Dec15

Appd/KFR

BE (I)

Elect. Eqpt. Ordering


Elect. Eqpt. Supply
Elect. Eqpt. erection

C 23

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawing

Prog.
-

Review meeting held on 29.09.15

885
31.67

78

352
0

Mech. Eqpt. Supplied started from 16.10.14. Electrical ordering startred from 04.03.15.

C 25

Drawing

Fire Protection System For BOF and CCP


(Pkg. 126-01) Consultant MECON

Total

BE (A)
BE I
DE (A)
DE I
Total

Agency-M/s Unitech Machines Ltd.,Gurgaon


Cost : Rs. 11.64 Crs.
Contract signed: 02.04.13
Cont. Compl. : 01.04.14.
Likely Completion: Mar16
Proj. Mgr V.K.Rai, DGM- 0563

13
39
48
3
103
Activity

Mech. Eqpt. Ordering


Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply

Submtd
13
36
45
3
97
Unit

T
T
T
T

Appd/KFR
13
33
38
2
86
Total vol.
696.7
5.1
696.7
5.1

AAN

Comtd.

0
0
0
0
0
Oct15
Plan

0
3
7
1
11
Prog.

0
0
0
0

U/S
0
0
0
0
0
Cum
Prog

661.5
4.86

Engg. meeting held at MECON, Ranchi during 22-23.05.14.

C26 Relocation of Flare Stack # 3 of Gas


Cleaning Plant (GCP) of Converter Shop
in SMS-II (Consultant BEDB) Agency-HSCL
Cost-Rs 1.51 Crs. Award Dt. 28.05.13.
Compl. Dt. 27.05.14.Likely Completion :
Proj. Mgr. VK Rai, DGM-0563

Oct15

Flaring Started and in progress.

Activity

Strl Fabrication
Strl Erection

Unit

T
T

Flaring Started from 14.08.15.

10/9/2015

Page : 18

Total vol.

350
350

Oct15
Plan

Prog.

Cum
Prog

350
350

Review meeting held on 06.06.14.

SN

SCHEME / PACKAGE
D 1 Installation of Buffer Vessels and
Pressure Reducing & Metering Stn. for
Oxygen, Nitrogen & Argon (Pkg. 075B)
Consultant-MECON,
AgencyM/s Blue Star Ltd, Kolkata & BHPV,
Visakhapatnam
Contract price Rs. 51.39 Crs.
Contract signed : 07.07.12 (Eff. date
06.07.12)
Contr. Completion : 05.07.13
Likely Completion: Dec.15
Proj. Mgr. R.K. Baghel, DGM, 3571

Important activities completed / Highlights

D2 Instn. Of Oxygen Evacuation Facilities


for 2x1250 TPD New Oxygen Plant
Consultant CET
Agency: M/s Bluestar, Kolkata.
Contract value: Rs 29.26 Crs.
Contract Signed : 18.03.11
Cont. Completion : 17.03.13
Likely Completion: Oct.15
Proj. Mgr. R.K. Baghel, DGM, 3571

Important activities completed / Highlights

D3 Augmentation of Propane Storage &


Distribution System for SMS-II
(Consultant-BEDB)

PROGRESS ON DATE

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings
BE (A)
DE (A)
DE I

Total
12
91
58
161

Total
Additional drawings
DE (A)
71
DE I
14
Total
85
Activity

Submtd.

Appd/KFR

AAN

12
91
55
158

10
80
45
135

0
8
1
9

2
3
9
14

0
0
0
0

70
9
79
Unit

65
8
73
Total
vol.
14050*
1673*
292*

3
0
3

2
1
3

0
0
0
Cum.
Prog.
13950
1542
248

Earth work
Concreting
Tech. Strl. Fabrication

M3
M3
T

Tech. Strl. Erection


Mech. eqpt. Ordering
Elect. eqpt. Ordering
Mech. eqpt. Supply
Elect. eqpt. Supply
Mech. eqpt. erection
Elect. eqpt. erection

T
T
T
T
T
T
T

292*
1860*
2.2*
1860*
2.2*
1860*
2

Comntd.

Oct15
Plan
100
50
4

Prog.

U/S

192

0
0
1.5
0.2
62
0.4

1860
2.2
1847
1.8
1765
1.6

Review meeting held on 03.09.15

*SCOPE RVISED
SCHEME.

AS

PER

CHAGE

ORDER

Erection of all 20 Vessels completed by 15.04.14. 2 nos. 100 m3 Argon, 6


nos. Erection & hydraulic testing of all 20 nos. vessels completed on
18.09.15.
Drawings
BE (A)
DE (A)
DE I
Total
Activity

Total
10
138
133
281

Submtd.
10
138
133
281
Unit

Appd/KFR
10
138
133
281
Total
vol.
9500
950
410

AAN

Comntd.

0
0
0
0

0
0
0
0

U/S

Plan
-

Prog.
-

0
0
0
0
Cum.
Prog.
9500
950
410

410

Oct15

Earth work
Concreting
Tech. Strl. Fabrication

M3
M3
T

Tech. Strl. Erection


Mech. eqpt. Supply
Elect. eqpt. Supply
Mech. eqpt. Erection
Elect. eqpt. Erection

410

T
T
T
T

561.3
2
561.3
2

1.3
1.3
-

Review meeting held on 03.09.15.

560
2
560
2

All 97 Towers & 19 Bridges supplied & erected by 15.02.14. Structural


fabrication and erection completed by 15.02.14. Civil work completed
by 15.03.14.
List of drawings submitted by party & approved by BEDB.Dispatch Kick-off meeting held on 21.10.14.
clearance of major equipments given y BSP.

Agency: M/s Gas Projects, Mumbai

Contract value: Rs 73.41 Lakhs


Contract Signed : 12.09.14
Cont. Completion : 11.03.15
Likely Completion: Oct.15
Proj. Mgr. R.K. Baghel, DGM, 3571

10/9/2015

Page : 19

SN

SCHEME / PACKAGE

E
E1

SP & OHP Zone


Installation of 2nd Sinter M/c (360M2)
for 2nd Strand in SP-III (Pkg.-020)
Consultant MECON
(Agency M/s L&T-Outotec)
Contract signed: 28.08.10,
Cost: Rs. 688.02 Crs.
Contr. Completion: 27.12.12.
(Proj. Mgr. P.K. Sutaone, DGM) 22567
*- Scope revised.

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

Defect rectification job is in progress.


Erection of balance equipment in
progress.

Proj. Mgr. Mr. P. K. Sutaone, DGM


22567.
*- Scope revised
to

M/s

Drawings

Comntd.

119
1
62
18
200

31
44
26
34
135
Oct.15

Total vol.

M3
T

Total

Plan

*46800
1770

Submtd.

122
6
65
142
335

BE (Appl.)*
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

Prog.

Appd/KFR

120
6
64
135
325

Activity

M3
T
T
T
T
T
T

AAN

119
5
58
130
312

U/S
1
5
8
4
18
Cum.
Prog.

46800
1769

0
0
3
0
3
Plan
25
3
82
1
3
68
12

The following activities have been completed.


Activity Unit
Progress
Piling
No.
2047
Earth work M3
186000
Bldg. strs. Fabn
T
11650
Techno. strs. Fabn
T
2000
Mech. Eqpt Supply (Imp.)
T
1200
Mech. Eqpt Supply (Indig.)
T
10730
Elect. Eqpt Supply (Imp.)
T
70
Elect. Eqpt Supply (Indig.)
T
1700
Refractory Supply (Imp.)
T
15
Refractory Supply (Indig.)
T
980
Refractory erection
T
995
Bldg. strs. Erection
T
11650
Techno. Strs. erection
T
2000
Mech. Eqpt. Erection
T
11930

Review meeting held on 24.12.14.

Comntd.

1
1
3
4
9

Oct.15

Total
vol.
*1400
*383
* 461
*267
*20
*267
*20

Unit

Concreting
Bldg. strs. Erection
Techno. Strs. Erection
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Scintillant

on

Drawings

Total
21
2
57
72
152

Activity

Contr. completion: 18.12.11.

Concreting
Techno. Strl erection
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Proj. Mgr. Mr. P. K. Sutaone, DGM


22567.

Agency - M/s Primetals Technologies India


Pvt. Ltd., Kolkata & M/s Primetals
Technologies, Austria, Consultant-CET,
Cost: Rs. 26.15 Crs. & Euro 626,048.00
Contract signed on: 13.08.15
Contr. completion: 12.12.16
Proj. Mgr. Mr. P. K. Sutaone, DGM 22567.

Unit

AAN

Stage-II approved on 06.05.10, Sanctioned Cost Rs. 40.72 Crs.

BE (Appl.)*
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

Consultant-MECON

Revamping of Sinter Cooler of SP-3

116
113
1599
913
2741

Prog

U/S

0
0
0
1
1
Cum.
Prog.
1375
380
379
266
17
199
8

Slab cast at +19M level of screen Bldg. on 04.04.15.


RPN issued
23.12.14.

Cost: Rs. 7.99 Crs.


Contract signed on: 19.06.10,

E3

Appd/KFR

267
163
1695
969
3094

Hot trial done on 19.03.14. PAC (of part facility) issued on 11.07.14 w.e.f. 11.04.14.
2nd Sinter M/c of SP-3 dedicated to nation by Steel Secretary on 17.10.14.
Commissioning certificate issued on 19.01.15 w.e.f. 28.11.14. Emergency Sinter
Storage Bldg. (ESSB) - Conveyor route of ESSB started on 15.04.15. Sinter taken in
one hopper of ESSB.

Modernization of SP-II (Pkg.-021) (Consultant MECON)


New Cold Sinter Screening System &
Conveyor SS-1 & SS-2 Conveyor width
Hearth layer feeding arrangement
extension work is in progress.
under Modernization of SP-II (Pkg.-21
Foundation for take-up tower for SS-1 &
A)
SS-2 conveyor is in progress.
Agency: M/s Petro General Engg.
works & M/s Sanmathy
Consultant-MECON
Contract signed: 05.06.10,
Cost: Rs. 22.86 Crs.
Contr. completion: 04.12.11.

ESP Based Plant De-dusting system under


Modernization of SP-II (Pkg.21 D)
(Agency- M/s Scintillant Projects)

Submtd

267
279
1695
969
3210

Concreting
Elect. Eqpt. Erection

Likely Completion: Nov.15

2.2

Total

Activity

Commissioning certificate issued


w.e.f. 28.11.2014.

E2
2.1

Drawings
BE (Appl.)*
BE (Info.)
DE (Appl.) *
DE (Info.) *
TOTAL

COMMITMENT AS PER LATEST MOM

Unit
M3
T
T
T
T

Submtd
21
2
56
70
149

Total
vol.
400
60
19.25
582
19.25

Appd/KFR

AAN

21
2
56
66
145

0
0
0
0
0
Oct.15

Plan
0
0
0
0
0

Comntd
0
0
0
4
4

Prog

U/S
0
0
0
0
0

Cum.
Prog.
350
57
18.75
543
13

RPN issued to M/s Scintillant on 23.12.14.


Contract signed with Consortium of M/s Primetals Technologies India
Private Limited, Kolkata and M/s Primetals Technologies, Austria GmbH,
Linz, Austria on 13.08.15 at a cost of Rs. 26,15,55,819/- and Euro
626,048.00 with a completion period of 16 months.

10/9/2015

Page : 20

The following activities have been completed.


Activity Unit
Progress
Earth work M3
870
Bldg. Strl. fabrication
T
8
Bldg. Strl. Erection
T
8
Techno. Strl fabrication
T
60
Mech. Eqpt. Ordering
T
582
Elect. Eqpt. Ordering
T
19.25
Mech. Eqpt. Supplied
T
582

Review meeting held on 29.09.15.

SN

SCHEME / PACKAGE

E4

Augmentation of OHP Part-A (Pkg.


060)

PROGRESS ON DATE
Commissioning activity in progress.
Defect rectification job in progress.

(Agency M/s HEC)


(Consultant MECON)
Contract signed on: 09.04.08,
Contr. Compl.: 08.04.10
Cost: Rs 184.74 Crs.
(Proj. Manager Mr. R.K. Malve DGM),
57068/22684

*- Scope revised

E5

Augmentation of Raw Material receipt


& handling facilities with New OHP,
Part-B (Pkg. 061)
Agency M/s EPI
Consultant MECON
Contract signed: 30.04.10,
Cost: Rs. 525.86 Crs.
Contr. Completion: 29.04.12.
Likely completion : Nov.15
(Proj. Manager-A.K. Bhatta DGM),
Mob. No. - 22169
*- Quantity revised as per available drgs.

Civil work for Conveyor Z & L - series is


in progress.
Civil work for LT substation Bldgs. are in
progress.
Erection of Bldg. structures is in
progress.
Mech. Eqpt. Erection at Stacker & Reclaimer yard in progress.
Techno. Strs. Erection at Yard area, Zseries conveyor & Track Hopper are in
progress.
Power & control cable laying at
Wagon Tippler complex is in progress.
Elect. Equipment erections at LTSS Bldg.
No. 1 & 2 are in progress.
8 M3 Concreting completed.
26 T Bldg. Strs. Erected.
5 T Techno. Strs. Erected.
50 T Elect. Eqpt. Ordered.
Review
Meeting
scheduled
09.10.15.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd. Appd/KFR
AAN
Comntd
U/S
122
0
2
2
BE (Appl.)*
126
126
22
0
0
0
BE (Info.)
22
22
293
0
0
2
DE (Appl.) *
295
295
214
0
1
0
DE (Info.) *
215
215
TOTAL
658
658
651
0
3
4
Oct.15
Cum. Prog.
Total
Activity
Unit
Plan
Prog.
vol.
Earth work
M3
*68050
37
68013
Concreting
M3
*19700
1
19699
Bldg. Strl. fabrication
T
*3451
1
3450
Bldg. Strl. Erection
T
*3451
30
3340
Tech. Strl. Erection
T
*503
3
500
Mech. Eqpt supply
T
* 2600
10
2590
Mech. Eqpt Erection
T
* 2600
40
2458
Elect. Eqpt Erection
T
*1960
40
1717
WT No. 5 inaugurated by Chairman on 18.06.13. PAC (part facilities New Wagon
Tippler No. 5 with SAC, belt conveyors J1C1/C2, J3C3/C4, J3SC3/SC4, J4C3, J4SC3,
J5C3 with mobile tripper, STC-3 & TBS, JH-5B, HTSS-54, LTSS-1&2 & LTSS-3 &4) issued on
27.08.14 w.e.f. 14.07.14. Hydraulic pressure test of fire hydrant pipeline at Stacker &
Re-claimer yard area completed on 28.08.15. Trial run of Twin Boom Stacker at load
taken on 11.09.15.
Drawings
Total
Submtd
Appd/KFR AAN
Comntd
U/S
BE (Appl.) *
334
293
227
40
16
10
BE (Info.)
25
18
17
0
1
0
DE (Appl.) *
467
467
274
60
88
45
DE (Info.) *
642
492
444
10
26
12

1468

TOTAL
Activity
Earth work
Concreting
Bldg. strs. Fabrication
Bldg. strs. Erection

Techno. Strs. Fabrication


Techno. Strs. Erection
Mech. Eqpt Ordering
Elect. Eqpt Ordering
Mech. Eqpt Supply
Elect. Eqpt Supply
Mech. Eqpt Erection

on Elect. Eqpt erection

1270

962

Unit

Total vol.

