Professional Documents
Culture Documents
AAIT Final Internship Report February, 2014)
AAIT Final Internship Report February, 2014)
February,2014]
CHAPTER 1
Page 0
AAIT
February,2014]
Company Background
1.1,Company Profile
JDAW consulting architects and engineer is Grade-1 firm. It
established in
April 2000 GC owned and
managed by arc Daniel Assefa.
The companys business has shown its development in a short
period of time through hard working of the staff members of
the company strengthening its capacity and presently the
company has an investment license with a capital of
183,000,000 Birr.
The company has 120 employees. Construction Company is
mainly engaged in the construction sector and undertakes
construction of apartments, guest houses, mixed use
buildings, sport fields and offices for government, NGOs and
private & public use.
Currently the main business lines of the company are:
Design for building, land scape and interior
Supervision work
AAIT
February,2014]
documented
Quality
Page 2
AAIT
February,2014]
AAIT
February,2014]
Page 4
AAIT
February,2014]
Page 5
AAIT
February,2014]
General Manager
Legal Advises
QMS
Auditor
finance
department
Authority sector
Secretary
Casher
Deputy Manager
IT
Design department
Supervision
&contractor
administration
departement
Plotting
Electrical
sanitary
Design
Design
Arc 1
Arc 4
structural
architectural
quality
Design
Design
survey
Arc 2
Arc 3
Arc 5
Page 6
AAIT
February,2014]
Draft person
CHAPTER 2
My overall internship experience
2.1, How I joined the company
It was during mid of October that we were given a letter with subject
that requests to host qualified interns from Addis Abeba University,
Faculty of Technology. We were also given a detailed orientation by
staff members about how the coming internship program was planned
to be and what possible challenges and problems we could face.
The orientation mainly focused on helping us realize that no one could
believe in us unless we were strictly responsible ready to learn & grasp
knowledge we could get from any one.
As soon as we were given the orientation I informally and formally was
searching for construction companies and design offices that could
give me the chance to practice in their projects. And I was given a
positive response from Jdaw arc &consulting office.
I started practicing there on October and I was required to work for a
week or two before I was given the expression of agreement to host
me.
Page 7
AAIT
February,2014]
Project Engineer
Site Engineer I
Page 8
AAIT
February,2014]
C, Slab
reading the length and width excluding the beams
multiplying the two dimensions for each panel
Page 9
AAIT
February,2014]
Page 10
AAIT
February,2014]
Page 11
AAIT
February,2014]
Column forms
This consists of a vertical mold of the desired shape and size which has
to retain the wet concrete and resist the initial hydrostatic pressure
caused by wet concrete.
Procedure:
The Construction procedure is as follow to erect vertical column from
Check the centering (eccentricity) of previous column heads to
column form
Column yokes (Cratury) are placed immediately after the slab cast,
and helps to keep the column forms straight and strong.
Gas is painted on form work to remove easily.
Page 12
AAIT
February,2014]
Beam forms
This is basically a three sided box supported and propped in the correct
position and to the desired level. The beam formwork sides have to
retain the wet concrete in the required shape and be able to withstand
the initial hydrostatic pressure of wet concrete whereas the formwork
soffit apart from retaining the concrete has to support the initial load of
the wet concrete and finally the set concrete until it has gained
sufficient strength to be self-supporting.
Procedure
The construction procedure is:
Page 13
AAIT
February,2014]
Slab forms
The slab in our site is solid slab and we prepare suspended beam form
work and slab form work together. The slab form work have to retain
wet concert and able to with stained the initial hydrostatic pressure of
wet concert whereas the form work soffit it appear from retaining the
concrete has to support the initial loads of the wet concrete and live
Page 14
AAIT
February,2014]
load finally the set concrete until it has ginned sufficient strength to be
self-supporting.
Procedure
Props positioned as per required spacing and leveled throughout the
slab and joists are laid horizontally.
Soffit (Fond or a form work under slab) or called panel as general
name is placed, leveled and petitioned. Range (gas) painted on it to
remove form work easily after dry.
Place ribbed block on
Place bottom and top (negative rein forcemeat) as required and fix
reinforcement with beam re- forcemeat bar.
Finally check before casting for space.
Page 15
AAIT
February,2014]
Scaffoldings
These are constructing to support the formwork. In addition, it serves
as a ladder for the workers to walk up & down, and to transport the
necessarily construction inputs, also enables for the workers to stand
on it at the time of plastering and painting. It is necessary to consider
width. It must be enough to pass walk up and down with material at
the time.
Page 16
AAIT
February,2014]
REINFORCEMENT
Setting of reinforcement
Reinforcing steel is buried in concrete to keep them from cracking and
Breaking. This reinforcing steel must be set in different forms before
the Concrete is placed.
Page 17
AAIT
February,2014]
the bar schedule showing nothing but lengths, sizes, and bending
needed for all the reinforcing bars in the construction for a given
footing pad, foundation column, beam, column, or slab. The bar bender
then cut and bend the steel rod as the requirement.
Placing of reinforcement
As required for the construction of footing pad, foundation column,
beams and columns, when all of the reinforcing bars have been cut to
the right lengths and have been bent, then the main beam & column
reinforcements tied with stirrups of diameter 6mm bars by tying wire.
