Professional Documents
Culture Documents
EMH Presentation - 1 0
EMH Presentation - 1 0
Aleksander Gornjak
Project Manager
EM Hidromontaa
P.O. BOX: 73739 Abu Dhabi
Tel. : +971-2-6724283
Email: emhidro@eim.ae
4/15/2015
Contents
1.
2.
3.
4.
5.
6.
7.
8.
Introducing EMH
Safety Policy
Environmental Policy
QC Policy
QA/QC Implementation
Organisation
Time Schedule
Mechanical activities
8.4 GT Exhaust
8.5 GT Enclosures
8.6 GT Loose Parts
8.7 HRSG
8.8 Main Stack
8.9 Diverter damper
8.10 Steam piping
8.11 Other equipment
8.12 Fin fan system
8.13 Fuel gas system
8.14 Horizontal pumps
8.15 Vertical pumps
8.16 Static equipment
2
Contents
9. Electrical Activities
9.1 Main equipment
(transformers, IPB,
MV/LV panels,...)
9.2 Cables
9.3 Cable trays, conduits
9.4 Earthing
9.5 Lighting
10.2 GT Side
4/15/2015
Introducing EM Hidromontaa
Slovenian Engineering and Construction Contracting Company
Founded in 1948
Power generating and distribution plants, oil, gas and petrochemical
plants, pipelines, desalination plants..
Projects in: Algeria, Austria, Bahrain, Croatia, Czechoslovakia,
Germany, Libya, Nigeria, Netherlands, Norway, Pakistan, Syria,
Sri Lanka, Sweden, United Arab Emirates,
Venezuela, Yugoslavia
1983 established branch in Abu Dhabi
Prequalified as contractor in the UAE with:
TAKREER, ADGAS, ADCO, ADWEA, DEWA
4/15/2015
4/15/2015
4/15/2015
4/15/2015
Potencial Hazard
T.B.M
HOUSE KEEPING
MANAGING POINT
Daily TBT performed by Safety officers discussing different safety topics
Permanent house keeping team under control of designated Safety officer
Close coordination with waste disposal subcontractor (Dulsco)
Mandatory use of safety harness with double lanyard for each work above 2m height
ELECTRICAL SHOCK
Only authorised and qualified electrical staff allowed to work on electrical components under PTW
Regular check of all electrical tools and distribution network
LIFTING OPERATION
Only certified staff allowed to work with lifting operation with cerified and inspected equipment
Regular inspection of lifting gears for evetual damage
OIL FLUSHING
OPERATION
Proper PPE and Oil Spilage Kits and Fire Fighting Equipment should be
available
A WOUNDED BY AN
EDGED MATERIALS
Protection of sharp edges with plastic material, mandatory use of protective equipment like helmets and hand gloves
4/15/2015
QC Policy
Companys activities places emphasis on experience,
expertise, capability, reliability and quality
Ensure that the requirements of the International Standards
and/or customer specifications are met
ISO 9001:2008 Certification
All employees follow the organization
and controls set out within the
operation procedures
4/15/2015
QC Policy
Certificates ASME PP, A
4/15/2015
10
QC Policy
Certificates ASME A and National Board R
4/15/2015
11
4/15/2015
12
4/15/2015
13
4/15/2015
14
Activities
1 Site construction
MANAGING POINT
All works should be performed in accordance with project specifications,
drawings and international standards
EMH Site Supervisors should ensure strict compliance with documentation
EMH QA/QC
2
inspection
RFI with pre inspected data should be forwarded to Client for joint inspection
and final acceptance
QA/QC handover
document
4/15/2015
4/15/2015
16
4/15/2015
17
4/15/2015
18
4/15/2015
19
4/15/2015
20
Time Schedule
4/15/2015
21
Mechanical activities
8.1 Gas Turbine
Check foundation
