Professional Documents
Culture Documents
Au5 Online Operating Manual
Au5 Online Operating Manual
M AN U AL
Revised By
: G.SRINIVASAN (SPNE)
CHECKED BY
Approved By
: P.V.SOLANKI (CPNM)
GUJARAT REFINERY
PREFACE
The unit has been revamped during August/Sept 02 to modify the flexibility of operation
by installing new preheat train and increase in the number of pumps for different products
& circulating refluxes.
This operating manual contains necessary guidelines for normal operation and emergency
procedures such as startup, shutdown and different emergencies and is supplemented with
write-ups, drawings etc. wherever necessary. The various operating parameters are
indicative only. It may call for any modification or change in operating parameters based
on the actual operating experience in near future. The operating manual was updated in
May-05 and various changes were incorporated such as shut down & start up checklists,
PSVs list, unit equipments list etc., for fusing the plant related information.
In revision March09, special attention was given for startup, shutdown and emergency
handling procedures. It was thoroughly revised & step-by-step procedure was given for
easy understanding. New chapters on Safety System, Control Valve Data and Advanced
Process Control have been added. Control valves fail safe position and Operation and
Maintenance of HSD Coalescer has been incorporated in this manual for better operation
guidance. In this revision Dechocking procedure of equipment drain line is incorporated.
LPG Vapouriser to MSQ and Light Naphtha from AU-V to AU-I rerun section lines were
commissioned and that has been incorporated in the revised manual.
Inter connections and routings under RUP PROJECT has been incorporated in this
revision ( May , 2011)
Following modifications were done during APRIL-2013 M&I and the same has been
incorporated in this revision .(SEPT-2013)
a) Relocating of EE-06A/B from downstream of desalter to upstream of desalterThe above change was done to increase the desalter inlet temp.for better
separation.
b) A new hook-up has been made in the main F.G header line of AU-5 at B/L to
MSQ UNIT .in addition to the existing line.
The above mentioned modification was done to ensure the un interrupted
supply of F.G to MSQ unit.
c) Back washing system is provided for all the overhead condensers of both columns
C-01& C-05.
The main aim of the modification was to increase the performance of the
condensers especially during summers & and to avoid fouling.
d) A new hook-up has been provided in the following exchangers
EE-20, EE-12A/B/C& EE-13D/E/F .
The purpose of the above modification is to increase the preheat of wash water
To desalter, utilizing the HEAVY NAPTHA Rundown temp
e) MOVs were installed in the following under mentioned locations.The objective is to
ensure the safe isolation during emergencies.
i)
P.V.SOLANKI
CHIEF PRODUCTION MANAGER
GR-1 UNITS,
AU-5.
CONTENTS
Sl. No
DESCRIPTION
Page. No
Chapter 1
BASIC PRINCIPLES OF DISTILLATION
9-15
Chapter 2
INTRODUCTION OF THE UNIT
16-25
2.1
ONSTREAM FACTOR
17
2.2
DESIGN FEED RATE
17
2.3
FEED & PRODUCT SPECIFICATIONS
18
2.4
FEED & PRODUCT BATTERY LIMIT CONDITIONS
22
2.5
UTILITY SPECIFICATIONS
23
Chapter 3
EQUIPMENT DATA
26-37
3.1
COLUMNS
27
3.2
HEAT EXCHANGERS/COOLERS/CONDENSERS
27
3.3
PUMPS
1
28
3.4
FURNACE/AIR PRE-HEATER
29
3.5
TURBO BLOWERS (ID & FD FANS)
29
3.6
VESSELS
30
3.7
TANKS
31
3.8
FILTERS
31
3.9
PSVS
31
3.10
TSVS
33
3.11
LIST OF CONTROLLERS
35
Chapter 4
PROCESS DESCRIPTION
38-100
4.1
BASIC OPERATIONS INVOLVED
39
4.2
CRUDE CHARGING INTO UNIT
40
4.3
CRUDE PREHEAT TRAIN-I
41
4.4
CRUDE DESALTING
42
4.4.1
DESALTERS OPERATION
43
4.4.2
DESALTER WATER SYSTEM
48
4.5
CRUDE PREHEAT TRAIN-II
49
4.6
FURNACE
50
4.6.1
PROCESS SYSTEM
50
4.6.2
FUEL SYSTEM
52
4.6.2.A
FUEL GAS SYSTEM
53
4.6.2.B
FUEL OIL SYSTEM
54
4.6.3
AIR PRE-HEATER (APH)
55
4.6.4
COMBUSTION AIR SYSTEM
55
4.6.5
ID/FD FAN STARTING & STOPPING PROCEDURE
56
4.6.5.1
ID FAN STARTING PROCEDURE
56
4.6.5.2
ID FAN STOPPING PROCEDURE
56
4.6.5.3
FD FAN STARTING PROCEDURE
57
4.6.5.4
FD FAN STOPPING PROCEDURE
58
4.6.5.5
FURNACE LIGHT UP & CUTOFF PROCEDURE
59
Sl. No
DESCRIPTION
Page. No
4.6.5.6
FURNACE CUTOFF PROCEDURE
60
4.6.5.7
FURNACE INTERLOCKS
61
4.6.6
DECOKING SYSTEM
63
4.7
MAIN ATMOSPHERIC COLUMN
64
4.7.1
FLASH ZONE
64
4.7.2
OVERHEAD SECTION
65
4.7.3
MIDDLE SECTION
66
4.7.4
BOTTOM SECTION (RCO CIRCUIT)
67
4.7.5
CIRCULATING REFLUXES/PUMP AROUND CIRCUITS
6
68
4.7.6
PRODUCT DRAW OFF TRAYS
68
4.8
PRODUCT STRIPPERS
69
4.8.1
HEAVY NAPHTHA STRIPPER
69
4.8.2
KEROSENE/ATF STRIPPER
70
4.8.3
GASOIL STRIPPER
71
4.9
NAPHTHA STABILISER
73
4.10
LPG-AMINE ABSORPTION SECTION
76
4.11
PRODUCT COOLING & RUNDOWN FACILITY
7
77
4.12
CAUSTIC/WATER WASH FACILITY FOR PRODUCTS
79
4.12.1.A
LPG CAUSTIC WASH SYSTEM
80
4.12.1.B
LPG WATER WASH SYSTEM
81
4.12.2.A
LIGHT NAPHTHA CAUSTIC WASH SYSTEM
82
4.12.2.B
LIGHT NAPHTHA WATER WASH SYSTEM
84
4.12.3.A
KERO/ATF CAUSTIC WASH SYSTEM
84
4.12.3.B
KERO/ATF WATER WASH SYSTEM
86
4.13
CHEMICAL INJECTION FACILITIES
8
87
4.13.1
CAUSTIC INJECTION
88
4.13.2
AMMONIA SOLUTION INJECTION
89
4.13.3
DEMULSIFIER INJECTION
89
4.13.4
CORROSION INHIBITOR/AHURALAN SOLN. INJECTION
89
4.13.5
WASH WATER SYSTEM
90
4.14
EFFECT OF OPERATING VARIABLES
90
4.14.1
DESALTER PARAMETERS
91
4.14.1.A
WATER INJECTION & PRESSURE DROP
9
91
4.14.1.B
OIL/WATER INTERPHASE LEVEL
91
4.14.1.C
DESALTER PRESSURE
92
4.14.1.D
DESALTER TEMPERATURE
92
4.14.1.E
DEMULSIFIER INJECTION
92
4.14.1.F
VOLTAGE & AMPERAGE
92
4.14.2
FURNACE COIL OUTLET TEMPERATURE & OVERFLASH FLOW
93
4.14.3
MAIN FRACTIONATING COLUMN PRESSURE
93
4.14.4
MAIN FRACTIONATING COLUMN TEMPERATURE
10
94
Sl. No
DESCRIPTION
Page. No
4.14.5
CIRCULATING REFLUXES FLOW
94
4.14.6
PRODUCT WITHDRAWL TEMPERATURE
95
4.14.7
STRIPPING STEAM
95
4.14.7.A
STRIPPING STEAM IN FRACTIONATING COLUMN
96
4.14.7.B
STRIPPING STEAM IN STRIPPERS
96
4.15
NORMAL OPERATING CONDITIONS
97
4.16
CRITICAL OPERATING PARAMETERS & INSTRUMENTS
98
11
Chapter 5
UTILITIES SYSTEM
101-116
5.1
INTRODUCTION
102
5.2
INSTRUMENT AIR
102
5.3
PLANT AIR
103
5.4
COOLING WATER
103
5.5
SERVICE WATER
104
5.6
DM WATER
104
5.7
BOILER FEED WATER
105
12
5.8
LP STEAM
105
5.9
MP STEAM
106
5.10
HP STEAM
107
5.11
FUEL GAS
107
5.12
FUEL OIL
108
5.13
FLUSHING OIL
108
5.14
ELECTRIC SYSTEM
110
5.14.1
ELECTICAL POWER FOR PUMPS
110
13
5.14.2
PLANT ILLUMINATION
110
5.14.3
INSTRUMENTATION POWER SYSTEM
111
5.15
EFFLUENT SYSTEM
111
5.15.1
SLOP SYSTEM
112
5.15.2
CLOSED BLOWDOWN (CBD) SYSTEM
112
5.15.3
OILY WATER SEWER (OWS) SYSTEM
113
5.15.4
SEWER WATER SYSTEM
114
5.15.5
AMINE DRAIN SYSTEM
114
14
5.15.6
FLARE SYSTEM
114
Chapter 6
NORMAL START-UP PROCEDURE
117-155
6.1
INTRODUCTION
118
6.2
BRIEF START-UP PROCEDURE
118
6.3
DETAILED START-UP PROCEDURE
(AFTER M&I SHUT DOWN)
120
6.3.1
PRELIMINARY PREPARATION
120
6.3.2
AIR REMOVAL FROM THE PROCESS SYSTEM
124
Sl. No
DESCRIPTION
Page. No
6.3.3
TIGHTNESS/PRESSURE TEST
132
15
6.3.4
FUEL GAS BACKUP
132
6.3.5
COLD CIRCULATION
135
6.3.6
HOT CIRCULATION
139
6.3.7
COMMISSIONING OF DESALTERS
145
6.3.8
NORMALIZATION OF OPERATING CONDITIONS
146
6.3.9
BRINGING UP NAPHTHA STABILISER SYSTEM
148
6.4
STEPS INVOLVED IN START UP FROM BOTTLED UP CONDITION
150
6.5
CHECK LIST FOR UNIT NORMAL STARTUP FROM BOTTLED UP CONDITION
153
Chapter 7
NORMAL SHUT DOWN PROCEDURE
156-166
7.1
16
INTRODUCTION
157
7.2
BRIEF SHUT DOWN PROCEDURE
157
7.3
DETAILED SHUT DOWN PROCEDURE
(FOR M&I SHUT DOWN)
158
7.3.1
THROUGHPUT REDUCTION
158
7.3.2
DISCONTINUATION OF CHEMICAL INJECTION
159
7.3.3
SHUT DOWN OF NAPHTHA STABILISER
159
7.3.4
DECOMMISSIONING OF DESALTERS
160
7.3.5
NORMAL SHUT DOWN
161
7.3.6
SHUT DOWN OF ATMOSPHERIC SECTION FOR M&I
162
7.3.7
EMPTYING OUT OF THE UNITS AND PURGING/ISOLATION
17
163
7.3.8
CHECK LIST FOR UNIT NORMAL SHUTDOWN FOR BOTTLED UP CONDITION
164
Chapter 8
EMERGENCY PROCEDURES
167-209
8.1
GENERAL GUIDELINES
168
8.2
POWER FAILURE
170
8.3
STEAM FAILURE
181
8.4
COOLING WATER FAILURE
185
8.5
INSTRUMENT AIR FAILURE
189
8.6
FEED FAILURE
193
8.7
ALL UTILITIES FAILURE
193
Sl. No
18
DESCRIPTION
Page. No
8.8
FAILURE OF HEATER TUBES
194
8.9
110V DC SUPPLY FAILURE
195
8.10
24V DC SUPPLY FAILURE
198
8.11
UPS FAILURE
201
8.12
DCS CONSOLE FAILURE
205
8.13
FIRE IN THE PLANT
208
Chapter 9
PROCEDURES
FOR
EQUIPMENT
MAINTENANCE/INSPECTION
210-224
9.1
PUMPS
211
9.1.1
COLD PUMP
19
HAND
OVER
TO
211
9.1.2
HOT PUMP
212
9.2
VESSELS
213
9.3
COLUMNS
217
9.4
EXCHANGERS/COOLERS/CONDENSERS/REBOILERS
222
9.5
TANKS
222
9.6
FURNACE
223
9.7
FLARE HEADER
223
9.8
CONTROL VALVES
224
9.9
SAFETY VALVES
224
Chapter 10
20
21
11.2.2
GOOD HOUSE KEEPING
231
Sl. No
DESCRIPTION
Page. No
11.2.3
INSTRUCTION TO PERSONNEL
231
11.2.4
REGULAR TRAINING OF EMPLOYEES
231
11.2.5
SAFETY AUDITS/SAFETY STUDIES
232
11.2.6
FIRE EMERGENCY MOCK DRILLS
232
11.3
FIRE PROTECTION SYSTEM IN REFINERY
232
11.4
FIRE PROTECTION SYSTEM IN THE UNIT
234
11.5
WORK PERMIT SYSTEM
234
11.5.1
TYPES OF WORK PERMITS
235
11.5.1.A
22
23
24
12.3
CAUSTIC SODA
254
Sl. No
DESCRIPTION
Page. No
12.4
DIETHANOL AMINE
258
12.5
DEMULSIFIER
261
Chapter 13
PROCESS UPSET & CORRECTIVE ACTIONS
265-272
13.1
RANGE OF CRITICAL OPERATING PROCESS PARAMETERS
269
13.2
CRITICAL INSTRUMENTS/CRITICAL OPERATING PARAMETERS AND ITS
IMPLICATIONS
270
Chapter 14
HANDING & TAKING OVER OF INFORMATION DURING SHIFT CHANGE
273-275
Chapter 15
CONTROL OF HAZARDOUS CHEMICAL INVENTORY LEVEL
276-277
Chapter 16
PLANT EQUIPMENT IDLING METHOD
278-279
25
16.1
FOR SHORT SHUTDOWN
279
16.2
FOR LONG SHUTDOWN
279
Chapter 17
TASK PERFORMED BY OPERATORS
280-297
17.1
PANEL OPERATOR
281
17.2
FURNACE OPERATOR
288
17.3
FIELD OPERATOR
292
17.4
PUMP OPERATOR
298
Chapter 18
DCS INFORMATION
298-300
Chapter 19
ADVANCED PROCESS CONTROL SYSTEM
301-312
Chapter 20
LABORATORY TEST SCHEDULE
313-314
26
Chapter 21
MASTER BLIND LIST
315-318
Chapter 22
CONTROL VALVES DATA
319-321
Chapter 23
LIST OF INTERLOCKS
322-327
Chapter 24
SKO/ATF SALT DRYER
328-330
Chapter 25
HSD COALESCER
331-335
Chapter 26
CHECLKISTS FOR TASK OBSERVATION
336-358
26.1
HANDING OVER PUMP FOR MAINTENANCE
341
26.2
TAKING OVER PUMP FOR MAINTENANCE
341
26.3
HANDING OVER VESSEL FOR MAINTENANCE
342
26.4
COMMISSIONING OF VESSEL
342
26.5
HEAT EXCHANGER COMMISSIONING
343
26.6
HEAT EXCHANGER DECOMMISSIONING
344
26.7
HANDING OVER OF TANK TO MAINTENANCE
345
27
26.8
TAKING OVER OF TANK FROM MAINTENANCE
346
26.9
CONTROL VALVE HANDOVER TO MAINTENANCE
347
26.10
CONTROL VALVE TAKING OVER FROM MAINTENANCE
347
26.11
HANDING OVER OIL GUN TO MAINTENANCE
348
26.12
TAKING OVER OIL GUN FROM MAINTENANCE
348
26.13
HANDING OVER OF APH FOR CLEANING
348
26.14
LPG VESSEL WATER DRAINING
349
26.15
FURNACE LIGHT UP DURING START UP
350
26.16
OIL BURNER LIGHT UP DURING NORMAL OPERATION
351
26.17
WARMING UP OF PUMP
351
26.18
HOT PUMP CHANGE OVER
352
26.19
COLD PUMP CHANGE OVER
353
26.20
EMERGENCY HANDLING DUE TO POWER FAILURE
354
26.21
TANK WATER DRAINING
354
26.22
CHANGE OVER OF PRODUCT ROUTING
355
26.23
AHURALAN SOLUTION PREPARATION
355
26.24
AMMONIA SOLUTION PREPARATION
356
28
26.25
CAUSTIC SOLUTION PREPARATION
356
26.26
AMMONICAL CAUSTIC SOLUTION PREPARATION
357
26.27
CAUSTIC REPLENISHMENT IN LPG/NAPHTHA CAUSTIC WASH SYSTEM
357
26.28
WATER REPLENISHMENT IN LPG/NAPHTHA CAUSTIC WASH SYSTEM
357
26.29
FLARE KOD DRAINING
358
Chapter 27
LIST OF GAS/SMOKE DETECTORS
359-360
Chapter 28
PROCESS FLOW DIAGRAMS (FROM P&ID)
361-363
Chapter 29
FURNACE DECOKING PROCEDURE
364-367
Chapter-30
EQUIPMENT DRAIN LINE DECHOCKING PROCEDURE
368-369
Chapter-31
INTER CONNECTIONS AND ROUTINGS UNDER RUP PROJECT.
370-371
Chapter-32
ANNEXTURE-1
i)
MODIFICATIONS OF M&I-2013
372-381
29
CHAPTER-1
BASIC PRINCIPLES OF DISTILLATION
30
PRINCIPLES OF DISTILLATION
Distillation is a technique by which two or more substances with different boiling points
can be separated from each other. For example, fresh water can be obtained from
seawater (water that contains salts) by distillation. When seawater is heated, water turns
into a vapor that can be condensed and captured. The salts in the seawater remain behind.
In contrast to the preceding example, distillation is most commonly used to separate two
or more liquids from each other.
General principles
Separation of components from a liquid mixture via distillation depends on the
differences in the boiling points of the individual components. Depending on the
concentrations of the components present, the liquid mixture will have different boiling
point characteristics. Distillation processes therefore depends on the vapor pressure
characteristics of liquid mixtures.
31
32
The boiling point diagram shows how the equilibrium compositions of the
components in a liquid mixture vary with temperature at a fixed pressure. Consider an
example of a liquid mixture containing 2 components (A and B) - a binary mixture.
The boiling point of A is that at which the mole fraction of A is 1. The boiling point of
B is that at which the mole fraction of A is 0. In this example, A is the more volatile
component and therefore has a lower boiling point than B. The upper curve in the
diagram is called the dew-point curve. The lower one is called the bubble-point curve.
The dew-point is the temperature at which the saturated vapor starts to condense. The
bubble-point is the temperature at which the liquid starts to boil. The region above the
dew-point curve shows the equilibrium composition of the superheated vapor.
The region below the bubble-point curve shows the equilibrium composition of the
subcooled liquid. For example, when a subcooled liquid with mole fraction of A=0.4
33
(point A) is heated, its concentration remains constant until it reaches the bubblepoint (point B), when it starts to boil. The vapors evolved during the boiling have the
equilibrium composition given by point C, approximately 0.8 mole fraction A. This is
approximately 50% richer in A than the original liquid. This difference between liquid
and vapor compositions in equilibrium is the basis for distillation operations.
Relative Volatility
34
The three-liquid mixture described above is added to a distillation flask. The mixture in
the flask is heated by a Bunsen burner or some other apparatus. The temperature of the
liquid mixture rises until it reaches the boiling point of any one liquid in the flask. In our
example, that liquid is A, which boils at 86F. Liquid A begins to boil when the
temperature in the flask reaches 86F. It turns into a vapor at that temperature, rises in the
distilling flask, and passes out of the flask arm into the condenser.
The condenser consists of a long tube surrounded by a larger tube. The outer tube
contains water, which enters near the bottom of the condenser and leaves near the top.
The water passing through the outer jacket of the condenser cools the vapor passing
through the inner tube. The vapor loses heat and condenses (meaning it changes back to a
liquid). It flows out of the condenser and into a receiving containera flask or beaker
placed in position to capture the liquid. The liquid (liquid A) is now known as the
distillate, or the product of the distillation.
Meanwhile, the temperature in the distilling flask has not changed, as indicated by the
thermometer in the mouth of the flask. Heat added to the liquid mixture is used to
vaporize liquid A, not to raise the temperature of the mixture. That temperature will begin
to rise only when liquid A has completely boiled away. By watching the thermometer,
therefore, an observer can know when liquid A has been completely removed from the
liquid mixture. At that point, the receiver containing pure liquid A can be removed and
replaced by a new receiver.
Once liquid A has boiled away, the temperature in the distilling flask begins to rise again.
When it reaches 104F, liquid B begins to boil away, and the sequence of events observed
with liquid A is repeated. Eventually, pure samples of A, B, and C can be collected.
Some liquids decompose (break apart) at or below
35
36
37
CHAPTER-2
INTRODUCTION
2.1
INTRODUCTION
38
The unit comprises of Crude Preheat Train, Crude Desalting, Atmospheric Distillation,
Naphtha Stabilization, LPG Amine wash and Caustic wash, Light Naphtha Caustic wash,
and Kerosene/ATF caustic wash. The main products from the unit are LPG, Light
Naphtha, Heavy Naphtha, Kerosene, Gas Oil and Long residue. Provision is also there for
with drawl of ATF (boiling range 140-240) during alternate mode of operation. During
ATF mode of operation Kerosene will not be withdrawn and the material boiling in the
range of 240-370 C will be withdrawn as Gas Oil stream.
2.2
ONSTREAM FACTOR
The following table provides hourly rates of feed and various products based on Arab
Mix Crude feed.
Sl no
1
Material
Quantity
375,000
Crude
39
Wt%
100
2
3.
4.
5.
6.
7.
4750
34350
9280
73,571
57,551
195,573
1.3
9.1
2.5
19.6
15.1
52.3
Specification
Unit
B. PRODUCTS
40
Value
0.8728
27.3
52.9
97.2
223.0
344.4
476.8
658.3
709.3
732.2
30.6
10.5
-124
0.6
165
2.0
Sr.No
.
1.
2.
Product
Specification
Value
TBP cut oC
TBP cut oC
IBP-170 oC
120-170 oC
3.
O/H Naphtha
Heavy
Naphtha
ATF
TBP cut oC
Flash Point oC
Freezing point oC
ASTM D-86 EP
140-240
38 (min)
-50 (max)
288 oC
4.
SKO
5.
Gas Oil
6.
Long residue
TBP cut oC
Flash Point oC
ASTM D-86 EP
TBP cut oC
Flash Point oC
ASTM D-86 95%
TBP cut oC
7.
LPG
140-270
36 (min)
300 (max)
240/270-370
34 (min)
Not to exceed 365oC
Shall not contain
more than 8% vol
(max) of material
boiling below 370 oC
Not more than 16.87
Kg/cm2
MOTOR SPIRIT
S. Characteristic
No
1
Density, 15C,
Kg/m3
2
RON, min.
Distillation:
Recovery at
70C, %v
BIS
Spec
710-770
Prec.
Limits
0.5/1.2
91
0.2/0.7
Manf.
Spec.
711768*
91.2
10-45
Slope
11-38*
41
Justification/Remarks
To take care of addition of 5%
ethanol
To take care of test margin
(In case due to sensitivity of
the blend MS is not in a
position to meet AKI, meeting
AKI will be guiding factor in
line with BIS Spec)
Lower limit to take care of
storage and handling impact.
