Professional Documents
Culture Documents
Shahnawaz Report Print
Shahnawaz Report Print
Mission Statement
Mission
Our Mission is to provide our customers with high quality electricity and water
services, whilst creating value for our shareholders.
Objectives
Our objectives are to:
Efficiently meet our obligation to supply Qatars need for electricity and water.
Operate on a commercial basis.
Comply with local and international health, safety, and environmental
standards.
Maximize the employment of capable Qatari nationals and develop them to
the competence level of employees in leading international companies.
History
Introduction
Qatar General Electricity & Water Corporation,was established in July, 2000
further to the Emiri Law number 10, to regulate and maintain supply of
Electricity
&
Water
to
customers.
Since inception, Kahramaa has operated as an independent corporation on a
commercial basis with a total capital of four billion Qatari Riyals. Kahramaa
was mandated with several responsibilities and commitments, some of which
are:
Board Of Directors
Kahramaa board of directors comprises of Chairman, vice-chairman and
several members. The board is appointed for a four-year office term subject to
renewal by an Emiri decree, based on Kahramaa's law- article 7.
a. Jurisdictions
3) Outdoor Substation
4) Under ground cables
5) Over head lines - OH/L.
1) Primary Substation
Main incoming supply to the Primary Substation is fed from 66
KV system. Two main incoming transformers are generally provided to feed
the 11 KV Distribution system. 11 KV Bus is provided with a Bus
Coupler(A120) for oparational flexibility and is normally in closed condition..
All Switchgear panels for incoming feeders,transformers and outgoing feeders
are equiped
transformer and Voltage transformers are also provided in each circuit for
protection & metering. Earthing transformers are provided for stable neutral
and for station supply. Circuit breakers are of either VCB/SF6 / OCB types are
used.DC System is 110 V DC with Battery and Charger. The primary
substatoin are well equipped with Control panel,protection panel,Switch gear
panel
and Axilliary facilities. Local and remote control is possible for all
Safety Measures
All primary Substation are well protected from fire hazards.Co2
fire extinguisher system (auotamatic) is provided in Primary substation where
Cicuit Breaker is OCB.But in new phase v Primarys are commissioned with
SF6 as insulation medium.
Operation Control
A selector switch is provided in each panel to control the
operation of breakers from either locally or remotely (Grid). Normally the
Selector switches are in Grid position where Out going feeders are in DCC
control and Incomers and Bus Coupler are in NCC control.A Senior
Authorised person can change the Selector switch position for work only with
the consent of Contrl Engineers of NCC/DCC.
2) Indoor Substation
All Indoor Substations are well equipped with Switchgear panels
with Circuit Breakers,isolating & eathing facility,control and protection circuitry
and metering facility for the smooth operation and control of feeder and Local
distribution transformers. All Feeders and L/Tx are connected to the common
bus of the Indoor substation through the
Oil Switches:- Oil is used as insulation medium for breaking /making the load
current. All switches are rated for breaking/ making load current and not
intended to break /make the fault current.But for transformer circuit Oil Fuse
Switches (OFS) are parovided with Oil Fuses.In OFS a mechanical inter
locked over load protection is provided for tripping the transformer circuit
under
SF6 Switches:- SF6 gas is used as insulation medium in new outdoor s/s's
where the breaking / making of load current is through the SF6 gas insulation
medium. In SF6 O/D substations, for transformer Switches are normally
provided with the Time Lag Fuses (TLF) for tripping the circuit Breaker (TXS)
on abnormal condition. These fuses are provided in the secondary circuit of
the CT across a shunt coil. Normal condition the current will flow through the
TLF( low impedence path) Any abnormality comes the fuse will blown out and
it will results the flow of current through the shunt coil (high impedence trip
coil) which in turn trips the circuit breaker.Different types used are :Tamco
Merlin Gerin
ABB
W Lucy
substations in the Earth Fault Indicator circuit for indicating passage of the
Earth fault. In SF6 -O/D Substation , CT is required in the TLF protection
circuitry.
Types of Out Door substation
Extensible RMU
Package Substation
Extensible RMU
The outdoor substation with one RMU unit and which has a provision to
extend its Bus bar towards
Package Substation
In package substation where the RMU unit and FeederPillar
units are attached (Bolted) to the transformer and formed a single package
unit. HV and MV cables are not required for transformer.
Main Switch,Transformer Switch & Earth Switch
10
Main Switches are intended to making /breaking load current only and
there is no associated protection circuitry. These switches are not
designed to break / make fault current.
TX Switches are provided with Oil Fuse/ TLF for tripping the circuit
under overload / abnormal condition.
Inter locking
1) Inter locking facility is provided between Earth Switch ON and Main
Switch ON condition.
2) Inter locking facility is provided between Earth Switch ON and TX
Switch ON condition.
3) No inter locking facility is provided between Earth Switch OFF and Main
Switch /Transformer Switch OFF condition.
4) Opening/Closing of test plug is allowed only when the earth switch of
respective circuit is in ON condition. In SF6 RMU , the TLF compartment
also having the inter locking facility of this type.
5) Safety and normal operational locks are also provided to all switches.
11
Manual type Manual reset is required after the Flag ON condition due to fault
Auto type - LT supply is provided to EFI and it automatically reset the Flag
due to the fault after a delayed time period when supply resumed.
Gas Pressure Indicator for SF6 RMU
The Gas Pressure Indicator reading should be in the green zone for the safe
oparation of SF6 RMU.
Filling Pressure at 20 degree cent.- 0.4 BARG
Minimum oparating Pressure
Red zone
0.05 BARG
11KV HT Single run 3 core cable connect the TX Switch to the Transformer
Primary winding. MV cable Seven run single core (Double run for phases and
Single run for neutral) connect the Transformer Secondary to the MV feeder
piller.
