Narrative Statement NPP-0050-QENFB Infra Structure & Utility Buildings
Narrative Statement NPP-0050-QENFB Infra Structure & Utility Buildings
BUILDINGS
Project Completion:
03-April-2017
Contract Price:
QAR 1,553,395,868.06/-
Project Data :
Contract:
Client:
Project Management
Consultant:
1.2
Project Description:
Infrastructure and utility building for new Naval Base Force to be developed on a
AECOM
Programme Description
Contractor:
Activities are organized under following work breakdown structure.
QM JV
1. GENERAL ADMINISTRATIVE
Project Start Date:
MILESTONES
31-December-2014
Page 1
Duration
AREA
Access
Completion
from
Date
Date
Commencem
4. ENGINEERING
ent Date
31-Dec-
30-Jul-15
212
2014
31-Dec-
26-Sep-
270
2014
31-Dec-
2015
29-Dec-
364
Area-G
2014
15-Apr-
2015
27-Mar-
453
Area-D
2015
31-Dec-
2016
21-Aug-
600
Area-F
2014
17-Aug-
2016
03-Oct-2016
643
6. CONSTRUCTION.
Area-A1
2015
31-Dec-
03-Nov-
674
Area-B
2014
31-Dec-
2016
24-Dec-
725
8. HANDING OVER.
Area-A2
2014
31-Dec-
2016
11-Jan-2017
743
For programming and planning purpose each sub division are further divided in to
Area-H
2014
16-Jan-
27-Feb-
790
Area-I
2016
16-Jan-
2017
27-Feb-
790
Balance of Works
2016
31-Dec-
2017
03-Apr-
825
2014
2017
KEY PERSONNEL CV
SUBCONTRACTOR PREQUALIFICATION
METHOD STATMENTS
SURVEYING AND SETTING OUT
DESIGN AND SHOP DRAWING
MATERIALS
5. PROCUREMENT/ DELIVERY
1. GENERAL ADMINISTRATIVE
Complete
Project Duration
Project commenced on 31st December 14 with the project duration of 825 days,
2. Preliminary
Contractual
Page 2
requirements
which
has
Performance
Bond,
Workmen
Civil/Structural
Once the setting out of the particular temporary work has been fully completed,
QM JV will start the Mobilization work will be started after getting Approvals of
Statutory authorities and Agencies for Temporary Work. The submission and
approval of work method statements, shop drawing, design and procurements are
sub divided in to the following categories Civil/Structural, Architectural, Electrical,
Mechanical, IT Facilities, Equipment and Local Access Road development for
various Mobilization works.
The following Temporary Works Facilities are included in our Mobilization plan at
initial stage
Temporary
Roads
Completion of Concrete Batching Plant and Connecting Temporary Roads.
Completion of Laydown Areas and Contractors Facilities
Completion of Maintenance Yard/Workshop
Page 3
relationship with a certain amount of lag the following activities will start and
proceed in the order specified: Floor Finishing and Carpet Laying, Fixing of Doors
and Windows, Fixing of Fixtures, Installation of Furniture.
Electrical Work
Once the Wall Finish over with the start to start relationship with a certain amount
of lag Conduit & wiring work will start and once Conduit & wiring work starts, with
a start to start relationship with a certain amount of lag the following activities will
start and proceed in the order specified: Lighting Fixtures, Fixing of fire detection
work will start after completion of temporary storm water arrangement, once
& alarm system, Fixing of panel boards, Installation of main feeder cables and
Existing utilities will start with a certain amount of lag the following activities are
start and proceed in the respective order: Excavation for Strom Water pipeline,
amount of lag Sanitary & drainage piping work will start and once Sanitary &
drainage piping work starts, with a start to start relationship with a certain amount
of lag the following activities will start and proceed in the order specified: HVAC
system, Installation of Fire Fighting Equipment, water supply piping, sanitary
fixtures & accessories, Installation of Pumps.
IT Facilities
Once the Installation of Furniture completed with the start to start relationship
Pipe Laying for Strom Water pipeline, Installation of Gullies for Strom Water
pipeline, Backfilling.
Once the Strom water backfilling started with a certain amount of lag Temporary
Site Access Roads Excavation will start. Excavation for road starts, with a start to
start relationship with a certain amount of lag filling of the Temporary road also
will start. Filling work starts, with a finish to start relationship Laying of Road
subgrade starts. Laying of Road Subgrade start with a start to start relationship
with a certain amount of lag the following activities will start and proceed in the
with a certain amount of lag Fixing of telephone system work will start and once
order specified:
Fixing of telephone system work starts, with a start to start relationship with a
Prime coat, Asphalt Concrete base course, Tack coat, Asphalt Wearing Course,
certain amount of lag the following activities will start and proceed in the order
Installation and Fixing of Kerbs Stone, Vehicle Crash Barriers, Precast Concrete
specified: Fixing of LAN, Internet Access & Wifi, Installation of Computer and IT
Footways and Paved Areas, Foundation work for Traffic Sign, Installation of street
accessories. Once Telephone system Completed with the finish to start relationship
Traffic Sign, Installation of Traffic signs, Road marking & Road studs.