Upper limit to take care of
addition of ethanol.
4
5
6
7
Recovery at
100C, %v
Recovery at
180C, %v, min
FBP,0C max
Benzene
Content, %v,
max
Total Sulphur,
ppm mass, max
RVP at 38C,
kPa
40-70
Slope
41-70
90
Slope
91
215
1
Slope
0.04/0.18
200
0.9
3
500
1000
35-60
0.03/0.84
145/467
153/495
3.2/5.2
2.7
450
900
38-57*
Copper
Corrosion
1 max
NA
1a
*
Parameters are applicable for ethanol doping areas only. For other areas BIS specs will
Prevail.
Gasoline containing ethanol should be supplied with addition of metal deactivator.
KEROSENE
S.No.
Characteristic
BIS Spec.
Prec. Limits
Smoke
Point,
mm , min
18
1/2
3
4
Distillation:
Final
Boiling
Point, Deg C,
max
Flash
point,
degree C, min
Total
sulphur,
ppm mass, max
Manf.
Spec
19
20 (Rlys)
20 (Rlys)
22(Def)
300
Slope
22(Def)
290
35
1/1.5
38
2500
175/580
2400
Justification/
Remarks
To take care of
test margin
To take care of
test margin.
Safety parameter.
To take care of
test margin.
Environmental
parameter.
To
take care of test
margin.
Characteristi
c
Cetane Index,
BIS
Spec.
46
Prec.
Limits
Function
42
Manf
Justification/ Remarks
. Spec
47
To take care of test margin
min
Rec at 370C,
%v, min
Flash
Point,
Deg C, min
Total sulphur,
ppm
mass,
max
Lubricity,
microns, max
Copper
Corrosion,
max
Particulate
Matter,
mg/Kg,
max
of density
and
distillation
43
(Assam
crude)
95
44
Slop
96
35
1/1.5
37
500
145/467
450
2500
460
175/580
60/120
2400
420
NA
1a
Not
specified
2.4/7.2
24
BIS
Spec.
-47
Prec.
Limits
0.7/2.6
Manf.
Spec
-49
Justification/ Remarks
To take care of test margin
300
Slope
290
38
1/1.5
40
3000
(Genl)
2500
(Defense)
50-450
50/175
2500
3-20/1063
250440
-do-
3
4
Characteristi
c
Freezing
Point, degree
C, max
Distillation,
final boiling
point, degree
C, max
Flash
Point,
Deg C, min
Sulphur total,
ppm
mass,
max
Electrical
Conductivity,
43
ps/m,
Aromatics, %
vol, max
25
(Genl.)
20
(Defense)
Sulphur
30 (Genl)
Mercaptan,
20
ppm
mass, (Defence
max
)
Lubricity,
0.85
WSD mm max (General)
0.65
(Defense)
2.5
1.4/3.0
20
NA
20
Defence requirement
0.65
Sl.No.
FEED
1.
2.
3.
4.
Feed/Product
Crude
Sour LPG
Lean Amine
Wild Naphtha/
Drag Stream
PRODUCTS
1.
LPG
2.
Light Naphtha
PressureKg/cm2 /
Temp o C
9.5/30
12.0/40
26.5/35
15/38
OM&S
AU2/AU3/AU4
Amine Regeneration Unit
DHDS/LAB
CRU/MSQ
12.0/40
7.0/40
3.
Heavy Naphtha
-/40
4.
5.
SKO
ATF
7.0/40
7.0/40
6.
Gas Oil
Kero Case
6.0/40
ATF case
7.0/40
Long residue
6.5/120
6.5/120
6.5/80 (min)
7.
Source/Destination
44
2.6
8.
9.
Sour Water
FLO
-/40
(2.5/5.0)/40
10.
11.
12.
Slop
Spent Caustic
Rich Amine
6.0/40
5.0/40
7.0/55
Storage
SRU
Routed to line from AU-3 to
GHP
GRE-ETP
Amine Regeneration Unit
UTILITY SPECIFICATIONS
Sr.No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
Utilities
HP Steam
MP Steam
LP Steam
BFW
Instrument Air
Plant Air
DM Water
Fuel Oil(VR +
VBLSHS)
Fuel Gas
PressureKg/cm2
33
11.5
4.5
17(max)
6.5
6.5
5
5
Temp oC
430
230
165
120(max)
Ambient
Ambient
40
90
40
Specification
FUELOIL
S.No
.
1
Prec.
Limits
0.8/2.5
1.0/3.6
175
0.8/3.0
148
0.025/0.1
0.8
HPS
45
S.No.
1
Characteristi
c
Kinematic
Viscosity
at
100C,
cSt,
max
BIS:Spec./Customer
rqmt.
40
Prec.
Limits
0.24/0.8
0
50
Flash point, C,
max
Water content,
%v, max
Justification/ Remarks
Test margin
48
0.3/1.0
100
2
Manf
. Spec
38
98
0.6/2
2/3.5
72
1.0
0.025/0.
1
93
0.8
LSHS
S.No.
1
Characteristic
Kinematic
Viscosity
at
100C, cSt, max
Water
content,
%v, max
BIS
Spec./Cust
omer rqmt.
50
Prec. Limits
0.3/1.0
Man
f
Spec
49
100
0.6/2
98
---do---
1.0
0.025/0.1
0.8
Test
margin
cushion
46
Justification/
Remarks
To take care of test
margin
and
S.No
.
1
Characteristi
c
Penetration,
1/10mm
BIS
Spec.
80100
Prec. Limits
(Repeatability/
Reproducibility
)
2.4-3/6.4-8
Manf
. Spec
Justification/ Remarks
84-96
1.8-2.1/4.8-5.6
60-70
47
62-68
CHAPTER-3
EQUIPMENT DATA
48
EQUIPMENT DATA
3.1 COLUMNS
Sl.
No
1
2
3
4
5
6
Col.
No
Service
CC-01
CC-02
CC-03
CC-04
CC-05
CC-06
Tray
No
Type
51
10
6
6
43
10
Valve
Valve
Valve
Valve
Valve
Valve
Safety Valves
Set Pr
Kg/Cm2
4.5
15
29.5
Exchanger No
EE-01
EE-02
E03
EE-04
EE-05
EE-06A/B
EE-07A/B/C
EE-08A/B
EE-09A/B
EE-10A/B/C/D
EE-12A/B/C
EE-13
EE-14
EE-15
EE-16A/B/C/D/E/F
EE-17A/B/C/D
EE-18A/B/C/D
EE-19A/B
EE-20
EE-21
EE-22A/B/C/D
Exchanger No
EE-23A/B/C
EE-24
Shell
Crude
Crude
Crude
LR
Kero/ATF
Kero/ATF
LR
Crude
GO CR
LR
Desalter water
Brine
GO CR
GO CR
C-01 O/H
C-05 O/H
C-05 FEED
LN
HN
LR
LR
GO
ATF / KERO
Service
Tube
Kero/ATF
Top CR
Gas Oil
Crude
Crude
Crude
Crude
Gas Oil
Crude
Crude
Brine
CW
C-05 Bottom.
Hy. Naphtha.
CW
CW
LN
CW
CW
CW
CW
Service
CW
CW
No
3
2
2
24
25
26
27
28
29
30
31
32
33
34
35
36
37
3.3
EE-28A/C
EE-28B/D
EE-29
EA-01A to H
EE-102A/B
EE-103A/B/C
EE-104A/B
EE-105A/B/C/D/E
EE-106 A/B/C/D
EE-107 A/B/C/D
EE-108 A/B
EE-109
EE-110 A/B
EE-111 A/B
FO
HP Steam
LPG
Fin Cooler
Crude
LR
CRUDE
LR
CRUDE
LR
HGO CR
KERO-I
LGO
LR
HP Steam
FO
LP Steam
C-01 O/H
LGO
CRUDE
KERO-I CR
CRUDE
LGO
CRUDE
CRUDE
CW
CW
CW
PUMPS
Pump
No
PA
1A to E
2A to E
5A/B/C
6A/B/C
7A/B
8A/B
9A/B
10A/B/C
11A/B
12A/B/C
14A/B
15A/B
16A/B
17A/B
18A/B
19A/B
20A/B
23A/B
24A/B
25A/B
26A/B
Pump
No
PA
Service
Crude Feed
Desalted Crude
Top Reflux
CC-05 Feed
Top CR
HN r/d
Kero r/d
Kero CR
GO r/d
GO CR
LPG Reflux
Desalter Water Stage-I
Desalter Water Stage-II
LPG NaOH Circulation
LPG water wash
LN caustic wash
LN water wash
Kero caustic wash
Kero Water wash
LPG Caustic / Water makeup
NH3 Injection
Service
KW
Rated
Amps
240
300
45
75
37
30
75
75
75
160
22
15
55
75
75
5.5
5.5
7.5
7.5
18.5
0.37
KW
25
31
75
126
62
52
126
126
126
260
37
26
93
14
14
10
10
14
14
32
1.1
Rated
Amps
Capacity
M3/hr.
max
287
310
146
79
242
18
124
358
125
361
78
38
38
36
36
25
25
34
34
5
7 Lit/hr
Capacity
M3/hr.
max
DP
Kg/cm
2
16
22
11
20
9
15
17
10
14
15
14
17.5
19
11
12
9
13
18
17
20
8.5
DP
Kg/cm
2
27A/B
29A/B
31A/B
32A/B
33
40A/B
41A/B
42A/B
43A/B
44A/B
45A/B
46
48
50A/B
51A/B/C
52A/B
102A/B
103A/B
104A/B
101A/B
3.4
Demulsifier Injection
Ahuralan Injection
Caustic injection
Caustic Circulation / m- up
47% caustic transfer
Wash water make up
LN rundown
VV-2 sour water
Spent caustic
Kero / ATF caustic M/up
IFO
CBD
ABD
LPG booster
LR
Coolant Water
Kero-I CR
LGO product
HGO CR
Kero-I
FIRED HEATER
05-FF-001-Charge heater
3.5
AIR PREHEATER
FANS
05-KA-001A/B FD fans
05-KA-02-ID fan.
3.7
DRUMS/VESSELS
0.37
0.37
0.75
11
3.7
11
15
3.7
5.5
15
45
18.5
7.5
45
180
30
90
90
90
110
1.1
1.1
2.7
20
20
26
7.3
10.2
28
75
37
9.6
75
19
50
150
150
150
183
11 Lit/hr
24 Lit/hr
410 Lit/hr
5
5
5
58
9
10
5
30
20
6
37
275
98
371
132
470
106
11
10
15.8
11.5
3.1
10.5
8
6
6.5
19.3
15.5
6.8
5
22
16.8
5.5
11
15.1
9
21.6
Sl.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
3.8
1.
Vessel no
VV-01A
VV-01B
VV-02
VV-03
VV-04
VV-05
VV-06
VV-07
VV-08
VV-09
VV-10
VV-13
VV-14
VV-15
VV-16
VV-17
VV18A/B
VV19A/B
VV-120
VV-25
VV-26
VV-27
VV-28
VV-29
VV-30
Operating
Pres./ Temp
Kg/cm2 // 0
C
11.5 / 123.5
11.5 / 123.5
2.1 / 40
9/40
18.7 / 40
Atm / 40
18 / 40
16.5 / 40
15 / 40
9.5 /40
8 / 40
15/40
14/40
13/40
1.2/40
Atm / 100
Atm / 40
Atm / 40
VV-32
VV-33
VV-34
VV-35
VV37A/B
VV-38
Flare KOD
ABD drum
Brine degasser
Flash condensate
Inst. Air vessel
9/40
10/40
1.5 / 90-120
32/237 -430
2/40-80
10 / 40-80
Atm/ 80120
1.5 /144
Atm / 60
Atm / 45
4 / 152
7.5 / amb
Coolant sump
Salt Dryer
HSD Coalescer
amb
4 / amb.
4/amb
VV-301
Service
TANKS
05-TT-001-47% Caustic Solution Tank
Set
Press
16
16
4.5
15
1901 / 1902
1903/1904
29.5
29.5
2001 / 2002
2003 / 2004
2201/2202
2203/2204
16
16
23
23
2501 A/B
14.5
3101 / 3102
3105
3203/3204
3201/3202
3.5
43
6.5
14.5
9.0
16.0
2.
3.
4.
3.9
1.
2.
3.10
Safety valves are normally characterized by fast opening, (popping action). These are
used for compressible fluids like gases. In this category come pressure safety valves
(PSV). Relief valves are used for non-compressible fluids (normally liquids). Relief
valves open in proportion to pressure increase over the set value or opening pressure. In
this category come temperature safety valves (TSV).
These pressure relief devices (safety valves as well as relief valves) are spring-loaded
valves. It is important to note that relief valves provide no protection against high
temperature.
The pressure relief valves are actuated by inlet static pressure and designed to open
during an emergency or abnormal condition, causing pressure build up. This action of
relief valve prevents internal fluid pressure from rising above specified value. Depending
upon type of application, safety valves are selected as closing type (auto reset) or nonclosing type.
Service
LOCATION
Set
Relieving
Selection
pressure
Temp C
Basis
Hold
Hold
H/C
Desalter-I
Kg/cm2 g
16.00
B
PSV1202A/
H/C
stage
Desalter-II sta
16.00
Hold
Hold
B
PSV-1501
PSV-1502
PSV-1503
PSV-1601
PSV-1602
PSV-1701
PSV-1702
PSV-1703
PSV-1704
PSV-1901
PSV-1902
PSV-1903
PSV-1904
PSV-2001
PSV-2002
PSV-2003
PSV-2004
PSV-2201
PSV-2202
PSV-2203
PSV-2204
PSV-2501A
TAG NO.
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
H/C
LPG
Service
05-CC-001
05-CC-001
05-CC-001
05-VV-002
05-VV-002
05-CC-005
05-CC-005
05-CC-003
05-CC-003
05-VV-006
05-VV-006
05-VV-007
05-VV-007
05-VV-009
05-VV-009
05-VV-0010
05-VV-0010
05-VV-013
05-VV-013
05-VV-014
05-VV-014
05-VV-020
LOCATION
4.5
4.5
4.5
4.5
4.5
15
15
15
15
29.5
29.5
29.5
29.5
16
16
16
16
23
23
23
23
14.5
Set
130
130
130
128
128
87
87
97
97
132
243
132
243
205
212
205
212
316
230
316
230
85
Relieving
Block discharge
Block discharge
Block discharge
Fire
Fire
Block discharge
Block discharge
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
Selection
pressure
Temp C
Basis
Kg/cm2 g
14.5
29.5
29.5
3.5
3.5
43
6.5
6.5
14.5
14.5
14.5
14.5
85
110
110
526
526
266
173.5
173.5
96
96
60
60
Fire
External fire
External fire
External fire
External fire
Fire
Fire
Fire
Fire
Fire
Fire
Fire
PSV1201A/
PSV-2501B
PSV-2601A
PSV-2601B
PSV-3101
PSV-3102
PSV-3105
PSV-3108
PSV-3109
PSV-3201
PSV-3202
PSV-3203
PSV-3204
LPG
LPG
LPG
Fuel oil
Fuel oil
HP steam
LP steam
LP steam
LPG
LPG
FG
FG
05-VV-020
05-CC-006
05-CC-006
05-VV-026
05-VV-026
05-VV-027
05-VV-035
05-VV-035
05-VV-029
05-VV-029
05-VV-020
05-VV-020
PSV43002A/B
PSV-4401
PSV-4402
PSV-0000
PSV-0000
Inst Air
MP
Steam
MP
Steam
HC
HC
05-
9.0
186.6
Fire
VV0037A/B
05-MD-001
15
285
C/V failure
05-MD-001
15
285
C/V failure
Salt dryer
Salt dryer
16
16
Ambient
Ambient
b) LIST OF TSVs
TAG.NO
SERVICE
LOCATION SP kg/cm2
TSV-1101
TSV-1102
TSV-1103
TSV-1104
TSV-1105
TSV-1201
TSV-1202
TSV 1301
TAG.NO
Crude
Crude
Crude
Crude
Crude
CW
CW
Crude
SERVICE
35.5
35.5
35.5
35.5
35.5
6
22
43
LOCATION SP kg/cm2
TSV 1302
TSV 1303
TSV 1304
TSV 1305
TSV 1307
TSV 1308
TSV 1604
TSV 1605
TSV 1606
TSV 1703
TSV 1704
TSV 1705
TSV 1801
TSV 1802
TSV 1803
TSV 1805
TSV 1806
TSV 1807
TSV 1808
TSV 1809
TSV 1810
Crude
Crude
Crude
Crude
Crude
Crude
CW
CW
CW
CW
CW
CW
CW
CW
CW
CW
CW
CW
CW
CW
CW
43
43
43
43
43
43
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
6.0
Relievin
g Temp.
150
150
150
150
150
65
65
215
Relievin
g Temp.
175
215
225
255
305
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
Selection Basis
Thermal Expansion
Selection Basis
TSV 1811
TSV 1812
TSV 3101
TSV 3102
TSV 3103
TSV 3104
TSV 3105
TSV 3106
TSV 5002
TSV 5003
TSV 5004
TSV 5005
TSV 5006
TSV 5007
TSV 5008
TSV 5009
TSV 5010
TSV 5011
TSV 5012
TSV 5013
TSV 5014
TSV 5015
TAG.NO
CW
CW
FO
FO
FO
FO
FO
FO
H/C
H/C
H/C
WATER
WATER
WATER
WATER
WATER
H/C
H/C
H/C
H/C
H/C
WATER
SERVICE
TSV 5016
TSV 5017
TSV 5018
TSV 5019
TSV 5020
TSV 5021
TSV 5022
TSV 5023
TSV 5024
TSV 5025
TSV 5026
WATER
WATER
WATER
WATER
WATER
WATER
H/C
H/C
H/C
H/C
H/C
2.12
6.0
6.0
16.5
16.5
3.5
3.5
16.5
16.5
EE-102A/B
35.5
EE-103A/B
35.5
EE-104A/B
35.5
EE-13B
6.9
EE-12 A/B/C
2.2
EE-16D
6.9
EE-16E
6.9
EE-16F
6.9
EE-106A/B
43
EE-105A/B
43
EE-107A/B
43
EE-108A/B
43
EE-18 C/D
2.5
EE-17D
6.9
LOCATION SP kg/cm2
EE-19B
EE-109
EE-110A/B
EE-111A
EE-111B
EE-103C
EE105C/D
EE-105 A/B
EE-107 C/D
6.9
6.9
6.9
6.9
6.9
6.9
35.5
43
43
43
43
65
65
245
245
245
245
245
245
150
150
150
65
130
65
65
65
210
250
310
310
150
65
Relievin
g Temp.
65
65
65
65
65
65
150
210
250
250
310
THER.EXPANSION
Selection Basis
S.No.
1
2
3
4
TAG NO.
5LV2602
5LV3104
5LV3106
SERVICE
BOILER FEED WTR
RICH AMINE TO ARU
STM CONDEN. TO FLASH DRM
LP STM COND. FRM VV-035
SIZE(in.)
1
1
1
1
Action
A/O
A/O
A/O
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
5FV1807
5FV2502
5LV3202
5PV1701
5FV2501
5PV3111
5FV1508
5FV2011
5FV2503
5PV1415
5PV1504A
5PV1504B
5PV1912
5PV2011
5PV3203
5PV4406
5SDV1406
5SDV1701
5SDV1901
5SDV1902
5SDV1903
5SDV1904
5SDV2001
1.5
1.5
1.5
1.5
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
A/O
A/O
A/O
A/O
A/C
A/C
A/C
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
S.No.
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
TAG NO.
5SDV2002
5SDV2003
5SDV2201
5SDV2202
5SDV2203
5SDV2601
5SDV2602
5LV1201
5LV3103
5FV1201
5FV1409
5FV2501
5LV1602
5PV3202
5SDV1401
5LV1202
5TV1702
5FV1401
5FV1402
5FV1403
5FV1404
5FV1804
5FV2206
5FV3102
SERVICE
WASH WTR EX VV-010
WTR FRM VV-025
CAUSTIC EX VV-013
WASH WTR EX-VV-014
WASH WTR EX VV-015
AMINE SETTLER BTM
LPG AMINE ABSORBER BTM
BR IN FRM DSTLR TO DGASR
FO TO VV-026
2nd STAGE DESAL. WTR I/L
PLANT AIR FOR DECOCKING
LPG TO AMINE ABSORBER
SOUR WTR TO VV-005
LP STM TO LPG VAPORISER
FO RETURN
1st STAGE DIST. WTR I/L
NAPH. STAB. BTM. SAT. EE-018A/B
CRUDE TO HTR PASS-1
CRUDE I/L PASS-2
CRUDE I/L PASS-3
CRUDE I/L PASS-4
HSD R/D
KERO/ATF COALASCER O/L
HP STM TO EE-028A/B/C/D
SIZE(in.)
2
2
2
2
2
2
2
2
3
3
3
3
3
3
3
3
4
4
4
4
4
4
4
4
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
A/O
LOCK
A/C
A/C
A/C
A/C
A/O
A/O
A/O
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
S.No.
73
74
75
76
77
78
79
80
81
82
83
5HV1701
5PDV1420
5SDV1402
5SDV1601
5SDV2501
5PV1423
5FV1410
5FV1412
5FV1413
5FV1414
5FV1505
5FV1805
5FV1806
5HV2001
5HV2002
5HV2201
5HV2202
5SDV1801
5FV1501
5LV1508
5LV1510
4
4
4
4
4
6
6
6
6
6
6
6
6
6
6
6
6
6
8
8
8
TAG NO.
SERVICE
SIZE(in.)
5SDV1403
FG SUPPLY
8
5LV1206
CRUDE BOOSTER PMP D/S
8
5FV1502 ATF/KERO CR RETURNED TO CC-001
10
5TV1116
EXCH-05-EE-006 A/B BYPASS
12
5FV6201
SKO TO DHDT
8
5FV6202
SKO TO ATF MEROX
8
5FV6203
HOT RCO TO DCU
8
5FC6204
HN TO DHDT
2
5FV6205
GO TO DHDT
6
5FV7218
LN TO ISOM
4
5FV7219
LN TO ISOM
4
A/O
A/O
A/O
A/O
A/O
A/O
A/C
A/C
A/C
A/C
A/C
A/O
A/O
A/C
A/C
A/C
A/C
A/O
A/C
A/O
A/O
A/O
A/C
A/C
A/C
A/O
A/O
A/O
A/O
A/O
A/O
A/O
CHAPTER-4
PROCESS DESCRIPTION
PROCESS
DESCRIPTION
59
PROCESS DESCRIPTION
4.1
Atmospheric Distillation
Naphtha Stabilization
For the sake of simplicity in process description, Atmospheric Unit is divided into a
Number of subsections as given below:
Crude Desalter
Naphtha Stabilizer
60
From the 14 headers, Crude Booster 05-PA-001 A/B/C/D/E take suction and deliver
crude to the preheat Train-I through a 12 discharge header. Provision was made at B/L to
receive LAB plant Return stream along with crude. The following connections are
provided in the suction line of booster pumps inside battery limit.
3 slop line from CBD Pump Discharge for reprocessing the slop.
The crude booster pumps have a capacity of 261 m 3/hr . The normal discharge pressure of
crude booster pump is 23.87 Kg/cm2 g. Normally two crude pumps will be in operation
and one will remain standby.
The following instruments are provided in the discharge header of crude booster pumps.
61
FI-1101 with flow tantalizer and recorder at DCS and sends signals to furnace pass
ratio balancing and also heat duty control
To heat the crude oil and bring it to the required desalting temperature.