Feeder Pillar
Bolt on Feeder Pillar(BOFP) 4 LT Out going Cables
Free Standing Feeder Pillar (FSFP)- 6 LT Cable Out going
MV panel could be mounted in two ways:1. As an attachement (Bolted) to the Transformer Secondary without MV
cables is called Bolt on Feeder Pillar(BOFP)
2. As a separate unit anchored to the ground and secondary of Transformer is
connected with MV cable called Free Standing Feeder Pillar(FSFP)
Special free standing feeder pillar Consumer FSFP and Special consumer
panel is available. 4 or 5 LT Out going Cables + Cable for one separate
consumer panel.
MV Panel - Components
MV link (R,Y,B &N)
Ammeter with Maximum Demand Indicating feature
12
In Feeder Pillar MV links are provided for LT Outgoing Cables (3 Phase 4 wire
with separate Earth wire ) HRC fuses are provided in LT cable for overload
protection rating depends on the load current. In some consumer MV panel is
available with ACB and REF protection.
- Separate earth pits are provided for LA,Pole Box and PMT
LT -
13
The working section should be dead , isolate & Earth at both ends
before doing any work
Main components
AB Switch (S)
Lightning arrester (LA)
Ploe Mounted Transformer (PMT)
Auto Recloser (R)
Pole Box
Flashing Fault Indicator (FFI)
Conductors & Earth wire
Air Break Switch - Designed to operate on load condition, AB Switches are
numbered in s- series. Oparating hand lever is provided on the botton of pole
with ON/OFF locking facility and can be lock off as a point of isolation.
For safety, open ABS and apply S/L and C/N & simillarly close ABS & L/OFF
Handle upward dirction
- ON
14
is
insulated oparating rod. The PE circuit consits of four wires and one lead of
each wire is connected together. Then first connect one wire to the Earth wire
and then the other three wires to R,Y,B, phases. After the work , the PE must
be removed fom the OH/L. While removing PE, first disconnect R,Y,B phases
wires and finally disconnect the wire from the earth conductor.
Pole Mounted Transformer (PMT)
Pole Mouted transformer (PMT) are transformer,which is mounted on an OH/L
pole PMT ratings are normally 100 KVA, 200 KVA and 500 KVA. Vector group
is Dynll.
15
Drop
Out
fuses
are
provided
for
the
transformer
Out going cable with Fuse Cut outs are used to feed the LT 3phase 4
wire system. Ratings available are 100 A, 200 A , 315 A .
Earthing arrangement for PMT Normally two Earth pits are provided,
one for ground /Body Earthing and the other one is for system neutral
earthing.
Pole Box
Termination in a pole which provides connection between OH/L
circuit and UG Cable circuit is called a Pole Box. The HT cable may be either
from any I/D Substation / Out Door Substation or from another OH/L portion
due to crossing of road / EHT line.
LA's are provided to protect the cable termination from lightning surges.
Auto reclosers
Auto recloser is provided to restore the service continuity after a
transient fault on OH/L. Faults which are not permanent called transient fault.
90% of the faults in OH/L are of transient nature, after a short time called the
dead time, the CB can be reclosed.
Auto recloser will trip the circuit for a fault beyond it (O/C or E/F) and it
save the healthy section.
Auto Recloser normally provided nearer to the AB Switch and that will
helps to isolate the faulty portion and there by restore the healthy
portion after opening the AB switch
CT's are also inserted with the Auto Recloser, to measure the load
current for protection.
16
Main Components
Battery 240/ 120 V AC is required to charge the battery.
VT
LA
497 MW
996 MW
RAS LAFFAN
756 MW
17
107 MW
473 MW
699 MW
SATALLITE STATIONS
i.
AL WAJBAH
ii.
SALIYAH
iii.
DSS
Q- POWER
TOTAL
3528 MW
Transmission network
Kahramaa transmission grid consists of the following voltage levels.
Transmission Network
220 KV
132 KV
66 KV
Distribution Network
11KV
0.433 KV
There are 100 Nos. of transmission substation out of which 90 Nos. are
Primary Substations. They are facilitating to feed 11 KV distribution systems.
The primary substations can be either any of the following type.
1. 220 / 132 / 66 / 11KV
2. 132 / 66 / 11KV
3. 220 / 66 / 11KV
4. 66 / 11KV
Demand Profile
The domestic consumption is more predominant in the system and domestic
load contributes major portion of the total demand. Remaining are industrial
and they contribute very less, near about 15% of the load (approx. 450
mw).Seasonal variations are predominant because of the extreme climatic
conditions. In summer, hot season begins from May September, the
demand reaches its maximum value But in winter season, (Nov- Feb), the
demand reaches its minimum value.
18
Two control
desks are available, they are (I) Generation Desk and the other is (ii)
Switching Desk.
(i) Generation Desk.
Controlling the Active and Reactive power flow to maintain the
system voltage & frequency to a predetermined value.
Act according to the surplus & deficit condition.
Act according to the abnormal condition.
Merit Order Dispatch is observed
Automatic Generation Control is in operation.
(ii) Switching Desk.
Coordinating & controlling to all Switching operations.
Give Sanctions ( PTW & SFT ) to all switching operation
Executing load rearrangement programmes during shut down /
abnormal conditions.
Arranging Periodic / Break down maintenance activities for the
network elements.
Frequency Control
Frequency is controlled by maintaining the balance between Active
power and Demand of the system. This is achieved by Automatic Generation
Control(AGC). AGC will ensure stable frequency by automatic adjustments of
generation in accordance with the system demand. AGC controls the active
power flow depending upon the current frequency.
Target Frequency
The system should run at a target frequency 50HZ with minimum deviation
(not exceeding 0.2 %) as far as possible to keep agreeable level of power
supply quality. The frequency band is 49.90 to 50.1 HZ .Beyond the set
frequency band, AGC change over to local. Participation factor percentage is
also selected to determine the degree of involvement of each generator unit in
the AGC mode of operation.