Placement of Turbine
Assembly works
- Piping
- Mechanical
Insulation works
Final check
4/15/2015
22
Mechanical activities
8.2 GT Generator
Check foundation and
installation of supports
Placement of Generator
Assembly works
- rotor
- exciting compartment
Alignment against
gas turbine
Final check
4/15/2015
23
Mechanical activities
8.3 Turbine Air Inlet
Preparation of material and
equipment
Erection of Air Intake System
(Steel Structure, Ducts, Filter
System, Piping)
24
Mechanical activities
25
Mechanical activities
8.7 HRSG
Preparation of
foundations
Installation of
casing structure
Erection of HRSG
modules and drums
Installation and
welding of piping
4/15/2015
26
Mechanical activities
27
Mechanical activities
Prefabrication of piping
Process and utilities piping
Erection & welding
Testing & Flushing/Blowing
28
Mechanical activities
8.12 Fin Fan Air Cooler System
Check foundation
Installation of supporting
steel structures
Placement of Fin Fan Coolers
and interconnection works
4/15/2015
29
Mechanical activities
8.13 Fuel Gas Compression & Fuel Gas Supply System
Phase I working area
Check & prepare
foundations
Placement of Gas
Compressors
Interconnection pipework
Alignment & grouting works
4/15/2015
30
Mechanical activities
8.14 Horizontal Pumps Installation
HRSG Feed Water Pumps
Closed cooling water
pumps
Make up water pumps
Back up Fuel Oil pumps
Service Water Pumps
Sump pumps
4/15/2015
31
Mechanical activities
8.15 Vertical Pumps
4/15/2015
32
Mechanical activities
8.16 Static Equipment
4/15/2015
33
Electrical activities
34
Electrical activities
4/15/2015
35
Electrical activities
MV/LV Panels
Check foundation
Bulk installation in
accordance to drawing
Busbars connection
Testing of busbars (HIPot,
Joint resistance)
4/15/2015
36
Electrical activities
9.2 Cables
MV/LV, Control
Preparation of pulling
cards
Cable drums
Route preparation
Setting of roller and
pulling
Dressing
Testing
4/15/2015
37
Electrical activities
9.3 Cable trays and Conduits
Preparation of supports
Installation of trays in
accordance to drawing
Earthing & Touch-up
paint
Covering
4/15/2015
38
Electrical activities
9.4 Earthing
Installation of earthing system
in accordance to drawing
CAD welding
Earth resistance test
4/15/2015
39
Electrical activities
9.5 Lighting
Preparation of material
Installation of lighting panels, lighting
fixtures in accordance to the drawings
Cable pulling
Termination
Testing
4/15/2015
40
10
I&C activities
10.1 Precalibration
Follow Data Sheets
Compare Setpoint of the
Instrument
Calibration
Calibration certificates
4/15/2015
41
10
I&C activities
10.2 GT Side
Skid mounted instruments
(Lube oil, fuel gas, fuel oil, skids..)
Install the skid as per the drawings
Check the alignment & accessibility of
skid & instruments
42
10
I&C activities
43
10
I&C activities
44
10
I&C activities
45
11
4/15/2015
46
11
4/15/2015
47
11
4/15/2015
48
11
4/15/2015
49
12
References
50
12
References
TNBE 1034MW/70 MIGD IWPP
2007-2008
Complete MEI Works - P&WI
Client: ADWEA/TAPCO
FUJAIRAH F2 IWPP
102 MIGD/Day MED Plant
2008-2010
Complete MEI Works WI
Client: ADWEA/FAPCO
4/15/2015
51
12
References
SHUWEIHAT S1 IWPP
1500MW Power Plant
2002 - 2004
Erection of TBN & BOP
Client: ADWEA / SCIPCO/ Siemens
4/15/2015
52
12
References
53
EM Hidromontaa
P.O. BOX: 73739 Abu Dhabi
Tel. : +971-2-6724283
Email: emhidro@eim.ae
4/15/2015
54