Professional Documents
Culture Documents
03 Schedule B Plaster
03 Schedule B Plaster
Name of
Work :-
S C H E D U L E 'B'
MEMORANDUM SHOWING THE ITEM OF WORK TO BE CARRIED OUT
It.
No.
1
1
Quantities
estimated
but may be more
or less
2
902.98
3
Smt Item No.1
Providing and Applying Polymer modified
cementious repair treatment to existing
damaged R.C.C. SURFACE (R.C.C. Lintel,
Slab, Chhajaa, Stair, Slab etc.) by removing
affected
concrete
portion
cleaning
reinforcement
thoroughly
with
light
hammering wire brushing & later applying an
approved
rust
remover
on
corroded
reinforcement applying a slurry coat to
reinforcement & concrete surface in the
proportion of (1.5 : 1) (Cement : Polymer)
as per manufacture specification). After that
applying a bond coat to the concrete surface
in the proportion of (50 Kg. of OPC Cement :
2 Liters of acrylic base polymer : 150 Kg. of
sand) adding 8 to 10 Liters water by hand
packing or trowel finish up to required
thickness including curing etc. complete & as
directed by Engineer in charge.
Estimated Rates
Item of
Work
In Figures
Rs./ Paise
Unit
In Words
4
5
6
538.49 Rupees
Five
Hundred Smt
Thirty Eight and Paise
Forty Nine Only
Total amount
according to
estimated
quantities
7
486245.70
1
2
2
902.98
3
Smt Item No.2
Colour washing with lime on wall surfaces
(three coats) to give an even shade including
thoroughly brooming the surface to remove
all dirt, dust, mortar, drops and loose scales
of lime wash and other foreign matter.
5
9.19 Rupees Nine and
Nineteen Only
Rupees Four Lacs Ninety Four Thousand Five Hundred Forty Four And Paise Nine Only
6
Paise Smt
TOTAL AMOUNT
7
8298.39
494544.09
Estimated Amount
Estimated Amount
Put to tender
Deduct
Total
% below
Rs.
Rs.
Rs.
494544.09
Put to tender
Add
Total
% above
Rs.
Rs.
Rs.
494544.09
Note 1
All the work shall be carried out as per Public works Department Hand Book and other specification of the Division
or as directed.
Note 2
All the columns in the Schedule B filled in INK and the total of the entries in the last column should be struck by
the Contractor under his Signature.
Note 3
Rate quoted include clearance of site (prior to commencement of work and at its close) in the respects and hold
good for work under all conditions, site moisture, weather etc. complete.
Executive Engineer,
Capital Project Division No.1,
Gandhinagar.