To recover heat from out going products and circulating reflux streams by heating the
crude oil, thereby improving fuel economy in operation at unit.
62
After HIC 5001, Crude flows through exchanges EE-102A/B shell side. Crude is
heated up to 74.3 C LGO (Tube side) is cooled from 134.9 C to 65 C.
In Exchanger EE-104A/B Crude passes in shell side and gets heated from 74.3 C
to 138.8 C tube side flow is Kero I C.R. and it is cooled from 185.7 C to 128
C.
Combined outlet from exchanger EE-104A/B and EE-103A/B/C then joins with
old Pre-heat Train I stream via H/C 5003.
All exchangers in Preheat Train-I are provided with bypasses to tackle maintenance/tube
Leakage problems. Thermal Safety Valves (TSV) are provided on each of exchanger
outlets on the crude side (cold stream) to take care of pressurization due to thermal
expansion of Local pressure gauges and temperature indications in DCS are provided
across every exchanger for performance monitoring of the particular exchanger unit.
The purpose of heating up crude in preheat train I before Desalter is to improve oils
Fluidity, reduce its viscosity, and to help mixing desalter water thoroughly with it. Here
crude is preheated from 30 C to 127 C for normal Kero Case (for ATF case 123.6 C).
From Crude Preheat Train-I, crude is routed to two stage Crude Desalter. MV-1201 &
MV-1202 are provided just upstream of two stage desalter. Normally desalting water is
added upstream of these mixing valves. Provision exists to add desalting water into crude
upstream of 05-EE-005. The purpose of the mixing valve is to thoroughly mix the crude
and water prior to desalting.
4.4
CRUDE DESALTING
63
exchangers, charge heater and Atmospheric column. Hence the need of their removal is
important before processing.
At high temperatures, Magnesium chloride decomposes and forms Hydrochloric acid,
corroding trays in the top section of column and tubes of overhead condensers etc. The
presence of calcium and sodium salts can cause plugging of heat exchanger and heater
tubes, there by rapidly reducing heat transfer co-efficient. The presence of Arsenic acts as
a poison to platinum catalysts if it is used in down stream process units. Presence of these
salts also promotes coke formation in heater tubes which results in increased pressure
drop as well as less heat transfer rates. The excessive coke formation results in escalation
of hot spots on heater tubes which can have serious and disastrous consequences for
heater tubes. At high temperature salts in crude oil show a tendency to deposit along heat
exchange surface of the equipment.
Caustic injection upstream of desalter in crude is done to neutralize acids present in crude
and convert them into water solvable salts. These salts are then removed by desalter water
in desalter. Caustic injection down stream desalter is provided to neutralize any other acid
traces formed at desalter operating conditions.
Brine is associated with crude both as a fine suspension of droplets and more permanent
emulsion. To break this tight emulsion, Demulsifier is added. This ensures better function
of Desalter. Demulsifier is injected into crude upstream of desalter. Provision also Exists
for injection of Demulsifier into the crude line at B/L for better mixing.
In fact, both caustic solution and Demulsifier are added into the crude before the first
exchanger in the preheat train I.
4.4.1
DESALTERS OPERATION
Two stage crude desalter comprising of two identical desalting units. 05-VV-00-001A/B
has been provided for reducing salt content in crude oil to the level of <0.5 PTB. Two
stage Desalter unit arrangement is provided to handle crude with widely carrying salt
contents. Depending upon salt contents in crude both desalter units can be operated either
in series or Individually but not in parallel. Any of the two desalters can be isolated and
bypassed. Crude desalter operates at 12.5 Kg/cm2 g pressure. It is designed to bring down
64
the salt content of the crude from 165 ppm to less than 0.5 ptb. Also, the water content of
crude is brought down from 0.2% volume to less than 200 ppm at the exit of desalter.
Crude and desalter water enters the Desalter (05-VV-00-001A/B) from its bottom. Crude
outlet from top of the vessel is connected to the Desalted crude pumps (05-PA-00002A/B/C) suction. For draining oily water and handling wash streams, desalter drain
connections to CBD/OWS are provided.
The material that collects at desalter bottom is a thick sludge that is corrosive and often
has a tendency to choke the piping. This material needs to be cleaned periodically. For
this de-sledging arrangements in both the desalter have been provided. Stage-I Desalting
water Pumps 05-PA-00-015A/B discharge is associated with distributors inside both the
desalter. FI-1211A and FI-1210B indicate desludging water flow to 05-VV-001A and 05VV-001B respectively. Desludging is a batch process. When desludging water is injected
in the desalter through distributor, it loosens up the muck collected at the bottom, and
facilitates its easy exit from outlet. Meticulous care should be taken during this operating
as sudden jerk can upset oil water inter phase, leading to water and salt carryover to
CDU. On stage-I desalter 05-VV-001A, inter phase level controller ILIC-1202 is
provided to ensure smooth functioning of the unit. In addition one inter-phase level low
low switch LSLL-1207 along with alarm is provided to prevent inter phase from getting
lost and resulting into oil carryover along with brine from desalter. Another lowlow
level (oil) switch LSLL-1203 with alarm (which in effect is high inter phase level) is
provided. In case of low oil level, amperage in desalter increases due to increased
conductivity and may eventually lead to short-circuiting. On actuation, this switch trips
power supply to desalter to prevent such an eventuality.
Since desalter is liquid filled vessel, the pressure control is achieved by manipulating PV1206/PV5001 provided on crude pump discharge line upstream of preheat train-I. Panel
mounted push buttons (to start PB-1201 A& to stop PB1201B) are provided to control
power supply to desalter. Actuation of LALL-1203 trips power supply to desalter, PSV1201A & 1201 B are provided to protect 1st stage desalter from over pressurization due to
blocked outlet. The discharge of these safety valves is routed to flash zone of
Atmospheric Column. Since this is a liquid discharge, safety valve outlet line is kept free
draining towards atmospheric fractionating column to avoid formation of liquid pockets.
65
Also the PSV 1201A/1201B are located close to the column to reduce the discharge pipe
length where two-phase flow may occur after PSV discharge.
Similar instrumentation and other facilities exist for II stage desalter 05-VV-001B also.
On II stage desalter 05-VV-001B, inter-phase level controller ILIC-1202 is provided to
maintain inter-phase level in the desalter unit. It can manipulate either LV- 1202 on I
stage desalter water pump discharge or LV-1201 on cold brine outlet from 05-VV-001A.
The selection for this is made by SS-1201/Ss-1202. One interphase level low-low switch
LSLL-1208 along with alarm is provided to prevent interphase from getting lost and
resulting into oil carryover along with brine from desalter. On actuation the switch closes
LV-1201 through de-energization of SOV-1201. The selection for this is made by SS1207. Local PG/TG are provided to indicate desalter pressure and temperature. PIC-1206
on desalted Crude line is provided for manipulation of PV-1203/PV5001 on crude charge
pump discharge line. Another low-low level (oil) switch (LSLL-1204) along with alarm
(which in effect is high inter-phase level) is provided. In case of low oil level, amperage
in desalter increases due to increased conductivity & may eventually lead to shortcircuiting. On actuation this switch trips power supply to desalter.
Since desalter are liquid filled vessels, the pressure control is achieved by manipulating
PV-1206/PV5001 provided on crude pump discharge line upstream of preheat train-I.
PSV-1202A &1203B are provided to protect 2nd stage desalter from over pressurization
due to blocked outlet.
To ensure that the crude and water are mixed thoroughly, the mixing valves MV1201/1202 respectively are provided at the upstream of both the desalter.
Depending upon salt content in crude, following three cases for desalter operation are
considered:
1) Both Desalter Stages in operation
2) Only Stage I Desalter in operation
3) Only Stage II Desalter in operation
All these cases are taken up in detail in following pages:
1)
66
67
Desalter Pressure
Desalter Temperature
68
Water used for desalting is stripped sour water from SRU. As other alternative, DM/SW
can also be used. Sour water or DM water/service water is first collected in desalter water
vessel 05-VV-005. Desalter water drum level is maintained by LIC-1205, manipulating
LV-1205 acting on incoming stripped water line/ DM water line in sequence. Provision of
Caustic solution injection in this drum is there to neutralize acids formed in crude at
elevated desalter temperatures.
Combined desalting water from desalter water drum 05-VV-005 is pumped by Second
Stage Desalting Water Pumps 05-PA 16A/B/C to 05-VV-001B under flow control FIC1201. It is heated up to about 99 C in shell side of 05-EE-012A/B/C by exchanging heat
with brine solution going out from desalter, which gets cooled from 122/118.5 C to 6359.5 C. TI-1208 is provided at the downstream of this exchanger on the desalter water
line. This heated water can join the crude header upstream of crude oil mixing valve MV1202 of desalter 05-VV-001B. Water containing dissolved salts from crude (also called
brine) in 05-VV-001B is pumped out by First Stage Desalting water pump (05-PA015A/B) to 1st stage desalter. This brine joins the crude header upstream of crude oil
mixing valve MV-1201 of Desalter 05-VV-001A. Provision is also available for make up
desalter water from Desalter drum 05-VV-001 to the first stage desalter pump 05-PA015A/B. The brine solution from 1st stage desalter 05-VV-001A is cooled in tube side of
05-EE-012A/B/C and 05-EE-013. Finally cooled brine is sent to brine degasser 05-VV034. From brine degasser it is routed into OWS Selector switches have been provide for
inter-phase controllers of desalter 05-VV-001A & 05-VV-001B to manipulate LV-1201 on
69
outgoing brine. On very low desalter level actuated by an low level alarm, SOV-1201
shall close LV-1201 to stop further withdrawal of water, thus eliminating risk of oil
carryover with brine.
4.5
70
Combined outlet of EE-106 & EE-105 again divided in to two branches parallely and
pass through exchanger EE-107A/B/C/D and EE-108A/B tube side. In exchanger EE107A/B/C/D crude is heated from 206.8 C to 291 C and hot stream L.R. is cooled from
360.4 C to 265 C. In exchanger EE-108A/B crude is also heated from 206.8 C to 291
C and hot stream HGO CR is get cooled from 326 C to 275 C heated crude @ 291 C is
then joins with EE-10A/B/C/D crude oil line and then fed to furnace FF-01.
4.6
FURNACE
Process System
Fuel System
PROCESS SYSTEM
Crude oil from Preheat TrainII is heated to desired vaporization temperature of 375 C in
crude furnace before entering the atmospheric column 05-CC-001 for fractionation.
Crude enters crude charge heater at the top of the convection zone. Bottom of the
convection zone the coils come out and enter the radiation zone from radiation zone,
crude flows to atmospheric column 05-CC-001.
The heater 05-FF-001 is a box type furnace having four parallel passes of 6 size,
numbered as pass 1 to pass 4.
Flow in each pass is regulated by individual pass flow controller FIC-1401 through FIC1404 (provided on each branch or pass). Ratio of crude flow in a particular pass to total
crude flow is maintained by a ratio controller. The crude flow in each pass is controlled
by a pass balancer in such a way that the weighted average temperature at the outlet of
71
each pass is maintained almost same. Crude flow through each pass is automatically
adjusted by individual pass flow controllers of each pass. Pass balancer receives software
input signals from FIC-1101 controlling crude flow, current values of all crude heater
pass flows and temperature as indicated by FIC-1401 through FIC-1404/TI-1407 through
TI-1410. Pass balancing is an advanced control feature, conceived for future
implementation. Pass balancer output is utilized by atmospheric column duty controllers
on circulating refluxes also. The distribution of crude through each pass should be
adjusted in such a way that the heat duties and hence out let temperature of all the passes
is more or less same. Depending on heat duty variation pass flow will vary. Inequalities
of flow through each pass to the extent of 10% can be tolerated, while operating on
manual mode or pass balancing is not working.
All the four passes of 05-FF-001 join together at the outlet of the radiation zone and then
enter the crude column 05-CC-001. Pressure gauges and temperature indications are
provided at all the external crossover of pass flows from convection to radiation section.
To avoid repetitive description, features of only pass 1 have been taken up. For other
passes identical arrangements exist.
FIC-1401 controls and indicates crude flow through pass 1. Through dual transmitter FT1401 from the same flow element, one flow low-low alarm FAL-1401B has been
provided to indicate vary low flow condition in pass 1. Actuation of this alarm will trip
the fuel supply to all burners of the heater excluding pilots. TI-1432/PI-1308 indicates
temperature/pressure of all pass flow control valves.
TI-1409 indicates coil outlet temperature (COT) of crude at pass 1 outlet High
temperature software alarm on the COT has been provided to alert the operator against
inadequate flow or harder firing in that particular pass. Prolonged high temperature may
lead to cooking up of that particular pass. Software signal of this TI-1409 is utilized by
pass balancer also. Finally heated crude enters a common manifold of 28 size, called
transfer line before entering atmospheric column.
TIC-1416/TI-1413 indicates combined, final coil outlet temperature of the crude. The
temperature indicator controller TIC-1416, which regulates the quantity of fuel to the
furnace, controls the final crude outlet temperature of the common transfer line. PI-1428
indicates pressure at radiation zone outlet in common transfer line. Pressure drop across
72
FUEL SYSTEM
05-FF-001 is a balanced draft furnace. Both the convection and radiation sections are
used for heating crude. The combustion chamber houses the radiant tubes. In this section
heat is primarily transferred by radiation from the flame and hot combustion products.
The convection section provided at the top of the radiation section serves to increase the
thermal efficiency of the furnace by removing further heat from the flue gas. The
radiation section has four identical cells & each cell has two flow passes. Tubes in
radiation section are arranged vertically along the walls. Convection selection has
horizontal tubes.
05-FF-001 is a dual fired furnace i.e. either fuel gas or fuel oil or both can be used as fuel.
The furnace has 19 burners. Each burner is mounted vertically upward at furnace floor.
Furnace fuel systems are discussed below.
73
4.6.2.A
Fuel gas (FG) from battery limit is supplied by a 8 header. The FG line is steam traced to
avoid condensation of heavier components in it inside the line itself and carry-over of
hydrocarbon liquid droplets to the burner. To arrest carry over of foreign particles like
rust etc a 100-mesh strainer is provided on the line.
FG to main burners passes through a shut down valve SDV-1403 whose open or close
position is indicated in control zoom by ZLH-1403 A/ZLL-1403B. Fuel gas flow to the
main FG burners is indicated in DCS by FI-1417. A local temperature & pressure alarm
PAL-1435B and a very low-pressure trip alarm PALL-1424A is provided at the inlet of
fuel gas to the main burners. If fuel gas pressure falls below PALL-1424A set value,
chances of flame failure in burner, accumulation of un-burnt FG in firebox and possibility
of explosion/back fire through heater opening is exists. Actuation of PALL-1424A will
shut the SDV-1403 on fuel gas supply to the main burners of the furnace, eliminating this
possibility. Minimum stop limit to PV-1423 and all valves on similar duty has also been
considered to avoid extinguishment of FG burners on closure of valve due to signal from
COT controller TIC-1416. Fuel gas pressure and hence flow to burners is controlled by
PIC-1423. It can be cascaded with crude oil coil outlet temperature (COT) controller
TIC-1416 through a selector switch SS-1415, COT can be used to select either for fuel oil
or fuel gas as the fuel-controlling COT. A 2 FG tapping upstream of shut down valve
SDV-1403 has been taken for pilot burners. On the pilot fuel gas line, FI-1416 is provided
to measure FG flow to pilot burners. Pressure in the pilot gas line is manually adjusted.
A low-pressure alarm PAL-1419B will alert the operator when pilot gas pressure falls.
PB-1401 has provided in the pilot line, for actuating SDV-1406 when the alarm has
come. PG-1418/PG-1425 indicates FG pressure in main and pilot gas lines in field at
heater battery limit.
4.6.2.B
74
Fuel oil (FO) is supplied to atmospheric furnace by a 4 line under pressure control PIC1415.
Flow indicator FI-1420 is provided on main fuel oil supply line and FI-1419B is provided
on the main fuel oil return line from heater. Since this is a closed circuit through which
FO circulation is maintained, the net consumption of fuel oil is measured as the
difference between the two by FDI-1420. Shut down valves SDV-1402/SDV-1401 is
provided on supply & return header of fuel oil. Open and close indications for these
valves are available in control room. A fuel oil pressure low low trip alarm PALL-1427B
and a pre trip alarm PAL-1426A are provide on FO (supply) line. Local PG near heater
battery limit is also provided to indicate pressure the FO in the field for local burner
adjustments.
Since FO is normally a congealable material, it needs to be always maintained in
circulating state. If it is left stagnant and unused in oil burners and piping, it can get
congealed despite the fact that tracing steam of the FO circuit is on. Circulation in heater
area FO piping (forming a closed circuit across all passes called fuel oil ring) is
maintained even when no FO burner is in use. A ratio of 1:1 fuel oil consumption to
return is normally maintained to obtain good control on firing and prevent congealing of
the IFO system. To prevent congealing inside piping, FO circulation past heater as well as
each burner should be maintained. FO is drawn by individual burners through a 3/4
header from main FO supply line and balance quantity is sent to FO return header. This
return header from cells joins a common return header before leaving heater area. When
there is no need of FO firing in the heater, the circulation can be maintained outside
heater, through a 2 header called ring by pass. Purge steam connection is provided on
each oil burner. Pressure gauges are provided on FO and atomizing steam line of each
burner. FO and atomizing steam lines are routed to each burner of the cell. FO burners
should be kept steam purged when idle. 2 flushing oil connection is provided on FO
(supply) line. CBD/OWS drain is provided on FO (Return) line. These provisions are
used to flash the line within battery limit after heater shut down. When fuel oil is fired, it
is atomized or sprayed as a fine mist for releasing complete combustion. The spraying of
FO is done by de-superheated MP steam in FO burners. Atomizing steam is supplied to
75
The heat carried away by the flue gas after the convection section is utilized for
preheating the air required for combustion. Atmospheric heater has independent air
preheating system to cater combustion air requirement of its burners. The combustion air
required for heater burners is supplied by two forced draft fans, 05-KA-001 A/B. Pilot
burners are self inspiriting type and do not consume combustion air from FD fan
discharge. The combustion air is preheated by flue gases in pre-heaters CAPH (05-FD001) & GAPH (05-FD-002). Air pre-heater is a shell and tube type heat exchanger. Cold
air from atmosphere is sucked by FD fans and forced through shell side. The hot flue gas
leaving the convection section of furnace is sucked by an ID fan 05-KA-002 from up
stream of stack damper and through tubes of APH. Flue gas exchanges heat with cold air
in tube side of APH. Cold flue gas from Air Pre-heater is discharged back to at D/S of
stack damper and let out to the atmosphere.
4.6.4
Combustion air is sucked from atmosphere by the FD fans. Combustion air from FD fan
enters APH. Bypass is provided to divert cold air with the help of hand operated damper
HIC-1462 & HIC-1463 in case APH outlet temp is below 176 OC to avoid corrosion. A
pressure transmitter and thermocouple are provided on the combustion air to F-1.
4.6.5
76
The following procedures are to be followed for starting and stopping of ID & FD fans.
4.6.5.1
77
As soon as the motor starts, the indication of motor on panel changes from pink to
red.
4.6.5.3
78
Consider the case of stopping FD-1A when both FD Fans are running.
Following interlocks to be kept in bypass mode while starting FD fan:
79
4.6.5.5
ii)
4. Keep low pass flow interlock FALL 1401 through FALL 1404 in line.
5. Stop box purging steam after creating a ve draft.
6. Start FD fan.
7. Check all igniters.
8. Reset pilot gas shut down valve SOV1406. Ensure all the individual pilot gas
burner valves at the furnace are closed before opening the SOV. By operating
B/V present in d/s of SOV1406 maintain pilot gas header pressure around 1.0-1.2
kg/cm2, pressure gauge is present in the field and flow indication is on the panel.
9. Pinch the primary and secondary air register of the pilot burner to be taken in line.
If needed pinch the air registers of adjacent burners. This is because if airflow is
very high then it is difficult for the burner to be light up.
10. Light up pilot gas burner with electrical igniter.
11. Once all the pilot gas burners are lighted up, gas burners are to be taken in line.
80
Reset SOV1402: - FO Shut Down Valve. Ensure all the individual oil
burner valves at the furnace are closed before opening the SOV
Open the FO return valve present near Burner Number 19.If this is not
opened then congealing will occur.
81
6. Close gas burners one by one except one. For putting off the last burner isolate
gas at main isolation valve. By this FG header to furnace will be depressurized,
then close the burner block valve. Get 5PC1423 & SDV 1403 closed, bypassing
inter lock.
7. After all the gas burners are off, cut off pilot gas burners by closing the main
isolation valve. After putting off all pilot burners, isolate individual burner valves.
8.
4.6.5.7
FURNACE INTERLOCKS
1.Furnace cut
off IFO SDV
82
1402 close
BPS-14052.IFO return
05-FC-1403-PASS FLOW LOW LOWFALL 1403
SDV1401
close
3. FG supply
SDV1403
Close.
83
4.6.6
DECOKING SYSTEM
Steam air decoking (SAD) of atmospheric heater tubes is done to remove coke deposit
from inside heater tubes with the help of steam and air. Removal of coke results in clean
heater tube internals & improves heater performance by better heat transfer to process
field. SAD also achieves low-pressure drop through heater tubes and reduces chances of
hot spot on heater tubes. Increased pressure drop and hard firing in furnace indicates
requirement of steam air decoking of the heater tubes. For this operation a dedicated
arrangement called SAD arrangement is provided. It comprises of decoking pot 05-VV017 and piping for Plant Air, Service Water and MP Steam connections to each pass flow
are provided to dislodge coke film deposit from inside the heater tubes. Local and control
room DCS mounted flow indications (FIC-1410, FIC-1412, FIC-1413, FIC-1414) are
provided on each steam connection. Plant air is injected to burn the remaining coke film
deposit clinging inside heater tubes and achieves final cleaning of the tubes. FIC-1409
indicates total flow of plant air into MP steam lines for SAD. Service water quench
provision is given on 05-VV-017 as well as flue gas line to quench the contents before
letting out to atmosphere.
To carry out SAD, pass flow inlet and outlet of the furnace 05-FF-001 are isolated from
process network and connected by means of swinging elbows with the decoking network.
Heater pass flow outlets are connected to the Decoking Drum 05-VV-017. MP steam is
introduced in heater passes and it is fired from outside. Thermal shock caused by flame
cracks coke scales inside tube and flowing steam dislodges them. These are carried to 05-
84
VV-017 after being quenched in flue gas line as well as decoking pot by service water
from where it is drained out. This operation is called spalling. When no more coke is
removed by spalling as indicated by relatively clear colour of effluent, Air along with
steam is introduced into pass flow to burn the coke of inside tube while firing from
outside. Coke is burnt by oxygen of air and thus tube cleaning is achieved. Burning of the
coke is indicated by increased tube metal temperature and presence of CO/CO 2 in flue
gas. Number of passes selected for spalling and coke burning is largely dependant on
limitations posed by steam availability and piping network. Sudden release of coke
during spalling may result in choking of the piping handling effluent or as hot spots on
tube during burning. SAD of only one pass at a time should be done if limitations in
steam and SAD piping are experienced. During SAD utmost care should be taken so that
heater tube temperature does not exceed the limit provided.
SAD of other heaters can also be planned along with CDU heater subject to limitations in
steam availability & case of monitoring.
