PowerPoint Presentation

Chapter 8

Boiler Operation Procedures


Taking Over a Shift First-Time Boiler
Start-up Procedures Routine Boiler
Start-up Procedures Boiler Maintenance
Procedures Boiler Shutdown
Procedures Boiler Inspection
Hydrostatic Test Boiler Troubleshooting

Chapter 8 Boiler Operation Procedures

Boiler operation information is communicated to the


boiler operator starting the shift to specify any special
procedures required.

Chapter 8 Boiler Operation Procedures

When blowing down the


gauge glass, water should
enter the gauge glass quickly
when the gauge glass
blowdown valve is closed.

Chapter 8 Boiler Operation Procedures

During a bottom
blowdown, the boiler
should be under
light load and the
water level should
be at the NOWL.

Chapter 8 Boiler Operation Procedures

The blowdown valve is


opened to evacuate the
low water fuel cutoff
chamber with the burner
firing during blowdown.

Chapter 8 Boiler Operation Procedures

When testing the


flame scanner, the
flame scanner sensor
is covered to simulate
a flame failure.

Chapter 8 Boiler Operation Procedures

Before starting the


boiler for the first time,
the boiler should have
a minimum water level
of approximately 2
above the bottom of the
gauge glass.

Chapter 8 Boiler Operation Procedures

The burner is started in


low fire according to
procedures specified
by the manufacturer.

Chapter 8 Boiler Operation Procedures

The boiler vent is closed


when pressure in the
boiler reaches 10 psi to
15 psi.

Chapter 8 Boiler Operation Procedures

The main steam stop


valve is opened slowly to
allow the pressure to
equalize when the boiler
is a few pounds below
the header pressure.

Chapter 8 Boiler Operation Procedures

A broken or discolored
gauge glass is replaced
using standard
procedures for maximum
safety.

Chapter 8 Boiler Operation Procedures

The low water fuel cutoff


controls must be installed
vertically for proper
performance.

Chapter 8 Boiler Operation Procedures

The burner is maintained and tested to ensure proper


operation and maximum efficiency.

Chapter 8 Boiler Operation Procedures

Feedwater pumps
should be checked
periodically to ensure
proper bearing
temperatures and
checked for any
unusual vibration.

Chapter 8 Boiler Operation Procedures

Safety valves are


routinely tested to ensure
proper operation and
must be serviced by an
authorized manufacturer
representative.

Chapter 8 Boiler Operation Procedures

Steam traps are checked


for proper operation
when determining the
cause of a steambound
feedwater pump.

Chapter 8 Boiler Operation Procedures

When inspecting a
boiler, inspect tube
sheets, tubes, and
other internal parts for
corrosion, overheating,
and/or other damage.

Chapter 8 Boiler Operation Procedures

Handhole covers are


removed to provide
access to boiler parts
during a boiler
inspection.

Chapter 8 Boiler Operation Procedures

All internal surfaces


are exposed and
cleaned prior to the
boiler inspection.

Chapter 8 Boiler Operation Procedures

Troubleshooting steps
from the manufacturer
provide a guide to
correcting a boiler
operation problem.

Chapter 8 Boiler Operation Procedures

The boiler room log lists


boiler operation data that
can be used to increase
boiler efficiency and
identify a potential
malfunction.