Professional Documents
Culture Documents
Principal Decisions
Principal Decisions
External wall construction: Cladding costs can be very high and the structure should be designed
recognising this and ensuring adequate fixing arrangements.
The external skin of a multi-storey building is supported off the structural frame. In most high quality
commercial buildings, the cost of external cladding systems greatly exceeds the cost of the structure.
This influences the design and construction of the structural system in the following ways:
The perimeter structure must provide a satisfactory platform to support the cladding system
and be sufficiently rigid to limit deflections of the external wall.
Reducing the floor zone may be more cost-effective than an overall increase in the area of
cladding.
Fixings to the structure should facilitate rapid erection of cladding panels.
Reducing the weight of cladding at the expense of cladding cost will not necessarily lead to a
lower overall construction cost.
Floor systems
The principal structural elements of a typical multi-storey building are the floors, beams, columns and
foundations.
The principal structural elements of a typical multi-storey building comprise floors, beams and columns.
A wide variety of alternative forms and arrangements can be used in multi-storey steel framed
structures.
This form of slab construction is particularly popular for multi-storey buildings when rapid construction
is required. Some of the advantages of the composite system are:
Steel decking acts as a permanent shuttering which can eliminate the need for slab reinforcement and
propping of the construction while the concrete develops strength. This leads to simple, rapid
construction.
Composite action reduces the overall depth of structure. It provides up to 2 hours fire
resistance without additional fire protection and 4 hours with added thickness or extra
surface protection.
It is a light, adaptable system that can be cut to awkward shapes and can easily be drilled or
cut out for additional service requirements.
The overall weight of this system is low, particularly if lightweight concrete topping is used,
reducing frame loadings and foundation costs.
The demands on cranage are low as many sheets of steel decking may be lifted at a time, and
then laid out by hand; the concrete topping may be placed by pump.
Precast concrete units are also often used with a steel frame, offering long spans and quick
installation.
Precast concrete floors area heavier form of construction than comparable composite metal
deck floors, but offer the following advantages:
Fewer floor beams since precast floor units typically span 6 to 8m.
Shallow floor construction can be obtained by supporting precast floor units on shelf angles.
Fast construction because there is no propping and no time is needed for curing and the
development of concrete strength.
Slimdek extends the range of cost-effective steel options for modern buildings. Ease of planning and
servicing, combined with a reduction in building height, gives significant cost and speed of construction
benefits.
Slimdek solutions can be designed to incorporate the latest technology in energy efficient services
principles.
Alternative floor framing systems
Composite beams mobilise the strength of the floor slab to improve the strength of the steel beam.
Composite action is achieved by welding studs to the beam flange to form a continuous shear
connection. The slab then acts as the compression flange for the beam. When used with composite
deck flooring, the studs are welded through the decking onto the flange of the beams below to form a
connection between steel beam and concrete slab.
Maximum beam span is about 15m and beam depth can be estimated as span/25 (see figure 1)
Weight comparisons for different beam layouts indicate the use of long span main beams.
Figure 1 shows the effect of varying the arrangements of primary and secondary beams. The weight of
steelwork per square metre for each arrangement is plotted against span of primary beam. This
comparison has been based on a limiting criterion of span/360 for superimposed load deflection
required by BS 5950 and incorporates an allowance for trimmers and connections.
The comparison highlights a number of interesting features relating to this type of floor system and floor
grids in general:
Long spanning secondary systems result in heavier floor steel than using long span primary
beams. For example, a 9m by 15m structural bay with 15m secondary beams uses 20
percent more steel than a 15m by 9m bay with 15m primary beams.
For the longer spans the effect of setting more stringent deflection criteria (say a flat limit of
25mm instead of span/360) is to increase the weight of steel required significantly (between
5 and 10 percent).
In practice long span secondary beams are often used.
This website uses cookies. By continuing to browse this website you are
agreeing to our use of cookies. Find out more by reading our privacy policy.
CONSTRUCTION
Register
Login
Home
About us
Products
News & events
Design
Case studies
Sustainability
Reference
Home Reference Teaching Resources Architectural Teaching Resource Design Choice of structural systems for multi-storey
buildings Floor systems
Floor systems
Reference
Teaching Resources
History
Technology
Design
Atria
Bridges
Introduction
Floor systems
structure
Structural principles
Concluding summary
Elements
Cladding
Architecture
Sustainability
Building in steel
Studio Guide
Floor systems
The principal structural elements of a typical multi-storey building are the floors, beams, columns and
foundations.
The principal structural elements of a typical multi-storey building comprise floors, beams and columns.
A wide variety of alternative forms and arrangements can be used in multi-storey steel framed
structures.
Fewer floor beams since precast floor units typically span 6 to 8m.
Shallow floor construction can be obtained by supporting precast floor units on shelf angles.
Fast construction because there is no propping and no time is needed for curing and the
development of concrete strength.