4.7
FLASH ZONE
Heated and partly vaporized crude feed coming from fired heater enters the flash zone of
the column above tray no.6 at 375 C. Hydrocarbon vapors flash in this zone and get
liberated. Non-flashed liquid moves down ward, which is largely bottom product, called
Long Residue. Certain degree of over flashing of crude is desirable for proper
stabilization of LR and fractionation of gas oil components. Over flash is achieved by
85
setting up COT at slightly higher than actually required. This over flashed material is
washed with gas oil coming down from below of 15 th tray. It strips out heavier vapor
components coming up which otherwise would move-up & cause coloration of gas oil
stream. Tray 7th to 14th forms the wash zone section of atmospheric column along with
LR. Flow of over flash liquid can be increased by both increasing COT and condensing
more material on 7th tray gas oil draw off. However, this will result in less gas oil yield
and higher energy consumption without any advantage. Too large flow of over flash
liquid may result in drop in bottom temperature and lighter bottom product, LR.
Over flash flow and temperature is indicated by FI-1504/TI-1527. Flash zone temperature
and pressure is indicated by TI-1502/PI-1525. Min. 1000 mm piping elevation is
provided between liquid entry nozzle on 6th tray and U loop bottom tangent line over
which FE-1504 is mounted. This elevation provides adequate liquid build up on up
stream of FE and ensures un-flickering, steady flow through orifice. Additionally it
provides some back pressure which is required to prevent flashing just down stream of
flow orifice due to pressure drop. One line of 3 is provided above 8 th tray to release
uncondensed components from over flashed liquid.
MP steam is introduced in the column below tray 1, at approximately 3.5 Kg/cm 2 g and
2300 C for stripping of LR. Steam stripping helps to remove lighter constituents from the
bottom product LR by reducing their partial pressure and vaporize without requiring
addition heat. Hydrocarbon vapors liberated by flashing move up along with steam in the
column for further mass transfer at trays in upper section. Steam flow to column is
controlled by FIC-1506. Steam flow to column is regulated based on outgoing LR
quantity to FPU/Storage. SS-1501 is provided for cut-off the LR Pump 05-PA-051A/B to
storage if LIC-1501 i.e. atmospheric column bottom low level. Desalters PSVs are
released to above 6th tray of fractionating column (CC-01).
4.7.2
OVERHEAD SECTION
86
0016A/B/C/D/E/F. The condensed Naphtha & steam are accumulated in crude column
overhead reflux drum 05-VV-002.
Top pressure of atmospheric column is maintained by PIC-1504, manipulating PV-1504A
on outgoing uncondensed gases from 05-VV-002 to flare or PV-1504B on incoming FG
from fuel gas header. Condensed hydrocarbons are allowed to settle in reflux drum where
steam condensate settles in vessel boot and is pumped by P42A/B to desalter water drum
05-VV-004 or sour water stripper of SRU unit under inter phase controller LIC-1602.
Sour water flow is measured by FI-1801 & its pH is indicated by PHI-1601. On actuation
of boot level alarm low (indicated b LAL-1603) SOV-1601 shall be closed by operation
and the flow has cut off. A part of accumulated hydrocarbons in 05-VV-002 is be pumped
back to atmospheric column as top reflux by Column reflux pumps 05-PA-005A/B/C
under flow control FIC-1505 to control top temperature. This flow controller can be
cascaded with atmospheric column top temperature controller TIC-1501 for precise
control of column top temperature.
Ahuralan is dozed at the top of column to arrest corrosion and ammonia solution is dozed
O/H vapor outlet line to maintain sour water PH level @ 6 to 6.5.
Excess quantity of Naphtha in reflux drum is pumped by stabilizer feed pumps 05-PA06A/B/C to stabilizer as feed. Reflux drum level controller LIC-1606 can be cascaded
with discharge of stabilizer feed pump flow controller, FIC-1701.
Minimum flow protection controllers FI-1610B/FI-1611B are provided for discharge of
reflux pumps & stabilizer feed pumps respectively. In the event of low flow in reflux or
stabilizer feed lines due to throttling of control valves, minimum continuous flow to each
pump, this arrangement prevents heating of pump due to closed discharge operation &
resultant damage to pump.
4.7.3
MIDDLE SECTION:
Middle section of the column has circulating refluxes and product withdrawal network. In
order to maximize heat recovery and balance the column loading for maintaining proper
temperature profile across the column, three circulating refluxes (CR) systems are
provided viz. Heavy Naphtha CR, Kero/ATF CR, and Gas Oil CR. These circulating
87
refluxes are drawn from their respective product draw off trays and are routed to preheat
recovery trains for heat recovery before entering back to the column again.
Duty controllers are provided on CR circuits to control CR flow rates to column. These
duty controllers take corrective action based on actual CR duty & desire CR duty. For a
particular type of crude and crude through put, the CR under reference will have certain
duty. This will be governed by total crude flow and specific heat of CR and is called
desired CR duty. Actual CR duty is also computed by duty controller based on real time
measurement of temperature difference between CR draw off and CR return stream, CR
flow rate and specific heat of CR. Total crude flow, CR temperature difference and CR
flow are measured by various instruments. Specific heat of CR is fixed by operator in
software for computation purpose and no on line measurement for this property is
available. Actual and desired CR duty is calculated in the duty controller as under:
Actual CR duty = Measured CR flow X CR temp. Difference X sp. Heat of CR
stream
Desired CR duty = (Desired CR duty/Desired total crude Flow) X Actual Crude
flow
Inputs to be manually configured by operator are specific heat of CR stream and ratio
(Desired CR duty/ Desired total crude flow) for each crude. Desired CR duty should be
estimated on pro-data feed rate basis to CDU. This is typical to all such duty controllers
on circulating reflux lines. Desired CR duty is compared with actual CR & the flow of
CR is varied to achieve desired CR duty.
4.7.4
88
flow. LR at a temperature of 365 C is pumped out from the bottom of the column by LR
pumps 05-PA-051A/B/C to LR Storage (or) FPU through (i) 05-EE-010A/B/C/D, 05-EE007A/B/C, 05-EE-004, 05-EE-021 and 05-EE-022A/B/C/D. (ii) 05-EE-107A/B, 05-EE105A/B/C/D/E, EE-103A/B, EE-111A/B. Independent level control LIC-1501 with high
& low level software alarm is provided to have redundancy of indication. SS-1501
selector switch is also provided for cutting the LR flow to LR Storage/FPU when the
atmospheric column level is low. A low level switch along with alarm LSLL-LALL-1504
is also given. Bottom temperature and LR pump suction temperature are indicated by TI1522. MOV-1501 also provided at column bottom LR line. ZLH-1501A & ZLL-1501B
limit switch connected through the MOV-1501 for open (or) close indication to DCS.
Pushbutton PB-1501A & PB-1501B are provided to close the MOV-1501 and to trip the
LR pump 05-PA-051A/B.
4.7.5
89
LGO Pump PA-12A/B/C discharge flows through EE-09A/B shell side, EE-14 (CC-05
re-boiler), EE-15 (CC-02 re-boiler) and then enter back to column via flow controller FC1503 on tray-18.
HGO CR pump PA-104A/B discharge flows through exchange EE-108A/B shell side and
then joins with LGO CR line at d/s of FC-1503 via flow controller FC-5010.
C5 bottom temperature is controlled by FC1704 casketed with TC 1707 situated across
E14. Whereas Heavy Naphtha stripper C2 bottom temperature is controlled by FC 1507
casketed with TC 1538 situated across E15.
4.7.6
Heavy Naphtha, Kero/ATF, Gas oil products (are withdrawn) flow by gravity from 34 th,
26th and 15th trays of atmospheric column to respective strippers 05-CC-002/05-CC-003
and 05-CC-004 (under respective level control of strippers). Draw off temperature of HN,
Kerosene/ATF, Gas oil is indicated by temperature indicators TI-1526/1509/1510
respectively in DCS. Vapor return lines from HN, Kerosene/ATF, GO strippers goes back
to fractionators column are provided joining at 36th, 28th and 17th tray of the atmospheric
column. TI-1503/TI-1504/TI-1505 provided on vapor return lines from HN,
Kerosene/ATF, GO strippers indicate Vapor return temperature. 3000 mm elevation
difference from 05-CC-001 column nozzle to upstream of each level control valve for its
smooth functioning 1500 mm elevation down stream of the level control valve ensures
sufficient back pressure to prevent flashing just down stream of control valve &
consequent two phase flow in product draw off piping.
4.8
PRODUCT STRIPPERS
Ten valve type trays are provided in HN stripper 05-CC-002. Local PG and LP steam
connections are also provided on this stripper. LP steam is used to purge the column
90
during M&I S/D. HN to be stripped is admitted on 10th tray of 05-CC-002 under its level
control LIC-1506. Minimum 1500 mm elevation difference is provided between stripper
entry nozzle and LV-1506 piping to provide back pressure and prevent flashing in piping.
HN in 05-CC-002 bottom is re-boiled in re-boiler 05-EE-015 by HGO C/R. HN is
stripped off by its hot vapors generated in re-boiler 05-EE-015. Mass transfer between
down coming HN liquid from tray 10 to bottom and uprising HN vapors takes place on
each tray. Finally stripped HN is drawn by 05-PA-008A/B and sent to product cooling
section. Outgoing HN temp. Is indicated by TI-1512. Stripped light vapor goes back to
36th tray of atmospheric column.
Gas oil CR supplies heat to Heavy Naphtha Stripper Re-boiler 05-EE-015 through F/C
1502. F/C-1502 is cascaded with TIC-1538. Pumps 05-PA-8A/B get suction from CC-02
bottom. PA-08A/B discharge line is divided into two branches.
In one branch it can be routed along with LGO through EE102 A/B via FC 5001. The
other part is cooled in cooler E20. After that, it flows through coalescer to remove carried
over water, and it can be routed to SKO R/D, LN R/D or BS2, Euro-III header of HSD.
FC2011
SKO
FC1807
GO
(EURO3)
FC5001 E102A/B (LGO)
GO
(BS2)
4.8.2
KERO/ATF STRIPPER
Six valve type trays are provided in Kero/ATF stripper 05-CC-003. Local PG and LP
steam out connections are also provided on this stripper. Kero/ATF to be stripped is
91
admitted on 6th tray of 05-CC-003 under its level control LIC-1508. Minimum 1500 mm
elevation difference is provided between stripper entry nozzle and LV-1508 piping to
provide back pressure and prevent flashing in piping. MP steam is used as stripping
medium in this stripper. Steam flow is regulated by FIC-1508 on steam line. It regulates
MP steam flow to 05-CC-003 based on per unit mass of Kero/ATF product outflow, as
indicated by FY-2203. Steam to product ratio is decided by operator and configured in
software for routine control. MP steam reduces partial pressure of hydrocarbon
components inside stripper and helps them vaporize at relatively low temp. Mass transfer
between down coming Kero/ATF liquid from tray 6 to bottom and uprising vapors takes
place on each tray. Finally lighter end stripped Kero/ATF is drawn by 05-PA-009A/B and
sent to preheat train I for exchanging its heat to crude in 05-EE-001. It is further cooled in
cooler E-23 / 24 before routing to caustic wash system. Provision is made for Pump PA01A/B getting suction from same suction header of PA-09A/B, which discharges to
cooler EE-109. Flow of this stream is controlled by 05-FIC-5007 located on EE-109
outlet line. Out let of both the circuits joins together & flows to caustic wash system.
Stripped light vapors goes to 28th tray of atmospheric column & its temperature is
indicated by TI-1504.
Combined kerosene flows to caustic wash vessel V13 through mixing valve
HIC2001.Continuous 10% caustic solution is circulated to neutralize H2S and light
mercaptans present in it. Outlet of V13 goes to water wash vessel V14 through HIC 2002.
Continuous water circulation is maintained in this vessel to wash out carried out caustic
along with it. After caustic wash the stream is passed through coalescer V15 to remove
carried over water particle along with it. It is then passed through a vessel containing rock
salt to absorb moisture from it.
Design data: salt to load: 61 Mt.
Inlet moisture: 1300-1500 ppm.
Outlet moisture: <200 ppm
SKO/ATF R/D flow is maintained FC2206 located U/S of salt dryer. It can be routed to
SKO/ATF/LABFS R/D as per requirement. Provision is also there to route SKO to HSD
or LR for which tapping is taken at upstream of salt dryer, its flow is controlled by FC
1807.
92
FC1809 HSD/LR
4.8.3
GO STRIPPER
93
FC 5003 R/D
** V-301
PC 5003 R/D
Mixed HGO & LGO from E110A/B and FC 1804 together enters the gas oil coalescer V301 to remove water carried over with it. Water accumulated in coalescer is controlled by
LC-5LV-0301 which is drained out to OWS / CBD. Gas oil from Coalescer outlet is
controlled by 1010FV5003 and 1010PV5003. Fixed quantity can be routed to desired
R/D tank and rest amount can be routed to other tank under PC control. HSD R/D can be
routed to as follows
Euro-III header
BS-2 header
NAPHTHA STABILISER
94
Naphtha stabilization is carried out in naphtha stabilizer 05-CC-005 where C1/C2/C3 and
C4 hydrocarbons are removed from naphtha. Stabilizer column has 43 nos. of SS-410
valve type trays. The column is provided with a set of safety valves PSV-1701/1702 set at
15-kg/cm2 g. Their discharge is routed to flare header. MP steam connection is provided
on 05-CC-005 for steam purging of the column during shut down. DCS mounted
temperature indication of top outlet; tray 38, tray 5 and bottom outlet are provided. Local
PG at tray 43, and below tray I is also provided to monitor pressure profile in the column.
Un-stabilized naphtha feed to the stabilizer is first heated up to 119 0 C in feed/ Stabilizer
Bottom Exchanger 05-EE-018A/B & 05-EE-018C/D parallel by exchanging heat with
outgoing stabilized naphtha product stream from stabilizer bottom. Feed from 05-VV-002
enters the column on the 20th tray under flow control FIC-1701 that is normally cascaded
with 05-VV-002 level controllers LIC-1606. Local PG, TG and TI-1701/TIC-1702 are
also provided on feed line to monitor feed temperature pickup.
Wild naphtha from DHDS, LAB plant & MSQ plant and drag stream from CRU are fed
to stabilizer along with its feed. DHDS Wild naphtha & CRU drag stream fed through 2
line each and joins at B/L. Wild naphtha from MSQ & LAB lines were commissioned
and wild naphtha enters the B/L through 2 line each joins at D/S of feed C/V FC1701.
The stabilizer overhead pressure is maintained by pressure controller PIC-1701. This
PIC-1701 acts on the control valve PV-1701 on outgoing line from stabilizer reflux drum
to fuel gas system. In case of increase of stabilizer pressure above set valve PV-1701
shall open and allow more fuel gas vapor to FG system. This will cause drop in stabilizer
pressure. Closure of this valve will increase stabilizer pressure due to less vapor flow
through condenser and resultant less condensation. One hot vapor bypass of 4 size has
also been provided across 05-EE-017A/B/C/D. It can be used to maintain stabilizer
pressure in case of rapid fall of stabilizer pressure. HV-1701 can be made to act for this.
TI-1729 indicates 05-CC-05 overhead vapor temperatures. Overhead vapors from
stabilizer go to the stabilizer overhead condenser 05-EE-017A/B/C/D. The condensed
liquid at 40 C is collected in the stabilizer reflux Drum 05-VV-003. This is LPG stream,
consisting of C3 and C4 hydrocarbons. It is pumped out by naphtha stabilizer reflux/LPG
product pumps 05-PA-014A/B under 05-VV-003 level control of LIC-1704. Part of it is
used as reflux to 05-CC-005 to control top temperature. Its flow is controlled by FIC-
95
1703, which can be cascaded with 05-CC-005 top temperatures Controller TIC-1703.
Uncondensed light hydrocarbons from 05-VV-003 top (C1/C2 component) termed as fuel
gas are routed to fuel gas system. FIC-1702 measures net FG flow from 05-VV-003. PIC1701 controls the pressure of 05-VV-003, acting on outgoing FG line. FI-1710 indicates
LPG minimum flow to 05-PA-014A/B. LPG is run down to LPG wash section under flow
control FIC-2503.
Sour water collected in the boot of 05-VV-003 is sent to CBD under vessel pressure.
High water level in boot may result in water carry over with LPG and can make the
stabilizer upset. The level in stabilizer reflux drum boot is indicated by LG-1705. Water
draining from boot is done manually. Independent low-level alarm switches are provided
in the boot. On actuation of level alarm low is boot, as indicated by LAL-1709, SDV1701 provided on sour water outlet line shall close. This feature shall prevent escaping of
LPG with sour water during water draining. PSVs 1703/1704, set at 15.0 Kg/cm 2 g are
provided on the stabilize reflux rum 05-VV-003, whose discharge is routed to flare
header. It prevents vessel from getting over pressurized in case of external fire. 2 line
connecting flare header with upstream of PSVs has been provided to depressurize the
column to flare. 2 service water connection is provided on 05-VV-003 LPG outlet line to
fill the vessel and wash the atmospheric column with water during shutdown.
One stabilizer re-boiler 05-EE-014 is provided at stabilizer bottom to supply necessary
heat duty for boiling the un-stabilized naphtha. Heating medium for this re-boiler is Gas
Oil CR from 05-EE-009A/B. FIC-1704 provided at GO CR supply line to 05-EE-014
controls GO CR flow to re-boiler. Tray 5 temperature controller TIC-1704 can be used to
control re-boiler duty with the help of FV-1704. It is to be noted that only one
temperature control i.e. either top vapor outlet temp. or tray 5 temp. Should be used for
stabilizer operation. While operating with relatively heavier un-stabilized naphtha stocks,
tray 5 temperature is normally more sensitive and results in more energy efficient
operation. One Baffle of adequate height inside column is provided. Height of baffle is so
selected that it ensures availability of adequate liquid head, which will be necessary to
cause gravity flow of colder liquid through re-boiler. Difference in densities of lighter and
colder liquid establishes circulation through re-boiler. TI-1706/TI1726 measures the
temp. Of GO CR supply and return respectively. Un-stabilized naphtha from column
96
bottom flows to re-boiler under gravity and is re-boiled in 05-EE-014. Heated and partly
vaporized naphtha from re-boilers enters below chimney tray. Lighter components from
un-stabilized Naphtha move up in the tray in vapor form and condense in overhead
condensers. Composition of re-boiler outlet liquid and liquid collected in column bottom
on either side of baffle is considered same. Stabilized naphtha overflows to other side of
baffle inside the column bottom. This is cooled in tube side of 05-EE-018A/B & EE18C/D then routed to product cooling section. 05-FI-5033 shows the light naphtha flow
from stabilizer bottom to feed/bottom exchanger 05-EE-018A/B & 05-EE-018C/D. The
temp. control valve TV-1702 has been provided at the bottom line and it has cascaded
with TIC-1702 provided at feed line to stabilizer. TI-1716 measures the outlet temp. of
light naphtha.
Stabilizer column bottom level is maintained by LIC-1702, acting as master controller to
FIC-2004 (Light Naphtha to storage). Independent high and low level alarm switches are
provided on column bottom. On actuation of level alarm low low in column bottom, as
indicated by LAL-1707, SDV-1801 provided on bottom outlet line shall close. This
feature shall prevent vapor break through i.e. escaping of vapors from stabilizer to caustic
wash section.
To cater the requirement of higher benzene & MS production, provision is made to
process AU5 Light Naphtha without caustic wash to AU1 naphtha splitter section via
5FC5106. Accordingly modification is made & tapping is taken at D/S of Light Naphtha
SDV.
Two separate LN R/D line from battery limit is provided to cater requirement to route
light naphtha to different rundown tanks.
4.10
97
drum pressure is maintained at 10.0 Kg/cm2 by PV-2501, releasing to fuel gas system i.e.
upstream of FG K.O. Drum. The level of the surge drum should always be maintained at
50%. Combined streams passes through a shut down valve SDV-2501 whose open or
close position is indicated in control room by XL-2501B/XL-2501A. Separate high level
switch LSHH-2501/LALL-2501 is provided to trip the combined stream flow to surge
drum by closing SDV-2501.
A low level switch LSLL-2502 along with LALL-2502 is also provided. LIC-2504 along
with LAH/LAL has been provided for level control purpose. Interlock has been provided
along with LSLL-2502 to trip the pump 05-PA-050A/B.
The LPG from the surge drum is pumped by the LPG booster pumps (05-PA-050A/B) to
the bottom of LPG Amine absorber column (05-CC-006) under flow control of FIC-2501.
FIC-2501 is cascaded with LIC-2504 level of surge drum. FIC-2501 indicates total LPG
flow from surge drum. FIC-2502 indicates minimum flow protection to 05-PA-050A/B.
PSVs 2501B set at 15 Kg/cm2 are provided on the top of surge drum 05-VV-020, whose
discharge is routed to flair header. It prevents vessel from getting over pressurized in case
of external fire. 2 line connecting flare header with upstream of PSVs has been
provided to depressurize the drum to flare.
In this LPG absorber column LPG is brought into contact of lean amine solution counter
currently under flow control FIC-2601. The lean amine is available at 35 C from the
Amine regeneration unit in the existing GHP Sulphur block, which is taken to the column
on flow control. LPG Amine absorber column has 10 nos. of trays. The column is
provided with a set of safety valves PSV-2601A & 2601B. Their discharge is routed to
flare header.
Separate high pressure switch PSHH-2601 along with PAHH-2607 is provided in column
top for controlling the column pressure by the way of lean amine flow cut off. A low level
switch LSLL-2605, SDV-2602 (whose open/close position ZLH-2602B/ZLL-2602A at
DCS) provided on bottom rich amine line shell close on very low C06 level.. This feature
shall prevent escaping of LPG with rich amine during low level. FI-2602 measures rich
amine quantity from absorber column to ARU.
The H2S in LPG is transferred to the amine and rich amine is sent back to ARU unit for
regeneration through column bottom level control LIC-2602.
98
Amine washed LPG is sent to amine settler 05-VV-004. In this settler Amine is separated
in the boot and washed LPG the top is sent to caustic wash. Amine collected in the boot
05-VV-004 is drained to Amine blow down (or) OWS. The level in Amine settler boot is
indicated by LI-2603 has provided with LAH/LAL software alarms. Amine draining from
boot is done manually. On actuation of level alarm low in boot, as indicated by LALL2602, SDV-2601 provided on amine outlet line shall close. This feature shall prevent
escaping of LPG with amine during amine draining.
4.11
The HN product can be sent to Gas Oil storage under flow control of FIC-1807
The HN product can be sent to Kero R/D line under flow control of FIC-2011
1 line tapping has provided from common HN product line for corrosion inhibitor
drum
99
Water collected in the boot of 05-VV-025, is sent to OWS under level control. Water
draining from boot is done manually. On actuation of level alarm low in boot, as
indicated by LALL-2100, SDV-2003 provided on outlet water line shall close. This
feature shall prevent escaping of product during water draining. Two PSVs 2005/2006 set
at 15 Kg/cm2 are provided on the coalescer 05-VV-025 whose discharge is routed to flare
header. It prevents vessel from getting over pressurized in case of external fire. A 2 line
connecting flare header with upstream of PSVs has been provided to depressurize the
vessel to flare.
Kero-II product flows from 05-PA-09A/B to EE-01 exchanger. Then it flows through
cooler EE-024. After cooler kero-II product flows through caustic wash vessel VV-13,
water wash vessel VV-14 and coalescer VV-15. Coalescer o/l is routed to R/D via salt
dryer (SKO / ATF / LABFS) & FC 2206. Kero is injected to G.O. via FC-1809.
Gas Oil from old & new circuit at 107.6 C/113 C is further cooled in 05-EE-023A/B/C &
E110A/B (Gas Oil Coolers) up to a temp. of 40 C and sent to RD through FV-1804 under
flow control of FIC-1804, TI-1804 measures the GO outlet temp. This product line is
provided with additional tapings to slops header and DHDS unit and flushing oil, product
G.O can be routed to three locations.