M3
M3
T
T
T
T
T
T
T
T
T
T

*375000
*100888
*14597
*14597
*4487
*4487
*3946
*1589
*3946
*1589
*3946
*1589

110

131

Oct.15
Plan
Prog.

1140
845
1306
1164
356
597
66
100
350
200
464
250

132
269
244
30
50

67
Cum.
Prog.

372780
98143
10519
6841
3808
495
3200
1150
3145
1047
2899
115

WT Complex: - Rotational drive system flushing jobs of WT completed on


18.06.15. No load rotational trial of Wagon Tippler (only upto 45 degree)
taken on 24.06.15. Long travel trial run, movement of Boom Conveyor &
Luffing of Boom of Stacker No. 4B conducted on 26.08.15. Erection of 2
spans Conveyor gallery of Conveyor Z2 completed on 12.09.15 & on
18.09.15. Trial & Testing of Twin Boom Stacker No. - 5B conducted successfully
on 30.09.15. Erection of 1 span Conveyor gallery of Conveyor Z-15 completed on
05.10.15.

10/9/2015

Page : 21

Review meeting held on 13.09.14

The following activities have been completed.


Activity Unit
Progress
Tech. Strl. fabn. T
503
Elect. Eqpt supply

1960

Conveyor J9AC1 & drive system of


Conveyor J5C2 tested in auto mode on
16.07.15.
PAC of bucket wheel

reclaimer issued on 12.08.15 wef


27.07.15.
Review meeting held on 20.07.15.

SN

SCHEME / PACKAGE

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

COMMITMENT AS PER LATEST MOM

F. BF ZONE

F1

Installation of BF-8 Capacity 2.8 MT /


Annum, useful vol. 4060 M3 (Pkg.-010)
(Agency M/s Paul wurth /L&T)
Consultant - MECON
Cost: Rs. 1591.32 Crs
Contract signed: 30.08.10,
Contr. completion: 29.12.12
Likely completion: Dec.15 (Furnace Heating
& Charging)

Drawings

Total

BE (Appl.)*
BE (Info.) *
DE (Appl.) *
DE (Info.) *

517
1204
3006
3504
8231

TOTAL
Activity

Unit

Submtd

Appd/KFR

501
1159
3004
3443
8107

473
1092
2712
3282
7559

Total vol.

AAN

7
2
85
26
120

Comntd.

Oct.15
Plan

U/S

21
59
135
105
320

Prog

0
6
72
30
108

Review meeting held on


25.03.15.

Cum. Prog.

Earth work
M3
*260000
260000
Concreting
M3
* 81000
300
61
80383
Bldg. Strs. Fabrication
T
*24785
24785
Bldg. Strs. Erection
T
*24785
250
38
23647
Techno. Strs. Fabrication
T
*20404
20404
Techno. Strs. Erection
T
*20404
350
29
19350
Mech. Eqpt Ordering (Imp.)
T
*4223
4223
Mech. Eqpt Ordering (Indig.)
T
*8757
8757
Elect. Eqpt Ordering (Imp.)
T
54
54
Elect. Eqpt Ordering (Indig.)
T
*510
510
Refractory Ordering (Imp.)
T
*2144
2144
Refractory Ordering (Indig.)
T
21022
600
20422
Mech. Eqpt Supply (Imp.)
T
*4223
0
4210
Mech. Eqpt Supply (Indig.)
T
*8757
25
20
8681
Elect. Eqpt Supply (Imp.)
T
54
0
51
Elect. Eqpt Supply (Indig.)
T
*510
5
502
Refractory Supply (Imp.)
T
*2144
2144
Refractory Supply (Indig.)
T
21022
350
50
19850
Mech. Eqpt. Erection
T
*12980
445
28
11806
Elect. Eqpt. Erection
T
*564
5
552
Refractory Erection
T
23166
650
62
21319
1 No. 2 MVA Transformer (56F-2T) 11KV/0.433KV at Stock House charged from HTSS- 56 feeder No. 74 on 31.08.15. Erection of
Tuyere Stock & ESP duct at Stock House completed on 31.08.15. Casting of 1st floor slab of TRT Electrical Control Room
completed on 10.09.15. 1 No. 2MVA Transformer (56F-1T) 11KV/0.433KV at Stock House along with PCC56F charged from
HTSS-56, feeder No.-15 on 11.09.15. Casting of slab of DG set room completed on 26.09.15. Leakage testing of cooling water
circuit No. 3 of BF-8 completed on 03.10.15. 1 No. 2 MVA Transformer (57A-1T) 6.6KV/0.433 KV, at Central Contrl Room along
with PCC 57-A charged from HTSS - 57, feeder No. - 617 on 06.10.15.
Up-gradation of Stoves No. 10, 11 & 12 of Blast Furnace #4 (Proj. Mgr. S.K. Ghosh, DGM) 20274 (Consultant CET), Stage-II approval received on 12.03.13 at a sanction cost of Rs. 70.65 Crs.
Oct.15
HTS design for Achieving Higher Hot Blast
Total issued drgs by CET -150/159 Nos. (52/53 Strl,
Review
Meeting
held
on
Activity
Unit
Total vol.
Cum. Prog.
Plan
Prog
Temperature (Pkg. WP-01)
15.07.15.
all 7 Utility, 50/55 Refractory, 16/17 Civil & 25/27
Award letter No.: 5(2934)/349,
Earth work
M3
1900
0
200
Mech.).
Civil job for 2 Nos. CA fan
Date of Award :16.03.13
M3
377
75
80
Drgs status (Evotechs Scope) 50/83 submitted, Concreting
foundations
shall
be
Agency : Evo Tech, Bhilai Award value Rs. 18.44 Crs,
Techno. Strl Fabrication
T
995
60
165
31 Appd, 1 AAN, 18 commented.
completed by 01.08.15 yet
Contr. Completion: 15.11.14
Techno. Strl Erection
T
995
75
165
Erection of Stove shell is in progress.
to be done.
Likely completion: Dec.15
Preparation for casting of CA fan foundation is Pkg. No. SP-02 Stove Refractory Material (18 items) 2098.55T/7274.47T Supplied.
Pkg. No. SP-03: -16.2/48.6T Columns, 17.1/51.3T Girders & 27.9/83.7T Grids supplied.
in progress.
(Proj. Mgr. Mr. B.K. Prasad DGM) 20271
*- Scope revised.

F2
2.1

Bustle pipe: PCPF brick lining work is in progress.


Dense brick lining from Hot Blast outlet of Stoves
to Hot Blast Main is in progress.
Dry slag pit: Heat resistance concreting at North
side pit No. 1 is to be done.
Erection of expansion joint in Gasline & Cooling
circuit pipeline at BF Shell in progress.
Erection of supporting strs for bag filters at PCI
area in progress.
INBA - Erection of structures & equipment are in
progress.
Stock House area Erection of Screens, under
size Chute, Fine conveyor gallery in progress.
Laying of cable from HTSS-56 is in progress.
Erection of hydraulic system is in progress.
Erection of vibro feeder at Stock House is in
progress.
Gas duct erection in progress.
Erection of valves at BF gas for stove is in
progress.
Erection of Gas Main at TRT area & Shuttle
conveyor at Stock House is in progress.
Testing of mixed gas line loop-2 for stove No. 2 is
in progress.
5 M3 Concreting completed.
5 T Bldg. Strs. Erected.
5 T Techno. Strs. Erected.
5 T Mech. Eqpt. Erected.
10 T Refractory erected.

Pkg. No.SP-04: All 15 Stove Valves, Lubrication & Hydraulic system (1 No. each) supplied.
Pkg. No. SP-05 Expansion joints: - All 5 Nos. Expansion joint supplied.

2.2

Combustion Air Fans & Gas Mixing Station


(Pkg-TK-06)
Contract signed on: 13.04.13
Agency: M/s TLT Engg India Pvt. Ltd., Kolkata,
Cost: Rs. 4.72 Crs.
Contr. Completion: 12.07.14

Likely completion: Mar.16

Drawings
DE (Appl. Cat.)
DE (Info. Cat.)
TOTAL

Total
25
25
50

Activity

Submitted
25
24
49

Page : 22

Total vol.

AAN
1
1
2

Commented
0
3
3

Oct.15

U/S
1
0
1

Cum. Prog.
Plan
Prog
Mech. Eqpt Supply
T
43.5
43.5
Elect. Eqpt. Supply
T
22.7
22.7
11 No. BE (Appl.) & 3 No. BE (Info). Drgs approved. All Mech. & Elect. Eqpt. Ordered & supplied.

10/9/2015

Unit

Apprd /KFR
23
20
43

Review Meeting held on


11.04.14.

SN

2.3

SCHEME / PACKAGE

Electrical, Instrumentation & Automation


System (Pkg-TK-07)
Contract signed on: 24.04.13
Agency: L & T, Kolkata, Cost: Rs. 8.36 Crs.
Contr. Completion: 23.12.14

PROGRESS ON DATE
Design
engineering,
equipment
ordering & supply is in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

BE
DE (Apl. Cat.)
DE (Info. Cat.)
TOTA

14
58
31
103

Likely completion: Dec.15

Submitted

Approved /KFR

AAN

Commented

U/S

14
52
15
81

13
39
5
57

1
5
2
8

0
6
7
13

0
2
1
3

Activity

Unit

Total vol.

T
T

* 64
* 64

Elect. Eqpt. Ordering


Elect. Eqpt Supply

Oct.15

held

on

Review meeting
09.07.15.

held

on

Review Meeting
05.01.15.

held

on

Cum. Prog.

Prog

Plan
0
0

Review meeting
30.10.14.

61.5
57.4

7 Nos. Ventury supplied at site.


F3

Installation of Hot Metal Handling System


For Blast Furnace (Pkg-031)
Consultant - MECON
(Agency M/s Qinhuangdao Qinye Heavy Ind.
with Associated Industrial Furnace,
Cost: Rs. 108.20 Crs.
Contract signed: 10.09.10,
Contr. completion: 09.05.12
Likely completion: Oct.15
(Proj. Mgr. Mr. B.K. Prasad DGM) 20271

Rail
Laying
at
TLRS
(566
RM
completed).
Sheeting job (6410 Sq. M out of 7000
Sq. M. completed).

*- Scope revised.

Drawings

Total

BE (Appl. Cat.)*

78
110
94
370
652

BE (Info. Cat.)*
DE (Appl. Cat.)*
DE (Info. Cat.)*
TOTAL

Submitted

Approved /KFR

AAN

Commented

U/S

77
110
85
370
642

62
110
75
368
615

15
0
1
0
16

0
0
9
2
11

0
0
0
0
0

Activity

Unit

Total vol.

Earth work
Concreting
Bldg. Strs. Fabrication
Bldg. Strs. Erection
Techno. Strs. Fabrication
Techno. Strs. Erection
Mech. Eqpt Ordering (Indig.)
Elect. Eqpt Ordering (Indig.)
Mech. Eqpt Supply (Imp.)
Mech. Eqpt Supply (Indig.)
Elect. Eqpt Supply (Imp.)
Elect. Eqpt Supply (Indig.)
Refractory Supply (Imp.)
Refractory supply (Indig.)
Mech. Eqpt. Erection
Elect. Eqpt. Erection

M3
M3
T
T
T
T
T
T
T
T
T
T
T
T
T
T

*12000
*4700
*875
*875
*265
*265
*370
100
2200
*370
25
100
*1474
717
*2570
125

Oct.15

Plan

Cum. Prog.
Prog.

0
55
3
25
6
0
-

10990
4622
875
872
265
190
364
100
2200
295
25
75
168
2308
54

0
2

All imported items 2200 T Mech. Eqpt. & 25 T Elect. Eqpt. Ordered. Refractory ordering
(Imported & Indig.) completed. Erection of all 12 Nos. TLC (Torpedo Ladle Car)
completed by 31.05.15.

F4

Modification of Stack Cooling system of BF


No. 7.
Consultant CET
Agency M/s Danieli Corus (Netherlands), M/s
Danieli Corus India (New Delhi) & M/s Beekay
Cont. cost: Rs. 11.023 Crs & Euro 28.69 Lakhs.
Contract signed: 16.09.13
Contr. completion: 15.08.14
Likely completion: 28th Feb.16
(Proj. Mgr. Mr. P.K. Ghosh DGM) 21144

*- Scope revised.

Drawings
BE (Appl. Cat.)
BE (Info. Cat.)
DE (Info. Cat.)
Total

Total

Submtd

Appd/KFR

6
20
20
46

6
20
20
46

6
20
20
46

Activity

Unit

Refractory Ordering (Indig.)


Refractory Ordering (Imported)
Mech. Eqpt Supply (Indig.)
Mech. Eqpt Supply (Imported)
Elect. Eqpt Supply

T
T
T
T
T

Total vol.

*40
*107.8
61
273
0.17

AAN

Comntd.

U/S

0
0
0
0

0
0
0
0

0
0
0
0
Oct.15

Plan

Prog

0
-

Cum. Prog

0
107.8
61
273
0.17

All 6 Nos. BE (Appl. Cat.), 20 Nos. BE (Info. Cat.) & 20 Nos. DE (Info. Cat.)
Drawings have been approved. All Elect. Eqpt. & Mech. Eqpt. (Indig. &
Imported) ordered & Supplied.

