NPP/0050QENFB INFRASTRUCTURE AND UTILITY

BUILDINGS

Project Completion:

03-April-2017

Contract Price:

QAR 1,553,395,868.06/-

PROGRAMME NARRATIVE STATEMENT


1.1

Project Data :

Contract:

Client:

Project Management
Consultant:

NPP/0050-QENFB Infrastructure and


Utility Buildings

NEW PORT PROJECT

1.2

Project Description:

Infrastructure and utility building for new Naval Base Force to be developed on a
AECOM

reclaimed platform, created from dredge materials


1.3

Programme Description

Contractor:
Activities are organized under following work breakdown structure.

QM JV

1. GENERAL ADMINISTRATIVE
Project Start Date:

MILESTONES

31-December-2014

TIME FOR ACCESS TO THE SITE


Contract Duration:

AREA WISE DURATION

825 Calendar Days

TIME FOR COMPLETION


2. PRELIMINARY
CONTRACTUAL REQUIREMENTS

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 1

MANAGEMENT AND SITE SUPERVISION

Duration

STATUTORY PERMITS AND APPROVALS

AREA

3. MOBILISATION & PRELIMINARY WORKS

Access

Completion

from

Date

Date

Commencem

4. ENGINEERING

ent Date

CONTRACTUAL SUBMISSION AND APPROVAL

Area A1 - " Foul Water,

31-Dec-

30-Jul-15

212

underground Installed &


Area
A2 - " Foul Water,
Tested)

2014
31-Dec-

26-Sep-

270

underground Installed &


Area-E
Tested)

2014
31-Dec-

2015
29-Dec-

364

Area-G

2014
15-Apr-

2015
27-Mar-

453

Area-D

2015
31-Dec-

2016
21-Aug-

600

Area-F

2014
17-Aug-

2016
03-Oct-2016

643

6. CONSTRUCTION.

Area-A1

2015
31-Dec-

03-Nov-

674

7. TESTING & COMMISSIONING

Area-B

2014
31-Dec-

2016
24-Dec-

725

8. HANDING OVER.

Area-A2

2014
31-Dec-

2016
11-Jan-2017

743

For programming and planning purpose each sub division are further divided in to

Area-H

2014
16-Jan-

27-Feb-

790

various levels based on the works involved.

Area-I

2016
16-Jan-

2017
27-Feb-

790

Balance of Works

2016
31-Dec-

2017
03-Apr-

825

2014

2017

KEY PERSONNEL CV
SUBCONTRACTOR PREQUALIFICATION
METHOD STATMENTS
SURVEYING AND SETTING OUT
DESIGN AND SHOP DRAWING
MATERIALS
5. PROCUREMENT/ DELIVERY

1. GENERAL ADMINISTRATIVE

Complete

Project Duration
Project commenced on 31st December 14 with the project duration of 825 days,

2. Preliminary

and it will be completed on 3rd April2017.Project Milestones


Project contractual milestones are identified under the conditions of the contract
by client.

Contractual

Programme starts with a start milestone as Project Start Date


The finish milestone project Completion Date
Identified Project contractual milestones dates are been listed in below table

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

The Preliminary work has start with Contractual requirements.

Page 2

requirements

which

has

Performance

Bond,

Workmen

Compensation Insurance Policy, Constructional Plant & Equipment Insurance


policy, professional indemnity insurance policy, Construction all-risk insurance
policy, and Parent Company Guarantee and Advance payment.

Management Site Supervision cost is considered as General Item as


mentioned in Schedule of Price.
Statutory permits and approvals which are requiring having preliminary
approvals prior require starting the construction works. the

following are the

require permits which having submittal 26 calendar days and Approval 30


calendar days, Obtaining All necessary permits With NOC, Environmental Permit
(MOE), Advertise Permit, Dewatering Permit, Interface Clearance, Excavation
Permit.