Minimum Spinning Reserve
19
AL SULAIMI
20
(local)
For Grid Transformer - control is done from the NCC (supervisory mode only)
- ON Load Tap changing is possible.
For Primary Transformer (66 / 11KV) Automatic control mode operation is
enabled with AVR(ON Load Tap Changing)
For Distribution Transformer OFF load, manual control only permitted.
When all the plants on bar (POB) are fully loaded and the
21
if necessary this is continued with next list and so on. Next load shedding list
for cyclic shedding is # 23.
Note: DCC should be informed before domestic shedding, and they inform the
stand by offices concerned. Maximum load shedding time is limited to 2 hrs.
First domestic load and then furnaces are restored and later import of energy
is stopped as frequency improves.
Condition 2 - A Sudden drop in frequency due to an unexpected major
generation loss. This is an unanticipated frequency drop situation.
Action required In this case automatic under frequency load shedding takes
place at various stages.
1. Automatic under frequency Bulk load shedding.
2. 11KV feeders at Primary s/s (domestic load) are kept selected at
predetermined frequency levels as below for automatic shedding.
Stage 1 A
Setting 49.2 HZ
Stage 1
Setting 48.8 HZ
Stage 2
Setting 48.4 HZ
Stage 3
Setting
48.0 HZ
Stage 4
Setting
47.8 HZ
Load shedding selector switch at the Primary's can be put in the desired stage
of under frequency tripping.
3. To improve MVAR levels during the under frequency tripping, reactors
are selected to be automatically closed during stage 2, 3, and 4.
4. First domestic and later the furnaces to be restored manually when
frequency improves.
Load Re arrangement
In order to meet the outage of network elements like Transformer, EHT line,
Bus section etc, the NCC may instruct the DCC to transformer load from one
Transformer to other or one primary to another primary.
Automatic Voltage Regulator
The voltage Band is 10.8 KV to11.20 KV, with a 100 second delay provides to
allow grid level restoration measures.
22
Objective
Monitors and ensures continuous electricity supply for the distribution
network, within the prescribed values of limit violations, giving priority to
security and safety.
Major functions
Controls Active & Reactive power flow in the network and there by
regulate the voltage.
Confirms to all the operation are done in strict compliance with the
department safety rules and regulations and there by ensuring system
safety and security.
Control , coordinate and direct to all switching operations by giving
instruction to field engineers for switching in the 11 KV network for
maintenance / repair of network components and for after fault
restoration.
Co-ordinate with NCC, in case of generation shortage or other system
contingency to shed the load in accordance to the prearranged
methods.
Issue permit to work (PTW), sanction for test (SFT) and isolation
certificate for work in distribution network and also ensure for proper
isolation and earthing by giving priority to safety and security.
Immediate restoration of supply after disturbance and there by limiting
interruption to the minimum.
Inform management about any abnormality & important events.
Co-ordinate with other department for the smooth and efficient
functioning of distribution Network.
23
Breaker status are transferred to DCC for monitoring and controlling. It also
provided alarm and limits violation condition to remind the Control Engineer to
act accordingly. The available data's in the DCC computer console can be
utilized to originate different report for the smooth functioning of DCC.
Available Data's & facilities
Loading Values of different Primary transformers.
Loading values of different outgoing feeders of PRY
Bus voltages of PRY
Breaker and VT status of PRY
Limit violation, alarm and important events.
All the data's available in the DCC console can be utilized for past and
present system analysis and also helpful for the contingency analysis. The
data's available in the database also helps to originate various technical report
& statistics.
24
Check whether all the safety aspects are taken care of before
execution.
Study the load rearrangement during the shut down, possible way of
back feeding, loading values of feeders and Transformers involved.
Check the load of feeders involved in paralleling at the time of
isolation and live phasing.
Analyze the paralleling involved in the programme and check
whether it is a bad paralleling or not.
Scrutinize the point of isolation, back feeding arrangement in terms
of system security and safety.
Study the loading condition due to the shut down and check whether
the shut down causes any overloading to any feeders and primary
transformers involved in the programme.
Check the substation planning Number and Name, Sequence of
operation and safety aspects related to the programme, date of
execution and duration of shut down etc.
Study the Live phasing route ,loading during Live phasing and
consumer effected (If any VIP Consumer is in the route of 11KV Live
phasing, then alternative path should he selected for doing the
same.
2. Activities on the day of execution
The verified switching programmes can be execute after considering the
following
Present loading of the feeders and transformers of the system
Present loading of feeders and transformers involved during isolation
(shifting load from one feeder to another) and during 11 KV Live
phasing.
Mostly the loading data's of Transformers and feeders are available in DCC
console except some PRY's. S.S.A can be utilized to collect the data's from
the PRY's where telemetry is not available.
Special care at the time of paralleling
Paralleling should be essential for NOP shifting and 11 KV Live phasing, while
paralleling, the following points to be noted.
25
After the work, DCC can advise the field engineer to establish new
NOP in view of load balance among feeders and Primaries.
3. Fault Restoration
Information about the fault is either any one of the following way
1. NCC will transmit the message if the standby Earth fault alarm initiated
at NCC or if the Primary Transformer CB tripped.
2. Alarm initiated at DCC telemetry console.
3. Information's from the call centre / stand by offices.
Action required:
If the CB of feeder at PRY has not tripped, then retrieve the past data
from data base and compare with the present load and calculate the
load loss. This load loss data will help to find out in which indoor the
tripping has occurred.
26
Collect all information from the SSA at site and from the Stand by
Engineer like relay indication, EFI status, station supply (Battery) and
abnormalities etc.
While test charging, keep the relay time setting to the minimum.
Isolate the faulty section, apply C/N, L/ off and apply CME at point of
isolation.