10/9/2015

Page : 23

SN

SCHEME / PACKAGE

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

F5

Installation of Cast House Defuming system


in Blast Furnace No.7 (Consultant CET)

Contract signed with Consortium of M/s Uniseven Engineering & Infrastructure Pvt
Ltd, Kolkata and M/s Soil & Enviro Industries Pvt Ltd, Kolkata on 22.08.15 wef
21.08.15 at a cost of Rs. 21,67,23,796/- with completion period of 12 months.

Agency- M/s Uniseven Engg. & Infrastructure


Pvt Ltd, Kolkata and M/s Soil & Enviro
Industries Pvt Ltd, Kolkata
Cont. cost: Rs. 21.67 Crs
Contract signed: 21.08.15
Contr. completion: 20.08.16
(Proj. Mgr. Mr. P.K. Ghosh DGM) 21144

F6
6.1

COMMITMENT AS PER LATEST MOM

Stage-II Approved on 16.02.11 at a cost of Rs. 21.27 Crs. (Rev. on 10.09.13) with completion period 14 months(Apr.12)
Rebuilding of Stove No. 18 of BF-6 (Consultant CET)
Total
Submtd
Appd/KFR
AAN
Comntd.
U/S
Electrical,
Instrumentation
&
Supply of balance Electrical equipment Drawings
20
20
16
1
3
0
Automation (Pkg-5)
(HT, LT Cable and Vacuum Contactor BE (Appl.)
DE (Appl.)
37
36
31
3
2
0
Agency: Hindustan Controls & Eqpt. P. Ltd.
Panel) is to be done.
Contractual cost: Rs. 2.53 Crs.
Contract signed: 18.03.11
Contr. completion: 17.05.12
Likely completion: Oct.15
(Proj. Mgr. V.K. Gawande, Sr. Mgr.) 22711

DE (Info) *
TOTAL

22
79

Activity

Likely completion: Dec.15


(Proj. Mgr. Mr. P. Subba Rao, DGM) 21090

Change
order
for
capacity MSDS-5:
enhancement of MSDS-4 & MSDS-5
Lighting jobs in progress.
under Augmentation of MSDSs -7 (Pkg.
70) Dt. Of issue of change order: 11.10.11,
Contract Price: 4.57 Crs.
Contractual Completion: 10.09.12.

Likely completion: Dec.15

*- Scope revised.

Unit

19
66

0
4

1
6

Oct.15

Total vol.

Plan

0
0

Cum. Prog.
Prog.

Elect. Eqpt Supply


T
24
1.5
22.5
Elect. Eqpt Erection
T
24
2
22
All Elect. Eqpt. Ordered. Trial of Gas Bleeder valve through PLC taken on 23.07.14.

G. POWER ZONE
Drawings
G 1 Augmentation of MSDSs & Installation MSDS-5:
BE (Appl. Cat.)
of MSDS-VII (Pkg.-070)
Lighting jobs in progress.
BE (Info. Cat.)
Contract No. TK-2008/282
Charging of outgoing feeders upto
(Consultant-MECON)
reactors are in progress (For sections 4, 5, DE (Appl. Cat.)
DE (Info. Cat.)
(Agency M/s Alstom)
6 & 9 - 13 feeders are charged).
TOTAL
Cont. signed on : 25.09.08
Activity
Contr. Completion : 24.09.10
Cost: Rs. 216.25 Crs.
Elect. Eqpt. supply
PAC issued on 19.03.15 w.e.f. 03.02.15.

20
76

Total

Submtd.

Appd/KFR

19
3
693
240
955

19
3
693
240
955

19
3
692
240
954

Unit

AAN

Comntd

0
0
1
0
1

0
0
0
0
0
Oct.15

Total vol.

U/S

Review Meeting held on 26.06.15.

0
0
0
0
0
Cum. Pro.

Plan
Prog
T
2425
1.5
2423.5
Mech. Eqpt. Erection
T
580
3
577
Elect. Eqpt. Erection
T
2425
25
2400
Preliminary Acceptance Certificate (PAC) for subject contract issued on 19.03.15
w.e.f. 03.02.15. Retrofit jobs - Door retrofit of 11KV reserve cubicle (panel) No. 41 at
MSDS-2 carried out on 19.06.15.
MSDS-4: Inauguration of MSDS-4 done by CEO, BSP on 29.10.13. 72 hrs. Trial run of all
3 units HVAC systems at MSDS-4 completed on 16.05.15.
MSDS-5: Charging of 50MVA Transformer (7T) with 11KV busduct on 05.09.15 &
50MVA Transformer (2T) with 11KV busduct on 09.09.15 completed. Charging of
11KV sections 7&8, 11KV Neutral Earthing Transformer (NET-7T) & 11KV Bus Coupler
(between section 6&7) with reactor completed on 11.09.15. HV test of HT cable to
existing 1 MVA Auxiliary Transformer-2T done on 11.09.15. 11KV sections 1, 2 & 3
through 11KV incomer-2 charged on 16.09.15. 11KV Out-going Feeder No.-148 for
Transformer Repair Shop charged upto reactor on 19.09.15. 16MVA Transformer-1T
charged on 22.09.15. Charging of 6.6 KV sections-1&2 done on 25.09.15. Charging
of Neutral Earthing Transformer for 6.6KV section-1 done on 29.09.15.
MSDS-7: 132 KV charged cable from MSDS-5to7 Normalised on 06.09.14. 2nd 1000
KVA transformer at MSDS-7 charged on 16.05.15.
Activity

Concreting
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Unit

Total vol.

M3
T
T
T
T

640
7.5
*40.7
7.5
*40.7

Oct.15

Plan

Prog

Cum.
Progress

1.5
1
2.1
1
2.7

GF, 1st & 2nd floor brick work, Ground floor flooring completed.

10/9/2015

Page : 24

638.5
6.5
38.6
6.5
38

SN

SCHEME / PACKAGE

G2

Installation of HT Distributed SubStation (Pkg. 071-A)


(Agency M/s ABB)
(Consultant-MECON)
Cont. signed on : 02.09.11
Contr. Completion : 01.05.13
Contract price: Rs. 339.61 Crs.
(Proj. Mgr. P. Subba Rao, DGM) 21090
Likely completion: Oct.15

*- Scope revised.

PROGRESS ON DATE
Eqpt. Erection at SSs - 43, 45, 47, 48, 56, 57,
60, 64, 65, 68, 71, 71A & 73 in progress.
Bldg. Structural Fabrication & erection job
is in progress.
HT panel testing at SS No. - 61 are in
progress.
11 KV Panel placements & interpanel
wiring at SS 63 are in progress.
19 M3 concreting completed.
17 T Bldg. Strs. Fabricated.
2 T Bldg. Strs. Erected.

G-3 Instn. of Boiler along with Steam TurboBlower Bldg. (Pkg.- 011-1A)
Consultant-MECON
Agency-M/s Fujian Long King Co. China
/Allied Energy Sys., New Delhi
Cont. price: Rs. 282.28 Crs.
Contract signed: 24.03.12
Contractual Completion: 23.11.13
Likely Completion : Dec15
(Proj. Mgr. : P. Subba Rao, DGM), 21090
* - Scope revised.

Total
129
2
1128
233
1492

BE (Appl. Cat.)*
BE (Info. Cat.)*
DE (Appl. Cat.)*
DE (Info. Cat.)*
TOTAL

Activity
Earth work
Concreting
Building strs. Fabrication
Building strs. Erection

Submtd. Appd/KFR
AAN Comntd
U/S
128
118
4
6
0
2
1
1
0
0
1037
949
37
50
1
229
195
34
0
0
1396
1263
76
56
1
Oct.15
Total
Cum.
Unit
Plan
Prog
vol.
Progress
M3 *133492 20000
518
96361
M3
*32091
2500
253
28183
T
*10400
2500
89
7655
T

Mech. Equipment ordering


Electrical eqpt. ordering
Mech. Equipment Supply

PAC (Part facility) for HT SS No. 43 &


48 issued on 26.12.14 w.e.f.
01.10.14.

T
T
T
T

Electrical equipment supply


Mech. Equipment Erection

STB building: Brick work in 0.0m, 18.0 m


level, Cooling water line nozzles / RCC
trench jobs, cable tray erection jobs, IPS
flooring jobs in progress. Aliignment of
pipe in STB-2 in progress.
Feed Pump House cum Electric annex
(FPH cum EA) Column & beams erection
job in progress.
All 3 boilers: Casing, structures, duct
work, pipe lines welding job in progress.
MCC Bldg. : 0.00 mtr slab PCC jobs in
progress.
CPRG: Trestles 3-19 erected. PGs & CGs
erected between Tr. Nos 3 to 14.
Boiler-1 & 2: ID Fan/FD Fan foundation
jobs (Total 8 fans) completed.
0.7 T eqpt erections completed.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

*10400
128
*6116
128
*6116
128
*6116

2000
24
41
4
2
30
1500

36

3
9
8
8
28
Oct15
Cum.
Activity
Unit
Total vol.
Prog.
Plan
Prog
31570
32500*
280
Earth work
M3
6.5
11752.4
12500*
250
Concreting
M3
18
3806.4
3916
146
Building strs. Fabrication
T
23.2
3649.8
3916
220
Building strs. Erection
T
5200
5393
100
Mech. Eqpt ordering
T
250
273
23
Elect. equipment ordering
T
4394
5393
450
Mech. equipment supply
T
242
273
25
Elect. equipment supply
T
800
2.7
4014.7
5393
Mech. equipment Erection
T
90
117
273
Elect. equipment Erection
T
Bi Flue Steel pipes erection completed for both Chimneys. Casting of 3.0 m RCC
floor completed for MCC cum CR building inside PBS-1 on 25.04.15. MV/LV
Switchgear building 8 m floor RCC slab cast on 20.05.15. MCC building 12 M slab
casting and 3 Nos. column casting done on 12.06.15. STB building 0-0 M level floor
casting done on 27.06.15. MCC control room building 16 M slab casting done on
17.07.15. CEA Inspection of electrical facilities carried out on 20.9.2015.

10/9/2015

250
84
563
420
1317

Page : 25

232
66
563
420
1281

174
46
397
358
975

8
1
8
4
21

25
1
22
7
55

Meeting

held

on

Review
05.09.15.

meeting

held

on

6426
104
6075
104
6050
43
2940

T
Electrical Eqpt. Erection
T
53
Total 6905 Fabricated Strs. Supplied. Substation No. 64: 4 (Four) Nos. 11 KV
sections charged through SS-64 Incomer-1 on 29.08.15. Final slab of Substation No.
61 cast on 29.08.15. Charging of cubicle No. 74 at Substation No. - 56 (for
Transformer 56F - 2T) done on 31.08.15. 2 Nos. outgoing cubicles (10 & 33) feeding
distribution transformers at SS-64 charged on 05.09.15. Erection of Cable Gallery No.
- 5 & 6 at SS-73 Cable route completed on 07.09.15. 6.6 KV sections at Substation
No. - 47 charged through 6.6KV Incoming cables (3 Nos. each) from MSDS-4 to SS
No. - 47 on 11.09.15. 9 Nos. outgoing transformer feeders for BRM charged from HT
Sub-station No. - 64 on 14.09.15. CEA Inspection of HT Substation No. - 65 carried out
on 20.09.15.
Drawings
Total
Submtd.
Appd/KFR
AAN
Comntd.
U/S
BE (A)
BE I
DE (A)
DE I
Total

Review
07.09.15.

SN

G4

SCHEME / PACKAGE
PROGRESS ON DATE
Instln. of Steam turbine generator, STG area
back pressure turbine generator,
Air Condition system erection, Pipe lines
Cooling water system & Power
erection in progress. Lighting job in
Evacuation Sys. (Pkg.- 011-1B)
progress.
Consultant-MECON
BPTG Area
Agency-M/s Triveni Engineering.
Cable termination, Civil finishing jobs,
Contract Price Rs. 170.50 Crs.
Under ground pipeline erection in
Contract signed: 19.01.12
progress.
Contractual Completion : 18.07.13
Cooling water pipe route
Likely Completion : Oct.15
CW pipeline erection in progress. Gallery
(Proj. Mgr. : P. Subba Rao, DGM), 21090
between TR 35 & 36 is in progress.
* - Scope revised
CWPH: Erection of 3 pumps completed.
Erection
of
4th
Pump
in
progress.Ventilation system jobs are in
progress.
Cooling Tower: Maintenance platform jobs
in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

Submtd.

BE (A)
BE I
DE (A)
DE I
Total

74
37
147
720
978

74
37
147
709
978

Activity

Appd/KFR
74
37
147
709
967

Unit

Earth work
Concreting
Piling
Building strs. Fabrication
Building strs. Erection
Mech. Eqpt ordering
Elect. equipment ordering
Mech. equipment supply
Elect. equipment supply
Mech. equipment Erection
Elect. equipment Erection

AAN

Total vol.

M3
M3
Nos.
T
T
T
T
T
T
T
T

41000
14061
340
1770 *
1770 *
1410
500
1410
500
1410
500

0
0
0
0
0

Comntd.
0
0
0
4
4

Oct15
Plan
Prog
1570
591
14
0
33
0
0
26
1
223
9
23.5

U/S

Review meeting held on 10.09.15.

0
0
0
7
7
Cum.
Prog.
39430
13477
340
1770
1749
1410
500
1404
499
1289
476.5

Mech Eqpt 1 Condenser, 1 Deaerator, 2 EOT cranes, 1 Turbine & PRDS


station, Ejector erected. Elect eqpt Alternator Reactors, HT reactor
isolator panel, DCS, AVR, Turbine control panel erected. PRDS and
Ejectors erected in BPTG. 25 MW STG rotated successfully on barring
gear on 29.5.2015. Casting of 25 MW SSF Over Head Tank foundations
done on 09.06.15. CEA Inspection of electrical facilities of Pkg 11-01B
carried out on 20.9.2015.
G5

Installation of 3x225 m3/h DM water DM Plant building :


Plant for PBS (Pkg.11-1C)
Civil finishing job in progress.
Consultant-MECON
Piping work in PBS-1 in progress.
Agency-M/s Technofab Engg Ltd/ M/s ARTES
Instrumentation & illumination
INGEGNERIA SPA, Italy
progress.
Contract Price Rs. 27.70 Crs.
Contract signed: 25.02.12
Contractual Completion : 24.02.13
Likely Completion : Oct.15
(Proj. Mgr. : P. Subba Rao, DGM), 21090

work in

Drawings

Total

Submtd.

