Professional Documents
Culture Documents
BHEL CFBC Experience
BHEL CFBC Experience
BHEL CFBC Experience
2011
TS TIDINGS
KUDANKULAM NPP
JUNE
: 2011
VOLUME : 15.01
HIGHLIGHTS
KOTHAGUDEM 500 MW UNIT 1 :
JUNE
2011
TS TIDINGS
INSIDE
Feed backs and suggestions from all departments of BHEL for improvement of TS
TIDINGS are welcome and may please be addressed to ADDL. GENERAL MANAGER
(TSX)/BHEL-PSSR/CHENNAI
TECHNICAL SERVICES / PSSR
JUNE
2011
TS TIDINGS
Unit is running around 400 MW, load limited due to poor quality of
due to coal feeding problem.
coal and
was completed.
Drum internal inspection was carried out and modification work was completed.
SAT 2 Transformer
completed.
completed.
was completed.
:
OCC
&
was
was completed.
M/s
Unit was under shut down from 28.05.11 due to rubbing in the Bearing-3
oil catcher area. BHEL/Haridwar team reached site and machining of the rotor
was done at site by grinding with machine on barring gear.
JUNE
water fill
test
was
2011
carried out
TS TIDINGS
Condenser
attended.
and
UNIT REACHED
FULL LOAD FOR THE FIRST TIME ON 26.06.11 AND
MAXIMUM LOAD REACHED WAS 515 MW.
Unit
commissioned.
KUTTIYADI 2 x 50 MW UNIT 1:
LGB oil leakage through oil vapour seal assembly was attended.
KUTTIYADI 2 x 50 MW UNIT 2:
Unit was
work.
under shut
down
since
27.05.11 for
carrying
out
maintenance
TG PG Test flow nozzle in HPH drip line and condensate line erection was
completed.
TECHNICAL SERVICES / PSSR
JUNE
2011
TS TIDINGS
Boiler was lighted up on 03.06.11 and stopped due to water wall leakages.
Water wall tube leakage works were completed and subsequently hydro test was
carried out.
COAL FIRING
since
18.05.11.
Preparatory
works
for
lignite
ESP
JUNE
2011
TS TIDINGS
DMCW 1A: suction valve door seal was replaced, pump NDE mech seal was
replaced and pump was taken into service.
PA fan -1A trial run was carried out after impeller design modification.
MS safety floating was completed and drum safety valve 1/3 floating was done
and is to be adjusted.
Unit was boxed up on 1.07.2011 due to transport conveyors B& C chain got cut.
Joint) failure,
heaters
were
Unit
was
under shut down
from 07.05.11 due to internal
Generator Transformer ( customer scope ).
fault of
Boiler was lighted up on 23.06.1 and unit was synchronized on 25.06.11, after
attending to 400 KV CB.
JUNE
2011
TS TIDINGS
Unit is under shut down after full load operation on 31/03/2011 for attending
to pending jobs and balance system commissioning.
ECO hoppers flue gas duct air tightness test was carried out.
TDBFP A : Governing system checking, control valve calibration and hydro test
of lines was completed. Feed water line flushing was completed.
CC pump C trial run was done after replacement with unit 4 CC Pump.
Furnace ATT
rectification
by
JUNE
2011
TS TIDINGS
JUNE
2011
TS TIDINGS
JUNE
10
2011
TS TIDINGS
TDBFP-B drive turbine was re-rolled to 5400 rpm on 29.05.2011. Oil injection test
was attempted and could not be achieved at 4KSC test oil pressure. Hand tripping was
also attempted but without any success. Suspecting jamming, the trip device was
opened and serviced; the pin was again found to be sheared. The pin was replaced and
the Drive turbine was cleared for rolling. After rolling the same phenomena were
observed again for the third time and the turbine was stopped and kept on Barring
Gear for analysis:
1. Hand trip knob was pressed in test position and it did not operate. It was
observed that holding/reset oil line is getting heated up during testing process.
2. Doubting generation of reset oil pressure during testing a dummy was provided to
block reset oil.
3. The turbine was reset. Lever of over speed tester is pressed down and hand wheel
is tightened to test position. Trip device knob was pressed and found to be
behaving normally (with the dummy in reset oil line).
4. It was suspected that the overspeed tester pilot position is not correct, which may
be causing the build up of reset oil pressure in the tester.
5. Over speed governor tester is dismantled. It was observed that in test condition
pilot piston is moving 12 mm (instead of 5 mm) downwards and oil above piston is
getting connected to holding oil port due to over travel of piston which is leading to
build up of reset oil. Shown in figures: 2 & 3.