Floors
UC
SHS
152 x 152
150 x 150
2-4
203 x 203
200 x 200
5-8
254 x 254
250 x 250
9-12
305 x 305
300 x 300
13-40
356 x 356
400 x 400
Floors
UC
SHS
152 x 152
150 x 150
2-4
203 x 203
200 x 200
5-8
254 x 254
250 x 250
9-12
305 x 305
300 x 300
13-40
356 x 356
400 x 400
Structural principles
The structure must be designed safely to carry the applied loadings.
The structure must have adequate strength and stiffness to resist the applied loads due to gravity and
wind. The function of the structure in resisting vertical loads due to gravity and horizontal loads due to
wind is generally considered separately.
The principal floor loadings are due to the self weight of the building and its occupancy. These are
referred to as 'dead' and 'superimposed' (or 'imposed') loads respectively.
The floor loadings to be supported by the structure have two components:
The permanent or dead loading comprising the self-weight of the flooring and the supporting
structure together with the weight of finishes, raised flooring, ceiling, air-conditioning ducts
and equipment.
The superimposed loading which is the load that the floor is likely to sustain during its life and
will depend on the use. Superimposed floor loading for various types of building are
governed by BS 6399, but the standard loading for office buildings required by developers
and funding agencies is usually 4kN/m2 where movable partitioning is used.
Dead and superimposed loads in commercial buildings are often approximately equal.
For normal office loadings, dead and superimposed loadings are roughly equal in proportion but higher
superimposed load allowances will be necessary in areas of plant or to accommodate special
requirements such as storage or heavy equipment. The optimum structural solution is to locate any
heavier loadings close to columns or where the floor spans are shorter.
The design of the floor structure is concerned mainly with vertical loads. The criteria determining
member sizes depend on floor span.
The criteria determining the choice of a member size in a floor system varies with the span.
The minimum size is fixed by practical considerations such as fitting practical connections. As the span
increases, the size will be determined by the bending strength of the member and, for longer spans, by
the rigidity necessary to prevent excessive deflection under superimposed load or excessive sensitivity
to induced vibrations.
Steel buildings have to be rigid enough in the horizontal direction to resist wind and other lateral loads.
In tall buildings, the means of providing sufficient lateral rigidity forms the dominant design
consideration and developments in this field have led to the construction of taller and taller buildings
such as the John Hancock Building or the Sears Tower in Chicago.
Most multi-storey buildings are designed on the basis that wind forces acting on the external cladding
are transmitted to the floors which form horizontal diaphragms, transferring the lateral load to rigid
elements and then to the ground. These rigid elements are usually either lattice or rigid jointed frames
or reinforced concrete shear walls.
Floor framing
In addition to strength and stiffness, building structures must be designed to avoid progressive collapse
in the event of a catastrophic accident.
The partial collapse of a system-built multi-storey building at Ronan Point in 1968 following a gas
explosion, led to a fundamental reappraisal of the approach to structural stability in buildings. This
centred on the need to limit the extent of any damage in the event of catastrophic or accidental
loadings. This concept of robustness in building design requires that any major structural element must
either be designed for blast loading, or be capable of being removed without precipitating progressive
collapse of other parts of the structure. This can be demonstrated by considering alternative load paths
and structural actions in the damaged state.
In addition, there is a requirement for suitable ties to be incorporated in the horizontal direction in the
floors and in the vertical direction through the columns. The designer should be aware of the
consequences of the sudden removal of key elements of the structure and ensure that such an event
does not lead to the progressive collapse of the building or a substantial part of it.
Rigid frames resist lateral forces through the stiffness provided by rigid joints
Rigid frames avoid any intrusion but are relatively expensive.
The advantages of the rigid frame are that:
open bays between all columns are created,
total internal adaptability is provided,
However, the disadvantages are that:
They are almost always more expensive than other systems,
Columns are larger than for simple connections.
Generally, they are less stiff than other bracing systems with large complex connections.
Lattice frames act as vertical trusses and a number of different forms are commonly used.
Lattice frames act as vertical trusses which support the wind loads by cantilever action. The bracing
members can be arranged in a variety of forms designed to carry solely tension, or alternatively tension
and compression. When designed to take only tension, the bracing is made up of crossed diagonals.
Depending on the wind direction, one diagonal will take all the tension while the other is assumed to
remain inactive. Tensile bracing is smaller in cross-section than the equivalent strut and is usually
made up of a back-to-back channel or angle sections. When designed to resist compression, the
bracings become struts and the most common arrangement is the `V' brace.
Shear walls are normally constructed in in-situ reinforced concrete, but may be either pre-cast concrete
of brickwork. They are more rigid than other forms of bracing, and there is a need for fewer of them.
Shear cores are shear walls in box form which provide torsional or twisting resistance as well as
providing a highly effective bracing system.
Shear walls are effective but may create difficulties during construction.
The advantages of shear walling are that:
concrete walls tend to be thinner than other bracing systems and hence save space in
congested areas such as service and lift cores,
they are very rigid and highly effective,
they act as fire compartment walls.
The disadvantages are that:
they constitute a separate form of construction which may delay the contract programme,
it is difficult to provide connections between steel and concrete to transfer the large forces
generated.
For more information on advantages/disadvantages of shear walling please click here
The floor structure transfers lateral loads from the faade to the bracing system.