Project Sign Board


Completion of Fuel Depot
Completion of Concrete Batching Plant
Temporary Site Access Road

The Mobilization Construction and installation works is sub divided in to the


following categories Civil/Structural, Architectural, Electrical, Mechanical, IT
Facilities, Equipment and Local Access Road development. The mobilization
constructions and installations works are detailed activity breakdown are
developed in the schedule.

3. Mobilization & Preliminary Works

Civil/Structural
Once the setting out of the particular temporary work has been fully completed,

QM JV will start the Mobilization work will be started after getting Approvals of
Statutory authorities and Agencies for Temporary Work. The submission and
approval of work method statements, shop drawing, design and procurements are
sub divided in to the following categories Civil/Structural, Architectural, Electrical,
Mechanical, IT Facilities, Equipment and Local Access Road development for
various Mobilization works.
The following Temporary Works Facilities are included in our Mobilization plan at
initial stage

excavation works will begin for footings. With a finish-to-start relationship


Construction of columns will start, once the Construction of columns started, with
a start-to-start relationship and a certain amount of lag, the following activities will
start and proceed in respective order: (The Construction of Frame Structure,
Construction and Fixing of Panels). After Completion of Construction and Fixing of
Panels with a finish to start relationship Construction of Roof Covering will start
and Finish.
Architectural
Once the Fixing of Panels Completed with the start to start relationship wall
finishing will start and once wall finishing work starts, with a start to start

Completion of Engineers Mobile Office


Construction of QBC & MSF JV Mobile offices
Completion of Construction Village, Medical Facilities and Connecting

Temporary
Roads
Completion of Concrete Batching Plant and Connecting Temporary Roads.
Completion of Laydown Areas and Contractors Facilities
Completion of Maintenance Yard/Workshop

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 3

relationship with a certain amount of lag the following activities will start and
proceed in the order specified: Floor Finishing and Carpet Laying, Fixing of Doors
and Windows, Fixing of Fixtures, Installation of Furniture.
Electrical Work
Once the Wall Finish over with the start to start relationship with a certain amount
of lag Conduit & wiring work will start and once Conduit & wiring work starts, with
a start to start relationship with a certain amount of lag the following activities will

start and proceed in the order specified: Lighting Fixtures, Fixing of fire detection

work will start after completion of temporary storm water arrangement, once

& alarm system, Fixing of panel boards, Installation of main feeder cables and

Existing utilities will start with a certain amount of lag the following activities are

Installation of Transformer and Generator set.


Mechanical Work
Once the Wall Finish completed with the start to start relationship with a certain

start and proceed in the respective order: Excavation for Strom Water pipeline,

amount of lag Sanitary & drainage piping work will start and once Sanitary &
drainage piping work starts, with a start to start relationship with a certain amount
of lag the following activities will start and proceed in the order specified: HVAC
system, Installation of Fire Fighting Equipment, water supply piping, sanitary
fixtures & accessories, Installation of Pumps.
IT Facilities
Once the Installation of Furniture completed with the start to start relationship

Pipe Laying for Strom Water pipeline, Installation of Gullies for Strom Water
pipeline, Backfilling.
Once the Strom water backfilling started with a certain amount of lag Temporary
Site Access Roads Excavation will start. Excavation for road starts, with a start to
start relationship with a certain amount of lag filling of the Temporary road also
will start. Filling work starts, with a finish to start relationship Laying of Road
subgrade starts. Laying of Road Subgrade start with a start to start relationship
with a certain amount of lag the following activities will start and proceed in the

with a certain amount of lag Fixing of telephone system work will start and once

order specified:

Fixing of telephone system work starts, with a start to start relationship with a

Prime coat, Asphalt Concrete base course, Tack coat, Asphalt Wearing Course,

certain amount of lag the following activities will start and proceed in the order

Installation and Fixing of Kerbs Stone, Vehicle Crash Barriers, Precast Concrete

specified: Fixing of LAN, Internet Access & Wifi, Installation of Computer and IT

Footways and Paved Areas, Foundation work for Traffic Sign, Installation of street

accessories. Once Telephone system Completed with the finish to start relationship

Traffic Sign, Installation of Traffic signs, Road marking & Road studs.
This sequence of the work is followed in the all temporary Works Facilities.
Temporary is further divided into:

Installation of Kitchen Equipment and accessories will start.