BE (A)
BE I
DE (A)
DE I

60
8
220
112
400

60
8
219
112
399

Total

Activity

Appd/KFR
60
8
219
112
399
Unit

Total vol.

AAN
51
7
205
98
361

Comntd.
4
0
4
3
11

Oct15
Plan
Prog

U/S
4
1
9
10
24
Cum.
Prog.

Earth work
M3
7300
20
7205
Concreting
M3
3000
24
2922
Building strs. Fabrication
T
30
0
30
Building strs. Erection
T
30
0
30
Mech. Equipment ordering
T
650
0
650
Elect. equipment ordering
T
30
0
30
Mech. equipment supply
T
650
2
642
Elect. equipment supply
T
30
0
30
Mech. equipment Erection
T
650
5
638
Elect. equipment Erection
T
30
1
25
Plant is in operation for DM water supply to Coke Oven battery # 11
from stream B & C. Generation of DM water from stream B done for a
continous period of 32.5 Hrs.

10/9/2015

Page : 26

Review meeting held on 28.01.15.

SN

SCHEME / PACKAGE

G6

Installation of Turbo-blower for BF No. 8


(Pkg.-012)
Consultant-MECON
Agency: M/s BHEL
Contract price: Rs. 256.75 Crs.
Contract signed: 11.11.10
Contractual completion:10.02.13
Likely completion: : Dec.15
(Proj. Mgr. : P. Subba Rao, DGM), 21090

PROGRESS ON DATE
Unit#1- cold blast pipe line jobs & oil line
jobs in completion stage. Common cold
blast collector supply to BF#8 - pipe line
erection job is in completion stage.
Unit#3- Condenser surge pipe drain pipe
line modification work U/P. CondenserImpulse tubing jobs in progress. Oil
flushing in progress. Cold Blast Line
Bellow
erection
job
in
progress.
Transmitters Governor- Oil tubing at 4.5
mtr under progress. TR.9 all transmitter
gland & termination work under progress
Instrument job & caliberation in progress.

COMMITMENT AS PER LATEST MOM

OVERALL STATUS AS ON DATE


Drawings

Total

BE (A)
BE I
DE (A)
DE I
Total

33
19
37
148
237

Submtd.
33
19
37
148
237

Activity
Earth work
Concreting
Piling
Mech. Eqpt. Ordering
Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply
Mech. Eqpt. Erection
Elect. Eqpt. Erection

Appd/KFR
29
18
26
130
203

Unit

Total vol.

M3
M3
Nos.
T
T
T
T
T
T

4800
1700
88
1590*
347*
1590*
347*
1590*
347*

AAN

Comntd.

1
3
0
1
7
4
0
16
8
24
Oct15
Plan
Prog
157
40.5
25
29.3
141

U/S

Review meeting held on 30.01.15.

0
0
0
2
2
Cum. Prog.
4643
1659.5
88
1590
347
1565
347
1560.7
206

Mech. Eqpt. Erected -- 3 turbines, 3 blowers, 3 condensers, 3 Hot wells,


3 steam ejectors, 3 gland steam condensers, 3 oil coolers, 3 oil tanks, 3
oil pumps stations. Suction air filter housing erected. CEP-1 & 2 RCC
trench completed.
H IATRS Zone
H-1 Inter Plant Tele-communication System
(Server based) thro fibre optical
network (Pkg-037)
Consultant-MECON,
AgencyM/s Equant Technology Services
Contract price Rs. 10.15 Crs.
Contract signed: 12.07.12.
Contr. completion : 11.01.14
Likely completion : Jan16
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Media gateway installation in progress.


Cabling work in progress.

Drawings

Total

Submtd.

BE (A)
BE I
DE (A)
DE I
Total

4
11
54
24
93

4
11
54
24
93

Activity

Appd/KFR
4
11
50
18
83

Unit

Total vol.

T
T
T
T

53
53
28
25

Eqpt. Ordering
Eqpt. Supply
Eqpt. Erection Phase-I
Eqpt. Erection Phase-II

AAN

Comntd.

0
0
0
0
0
4
0
6
0
10
Oct15
Plan
Prog
0.5
8
7

U/S
0
0
0
0
0

Review meeting held on 07.08.15.


Suppy of PCB by 01.11.15.

Cum. Prog.
53
52.5
22
0

Software configuration at all 3 exchanges completed. UPS and battery


installation work completed by 05.06.15. Sector-9 and Sector-5
exchanges commissioned by 15.06.15.
H-2

Energy monitoring system (Pkg.-075A)

Drawings

Total

Submtd.

Appd/KFR

Consultant-MECON,

BE (A)
BE I
DE (A)
DE I
Total

4
1
22
9
36

4
1
22
9
36

4
1
20
3
28

AgencyM/s Masibus Automation


Contract price Rs. 3.47 Crs.
Contract signed: 30.05.12.
Contr. completion : 29.05.14
Likely completion : Dec.15
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Activity
Eqpt. Supply
Eqpt. Erection

Unit

Total vol.

T
T

4.9
4.9

AAN

Comntd.

0
0
0
0
2
0
0
6
2
6
Oct15
Plan
Prog
0.9

U/S
0
0
0
0
0
Cum. Prog.
4.9
4

All 18 nos. RTU connected with Central Energy Monitoring system. UPS
charged on 22.05.14. OPC server installed at OP-II for BOO plant
parameters.

10/9/2015

Page : 27

Review meeting held on 30.10.14.

SN

H-3

SCHEME / PACKAGE
Installation of Hot metal Rail Weigh Bridges
(Pkg-099B) Consultant-MECON,

PROGRESS ON DATE

AgencyM/s Sartorius Mechatronics


Contract price Rs. 1.94 Crs.
Contract signed: 14.05.14.
Contr. completion : 13.05.15
Likely completion : Mar16
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

OVERALL STATUS AS ON DATE


Drawings

Total

BE (A)
BE I
DE (A)
DE I
Total

2
21
13
12
48

Activity
Eqpt. Supply
Eqpt. Erection

Submtd.

Appd/KFR

2
21
13
12
48

AAN

2
19
13
12
46

Unit

Total vol.

T
T

54
54

0
0
0
0
0

Comntd.

U/S

0
2
0
0
2

Oct15
Plan
Prog
54
50
-

COMMITMENT AS PER LATEST MOM


Review meeting held on 26.02.15.

0
0
0
0
0

Cum. Prog.
50
0

Site work inaugurated on 02.03.15.


H-4

Installation of Rail & Road Weigh Bridges


(Pkg-099 A) Consultant-MECON,
AgencyM/s ACME Automation
Contract price Rs. 1.72 Crs.
Contract signed: 19.11.14.
Contr. completion : 18.11.15
Likely completion : Nov.15
(Proj. Mgr. M.V. Subramanyam, DGM), 22557

Drawings

Total

BE (A)
BE I
DE (A)
DE I
Total

9
20
7
10
46

Activity
Earth work
Concreting
Eqpt. Supply
Eqpt. Erection

Submtd.

Appd/KFR

9
20
7
10
46

AAN

9
19
3
10
41

Unit

Total vol.

M3
M3
T
T

178
523
60
60

0
0
0
0
0

Comntd.

Oct15
Plan
Prog
100
-

U/S

0
0
0
0
0

0
1
4
0
5

Review
15.06.15.

meeting

Cum. Prog.
158
225
60
0

Site work inaugurated on 25.02.15. Organisation chart submitted by


party. Equipment supplied completed on 31.08.15.
I. CIVIL SERVICES, TOWNSHIP & MINES ZONE
I-1 Providing a Space frame covering for
School Courtyard at Senior Secondary
School Sector-X of BSP (Consultant-BEDB)

Party has already submitted soft & hard copy of all drgs to BEDB.

Agency: M/s Alumax, New Delhi


Contract price Rs. 1.42 Crs.
Contract signed: 21.02.14.
Contr. completion: 20.02.15
Likely Completion: ---------

(Proj. Mgr-: I.N. Wamhne, DGM), 22046


I-2

Appointment
of
consultant
for
development of Aquatic Centre near
Jayanti stadium ConsultantBEDB,
AgencyM/s ARCH-EN DESIGN Lucknow

Draft soft copy of specification & tendor Award letter issued on 20.12.12.
schedule sent by zone to Arch in design for
finalisation from their side on 08.04.15.

Award Value Rs. 29.86 Lakhs.


Date of Award: 20.12.12.
Contr. completion: 19.03.14
Likely Completion: 19.03.16
(Proj. Mgr-: D.K. Pouria, DGM), 21954

I-3

Construction of RCC Overhead Water


Tank (Capacity 1875 Cum) at Sector -2
in Bhilai Township for TED
ConsultantBEDB,
Agency M/s Soul Engineers, Bhilai &
M/s Dubey & Goyal Company, Raipur
Contract signed: 12.07.14
Contract Price Rs. 2.92 Crs.
Contr. completion: 11.07.15

Likely Completion: Jan.16

(Proj. Mgr-: I.N. Wamhne, DGM), 22046

Reinforcment, shuttering & concreting of


Activity
columns for water tank above 18 Mtr. in
Earth work
progress.
Concreting
Office Bldg.:- civil work completed.
Pipe laying

Unit

Total vol.

Oct.15
Plan

Prog.

Cum. Prog.

M3

800

500

M3
RM

800
223

20
0

400

Earth work completed on 01.12.14. Concreting work started on


15.01.15. Water Tank: Plinth beam casting completed. Tie beam at 4
mtr. Level casting completed. Office bldg: Plinth beam casting
completed on 11.04.15. Casting of Lintel beam for Office bldg.
completed on 11.05.15. Casting of slab for Office bldg. completed
on 13.06.15. civil work completed on 07.08.15.

10/9/2015

Page : 28

held

on

SN

SCHEME / PACKAGE

J-1

J. UTILITY ZONE
Aug. of Power Supply facilities for BF
Slag dumps (Electrical Pkg.) (Pkg.-2).
Consultant BEDB

Agency: Hindustan Controls & Eqpt. Ltd.

J-2

Award value. Rs. 3.06 Crs,


Date of Award :27.07.11,
Contr. Completion: 26.04.12
Likely Completion: --------(Proj. Mgr. : N.C.Ray, DGM), 21359
Appointment of consultant for secured land
filling facilities for disposal of hazardous
wastes generated in BSP Consultant- BEDB
Agency: Infra-in consulting Pvt. Ltd.
Award value Rs. 18.87 Lakhs.
Date of award: 07.12.11.
Contr. completion : 06.03.14

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

COMMITMENT AS PER LATEST MOM

Illumination work at S/S bldg. in progress.

7 nos. HT Isolator, all cables, 5 nos. high mast light & GI pipe supplied
and 2 nos. high mast erections completed. Fabrication of Cable tray
Balance Supply: LT & HT panel, Bus duct &
completed. 3 nos. transformers supplied at site on 15.05.14. HT cable
battery charger.
laying completed.

M/s Infra-in consulting Pvt. Ltd has not Presentation of detail project report held on 15.10.12.
applied for further date extension to
complete the work.

(Proj. Mgr.: D.K, Pouriya DGM), 21954

J -3 Relocation of Bhilai Warehouse:


I
Dunnage work Phase-2A (Pkg-02).

Material collected. 25 T Strs. fabricated & erected

Consultant CET
Agency - M/s Sanjay Engr. & Fabricators

Award value Rs. 66.35 Lakhs.


Date of Award: 07.09.12,
Contr. Completion: 06.01.13
Likely completion: Dec.15
(Proj. Mgr.: D.K, Pouriya, DGM), 21954

II

Activity

Relocation of Bhilai Warehouse:


Civil & Structural work (Pkg-05).
Consultant CET,
Agency - M/s BSBK
Award value Rs. 11.10 Crs.
Date of Award: 18.05.10,
Contr. Completion: 17.04.11
Likely Completion: Nov.15
(Proj. Mgr. : G. Ravibabu, AGM), 22695

Unit

Total vol.

Earth work
Concreting
Brick work
Plastering
WBM
RCC Pipe Laying

M3
M3
M3
M2
M3
RM

39000
7000
2200
26000
22000
330

Rail track laying

RM

3000

Oct.15
Plan
Prog.
1000
100
470
0
0
250
-

Cum. Prog.
34635
6523
2055
25680
22000

3000

Boundary wall: 885/898 columns cast.

J-4

Gas mixing & Booster Station (Pkg076).


Consultant-MECON.
Agency-M/s NICCO Corporation,
Cont. Price Rs. 13.62 Crs.
Contract signed: 06.01.12
Contr. Completion : 05.01.13
Likely completion: Dec.15
(Proj. Mgr. : G. Ravi Babu, AGM), 22695

Drawings

BE A
BE I
DE A
DE I
TOTAL

Total

Submtd

Appd/KFR

AAN

15

14

14

Comntd
0

U/S
0

30

30

29

67

66

64

56
168

51
161

51
158

0
2

0
1

0
0

All Earth work 3300M3, All Concreting 950M3, All 75T Bldg. strs.
fabrication & erection , All 5T Tech. strs. fabrication & erection, all
270T Mech. eqpt. & 20T Elect. eqpt. ordering, supply & erection
completed, Equipment Erection completed on 01.10.14. HT & MCC
panel charged on 31.03.15. Engg. closer meeting organized by
MECON Ranchi on 10.09.14 to complete the engg. issue. TOP
connection completed on 14.04.15. Blower fan testing completed.

10/9/2015

Page : 29

Review
28.05.14.

meeting

held

on

SN

SCHEME / PACKAGE

J-5

Interplant fuel gas and industrial gases


pipeline for all units (Pkg. 075).
Consultant- MECON
Agency: M/s Tata Projects ltd.

Contract price Rs. 147.16 Crs.


Contract signed: 22.01.11
Contr. completion : 21.04.12

Likely Completion : Oct.15


(Proj. Mgr. Ashok kumar, DGM), 22184

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

Design engg. in progress.


50 M3 Earth work completed.
20 M3 Concreting completed.
6 T Bldg. strs. fabricated.
6 T Bldg. strs. erected.
5 T Tech. strs. erected
Pipe ercetion at C zone in progress.
A-Zone: O2 line laying completed.
Welding
work
in
progress
(95%
completed).