Inform the fault to the O&M section for repair and rectification.
Before test charging, if OH/L involved make sure that all of the OH/L
patrolling gang are away from the live system. This is confirmed by
direct contact with Field Engineer.
Give instructions as per the programme to the Field Engineer and ask
him to repeat the given instructions.
27
Always tell the name and planning No. of location and circuit to the
Engineer.
Before issuing PTW and SFT confirm that the working section is
isolated, Earthed at both ends. And also confirm that the S/L and C/N
applied at the point of isolation.
Rack out VT from the line only after isolating both ends. And VT should
be rack in before energizing the cable. VT status should always confirm
before energizing the circuit.
After isolating a circuit breaker (Rack out) always instruct the Field
Engineer to do Trip Test for the CB.
Before earthing a section, confirm that the section is dead and isolated.
Apply CME at both ends to a faulty section after isolating both ends.
Also apply S/L and C/N.
28
A field engineer can't hold more than one SFT at a time. SFT is issued
by the field engineer to himself and his direct supervision involvement
is required to perform the test.
The field engineer can't suspend the SFT. He has to cancel SFT before
he leaves the site. Any inconvenience occurred to complete the test,
then he should cancel the SFT and also confirm the switching positions
before the leaving the site.
29
In case of PMT, remove the HT fuse and then adjust the tap
position as required.
NOP Shifting:
Paralleling between same or different sources is required
Different Situations:
During shut down works to back feed the load to avoid interruption.
Protection status
Cable length
2. Abnormality Report
Any abnormality / tripping happened in the system should be recorded in the
Station Log and also prepare an abnormality report of the incident with details
in a prescribed form.
30
31
section after obtaining the proper consent from governmental authorities. ROA
wing should arrange the approval from the governmental agencies (Qtel,
Sewerage, Civil engineering Department, Road Division and Water
Department of Kahramaa).
Estimates the material requirement and coordinate the same with the
suppliers & ABUHAMUR work shop
Allocate the work to different contractors and coordinate with them for
final execution.
The single line diagram with all details (substation type ,cable length &
type , transformer capacity & Nos ) of the existing network and the
proposed alterations should be send along with the switching
programme to the DCC for concurrent and comments in advance
(before 48 hrs ). Keep a copy of the same ( switching programme &
drawing ) for reference & execution
Commissioning
32
The system control engineer should arrange for possible back feeding
and load transfer in order to avoid interruption during the execution of
work.
Check the new label and fix it properly and confirm the same to
control (DCC)
After checking all the safety aspects, the Construction Engineer can
commission the new s/s with proper consent from the System Control
Engineer.
-
If all the above checks are satisfying, then Commission the new system.
33
1. Cable Identification.
2. Spiking
3. Colour phasing ( core phasing )
4. 11 KV Jointing work & Termination work on HT cable )
5. HV pressure test for 11 KV cable and Bus Bar
6. Dead phasing check 11 KV system
7. Live phasing check - 11 KV system
8. Phase rotation check for MV side.
9. MV voltage check.
10. Trip / test check for CB.
11. Relay inter trip check
12. Transformer, Switchgear panel, Switches and Substation observation.
13. Relay setting & fault level.
Cable Identification
During construction and maintenance, the existing cable has to be cut
for fault rectification and for commissioning new substations in between the
existing cable. Then the Field Engineer should confirm the cable which is
going to be cut is the same cable that he isolated and earthed for doing the
work. This is required only where more cables are present with the isolated
and earthed cable. Any mistake will leads to danger to human life and to
system safety. So before doing any work on cable (joints), the field engineer
should always identify the cable by using proper methods.
Safety measures
The cable has to be dead, isolated and earthed at both ends as
per the switching programme and with proper consent from
System Control Engineer.
SFT is required and is issued by the Field Engineer to himself
with consent of system control engineer.
Senior Authorized Person in charge of the work has the full
responsibility of the operation and test
Method
The Identifier kit consists of an Audio Transmitter and Receiver set, by which
the signal generation and reception is possible. For cable identification test,
connect the Audio transmitter between any two phases of the isolated cable
34
after removing the earth. Keep remote end of cable as earthed for return path
.Then by using the Audio receiver and head phone, we can identify the cable
in which signal is generated. When the receiver is put nearer along the cable
gives a clear beep but varying sound from the cable trough which transmitted
the signal. Sound variation is obtained only from the injected cable due to the
twisting of cable pairs. But for other cables, humming sound is obtained from
live cables and clear beep but not varying is obtained from dead cable if any.
The Cable Identification test is done by the field engineer himself in charge of
work. See the figure.
Spiking
After identifying the cable, before cutting, spiking has to
require for 100% confirmation that the cable is absolutely dead and safe for
cutting. Spike gun is a special arrangement, where the iron bullet is used for
firing. The spiking gun with bullet is placed over the cable and firing is done
remotely with the help of a rope. If the cable is the correct one, there is no
heavy sound. But for live cables heavy flash over and tripping may occur.
Thus spiking will helps to avoid dangerous situation and it provide more safety
to the working personnel's.
Safety measures
After spiking, the cable has to be cut and prepare ends for phasing PTW is
required for any work on cables. But this is a lengthy procedure which can be
reduced subject to pre conditions detailed on Kahramaa S.O.M. No.7.
Colour phasing / Core phasing Phase identification check
During construction / maintenance, cable jointing, break and make termination
works are required. Due to straight jointing perfection and easiness, human
errors and termination difficulties, there may be a chance of colour crossing
while doing cable works with respect to the system colour. So colour phasing
is required during termination & jointing work and is the process of identifying
the 3 phases of system with the 3 core of the cable. Incorrect phasing cannot
be parallel with other systems. So colour phasing is more essential for all type
35
36
together for same point of isolation is not permitted. If PTW is issuing after the
SFT, then the Control Engineer should always confirm the switching position
and also confirm that both ends of the cable is isolated and earthed.
