Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Dsq.

Field Forthcoming planned S/D Hereunder are the depicted procedures for lines and vessels at inlet and outlet of CTP
in order to enable carry out S/D activities safely and smoothly
-

Some tasks will be carried out in concurrently while some to be in


consequentially

The next procedures to be followed:


-

Initiating total CTP plant S/Make sure the automatic S/D valves on all trunk
lines, are positively closed.
Open manual valves upstream pig receivers of NSG and NWSG wells
Use 2 cold flare lines to depressurize Sections upstream slug catcher of NSG
wells, SSG wells and 12 section of NWSG wells use valves B&C Refer to
attached Dwg. No. 1
6 trunk line of NSG1-1, 1-2
Both wells feeding the line will be closed-in using lower and upper master
valves and further isolated from well side via closing manual wing valve, gas
choke and manual 6 valve. Moreover, the 6 header manual isolation valve on
the duplex flow line will be closed
Completely depressurize the line Venting the gas from CTP side using 6 vent
line to flare header (open manual valve A Dwg 1),now 6 trunk line is
depressurized till SDV-30.01
Open 2 manual valve to cold flare to depressurize the line section from
automatic S/D valve.. till the 16 inlet header
Use 2 connection for tie-in with contractor (Spesco) N 2 supply for line purge
Refer to attached Dwg. No. 1
12 trunk line of NWSG1-1
The line will be kept pressurized till the automatic S/D valve SDV 32.06, then to
be depressurized from that point till the 16 inlet header using the 2 cold flare
vent
Upon assuring the line is depressurized, start replacement activities of the
passing 2, 6 and 12 manual valves on NWSG line to inlet header Refer to
attached Dwg. No. 1
Slug catcher
Switch over power generation to be used the diesel fuel generator.
Bypass protection instrumentation on slug catcher and Lower the liquid levels
(water to degasser and condensate to condensate stabilizer and) inside the
vessel as low as possible
Drive all liquids to closed drain vessel
Completely Depressurize slug catcher to flare using 2 depressurizing valve
and open manholes for ventilation
Upon measurement of O2 and gas concentration start vessel internal cleaning
All instrumentation particularly liquid monitoring (condensate and water levels
to be dismantled and re-calibrated)
Refer to Dwg. No 2 (slug catcher )
LTS

Bypass protection instrumentation on slug catcher and Lower the liquid levels
(condensate to condensate stabilizer and MEG to pertinent storage tanks)
inside the vessel as low as possible
That condensate to condensate stabilizer and MEG to pertinent storage tanks
Drive all liquids to closed drain system through nozzles 13 and 14
Then Completely Depressurize slug catcher to flare using 2 depressurizing
valve and open manholes for ventilation
Upon measurement of O2 and gas concentration start vessel internal cleaning
Start vessel internal cleaning
All instrumentation particularly liquid monitoring (condensate and MEG levels
to be dismantled and re-calibrated) regarding both vessels
Refer to Dwg. No 2 (slug catcher and Dwg. No. 3, 4 for LTSs A &B)

Degasser
Use degasser dumping pumps to lower produced water level till the trip level of
the pumps and isolate the degasser using the manual valves then completely
drain the vessel to closed drain system and depressurize to flare.
Refer to Dwg. No.

BVS1
Upon initiating GPSD,
Based on the sealing condition of 16 up and downstream the S/D valve SDV5302 there are two scenarios for isolation and depressurizing
First
Make sure 16 valves up and downstream S/D valve SDV- 5302 are positively
sealing by testing for leak through 0.5 bleeding nipple
Dismantle 0.5 connection of pressure gauges up/downstream the S/D valve
SDV- 5302 to depressurize the 16 line section then apply proper quantity of
N2 inside for purging.
Second
If the manual valve up/downstream arent sealing
You will have to use the 4 vent valve to cold flare, in addition to the 4 vent
line to flare system (installed on temp. pig launcher ) to depressurize the 16
line section from CTP to the BVS1
(refer to Dwg..)to flare system
BVS-2 (RPF area)

List of requirements
-

NWSG TL:
2 X 2 X 600 Sp. w gasket

2 X 6 X 600 Sp. w gasket


2 X 12 X 600 Sp. w gasket
Slug Catcher:
2 X 24 RJ gasket
2 X 4 600 Sp. w gasket
4 X 2 X 600 Sp. w gasket
1 X 3 X 600 Sp. w gasket
LTS:
2 X 24 RJ gasket
3 X 2 600 Sp. w gasket Gasket
Degasser

You might also like