Local Access Road Development
Once the Roof Covering completed Excavation and Subgrade preparation around
building will start and complete with the start to start relationship the Fence
around the Building will start and Internal Road Development and Connection to
Temporary Road access also will start. Once Internal Road Development and
Connection to Temporary Road access completed, with a finish to start relationship
Landscaping, Landscaping & Parking Facilities will complete.
Temporary Site Access Roads
Once the Statutory approvals completed Existing Utilities protection will start.
From Existing Utilities protection with start to start relationship with certain lag the
bedding & Laying of temporary for utilities will start, once Laying of temporary
utilities completed Backfilling will start with the finish to start relationship. Road
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 4

Laying of Road Sub base course, Laying of Road base course,

Construction of Engineers Mobile offices


o Civil / Structural work
o Architectural
o Electrical Work
o Mechanical Work
o IT Facilities
o Equipment
o Local Access Road Development
o Testing and Commissioning
Construction of Engineers Mobile offices
o Civil / Structural work
o Architectural
o Electrical Work
o Mechanical Work

o IT Facilities
o Equipment
o Local Access Road Development
o Testing and Commissioning
Construction Village and Medical facilities
o Construction Village and Medical facilities Phase-1
Civil / Structural work
Architectural
Electrical Work
Mechanical Work
IT Facilities
Equipment
Local Access Road Development
Testing and Commissioning
o Construction Village and Medical facilities Phase-2
Civil / Structural work
Architectural
Electrical Work
Mechanical Work
IT Facilities
Equipment
Local Access Road Development
Testing and Commissioning
o Construction Village and Medical facilities Phase-3
Civil / Structural work
Architectural
Electrical Work
Mechanical Work
IT Facilities
Equipment
Local Access Road Development
Testing and Commissioning
Contractor Laydown area and facilities
o Formation for Laydown Area
o Testing and Commissioning
Maintenance yard and workshop
o Civil / Structural work
o Electrical Work
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

o Mechanical Work
o IT Facilities
o Local Access Road Development
o Testing and Commissioning
Fuel depot
o Civil / Structural work
o Electrical Work
o Mechanical Work
o IT Facilities
o Local Access Road Development
o Testing and Commissioning
Project Sign Board
o Civil / Structural work
o Electrical Work
o Testing and Commissioning
Temporary Site Access Roads
o Utility Protection
o Storm Water Drainage
Maintenance is also subdivided in to the following Completion of Engineers
Mobile Office, Construction of QBC & MSF JV Mobile offices, Completion of
Construction Village, Medical Facilities and Connecting Temporary Roads,
Completion of Concrete Batching Plant and Connecting Temporary Road,
Completion of Laydown Areas and Contractors Facilities, Completion of
Maintenance Yard/Workshop, Project Sign Board, Completion of Fuel Depot,
Completion of Concrete Batching Plant, Temporary Site Access Road. And each
temporary work has separate maintenance and it will be starting after
completion of the Temporary Works Facilities.
4. Engineering
Contractual submission and approval: which include the programme General
Items submittal and General Items approval of Project Management Plan
Submission and Approval (PMP), Project Quality Plan Submission and Approval
(PQP), HSE Plan Submission and Approval (HSEP), Risk Management Plan
Page 5

Submission and Approval (RMP), Construction Environmental Management Plan


Submission and Approval (CEMP), Baseline Programme, Emergency Incident
Response Plan (EIRP) , Temporary Traffic Management Plan (TMP), 120days
Programme.

Electrical
Mechanical
Telecommunication

Method statements: which include the Methods statements submittals and

Key Personnel CV submission and approval: which include the programme


Key personnel CV submittal and approval of Project, the following CV Submittal
for Key personnel.