Page 18
AAIT
February,2014]
For case of footing pad it may be fixed in the site of its cast as per size
of footing.
Reinforcing steel is placed in position in the concrete form by workers
(bar benders). As the main beam & column bars have been produced
before, it should place in position carefully.
Page 19
AAIT
February,2014]
Page 20
AAIT
February,2014]
And for slab after cut of right length the reinforcement is placed on the
prepared form work
and bend as necessary and fix with beams per the design the bottom
and top reinforcement.
Stair construction
Stair is a structure which is used as a link between one floor and
another floor. it need specialized professionals and need special need
than anther works
Procedures
The procedures to construct the stairs are as follow
Form works (panels) were constructed. In addition, the level,
cleanness and smoothness of the form work were also checked.
Page 21
AAIT
February,2014]
Page 22
AAIT
February,2014]
Page 23
AAIT
February,2014]
Concrete work
Concrete is arguably the most important building materials, paying
apart in all building structures. It is very durable and fire resistant.
Concrete is made of crushed rock or gravel that is mixed with sand,
Portland cement and water.
The forms for the concrete beams, columns, and slabs have been set
tied together and braced in to position. The reinforcement steel bar
has been set in the forms and tied in place so that it will not move
when concrete is placed around it. We are now ready to prepare the
concrete to place in the forms.
Preparing materials for concrete:
Cement
Cement for cast-in-place shall be Portland or Portland-pozzolana.
Whichever type of cement is being used it must be properly stored on
site to keep it in good condition. Cement shall be stored in bags or
containers in an enclosed and ventilated Space that would protect it
from Deterioration.
Page 24
AAIT
February,2014]
Aggregate
Aggregates shall be obtained from approved source.
Fine aggregate: shall be natural or crushed gravel or
stone, clean sharp
sand free from harmful matter. Generally, the sand that is used in
concrete is called Fine aggregate.
Coarse aggregate: an aggregate pass through 7.5mm
sieve and which are entirely retained on 4.75mm sieve. Generally, the
gravel or crushed rock that is used in concrete is called coarse
aggregate.
Water
Page 25
AAIT
February,2014]
Must be cleaned and free from impurities which are likely to affect the
quality or strength of the resultant concrete. It is often said that the
water used in concrete should be fit to drink.
Mixing of concrete
The process of mixing cement, water, fine aggregate & coarse
aggregate in suitable
Proportion is known as mixing of concrete. This process should ensure
uniform color, consistency, and homogeneity of the concrete.
Segregation should not take place during process of mixing. Here,
before mixing for casting, trial mix should be done to know the quality
of concrete.
The mixing methods may be hand mixing or machine mixing. On large
works, machine mixing proves economical and convenient. Concrete
produced by machine mixing is more homogeneous. The mixer shall be
thoroughly cleaned before use, and the first batch shall contain excess
cement to coat the inside of the drum. The volume of concrete in any
batch shall not excess.
Page 26
AAIT
February,2014]
CHAPTER 3
The overall benefits I gained from the
internship
3.1 In terms of improving my practical skills
During my internship experience, I have been able to gain a lot in
improving my practical skills as I have been observing, learning and
practicing:
The different stages of building construction
The communication language used at construction site
The use of ancillary items and the way they were applied to
different building parts
Project evaluation in terms of cost
Different problems that can occur during construction and the
possible ways to address those problems
Page 27
AAIT
February,2014]
Flat slab
Ribbed slab
Page 28
AAIT
February,2014]
fig13, spancer
AAIT
February,2014]
AAIT
February,2014]
In general, I have learned that there are many problems and variations
that could occur during construction phase of a building. And the
solutions should be flexible and creative according to the type of the
problem occurred.
Page 31
AAIT
February,2014]
Page 32
AAIT
February,2014]
AAIT
February,2014]
Page 34
AAIT
February,2014]
AAIT
February,2014]
to
plan
Financial management
Wide financial flow is achieved through detailed market studies and
also taking long term contracts with the best material suppliers in
terms of quality and cost.
Page 36
AAIT
February,2014]
CHAPTER 4
Conclusions and recommendations for the company
4.1, Conclusions
I have been involved in the apprenticeship program for the last 4
months in jdaw arc consulting office . The internship experience has
helped me to:
Learn Practical consideration for building construction & design
Upgrade my theoretical knowledge and visualizations
Learn about project evaluations & cost management
Upgrading my ability to be creative, confident and take risks in
my future professional career
As was discussed in the company profile and major achievement of the
company, it has gained a considerable capital growth and recognition
from the international organization for standards. It has achieved the
rapid growth by focusing on finding large projects and by trying to
double its project performances.
Page 37
AAIT
February,2014]
Page 38
AAIT
February,2014]
4.2, Recommendations
AAIT
February,2014]
AAIT
February,2014]
Appendix
Hard core = /
Stirrup= ,
Plumb bob=
Footing pad bars= ,
Bottom soffit =
Page 41
AAIT
February,2014]
Side board =
Brace =
Float =
Scaffolding = ,
Tee= ,
Profile= ,
String= ,
Yoke =
References
Building construction by Dr. Abebe Dinku
Page 42
AAIT
February,2014]
February 2014
Page 43