Competent person - Kahramaa certified HV Cable jointer / Fitter with
Identity card of Kahramaa
Dead joint
37
11 KV DC (Negative)
+11 KV)
Duration - 15 Minutes
Apply 22 KV DC between R&Y phases for 15 minutes. And repeat the same
test for the other two combinations (R-B & Y-B)
Safety during pressure test
SFT is required for doing Pressure Test.
Before doing Pressure Test, remove all type of earth applied for the
section.
Inform to all the personnel working at site about the test and keep
them away.
The field engineer responsible for the test should confirm that all newly
constructed / repaired elements including Bus Bar, cable joints,
termination are subject to the test.
38
After the Pressure Test, the SFT taken should return and cancelled
with the consent of system control engineer. Confirm switching
position is mandatory.
11 KV DEAD PHASING
This is a method of checking R, Y, B, phasing of the newly constructed
elements from known end to the other end before live phasing. Dead phasing
will not disturb the existing system. This is a pre - confirmation test before live
phasing.
11 KV LIVE PHASING
After all type of constructional / maintenance activities on cables,
terminations, the 11 KV live phasing is required. This is essential for meeting
same RYB sequence condition before paralleling between two systems. It
always conducted at I/D substation and it prove that the added network
elements in same phase sequence with respect to the existing. The I/D
Substation nearer to the newly commissioned Substation should be taken in
order to minimize interruption to the consumers.
Live phasing proving the there statements below:R phase is connected to Existing System R phase
Y phase is connected to Existing System Y phase
B phase is connected to Existing System B phase
At the time of live phasing, we have two different sources from two stations
and is available at the Bus Bar spout and Cable spout in an Indoor S/S. One
is the existing supply source of I/D substation where the live phasing test to
be carried out and is available at the Bus Bar spout. The other one is the
existing supply taken through the new circuits (includes all terminations, cable
joints, and Bas Bar except the transformer circuit) and is available at the
Cable spout of the Indoor S/S.
Live phasing sticks
Live phasing is proved by measuring the voltage between the phases
available at the Bus Bar spout and the Cable spout. Live phasing sticks
consists of two sticks connected in a special manner with a Voltmeter and one
is inserted in Bus bar spout and the other is inserted in the Cable spout during
the test. The Voltmeter measures the potential difference between the Bus
39
Bar spout phases and the Cable spout phases. While observing the live
phasing between the two system available at Bus bar spout &
Cable spout, for correct live phasing the voltage should be as follows:R of (Bus bar spout) to R (Cable Spout) 11 KV
Y of (Bus bar spout) to Y (Cable Spout) 11 KV
B of (Bus bar spout) to B (Cable Spout) 11 KV
R of (Bus bar spout) to Y (Cable Spout) 5.5 KV
Y of (Bus bar spout) to B (Cable Spout) 5.5KV
B of (Bus bar spout) to R (Cable Spout) 5.5KV
If any mistakes happened during work, then the voltmeter will indicate
incorrect reading. Then the Field Engineer should rectify the mistake.
At Indoor substation, the CB towards the new circuit should be kept opened.
Then Bus Bar spout is having the existing supply and cable spout is having
the existing system through the new circuit. By inserting live phasing sticks
between bas bar spout & cable spouts, we can confirm whether the live
phasing is correct or not.
Safety during live phasing
Include all the terminations, cable joints for checking the live phasing.
Some times including all joints and termination together is not possible
at that time check separately for different routs.
Make sure that all the newly constructed /repaired circuit is included in
the test and have the same phasing with respect to the existing system
phasing.
the
Field
Engineer
and
System
Control
Engineer.
40
bad paralleling etc. We can conduct live phasing at any I/D substations
( existing or new one )
If the supply is taken through the new circuit includes an existing O/D
substation, then the existing and new phase rotation has to be check
for consumer safety.
R-N
Y-N
- 240 V
B-N
R-Y
B-Y
- 433 V
R-B
Safety
Keep the MV side link / ACB as open during the phase rotation and MV
voltage check.
41
- Oil check
- Tap position (nominal 3).
- Termination (MV & HV)
- Name plate details (Rating and % Z)
Circuit Breaker
- fault level
- Operation check.
42
- Circuit labeling.
- Meters to be check for its functioning.
- provide operational locks.
- relay setting & trip circuit status.
system is always in
43
i.
ii.
locate the cable fault. After finding the fault, the field engineer has to
arrange the excavation team and the cable jointer. After repairing he
has to restore the supply.
All these above discussed activities should be coordinated by the
senior Engineer of O&M and shall comply the safety practice and Operation
Memorandum of Kahramaa. The interference to the live system is permitted
only with the proper consent from the System Control Engineer on duty
44
) the field
engineer should obtain proper consent from System Control Engineer (DCC).
Immediate supply Restoration:Immediate supply restoration always gives better service to
consumers and is important in distribution system. The kahramaa distribution
system has adopted an efficient and effective way for overcoming the
emergency breakdown condition. The field engineer are posted on a round
the clock rotation basis for the stand by duty in order to attend the emergency
tripping conditions and restoration thereon. During the tripping and emergency
condition, the system control engineer should co-ordinate and directs the field
engineers for immediate restoration. The system control engineer should
direct and co-ordinate by giving instructions to the field engineer as per the
relay indication and other field information. First, he should find out the faulty
portion and then isolate it from the healthy system and then restore the
remaining healthy system as early as possible. After that, DCC Control
engineer has to direct and coordinate the field engineer to rectify the faulty
section as early as possible. All the above switching operation must be done
according to the safety rules & as per the Operation Memorandum of
kahramaa.