Project Director CV Submissions and Approvals, Programme

Controls CV Submissions, Project Manager CV Submissions and Approvals,


Technical Manager CV Submissions and Approvals, Senior Structures Engineer CV
Submissions and Approvals, Electrical Services Manager CV Submissions and
Approvals, Highways (Pavement) Engineer CV Submissions and Approvals,
Underground

Utilities

Engineer

CV

Submissions

and

Approvals,

Senior

Geotechnical Engineer CV Submissions and Approvals, Senior Infrastructure


Engineer CV Submissions and Approvals, Environmental Manager CV Submissions
and Approvals, Health and Safety Specialist CV Submissions and Approvals,
Commercial Manager CV Submissions and Approvals, Quality Manager CV

approval of the project.


The following are subdivided by category of the Methods statements

General
Civil
Architectural
Road Works
Electrical
Mechanical
Telecommunication

Surveying and Setting Out: Surveying and setting out will start with Surveying
method statement. Once Preparation of Survey data and Submission completed
with the finish to start relationship surveying data Approval will be starting.

Submissions and Approvals, Commissioning Manager CV Submissions and

Design and Shop Drawing: which include the Shop Drawing submittals and

Approvals, Lead Project Surveyor CV Submissions and Approvals, Construction

approval of the project.

Manager CV Submissions and Approvals.

The following are subdivided by category of Shop Drawing

Subcontractor Prequalification submission and approval: which include the


subcontractor prequalification submittals and approval of the project.
The following are subdivided by category of the subcontractor prequalification

General
Civil
Architectural
Road Works

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

General
Civil
Architectural
Road Works
Electrical
Mechanical
Telecommunication

Materials: which include the Material submittals and approval of the project.
Page 6

After Asphalt Design Approval and Concrete Design mix Approvals Material
Delivery will start for Asphalt and Concrete.

ROAD AND UTILITIE WORKS

The following are subdivided by category of Material

Area-A1-Foul Sewer Line:


Naval access road from 0+000 to 0+900 which is falling under Area A1, Foul sewer

General
Civil
Architectural
Road Works
Electrical
Mechanical
Telecommunication

network line for this area to be completed on or before 30-Jul-15 as per


contractual milestone requirement. For construction contractor planning purpose,
we have divided into two sections:

Foul water Network naval access road (0+000 to 0+450)


Foul water Network naval access road (0+000 to 0+900)

5. Procurement / Delivery
After approval for each material, delivery of the material will start to site and long

Area-A2-Foul Sewer Line:

lead items will be delivered as per the procurement schedule.

The following roads are falling under area-A2,

6. Construction
The construction of the project comprises of the construction of each area with
Infrastructure and Utility Buildings. List of area are mention below.

Area-E

Area-G

Area-D

Area-F

Area-A1

Area-B

Area-A2

Area-H

Area-I

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Road
Road
Road
Road
Road
Road
Road
Road
Road
Road
Road
Road

13
10
8
7
20
12
9
18
18A
18D
22
6

Foul sewer line for the above mentioned roads to be completed on or before
26/Sep/15.

Page 7

Contractor planned to start the foul sewer line work by road-wise, once we have

Following scope of works cover under Area G:

completed the initial activity for one road and will proceed for other road. Other

Utility and Road work:

activities will follow the same sequence. All the durations are calculated based on

the optimistic practical productivity.


Area E:

Sub-station:

Road 17 from 0+000 to 1+550 which is falling under Area E, all the works related

1.
2.
3.
4.

to this work has to be completed on or before 29-Dec-15 as per contractual


milestone requirement. For construction contractor planning purpose, we have
divided into two sections:

Visitors Block

Foul water pumping station


Maintenance yard sub-station
Berth area sub-station
Sea water pump station

This entire works to be completed on or before 27-Mar-16 as per contractual

Road 17 (0+000 to 1+000)


Road 17 (1+000 to 1+550)

milestone requirement.
The following works are the scope of the works to be completed under visitors

The following works are the scope of the works to be completed this Area E

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

block:

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

First, we start with utility works which is related to this road after complete the

First, we start with utility works which is related to this road after complete the

utility work, we start the road work, once we have completed the initial activity for

utility work, we start the road work, once we have completed the initial activity for

one road and will proceed for other road. Other activities will follow the same

one road and will proceed for other road. Other activities will follow the same

sequence.

sequence.