B-Zone: Earth work & concreting for


trestle foundation & back filing in
progress.
Shuttering
and
Reinforcement
in
progress.
C-zone: DN 1200 Pipe line erection &
Ground assembly are under progress.
Testing of BF pipeline DN 2200 for COB11 completed.
D-Zone: Earth work & concreting for
trestle foundation & back filing in
progress.
Shuttering
and
Reinforcement
in
progress.
Strl. erection in progress.

Drawings

Total

BE (A)
BE I
DE (A)*
DE I*
Total

25
5
440
1878
2348

Submtd.

25
5
440
1878
2348

Activity

Unit

Earth work
Concreting
Bldg. Strl. fabrication
Bldg. Strl. erection
Tech. Strl. fabrication
Tech. Strl. erection
Mech. Eqpt. Ordering
Elect. Eqpt. ordering
Mech. Eqpt. supply
Elect. Eqpt. supply
Mech. Eqpt. erection
Elect. Eqpt. erection

M3
M3
T
T
T
T
T
T
T
T
T
T

Appd/KFR

22
3
428
1753
2206

Total vol.
*100000
*16348
*7305
*7305
10000
10000
37
3
37
3
37
3

AAN

Comntd

U/S

1
1
0
108
110

1
1
12
17
31

1
0
0
0
1
Oct.15

Plan
3000
650
500
350
0
250
0
0
0
0
0
0

Prog.
400
148
37
37
19

Cum. Prog.
91514
14961
4638
3653
9098
3579
36
2
36
2
10
0.5

Compressed air line DN 250 from CAS - 4 to URM successfully charged


on 02.03.15. HP Steam line TOP connections at CDCP end & BPTG end
has been completed on 06.04.15. Radiography for 66 Ata HP Steam line
connection at CDCP completed on 13.04.15. Bend fabrication for mixed
gas line at E-zone completed on 15.04.15. Mech. & Elect. Eqpt. erection
started on 26.09.15.
Zone-A: All 262 nos. trestle & girder erection completed, erection of pipe
line 99% completed. Zone-B: 152 nos. out of 195 nos. foundation bolt lift,
117 nos. Trestle & 72/174 nos. girder erection completed, Erection of
Pipe line 26% completed. Zone-C: 94 nos. out of 109 nos. foundation bolt
lift & 89 trestle & 67/90 nos. girder erection completed, Erection of Pipe
line 56% completed. Zone-E: All 83 nos. foundation bolt lift, 82 Trestle & 72
nos. girder erections completed Pipeline erection 95% completed. ZoneD: 101 no. out of 160 nos. bolt lift & 26/160 nos. trestle erection
completed.

10/9/2015

Page : 30

COMMITMENT AS PER LATEST MOM


Review meeting held on 08.07.14.

SN

SCHEME / PACKAGE

J - 6 External Water Supply system for BOF


& CCP (beyond battery limit) (Pkg. 077-01).
Consultant- MECON
Agency M/s Aireff Detox Ltd.

Contract Price Rs. 113.49 Crs.


Contract signed: 29.06.12,
Contr. completion: 28.09.13
(Proj. Mgr.; Ashok Kumar, DGM), 22184
Likely completion: Jan.16

J- 7 External Water System for Mills and


Fire Water Pump houses (Pkg-077-02).
Consultant- MECON

Agency M/s McNally Bharat Engg.,

Kolkata & Southern Cooling Tower,


Kolkata .
Contract Price Rs. 114. 30 Crs.
Contract signed: 22.09.12,
Contr. completion: 21.12.13
Likely completion: Nov.15

(Proj. Mgr.: - N.C.Ray, DGM), 21359

PROGRESS ON DATE
Design Engg. in progress.
WTP-1: 16/22 nos. piles casting completed.
WTP-3: Thickner A (BOF): Plinth beam casting
completed.
Thickner B (BOF): column upto slab level
completed.
Thickner C (BOF): R/S for slab of in progress.
Thickner A&B (SRU): All footing completed.
SST PH plinth beam casting completed.
WTP-4: Excavation for SST in progress.
Plinth beam of SST pump house completed.
ECR:18/22 nos. footing completed.
WTP-5: 24/25 nos. footing completed for MWPH.
65/94 nos. footing completed for common
pump house with emergency overhead tank.
Common pump house earth work in progress.

Design Engg. in progress.


3 M3 Concreting completed (WTP-5).
2 T Bldg. strs. Erection.
WTP-1: Floring in progress.
Strl. erection in progress.
WTP-2: Brick work completed & plastering

OVERALL STATUS AS ON DATE


Drawings

BE A*
BE I
DE A
DE I
TOTAL

66

66

47

12

23

23

19

234

151

36

34

58

23

184
507

75
315

32
117

0
38

40
129

3
31

Unit

Total vol.

Oct.15
Plan
Prog.

M3
M3
T
T
T
T
T
T

*104000
*21235
*2800
*2800
*3000
*530
*3000
*530

Earth work
Concreting
Tech. Strs. Fabrication
Tech. Strs. Erection
Mech. Eqpt. Ordering
Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt. Supply

AAN

2000
1000
50

Comntd

1550
91

200
10
80
5

U/S

BE A
BE I
DE A
DE I
TOTAL

104
24
494
158
780
Activity

Earth work
Concreting
Bldg. Strs. Fabrication
Bldg. Strs. erection
Tech. Strs. Fabrication
Tech. Strs. erection
Mech. Eqpt. Ordering
Elect. Eqpt. Ordering
Mech. Eqpt. Supply
Elect. Eqpt supply
Mech. Eqpt. Erection
Elect. Eqpt Erection

82
17
296
92
487

M3
M3

63
9
186
60
318
Total
vol.
87420
*19785

MT
MT
MT
MT
T
T
T
MT
T
MT

*425
*425
*435
*435
*1500
*905
*1500
*905
*1500
*905

Unit

0
0
14
0
14

78012
8181

1970
450
61
20

18
8
60
23
109

Oct.15
Plan
Prog
600
20
700
58
100
60
0
0
0
0
0
0
100
50

2
5

1
0
36
9
46
Cum. Prog.
73939
14769
216
169
150
100
1300
500
400
400
41
50

Mech. eqpt. erection started on 25.01.15. WTP-1: Civil work of WTP-1 in all respect up to tie
beam at RL 318.40 completed by 30.01.15. WTP-2: Casting of slab at 314m level
completed on 10-11.01.15. WTP-3: - Casting of fan deck slab of WTP-3 cooling tower
completed on 03.04.15.WTP-4: Casting of slab of pump house at WTP-4 completed on
10.06.14. WTP-5: Raft concreting started on 13.08.15. PCC work started on 29.05.15.
Scale pit raft concreting completed on 16.07.15. WTP-6: Concreting of secondary settling
tank wall completed on 11.03.15. Hot sump wall completed. Concreting of cold sump
slab 80% completed on 19.09.15.ECR (WTP-6 BRM area): Casting of slab for ECR completed
on 11.06.15. Casting of air washer slab for ECR completed on 15.09.15.
WTP-7: SST completed. Concreting of ICW Cooling Tower up to fan deck level

completed. Concreting of slab for ECR bldg. at WTP-7 BRM area completed on
28.07.15. Casting of Pump house slab completed on 04.09.15

10/9/2015

Page : 31

Review meeting held on 27.12.14.

Cum. Prog.

Eqpt. ordering & supply started on 17.02.15. WTP-1: Raft Concreting completed on
10.12.14. casting of top slab of PH completed on 28.08.15. WTP-3: Earth work for
thickener started on 09.08.14. WTP-4: Excavation for Secondary settling tank started
on 12.03.15. ECR:10/22 nos. footing completed.
WTP-5: Excavation for MWPH & DWPH completed.
Drawings
Total
Submtd
Appd/KFR
AAN
Comntd
U/S

in progress.

WTP-3: Cable gallery footing from S/S-68


to ECR bldg. in progress.
WTP-4: All 4 pumps foundation grouting
completed. Plastering work in progress.
WTP-5: Raft concreting started on
13.08.15.
Scale pit 3rd lift of wall & trench
concreting in progress.
WTP-6: Concreting of cold sump slab
80% completed on 19.09.15.
Concreting of secondary settling tank
wall up to walkway lavel completed.
Concreting of Cooling Tower in
progress.
WTP-7: Concreting of wall for Pump
sump & common sump in progress.

Submtd

Activity

Appd/KFR

COMMITMENT AS PER LATEST MOM

Total

Review meeting held on 0405.09.15.

SN

SCHEME / PACKAGE

J-8

Aug. of Make-up water and drinking


water system (Pkg. 078)

J-9

PROGRESS ON DATE

Design Engg. in progress.


40 M3 Earth work completed.
Consultant MECON,
3 T Tech. strs. erected.
Agency- M/s Vishwa Infrastructure,
Intake pump house: (Maroda-2)
Contract Price Rs. 90.04 Crs. + Revised cost
Erection of gangway in progress.
7.89 Lakhs., (Total cost 90.11crs.)
ECR: Fixing of door & windows, rolling
Contract signed: 01.10.11
shutter are balance.
Contr. Completion : 31.12.12
Makeup water (IW) Pipe Route: Civil work for
Likely Completion : Oct.15
pedestal & erection of Tech. pipe line
(Dia. 900 mm) in progress.
(Proj. Mgr. VS Sai, DGM), 21216
MWPH: Concreting of wall in progress.
Drinking water treatment plant:
Earth work for ECR (DWTP) 10/34
foundation completed.
Excavation for cable gallery foundations
15/25 nos. completed.
Raw water pipe route: (Maroda -2 to DWPH).
1100/1200 Mtr. Pipe laying completed.
Pipe pushing (near intake PH under rail
track) completed & pipe laying in
progress.
Wraping coating of pipe in progress.

Construction of Railway siding and MGR Sys.


including earthwork, Construction of bridges,
supply of ballast and P-way linking in connection
with modernization of Peripheral Yard (Pkg.-95A)
(Sch.-A) ConsultantRITES,
Agency- M/s Jhajharia & Arcon,
Award value Rs. 79.38 Crs.
Date of Award - 29.06.11.
Contract signed : 03.08.11
Contr. Completion : 28.12.12
Likely Completion : Dec.15
(Proj. Mgr.: D.K, Pouriya DGM), 21954

J-10 Design, Supply, Erection,Testing & Commissioning

of Railway Electrification work of existing/


proposed Railway Tracks Switching Post (SSP)
including modification of existing 25KV AC, 50 HZ
Single Phase Over-Head Equipment (OHE) (Pkg.
095A, Schedule - C) ConsultantRITES,
Agency- Bright Power Projects Pvt. Ltd., Mumbai

Ballast spreading work for track laying


of MOR line in progress.
Earth work at MGR line in progress.
400 M3 Earth work completed.

Drawings

Total

BE A
BE I*
DE A
DE I

34
14
226
61
335

TOTAL

Activity

OVERALL STATUS AS ON DATE


Submtd
Appd/KFR
AAN
34
12
162
43
251

32
11
77
25
145

Unit

Total vol.

COMMITMENT AS PER LATEST MOM


Comntd

0
2
0
1
57
17
0
18
57
38
Oct.15
Plan
Prog
950
300
350
45
90
19
80
16

U/S

Review meeting held on 16.09.14.

0
0
8
0
8
#Cum. Prog.

Earth work
M3
*50000
41408
Concreting
M3
*15000
9432
Bldg. Strs. fabrication
MT
*1250
703
Bldg. Strs. Erection
MT
*1250
578
30
Tech. Strs. supply
MT
6000
4615
120
Tech. Strs. erection
MT
6000
21
2959
10
Mech. Eqpt ordering
MT
*550
350
10
Elect. Eqpt ordering
MT
*250
170
15
Mech. Eqpt Supply
MT
*550
10
350
5
Elect. Eqpt Supply
MT
*250
19
151
35
Mech. eqpt. erection
MT
*550
3
10
Elect. Eqpt erection
MT
*250
#Cum. Prog. Reconciol by zone on 07.10.15. DWTP: Casting of Dirty Back wash water
compartment completed. Casting of Drinking water treatment plant Pump House
slab completed on 10.09.14. MWPH: Laying of DN 900mm pipe near Boria gate
completed on 07.12.13. Intake PH: Casting of top slab of IWPH completed on
12.01.15. ECR: casting of slab completed on 15.09.14. Mech. & Elect. eqpt. supply
started on 08.04.14. MCC panel for IWPH supplied on 09.09.14. Mech. eqpt. erection
started on 13.08.15.
Oct.15
Cum. Prog.
Activity
Unit
Total vol.
Plan
Prog
Earth work
M3
1080000
10000
2300
904200
Concreting
M3
6130
0
3661
Supply of Ballast
M3
103500
0
75230
Dismtlg. of existing track
RM
8000
0
1400
Laying of railway track
TM
41500
500
24925
WT-5 - Main line (Western side) track connectivity completed & loco

Review meeting held on 23.09.14

testing completed on 29.04.13. 5 nos. out of 7 nos. Bridge deck slab


completed.
Contract signed on 01.08.2015. Award letter issued to at a total cost of
Rs. 18,83,63,711.62 on 06.07.15 with completion period of 24 months.

Award value Rs. 18.83 Crs.


Date of Award 06.07.15.
Contr. Completion : 05.07.17
(Proj. Mgr.: D.K, Pouriya DGM), 21954

J-11 Railway track works for plant internal yard

Activity

(Pkg.-95B)

Unit

Total
vol.

M3
M3
M3
RM
RM

150000
5800
79000
13500
*37300

Oct.15
Plan
Prog

Cum. Prog.

ConsultantMECON
Agency -M/s ISC projects Pvt. Ltd. Bhusawal
Contract Price Rs. 76.08 Crs. (4th revision)
Contract signed 18.08.10
Contr. completion; 17.02.13
(Proj. Mgr.; D.K, Pouriya DGM), 21954

Earth work
Concreting
Supply of Ballast
Dismtlg. of existing track
Laying of railway track

Likely Completion : Oct.15

Track no. 18 near high line linking completed on 22.10.13. Line no. 41: track laying of
dump car line, Boiler coal line & escape engine line completed by 23.05.14.

10/9/2015

Page : 32

0
0
0
0
0

147835
5458
61000*
11761
15500*

Review meeting held on 24.12.14.