G.O. to FCC units. (2) G.O. to GHC HSD R/D (3) G.O. to BS2 and (4) GO to EuroIII
Long residue from 05-PA-051A/B/C at 363.9 C/364.2 C sent to crude preheat trains II &
I for exchanging heat with incoming crude through 05-EE-010A/B/C/D (LR/Crude
Exchanger III), 05-EE-007A/B/C (LR/Crude Exchanger II), 05-EE-004 (LR/Crude
Exchanger I), and EE-107A/B/C/D/E, EE-105A/B, EE103A/B/C. The outgoing LR
temperature is around 143 C/ 134 C. After this the LR is cooled at LR cooler 05-EE-021
& EE-110A/B up to 120 C outlet of this cooler one portion has sent to FPU storage under
100
flow control FIC-1805 through FV-1805. Remaining LR product sent to further cooling at
LR cooler 05-EE-022A/B/C/D up to the temperature of 80 C. After that the product has
sent to LR storage under flow control FIC-1806 through FV-1806. Product tapings for
slop header and LR circulation to unit crude pump suction for unit start up is also
provided.
Provision is made to route Hot LR to VDU as hot feed via 5FC1805 in June 2006 and a
2 line tapping is provided to route FPU-2 Heavy gas oil to cold LR rundown at battery
limit as carter stock.
4.12 CAUSTIC/WATER WASH FACILITIES
Refer P&ID No.: I) 3551-05-02-41-0120 Rev 2
II) 3551-05-02-41-0119 Rev 2
III) 3551-05-02-41-0122 Rev 2
Caustic wash is generally used to remove Sulphur components like hydrogen sulphide
and/ or methyl & ethyl mercaptan. Equal volumes of hydrocarbon liquid & caustic
solution are mixed / re-circulated. During this operation, caustic hydrocarbon emulsion is
formed which is allowed to settle in a vessel. Typical retention time is 90 minutes to 45
minutes. Naphtha, Kerosene and ATF are washed with 10% caustic solution to remove
CS2, H2S, phenols and mercaptan which may be present or can be generated during
processing. Caustic solutions are hazardous wastes. Traces of caustic are removed by
water washing of these streams. The caustic water wash systems are described below:
4.12.1.A LPG CAUSTIC WASH SYSTEM
LPG from Amine Wash Unit is routed for caustic water wash. LPG is admitted in LPG
Caustic wash vessel 05-VV-006 through a static mixer 05-JV-002. LPG caustic wash
circulation pump 05-PA-017A/B, takes suction from bottom of 05-VV-006 and
discharging into 05-VV-006 through mixer. 10-vol% caustic solutions is circulated by
these pumps where it is mixed with LPG. Mixing in the static mixer results in conversion
and transfer of H2S, mercaptan & other chemicals to sodium sulphides. Depending on
efficiency of mixing in the mixer, reduction of above chemicals shall take place. Mixing
of the two streams can be improved by throttling the mixer rotation. Hydrocarbon phase
101
separates out from caustic in 05-VV-006 due to adequate availability of residence time.
LPG overflows from top of 05-VV-006 to water wash vessel 05-VV-007 through another
static mixer 05-JV-003. Caustic solution settled in 05-VV-006 bottom is re-circulated
again. On repeated circulations, strength of caustic goes down to less than 7.5% of its
initial strength due to picking up of compounds mentioned above. This is called spent
caustic and is drained out through 2 line to spent Caustic water Wash drum 05-VV-006.
Spent caustic draining from the bottom of the vessel 05-VV-006 is done manually.
Independent low-level alarm switches are provided in the vessel. On actuation of level
alarm low in the vessel is indicated by LALL-1903, SDV-1901 provided on spent caustic
outlet line shall close. This feature shall prevent escaping of LPG with spent caustic
during spent caustic draining.
During Caustic make up, normally caustic circulation should no be stopped and strength
of spent caustic solution should be increased by gradual draining and equivalent make up
by 05-PA-025A/B. Quantity of caustic make up in indicated by FI-1901B.
PSV-1901 & 1902 are provided on 05-VV-006 top, whose discharge is routed to flare
header. It prevents vessel from getting over pressurized in case of external fire. LI-1901B
with LAL has been provided for measuring the level of the vessel. 05-VV-006 always
operates with full of liquid, without any vapor space.
Spent Caustic degasser 05-VV-016 is a vertical vessel connected with flare. It receives
caustic from LPG caustic wash, Light Naphtha, Kero/ATF wash system. Vapors
disengaged from caustic solution escape to flare and spent caustic is pumped out to ETP
by spent caustic pumps 05-PA-043A/B. LI-1911 with LAL/LAH has been provided for
measuring level in the vessel. Independent low level alarm switches are provided in the
vessel. On actuation of level alarm low in the vessel is indicated by LALL-1914, SDV1904 provided on spent caustic degasser outlet line shall close. This feature shall prevent
escaping of hydrocarbon vapors with spent caustic during pumping.
4.12.1.B
LPG carries with it fine droplets of caustic solution which can make product corrosive if
stored as such. Therefore to remove these traces of caustic solution LPG water wash
vessel 05-VV-007 is provided. LPG water circulation pump 05-PA-018A/B takes suction
102
from 05-VV-007 bottom and discharges water back to vessel through the static mixer 05Jv-003. Circulating water flow measures through FI-1903B in DCS.
Water mixes with LPG in 05-JV-003 results in its water saturation. An inter phase of
alkaline water and water washed LPG is formed in 05-VV-007. LI-1904B with LAL
shows the level of the vessel. Water washed LPG floats on top of water in the vessel.
Water saturated caustic free LPG is routed to LPG coalescer 05-EE-008.
Water entering with LPG settles down in lower portion of 05-VV-007. This alkaline water
draining from the bottom of the vessel 05-VV-007 is done manually. Independent low
level alarm switches are provided in the vessel. On actuation of level alarm low in the
vessel is indicated by LALL-1906, SDV-1902 provided to arrest escaping of washed LPG
with water during draining. Quantity of water make up to 05-VV-007 by 05-PA025A/B is
indicated by FI-1904B.
PSVs 1903/1904 are provided on 05-VV-007 top to prevent it from over pressurization
due to exposure of vessel in the external fire. 05-VV-007 always operates with full of
liquid, without any vapor space.
From the LPG Water Wash vessel 05-VV-007 the top portion is sent to LPG Coalescer
LPG Coalescer 05-VV-008 is provided for reducing saturated water content in LPG from
0.2 wt% to 80 ppm. Coalescer element is provided inside the vessel to meet the abovementioned parameter. Retention time is 4 hours for enabling water droplets to coalescer
and separate efficiently from LPG. LI-1910B shows the coalescer level in DCS. From the
Coalescer, the product is sent to LPG storage under pressure control of PIC-1912 through
PV-1912. In the common product line there is a product tapping for LPG Vaporizer. FIC1906 measures net LPG quantity from coalescer to storages.
Water collected in the boot of 05-VV-008, is sent to OWS/CS under level control. Water
draining from boot is done manually. On actuation of level alarm low in boot, as
indicated by LALL-1909, SDV-1903 provided on outlet water line shall close. This
feature shall prevent escaping of product with during water draining. Two PSVs
1905/1906 set at 15 Kg/cm2 are provided on the coalescer 05-VV-008, whose discharge is
routed to flare header. It prevents vessel from getting over pressurized in case of external
fire. 2 line connecting flare header with upstream of PSVs has been provided to
depressurize the vessel to flare.
103
Light Naphtha from light naphtha cooler 05-EE-019 is routed for caustic wash.
Light Naphtha is admitted in Light Naphtha caustic wash drum 05-VV-009 through a
mixing valve HIC/HV-2001 Caustic circulation pumps 05-PA-019A/B, taking suction
from bottom of 05-VV-009 and discharging into 05-VV-009 through mixing valve HV2001 are provided. 10% vol caustic solution is circulated by these pumps where it is
mixed with Naphtha. Mixing results in conversion and transfer of H2S, phenols
mercaptan & other chemicals to caustic solution. Depending on efficiency of mixing in
the mixing valve, reduction of above chemicals shall take place. Mixing of the two
streams can be improved by throttling the stream valve with the help of HIC-2001.
reduced port opening of the mixing valve increases stream velocity through the valve,
resulting in better energy transfer to streams for mixing. However, impact of additional
pressure drop due to mixing valve throttling on run down control valve and upstream
system should be carefully evaluated and monitored. Hydrocarbon phase separates out
from caustic in 05-VV-009 due to adequate availability of residue time. Naphtha over
flows from top of 05-VV-009 to water wash vessel 05-VV-010 through another mixing
valve HIC-2002/HV-2002. Caustic solution settled in 05-VV-009 bottom is re-circulated
again on repeated circulations, strength of caustic goes down to less than 75% of its
initial strength due to picking up of compounds mentioned above. This is called spent
caustic and is drained out through 4 line to spent Caustic water degasser 05-VV-016.
Spent caustic draining from the bottom of the vessel 05-VV-009 is done manually.
Independent low level alarm switches are provided in the vessel. On actuation of level
alarm low in the vessel is indicated by LALL-2003, SDV-2001 provided on spent caustic
outlet line shall close. This feature shall prevent escaping of fresh caustic solution with
spent caustic during spent caustic draining.
During Caustic make up, normally caustic circulation should not be stopped and strength
of spent caustic solution should be increased by gradual draining and equivalent make up.
Quantity of caustic make up is indicated by FI-2003B.
PSV 2001/2002 are provided on 05-VV-009 top, whose discharge is routed to flare
header. It prevents vessel from getting over pressurized in case of external fire. LI-2004B
104
with LAH/LAL has been provided for measuring the level of the vessel 05-VV-009
always operates with full of liquid, without any vapor space.
Spent caustic degasser 05-VV-016 is a vertical vessel connected with flare. It receives
caustic from LPG caustic wash, hydrocarbons vapors disengaged from caustic solution
escape to flare and spent caustic is pumped out to ETP by spent caustic pumps 05-PA043A/B. LI-1911 with LA/LAH has been provided for measuring level in the vessel.
Independent low level alarm switches are provided in the vessel.
On actuation of level alarm low in the vessel is indicated by LALL-1914, SDV-1904
provided on spent caustic degasser outlet line shall close. This feature shall prevent
escaping of hydrocarbon vapors with spent caustic during pumping.
4.12.2.B
Caustic washed naphtha carries with it fine droplets of caustic solution, which can make
product corrosive if stored as such. Therefore these caustic solution traces need to be
removed from naphtha before sending it to storage. For this purpose, through water wash
is given to Naphtha. Naphtha water wash vessel 05-VV-010 is provided for this purpose.
Light Naphtha water circulation pump 05-PA-020A/B takes suction from 05-VV-010
bottom and discharges water back to vessel through HV-2002. Circulating water flow
measure through FI-2002B in DCS.
Water mixing with Naphtha in HV-2002 results in its water saturation. An inter phase of
alkaline water and water washed naphtha is formed in 05-VV-010. LI-2008B with
LAL/LAH shows the level of the vessel. Water washed naphtha from the top of the
vessel (caustic free) is routed to light naphtha storage by Light Naphtha Product pump
05-PA-041A/B under flow control of FIC-2004 through FV-2004. Stabilizer bottom level
controller LIC-1702 can also be cascaded with this flow controller to maintain level in
the stabilizer bottom.
Water entering with Naphtha settles down in lower portion of 05-VV-010. This alkaline
water draining from bottom of the vessel 05-VV-010 is done manually. Independent low
level alarms switches are provided in the vessel. On actuation of level alarm low in the
vessel is Indicated by LALL-2007, SDV-2002 provided on alkaline water line to spent
105
caustic water degasser shall close. This feature shall prevent escaping of washed naphtha
with spent caustic during water draining. Quantity of water make up to 05-VV-010 is
indicated by FI-2005B.
PSVs 2003/2004 are provided on 05-VV-010 top to prevent it from over pressurization
due to exposure of vessel in the external fire. 05-VV-010 always operates with full of
liquid, without any vapor space.
4.12.3.A
Kero/ATF from Kero/ATF cooler 05-EE-024 / 23C is routed for caustic water wash.
Kero/ATF is admitted in Kero/ATF caustic wash vessel 05-VV-013 through a mixing
valve HIC/HV-2201. Kero/ATF Caustic circulation pumps 05-PA-023A/B, taking suction
from bottom of 05-VV-013 and discharging into 05-VV-013 through mixing valve HV2201 are provided. 10-vol% caustic solution is circulated by these pumps where it is
mixed with Kero/ATF. Mixing in the valves results in conversion and transfer of H 2S,
phenols, mercaptans & other chemicals to caustic solution. Depending on efficiency of
mixing in the mixing valve, reduction of above chemical shall take place. Mixing of the
two streams can be improved by throttling the mixing valve with the help of HIC-2201.
Reduced port opening of the mixing valve increases stream velocity through the valve,
resulting in better energy transfer to streams for mixing. However, impact of additional
pressure drop due to mixing valve throttling on rundown control valve and upstream
system should be carefully evaluated and monitored. Hydrocarbon phase separates out
from caustic in 05-VV-013 due to adequate availability of residence time. Kero/ATF
overflows form top of 05-VV-013 to water wash vessel 05-VV-014 through another
mixing valve HIC-2202/HV-2202. Caustic solution settled in 05-VV-013 bottom is recirculated again. On repeated circulations, strength of caustic goes down to less than 75%
of its initial strength due to picking up of compounds mentioned above. This is called
spent caustic and is drained out through 2 line to spent Caustic/water degasser 05-VV016. LI-2202B measures the level in the Kero/ATF Caustic Wash drum 05-VV-013. Spent
Caustic draining from the bottom of the vessel 05-VV-013 is done manually. Independent
low level alarm switches are provide in the vessel. On actuation of level alarm low in the
vessel is indicated by LALL-2203, SDV-2201 provided on spot caustic outlet line shall
106
close. This feature shall prevent escaping of hydrocarbons with spent caustic during spent
caustic draining. During Caustic make up, normally caustic circulation should not be
stopped and strength of spent caustic solution should be increased by gradual draining
and equivalent make up. Quantity of caustic make up is indicated by FI-2201B.
PSV 2201/2202 are provided on 05-VV-013 top, whose discharge is routed to flare
header. It prevents vessel from getting over pressurized in case of external fire. LI-2202B
with LAL has been provided for measuring the level of the vessel. 05-VV-013 always
operates with full of liquid without any vapor space.
Spent Caustic degasser 05-VV-016 is a vertical vessel connected with flare. It receives
caustic from LPG caustic wash, Light Naphtha, Kero/ATF vapors disengaged from
caustic solution escape to flare and spent caustic is pumped out to ETP by spent caustic
pumps 05-PA-043A/B. LI-1911 with LAL/LAH has been provided for measuring level in
the vessel. Independent low level alarm switches are provided in the vessel. On actuation
of level alarm low in the vessel is indicated by LALL-1914, SDV-1904 provided on spent
caustic degasser outlet line shall close. This feature shall prevent escaping of hydrocarbon
vapours with spent during pumping to ETP.
4.12.3.B
Caustic washed Kero/ATF carries with it fine droplets of caustic solution, which can
make product corrosive if stored as such. Therefore these caustic solution traces need to
be removed from Kero/ATF water wash is given to Kero/ATF. Kero/ATF water wash
vessel 05-VV-014 is provided for this purpose. Kero/ATF water circulation pump 05-PA024A/B takes suction from 05-VV-014 bottoms and discharges water back to vessel
through HV-2202. Circulating water flow measures through FI-2203 B in DCS.
Water mixing with Kero/ATF in HV-2202 results in its water saturation. An inter phase of
alkaline water and water washed Kero/ATF is formed in 05-VV-014. LI-2205B with LAL
shows the level of the vessel. Water washed Kero/ATF floats on top of water in the
vessel. Water saturated with caustic free from Kero/ATF settles down in lower portion of
05-VV-014. This alkaline water draining from the bottom of the vessel 05-VV-014 is
done manually. Independent low level alarm switches are provided in the vessel. On
actuation of level alarm low in the vessel is indicated by LALL-2206, SDV-2202
107
provided on alkaline water line to Spent Caustic/water degasser shall close. This feature
shall prevent escaping of washed Kero/ATF with spent caustic during spent caustic
draining. Quantity of water make up to 05-VV-014 is indicated by FI-2204 B.
PSVs 2203/2204 are provided on 05-VV-014 top to prevent it from over pressurization
due to exposure of vessel in the external fire. 05-VV-014 always operates with full of
liquid without any vapour space.
From the Kero/ATF water wash vessel (05-VV-014) the top portion is sent to Kero/ATF
Coalescer. Kero/ATF Coalescer 05-VV-015 is provided for reducing water content in
Kero/ATF 0.2 wt% to 100ppm. Coalescer element is provided inside the vessel to meet
the above-mentioned parameter. Retention time is 4 hours for enabling water droplets in
coalescer and separate efficiently from Kero/ATF. LI-2210 B shows the coalescer level in
DCS. From the coalescer, the product has sent to Kero/ATF storage under flow control of
FIC-2206 through FV-2206. in the common product line, product tapping for Kero/ATF
to Gas oil rundown has provided. FI-2205 measures net Kero/ATF quantity from
coalescer to storage.
Water collected in the boot of 05-VV-015, is sent to OWS under level control. Water
draining from boot is done manually. On actuation of level alarm low in boot, as
indicated by LALL-2209, SDV-2203 provided on outlet water line shall close. This
feature shall prevent escaping of product with during water draining. Two PSVs
2205/2206 set at 15 Kg/cm2 are provided on the coalescer 05-VV-015, whose discharge is
routed to flare header. It prevents vessel from getting over pressurized in case of external
fire. 2 line connecting flare header with upstream of PSVs has been provided to
depressurize the vessel to flare. Kero/ATF from coalescer (VV-15) sent to Kero/ATF salt
dryer for better removal of moisture/water from the kerosene. In Kero salt dryer,
Kero/ATF goes in at the bottom and exits at the top of the dryer. Continuos removal of
brine water is carried out once in a shift to avoid accumulation of water in dryer. For
further details, please refer to kero/ATF salt dryer chapter.
4.13
108
Hydrochloric acid from the salt in the crude and hydrogen sulphide dissolved in the crude
(or formed from the dissociation of heavy Sulphur compounds present in crude)
concentrates in the overhead system. Both form of acid solutions, which are corrosive.
Measures must be taken to over come their effects. The overhead system including
condensers and reflux drum is made of carbon steel. In order to protect this section,
caustic solution, ammonia solution and corrosion inhibitors are added at various points.
The purpose of injection caustic at the outlet of desalter is to achieve better mixing of
these chemicals with crude and neutralize the acids and salts, mainly HCL and H 2S as
soon as they are formed (at a temp. Of 120 C and above) the reaction products i.e. sodium
and ammonia salts go along with reduced crude. The balance acids and acid gases if any
will go up to the overhead system where ammonia is injected in the overhead vapor line
to neutralize. Amount of ammonia should be controlled in such a way that pH of reflux
drum water remains at 6.5+0.2.
Injection of caustic at the outlet of desalter should be maintained in such a way that the
salt formation should be low in the overhead circuit, which might scale up the overhead
condenser tubes.
A slightly acidic condition of the overhead system is desirable to keep ammonium salts in
solution, which if precipitates would foul and plug the condensers. Corrosion against
slightly acidic conditions is minimized by adding corrosion inhibitors in the overhead
vapor line. The inhibitor is also added in reflux line. Top section of the column is also
benefited from the injection of corrosion inhibitors mainly in the reflux line. These
inhibitors are high boiling compounds and can perform satisfactorily at higher column
top temperature also.
The amount of inhibitor injected depends upon the type of inhibitor used and generally
specified by the vendor. However slight adjustment is made by operating personal
depending upon iron content in the reflux drum water. These inhibitors are filming
organic compounds, which cover entire metal surface of the system with a thin film. This
prevents contact of corrosive water with metal surface.
Various points of chemical injections are listed below:
4.13.1
CAUSTIC INJECTION
109
Caustic solution having strength of 47% is received from off sites through 3 header. It is
diluted to two different strengths for use in unit. Five caustic tanks are provided within
battery limit. One strong tank 05-TT-001 stores strong caustic solution with strength of
47% two tanks 05-TT-002A/B provided to store weak caustic solution with strength of 10
%.& two tanks, 05-TT-006A/B provided to store weak caustic solution with strength of
3.5% Each storage tank is provided with DM water connection for dilution purpose. LIs
and overflow lines are provided on each tank. Care should be taken to ensure that tanks
are not pressurized due to inadequate relieving of air through tank vent.
Strong Caustic solution from 05-TT-001 is pumped by caustic make up pump 05-PA-033
to 10% caustic dilution tank 05-TT-002A/B from 05-TT-002A/B is pumped by caustic
make up pump 05-PA-032A/B to following destinations.
Dilute caustic solution from 05-TT-006A/B is pumped by Caustic injection pumps 05PA-031A/B to following destination:
4.13.2
Ammonia gas drawn from ammonia cylinder, brought from out side agency, is injected at
reduced pressure into ammonia solution vessel 05-VV-018A/B. DM water connection is
provided on ammonia vessel for preparing solution. Ammonia solution vessel is a vertical
vessel with a water seal on its vent to prevent escaping of ammonia while preparing
solution. Water seal will blow off during excess pressure build up in the vessel. Finally
prepared ammonia solution is injected by ammonia solution injection pumps 05-PA-
110
026A/B to Crude column overhead line. FI-2411 measures the net quality of ammonia to
crude column overhead.
4.13.3
DEMULSIFIER INJECTION
4.13.4
DM Water is received and stored at Wash water make up tank 05-TT-005. LI-2408 with
LAH/LAL and overflow lines is provided in the vessel. From 05-TT-005 wash water is
pumped by wash water makeup pumps 05-PA-040A/B to the following destinations for
water wash purpose.
111
4.14
Only operating experience with desalter can determine optimum operating conditions. No
two crude behave alike at the same desalting conditions, but all are affected similarly by
change in desalting conditions.
3.14.1.A
Water injection should be started only after the crude temp. reaches specified desalting
value and power is switched onto the grid. Initially the injection rate should be limited
between 2-6% of crude flow rate and point of injection should be just upstream of the
mixing valve. If crude is Napthenic, water injection should be considered upstream of
preheat trains.
112
The pressure drop across mixing valve should be adjusted to give the required degree of
desalting. The higher the total pressure drop (inclusive of mixing valve and desalter), the
more efficient the contact between the salt in the crude and the injection water. Too highpressure drop will result in excessive emulsification and poor separation of oil and water,
resulting in carry over of water in the desalted crude. A pressure drop between 1 to 2
Kg/cm2 is normally sufficient, which can be adjusted by manipulating mixing valves at
desalter inlet.
Optimum water injection rate and pressure drop across mixing valve should be
established to get the desired desalting of crude. Once this is done, the conditions should
be maintained steady and should be varied only for changes in feed rate and feed
quantities.
4.14.1.B
The oil-water interface level should be maintained below the centre line of the desalter
vessels to avoid escaping of water and sludge along with the crude, if sudden pressure
surge takes place. Incorrect operation of the interface level controller can result in more
water in desalted crude due to less hold uptime available for oil(high interface level) and
more oil carry over in brine water due to less hold uptime available for water (low water
level). Also too high an interface level may push battery mixture up between the
electrodes and cause them to short circuit.
