Professional Documents
Culture Documents
Understanding The APTEL Judgement On Compensatory Tariff Case of Adani and TATA
Understanding The APTEL Judgement On Compensatory Tariff Case of Adani and TATA
Understanding The APTEL Judgement On Compensatory Tariff Case of Adani and TATA
the imported coal price and (ii) the change in law by Government
of Indonesia.
The Central Commission (CERC) under an Interim Order dated
15/04/2013 rejected the claim of Force Majeure and Change in
Law and constituting an Expert Committee for suggesting the
compensatory tariff which would be payable to CGPL by invoking
Section 79(1)(b) of the said Act.
Findings of Expert Committee and CERC's order in both
Adani and TATA petitions
The Expert Committee headed by the Chairman - Mr. Deepak
Parekh along with other eminent members, having representation
from state beneficiaries and assisted by independent advisers,
legal consultants and KPMG as the financial consultant submitted
its Report before the Central Commission On 16/08/2013. The
Report was signed by its Chairman Mr. Deepak Parekh and one
Ms. Arundhati Mukherjee of SBICAP.
The Central Commission passed Final Order dated on 21/02/2014
holding that the claim of Force Majeure is not admissible, and
granted relief in exercise of its regulatory power under Section 79
of the Electricity Act, providing for a formula for granting
compensatory tariff to Adani Power as well as TATA Power.
The Appeals in APTEL
Being aggrieved by the CERC order dated 21/02/2014, Haryana
Utilities and other Non-state, non - profit consumer organizations
filed appeal to APTEL in both Cases.
Key issues before APTEL and the order The APTEL, in this elaborate order adjudicated on 15 issues
emerging out of these cases. Some of the issues and APTEL's
views thereon are summarized here for developing understanding
on some of the most critical areas of concern in present day
scenario of competitive bidding in Power sector.
1. Section 79 of Electricity Act, 2003, describes the functions of
Central Commission (CERC). Section 79 (1) (a) empowers the
CERC to regulate the tariff of generating companies owned or
controlled by Central Government and section 79(1)(b) of the said
Act confers power on the Central Commission to regulate tariff of
generating companies other than those owned or controlled by
the Central Government if such generating companies enter into
or otherwise have a Composite Scheme for generation and sale of
electricity in more than one State.
The issues identified was that whether the supply of power to
procurers in more than one State from the same generating
station of a generating company, ipso facto, qualifies as
Composite Scheme to attract the jurisdiction of the Central
Commission under Section 79 of the said Act?
This issue is relevant with regards to the jurisdiction of CERC on
cases arising out of supply of power from the same generating
station of a generating company. The APTEL held that the supply
of power to more than one State from the same generating
station of a generating company, ipso facto, qualifies as
Composite Scheme to attract the jurisdiction of the Central
Commission under Section 79 of the said Act.
2. One of the most sensitive issues was that whether the Central
Commission has the regulatory powers under Section 79(1)(b) of
the Electricity Act to vary or modify the tariff or otherwise grant
compensatory tariff to the generating companies in case of a
tariff determined under a tariff based competitive bid process as
per Section 63 of the said Act.
On this issue, the Tribunal entered into elaborate reasoning and
emphasized that the Section 63 of Electricity Act, 2003, provides
for a specific mode of determination of tariff namely
determination of tariff by bidding process in contrast to section 62
of the Act. It starts with a non-obstante clause and specifically
excludes the operation of Section 62, which under its subsection 4
provides for amendment of tariff, if necessary Since Section 63
excludes Section 62, this provision of amendment is not
applicable to determination of tariff by bidding process under
Section 63.
Section 63 contemplates determination of tariff through a
transparent process of bidding in accordance with the Guidelines
issued by the Central Government in this regard. It makes it
obligatory on the Appropriate Commission to adopt the tariff if it
is determined through the transparent process of bidding in
accordance with the said Guidelines issued by the Central
Government. Tariff determination by bidding process is guided
and controlled by the specific Guidelines issued by the Central
Government, which are accompanied by Standard Bid Documents
i.e. RfQ, RfP and PPA.
out/ altered the premise on which the bid was submitted by the
Bidders and made the agreements 'onerous' which is
contemplated as a Force Majeure Event under the PPAs.
However, in case of Adani's bid 1, APTEL did not accept the
submission that the supply from GMDC was the basic premise or
condition of PPA dated 2/2/2007 and PPA was entered into solely
on the basis of availability of coal from GMDC and the nonavailability of coal from GMDC to Adani Power has resulted in
Change in Law or Force Majeure Event and APTEL rejected the
Adani's submission of Change in Law or Force Majeure on this
account.
5. Another issue was that whether the bidders (TATA and Adani)
have taken the reasonable care to quote for escalable energy
charges in the bid. Here it is noteworthy that though it was open
to the generators to quote escalable energy charges in bid which
would have aligned the bid to market prices, TATA quoted nonescalable fuel charges for 55% of the contracted coal supply and
Adani chose to quote 100% non-escalable fuel charges.
ATPEL concluded that despite the fact that generators had partly
or fully quoted non-escalable tariff but not in all circumstances
can a generator be denied relief just because it quoted nonescalable tariff in the bid or under the PPA. As Adani Power and
TATA would have not known that Indonesian Government in
exercise of its sovereign power would issue regulation directing
that the coal prices for import of coal by the mining companies in
Indonesia should be benchmarked to the international market
price. Therefore, in the peculiar facts of this case, the fact that
they had quoted non-escalable rates cannot be taken against
2.
3.