SN

SCHEME / PACKAGE

J-12 Road works & road culvert over Tandula


canal (Pkg-100-2).
Consultant MECON,
Agency: M/s HSCL
Award value Rs. 12.50 Crs.
Date of Award: 25.02.10,
Contlr. Completion : 24.02.11
Likely Completion : Nov.15
(Proj. Mgr. : S.S. Prasad, Mgr.), 22708

J-13 Construction of Fly Over at 3 locations &


road network (Pkg.-111-01).
Consultant MECON
Agency: M/s SP Singla Construction,
Contract Price Rs. 74.06 Crs. (Addition
sanction on 21.10.13 Rs. 8.03028 Lakhs)
Contract signed on 14.07.10
Contr. completion: 13.07.12.
Likely completion: Dec.15
(Proj. Mgr.- Ashok Kumar, DGM), 22184

PROGRESS ON DATE

Road No.- 8: Earth work & sub grade


work in progress.

OVERALL STATUS AS ON DATE


Oct.15
Total vol.
Plan
Prog

Activity

COMMITMENT AS PER LATEST MOM

Unit
M3
M3
M3
M2

Earth work
Concreting
Sub grade
Road carpeting

210277*
4100
60200
72450*

0
0
200
0

Cum. Prog.

Review meeting held on 25.09.14.

162575
3979
59020
49259

25

Road carpeting behind PRO completed on 01.07.14. Survey for 8A, 8B &
8C completed.
Drawings

Total

Submtd

BE (A)
ROB No.-2: Road widening work from BE (I)
Boria road T junction to Boria gate in DE (A)
TOTAL
progress.

28
2
95
125

17
2
52

Activity
Service road work from CED circle to
Bhathi Thana in progress.
Piles
ROB No.-3: Concreting work in Earth work
Concreting
progress.
Elect. Eqpt. ordering
Elect. Eqpt. supply
Elect. Eqpt. Erection
Bldg. Structural fabn.
Bldg. Strl. erection
Road WMM
Road Carpeting (BM)

Appd/KFR

71

62
Total
vol.
344
260000
26000
33.8
33.8
33.8
28
28
65000
4450

Unit
Nos.
M3
M3
T
T
T
T
T
M2
RM

AAN

13
2
47

Comntd

2
0
2

2
0
3

Oct.15
Plan
0
0
100
0
0
0
0
0
4000
0

U/S

Review meeting held on 18.10.14.

0
0
0

0
Cum. Prog.

Prog.

127
58600
16291
9
9
6
10
8
15550
2350

F.O.no.-2: Road widening work from Boria road T junction to Boria gate
in progress. F.O.no.-3: GAD submitted on 29.07.14. Casting of 10th deck
slab completed by 30.05.15. F.O. no.-1: GAD approved from railway.
Approval of GAD awaited form NHAI.
J-14 Electrical enabling works at TDS-I & new
LT substation near Boria Stores (Pkg.113).
Consultant MECON,
Agency M/s ABB
Contract price Rs. 26.18 Crs
Contract signed on : 01.05.08,
Contr. completion: 31.03.09
Likely completion: -------(Proj. Mgr. : N.C.Ray, DGM), 21359

M/S ABB has submitted letter on Drawings


15.06.15 for issue of commissioning BE (A)
BE I
certificate.

Total

Submtd.

14
3
71
101
189

DE (A)
DE I
TOTAL
Activity

Unit

Appd/KFR

AAN

Comntd

U/S

14
3
66
93

9
3
48
85

5
0
16
1

0
0
2
7

0
0
0
0

176

145

22
Oct.15
Plan
Prog

Total vol.

Cum. Prog.

Earth work
M3
1284
1284
Concreting
M3
877
877
Elect. Eqpt. Supply
T
1185
1185
Elect. Eqpt. Erection
T
1185
1185
HM Tower: 18/19 nos. high mast tower charged by 29.03.13. 29/32 nos.
CSS erection completed by 08.02.14. Erection completed on 01.07.14

10/9/2015

Page : 33

Review meeting held on 27.09.14

SN

SCHEME / PACKAGE

J-15 Installation of fire fighting system for


transformer installed in TDS-1 (Pkg.113A) Consultant MECON,

PROGRESS ON DATE

OVERALL STATUS AS ON DATE

Design engg. is in progress.

COMMITMENT AS PER LATEST MOM

Communication protocol issued on 04.11.14. List of drawing & Billing Kick off meeting held on 14.11.14.
schedule approved, Power od attorney submitted. Land allotted for
stores at TDs-1.

Agency M/s Vendere sales service Pvt. Ltd.


Contract price Rs. 44.82 Lakhs
Contract signed on : 29.10.14
Contr. completion: 28.04.15
Likely Completion: Dec. 15
(Proj. Mgr. : G.S. Wadhwa, Mgr), 21484

J-16 Data network and Intranet Services


(Pkg-117A).

Erection work of Intranet in new PSS of


Boria store completed.

Consultant- MECON
Agency- M/s HCL Info systems
Contract price Rs. 0.8137 Crs
Contract signed on : 30.04.11
Contr. Completion by : 29.08.11
Likely completion: -------(Proj. Mgr. : N.C.Ray, DGM), 21359

J-17

Diversion/Piping of Outlet No-7, 14, 15


16 & 17 (Pkg.-118G).
Consultant- MECON,
Agency M/s Kulkarni & Sahu,
Award value of Rs. 9.39 Crs.
Date of award: 03.11.10,
Contr. Completion: 02.11.11
Likely Completion: Feb.16
(Proj. Mgr. : S.S. Prasad, Mgr), 22708

J-18

Recycling of Waste Water from Outlet-B


(Comprising of Outlet 8, 9 & 10) (Pkg-1) for
WMD. Consultant- BEDB,

Outlet 14 & 15: Work restored on


13.06.15.
Outlet-15: Back filling in progress.

Relocation of refractory storage shed from


near SP-3 to Boria Storage Complex (Pkg118P). Consultant- MECON,

Consultant- MECON, Agency; HSCL


Award value Rs. 3.797 Crs,
Dt. of Award : 19.08.09
Contr. Completion: 18.08.10
(Proj. Mgr. : D.K, Pouria, DGM), 21954

Oct.15
Plan
Prog

Cum. Prog.

Unit

Total vol.

Oct.15
Plan
Prog

Earth work

M3

Concreting
RCC Pipe laying

M3
RM

129500
12110
1150

500
300
0

1000
15.8
15.8
15.8

Cum. Prog.

63330
4801
1029

Kick off meeting held on 31.10.14. List of drawing & Site organisation
chart submitted on 08.12.14. Name plate & QAP approvesd on 08.12.14.
Name plate & numbering system, List of drawing & document, list of
equipment, P&I diagram approved on13.01.15. Layout Plan, GA & cross
section of plant submitted on 10.01.15. Pert Network submitted on
29.01.15. L-2 Network submitted on 03.02.15.

Strl. Fabrication & erection in progress.

Activity

Unit

Total vol.

Oct.15
Plan

Prog

Cum. Prog.

Kick off meeting held on 31.10.14.

Earth work
M3
3700
0
3125
Concreting
M3
1313
0
450
230
Strl. Fabrication
230
T
230
200
Strl. Erection
T
0
All 44 foundation bolt lift completed by 25.01.14. Strl fabrication started
on 30.01.13. Strs. erected started on 27.01.14. All 44 strl. Column erected
by 29.03.14. Erection of bracing (1-18) completed. Fabrication &
erection of all 18 nos. truss completed.

Award value Rs. 1.45 Crs.


Date of award: 07.01.12,
Contr. Completion: 06.07.12
Likely Completion : Feb.16
(Proj. Mgr. : Ashok D. Thawre, AGM), 21967

Civil & Strl. for Relocation of Mech. Repair


Shop & Quenching Car repair shop. (Pkg.
119-01)

Total vol.

Outlet # 14 (850RM): 375 RM completed. Outlet # 15 (350RM): 320 RM pipe


laying completed by 16.04.14. All 9 nos. man holes completed. Outlet # 16
(70 RM): All 70 RM pipe laying completed by 13.02.14.

Agency: M/s Hitesh Bhai Patel,

J-20

Unit

Earth work
M3
1000
Elect. Eqpt. ordering
T
15.8
Elect. Eqpt. supply
T
15.8
Elect. Eqpt. Erection
T
15.8
Cable laying job completed. All work completed on 30.09.2014.

Activity

Agency M/s Otto Projects Pvt. Ltd., Kolkata


Contract price Rs. 6.25 Crs.
Contract signed on: 17.10.14,
Contr. Completion: 16.01.16
(Proj. Mgr. : J.M. Palaiya DGM), 22577

J-19

Activity

M/s HSCL has not applied for Further date


extension to complete the work due to
M/S HCEPL (Pkg.119-02) has not
completed the Elect. job.
Balance work:
Track connection from SS-21L to Q/Car
repair shop including RCC inspection pit.

Activity

Unit

Total vol.

Concreting
M3
2800
Brick work
M3
650
Road carpeting
M2
1800
Railway track laying
RM
150
Road carpeting completed on 21.12.11.

10/9/2015

Page : 34

Oct.15
Plan
Prog

0
0
0

Cum. Prog.

1740
606
1800
0

SN

SCHEME / PACKAGE

J-21

Elect. Power & Ventilation Facilities for


Mechanical Repair Shop & Quenching Car
Repair Shop (Pkg.119-02)
Consultant-MECON,
Agency- M/s Hindustan Controls & Eqpt,
Contract price Rs. 2.519 Crs).
Contract signed on: 09.01.10,
Contr. Completion: 08.10.10
Likely Completion : Dec.15
(Proj. Mgr. : N.C.Ray, DGM), 21359

J-22

J-23

J-24

Technological & Services for Relocation of


Mech. Repair Shop for CO&CCD (Pkg.
119-03)
Consultant MECON,
Agency: M/s GAME
Contract price Rs. 1.75 Crs.,
Contract signed on :13.10.09,
Contr. Completion : 12.04.10,
Likely Completion : --------(Proj. Mgr. : D.K, Pouria, DGM), 21954
Dismantling of existing bldg./shed in old
administrative bldg complex, stockyard &
CMO for construction of Universal Rail Mill &
new CMO yard (Pkg.-120G)
ConsultantMECON, Agency-M/s Radha Constn.
Amount to be paid to BSP Rs. 1.71Crs.
Date of Award: 16.08.10,
Contr. Completion: 15.11.10
(Proj. Mgr. : G. Ravibabu, AGM), 22695
Relocation
of
printing
press
from
Old
Administrative bldg. to CEZ area (Pkg.-120N)
Consultant-MECON,

Agency M/s Sadani Enterprises,

PROGRESS ON DATE

Electrical Equipment erection


progress.
Cable laying in progress.

OVERALL STATUS AS ON DATE


Oct.15
Unit
Total vol.
Plan
Prog

Activity

in

COMMITMENT AS PER LATEST MOM


Cum. Prog.

Elect. Eqpt. Supply


T
72.1
0
48
Elect. Eqpt. Erection
T
72.1
0
31
All 200 M3 Earth work, 150 M3 Concreting & 72.1 T Elect. Eqpt. Ordered.
2 nos. PDB supplied. PDB erected at MRS.

Drawings

Total

Submtd.

DE (A)
TOTAL

7
19
3
29

7
14
1
22

Critical issue:
BE (A)
Issue of load data for equipment
BE I
foundation drawings by MECON.

Activity

Dismantling of Eqpt.
Relocation of Eqpt.
Case handles in arbitration.

Appd/KFR

7
14
0
21
Unit

No.
No.

Activity

Total vol.

AAN

U/S

0
0
1
1

Cum. Prog.

Oct.15
Plan
Prog

Total
vol.

0
0
0
0

Oct.15
Plan
Prog

62
40
Unit

Comntd.

0
0
0
0

62
22
Cum. Prog.

Dismantling of sheet
M2
30000
0
26250
Dismantling of Railway track
MT
200
0
200
Dismantling of Boundary wall
RM
490
0
Dismantling of Railway track completed on 09.07.11. Case handles in
arbitration.
-

M/s Sadani Enterprises has not applied 10 nos. Machine commissioned successfully by 26.03.13.
for further date extension to complete
the work.

Contract Price Rs. 34.15 Lakhs.


Contract signed on 11.04.11,
Contr. completion: 10.10.11
(Proj. Mgr. : N.C.Ray, DGM), 21359

J-25

Replacement of NB 1200 mm mixed gas


pipe line from mixing station to
normalizing furnace. Consultant- CET,
Agency : HSCL
Award value Rs. 1.712 Crs.
Date of award: 06.12.11.
Contr. completion: 05.11.12
Likely completion : Oct.15
(Proj. Mgr. H.L. Ghidole, AGM), 20416

K.
K1
K2
K3

SPECIAL PROJECT UNIT


Installation of Steel Processing Unit at Hosangabad (M.P.)
Installation of Steel Processing Unit at Ujjain(MP)
Installation of Steel Processing Unit at Gwalior (MP)

Activity

Earth work
Concreting
Fabrication of Strs.
Erection of Strs.
Fabrication of Tech. Pipes
Erection of Tech. Pipes
Column strengthening of all

Unit

Total vol.

Oct.15
Plan

Prog

M3
705
0
M3
215
0
T
135
0
T
135
0
RM
1660
0
RM
1660
0
42 columns completed by 09.09.13.

Cum. Prog.

245
108
72
63
839
839

SAIL Board has decided that the SPUs will be established with Joint Venture.