The stand by offices staff provides assistance to locate the fault during the
restoration process. Along with the stand by office staff, kahramaa has
substation attendants who comes under NCC and posted to some Primary
Substations. The SSA also provides necessary assistance during a fault or
system disturbance. Apart from the above, kahramaa providing stand by
diesel generators, this is capable of delivering power to the interrupted
consumers. DG Set allocation is mainly depends on the duration of
interruption and the nature of consumer.
Load re- arrangement (NOP Shifting)
As discussed in the introduction, in kahramaa distribution system, the open
ended Ring main system (Ring off with NOP) is mostly used. NOP is the
normally opened points in the 11 KV Distribution systems and is shifted to
transfer load from one primary to another or shifted load from one feeder to
another feeder of same primary. NOP is provided for the smooth operation of
system grid and for operational flexibility. Closed Ring operation is also
45
provided for some important distribution consumers. But mostly all I/D and
O/D substations are feeding from one source at a time and there is always
one or more alternative sources (either from same or different PRY) are
available as NOP. Some Radial feeding s/s and multiple source feeding s/s
are also available (same primary). The location of NOP decides the loading of
the 11 KV feeders which in turn reflects the loading of the transformers of the
Primary Substation.
NOP shifting will always helps to balance the loading among 11 KV feeder/
primary transformers and also helps to back feed the system at the time of
supply failure. There NOP shifting can be execute either by a pre-planned
manner (prior switching programmers) or for an emergency situation like over
loading / tripping of feeder / transformer (PRY). If it is in urgent nature, then
the field engineer on stand by duty has to attend the NOP shifting. The preplanned NOP shifting programme is normally executed by the field engineer
on system operation duty.
For system operation load shifting (NOP- Shifting), the DCC
should prepare the switching programme and the switching is
done by the field engineer.
repair
maintenance
activities
for
switch
gears,
panels,
transformers, switches etc are done at this work shop. There are different
section are working under the Head of workshop. The man power for the O&M
activities and constructional activities are also supplied from this work shop
.Round the clock duty is also available for some important areas.
Fitting Section
OHL Section
Cable section
Diesel Generator section
Stand by Offices
46
- Primary substation
-Collecting informations from the different sites as per the requirement
of NCC/DCC.
Switching Programme
A group of sequential operation and activities required to avail shutdown for a
live system to perform some operational, repair / Maintenance work and to
energize back the system to normal after completion of work.
Switching Programme Form
Operation No
Location
Circuit
Operation
Time
Initial
Work Execution
For
arranged
work
like
preventive
maintenance,Corrective
47
programme after obtaining proper data from DCC and send to the DCC
prior to the execution(48 hrs before).
For emergency break down / tripping work the field engineer should
operate according to the proper instruction from control engineer on
duty ( DCC).
48
49
Other Relays
Master trip Relay-All relays are wired to the master trip to initiate the tripping
signal for Circuit breaker. Type F8H trip relay.
Pilot wire inter trip Type TEC Relay
Pilot wire protection sustained inter trip -Type TC-5
Earthing transformer and system protections
Since the Primary transformer is star delta, an Earthing transformers OF 500
KVA with Zig Zag winding is used on the 11 KV side with tertiary delta
winding.
Tertiary 166.6KVA
11/0.415KV
Percentage impedance 4.23 %
Impedance per phase is 27.5 ohm
Maximum fault current for 3 seconds is 750 A
Earthing transformer is required for the following purposes
The earthing transformer is mainly used for the earthing purpose. It
creates an artificial neutral point on the delta 11 KV side winding.
Used to limit the fault current to a maximum of 750 Amps
Used for the purpose of SBEF protection and also for the REF
protection
50
51
52
send blocking signal, PBDP (50 high set)will trips the LV ,HV side breakers of
transformer along with the Bus coupler breaker.51 elements act as a back up
protection for the feeder
Grading
50element -100 milli sec time delayed operation.
51element (O/C) graded with the feeder IDMT O/C and TX HV side O/C
(Time grading only possible - 300 milli sec)
51 element (E/F) - graded with feeder E/F (IDMT) and SBEF
(Magnitude grading only possible)
CT is -2000/1; current setting is normally 7% (300 m sec time grading)
Primary substation feeder protection
Normal protection scheme consist of the following relays.
1. Pilot wire protection
2. Standard IDMT Relays (2 O/C +1E/F)
53
The padding Resistance to set to a value such that, the total loop
resistance of the pilot wire cable is 1000 . Let RL be the Pilot wire
lead resistance. There the padding resistor to be provided at each end
is , RP =1000-RL (RL is normally about 10 ).
Pilot wire supervision relay is also used to detect any fault in the pilot
wire circuit and for any type of fault in the pilot wire
SOLOKOR R unit protection acted and the Feeder trips only at receiving end,
it can be assumed that it is pilot wire problem and in this Situation, the feeder
not to be put in service until the Pilot wire unit protection is decommissioned.
The sending end of the feeder Tripped on SOLKOR R unit protection but no
tripping at the receiving end. Then in this situation the feeder not to be put in
service until the 11kv cable is
on the Cable, then the feeder to be charged from the sending end.
54
100 milli sec 300 milli sec delayed operation is provided for this type relay in
order to avoid tripping during heavy inrush currents (100 m sec 300 m sec) is
the decaying time required for inrush. In some cases, SOTF protection is also
provided with Harmonic Restraint feature (100 millisecond delay ) or with out
Harmonic Restraint feature (300 millisecond delay ). The 2nd Harmonics from
magnetizing inrush currents or switching surges will decay with in 300 milli
second.
51- Normal IDMT element with grading.
Stage-2
50 element - Initiate blocking signal to the Partial Bus bar high set element
and the signal will reach within 60 milli sec. during a fault in the out going
feeder. The High set element of IDMT relay is not used for tripping but it
sending blocking signal to the partial Bus bar relay.
Relay Operation
For Three phase balanced fault R&B O/C relay will operate.