4.14.1.C
Desalting temperature is another important variable, which affects oil water separation in
Desalter. Most crude oils have an optimum-operating temp. range of around 127 C for
Kero case and 123.5 for ATF case. Lower the temp. higher the viscosity of the oil that
113
slows down the separation rate. As crude conductivity and solubility of crude in water
increases with temperature operating beyond this range will lead to drop in grid voltage
and high amperage which imposes limitation on good separation. Excessive amperage
will eventually cause the circuit breaker to open, tripping the electric grid and rendering
the electrical system inoperable until the thermal relay is closed. Very high temp may lead
to vaporization of crude in the desalter.
4.14.1.E
DEMULSIFIER INJECTION
Tight crude water emulsions can be broken by use of demulsifying chemicals. The
amount of chemicals required to break the emulsion dependents on the nature of the
emulsion, type of crude and other operating conditions like residence time, temp. etc.
Required emulsification chemical injection rate should be established empirically for
optimum operation of desalting unit. Demulsifier soluble in Kerosene has been
considered for use in the unit.
4.14.1.F
The desalter electrical panel typically houses pilot lights, a voltmeter and ammeter. The
voltmeter gives the voltage across the primary circuit of the transformer. The ammeter
gives the current flow. These meters give an indication of the performance of the grids
inside the desalter. In case, crude water emulsion is too tightly bound or if the interface
level is too high there will be flickering of the pilot light, the amperage will increase and
the voltage will drop. Take corrective action to break the emulsion or reduce the interface
level.
For more details about the operation of desalter the vendors operating and maintenance
manual should be referred.
4.14.2
The quantity of crude oil vaporized during its passage through the atmospheric heater
depends on transfer temperature and the pressure at the flash zone of the column. In order
to achieve proper separation i.e. desired recovery of distillates a little over flash is
maintained by keeping the transfer temperature slightly on higher side. This quantity is
114
measured by FI-1504 and at normal capacity the flow is about 25/20 M 3/hr (about 6 to
9% vol. on crude charge feed). This also indicates the presence of liquid level in the trays
down below the GO draw off section. Dry operation of these trays should be avoided to
minimize coke-forming tendency. Maintaining excessive over flash flow will result in
more consumption of energy without any advantage & more RCO generation.
Lower heater coil outlet temperature will effect product quality more in lower section of
the column e.g. gas oils & below (by making then off spec due to carry of heavier
components from LR) and lowering down recovery as well as LR will contain more
lighter components. Yield & quality of products drawn from upper section of the column
may not be affected much.
Higher than normal coil outlet temperature enhance crude cracking possibility inside
heater tubes, leading to coke deposition and higher pressure drop. This may reduce
overall run length of the unit and may force a planned shut down. At the same time
specification of heavy products may not met and higher recovery may be experienced at a
given temp.
4.14.3
The effect of column top pressure is more pronounced on lighter streams. Lower column
top pressure aids in greater vaporization of all streams, particularly lighter streams.
Column operation with lower top pressure will make all side draw products and top
stream slightly heavier. There will be more load on overhead condensers and loss of
lighter components may take place from reflux drum to maintain normal operating
pressure. Higher than normal top pressure will have reverse effects.
Increase in column top pressure will increase column flash zone pressure also. Increased
flash zone pressure will result in lower product yield of all side off streams. The effect
will be reflected in LR also (bottom most stream) which will become lighter.
It is important to note that column pressure is largely dependent upon equilibrium
conditions in reflux drum. Efforts should be made to operate the column at the intended
design pressure only, depending upon type of crude. During normal operation total
condensation of overhead stream is expected and thus both the control valves of split
range pressure controller (on FG make up side as well as flare side) shall remain shut.
115
4.14.4
overcome effect of change in top temp. HN draw off should be suitable adjusted to
maintain its draw off temp.
Too low top temp. will start steam condensation at the top section of the column, which
may increase rate of corrosion in the top section of the column.
4.14.5
The circulating Reflux mainly removes heat form the column and reduces the vapour
load in the particular section of the distillation column. The flows of the three circulating
refluxes: Heavy Naphtha CR, Kero, CR and GO CR are controlled by respective duty
controllers respectively. Increase of circulating reflux flows will result in higher crude
preheat temp. by greater heat recovery in heat exchanger train.
Even through various CR return temperature will be governed by functioning of
respective duty controllers, these may be maintained by operating the bypass of
respective exchangers also. Any change in circulating reflux affects quality and quantity
of its own product and those products, which are immediately above and below it. The
effect of change of CR variation on other streams is not discussed, as it is not that much
pronounced.
A higher than normal Heavy Naphtha CR flow will remove more heat from column in
HN CR zone. When this heat removal becomes excessive, column top temp. shall also
show a tendency of decline, requiring lower top reflux flow. This will cause lower liquid
transport between top tray and HN draw off, causing poor fractionation between overhead
and HN. It will come down, as there will be less overhead product to condense. The
kerosene cut will be correspondingly lighter.
116
High GO CR flow will tend to lower the temp. resulting in lighter product on this tray.
Thus GO will be lighter and Kerosene will also be lighter.
Likewise a high GO CR will tend to lower the draw off temp. of GO product, making GO
and LR lighter.
4.14.6
The withdrawal (Draw off) temperature of the products is controlled by withdrawal rate
of the streams. Increase in product withdrawal temperature makes it heavy. An increase in
withdrawal rate of one side stream increases the withdrawal temperature and boiling
ranges of all side streams down below in the column unless their withdrawal rates from
the column are also reduced correspondingly.
For example, if kerosene product withdrawal rate is increased, the internal reflux in the
trays below the draw off tray will be reduced. Thus end point of kerosene is increased.
Increased kero draw off will have a tendency of lowering availability of material on GO
tray, requiring corresponding reduction in GO draw off to maintain same FBP. If GO
withdrawal rate is not reduced to maintain its draw off temp. its boiling range will shift
upwards.
Similarly reverse action takes place when withdrawal temp. is lowered by reducing the
quantity of withdrawal.
4.14.7
4.14.7.A
STRIPPING STEAM
STRIPPING STEAM IN FRACTIONATING COLUMN
Super heated MP steam is used to strip kero/ATF and GO at the bottom of the crude
column. The stipulated bottom steam rate should be maintained by FIC-1508 & FIC-1509
for economical stripping and normally it should not be varied. Lowering the steam rate
below the specified optimum value may leave some GO in the LR and this is undesirable.
Exceeding the design steam rate might cause entrainment of LR into the GO because of
excessive vapour velocity. Also it will ultimately overloads the overhead condenser
system.
117
4.14.7.B
The flash points (IBP to some extent) of Kero/ATF and GO products can be controlled by
varying the stripping steam rate to respective strippers.
It is advisable not to exceed the steam/ vapour flow rate beyond the design value in any
of product strippers viz. HN, kero and GO strippers as this will tend to lift some of the
high boiling material into atmospheric column. If the desired flash point could not be
obtained by designed rate of stripping steam, the draw off of product just above it may be
increased to enhance its IBP. Use of MP steam in any of the strippers shall cause
reduction of partial pressure of hydrocarbon and may result in evaporation of lighter
components from the stock. This may also be reflected in terms of flash point of the
product.
Stabilizer removes the majority of butane and lighter hydrocarbons from the naphtha
stream. These are recovered as overhead fuel gas product. High stabilizer top temp. will
make overhead product heavy; even C5, C6 components may be carried into fuel gas and
condensing in the distribution line after wards. Lower top temp. attained by increasing
top reflux will reduce heavier ends in fuel gas.
RVP of LPG may go up on account increased presence of C3 and lower components. To
correct the situation, stabilizer top pressure should be lowered a bit. Too low bottom
temp. may result in higher than allowable vapour pressure (RVP) of naphtha and at the
same time it will reduce yields of overhead streams.
Low stabilizer top pressure in the column will cause higher amount of hydrocarbon
compounds (C3 and C4) to escape into overhead system. This has got similar effect as
that of higher temp. in the column.
4.15
CURDE TYPE
LS
HIGH
NIGERIA
SULPHU
N
Total Flow m3/hr 510
Tput: MT/D
10500
CIT
263
R
520
10800
274
118
BH
FARCADOS
510
10500
264
530
10800
263
COT
365
COT Maintained 365
Furnace
(FF01)
FC-1401 M3/Hr
FC-1402 M3/Hr
FC-1403 M3/Hr
FC-1404 M3/Hr
Top
141
151
150.3
141.3
Press 2.3
Kg/Cm2
TOP Temp 0C
114
Withdrawal Temp
HN
156
SKO
208
GO
304
Withdrawal Rate
HN
30
SKO
120
GO
125
CC-05
TOP 64
TEMP. 0C
CC-05 Top Pres. 10.5
375
375
365
360
351
370
150
161
153
144
141
153
151
141
154
151
156
147
2.3
2.3
2.3
111
114
113
150
210
311
154
208
304
157
211
302
25
95
111
67
30
110
120
65
36
74
177
10.5
10.5
10.5
Kg/Cm2
4.16
Sl.
No
1
Equipment
Critical
Parameter
Furnace Pass 80-140
flow
m3/hr
Furnace COT
365 375 C
Instrument
Provided
FRC
pa
TC
cascaded
with PC on
oil or PC on
gas
119
Remarks
1)Ensure flow above low alarm limit
2)Ensure equal pass flow through all
passes
1)Ensure steady oil temp.
2)Ensure steady oil pressure.
3)Ensure steady gas pressure
4)Ensure steady atomizing
steam pressure.
5)Ensure
healthy
burner
Column
Pressure
Over Flash
15-20 m3/hr
Column
Bottom Level
40-50%
Furnace O2
02-03%
Furnace arch -5 to
pressure
mmwc
condition
PC
split
2)Ensure
good
desalter
between FG operation
& Flare
3)Ensure steady top temp.
+2 PI
10
11
to TI
TI
LDIC
120
12
Desalter
Amps
< 5 amps
13
Desalter
Pressure
11.5 to 12.5
14
15
Caustic
/ 40 to 50%
water
wash
vessels inter
phase level
LCV
16
Boot Water
Chloride
content
High
Fe content
High
PG / PC on
4)Ensure
desalter
good
operation
1)Ensure 30-40% level
2)At low-level objective will
not solve. Feed H2S may not get
removed
3)At
high-level
caustic
solution will be carried over to storage
tank & wll result in failure of Cucorrosion test.
ppm
dozing
121
CHAPTER-5
UTILITIES SYSTEM
122
UTILITIES SYSTEM
5.1
INTRODUCTION
Please refer following P & IDs for major utility distribution description:
3551-05-02-41-0141 Rev.2 LP steam, SW, PA System
3551-05-02-41-0142 Rev.2 CW, DMW Distribution Systems
3551-05-02-41-0143 Rev.2 Instrument Air, Fuel oil, Fuel Gas distribution system
3551-05-02-41-0144 Rev.1 MP Steam/HP Steam/BFW system
3551-05-02-41-0145 Rev.2 Flare System
3551-05-02-41-0146 Rev.2 CBD System
3551-05-02-41-0147 Rev.1
INSTRUMENT AIR
DCS. Various instrument air tapping are taken from this header. Instrument air is used as
motive force for pneumatically operated control valves.
5.3
PLANT AIR
Refer P & ID No.3551-05-02-41-0141 Rev.2
A 4 plant air header supplies plant air to the unit. The header is provided with an
isolation valve and a spectacle blind at the unit battery limit. The pressure of the PA at the
battery limit is indicated by PI-4104. FI-4102 indicates PA flow to unit. A number of
utility Hose stations are provided for plant from this 4 header. For decoking of crude
furnace separate 4 tapping are taken from main header. 1 size plant air tapping is
provided to seal pot.
5.4
COOLING WATER
05-EE-019
05-EE-022A/B/C/D
LR cooler II
05-EE-021
LR cooler II
05-EE-111A/B
LR cooler I
124
05-EE-023A/B/C
05-EE-024
Kero/ATF cooler
05-EE-016A/B/C
05-EE-017A/B/C
05-VV-038
05-VV-030
CBD Drum
Furnace
05-EE-019B
LN cooler
05-EE-016A/B/C/D/E/F
05-EE-017A/B/C/D
05-EE-110A/B
LGO coolers
05-EE-109
Kero I cooler
05-EE-13A/B
Brine cooler
Above all, CW supply is provided for all pumps bearing & seal flush cooling in the unit.
5.5
SERVICE WATER
05-PA-032A/B
05-PA-005A
05-PA-014A
CBD Drum
05-VV-034
Brine Degasser
125
05-FD-001
05-FD-002
5.6
DM WATER
LP STEAM
To 05-VV-029/05-EE-29
To 05-VV-001A
To 05-VV-001B
To 05-CC-001
To 05-CC-002
126
To 05-CC-003
To 05-CC-004
To 05-CC-005
To 05-CC-006
To 05-PA-051A/B/C
To 05-PA-011A/B
To 05-PA-007A/B
To 05-PA-012A/B/C
To 05-PA-010A/B/C
To 05-PA-002A/B/C/D/E
To 05-PA-09A/B
To 05-PA-102A/B
To 05-PA-103A/B
To 05-PA-104A/B
To 05-PA-45A/B
05-FF-001
As snuffing steam
To Air Pre-heaters
05-VV-035
05-VV-030
05-VV-026
5.9
MP STEAM
127
Decoking steam
Atomizing steam
MP to LP steam
5.10
HP STEAM
4 HP Steam to de-superheat by Boiler Feed Water injection in steam de-superheater 05-MD-001. The TIC-4406 maintains MP Steam temperature at de-superheater outlet by manipulating BFW injection into de-super-heater.
5.11
128
LPG can be vaporized in LPG vaporizer 05-VV-029 with the help of LP steam to produce
FG. LPG flow to 05-VV-029 is indicated by FI-3202. It is admitted into vaporizer under
level control LIC-3202. Independent high & low-level alarms are also provided on LPG
vaporizer. LPG vaporizer pressure is maintained by 05-PIC-3202 by manipulating PV3202 on LP steam flow to vaporizer. Vaporized LPG is admitted into fuel gas KOD 05VV-028. FG from combined FG header is also being routed directly into 05-VV-028 for
condensate de-entertainment. FG from this KOD is taken out for distribution through a
12 header under pressure control PIC-3204. PSV-3201 & PSV-3202 are provided to
protect 05-VV-029 & PSV-3203/3204 is provided to protect 05-VV-028 from over
pressurization. Drain of 05-VV-029 & 05-VV-028 are normally routed to flare due to
flashing nature of streams handled.
FG consumption in AU-V is indicated by FI-4304. PI-4304 measures pressure of the FG
header at battery limit. Local pressure & temperature gauge have been provided at battery
limit. Fuel gas is delivered to crude charge heater (05-FF-001) as fuel and Atmospheric
Column reflux drum (05-VV-002) & fuel oil surge drum (05-VV-026) to maintain
pressure. It is also connected as purge to flare header. AU-V LPG vapouriser can be used
as a fuel gas to CRU fuel gas system, in case of requirement.
Modification is made to use AU5 LPG vaporizer to cater the requirement of GR Fuel gas
system. Its flow is maintained by 5FCV 257A. A new line has also been laid out to cater
the fuel gas requirement for MSQ plant during commissioning via 5PCV0204.
5.12
FUEL OIL
129
have been provided near respective heaters. Fuel oil flow to heaters is measured by flow
meter on respective FO (supply) header. A return fuel oil line has been provided from
furnace. Return line has been provided with a globe valve, shut down valve & flow
meters. About 50% of the supply fuel oil allowed to return through this line. This
circulation of fuel oil to atmospheric furnace is recorded by flow differential recorder.
Fuel oil return header with bypass has been provided from supply line to allow
independent FO circulation for the furnace.
5.13
FLUSHING OIL
Suction line
b) 05-EE-022A/B/C/D
Shell side
c) 05-EE-021
Shell side
d) 05-EE-010A/B/C/D
e) 05-EE-009A/B
Shell side
f) 05-EE-007A/B/C
g) 05-EE-006A/B
Shell side
h) 05-EE-001
Shell side
i) 05-EE-002
Shell side
j) 05-EE-003
k) 05-EE-004
l) 05-EE-005
Shell side
130
m) 05-EE-028A/B/C/D
Shell side
n) 05-PA-002A/B/C/D/E
Suction line
o) 05-PA-001A/B/C/D/E
Suction line
p) 05-PA-045A/B
Suction line
q) 05-EE-102A/B
Shell side
r) 05-EE-103A/B
s) 05-EE-103C
t) 05-EE-104A/B
Tube side
u) 05-EE-105A/B
v) 05-EE-105C/D
w) 05-EE-105E
x) 05-EE-106A/B
Shell side
y) 05-EE-106C/D
Shell side
z) 05-EE-107A/B
aa) 05-EE-107C/D
ab) 05-EE-108A/B
Tube side
ELECTRIC SYSTEM
Electrical load for AU-5 is anticipated as 3220 KW. In the event of power failure back up
Emergency power supply arrangements has provided. Electrical system of AU-5
compromises of a Number of sub-systems. They are briefly described as under.
5.14.1
05-PA-001A/B/C/D/E
05-PA-002A/B/C/D/E
05-PA-51A/B/C
RCO pumps
131
Above motors are termed as HT motors. Remaining all other motors are fed by lowtension feeder at 415 5%V, and 230 5%V, 3 phase, AC power.
Motor start/stop push buttons and local Ammeters are provided at local control station for
motors in field. However, local Ammeters are provided only for motors with rating 55
KW and above. All LT motors feed through switch fuse contractor are provided with
240V AC control supply. 110 V DC control supply is provided for all HT motors & motor
having rating exceeding 75 KW, & power motor control centre. Running status lamps for
pump are provided on control room auxiliary console panels as per P & ID for critical
motors with potential free contacts, similar to control room instruments.
5.14.2
PLANT ILLUMINATION
All plant lightings are provided with 230 10% V AC power. For maintaining emergency
lighting, emergency lighting fixtures are fed with 110 V DC power feeder, so that in the
event of power failure, minimum light in critical areas such as control room, sub-station
escape route etc. are sustained.
4.14.3
In the event of power failure, 110 V AC supply will remain available for a
maximum period of 60 min to above instrument to facilitate safe shut down of
process units. If power from main feeder is still not resumed plant instrument will
132
assume safe shut down position according to logic built in PLC. After power is
resumed DCS system and supervisory computer should be booted before reverting
back to normal operations.
5.15
EFFLUENT SYSTEM
All off-spec. hydrocarbon streams contaminated with water, water contaminated with
hydrocarbons/chemicals and such liquid streams that can not be disposed off directly are
collected & treated either for recovery of hydrocarbons or to render them harmless to
receiving stream or for both the purpose. For this purpose, slop system, CBD system,
OWS system, Sewer Water (SWS) and Amine drain system are provided.
These systems are described sequentially as under:
5.15.1 SLOP
Those off-spec. hydrocarbon streams that are not contaminated with water and need to be
disposed off are termed as dry slop. 10 size slop header is provided in the unit to collect
slop from AU-5 that can be routed to GRE /OMS slop tank.
5.15.2 CLOSED BLOW DOWN (CBD)
Refer P & ID No. 3551-05-02-41-0133 Rev.2
3551-05-02-41-0146 Rev.1
Those Hydrocarbon Streams that are either free of water or only slightly contaminated
with water are received in closed Blow Down (CBD) vessel, 05-VV-030. Such
Hydrocarbon streams are generated especially during shut down periods when equipment
& systems are drained under gravity to clear hold up oil. The hydrocarbon in the CBD
vessel should be received at a temp. Well below flash point of lightest component present
inside.
Closed Blow Down network helps reducing amount of hydrocarbon finding its way to
effluent treating facility via OWS during equipment draining. Uncontaminated
hydrocarbons from equipment draining is collected & routed to CBD vessel via CBD
system covering entire unit equipment.
133
Two 6line closed blow down headers run across plot AU-5. These are provided with
clean out pit at header ends with Flushing oil connection to flush heavy congealing
hydrocarbon material accumulated in header, if any. One utility connection is also
provided on each CBD header end, close to FLO connection to flush CBD headers with
any other utility. However, care should be taken to avoid steaming of CBD header, as line
is not designed for steam out conditions due to absence of expansion provisions.
05-VV-030 is provided within AU-5 battery limit. CBD drum is a horizontal drum
located underground in a pit. The drum is provided with a coil through which cooling
water or LP steam can be passed. Hydrocarbons mixed with slight water are allowed to
enter in this drum from where Hydrocarbon is pumped out by CBD pump 05-PA-046 to
existing crude/slop header. LAH-3302 and LAL-3302 are provided to auto start and auto
stop the CBD pump. LI-3301B indicates the level of the drum. TI-3301 & PI-3301
indicates the temp. of the contents in the CBD drum & pressure inside drum. Under
normal condition, it is expected to remain at atmospheric pressure. A small purge of
steam is provided at the vent of the drum to guard against lighting and static electricity
hazards.
One coil is provided inside CBD drum through which either cooling water can be
circulated or LP steam can be introduced. Cooling water shall be introduced to bring
down temp. of hot material drained & accumulated inside vessel while LP steam can be
introduce in the same coil after isolating cooling water to decongeal/heat-up accumulated
heavy material inside vessel & bring it to pump-able viscosity. TI-3302 indicates temp. of
contents going out of CBD vessel.
4.15.3 OILY WATER SEWER (OWS)
This system is also called OWS system is mainly to collect water contaminated with
hydrocarbon oils. Such streams are usually generated during equipment draining &
flushing during routing operation. Streams suitable for OWS are also generated as a result
of floor washing, cleaning of spilled oils etc. Streams suitable for OWS should never be
routed to CBD as it may ultimately lead to receipt of lot of water in slop tanks. Drained
streams at ambient temperature received through OWS fennels etc. are routed to ETP
134
through a combined header. All equipments having CBD connections are normally
provided with OWS/SWS connection on following basis:
All continuous draining (HC bearing streams) having CBD connections are
provided an additional connection to OWS.
All intermittent draining (HC bearing streams) are provided a CBD connection
and connections to OWS.
Pump base plates, TSV discharges and floor washing are also routed to OWS. Care
should be taken that at no time any spark reaches vapour space of OWS fennels. This
may result in explosion immediately there or elsewhere in network wherever explosive
mixture of Air & Hydrocarbon vapours is present is appropriate for explosion.
5.15.4
SWS are similar to OWS and are routed to ETP separately through underground piping.
AT ETP provision to route SWS to OWS is also provided. The SWS thus shares the OWS
load as & when necessary.
Those effluent streams that contain only traces of hydrocarbon or are completely free of
oil should be diverted to SWS.
Storm channel around the plant is an open channel. As streams of storm channel leave the
plant without any separation or treatment, free Hydrocarbons should not be allowed to
escape in storm channel. Elaborate arrangement exists to handle oil free effluent of unit.
Effluent finally escaping through storm sewer without any treatment must meet statutory
specifications for safe disposal.
5.15.5 AMINE DRAIN SYSTEM
Refer P & ID No. 3551-05-02-41-0148 Rev.2
Drained Amine streams from amine absorber (05-CC-006) and Amine
135
Settler (05-VV-004) that is either free of water or oil or slightly contaminated with water
is received in 05-VV-033 (Amine Sump). Amine sump is provided within AU-5 battery
limit.
Amine Regeneration unit. LI-4801 with LAL/LAH indicates the level of the sump. TG4802 shows the temperatures of the contents in the amine sump.
One coil is provided inside amine pump through LP steam can be introduced to boil out
the contaminated water in amine. TG-4801 and PG-4801 indicates the temp. and pressure
of contents going out of Amine drain sump.
4.15.6 FLARE SYSTEM
Refer P & ID No. 3551-05-02-41-0133 Rev.2, 3551-05-02-41-0145 Rev.1.