Area G:

For Buildings, activities are categorized like following work breakdown structure:

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 8

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

(0+000to
(0+000to
(0+000to
(0+000to

0+550)
1+180)
0+200)
0+620)

5. Foul water pumping station PS 1


6. Maintenance yard sub-station PS 2
7. Service Point Sub-station 1
8. Service Point Sub-station 2
9. Communication Shelter 009
10.
Communication Shelter 010

move to other building to continue.


Area D:

This entire works to be completed on or before 21-Aug-16 as per contractual

Following scope of works cover under Area D:

milestone requirement.

Utility and Road work:

The following works are the scope of the works to be completed for utility and road
works:

Road 3 (0+000 to 1+900)


Road 2 (0+000 to 0+725)
Road 2 (0+725 to 1+600)
Road 1 (4+852 to 5+568)
Road 55 (0+000 to 1+000)
Road 55 (1+000 to 2+079)
Road 55 (2+079 to 2+950)
Security Access Road 3 (0+000 to 0+950)
Security Access Road 3 (0+950 to 2+006)
Security Access Road 4 (0+000 to 0+925)
Patrol Road 2 (0+000 to 1+050)
Patrol Road 2 (1+050 to 2+165)
Patrol Road 3 (0+000 to 0+950)
Road 31 (1+800 to 2+100)
Road 5 (0+000 to 1+325)
Road 43 (0+000 to 0+443)
Road 44 (0+000to 0+550)
Road 45 (0+000to 0+550)

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

46
47
48
49

Sub-station:

After completion of initial activity for the particular building, then the crew will

Road
Road
Road
Road

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:
Page 9

one road and will proceed for other road. Other activities will follow the same

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

sequence.
Area A1
Following scope of works cover under Area A1:
Utility and Road work:

After completion of initial activity for the particular building, then the crew will

move to other building to continue.


Area F:
Berth area works cover under Area F:
The following works are the scope of the works to be completed this Area E

Sub-station:

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road work- VIP Berth
Road Work Operational Berth

1.
2.
3.
4.
5.
6.

This entire works to be completed on or before 03-Oct-16 as per contractual


milestone requirement.
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for

Page 10

Foul water pumping station PS 6


Communication Shelter 001
Communication Shelter 002
Communication Shelter 003
Communication Shelter 004
Communication Shelter 005

This entire works to be completed on or before 03-Nov-16 as per contractual


milestone requirement.
The following works are the scope of the works to be completed for utility and road
works:

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Naval Access Road (0+000 to 0+450) part 1


Naval Access Road (0+450 to 0+900) part 2
Naval Access Road - part 3
Road 1 - 0+000 to 0+852
Road 1 - 0+852 to 1+852
Road 1 - 1+852 to 2+852
Road 1 - 2+852 to 3+852
Road 1 - 3+852 to 4+852

Foul water Network


Potable water distribution network

Fire water distribution network


Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

After completion of initial activity for the particular building, then the crew will
move to other building to continue.

Road 18
Security
Security
Road 26
Road 28
Road 25
Road 27
Road 21
Road 29
Road 30
Road 23
Road 24
Road 36
Road 37
Road 38
Road 16
Road 32
Road 33
Road 34
Road 35
Road 39
Road 40
Road 41

Sub-station:
1.
2.
3.
4.
5.
6.