For Three phase earth fault
Phase to phase fault
IDMT act as primary protection in feeders where pilot wire protection not
commissioned. If an Out going feeder is commissioned with pilot wire
protection, then the IDMT relay act as a back up protection.
Protection used in Indoor Substation
Feeders-1) Standard IDMT relay (2O/C(R and B phases) +1E/F(Y phase))
Induction type TJM10 and Static relay-MCGG52
2) Pilot wire protection - SOLKER R instantaneous tripping
Pilot wire protection (SOLOKOR R) is provided in cables between two
indoors and also provided between the Indoor and Primary s/s.
Bleed off feature is available for 20% of the cable full load. That means
for a 300 ampere cable, 20% bleed off is allowed (60A).
Transformer protection 11/.433KV
HV side is protected by EIDMT O/C & E/F protection with separate
High set instantaneous element for O/C and E/F.
55
From first indoor the current setting is fixed as 100% for O/C and 30% for E/F.
Then the protection is graded by time and always keeps a grading margin of
0.125 TSM to avoid false tripping. The maximum grading stages allowed is 3.
Protection used in Out door Substation
Feeder
- no protection is available
- EFI is provided to identify the path of earth fault current.
Transformer
56
CT Ratio
TLF rating
Max.distributor
KV
KVA
A
11
200
50/5
160
11
300
50/5
250
11
500
50/5
7.5
315
11
800
50/5
12.5
400
11
1000
100/5
7.5
500
11
1250
100/5
10
630
11
1500
100/5
12.5
630
11
1600
100/5
12.5
630
- Directional relay(67)
Closed Ring
Protection schemes required for a closed ring system are as follows
Pilot wire protection (SOLKOR R-type) should be commissioned before
closing a Ring system. Ring splitter should be provided in order to separate
the ring at the time of tripping of Bus coupler CB by the operation of
PBDP/SBEF protection during the fault. Ring splitter is an IDMT relay with
current setting 100% for O/C and 20% for E/F element. The time setting
should be minimum (0.1 TSM)
OR
IDMT (2 O/C+E/F)
57
IN OH/L, the earth path resistivity is very high and then the normal E/F relay
will not detect the earth fault of the system. To overcome, this condition OH/L
are provided with sensitive earth fault relay (current setting is 3% with a long
definite time lag of 3 seconds).
CT Ratio - standards
Primary substation
LV side of TX and Bus bar - 2000/1 for PBDP
-2000/1 for D O/C and D E/F
Out going Feeders
Earthing Transformer
Indoor substation
Feeders
metering.
Transformers -
- 5P10, 15VA
- Class 1
- 110V DC
- 30V DC
General Informations
Location map
NO P Shifting
System Safety.
58
59
where the circuit on which work is to be carried out could be energized. The
keys for such locks shall be kept in a key safe, if provided, or in some other
safe place preferably in the possession of the Senior Authorized Person in
charge of the work. See Kahramaa Safety Rules12.3
Locking facility available for Indoor VCB
Earth Switches
Panel Door
Without opening the OCB, the inter locking lever will not be
disengaged.
The Isolating lever entry is possible only when the OCB/VCB in opened
condition.
Closed condition of Earth Switch will not permit to Rack in UCB into
Service position.
When VCB is in Service position, the Earth Switch closure not allowed.
60
substation.
(First
switch
off
the
substation
where
61
identification failed and then close the main switch one by one. Then
identify the circuit from the feeding source by checking the station
supply.)
Pot End & Cap End Cables
Pot End ( P.E ) - Idly charged cable without connected load.
One ends of the cable is connected to the 11KV Bus and the other end is kept
free ( not terminated but the terminals are made and covered with a pot
termination kit ). Pot End cable is idly charged from one end.
Cap end ( C.E ) - Earthed Cable
One end of the cable is connected to the 11 KV Bus and the other end is kept
free, not terminated but only covered with a cap. The cap End cable is always
in earthed condition from its 11 KV Bus side.
Parallel Operation
Condition for parallel operation of two systems
1. frequency,
2. Voltage and
3. Phase sequence should be same
In Kahramaa, QGEWC system, the frequency is same. There is no
interconnecting system. The phase sequence can be correct is there any
mistake. Then the only one depending variable is voltage. So, the voltage
variation between the two sources for paralleling should keep as minimum
within the prescribed limit. So before paralleling, the voltage of the two
sources should be same as possible by adjusting the tap position of tap
changer.
Parallel operation of transformers
The five essential condition to be satisfied are that they should all have the
same.
Polarity
Voltage ratio
Percentage impedance
Phase rotation.
Identical vector diagram and phase displacement.
Active and reactive power transfer
62
Percentage
impedance of the transformers are different (iii ) line impedance up to the load
from the sources are different due to the difference in length .
Tap Blocking
At the time of paralleling, the tap position should be normal to all
transformers to avoid the voltage difference. The voltage difference is not
advisable for healthy paralleling. So blocking of tap is required at the tune of
63
Vertical isolation.
1. Service position -
transformer circuit when OCB is in closed condition , the live Bus bar is
connected with the feeder / Transformer.
2. Circuit Earth Position ( CK/E )
OCB provides connection facility between feeder / transformer circuit and
earthing system (station earth) .When OCB is in closed condition , the feeder /
transformer circuit is in earthed condition.
3. Bus bar Earth Position
OCB provides connection facility between Bus bar and earthing system. When
it is in closed condition ,the Bus bar is earthed.
Vaccum Circuit Breaker - Horizontal isolation
1. Service position
VCB provided connection facility between Bus bar and Feeder / Transformer
circuit.
2. Isolated / Tested Position
This is Rack / out condition, that means disconnected from the live system.
Commissioning
of
new
Eng: Dharam
and
earthed
as
per
to
make
and
break
(2
No)
64
TAMCO VCB
s/s
(11325-
I/D).