All stability systems use the floor plate as a diaphragm to transfer lateral loads from their point of
application to the bracing elements. The designer should ensure that the floor is capable of performing
this function.
Suitable location of bracing elements is therefore a fundamental requirement of the bracing system
design.
Isolated shear walls can be used to provide stability to the building frame, where the positioning of the
building cores requires additional stability structures.
Introduction
The successful integration of structure is crucial to solving the aesthetic, functional, technical and
economic requirements of a building. These requirements must be addressed during the design
process.
The choice of structural system is a critical element of the design process, but not one that cannot
easily be abstracted. Decisions regarding structure will be part of a problem solving process that will
require consideration of various requirements and the choice of structural system may be dictated by a
number of these. Although structure may simply be regarded as a means of supporting the building, its
contribution is a far more complex and fundamental aspect of building design.
When considering structure, there is a wide choice of structural systems and materials that may be
used.
Common systems include:
planar (or loadbearing) forms e.g. masonry or concrete walls
frames, e.g. timber, steel or concrete linear elements
membrane, e.g. fabrics and shells.
Steel has useful properties of strength, versatility and ease of connection which make it appropriate for
frame systems. In addition it lends itself to prefabrication.
Steel construction generally uses standard section columns and beams, but also includes arches,
trusses and grids, which can be connected together to produce a wide range of shapes and forms.
Other sections and shapes can be fabricated to order.
A frame deals primarily with the structural forces in a building, allowing other elements, such as walls,
cladding, insulation and weatherproofing, etc to be independent of the main structural requirements of
the building.
Whilst other materials can be used to form structural frames, steelwork, with its properties of strength,
isotropy and stiffness, also its straight and compact linear elements, easily assembled from
prefabricated elements, is particularly appropriate. These elements gather and transfer the major
structural loads as directly as possible to the foundations. These qualities provide strong, lightweight
structural systems that can support large spans and tall buildings whilst maintaining cost-effectiveness.
There are several points in the design process at which the consideration of structure may become
critical, depending on the brief, availability, visual language or cost.
Initial design approaches will necessarily be concerned with the brief development and plan
organisation. The exact point at which a decision concerning choice of primary structure can occur at
various points, e.g. as part of the brief, or dictated by availability of materials; it may be a particular
aesthetic requirement; or it may occur as part of a cost comparison with other structural forms.
A number of early decisions about the form and organisation of the building will affect the choice of
structural system. These include:
Different combinations of tension and compression occur as the result of bending in beams, trusses
and arches. The shape and size of these elements must allow for these.
Horizontal trusses are a combination of compression and tension (C+T) elements
Solid beams combine tensile and compressive capabilities to resist bending effects within a shallow
depth. The greatest shearing (S) effects occur at the beam ends.
Bending and deformation resistance depend on 2nd moment of area, I, a geometric sectional function.
For a simply supported beam the value of applied bending moment (M) is half that for the same total
load W concentrated centrally.
Arch geometries will be subject to a combination of compression and bending (C+B).
Whilst bending elements will require calculation to ensure adequate strength and stiffness, estimates of
sizing such as span/depth ratios and safe load tables can be used at design stages.
With a simple "Post" and "Beam" structure system, the beams always have greater depth than the
columns. A "bending" system always uses more material than one with direct compression and tension
forces only.
An initial preliminary assessment for the scale of various section types can be made from conservative
"Rules of Thumb". These are adequate for uniformly distributed loading - heavy concentrated loads will
need increased depth. Rules of Thumb are more difficult for "Columns" and a "Safe Load Table" can be
useful here, this can be found in the blue book.
Elements behaving primarily in tension and compression have different structural considerations.
A tension element with no internal bending stiffness takes up a funicular "hanging" form. Pure tension
elements (i.e. those that carry no compression or bending) can be very small rods, cables or wires
A centrally loaded long "pin-ended" circular compression element can deform and eventually buckle.
Note that sideways applied loading or an eccentric end load will always make the element deform more
easily and a greater bending stiffness will be needed.
Tension elements
Compression elements
With vertical columns and walls, there are three principal options, vertical cantilevers, rigid jointed
portals, and bracing:
Stability can be provided in one of three basic ways:
Vertical cantilever about the foundation. The column is "rigidly" fixed to the base. Such
columns are "pin" jointed to the beam at the top, sharing the applied load, and are designed
as "propped cantilevers". Note that the foundation size will be greater than for the systems
outlined below to limit soil pressures due to the transfer of bending moments to the
foundation
Rigidly jointed "portal" frames of various types in which the column is rigidly connected to the
roof `beam'
Braced by "pin" jointed slender tensile or compressive elements. With two crossed tensile
elements, one will always go into compression and be ineffective when wind loads are
acting Note that combined horizontal and vertical loading will increase the tendency to sway
horizontally. A frame will also sway sideways under eccentric vertical loading.
Diagonal bracing
Additional structural elements may also be used to resist reactions to horizontal loads, such as
bending, swaying and torsion. These include shear walls and cores.
In tall buildings elements such as lifts and fire escape stairs are also required and these can be used to
provide lateral stability. Additional elements such as shear walls can also be incorporated into the
design.