10/9/2015

Page : 35

L.
SN
L1

STAGE-I approved schemes other than 7.0 MT expansion


SCHEME / PACKAGE
Setting up of a 1.0 Mtpa Pellet Plant along with Generated Iron Ore
Fines (GF) / Slime Beneficiation Plant at Dalli Mines of BSP
(Consultant-CET) (PCC-TK- A.C.Rathi, DGM I/c) 21751

L2

L3

NIT
01.08.14

TOD
20.10.14

PBOD
10.03.15

BIDDERS
Consortium of MECON Ltd.,
Bangalore

Replacement of Analogue Thyristor System with Digital DC Drive


System for DC Motors of Stands 1D to 12D Mechanisms of Merchant
Mill (Consultant- EDD) (PCC TK A C Rathi, DGM I/c) 21751

23.08.14

31.10.14

10.07.15

DIL Ltd., Kolkata

Extension of Spillage Coke Chain Conveyor in COB#4 upto the end


of COB#3 of CO&CCD (Consultant- CET)
(PCC TK - A C Rathi, DGM I/c) 21751
Installation of Dedusting system for Reversible Shuttle Conveyor area
of BF-7 Stock House
(Consultant-EDD) (PCC-TK- A.C.Rathi, DGM I/c) 21751
Route relay inter locking by Solid state Interlocking signaling system
for internal railway yard (Re-tendered)
(Consultant- RITES, Gurgaon) (PCC NTK- Satya Prakash, DM) 22738
Delinking of Sewerage Systems of Main Hospital, Hospital Sector
&Talpuri Areas from Hudco Network and Diverting it to Supela
Pump House at Sector- 6 in Bhilai Township.
(Consultant- EDD) (PCC TK A.C. Rathi, DGM I/c) 21751

31.10.14

29.11.14

25.02.15

Bhilai Techneeds, Bhilai

31.10.14

27.12.14

10.08.15

Enviropol Engg. Pvt Ltd., Noida

10.05.13

24.06.13

08.01.14

MRT Signals, Nagpur

11.03.14

25.04.14

20.09.14

Mate Consultants, Kolkata

L7

Up-Gradation of Sinter Machine-1 of Sintering Plant II


(Consultant CET) (PCC-TK V Anil Kumar, AGM ) 20206

16.12.13

27.12.13

13.04.15

L8

Replacement of 6 nos. conventional lathes by 3 nos. 5 T CNC


lathes for MM & WRM rolls in RTS
(Consultant-CET) (PCC-TK- A.C. Rathi, DGM I/c) 21751

20.05.14

16.07.14

07.07.15

L9

Installation of On-line Marking Facility for Bloom Caster Machine-5


of SMS-II (Consultant CET)
(PCC-TK- R K Panigrahi, DGM) 20168
Installation of ESPs as replacement of Multicyclones for all 4 Nos of
Sinter Machine Sinter PlantII
(Consultant- CET) (PCC TK A C Rathi, DGM I/c) 21751
Construction of retaining wall for active waste dump at Dalli Mech.
Mines. (Consultant- Mines) (PCC NTK- A.K.Agrawal, DM) 23219
Addition of Facilities at First Floor in Steel Club Sector-8 at Bhilai
(Consultant EDD) (PCC NTK- P K Sur, AM) 23207
Repl. of Stands 6 & 8 with Housingless Stands in Merchant Mill
(Consultant CET) (PCC-TK A C Rathi, DGM I/c) 21751

14.03.15

15.04.15

03.08.15

Replacement of Electrical drives, Panels & Control Systems by


modern state of the art systems for Slab Caster -3
(Consultant EDD) (PCC-TK- R K Panigrahi, DGM) 20168

L4

L5

L6

L 10

L 11
L 12
L 13

L 14

STATUS AS ON DATE
(L-1 Cost - 556.02 Cr., Estimate - 732.08 Cr.)
Proposal sent to Corporate Office on 26.03.15 for Stage-II approval.
Reply on PAG meeting sent to Corp. Office by PP&E deptt. on 02.07.15.
PAG held on 25.06.15.
Validity of offer including price bid has been extended by M/s MECON
Limited up to 31.10.15.
{L-1 Cost - Rs. 14.47 Crs. (NOC), Cost Estimate -Rs. 23.11 Crs. (NOC)}
Case sent to PP&E on 03.08.15 for obtaining Stage-II approval.
E-mail sent to PP&E and Shop (MM) on 10.09.15 to inform the status of
the pkg., reply awaited.
{Negotiated price - Rs 67.54 lakhs (NOC), Estimate - Rs 64.34 lakhs (NOC)}
Documents sent to Shop on 11.08.15 for obtaining Stage-II approval.
Validity of offer extended by M/s Bhilai Techneeds till 31.10.15.
Documents sent to Project Co-ordinators on 24.09.15 for obtaining
Stage-II approval.
(L-1 cost 31 % more than Estimate, Estimate-Rs. 8.6 Crs.)
Validity of offer not extended by party.

(L-1 cost Rs. 6.67 Crs., Estimate-Rs. 5.22 Crs.)


TC held on 23.01.15 & 05.03.15, Committee deliberated on L-1 price and
opined that as the final price of the party is 25.59% higher than the
estimate after negotiation, it is appropriate to re-tender the package with
revised TS. TC to be held further.
Consortium
of
BEC
& (L-1 cost Rs. 19.88 Crs., Estimate-Rs. 17.78 Crs.)
Shop proposed on 26.08.15 to drop the present tender and to do
Ormetoyumz
retendering without change in scope of work & TS with change in EC if
required.
TC held on 01.10.15 to cancel the present tender.
{L-1 Cost : Rs 7.37 Crs. (NOC), CETs estimate : Rs 18.81 Crs.(NOC)}
Consortium of M/s Nantong
TC held on 30.07.15 &01.08.15 for award of work, recommendation
Wexing Machine Co. Ltd. & M/s
under approval.
Shenzen China Dragon Ltd,
Letter sent to Shop on 19.08.15 to review the status of this package.
China
Consortium of Maco Corporation
India Limited, Kolkata and Green
Project S.r.I, Italy

{L-1 Cost : Rs 4,39,57,641 (NOC)}, CETs estimate : Rs. 8.76 Crs. (NOC)}

TC held on 14.09.15 and 23.09.15, recommendation approved on


29.09.15 for award of work to L-1 bidder.
Original, differential and decremental price bid of all 6 bidders opened on
15.09.15. Evaluation report awaited from CET.

14.10.14

05.12.14

15.09.15

GEA Process Engineering (India) Pvt.

25.02.15

11.05.15

31.08.15

22.06.15

22.07.15

01.10.15

Maa Jagdamba Enterprises,

Bhilai
Amkay Construction Co. , Bhilai

09.06.14

13.09.14

28.03.14

16.05.14

1. Rana Udyog Pvt Ltd., Kolkata


2. P P Rolling Mills Mfg. Ltd, New Delhi
3. Morgardshammar AB, Sweden
4. Treet Machines Ltd, Ghazibad
5. A R Engg. Works, New Delhi
1. KCS Private Limited, Rourkela
2 Parker Hannifin India Pvt. Ltd., Kolkata
3 Sterling and Wilson Limited.
4 L & T Ltd.
5. Siemens Ltd.
6. Danieli India Ltd

10/9/2015

Page : 36

TC held on 01.10.15 for award of work, recommendation under approval.


RA held on 01.10.15, report awaited from M/s Metal Junction.
TC held on 22.08.15 & 11.09.15 for dropping the tender,
recommendation approved and the tender has been dropped.

TER issued by EDD on 27.08.15 and the same has been forwarded to
Shop on 03.09.15.
CBEC held on 22.09.15.

SN
SCHEME / PACKAGE
L 15 Relocation of Nitrogen Vessels (7 Nos.) and installation of New
Pressure Reducing and Metering Station (PRMS) Package-II
(Consultant MECON) (PCC-TK- R K Panigrahi, DGM) 20168

NIT
19.12.14

TOD
05.02.15

L 16 Replacement of Wet Type LD Gas Holder (Cap. 40,000 M3) by Dry


Type LD Gas Holder (Cap. 60,000 M3) Package-I
(Consultant MECON) (PCC-TK- R K Panigrahi, DGM) 20168

19.12.14

05.03.15

L 17 Installation of Gas Mixing Station of COB#3 in CO&CCD


(Consultant- CET) (PCC TK A.C.Rathi, DGM I/c) 21751

24.02.15

26.03.15

L 18 Upgradation of Waste Gas ESPs of Sintering Plant-III


(Consultant CET) (PCC-TK- R K Panigrahi, DGM) 20168

09.03.15

06.05.15

L 19 Flooring of EHT Yards (MSDS-I, II, III, IV, V & VI)-PSD


(Consultant EDD) (PCC NTK- Md. Naushad Aalam, DM) 22660

01.07.15

30.07.15

L 20 Building and Infrastructure (Pkg.-1) for Setting Up of Static Facility


for Environmentally sound Management of PCB at BSP, Bhilai
(Consultant CET) (PCC-TK- R K Panigrahi, DGM) 20168

26.06.15

13.08.15

L 21 Installation of Coal Dust injection system in BF No-4


(Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206

15.07.15

18.08.15

PBOD

BIDDERS
1. Tuaman Engineering Limited, Kolkata
2. Linde India Limited,Kolkata
3. Blue Star Limited,Kolkata
4. Sanmathi Enterprises,Bhilai
5. Bhilai Techneeds, Bhilai & Mechast Engineers, Bhilai
6. Otto Projects Pvt. Ltd, Kolkata
1. Beijing Shougang Construction Group CoLtd.,
China -Stewarts and Lloyds of India Ltd, Kolkata.
2 Motherwell Bridge Ltd., UK Gillanders Arbuthnot & Co Ltd, Kolkata
3. Bengal Tools Limited
4. Lazarus and Associates Limited, UK and Maco
Corporation (India) Pvt. Ltd. Kolkata
1. Otto Projects Pvt. Ltd., Kolkata
2. Graduate Agro & Mechanical Engineers, Bhilai
3. Technovations, Bhilai
4. Consortium of Mechast Engineers, Durg and Forbes
Marshall Pvt. Ltd., Pune
5. Instrumentation Ltd., Kota
6. Consortium of Oriental Nicco Projects Private
Ltd., Ahmedabad and Oriental Enterprise Pvt. Ltd.,
Vadodara
1. Hamon Research-Cottrell India, Kolkata
2. Unicon Engineers, Coimbatore
3. Elex India P Ltd, Thane & BSBK Bhilai
4. Andrew Yule & Co. Ltd., Kolkata
5. GEA Process Engg (India) Pvt. Ltd., Thane
6. Soil & Enviro Industries Pvt. Ltd., Kolkata
7. K.C. Cottrell India Pvt. Ltd., Gurgaon
8. Alstom India Ltd., Kolkata
1. Amkay Construction Co., Bhilai
2. R K Infrastructure, Ambikapur
3. Rajasthan Associates,Raipur
4. Kulkarni & Sahu Buildcon Pvt. Ltd., Bhilai
5. HSCL, Bhilai
6. West India Construction Co., Bhilai
1. BSBK, Pvt. Ltd., Bhilai.
2. S.K. Jain Construction Pvt. Ltd. Bhilai
3 Vishwa Infrastructure and Services Ltd. Hyderabad
4. Reliable Hi-Tech Infrastructure Pvt. Ltd., Rourkela
5. HSCL, Bhilai
6. Graduate Agro & Mechanical Engineers, Bhilai
1. Oriental Nicco Projects Pvt. Ltd., Kolkata
2. Danieli Corus India Pvt. Ltd., New Delhi
3. Kuttner GmbH & Co KG, Germany
4. Paul Wurth India Pvt. Ltd.

STATUS AS ON DATE
TAR issued by MECON on 26.08.15.

TAR received from MECON on 29.07.15.


MECON forwarded the details on 19.08.15 related to fulfilment of
eligibility of techno-commercially eligible bidders for verification.
Confirmation/ verification are being sought from the issuing
authority.
Revised TAR awaited from MECON.
Corrigendum to TER received from CET on 01.10.15 and the same
is forwarded to Shop for obtaining TBEC recommendation.

TBEC held on 25.08.15.


CBEC held on 31.08.15.
TC to be held.

Documents submitted by all the three parties and sent to EDD on


06.10.15 for evaluation.

Technical meeting held with bidders from 15.09.15 to 22.09.15 at


CET, Ranchi.
TER and TBEC report are awaited.
Techno-commercial offers sent to CET, Shop & Zone on 19.08.15.

5. China First Metallurgical Construction India Pvt. Ltd

L 22 Installation of Coal Dust injection system in BF No-4


(Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206

15.07.15

18.08.15

L 23 Development and operation of 14 MTPA Iron ore Mine at Rowghat of


BSP (Consultant- M/s aXYKno Capital Services Ltd)
(PCC-TK- A.C. Rathi, DGM I/c) 21751

06.05.15

31.08.15

L 24 Modification of F-type block(24 unit/block) into 2F type block (having


12 unit/block) along with other renovation work
(Consultant TED) (PCC NTK- P K Sur, AM) 23207
L 25 Fabrication and Erection of Structural staircase for Ladle Furnace 1
at SMS III (Consultant- Steel Zone)
(PCC NTK- Satya Prakash, DM) 22738

04.08.15

03.09.15

6.
7.
8.
9.
10.
11.

CISDI Engineering Co Ltd, China


Oriental Nicco Projects Pvt. Ltd., Kolkata
Danieli Corus India Pvt. Ltd., New Delhi
Kuttner GmbH & Co KG, Germany
Paul Wurth India Pvt. Ltd.
China First Metallurgical Construction India Pvt.
Ltd.
12. CISDI Engineering Co Ltd, China

1. Jaiprakash Associate Ltd., Noida


2. Theriveni Valencha JV, Tamil nadu
3 Lanco Infratech Ltd, Gurgaon
4. ACB (India) Ltd, Gurgaon
1.
2.
3.

15.09.15

18.09.15

18.09.15

10/9/2015

West India Construction Co., Bhilai


Welcome marketing,Bhilai
Speciality Protection, Bhilai

Suprabhat Pal, Bhilai

Page : 37

Techno-commercial offers sent to CET, Shop & Zone on 19.08.15.

Technical and commercial comments sent to all 4 bidders on


17.09.15.
Techno-commercial offers of 3 bidders opened on 15.09.15 and sent
to TED for evaluation.
Award letter issued to M/s Suprabhat Pal, Bhilai on 05.10.15 at
the value of Rs. 98684 and completion period 3 months.

SN
SCHEME / PACKAGE
L 26 Re-building of COB No.7&8 in CO&CCD
(Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206
a.
Battery Proper (Pkg-1)
b.
Oven Machines (Pkg-2)

NIT

TOD

22.06.15

13.08.15

PBOD

BIDDERS

1. Beekay Engg. Corpn., Bhilai - Gosa Fom, Serbia


2. Taiyuan Heavy Industry Co. Ltd. - Associated
Industrial Furnaces (P) Ltd.
3. Graduate Agro & Mechanical Engineers, Bhilai
4. Bhilai Engineering Corporation Ltd., Bhilai
5. Paulwurth Italia SpA - Paulwurth India Pvt. Ltd. Larsen & Toubro Ltd.
1. Consortium of Beekay Engg. Corporation, Bhilai Hutni Projekt, Frydek-Mistek, Czech Republic
2. NCC Limited, Hyderabad
3. Nuberg Engineering Ltd., Noida
4. Oriental Nicco Projects Private Ltd., Kolkata
5. Beijing Shougang Construction Group - Stewart
& Lloyds of India Ltd.
6. MECON Ltd., Ranchi
7. Gillanders Arbuthnot & Co. Ltd., Kolkata - JSC
Vukhin, Russia
8. BTL EPC Ltd., Kolkata
9. Paul Wurth India Pvt. Ltd.-DMT GmbH & Co.
KG
10. Shriram EPC Ltd., Kolkata - Baosteel
Engineering & Technology Group, China
11. Consortium of M/s Bhilai Techneeds, Bhilai, M/s
Shanxi Qiyuan Chemical Engineering Design Co.
Ltd., Taiyuan and M/s China Metallurgical
Engineering & Project Corporation, Beijing.

c.