Commissioning
Eng. Dharam
1250
of
KVA
new
transformer, earthed
as
isolated
per
Issued
and
switching
SFT
to
RMU is TAMCO ( SF 6 )
rated current 630A, Rated short (1 No) straight joint for the new
time breaking current = 20 KA for 3 substation, cancelled PTW. Issued
Sec
at
9935- I/D.
done
at
9935
Live
I/D.
06-06-2006
Eng.
Choudary
identification,
spike
and
color
65
07-06-2006
Eng Nizamudeen
in between 4180 (O/ D) and 4160 programme. Isolated & Earthed the
(O/D) substation.
working
section
at
both
end.
checking
voltage
Normalized
the
&
existing
phase
the
system
establishing NOP.
08-06-2006
12-06-2006
Eng: Dharam
Extensible type.
66
Extendible type
confirm
SW/P.11
KV
Live
13-06-2006
Eng. Nizamudeen
10313 KR 6 O/D and to close the both ends. SFT issued for colour
ring with spare cables of 10313 KR- phasing. cancelled SFT , PTW
6 O/D between 9787 KHORE EAST issued to make 3 Nos ( Break and
-5 and 10319 KHORE SOUTH O/D
After MV check and phase rotation between 10319 KR-9 O/D and
commissioned the s/s and TX's.
SFT
for
HV
P/Test,
Naeeja North PRY ( A 200 ) and ( applied CME at both ends. SFT
0534 ) OAP 8 I/D.
VCB
at
Naeeja
PRY
SEIMENS.
SFT
for
HV
P/Test,
67
Replacement of SPAJ135C by
Eng. Shahul
19.06.2006
Attended
With technicians
Primary
magnetization
injection,
Trip
test,
circuit
Eng. Shahul
SIEMENS-SIPROTEC-7SJ61
2.Indoor substations
21.06.2006
With technician
KVA)
CT Ratio changing
22.06.2006
Saliya
With technician
operated
25-05.2006 to
NCC
01.07.2006
Transmission protection
Commissioning
Eng. Murali
02.07.2006
AL SADD PRY
28.06.2006
Eng. Salim
03.07.2006
Eng. Sherrif
04.07.2006 to
06.07.2006
Transmission O&M
Relay maintenance
69
Mr. Raju
Work
Remark
Replacement of faulty TX4 (Due to oil leak )at VCB TAMCO
(9649) City Centre -1-1/D
E/S available for each
circuit consumer MV panel
VCB TAMCO
with ACB available and REF
realy provided for MV side
protection.Inter trip for HT is
provided.Before
restoring
MV
side,Checked
MV
voltage & Phase rotation
Safety
Operational safety as per
switching
programme
instruction from system
control engineer.
After proper isolation &
Earth, issued PTW for
Break and make 11 KV
termination.
1.Replacement of faully TX (Due to oil leak)at O/D extensible RMU ( oil ) Operational safety as per
an O/D substation.
Yorkshire type.
SW/Programme
PTW issued for break
and
make
HT
termination to New TX.
2.Replacement of transformer(BOFP) by a Semi Extensible RMU ( Oil Operational safety as per
New TX ( FSFP) at an O/D substation.
).
SW/Programme
Before restoring MV side PTW issued for break
checked MV voltage
& and
make
HT
phase rotation.
termination to New TX.
70
Date
23.05.06
Engineer
Mr.Rajivkumar
Work
NOP shifting programme to
Load DUHAIL PRY
system operation duty.
Remark
Safety
3nos1/D&5nosO/D Substation visited as a Operation as per system
part of NOP shifting.
control
(
DCC
)
VCB - EPE, TAMCO
switchihng programme.
OCB - south wales
Confirm
supply
is
RMU important
in
each
operation.
24.05.06
Mr. Hakim
25.05.06
Mr. Raju
(Stand by Duty)
Fault restoration
SFT & PTW issued for an HT Cable
between NDC,PRY & an I/D S/S
Issue
SFT
for
Identification,
Spike&
Colour phasing .
Issue PTW for one
termination & one No:
ST joint nearer to 5716
O/D
Issue
SFT
for
spike,colour phasing the
cable.
Issue PTW for straight
joint the cable
27.05.06
Mr. Raju
28.05.06
Mr. Mahmood
11 KV OHL MaintenanceRedial circuit from ( 9757 ) new Al Qayan RMU at O/D s/s is
O/D
( Al Khore lnd.Area)
SF6 ( TAMCO )
Replacing ABS (S-144 ) , (S- 145) & 8
Nos. LA installation at Pole box and PMT
29.05.06
Mr. Inose
30.05.06
Mr.Rajivkumar
31.05.06
Mr. Hakkim
2.Fault restoration
KHORE A300- tripped at an 1/D
substation, the OHL lodial line ( with two
TEE off -circuit ) Total supply failure.
Indication - stand by E/F flag ON at PRY
and alarm initiated at NCC for both TX
01.06.06
ABU HAMUR WORK SHOP VISIT
2) Fault restoration
Industrial area 1671- MI 1/D
Substation, one TX ( 500KVA ) tripped
on over load
TX -replaced by ( 1000 KV )
one
No.
Jumper
connection and for raise
the Pole box. 72
1/D E/F relay operated
Noticed all indication
EFI flagged at one pole Box(Radial TEE- and
after
proper
off circuit )
petrolling found that the
earth
wire(1
span)
snapped in the radial
TEE-off circuit.Isolated &
earthed
the
faulty
portion. Then charged
the healthy circuit from
the 1/ D (All Relays and
indications resetted.Kept
the relay setting TSM
minimum
for
test
charging.).PTW issued
Hands on training on different types of for fault rectification.
switches ( Oil & SF6 ), VCB & OCB'S
Issued PTW
for
transformer
Indication R&B O/C
replacement.Informed
protection department to
change
the
relay
settings.