Professional Documents
Culture Documents
Presentation (Synch Condenser)
Presentation (Synch Condenser)
MANAGEMENT IN CESC
NETWORK
(Operation of NCGS units as
Synchronous Condensers)
1.Introduction
2.Exercises that have been carried out
3.Path forward to execution
Introduction
-The quadrature component of the lagging current will directly oppose the rotor
flux and hence diminish the resultant air gap flux, resulting in reduction of
terminal voltage.
I1
V
I2
VAR FLOW
CESC
~
CESC
~
SEB
V1
V2
V1 < V2
~
SEB
b) Low system voltage may lead to grid voltage instability and the whole
grid may collapse. Such grid failure at Southern and Western grid took
place, a few years back due to low voltage.
c) Low voltage may lead to rotor angle instability while overloading a
generator.
This increases the generator current and often crosses the rated limit.
During peak summer evening load, both active and reactive becomes
equally important
Resort to Method 2
Several cap banks have been installed. But supply / demand reactive power
is so much impaired, that we are not yet been able to manage the reactive
demand.
The cap banks are prone to failure due to harmonic overheating and
electrical resonances.
Switched capacitors are added to the system in steps which can develop
over voltages.
Resort to method 2
(Advantages of Synchronous Condenser)
Step less smooth control.
The system produces no switching transients and is not affected by system
electrical harmonics.
Synchronous condensers are also very reliable and require little maintenance.
Initial cost is comparable to switched capacitors and is considerably less than
static VAR compensators.
Life expectancy is in the range of 20 30 years.
With
a view
to the advantages of
synchronous condensers and imminent
retirement of NCGS Units as generators,
conversion of the NCGS units to
synchronous condensers is being thought
of.
35
30
25
20
15
10
5
0
33 KV
IG = 618 A
If2 = 180 A
If1 = 100 A
RATED VOLTS
180 A
50
100
Rotor Current (A)
150
700
600
500
400
300
200
100
0
200
Stator Current
NCGS #2 (OCC-SCC)
Capabilty
Chart
Of
NCGS
30 MW
Machine
Q: We intend to remove the LP spindle and fit a dummy shaft, remove enough
HP turbine blading such that the output of HP is limited to running the generator
rotor to speed. Once synchronised the steam supply will cut off leaving the HP
blading to run in the air. Is this option possible? If so,
How much HP blading needs to be removed to power the machine to speed?
Is vacuum necessary with the remaining blades or can they run in air?
Can the condenser take resulting positive pressure?
A: Generally for smaller machines it takes around 6% of the mass flow of steam
to drive a machine up to full speed no load. However, regarding how much of
the existing blading would be required to do this is not a simple calculation as
there are potential windage heating effects etc to be considered. Coupled with
the fact that the HP blading is old design 600 series we believe this would be a
novel approach to the conversion to synchronous condenser operation and
therefore a design study would be required to confirm whether this method of
conversion would be possible. Given that this method also removes the
possibility of the machine ever again operating as a turbine generator it would
be better to consider other less destructive options for the conversion, as
above. In addition, all the reports and literature consulted have indicated that
the steam turbine is mechanically uncoupled from the generator when
operating as a synchronous condenser.
Q: Is there any clutch available for decoupling the machine from the prime
mover?
A:There is a special type of clutch available commercially called a synchroself-shifting clutch (SSS clutch). The clutch is connected between the
generator and the prime mover. The clutch is an arrangement of fluid-drive
gears which operate automatically by torque reversals. On starting, the
clutch engages both the prime mover and the generator as soon as torque is
applied. When the generator is synchronised to the system, power is cut off
from the prime mover, the clutch disengages and the prime mover slows
down alone. If required the prime mover can be run up again and at the
correct speed the clutch will engage both machines. This system has been
used on gas turbine generators up to around 100 MVA. The supplier of this
type of clutch is SSS Gears Limited UK.
Note: There should be some form of bound bearing applied to the generator
rotor following disconnection from the turbine. This is to eliminate any axial
movement of the rotor during operation as a synchronous condenser. Also,
for New Cossipore unit 1, the main oil pump is at the governor end,
therefore as the main turbine would be disconnected the auxiliary oil pump
must be in operation during run up and operation of the synchronous
condenser.
http://www.bheledn.com/acheivments2.htm
http://www.exeloncorp.com/ourcompanies/powergen/nuclear/zion_
generating_station.htm
During the Spring of 1998, Commonwealth Edison Company successfully modified two retired 1220
Mva nuclear generators for operation as synchronous condensers. This presentation will discuss the
planning studies which identified the need for the synchronous condenser, alternative starting
mechanisms considered, and operational issues and experience with the synchronous condenser.