6. The hand wheel position of tester in TDBFP A was checked and compared with
TDBFP B for establishing the overtravel.It was found that the TDBFP-B tester
hand wheel position was up by 6mm (approx) when compared to TDBFP A. The
tester was kept at intermediate position by partially closing the hand wheel and
Trip device knob was pressed and found to be behaving normally. Shown in
figure:4.
7. The downward movement of the pilot is stopped by the hand wheel after required
travel of 5 mm as per drawing. This over travel confirmed the improper fixing of
Hand wheel at works.
JUNE
11
2011
TS TIDINGS
closed at hand wheel fully closed condition. Hand wheel was fixed in correct
position and the locking pin was tightened properly.
Conclusion
After the above correction, Turbine resetting was done. Trip device operation was
checked, repeatedly, by pressing the hand lever in test condition. The behaviour of
the trip device was found to be normal. Oil injection test and actual over speed test
was carried out, the performance was found normal. Over speed pin acted at 4 ksc of
test oil pressure and tripped at 5881 RPM during actual over speed test.
The feedback of this defect in assembly was given to BHEL, Hyderabad. Limiting the
travel of over speed tester pilot to the required length by other than hand wheel is
to be reviewed to avoid such problem.
JUNE 2011
12
Figure: 1
TS TIDINGS
Figure:2
JUNE 2011
13
Figure:3
Figure:4
TS TIDINGS
JUNE
14
2011
TS TIDINGS
Problem detail:
Kothagudam unit 11 was synchronized for the first time with grid on 30/03/2011.
Subsequently unit was restarted on 27/05/2011 at 13:55 hrs. Unit was loaded upto
120 MW with four mills taken into service. The main steam temperature of almost
rated parameter was reached. At 16:00 hours sparks were observed at IP rear oil
guard area for few seconds and disappeared. Again at 21:00 hrs similar observation
was made. Close monitoring of all parameters were made and there were vibration
changes during this period. Unit tripped at 01:30 hrs due to tripping of 80mva
transformer causing tripping of auxiliaries. After trip out, during machine on barring
gear oil leakages and smoke were observed in IP rear area. It was planned for
inspection of IP rear pedestal.
Analysis and rectification:
The expansion achieved in IP rotor was 15mm during these above observations. Axial
rubbing marks of IP Rotor collar with the oil guard ring (Turbine side) at bearing
pedestal number 3 were observed. On further inspection & dimensional measurement it
was observed that the maximum axial clearance available for expansion of IP rotor
towards +VE side (Gen side) in front of pedestal no-3, in present condition, is only
15mm instead of the required gap of 25mm approx as per design/drawing. Damage
was noticed on oil guard ring (Turbine side) of pedestal 3 after axial expansion of IP
rotor (refer photo I and II). This is due to the IP rotor dimension which is physically
maintained as 80 mm in manufacturing instead of 70 mm as shown in the section EE of
drg no 0-10201-41000 IP ROTOR (refer sketch I and II). All other dimensions
are found to be as per drawing and shown in the SKETCH I. Damage to oil guard ring
(Turbine side) of pedestal no 3 and its outermost sealing strip due to axial rubbing is
beyond repair and the oil guard needed replacement (refer attached photos).
BHEL/Hardwar was referred to analyze the failure. Team from BHEL,Hardwar was
deputed and the dimensions of the rotor was verified and it was decided to carry out
TECHNICAL SERVICES / PSSR
15
JUNE
2011
TS TIDINGS
in situ machining of the rotor. The rotor was machined by grinding by BHEL hardwar
technicians with machine in barring gear. As the gap available for machining was small,
it could be done with pedestal top half removed condition only. For putting the
machine on barring gear with pedestal No.3 top half open condition, the oil flow to
the bearing was reduced to minimum by adjusting the lub oil inlet throttle. The speed
of barring gear was maintained around 35 RPM during machining by throttling of
barring gear inlet valve. The final diameter of the rotor to the tolerance limit of
0.02 mm was achieved by polishing with emery paper during machine on barring gear.
The damaged oil guard was replaced with new one.
Conclusion:
After machining of the rotor, unit was restarted and full load of the unit was
achieved and rubbing problem was resolved. The axial dimensional check of machines in
other projects were also carried out as per advice of BHEL,Hardwar for such
deviations and it was found in few of the units machining was required to avoid axial
rubbing. This dimension was not in Quality checklist for production and it was
suggested to BHEL, Hardwar to introduce the same to avoid such occurrence in
future.