In the event of abnormal operating conditions/emergencies, the hydrocarbon operating
system may get pressurized. In order to prevent this pressure form shooting up and
crossing design valves of respective system/equipment and causing accident and/or
equipment damage, it may become necessary to relieve some amount of non-condensable
hydrocarbon vapors to system that renders them harmless. For this purpose, a network of
flare headers is provided for collection of vapors in unit to which all relevant equipments
are connected.
Flare lines should be tested pneumatically because of line support considerations. Entry
of steam and condensate in flare headers should be avoided as it may lead to
extinguishing of main flare
The combined flare header enters flare knock out drum 05-VV-032 for de-entrainment of
condensate droplets. Local instrument is provided on 05-VV-032. LI-032 with LAH/LAL
is provided on flare KOD to indicate high and low condensate level. LSHH/LAHH-3308
also provided in the vessel. It will open SDV-3310 on vessel bottom outlet. Similarly,
LALL-3307 will close SDV-3301 & avoid vapor break through it. CBD vessel requires
manual draining. One isolation valve with a spectacle blind in between has been provided
on flare header at battery limit of the unit. A 2 fuel gas connection has been given to the
flare header for purging purpose RO-4502 is provided on FG purge line to flare to
maintain & control FG pressure entering flare header. The FG purge is provided in flare
header to prevent vacuum formation due to condensation of condensable hydrocarbons
136
05-VV-016
05-VV-020
FO surge drum
05-VV-026
05-VV-014
05-VV-013
Kero/ATF Coalescer
05-VV-015
LPG Coalescer
05-VV-008
05-VV-007
05-VV-006
05-VV-025
05-VV-010
LPG drum
05-VV-029
05-VV-028
05-VV-009
05-CC-001
Naphtha stabilizer
05-CC-005
05-VV-002
05-VV-003
05-CC-006
Following equipments of AU-5 are also connected with same 24 flare header:
137
05-EE-017A/B/C/D
05-PA-005A/B/C
05-PA-006A/B/C
05-PA-014A/B
05-PA-008A/B
05-PA-041A/B
138
CHAPTER-6
NORMAL START-UP PROCEDURE
INTRODUCTION
Start up and shut down are the most critical periods in operation of any process unit. It is
then that the hazardous possibilities for fire and explosion are highest. Start up and
normal operating procedures of all the units are described in this section.
The hazards encountered most frequently in start up and shut down of units are
accidental mixing of air and hydrocarbons and contacting of water with hot oil. Other
hazards primarily associated with start up are excessive pressure, vacuum and
thermal/mechanical shocks. These can result in flares, explosions, destructive pressure
surges and other damages to unit as well as injury to personal.
Fires occur when oxygen and fuel vapor or mists are mixed in flammable proportions and
come in contact with an ignition source. They may run out of control or touch off
devastating explosive. Pressure surge from unplanned mixing of water and hot oil may
cause damage of equipment and/or loss of valuable production. Extensive costly down
time on process unit may result. Fires usually follow if the explosive bursts lines or
vessels. Following are the highlights of the operation of AU-5. Operating conditions
given here are for AM crude case. Suitable changes in operating conditions should be
made as per operating conditions given in sec. 5.6.1 for specific of operation.
6.2
Start up summary for various process sections is given in following pages to develop a
quick comprehension of start up strategy to be adopted. After mechanical completion of
the unit, it is steam purged for expelling air and kept under fuel gas pressure. After water
draining, cold crude circulation is established and water in the system is swept out. Crude
Charge Heater 05-FF-001 is fired. About 50% of normal flow is maintained through
heater coils. Transfer temp. is raised insteps to 120 C at a rate of 40 0 C/hr. The COT is
maintained for about four hours to remove residual water from the system by
evaporation. The transfer temperature is then further raised to 250 0 C at 300 C/hr. Hot
bolting of flanges and manhole covers likely to remain in hot service is carried out at this
stage by holding the temperature at around 2500 C during this activity.
Top temp. of the column will gradually rise. When the column top temp. reaches more
than 100 C steam will escape from the column and condense in overhead naphtha
condensers. As top temperature rises further, column pressure is slowly raised to its
normal value. Higher pressure will help in better condensation of vapors. As level starts
building up in atmospheric column reflux drum, refluxing can be started after draining
water.
05-FF-001 COT is then further raised to 300 C. The column top temperature and pressure
are maintained constant. When naphtha make increases that is indicated by rising level in
crude column overhead reflux drum V-02, it can be routed to the naphtha stabilizer
column or else it can be slopped. Stripping steam to crude column is admitted at this
stage and unit is brought out of circulation. When levels appear in the crude column side
stream strippers, line up circulating reflux circuits, and maintain strippers levels at about
50%. Water is to be drained before starting the circulating reflux pumps. 05-FF-001 COT
is then further raised to normal value of 375 C. Flow and temp. of all CR streams are
adjusted to maintain proper temp. Profile in the column. Line up all product circuits up to
battery limit. Start respective product pumps when level appears in the strippers. Route
all products to slop header initially.
Start diverting un-stabilized naphtha-to-naphtha stabilizer column. Once sufficient level
(about 70%) is built up in stabilizer column bottom, stabilizer column will be brought on
stream by gradually cutting in the heating medium (gas oil CR) in re-boiler. As
temperature of the stabilizer column rises, pressure will increase and level will appear in
the stabilizer reflux drum. When level appears in the stabilizer reflux drum, start
refluxing. Stabilized naphtha from stabilizer bottom is routed to storage tanks through
naphtha coolers. & LPG from stabilizer top is routed to Horton sphere after amine &
caustic wash.
LR at outlet of atmospheric column bottom is routed to slop header/ storage via product
cooler. When the normal transfer temp. of 375 C has been attained at normal crude feed
rate make necessary adjustments and normalize the operating conditions in atmospheric
section.
6.3
Preparation for start-up needs a complete review of the start-up procedure by the
operating crew. Activities of atmospheric Unit V should be co-ordinate with off sites,
utilities and other units.
Start up of the unit involves the following consecutive phases.
Hot circulation
PRELIMINARY PREPARATION
Prior to actual commissioning of the plant, it should be established that all preparatory
works have been successfully completed and all instrument/equipment are ready to
function. It is to be ensured that:
Blinds are installed as per master blind list. Each removal and insertion of a blind
should be noted and installed by the in-charge.
All vessels, piping, equipment are pressure tested, flushed and ready for service.
All rating equipment such as pumps, motors etc. have undergone functional test
successfully.
All instruments have been checked and calibrated. Controls should be kept on
manual as far as possible.
All safety valves are in position after setting lock open position. Spare valves
should be kept isolated as per P & ID stipulation.
Flare, amine drain, closed blow down, sewer and flushing oil systems are in
operable condition.
All related units are informed of the start-up plan (RSM / OMS/TPS/Water block)
Fuel oil and fuel gas blinds are removed and both headers charged.
Tightness, vacuum test and heater refractory dry out will form part of pre-commissioning
activities for the first start-up. For subsequent start-ups the tightness test and vacuum test
can be done in conjunction with the step of elimination of air.
Procedure of commissioning of Utilities / FO / FG / FLARE
1. STEAM
When dry steam starts coming from trap bypass, increase battery limit valve
opening.
Commission by the same procedure all coolers & condensers after displacing air.
2. FUEL OIL
Keep all the isolation & bypass valves of V26 split range pressure C/V.
Drain condensate from all LPDs and Vent through all HPVs & Vessel vent.
Back up gas in the system by opening V26 make up PIC bypass valve, at the same
time stop steam injection & close all vent & drains.
Drain water from all LPDs of the circuit & from V26.
Stop circulation. Allow to settle water for 2 hr. Drain V26 to minimum level.
Receive VR in V26.
Establish circulation.
3. FG COMMISSIONING
Provide steam hose connection at LG drain of VV28 FG KOD & of VV29 LPG
drum.
Start steaming through the all above points. Drain & vent from all available LPDs
& HPVs, & from filter drain.
Back up gas in the system by opening battery limit valve at the same time stop
steam injection & close all vent & drains.
4.
Drain water from all LPDs of the circuit & from V28/V29
FLARE COMMISSIONING
Provide steam connection if is not there at the furthest end of the system
Introduce steam & purge the system to flare for 2 hrs, drain condensate from
KOD drain, from B/L valve U/S flange W/O & U/S bleeder.
Maintain pressure 0.5 Kg/Cm2. Check & fix if any leakage is there.
6.3.2
Air from various equipment piping etc. is eliminated by steaming of various sections of
the unit can be carried out simultaneously or in a convenient sequence. The following
basic points should be taken care during steaming of the equipment systems.:
Cooling water to the condensers and product coolers to be isolated and water
should be drained out from the condensers, coolers etc.
Keep instrument tapping like PT, FT etc. isolated from main process piping.
For the purpose of air removal unit is divided into following circuits for steaming: 1. Crude Preheat Train I Circuit Before Desalter
1a) Old preheat train I before desalter consisting of
PA-01 5HC5001 EE-01 EE-02 EE-03 EE-04EE-05EE-06 Desalter
1b) New preheat train I section before desalter consisting of
EE-103A/B/C
5HC5002 --EE-102A/B
Desalter
EE-104A/B
EE-106A/B/C/D
EE-108A/B
F01 C01
EE-107A/B/C/D
EE-18A/B
LN from C-5 Bottom5TC1702
EE-19A/B**
EE-18C/D
FC 5106 AU1 rerun Section
HN to LN
**SOV1701HC2001BVV-09HC2002BVV-10PA041A/B5FC2004
LN to AU-I rerun section
LN R/D
HN / SKO
C1LC1510C4PA11EE-08A/BEE-03EE-23A/B/C
5FC1804
PA-06
**
5FC1701 CC-05
EE-18 C/D
** CRU drag stream, DHDS / Lab / MSQ unit wild Naphtha are joining at D/S of
Fc1701.
9) LPG PRODUCT CIRCUIT
LPG circuit is divided into following circuits
C5 top HIC 1701 E17 A-D V3
V03 top PRC 1701 FG system
V03 bottom PA-14A/B FC1703 C5 reflux
AU4 LPG
V03 bottom PA-14A/B - 5FC2503 SDV2501 VV-20
V20 top PC2501 FG
VV-20 Bottom PA-50 5FC2502 VV-20 (min. cir)
5FC2502 CC-06
C6 top VV-04 VV-06 VV-07 VV-08 5PC1912 LPG r/d
FI 3202 Vaporizer
Amine to and from C06 line steaming is also steamed.
The condenser bypass line through HIC 1701 also to be made air-free.
LP system connections are given at appropriate places on piping & equipment to
introduce LP steam in above sections. Before introducing steam, water to all coolers and
condensers should be isolated and drained. This is to avoid condensation of steam in large
quantity in these equipment due to flow of cooling media, i.e. cooling water. It may lead
to frequent hammering in unit equipment. LP steam from hose stations can also be used
to boost up external steam supply. Initially there may be condensation of steam inside
unit equipment due to cold equipment internals. In such conditions, LP steam supply may
need augmentation of small quantity of MP steam through heater pass flows and other
available points. Care should be exercised while using MP steam for steaming to ensure
that none of equipment is subjected to operating conditions exceeding their design
parameters. The low point drains of pipes and equipment should be kept open to remove
condensate. During initial steaming, line rust etc. may frequently keep coming and
chocking the drains may be rather frequent. Special care should be taken to ensure that
none of the drain points are chocked due to accumulation of foreign material. High point
vent should also be opened for air removal. Once system warms up, less steam will
condense in the system and few steam points may be pinched. Steaming is done till clear
steam stars coming out from all vents. Clear steam venting for at least four hours shall be
an indication of fairly good air removal. Excessively high steaming rate may dislodge
column internals and cause damage. Hence it is a good practice to keep a watch on steam
consumption during steaming.
No steam condensate should be allowed to get accumulated inside unit equipment.
Vigorous steam venting from various points of the unit is described below till be
continued for about 4 hours. It is expected that oxygen will be eliminated at the end of
this period. Samples may be checked from different locations to check that 02 content is
less than 1%.
During the period of steaming, systems should also be checked for leakage. Attend the
leaks by depressurizing the system. Reset and purge as applicable.
When sufficient steam comes out from all the vents and drains reduce steam inlet to
maintain positive pressure.
Following major points may be followed for steaming out of the unit:
a) Admit steam into the feed system by connecting temporary hoses to the crude oil
feed line at the battery limit of unit.
b) Open steam slowly into the system and allow piping and equipment to gradually
warm up. Drain condensate frequently from low points. Steaming should be done
up to crude charge pump suction. Eliminate air through all exchanger vent points
and drain out condensate from all exchanger low points. Flushing oil header
should also be streamed out.
c) A steam hose connection should be provided at the discharge of crude charge
pump for steaming the preheat section up to desalter.
d) Introduce steam into preheat train I/II connection using 2 LP steam downstream
of crude charge pump. Keep watch on desalter pressure, which should be
maintained around 0.5 Kg/cm2 g. If necessary, throttle steam purge desalter safety
valve inlet lines also. Air should be completely purged out from both inlet and out
let lines of each safety valve. Desalter water circuit should not be included for
steaming out. However lines up to mixing valve, and chemical injection lines up
to first isolation valve from desalter should be included for steaming. Allow steam
to vent from desalter top and other high point vents.
e) Line up atmospheric column overhead condensers, and atmospheric column
reflux drum with the column. Ensure water to condensers is isolated and water is
drained out. Open vents of overhead naphtha reflux drum and crude column. Line
up heavy naphtha, Kero, GO strippers and product circuit, and circulating reflux
circuits up to the respective pumps. Keep pump suction and discharge valves
closed for same reasons reason as explained above. Introduce LP steam in the
circuit from permanent steam connections as well as Stripping steam at a
controlled rate to warm up the system.
f) Slowly open some MP steam also into all the passes of atmospheric heater coils
through emergency steam connections (provided at down stream of pass flow
control valves) and in crude column bottom. Also open steam to the crude column
bottom and side strippers via strippers steam lines. MP steam is used as
augmenting stream to adequately carry out steam out. Too high a flow rate of
steam may dislodge the column internals and damage them.
g) Vigorously steam for at least 4 hours and then shut off crude column vent. Allow
steam to vent from atmospheric column reflux drum.
h) Maintain 1.0-1.5 Kg/cm2g pressure in column flash zone by regulating the
quantity of steam being introduced into the system. Drain condensate from low
points and allow system to warm up. Regulate the steam flow to heat up the
system gradually. Continue purging till steam comes out from the top of the crude
column, crude column reflux drum and side stripper vent connections. For
steaming out heavy Naphtha and Kero side strippers, back-up steam form crude
column and vent through 2 utility connection in these strippers. Release
condensates through pump suction strainer flanges, wherever applicable.
i) Back up steam from atmospheric column to preheat train I/II. LP steam from
hose stations can also be connected in desalted crude pump discharge circuit to
boost up external steam supply. Back-up steam from charge heater to preheat
trains-II. Increasing C-001 pressure slightly if required. LP steam from hose
steaming. In such cases, it may become necessary to fire the heater at the time of
steaming itself for evaporating water. Commission flare header and fuel gas
header to furnace after removing battery limit blind. Fire the heater at a small rate.
Heater is fired to avoid condensation in tubes and subsequent hammering when
steam is introduced in cold tubes. Maintain firebox temp. at about 250 C. Pilot
burners will be lighted initially. Main burners can be lighted afterwards, if
required. Keep open the vents at crude column top and crude column reflux drum.
q) Steam out LR circuit and all LR product lines up to isolation valve at the battery
limit.
r) Air elimination from product run down circuits in off sites should be done by
filling water in line and displacing the same by products when the same are
available except for water sensitive products like ATF whose run down temp. is
high.
s) Air elimination from water circuits and chemical dosing circuits need not be
carried out except up to first isolation valve where these lines may be subjected to
hydrocarbons.
6.3.3
TIGHTNESS/PRESSURE TEST
For leak testing, tightness test is to be done. Ensure that all piping & equipment vents and
drains closed. Pressurize the system up to 1.0 Kg/cm2 g with LP steam or air and check
for any leak through the flanges / instruments.
Usually for a very big system, pressurization by steam for tightness test proves
convenient. Limitations posed by design pressure design temp. should be strictly adhered.
The leakage identification is normally done visually when steam is used and by soap
bubble test when air is used.
Liquid soap solution may be sprayed poured on all the joints one by one and check for
any bubble formation. If a bubble is formed on joint or flange, there is an air leakage.
Leaks are to be attended after depressurizing. Big leaks can also be identified by pressure
drop identification. In view of large number
solution, it is suggested that only those systems should be taken up for tightness test by
air which should not be subjected to steaming or are likely to get exposed to vacuum
during vacuum test & normal operation.
Tightness of other systems may be done along with steam purging & pressurizing by
steam. Thus tightness test by air and steam purging tightness test by steam can be carried
out almost parallel, depending on availability of manpower & ease of monitoring.
6.3.4
Fuel gas is available from off sites for start-up of the unit. Purpose of fuel gas backing
into the system is to drain steam condensate from unit equipment as well as replace steam
with fuel gas. It the absence of fuel gas, condensation of steam may result in vacuum
formation inside unit equipment; most of which may not be designed for such full
vacuum or part vacuum conditions.
I. Steam in system is cut-off slowly and fuel gas is backed in. cutting off steam
results in condensation of steam inside unit equipment due to heat loss from bare
piping and equipment surface. Fuel gas can be backed from separate headers into
atmospheric column, stabilizer. It is advisable to back in fuel gas section wise.
This helps in better monitoring of operation and excessive withdrawal of fuel gas
from FG pool. Adjust gas-backing rate in such a way that fuel gas system is not
disturbed resulting in low fuel gas pressure due to excessive withdrawal during
this operation. Pressure surges during fuel gas backing-up should be avoided.
Ensure that all vents are closed and properly capped / blinded before FG back up.
II. Open the low point drain one by one and drain out condensate completely. Check
list to be prepared to ensure that all drains are made free of condensate. A log
should be kept for drain check showing the time of check, absence of condensate
and initials of the person who made the final check on the drain. Each drain must
be closed and capped / blinded as soon as gas issues form it.
III. Build up pressure in the columns @ 0.5 Kg/Cm2
IV. Back-up gas from column to all the product run down lines through internal and
circulating reflux lines from the column.
V. Drain out water from the following points:
a. Preheat exchangers
b. Transfer line
c. Pump around and reflux lines
d. All product circuits up to battery limit
e. All pumps
f. All exchangers and coolers
VI. Repeat draining operation every half an hour till no more condensate is drained.
Maintain the whole system at 0.5 Kg/cm 2g fuel gas pressure. Ensure all vents are
closed and capped off. Shut all drain points and cap off.
VII. After all the sections have been floated on fuel gas, water is drained from low
point drains. Positive pressure in the system will facilitate draining residual water.
VIII. Air from all the hydrocarbon system must be removed thoroughly before
proceeding for fuel gas back up.
IX. Before backing in fuel gas into the system, flare header inside the unit should be
charged and flare should be activated. Fuel gas purge to flare header should be
established. Fuel gas into furnace fuel piping should be charged at this stage only
if proper monitoring is available. Cooling water circulation is started through all
coolers and condensers.
X. Removal of water from the system is an important step for smooth start-up.
XI. Before admitting fuel gas into the system, all vents and drains in hydrocarbon
service will be closed. Steam entering the system is throttled slowly. Furnace fire
are cut off. Cooling water is commissioned to the overhead condensers and
coolers and air coolers started. During gas backing ensure that vacuum is not
formed in the system due to condensation of steam.
XII. As the system cools, condensate will accumulate. The drain at each low point is
opened and the condensate is drained. Never leave open drains unattended. Each
drain, which is opened and checked, should be listed in the start-up procedure. A
log should be kept for the draining activities showing time of check and absence
of condensate. Each drain must be closed as soon as gas issue out from it. When
the draining is complete the system is ready to take crude oil.
Major steps for fuel gas backing into the systems are as under:
i)
ii)
Close all the vents one by one. Adjust steam inlet rate to
maintain system pressure about 0.5 Kg/cm2g cap off all
vents properly to avoid leakage of gas through these
points. Throttle the drain valves to allow only condensate
to flow to keep the system hot. Keep watch on the system
pressure. Adjust steam inlet if necessary.
iii)
iv)
v)
6.3.5
COLD CIRCULATION
The purpose of cold circulation is further water removal from piping network and bottom
of equipment, which could not be removed during water draining. Cold oil carries liquid
water into low points of the circuit. During circulation drain at low points (preferably
from desalter and column bottom pump) must be opened frequently to ensure that no
more free water is drained. The circulation rate must be sufficiently high to sweep the
water and not merely flow over it. All plugged drains must be cleared for draining during
circulation. While draining water, unnecessary loss of oil to OWS should be avoided for
reasons of safety and economy. Normally one hour of settling time is allowed after every
four hours of circulation. Settling time may be reduced progressively at advanced stages
of cold circulation. Cold oil circulation gives further opportunity of trying out various
pumps and control systems prior to going up on temp. in sequence of start up. All
instruments should be commissioned during cold crude oil circulation. It should be
ensured that flow rate during cold circulation remains well above minimum continuous
flow through various pumps involved, as suggested by pump vendors. Similarly flow
through control valve should be maintained above minimum flow stipulated in control
valve data sheets to avoid possible chattering.
Crude tank that will feed the unit will be prepared in advance by through draining of
water. Sample will be analyzed and dips will be taken. It will then be lined up to the unit.
i)
ii)
iii)
Crude will begin to flow under gravity into the line and
displace gas. This gas is vented out from the crude pump
v)
vi)
vii)
viii)
ix)
x)
xi)
(b)
Once level in the crude column has been built up, establish cold circulation as per the
lineup given below.
Crude Tank --->Crude Booster Pump in Offsite ---- Crude Pump in Unit PA-01 -->
Crude Preheat Train Circuit Before Desalter (including both New and Old Preheat Train)
----> Desalter ----> Crude Preheat Train Circuit After Desalter (including both New and
Old Preheat Train) -----> Furnace -----> Column -----> Column Bottom Pump PA51RCO R/D circuit Crude Pump suction
i. Stabilize the second stage desalter pressure at around 9.5-11.5
Kg/cm2g and put PIC-1206 on auto. Observe the performance of
all control valves in the circuit. Crude oil will gradually displace
fuel gas and build up level in crude column. Crude oil passes
through crude preheat train I, desalter, crude preheat train II,
atmospheric furnaces and then to atmospheric column bottom.
ii)
iii)
iv)
vi)
vii)
viii)
6.3.6
HOT CIRCULATION
(a)
Commissioning of Desalter
Firing the Heater
When the cold circulation has been well established and water in the atmospheric system
has been thoroughly drained out, 05-FF-001 firing will be done as per recommended
procedure spelt out in heater operating manual
Following to be ensured again which pertains primarily to commissioning of utilities and
proper lining up of unit before firing the header:
i)
ii)
iii)
iv)
v)
vi)
(b)
ii)
iii)
iv)
v)
vi)
At the end of four hours, carry out test for water content
in circulating crude oil. Water content equal to or less
than that of tank sample is indication of good water
removal. A value of about 0.2% wt. of water content is
often obtained at this stage of hot circulation & is
acceptable.
ii)
Closely watch all instrument reading and check their performance. Recalibration of few of the instruments may be necessary.
iii)
iv)
Top temp. of the column will rise gradually. When it reaches more
than 100 C steam in the atmospheric column will not condensate and
will escape from column top. It will finally condensate in the column
overhead condensers and accumulate in reflux drum.
v)
When level appears in the reflux drum check for presence of water and
drain it out. Local check for levels must be made.
vi)
vii)
viii)
Care is to be taken so that water does not go in the top reflux stream.