Area B:
Following scope of works cover under Area B:

(0+000 to 0+900)
Access Road 8 (0+000 to 0+700)
Access Road 9 (0+000 to 0+240)
(0+000 to 0+320)
(0+000 to 1+000)
(0+000 to 0+220)
(0+000 to 1+000)
(0+000 to 0+200)
(0+000 to 0+250)
(0+000 to 0+250)
(0+000 to 0+350)
(0+000 to 0+750)
(0+000 to 0+500)
(0+000 to 0+075)
(0+000 to 0+150)
(0+000 to 0+275)
(0+000 to 0+413)
(0+000 to 0+345)
(0+000 to 0+075)
(0+000 to 0+150)
(0+000 to 0+550)
(0+000 to 0+075)
(0+000 to 0+400)

Foul water pumping station PS 4


Foul water pumping station PS 5
Service Point Sub-station 3
Service Point Sub-station 5
Communication Shelter 007
Communication Shelter 008

Utility and Road work:


This entire works to be completed on or before 24-Dec-16 as per contractual

Security Access Road 2 (0+000 to 1+600)


Road 31 (0+000 to 1+964)
Security Access Road 1 (0+000 to 0+182)

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

milestone requirement.

Page 11

The following works are the scope of the works to be completed for utility and road
works:

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

Road 20 (0+000 to 0+595)


Road 7 (0+000 to 0+700)
Road 6 (0+000 to 0+640)
Road 6A (0+000 to 0+099)
Road 18D (0+000 to 0+325)
Road 18 (0+900 to 1+800)
Road 16A (0+000 to 0+368)
Road 15 (0+000 to 0+300)
Road 12 (0+000 to 0+792)
Road 13 (0+000 to 1+225)
Patrol Road 1 (0+000 to 0+800)
Road 10 (0+000 to 0+300)
Road 9 (0+000 to 0+270)
Road 8 (0+000 to 0+150)
Security Access Road 8 (0+700 to
Security Access Road 7 (0+000 to
Security Access Road 5 (0+000 to
Security Access Road 6 (0+000 to
Road 19 (0+000 to 0+310)
Road 22 (0+000 to 0+200)
Road 11 (0+000 to 0+293)
Road 14 (0+000 to 0+702)

1+050)
0+600)
1+450)
0+050)

Sub-station:

After completion of initial activity for the particular building, then the crew will
move to other building to continue.
Area A2:
Following scope of works cover under Area A2:
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Utility and Road work:

Page 12

1.
2.
3.
4.
5.
6.
7.
8.
9.

Potable water pump station


Compressor Building
Fire Fighting fresh water pump station
Telecommunication Building
Communication Shelter 006
Communication Shelter 011
Utility Area Substation
Land fuel oil building
Drain water lift station PS3

This entire works to be completed on or before 11-Jan-17 as per contractual


milestone requirement.

Berth area works cover under Area H:

The following works are the scope of the works to be completed for utility and road
works:

Area H:

The following works are the scope of the works to be completed this Area H

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road work- Berth Area

For Marine fuel oil Buildings, activities are categorized like following work
breakdown structure:

one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

This entire works to be completed on or before 27-Feb-17 as per contractual


milestone requirement.
First, we start with utility works which is related to this road after complete the

After completion of initial activity for the particular building, then the crew will
move to other building to continue.

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.

Page 13

Area I:

one road and will proceed for other road. Other activities will follow the same
sequence.

Following scope of works cover under Area I:

For Buildings, activities are categorized like following work breakdown structure:

Utility and Road work:

Visiting Navy Berth Area


Road 55 (2+950 to 3+666)
Patrol Road 3 (0+950 to 1+663)
Security Access 4 (0+925 to 1+644)
Road 13 (1+225 to 1+576)
Security Access 5 (1+225 to 1+959)
Patrol Road 1 (0+800 to 1+291)

Sub-station:

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

After completion of initial activity for the particular building, then the crew will
move to other building to continue.

Service Point Sub-station 4


This entire works to be completed on or before 27-Feb-17 as per contractual
milestone requirement.

Balance of works:
Following scope of works cover under Area G:

The following works are the scope of the works to be completed for utility and road

Sewerage Treatment Plant

works:
For Buildings, activities are categorized like following work breakdown structure:

Foul water Network


Potable water distribution network
Fire water distribution network
Irrigation water distribution network
Telecommunication
Electrical works
Storm water drainage works
Road works.