16
JUNE
2011
TS TIDINGS
Photo 1
TECHNICAL SERVICES / PSSR
17
JUNE
2011
TS TIDINGS
Photo 2
18
JUNE
2011
TS TIDINGS
19
JUNE
2011
TS TIDINGS
Design issues arising out of adapting for low volatile fuel are discussed and path
forward is elucidated.
Key Words :
Bharat Heavy Electricals Limited (BHEL); Circulating Fluidised Bed (CFB); Circulating
Fluidised Bed Combustion (CFBC); Petcoke; Cofiring; FBHE (Fluidised Bed Heat
Exchangers); Oxides of sulphur Sox; Oxides of Nitrogen NOx; Selective Catalytic
Reduction (SCR); Flue Gas Desulphurisation (FGD).
Introduction to CFB Technology:
The fluid bed combustion process facilitates power production firing a wide range of
fuels while meeting stringent required emissions limits. CFB technology has
demonstrated an unparalleled ability to achieve low NOx production without the need
for post- combustion temperatures (850-900* C) and the staging of air by application
of secondary air admission zones. Furthermore, CFB technology has exhibited fuel
flexibility with an ability to burn waste materials and fuels previously deemed
uneconomical and/or impossible to handle by conventional boiler firing system
technologies.
A large mass of solid particles, once heated, help in maintaining combustion
temperature and stabilize combustion over wide ranges of heating values of fuels thus
allowing a range of poor quality and waste fuels, as well as usual fuels, to be
combusted.
In a fluidizing bed, gas is passed upward through a bed of solid particles. At low
flow, solid particles remain in contact with one another and the bed solid particles are
stagnant. As the gas flow increases, a point is reached at which the forces are
sufficient to separate the solid particles, and the beds acts much like a fluid.
Large portions of the fuel and limestone are suspended in the gas stream and the
gas-solid phase extends throughout the furnace. Even though the velocity in the
combustor is sufficient to entrain most of the particles, the dynamics of solids in the
combustor is such that suspended particles tend to form clusters. The size of these
clusters increases to sizes for which velocity of the gas is below entrainment velocity
causing the material to fall down the furnace. On their way down, these clusters
collide with rising material, breakup, and the smaller particles travel up again. This
action promotes mixing and gas to solid contact in the bed. Some of the material in
the bed is too large to be entrained until it is reduced in size by combustion and
attrition. Fresh feed of coal and limestone maintains the bed condition. In a typical
20
JUNE
2011
TS TIDINGS
combustor, bed velocity is maintained at approx. 4-6 m/s. At this velocity. Erosion
rates are low and heat transfer rates are reasonable. The circulating inventory would
normally consist of particles of size ranges of 0.03 to 2 mm, depending on the fuel.
In general, fuels with low volatile content. Low volatile matter fuels would require
finer sizes and high recycle rates, in the range of 10:1 to 100:1 to ensure good
carbon burn out. The size of the particles is critical, if the feed is too fine,
excessive material will remain in the gas leaving the cyclones resulting in an
insufficient material in circulation.
A combustor temperature between 8500 C and 9000 C is usually selected in CFBC.
Combustion stability is provided by the high thermal inertia of the large mass of fuel
and inert material in the bed. Acceptable burnout of fuel results from the long
residence time of fuel in the bed and by recycles of material captured. A wide range
of fuels may be fired in fluidized bed boilers because the design is for combustion
temperatures that are lower than the ash softening temperatures of most of the
fuels. The use of a scrubber may not be required for S0X control. The potential for
high temperature corrosion due to high vanadium content in the fuel and low
temperature corrosion due to high sulphur in the fuel is reduced by bed absorption. In
the combustor, limestone continuously reacts and, therefore, it is necessary to
continuously feed limestone with the fuel. The Sulphation reaction requires that there
is always an excess amount of limestone present. The amount of excess limestone that
is required is dependent on a number of factors such as the amount of sulphur in the
fuel, the temperature of the bed, and the physical and chemical characteristics of
the limestone. Sulphur capture by mixing higher percentage of limestone.
Fuel characteristics & Impact on Emission.
The uncontrolled SOX emission from the combussion of a coal with 1.0% - (weight%)
sulphur with a heating value of 3800kcal/kg under normal combustion conditions is
about 2000 mg/nm3 In number of countries with 3% (wt) sulphur removal would be
required for environmental compliance. Sulphur dioxide emissions can be reasonably
predicted given the sulphur content in the fuel, however NO X emissions are not so
easy to predict, because the amount of NOX produced in a combustor depends not only
on the type of fuel being burned but also on the process conditions observed in a
particular combustion device.