The justification for the synchronous condenser was demonstrated by planning studies which
showed the critical need for voltage support after the Zion generators were retired. The synchronous
condensers enabled ComEd to maintain voltage stability margins to the same level as before the
generators were retired.
During the design stage, one of the biggest challenges in the conversion to synchronous condenser
was designing the starting mechanism. Several alternatives were investigated, including utilization of
a starting motor to accelerate the generators to synchronous speed, and utilization of a variable
frequency drive to accelerate the generator from a standstill.
The first synchronous condenser was synchronized ahead of schedule on May 25, 1998. The
second unit was synchronized on June 2, 1998. The synchronous condensers proved to be a very
valuable asset during operation during the summer of 1998. Operation of the synchronous
condensers enabled ComEd to maintain adequate voltage stability margins throughout the summer.
http://www.ece.iit.edu/~flueck/chicago_pes/1998/anb0210.html
Your request letter in this forwarded mail is seen and dicussed with our design
engineers, concerned and the following are our comments:
Generator can be in principle operated as synchronous Condenser to improve Power
factor in the system. But if Generator is to be operated as Synchronous Condenser, a starting
motor with a suitable decoupling device is required to bring generator to synchronous speed. At
present BHEL does not have any such equipment (motor with decoupling device) nor the required
experience associated with this.
However you can visit, if desired so, TNEB Basin Bridge GT Power Plant where BHEL
(HYD) has supplied Generator to operate as generator normally and as synchronous condenser
occasionally.
Further we do not have any knowledge or necessary information on GTO thyristor
controls being supplied by BHEL EDn, Bangalore for 67 MW Synchonous Condenser at TEC as
mentioned in your letter. You may further probe in this matter with our Bangalore unit directly.
Phase-1:
(On immediate basis)
To prove the rotor withstanding capacity, the team feels to operate
the machine as a generator at a very low active power (to the tune of
4 5 MW) and maximum lagging MVAR (to the tune of 26 MVAR)
and P.F.=0.2
To accomplish this, the following are required
-Generator rotor temperature detection system by VI method
already exists
~
Synchronous Condenser
~
Synchronous Generator
Phase-3:
(When NCGS retires fully and there is no active
demand & steam generation)
In this phase, NCGS will be considered as pure synchronous condenser
station.
The exciter will be used as prime mover.
The electrical supply to the exciter will be provided from a motor generator
set. One such motor generator set exists at Mulajor Generating Station.
A separate excitation system will be required for the excitation of the
synchronous condenser
Schematic of phase-3
33 KV Bus Bar
Synchronising Circuit Breaker
Extra Thrust
Bearing Arrangement
Turning Gear
Arrangement
Existing Exciter
To be used as
DC Motor
Synchronous
Condenser
SEE
Lube Supply
From AOP
JOP Supply
DC Generator
Induction Motor
3 phase AC supply
CONVERSION OF 30 MW
SYNCHRONOUS GENERATOR
TO SYNCHRONOUS
CONDENSER
MW
MVA
VOLTS
STATOR CURRENT
P.F.
RPM
EXCITATION VOLTAGE
ROTOR CURRENT
: 30 MW
: 35.3 MVA
: 33 KV
: 618 A
: 0.85
: 3000
: 300 V
: 260 A
T/A-1 READINGS FOR LOW ACTIVE POWER & HIGH REACTIVE POWER
TEST ------- ON 24.11.06
Pilot
excitor
output
crt (1-5)
A
Main
excitor
field
voltage
(7-8) V
Gen.
Field
(rotor)
voltage
V
Gen.
Field
(rotor)
current
(L-260 )
A
Stat
or
volta
ge
KV
Deriv
ed
Powe
r
facto
r
Activ
e
power
MW
Rea
ctiv
e
pow
er
MVA
R
L=LIMIT
Stator
current
(L-550
A)
Rotor
temp
(L190 O
F) =
88 o C
Air Air
cooler
temp I/L
(L- 140 O F)
Air
Air
cool
er
tem
p
O/L
(L108
O F)
Cond
Temp
opp ex
duct
(L- 198
O F)
Back of
core
temp (L198 O F)
Sl
.