This sequence of the work is followed in the all temporary Works Facilities.
Temporary is further divided into:
Page 4
o IT Facilities
o Equipment
o Local Access Road Development
o Testing and Commissioning
Construction Village and Medical facilities
o Construction Village and Medical facilities Phase-1
Civil / Structural work
Architectural
Electrical Work
Mechanical Work
IT Facilities
Equipment
Local Access Road Development
Testing and Commissioning
o Construction Village and Medical facilities Phase-2
Civil / Structural work
Architectural
Electrical Work
Mechanical Work
IT Facilities
Equipment
Local Access Road Development
Testing and Commissioning
o Construction Village and Medical facilities Phase-3
Civil / Structural work
Architectural
Electrical Work
Mechanical Work
IT Facilities
Equipment
Local Access Road Development
Testing and Commissioning
Contractor Laydown area and facilities
o Formation for Laydown Area
o Testing and Commissioning
Maintenance yard and workshop
o Civil / Structural work
o Electrical Work
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS
o Mechanical Work
o IT Facilities
o Local Access Road Development
o Testing and Commissioning
Fuel depot
o Civil / Structural work
o Electrical Work
o Mechanical Work
o IT Facilities
o Local Access Road Development
o Testing and Commissioning
Project Sign Board
o Civil / Structural work
o Electrical Work
o Testing and Commissioning
Temporary Site Access Roads
o Utility Protection
o Storm Water Drainage
Maintenance is also subdivided in to the following Completion of Engineers
Mobile Office, Construction of QBC & MSF JV Mobile offices, Completion of
Construction Village, Medical Facilities and Connecting Temporary Roads,
Completion of Concrete Batching Plant and Connecting Temporary Road,
Completion of Laydown Areas and Contractors Facilities, Completion of
Maintenance Yard/Workshop, Project Sign Board, Completion of Fuel Depot,
Completion of Concrete Batching Plant, Temporary Site Access Road. And each
temporary work has separate maintenance and it will be starting after
completion of the Temporary Works Facilities.
4. Engineering
Contractual submission and approval: which include the programme General
Items submittal and General Items approval of Project Management Plan
Submission and Approval (PMP), Project Quality Plan Submission and Approval
(PQP), HSE Plan Submission and Approval (HSEP), Risk Management Plan
Page 5
Electrical
Mechanical
Telecommunication
Utilities
Engineer
CV
Submissions
and
Approvals,
Senior
General
Civil
Architectural
Road Works
Electrical
Mechanical
Telecommunication
Surveying and Setting Out: Surveying and setting out will start with Surveying
method statement. Once Preparation of Survey data and Submission completed
with the finish to start relationship surveying data Approval will be starting.
Design and Shop Drawing: which include the Shop Drawing submittals and
General
Civil
Architectural
Road Works
General
Civil
Architectural
Road Works
Electrical
Mechanical
Telecommunication
Materials: which include the Material submittals and approval of the project.
Page 6
After Asphalt Design Approval and Concrete Design mix Approvals Material
Delivery will start for Asphalt and Concrete.
General
Civil
Architectural
Road Works
Electrical
Mechanical
Telecommunication
5. Procurement / Delivery
After approval for each material, delivery of the material will start to site and long
6. Construction
The construction of the project comprises of the construction of each area with
Infrastructure and Utility Buildings. List of area are mention below.
Area-E
Area-G
Area-D
Area-F
Area-A1
Area-B
Area-A2
Area-H
Area-I
Road
Road
Road
Road
Road
Road
Road
Road
Road
Road
Road
Road
13
10
8
7
20
12
9
18
18A
18D
22
6
Foul sewer line for the above mentioned roads to be completed on or before
26/Sep/15.
Page 7
Contractor planned to start the foul sewer line work by road-wise, once we have
completed the initial activity for one road and will proceed for other road. Other
activities will follow the same sequence. All the durations are calculated based on
Sub-station:
Road 17 from 0+000 to 1+550 which is falling under Area E, all the works related
1.
2.
3.
4.
Visitors Block
milestone requirement.
The following works are the scope of the works to be completed under visitors
The following works are the scope of the works to be completed this Area E
block:
First, we start with utility works which is related to this road after complete the
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
one road and will proceed for other road. Other activities will follow the same
sequence.
sequence.
Area G:
For Buildings, activities are categorized like following work breakdown structure:
Page 8
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
(0+000to
(0+000to
(0+000to
(0+000to
0+550)
1+180)
0+200)
0+620)
milestone requirement.
The following works are the scope of the works to be completed for utility and road
works:
46
47
48
49
Sub-station:
After completion of initial activity for the particular building, then the crew will
Road
Road
Road
Road
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:
Page 9
one road and will proceed for other road. Other activities will follow the same
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
sequence.