First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 14

Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works

After completion of initial activity for the particular building, then the crew will

construction of the work will be started. QM JV will execute the work without

move to other building to continue.

disrupting the traffic flow and temporary diversion will be provided in case the

QM JV will start the project with construction of the Foul water lines in the

traffic diversion is necessary.

location A1 & A2 Area and will be followed with the infrastructure and utility
Building works. Commencement of worked are dependent on the approval of
necessary permits. Various pre-construction plans, work method statements,

Principal Materials:

materials, Procurement material, Contractual Documents etc. will be submitted

Principal Materials

Unit

Quantity

Concrete

m3

204,165

After getting the approval form concerned bodies the Erection of Batching

Steel Rebar

Ton

11,998

Plant, Installation of Engineers office and Contractors office etc., and the

Tanking Membrane

m2

327,668

construction of the work will be started. QM JV will execute the work without

Sub-Base - Class B

Ton

166,533

Road Base - Class A CBR 80%

Ton

301,794

Road Base - Class A Gabbro CBM

m3

81,054

Asphalt BC (Type 1)

Ton

326,000

Asphalt SC (Type 1 Gabbro)

Ton

90,560

to the Engineer for his review in the mean while. Also incorporated in this
stage is the mobilization of the site offices, the required plant & machinery etc.

disrupting the traffic flow and temporary diversion will be provided in case the
traffic diversion is necessary.
1.4

Planning Methodology:

QM JV will start the project with construction of the Foul water lines in the

DI Pipes (100mm to 400mm dia)

8,710

location A1 & A2 Area and will be followed with the infrastructure and utility

GRP Pipes (150mm to 900mm dia)

63,887

Building works. Commencement of worked are dependent on the approval of

uPVC Pipe 75mm, perforated

68,546

necessary permits. Various pre-construction plans, work method statements,

uPVC Pipe 150mm

31,090

HDPE Pipe 300mm, perforated

18,432

HDPE Pipe (50mm to 630mm OD)

no

121,516

After getting the approval form concerned bodies the Erection of Batching

PVC Ducts (90mm to 150mm dia)

1,824,085

Plant, Installation of Engineers office and Contractors office etc., and the

Fire Hydrant

373

materials, Procurement material, Contractual Documents etc. will be submitted


to the Engineer for his review in the mean while. Also incorporated in this
stage is the mobilization of the site offices, the required plant & machinery etc.

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 15

(i)

JRC12 Cover

No

560

JRC14 Cover

No

621

Catch Pit 1600x700 mm

569

Kerbs

No

200,840

Activity durations and resource assignments, assumed daily production,


required logics and their lags for predecessors and successors will be
modified if necessary based on site obstructions/ interfaces. Hence Phase
planning will be subjected to modification if necessary. And the Baseline

(ii)

programme indicates the planning implementation with each Area.


As indicated in the Planning Methodology QM JV intends to start the work
with Foul Water line in Area A1 & A2 and followed with the infrastructure
and utility Building works. Assuming that all the necessary permits and
approvals will be issued on time and no obstructions will stop QM JVs

(iii)

work progress.
QM JVs assumed that all the client (New Port Project Steering committee,
AECOM, COWI) and Government authoritys (Mesaieed Municipality,
MIC/QP and MPCL, Kharamaa, Ooredoo, Ashghal, MoE ) permits/
approvals/sanctions will be on time without any delays, any interruptions

(iv)

for the work to start or further progress.


All submittals, method statements, shop drawings will be approved

(v)

before starting the particular work.


QM JVs assumes that if any scope of the project changes, if any
additional works are incurred it will affect the end date of the project and
the client will accept the required time allocation for such works.

All the Client interfaces and other contractor interfaces on site will be resolved
within a week or less before the commencement of work by QM JV.
1.5

Assumptions for the programme:

The Baseline programme has been developed as follows:

NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS

Page 16