N
o
Start
Time
Pilot
Excitor
output
voltage
10-10
13
6.3
10.32
118
119
34.2
0.781
100
34
97
87
107.1
106.7
10-20
15
11.82
138
139
34
0.53
135
43
101
88
113.3
116.1
10-30
10-35
18
13.82
162
162
34
0.385
12
235
50
102
88
115.2
123.2
10-50
10-50
19
8.6
14.99
184
181
33.9
0.298
16
295
56
105
89
120
130.1
11-15
11-15
22
9.8
17.53
215
210
33.8
0.242
20
380
66
108
90
125.7
136.7
11-45
11-45
25
10.6
19.3
240
230
33.8
0.204
24
405
82
113
92
136
148
12-40
Frequency = 49.45 HZ
End
Time
Rotor
Temp
Shunt
Main
Rheostat
8
Gen. Field
Ammeter Shunt
Field Switch
S
h.
Fi
el
d
Fi
el
d
Vo
lt V
m
et
er A
P.
Ex
M
ai
n
N
eg
Fi
el
d
M Ex
Disc
Res
1
Ex Field
Ammeter
Main
Ex
Field
Dis
Sw
Gen. Field
Voltmeter
T/A
Rotor
Field
T/A-1 READINGS FOR LOW ACTIVE POWER & HIGH REACTIVE POWER TEST ------ON 12-12-2006
Freq
=
49.15 Hz
Bus Voltage =
Start
Time
Pil
ot
Ex
cit
or
vo
lta
ge
V
Pilo
t
exci
tor
out
put
ct
A
9-50
15
6.9
10-15
16
7.5
10-30
19
11-00
33 KV
Reac
tive
powe
r
MVA
R
(from
analo
g
meter
)
Stator
curre
nt
(L550
A)
Rotor
temp
(L- 84
O C)
Powe
r
factor
Ac
tiv
e
po
w
er
M
W
33.2
0.96
10
190
48
93
80
105.5
108.6
10-15
149
33
0.55
10
10
195
54
96
81
110
118.2
10-30
180
179
32.4
0.32
14
14
270
64
97
81
113.3
125.3
11-00
16.7
220
210
32.3
0.26
20
20
360
72
99
82
118.2
130.9
11-30
10.
9
19.3
245
235
32
0.21
25
25
455
82
97
86
125.8
138.6
13-00
11.
5
21.05
258
235
32.6
0.1
25
25
450
84
93
87
124.8
140
14-00
25
25
84
93
88
126.9
143.8
15-00
Main
excito
r field
voltag
e
(7-8)
V
Gen.
Field
(rotor)
voltage
V
Gen.
Field
(rotor)
current
A
140
142
12.6
149
8.5
15.2
22
9.6
11-30
25
13-00
27
14-00
Sl.
No
Stato
r
volta
ge
KV
Reactive
power
MVAR
(from
SCADA)
Air Air
cooler
temp
I/L
(L- 140
O F)
Air Air
cooler
temp
O/L
(L108 O
F)
Cond
Temp
opp
ex
duct
(L198 O
F)
Back
of
core
temp
(L198 O
F)
End
Time
100
80
60
40
20
0
0
1000
2000
rpm
3000
4000
Ext
100 V
Power
Supply
Unit
Main
Rheostat
8
Fi
el
d
Vo
lt V
m
et
er A
P. Ex
Sh.
Field
Rotor
Temp
Shunt
M
ai
n
N
eg
Fi
el
d
Gen.Field
Ammeter
Shunt
M Ex
Di
sc
.R
es
Mai
n
Ex
Fiel
d
90 KW
Tr.
Rectifier
Armature
Supply
Field
Switch
T/A
Rotor
Field
Gen.
Field
Volt
mete
r
A load test has been carried out for the transformer rectifier with
heater load
Front view of the 100 V DC power supply. When the shut current is below
set value, the red lamp will glow and drop out the DC contactor of the
armature supply.
When the shut current is more than the set value, the green lamp will glow
and enable the armature DC contactor to pick up