21
JUNE
2011
TS TIDINGS
Constituents
Average
Range
Carbon
79.74
75.0-85.0
Hydrogen
3.31
3.0-3.6
Nitrogen
1.61
1.3-1.9
Sulphur
4.47
3.4-5.3
Ash
0.27
0.0-0.6
Oxygen
0.00
0.0-0.1
Moisture
10.60
5.5-15.0
HHV kcal/kg
7475
7000-8050
HGI
55
35-55
Ash Properties, ppm
Vanadium
<2000
500-2000
Nickel
336
250-450
Iron
84
50-250
Table 1
A typical representative of Petcoke is presented in table 1. The above fuel
characteristics have forced many utilities to opt for only co-firing or blending with
coal to improve flame stability and avoid preclude ignition problems. The low volatile
matter in the coke makes it the fuel harder to burn unless the temperatures are
22
JUNE
2011
TS TIDINGS
raised higher and longer residence time are provided. Both the requirements increases
the NOX generation potential.
Petcoke is produced from virgin crude residues by precipitation reactions of high
molecular weight compounds, asphaltenes, and resins or from highly aromatic tar or
decanted oil stokes by condensation and polymerization of aromatic compounds.
Delayed Petcoke is produced by a semi continuous process, which can be carried
through in one of the following ways: ultimate, once-through, or intermediate coking.
The sulphur content of the Petcoke strongly depends on the nature of the cokinf
feedstock (crude oil) and its sulphur content. The sulphur content of the feed stocks
increase with increasing the concentration of asphaltenes and conradson carbon
content. For instance, higher sulphur contents were found in sponge coke (produced
from high-resin asphaltene feed stocks) than in honeycomb coke (produced from
low-resin asphaltene feed stocks) or needle coke (produced from highly-aromatic
feed stocks).
The sulphur content in petcoke varies widely mainly depending on the sulphur content
of feedstock, Typically sponge coke contains between 1% and 6% Sulphur sponge coke
containing 4% Sulphur is used for fuel whereas that of less than 4% sulphur content is
used in anode manufacturing. Needle cokes used for electode manufacturing, are
required to have less than 1% sulphur content.
Coking temperature also affects the sulphur content of petcoke, though in less
degree, mainly due to the vaporization and removal of the low sulphur containing
volatile matter, which result in a reduction of the total sulphur content in the coke.
Most of the sulphur in Petcoke exists as organic sulphur bound to the carbon matrix
of the coke. Some sulphur could also exist as sulphates and as pyretic sulphur, but
these do not in general make up more than 0.02% of the total sulphur in coke.
Hence, it is more critical to ensure a fair degree of desulphurization to capture the
SOX emanating from combustion of petcoke.
Advantages of CFB process for Petcoke Firing:
The following list of process advantages in combination with unique design innovations
have enabled the 100% firing of Petcoke Large amount of ignition energy in the bed
makes up for the delayed combustion characteristics of the fuel. Pulverisers are not
employed as the process support combussion of
larger particles of millimeter
diameter.
TECHNICAL SERVICES / PSSR
23
JUNE
2011
TS TIDINGS
The process employs part of combussion air to fluidise or hold up the particle thus
ensuring oxygen concentration all around the particle.
This improves carbon utilization also. High carbon content with low volatiles would be
precursor for high carbon loss and it is overcome by process capability of employment
of primary loop of cyclone, which provides good residence time for the finer particles
to burn out the carbon content.
Lower combustion temperatures aids in in-situ sulphur capture. It also avoids fouling
and slagging problems.
The bed with its larger inventory provides better restart capability.
As the bed provides a near homogenous temperature to high turbulence mixing of bed,
the local hot or cold spots are avoided.
Description of Process Design of CFB boiler for Petcoke Firing.
The major components of the CFB boiler system are the furnace cyclone separator,
the non-mechanical loop seal/seal pot and the convection superheater surface. In the
furnace the bed material, with the fuel, is fluidized with primary air, which
turbulently transports the solids up the full height of the furnace. Combustion of the
fuel takes place as it rises and heat is transferred to the membrane water-wall
tubing that form the walls of the furnace. The hot combustion gases with the
entrained solids exit at the top of the furnace into the cyclone separator. The
cyclone separates the solids from the combustion gases and returns the solids,
including any unburned solid fuel, through the non-mechanical loop seal or seal pot to
the furnace where they mix with incoming fresh fuel. The long solids residence time
due to recirculation of the solids ensure high combustion efficiencies for a wide range
of fuels.
Heat for steam generation is removed from the system in three main areas:
A primary loop: where heat is removed from the solids circulating in the CFB system.
Here the heat removal is achieved by transfer through the water walls of the upper
part of the combustor.