Replacement of By-Product Plant Equipment (Pkg-3)

22.07.15

05.10.15

d.

Supply of Design & Engineering Drawings, Providing Expert


Supervision, Performance Guarantee and Inspection of Refractories
at Suppliers premises (Pkg-4)

22.07.15

01.08.15

CUI, Ukraine

e.

Enabling Works for COB#7 (Pkg-5)

22.06.15

01.08.15

04.08.15

22.09.15

1. Rosy Enterprises Pvt. Ltd., Rourkela


2. West India Construction Company, Bhilai
3. HSCL, Bhilai
4. A.K.Dutta & Co. Pvt. Ltd., Jamshedpur
5. Consortium of Sanmathi Enterprises, Bhilai &
S.B.Construction (P) Ltd., Rourkela
6. N.P.Construction, Bokaro
7. Beekay Engineering Corporation, Bhilai
1. GEA Proces Engg (India) Pvt Ltd, Thane
2. Thermax Ltd, Pune
3. Bhilai Techneeds, Bhilai
4. Macmet Engineering Limited, Kolkata
5. Consortium of Enviro Care Filtration & System
& Atmastco Pvt. Ltd.
6. Unicon Engineers, Coimbatore
7. Uniseven Engg. & Infrastructure Pvt. Ltd.,
Kolkata
8. BTL EPC Ltd, Kolkata
9. Evo Tech Pvt Ltd, Bhilai

L 27 Installation of ESP in Sinter Dispatch Route of Sinter Plant II (Pkg.II) (Consultant-CET) (PCC TK V Anil Kumar, AGM) 20206

STATUS AS ON DATE

Note processed on 07.10.15 for approval for issue of NIT.


Technical discussions heldat CET, Ranchi during 19.09-23.09.15.

Techno-commercial offers of 11 bidders opened on 05.10.15 and


and sent to CET, Shop & Zone for scrutiny.

TBEC held on 25.09.15. CBEC held on 29.09.15.


TC held on 29.09.15 for communicating BSPs reply to M/s CUI.
TER received from CET on 07.10.15. Addendum to TBEC received
on 07.10.15 for communicating additional points w.r.t Pkg-1 TS to
M/s CUI.
TC to be held again for deciding further course of action.
TER received from CET on 28.09.15 and forwarded to Shop for
TBEC recommendation.

Techno-commercial offers of 9 bidders opened on 22.09.15 and sent


Sent to all concerned agencies on 23.09.15 for evaluation.

TC held on 01.04.15 for cancellation of subject tender, TC MOM


approved by ED I/c (Projects) on 08.04.15.

L 28 Installation of Secondary Emission Control for three Converters in


SMS-II (Pkg-2) - Civil Works
(Consultant CET) (PCC NTK- V K Shail, AM) 23177
L 29 Installation of Slab Dimension Measurement and Slab Positioning
System in Plate Mill
(Consultant-CET) (PCC TK A C Rathi, DGM I/c) 21751
L 30 Installation of Secondary Emission Control for 3 Converters in SMSII (Pkg. I) at BSP (Consultant-CET)
(PCC-TK- R K Panigrahi, DGM) 20168

TC recommendation approved on 20.03.15 to cancel the subject


tender and re-tender the package after review of Eligibility criteria.
Revised TS and Eligibility criteria awaited.
Board note sent on 04.07.15 for submission of fresh proposal for the
subject package based on revised TS and estimate within 2 months.

10/9/2015

Page : 38

SN
SCHEME / PACKAGE
L 31 Installation of Electric Motor driven turbo blower at P & B Station
(Consultant MECON) (PCC TK- R K Panigrahi, DGM) 20168

NIT

TOD

PBOD

BIDDERS

L 32 Radiotherapy Phase III - Proposed LINAC Facility (Architectural,


Civil, Water Supply & Sewerage, Electrical and Air Conditioning
Works (Consultant-EDD) (PCC NTK- A.K. Agrawal, DM) 23219
L 33 Replacement of Exhauster # 7 with higher capacity exhauster in Gas
Condensation Plant#2 of CO&CCD
(Consultant- CET) (PCC TK - A C Rathi, DGM I/c) 21751

M. MODERNISATION & EXPANSION OF BSP TO 7.0 MT

Stage-I approved by SAIL Board on 03.04.07 at an indicative cost of Rs. 11262 Crs. and sanctioned Rs. 200 Crs. Towards Enabling / Preliminary works.

M1

Capacity Enhancement at MSDS- 4 & 5 (Pkg 70 A)


(Consultant-MECON) (PCC TK A C Rathi, DGM I/c) 21751

15.05.14

22.10.14

03.03.15

Sterling & Wilson, Kolkata

M2

Fire Station Building (Pkg. No. 138) (Retendered)


(Consultant-MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Duration 12 months

14.08.14

22.09.14

13.08.15

Amkay Construction Co., Durg


Balaji Enterprsies, Bhilai

M3

Procurement of Rail Road Shunting Locomotive 02 Nos.


(Pkg -098-II)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Duration 08 Months

31.08.13

08.11.13

M4

Octmentation of SMS-II (Pkg.-038)


(Consultant-MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Modernization of Gas Cleaning Plant (Pkg.-038-03)
(Re-tendered) Duration 12 months
Combined blowing of Argon / Nitrogen in Converter
(Pkg.-038-05) (Re-tendered)
Modernization of BOF Automation (Pkg.-038-06)
(Re-tendered)
Duration 18 months
Construction of Mould & Segment Repair Shop (Pkg-129A)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Fire Protection System in Universal Rail Mill and Bar & Rod Mill
(Pkg No 126-02) (Consultant- MECON)
(PCC TK A.C.Rathi, DGM I/c) 21751
Procurement of Refractories and its Support Structure for Protection
lining of BOF & CCP Complex (Pkg. No.-124) (Consultant- MECON)
(PCC-TK- R K Panigrahi, DGM) 20168
1. Refractory bricks , castables and mortars - (06 items)

i.
ii.
iii.

M5
M6

M 7

STATUS AS ON DATE
As per MOM held at SAIL Corporate Office on 04.07.15, proposal is
kept in abeyance for time being. Meanwhile, BSP may examine the
feasibility of interconnection of the air blast grids of PBS-1 & PBS-2
with the help of Consultant.
TC recommendation approved on 09.08.13 for cancellation of the
present tender & re-tendering the package.
Revised proposal awaited from Zone.
Letter sent to Shop on 29.08.13 informing about the cancellation of
tender and to re-tender package after reviewing TS & Eligibility
criteria.

10.03.15

10.04.15

24.02.15

02.05.15

1. TrackmobileLic, USA (Offer submitted by


Lloyds Engg. Corp., Kolkata)
2. Harbin Railway Bureau Industry General
Corp., China.
3. ITK Ingenieria S.A., Spain.
4. Zephir spa (c/o M/s OctagonaIndia, Delhi

08.09.15

HSCL,Bhilai
1.New Fire Engineers.
2. Sterling & Wilson:
3.Securix multiple solution
4. SFS Fire & Security

{L-1 Cost Rs. 48.76 crs, Estimate Rs. 40.24 crs (NOC)}
Case sent to PP&E on 18.04.15 for obtaining Stage-II approval.
Revised price after discount received from bidder on 08.09.15 and
has been sent to MECON for re-evaluation.
Vide our email dtd 06.10.15, party has been requested to extend the
price & offer validity upto 31.12.15.
- {L-1 Cost Rs. 8.9 crs, (LCNC) Estimate Rs. 10.97 crs}
Case sent to PP&E on 15.09.15 for obtaining Stage-II approval.
TC recommendation approved on 15.09.15 for award of work to
Consortium of M/s Amkey Construction Co., Durg and M/s Balaji
Enterprises, Bhilai.
Revised Final TAR received from MECON on 08.06.15.
Mail sent to MECON on 17.08.15 to give commercial
comments/recommendation on offers submitted by parties.

Duly cleared EOI alongwith comments for incorporation of Financial


Eligibility Criteria has been forwarded to Shop on 02.07.15.
MECON suggested BSP on 26.08.11 not to invest for this package.
Case is under process by Shop to drop the proposal.
TC recommendation approved on 30.03.15 to cancel the present
tender. Letter along with copy of approval forwarded to GM (SMS II
& CCP) on 31.03.15 for further processing the case.
Price bids opened on 08.09.15.
TC held on 28.08.15, further process (approval) kept on hold as per
Key drivers instruction.
TS issued by MECON on 07.02.15.
Cost estimate received from MECON on 01.04.15.
PO created on 22.07.15 to M/s SRU, Bokaro at a LCNC cost of Rs.
18.61 Crs. and delivery period is 31.03.16.

10/9/2015

Page : 39

SN

SCHEME / PACKAGE
2. High Alumina Low Cement Gunning Castable (01 item)
Open Tender

NIT
07.05.15

TOD
05.06.15

3. SS Anchors 03 items
Open Tender

18.05.15

10.06.15

1. Luthra C.S. Engg. Works


2. Industrial Associates
3. Raghukul Marketing and Engg. Services
4. AMI Refractrahold
5. Jana & Co., Howrah
6. Ravi Engineering Works Bhilai
7. Bhilai Techneeds, Bhilai
8. R. K. Steel Industries, Bhilai
9. Arun Engineers and Fabricators,
10.Rajat Metals, Mumbai
11.Sunrise Machination LLP, Pune

Comments/recommendation received from Shop on 24.09.15 and


MECON on 01.10.15 and sent to Purchase along with Shops
comments.
Reminder sent to MECON on 29.09.2015 for comments
/recommendation on parties offers and clarification.

M8

Mould & Segment Repair Shop Machines/Equipments (Pkg-129B)


(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168

09.05.15

13.07.15

Post MoM clarification/documents sought by MECON from all


bidders.

M 9

Procurement of Freight cum Passenger Elevators for BOF & CCP of


SMS-III (Pkg.-029C) (05 items)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168

05.06.15

28.08.15

1. Shiv Machine Tools, Chennai


2. MUV Multitech Pvt. Ltd., Chennai
3. Elite Engg. & General Works, Batala
4. Maco Corporation (India) Pvt. Ltd.,
Kolkata
1.East Endia Elevators, Ahmedabad
2.ORBIS Elevators Co. Ltd., Ahmedabad
3. ECE Industries Ltd., Nagpur
4. Kone Elevator India Pvt. Ltd.Raipur
5. Omega Elevators, Ahmedabad

M 10

Balance Railway Track Work for Plant Internal Yard (Pkg- 95B1)
(Consultant- MECON) (PCC NTK- Satya Prakash, DM) 22738

13.08.15

04.09.15

Jhajharia Nirman Ltd, Bilaspur

M 11

Mobile firefighting equipments (Pkg. 098-3)


2. Towing Vehicle (PR No.-1200000892) (Re-tendered)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168
Stack emission control for 2 nos of vertical shaft kilns of RMP-II
(Consultant-CET) (PCC TK R K Panigrahi, DGM) 20168
Laboratory Buildings and Laboratory Equipments (Pkg-090A)
(Consultant- MECON) (PCC-TK- R K Panigrahi, DGM) 20168

20.02.15

09.09.15

1. Tata Motors

01.10.15

29.10.15

M 12
M 13

M 14

Power Factor Compensation (Pkg-071B) (Consultant MECON)


(PCC TK A C Rathi, DGM I/c) 21751 Duration 16 months

M 15

Plant wide Network connectivity (Pkg.145)


(Consultant- MECON) (PCC TK A C Rathi, DGM I/c) 21751

M 16

Solid state Interlocking Signaling system (Pkg.-096)


(Consultant-MECON) (PCC-TK - A C Rathi, DGM I/c) 21751
Installation of New LT Substation - 50B and Replacement of existing
substation - 9B & 9H (Pkg.-118 R)
(Consultant-MECON) (PCC TK V Anil Kumar, AGM) 20206

M 17

M 18

PBOD

Bidders
1. Continental Refractories.
2. Sharadaa Ceramics.
3. Shreekant Ind..
4. Industrial Associates.
5. Refcom.
6. Dalmia Refractories.
7. TRL Krosaki.
8. National Refractories.
9. Champion Ceramics
10. IGL Refractories
11. Arvind

STATUS AS ON DATE
Comments/recommendation received from Shop on 26.09.15.
Reminder sent to MECON on 29.09.15 & 0810.15 for comments /
recommendation on parties offers and clarification

Reminder sent to MECON and Shop on 03.10.15 to give


comments/recommendation on partiess offers.

(L-1 price Rs. 13.22 Crs., Estimate- Rs. 18.22 Crs.)


Price evalauation received from MECON on 25.09.15.
Price negotiation to be held.
Reminder
sent
to
MECON
on
29.09.15
comments/recommendation on parties offer.

for

Tender uploaded on SAILs website on 01.10.15 with due date of


bid submission as 29.10.15.
Eligibility criteria clearance from Standing Committee received on
03.10.15. Mode of tendering suggested by Shop received on
07.10.15.
MECON to issue revised TS after compiling the relevant data from
technological packages.
Final TS, Eligibility & Commercial Volume awaited from MECON.
Final TS awaited from MECON.
MECONs offer pertaining to preparation of SIP received on
24.10.14. Letter forwarded to PP&E on 24.10.14 for further needful.
TC recommendation approved on 17.02.15 to drop the present tender
and to revise TS and EC for re-tendering the case.
Final TS, Eligibility & Commercial Volume awaited from MECON.
TC held on 30.07.15 and recommendation approved to cancel the
present tender.

Ferro-alloy storage yard (Pkg.123) (Retendered)


(Consultant-MECON) (PCC-TK- R K Panigrahi, DGM) 20168

10/9/2015

Page : 40

You might also like