Area A1
Following scope of works cover under Area A1:
Utility and Road work:
After completion of initial activity for the particular building, then the crew will
Sub-station:
1.
2.
3.
4.
5.
6.
Page 10
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
After completion of initial activity for the particular building, then the crew will
move to other building to continue.
Road 18
Security
Security
Road 26
Road 28
Road 25
Road 27
Road 21
Road 29
Road 30
Road 23
Road 24
Road 36
Road 37
Road 38
Road 16
Road 32
Road 33
Road 34
Road 35
Road 39
Road 40
Road 41
Sub-station:
1.
2.
3.
4.
5.
6.
Area B:
Following scope of works cover under Area B:
(0+000 to 0+900)
Access Road 8 (0+000 to 0+700)
Access Road 9 (0+000 to 0+240)
(0+000 to 0+320)
(0+000 to 1+000)
(0+000 to 0+220)
(0+000 to 1+000)
(0+000 to 0+200)
(0+000 to 0+250)
(0+000 to 0+250)
(0+000 to 0+350)
(0+000 to 0+750)
(0+000 to 0+500)
(0+000 to 0+075)
(0+000 to 0+150)
(0+000 to 0+275)
(0+000 to 0+413)
(0+000 to 0+345)
(0+000 to 0+075)
(0+000 to 0+150)
(0+000 to 0+550)
(0+000 to 0+075)
(0+000 to 0+400)
milestone requirement.
Page 11
The following works are the scope of the works to be completed for utility and road
works:
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
1+050)
0+600)
1+450)
0+050)
Sub-station:
After completion of initial activity for the particular building, then the crew will
move to other building to continue.
Area A2:
Following scope of works cover under Area A2:
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS
Page 12
1.
2.
3.
4.
5.
6.
7.
8.
9.
The following works are the scope of the works to be completed for utility and road
works:
Area H:
The following works are the scope of the works to be completed this Area H
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
For Marine fuel oil Buildings, activities are categorized like following work
breakdown structure:
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
After completion of initial activity for the particular building, then the crew will
move to other building to continue.
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
utility work, we start the road work, once we have completed the initial activity for
one road and will proceed for other road. Other activities will follow the same
sequence.
Page 13
Area I:
one road and will proceed for other road. Other activities will follow the same
sequence.
For Buildings, activities are categorized like following work breakdown structure:
Sub-station:
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
After completion of initial activity for the particular building, then the crew will
move to other building to continue.
Balance of works:
Following scope of works cover under Area G:
The following works are the scope of the works to be completed for utility and road
works:
For Buildings, activities are categorized like following work breakdown structure:
First, we start with utility works which is related to this road after complete the
utility work, we start the road work, once we have completed the initial activity for
NPP/0050-QENFB INFRASTRUCTURE & UTILITY BUILDINGS
Page 14
Earthworks
Structural works
Architectural works
Doors and windows
Metal works
Mechanical works
Electrical works
External works
After completion of initial activity for the particular building, then the crew will
construction of the work will be started. QM JV will execute the work without
disrupting the traffic flow and temporary diversion will be provided in case the
QM JV will start the project with construction of the Foul water lines in the
location A1 & A2 Area and will be followed with the infrastructure and utility
Building works. Commencement of worked are dependent on the approval of
necessary permits. Various pre-construction plans, work method statements,
Principal Materials:
Principal Materials
Unit
Quantity
Concrete
m3
204,165
After getting the approval form concerned bodies the Erection of Batching
Steel Rebar
Ton
11,998
Plant, Installation of Engineers office and Contractors office etc., and the
Tanking Membrane
m2
327,668
construction of the work will be started. QM JV will execute the work without
Sub-Base - Class B
Ton
166,533
Ton
301,794
m3
81,054
Asphalt BC (Type 1)
Ton
326,000
Ton
90,560
to the Engineer for his review in the mean while. Also incorporated in this
stage is the mobilization of the site offices, the required plant & machinery etc.
disrupting the traffic flow and temporary diversion will be provided in case the
traffic diversion is necessary.
1.4
Planning Methodology:
QM JV will start the project with construction of the Foul water lines in the
8,710
location A1 & A2 Area and will be followed with the infrastructure and utility
63,887
68,546
31,090
18,432
no
121,516
After getting the approval form concerned bodies the Erection of Batching
1,824,085
Plant, Installation of Engineers office and Contractors office etc., and the
Fire Hydrant
373
Page 15
(i)
JRC12 Cover
No
560
JRC14 Cover
No
621
569
Kerbs
No
200,840
(ii)
(iii)
work progress.
QM JVs assumed that all the client (New Port Project Steering committee,
AECOM, COWI) and Government authoritys (Mesaieed Municipality,
MIC/QP and MPCL, Kharamaa, Ooredoo, Ashghal, MoE ) permits/
approvals/sanctions will be on time without any delays, any interruptions
(iv)
(v)
All the Client interfaces and other contractor interfaces on site will be resolved
within a week or less before the commencement of work by QM JV.
1.5
Page 16