External fluid bed heat exchanger (FBHE): FBHE consisting of fluidized chambers,
where part of the solids circulating in the system are directed and fluidized in order
to maintain flow and optimum heat transfer conditions and after heat transfer to
superheat/evaporator surfaces, are returned to the combustor at reduced
temperature, The system operates like a conventional fluidized bed.
TECHNICAL SERVICES / PSSR
JUNE
24
2011
TS TIDINGS
In back pass, heat is removed from the flue gas through superheater and economizer
surfaces and an air preheater.
The entire combustor as well as the grate is enclosed by water walls and the lower
water wall section is refractory lined to prevent corrosion and attack of the metal
surfaces.
The upper water wall section is not refractory lined and provides the majority of the
evaporative duty of the boiler.
Flue gas resulting from the combustion of the fuel along with the entrained solids exit
the combustor via gas outlet located in the upper portion of the water wall and is
ducted to the recycling cyclone designed to remove more than 99% of the solids
entrained by the gas from the combustion chamber. The flue gas exiting the cyclone
follows a path some what similar to a conventional boiler system namely:
A)
B)
C)
D)
E)
F)
G)
25
JUNE
2011
TS TIDINGS
26
JUNE
2011
TS TIDINGS
The units at SLPP were started up in November 1999 and after resolving teething
problems, commercial operation of the units began in February 2000, The units
underwent a reliability trial for a month (May 2000), and this included a full load trial
for 10 days during which they were operated continuously at rated load.
Although the units were designed for lignite of HHV of 4240 kcal/kg the units are
now being fired with lignite having heat value of close to 3000 kcal/kg. The units
performance matches design predictions quite well. The operational and erection
feedbacks has been captured and incorporated in subsequent CFBC designs.
Unique Design Challenges Involved for 100% Petcoke Firing
Petcoke is a difficuilt fuel for combustion and offered for the first time for 100%
firing in CFBC boiler in India. This fuel contains very low volatiles (in range of 10%
viz a viz >25% for lignite), higher sulphur (in range of 6% viz a viz 1% for lignite) as
compared with other coals like lignite.
Other coals such as Lignite has more volatiles and the ash is more friable than that
from Petcoke. Petcoke is devoid of its volatile content as it has already been exposed
to high temperatures in the refinery process and is of high Carbon content (>70%),
The absence of volatiles makes the combustion of carbon in Petcoke difficult. The
combustion characteristic of Petcoke is such that the heat release is delayed by a
couple of minutes after entering the combustor.
Sulphur capture reaction is a complex gas-solid reaction, which is highly dependent on
surface property and size of the solid under reaction (limestone). The sulphur-dioxide formed from combustion of fuel sulphur has to penetrate the pores in the
calcium sulphate. This capture is further critical in Petcoke, which has higher sulphur
content in comparison to other coal like lignite.
The design development of CFBC boiler firing 100% Petcoke involved extensive trials
at CFBC test facility to evaluate fuel characteristics in CFBC environment. Fixing two
levels of secondary air elevation to ensure better control over NOX and combustion
process are other unique features employed in the design. The trials were also used
to arrive at optimum level of Ca/S ratio to reduce SOX to desired levels
27
JUNE
2011
TS TIDINGS
JUNE
28
2011
TS TIDINGS
2.
3.
29
JUNE
2011
TS TIDINGS
4, 5, 6 & 7
1 & 2
5
7
250 MW
KOTHAGUDEM UNIT - 10
210 MW
VIJAYAWADA UNIT 1 & 6
MUDDANUR UNITS - 2 & 4
RAICHUR UNIT - 6
METTUR UNIT 3 & 4
NORTH CHENNAI UNIT - 2
NEYVELI UNIT 4 & 6
30
JUNE
2011
TS TIDINGS
JUNE
31
2011
TS TIDINGS
STATION
2010-11
2011-12
North Chennai
Neyveli
Raichur
Tuticorin
Ramagundam
Muddanur
Kothagudam
Vijayawada
VTPS - 7
Mettur
Talcher
Simhadri
Sipat
Amarkantak
69.95
89.12
57.45
89.60
101.03
92.77
81.75
78.53
62.37
90.08
93.69
100.35
96.55
--
90.91
95.10
81.58
87.94
89.52
89.53
89.30
93.44
98.46
98.07
91.44
101.62
91.18
95.10
120.00
2010 - 11
2011 - 12
100.00
80.00
60.00
40.00
Am
arkantak
Sipat
Sim
hadri
Talcher
M
ettur
VTPS- 7
Vijayaw
ada
Kothagudam
M
uddanur
R
am
agundam
Tuticorin
R
aichur
N
orthC
hennai
0.00
N
eyveli
20.00