Refluxing will be started at a small rate.
ix)
x)
(d)
Cap off all drains securely that were used to drain water.
iii)
See column top temp. and pressure reaches its normal value, line
up all circulating reflux circuit, starting from HN to GO CR in
descending order. Ensure that there is no water in any of
circulating reflux circuits by draining. Start refluxing at minimum
flow rate after draining water from pump drain. This operation
shall gradually stream line temp. profile in the column.
iv)
v)
vi)
vii)
100
compliance
to
ensure
condensate
is
properly
ix)
xi)
Watch column top pressure and temp. read just circulating refluxes
and top reflux if necessary. Raise the circulating reflux by
adjusting to 60-70% of its normal flow rate. Adjust return temp. of
top reflux, top CR, kerosene CR, GO CR at 40,94/95,140.6/138.4
and 71.1/170.7 C respectively by manipulating respective
exchanger by pass valves. Various duty controllers should not be
put in operation till steady state operating conditions are
established.
xii)
xiii)
When the coil outlet temp. reaches its normal value 375 C, put
TIC-1416 on auto/cascade with fuel oil / gas firing controller and
make all operating conditions steady. Commission hot medium to
HN stripper re-boiler. Normalize stripping steam flow to Kero/ATF
and GO stripper. Ensure that condensate is already drained before
allowing steam flow to the strippers.
xiv)
xv)
6.3.7
COMMISSIONING OF DESALTERS
Desalter can be brought into service at this stage. Stabilize desalter pressure at about 9.511.5 Kg/cm2g by PIC-1206. Control the desalter temp. at about 130 C by adjusting the all
hot medium streams passing through preheat train I. Variation in Hy. Naphtha CR,
Kero/ATF CR GO temp. Due to above adjustments by way of operation of exchanger
bypass will be taken care of by respective product coolers.
i)
Check oil water interface level through the try lines and
check for any presence of vapour
ii)
iii)
iv)
v)
charge.
The
rate
of
injection
to
be
vii)
At this stage normal operating conditions are established for atmospheric section at turn
down capacity of normal throughput of the plant. All products are routed to their
respective storage tanks/down stream plants.
Feed rate of the plant is to be raised to its normal capacity in steps as outlined below.
i)
ii)
iii)
iv)
v)
vi)
viii)
ix)
6.3.9
Commission PIC-1701 (stabilizer top pressure) on auto, with set point at about 9
Kg/cm2g. PIC-1701 being controller with characteristics so selected that initially the
control valve PV-1701 will remain full closed. If pressure increase still persists, PV-1701
shall also start opening and go to full open condition to relieve maximum fuel gas from
stabilizer reflux drum.
i)
ii)
iii)
iv)
Raise gradually stabilizer trey temp. by adjusting TIC-1703/FIC1704. When tray temp. stabilizes at around 170 C put TIC-1703 on
auto. Sudden increase of temp. and pressure will destabilize the
column making heavy fraction to go to the top, requiring longer
time to stabilize. So increase or decrease of temp. or pressure of
stabilizer shall be done gradually.
v)
vi)
vii)
ix)
x)
xi)
xii)
Water from water wash vessel shall also be drained to spent caustic
drum VV-16. However draining of wash water to this vessel shall
be indicated in inter-phase level LI-2008B on the water wash
vessel. Quantity of water drained should be made up by running
water make up pumps 05-PA-040A/B. Streams collected in the
degasser vessel after degassing shall be sent to ETP by spent
caustic pumps 05-PA-043A/B.
6.4
1.
2.
EE-103A/B/C
5HC5002 --EE-102A/B
Desalter
EE-104A/B
Desalter
PA-025HC5005 EE-07A/B/CEE-08A/BEE-09A/B
EE10A/B/C/DFF-01CC-01
FF-01CC-01
EE-107A/B/C/D
15. light gas & FO burner as per requirement & raise COT @ 40 0C/hr.
16. Raise temp. to 1200C. Hold for 2 hrs to strip off water to over head reflux drum.
17. Raise temperature to 2500C.
18. With the increase of temperature column top pressure will increase. Maintain top
pressure 1.5/2.14 Kg/cm2g by PIC-1504.
19. Switch on desalter, Drain out accumulated water fro desalter.
20. Adjust RCO cooler O/L temp to 50-600C
21. When level builds up in V02, Drain water & start reflux pump.
22. Maintain top temperature.
23. Check & get hot bolting done the leaky/smoky flanges.
24. Raise temperature to get 3000C C01 bottom.
25. Drain condensate & introduce stripping steam to C01/C03/C04.
26. Bring unit out of circulation by routing RCO to R/D. Adjust RCO cooler to get
required R/D temperature.
27. Rout V02 sour water to SRU.
28. Start CR pumps when level appears in stripper & adjust column condition.
29. Start product pump & rout initially to off spec. tank. Adjust draw temperature.
30. Diver V2 gasoline to stabilizer.
31. Introduce slowly heat to Stabilizer & HN stripper Reboiler.
32. Adjust column condition.
33. Commission Amine wash system.
34. Commission LPG / Naphtha & SKO naphtha caustic wash system.
35. Rout LPG through amine & caustic wash system to Horton sphere.
36. Rout LN / SKO through caustic wash system.
37. Send product sample to laboratory. When certified rout to on grade R/D tank.
38. Take all inter locks in line.
39. Slowly increase TPut as per requirement.
40. Start Stripped sour water injection to desalter.
41. Start all chemical injection. Maintain PH
42. Start ID fan. When its suction exceeds 1600C, close STD as required.
6.5
Sl.No
Description
Action by
InformRSM/OMS/TPS/Water
Block/Laboratory about Start up
Check & rectify all furnace igniter
Check & commission all utilities, if
decommissioned.
Check all FG and FO burner valves. These
should tight shut.
Bypass IFO low pressure inter lock &
establish IFO circulation through furnace by
opening IFO C/V & return BPC.
Adjust to obtain IFO required temperature.
Establish IFO circulation, first with RCO
then switch over to VR.
Prepare / top up chemical solution
Ahuralan
Ammonia
Ammonical caustic
Demulsifier
Check all motors for power supply
S/I
2
3
4
5
6
7
8
9.
10.
11
12
Field Opr
Panel/Field
Opr.
Field Opr
Panel/Field
Opr
Panel/Field
Opr
Field Opr
Pump/Field
Opr.
Panel/Field
Opr
Panel/Field
Opr.
S/I
Panel/Field
Done
YES/
NO
Remarks
13
14
15
16
17
18
19
Sl.No
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Opr
Field Opr
Panel/Field
Opr.
Field Opr
Panel Opr.
Field Opr
S/I/Field
Opr.
Panel/ Field
Opr
Action by
Done
YES/
NO
Remarks
36
37
38
Field Opr.
Pump/Panel
Opr
Panel
/Field /Pump
Opr.
39
Panel
/Field /Pump
Opr.
40
S/I/Panel/Fie
ld Opr.
Panel /Field
Opr.
Panel Opr.
Panel/Pump
Opr.
Panel Opr.
41
42
43
44
CHAPTER-7
GENERAL
In this section, procedure for planned shut down is discussed. While shutting down all
process units simultaneously or any section of the process unit, care should be taken not
to admit air into the system until all hydrocarbon vapors have been removed.
It is important that process unit operates involved in shut down understand the purpose
and effect of each activity. In particular, operators should make sure that their actions will
not result in creation of hazardous conditions either because actions taken were wrong or
these were taken at wrong time.
Rate of temperature drop in process unit equipment should not be very sharp to induce
thermal stresses in piping and equipment. All related process units, utilities and of sites
should be kept informed well in advance about the shut down plan. It is to be ensured that
a slop tank and one crude tank having sufficient space is available to receive the slops/off
spec material. Closed blow down drum should be emptied out and should be kept ready
to receive hydrocarbons draining/flushing from equipment. Flushing oil should be made
available in adequate quantity and adequate pressure. Adequate ullage should be ensured
in off sites slop tank.
7.2
The throughout to CDU will be gradually reduced to about 50% of normal capacity or
turn down capacity of the unit and all other flow rates shall be reduced on pro data basis
wherever applicable to be suitable for operation of the unit on reduced capacity.
Necessary adjustment will be done in reflux rates withdrawal rates in all the sections of
the unit to keep the product on specification.
Number of burners will be reduced in the CDU, furnaces if necessary. Chemical injection
will be discontinued.
Adjustment will be done in stabilizer column operation to stop production of LPG, which
will be released to fuel gas system. All caustic wash sections will be bypassed. Desalter
will be taken out of service.
COT of atmospheric section will be gradually reduced to 300 C . Divert product to slop
when they become off spec. Cut off column bottom stripping steam. Re-circulate LR
along with other product through slop header. Back up FG when pressure tends to
become low. Cut off fire in atmospheric heater and allow to cool down while on
circulation. When system is sufficiently cooled, empty out all equipment to slop. Flush
out fuel oil system.
Steam out columns exchangers etc. to remove hydrocarbon vapours etc. if opening of the
equipment in hydrocarbon service is planned.
7.3
The procedure indicated below will ensure a safe and smooth shut down of the units but
is not mandatory.
Plan chemical solution preparation in advance so that very little solution is drained after
unit is shut down for M&I.
The important steps in the shutdown procedure are summarized as below:
Reduction of feed rate to all units.
Discontinue chemical Injection
Shutdown stabilizer
Decommissioning of desalters
Putting the CDU on circulation
Shut down atmospheric section
THROUGHPUT REDUCTION
Reduce crude throughout gradually to 50% of normal feed rate step by step. Manipulate
all atmospheric heater pass flow controllers for this purpose, bypass low pass flow / low
FO / FG pressure inter lock.
Make adjustment on all operating variables in each step so that normal operating pressure
and temp. conditions are maintained.
7.3.2
Control system of stabilizer column shall be changed from total condensation to partial
condensation operation. LPG down stream unit will be informed about discontinuing
LPG production.
Inform DHDS and LAB to stop wild naphtha to AU5 unit. Also inform CRU to stop drag
stream to AU5.
Reduce feed to stabilizer. De-cascade atmospheric column reflux drum level controller
from stabilizer feed flow controller. LPG-to-LPG vaporizer should remain isolated at
HIC-1901 and to Amine regeneration unit.
De-cascade stabilizer column top temp. controller TIC-1703 from reflux flow controller
FIC-1703. increase top reflux to stabilizer and cut off LPG withdrawal from reflux drum.
De-cascade stabilizer reflux drum level controller LIC-1704 from LPG product flow
controller FIC-2503. Bring the column to total reflux operation, by maintaining pressure
such that only sufficient vapor condenses to maintain reflux flow.
Reduce the column top pressure very gradually by operating PIC-1701. Care must be
taken to reduce the pressure very slowly to avoid lifting of heavy ends to the top and
sudden release of heavy components to fuel gas system, which may condense afterwards
in FG system.
Reducing heating medium flow (GO CR) to stabilizer re-boiler. Operate TIC-1704 first to
lower the temp. Throttling of FV-1704 by manual mode can be done for this operation.
Pump out stabilizer top reflux drum liquid to stabilizer till reflux pump looses suction.
Keep receiving feed to stabilizer till atmospheric column starts operating on total reflux
in source of shut down and then cut off feed to the stabilizer. Close the isolation valve in
the stabilizer feed line.
By utilizing the available pressure, empty out the stabilizer bottom to slops storage tank
and maintain stabilizer bottom level. Keep a watch on rundown stream, as it may contain
lighter components, which may create problem in slop tank.
To facilitate emptying out, top pressure control valve of the column may be closed.
Heating up bottom contents can also be done if necessary to build up pressure for this
purpose. Care must be exercised to prevent gas break through from stabilizer column to
storage tank due to sudden loss of level in stabilizer bottom while emptying out.
Bypassing the caustic wash system should be done prior to shut down of the system. As
soon as caustic wash system is bypassed both the caustic circulation pump and water
circulation pump to be stopped.
Reduction in stabilizer column pressure, naphtha flow and stabilizer bottom level will
all indicate completion of the emptying out of the column. After emptying out, isolate the
column by shutting off valve on the inlet and outlet streams and then depressurize slowly
by releasing to flare through depressurizing valve.
After depressurizing, residual liquid in column, piping exchanger will be drained to CBD
or OWS. LPG should not be drained to CBD or OWS in large quantity, as it may flash in
the way.
7.3.4
DECOMMISSIONING OF DESALTERS
Switch off power to both desalters and then stop desalting water to both the units.
However crude flow through desalters can be maintained.
Shut off desalter effluent water (brine) lines after ensuring the water level is lowered to
minimum.
Wide open the mixing valves at desalter inlet by manual operating MV-1201 & MV-1202
the pressure control system of the desalters should to work so that steady desalted crude
pump suction pressure is ensured.
When CDU is on hot circulation, as elaborated ahead, desalter can be bypassed after
opening PV-1206 at desalter inlet fully in manual mode. Drain desalter content into close
blow down (CBD) system. Desalter can be kept filled with gas oil and be isolated after
draining. Keep desalter pressure around 0.3 Kg/cm2g when it is idle.
7.3.5
NORMAL SHUTDOWN
CDU is still running with around 50% of normal capacity with LR routed to slop and the
side draw off products from atmospheric column are going to respective product tanks.
Start reducing atmospheric furnace COT by TIC-1416 at 30 C per hour.
As temp. of crude oil drops, there will be less of distillate product and column pressure
will tend to fall. Admit fuel gas into the reflux drum through pressure controlled PV1504B if fuel gas is available from else where.
As column temperature start dropping, quantity of products will go off spec. Divert the
off spec distillate products to slop at the battery limit. Inform related units about the
rerouting.
At a column bottom temperature of around 300 C cut off stripping steam to column
bottom. Keep striping steam to side strippers also to be discontinues as and when side
draw off products are diverted to slop. Also GO CR to HN reboiler to be stopped.
With a drop in column top temperature, the overhead product yield will gradually come
down. Stop withdrawing naphtha product and resort to total top refluxing. Liquid in
reflux drum will be emptied out into crude column slowly.
Gradually stop product withdrawal and stop product pumps, when they give unsteady
performance on continuous operation.
Reduce CR rates. Stop all CR pumps one by one, starting from HN CR pump as and
when they loose suction.
With lowering of heater COT, LR yield will increase and its viscosity will come down.
Line up LR R/D to pre-desalter crude pump suction and establish close circulation of LR,
as was done during hot circulation at the time of start up.
Isolate the crude feed line from the unit battery limit.
Hot circulation circuit:
PA-1 -->Crude Preheat Train Circuit Before Desalter (including both New and Old
Preheat Train) ----> Desalter ----> Crude Preheat Train Circuit After Desalter (including
both New and Old Preheat Train) -----> Furnace -----> Column -----> PA-51 ------>RCO
circuit. ----> P1 suction.
When heater box temperature drops to about 200 C, cut off all furnace fire. Purge out
burners and firebox and get FG line blinded. Continue IFO circulation.
Continue crude circulation till system gets cooler down sufficiently to about 100 C at
the column bottom. After this, stop all crude pumps. Discontinue RCO pump discharge
from crude tanks and line up LR pump discharge to slop tank. Stop LR pumps also when
they loose suction. Stop ID / FD fan
7.3.6
Take flushing oil to the atmospheric column through RCO pump suction. Build up about
80% level at the bottom of the column.
Line up circuit again through LR circuit and crude charge pump and complete the
circulation block up to column.
PA-1 -->Crude Preheat Train Circuit Before Desalter (including both New and Old
Preheat Train) ----> Desalter ----> Crude Preheat Train Circuit After Desalter (including
both New and Old Preheat Train) -----> Furnace -----> Column----->PA-51------>RCO
circuit ------>PA-1
Flash out heavy stuff from all exchangers/control valve bypasses by operating
them one by one.
Deblind & line up service water connection at P01 suction. Start P01 & push the
line material (Both new & old circuit) to column via desalter. When desalter interphase level raises to 100% bypass & drain desalter content to CBD &
subsequently pump out CBD content to slop tank. Continue water flushing to
C01& pump out C01 to slop header through RCO circuit.
After water flushing is over, isolate & bypass all RCO & Crude Heat Exchangers
& drain all the exchangers to CBD.
Slowly open steam to the discharger of crude charge pumps and flush the lines
and equipment into the C01 bypassing desalter. Steam crude preheat exchangers
and displace the material into the column. Open emergency steam to all the passes
of the furnace to expedite the displacement (this is suggested in view of large hold
up of hydrocarbon in piping which remain stagnated).
Pump out the material collected at crude column bottom to slop tank. Run LR
pump as and when necessary.
Steam out discharge of RCO pump and route the material into slop header. Care
should be taken to avoid steaming beyond battery limit.
7.3.7
After maximum quantity of hydrocarbon material has been removed from the unit, drain
all equipment and lines to CBD one by on. Drain Amine settler bottom to amine drain.
Reverse blinds on CBD lines from various equipment to open position. Drain all the oil in
the CBD. Ensure adequate ullage in CBD drum by pumping out CBD drum contents to
slop. Rise in CBD drum level should be watched periodically while draining.
Decommission FG header to flare header & purge with steam. Isolate flare header at
battery limit. Reverse the blind to close position of the fuel gas header in the plant battery
limit, if FG is not required by ARU. Decommission LPG vaporizer. Blind off fuel gas
line. Isolate all inlet and outlet lines at the battery limit.
Flush out fuel oil header by taking flushing oil at unit battery limit. Drain out oil to CBD.
Open vent at top of equipment, other high point vents and reflux drum vents etc. before
steaming. The step of steaming can be taken up only after shutdown of the rest of the unit
so that cooling water can be isolated for effective steaming. Steam out for a period of
about four hours, after which it will be discontinued. Allow the system to cool down with
vent valves full open. Stop steaming the equipment when steam enters CBD system.
Start steaming crude column, stabilizer column, desalter, furnace coils and exchanger
trains etc. as detailed under the section of start up procedures. Continue steaming till all
hydrocarbon vapours are removed from the system. Ensure that column vents are opened
to atmosphere to avoid vacuum formation. During steaming care should be taken so that
system pressure does not exceed operating pressure. Then stop steaming and let the
equipment to get cooled. Connect steam hoses to the utility connection point of all
equipment and start steaming.
Steam out the headers in hydrocarbon service till clear steam comes out from all high
point vents and all hydrocarbons are eliminated.
Shut off steam to the lines.
Carry out insertion of blinds as per the master blind list for isolating the unit for
maintenance.
After positive isolation is over start again steaming followed by hot water wash by
introducing water from top of the column by reflux pump. At least 4-hour hot water
wash to be done followed by cold-water wash to cool down the columns.
Blind steam out point & open column manholes.
During steam purging ensure that dry steam has come out from all LPDs & HPVs & no
trapped hydrocarbon is left inside.
7.3.8 CHECK LIST FOR UNIT NORMAL SHUTDOWN FOR BOTTLED UP
CONDITION
Sl.No
Description
InformRSM/OMS/TPS/Water
Block/Laboratory about S/D
2
Ensure flushing oil availability in GHC
3
Ensure slop tank at GRE has sufficient
ullage
4
Check CBD pump is in healthy condition
Sl.No
Description
5
6
7.
8.
Action by
Done
YES/NO
Remarks
Done
YES/NO
Remarks
S/I
S/I
S/I/Panel
Opr.
Pump.Opr
Action by
S/I
Panel/Field
Opr.
S/I/Field
Opr.
Panel Opr.
Panel/Field
Opr.
Field Opr.
Panel/Field
Opr.
Field Opr.
Panel/Field
Opr
Panel/Field
Opr
Panel/Field
Opr
20
21
Sl.No
Description
Action by
22
Panel/Field
/Pump Opr.
15.
16
17
18
19
23
24
25
26
27
Field Opr
S/I
Field Opr
Panel/pum
p Opr
Pump Opr.
Panel/Field
Opr
Field Opr.
Panel/Field
Opr
Field Opr
Field Opr
Panel/Field
Opr
Done
YES/NO
Remarks
28
29
CHAPTER-8
EMERGENCY PROCEDURES
EMERGENCY PROCEDURES
8.1
GENERAL GUIDELINES
An emergency in the unit means a serious up set in the unit operating conditions resulting
in products going off, and damage to equipment (if proper actions are not taken promptly
and so warrants quick decision and quick actions.
Under emergency conditions, action is to be taken promptly as per the guidelines given
below:
The product inside the heater coil should not get excessively heated, to avoid
coke formation.
Cut off oil firing and gas firing before putting off the pilot gas burners. Close the
unit limit gas and unit B/V and depressurize the gas line to flare line.
Firebox purging steam should be opened immediately after cutting off pilot gas
burner.
Heater coil pressure must be lower than available steam pressure, when coilpurging steam is opened.
The passivation solution should be prepared at the earliest, since the same may be
needed for passivation of F-1 coils.
Steam flushing of individual oil burners, is required to keep the tips free for
subsequent light up.
Fuel oil BPC bypass valve is required to be opened in time, so that BPC pressure
does not exceed 10.0 kg/cm2.
Crude feed line battery limit isolation valve is to be closed before establishing
circulation.
While pumping out any material from the unit pump out temperature has to be
low enough.
Crude oil circuit must be flushed with diesel at the earliest convenient time to
avoid congealing.
Power failure
Steam failure
Water failure
8.2
UPS failure
DCS failure
A power dip of eve 2/3 seconds is enough to trip a motor. If on the other hand, due to
malfunctioning of a transformer in the sub-station or some cable faults or power shedding
etc. there is a partial/total failure of power supply to the unit, then unit will have to be
shutdown depending on the resumption of power supply to the unit. The pumps will not
be transferring liquid from one place to other because the motors have stopped.
Power failure may be of 3 types
1) HT POWER FAILURE
2) LT POWER FAILURE
3) TOTAL POWER FAILURE
EFFECTS OF POWER FAILURE:
No reflux to columns.
Columns top temperature will start shooting up and pressure will also shoot up.
For sometimes the vapors will continue to come from column overheads and
condense in condensers and then go to vessels. So, vessels will become full. Since
there is no material going out of the vessels, vessel safety may pop.
There are chances of fire in the plant due to thermal shocks and leaks.
Heater refractory may get a thermal shock. Hence there are chances of bricks
falling down.
1) HT POWER FAILURE
In case of HT power failure only Crude pump will trip. Furnace will cut off on Low pass
flow inter lock.
Sl.No
JOB DESCRIPTION
Action
Done
Inform RSM/TPS/OMS/SPNM
Furnace should trip on inter lock. Close FG
by
S/I
Panel
YES/NO
1
2
3
Opr.
Field
Opr.
Field
Opr.
Field
Opr.
Pump
Opr.
Panel/Fie
pool.
If power clearance is obtained from TPS
ld Opr.
Remarks
immediately
Start stand by pumps & establish flow
Panel/Pu
mp Opr.
Panel
Opr
Field
are off.
Start FD fan after bypassing its inter lock.
Opr.
Panel/Fie
ld Opr.
Field opr.
burner in line.
Raise temperature @ 40 deg / hr.
Panel/Fie
9
10
11
ld Opr.
Panel
Opr.
Panel/Fie
ld Opr.
Panel
Opr.
Pump
Opr.
S/I
situation.
Start coil purging steam & displace the oil
Panel/Fie
ld Opr.
the
S/I
exceed)
Cut off striping stream c/vs. of CC-01/CC-
Panel
Opr.
Field
Opr.
Panel/Fie
ld Opr.
Panel/Fie
ld Opr.
Panel/Fie
draft mode.
Run FD till Column cools down / Column
ld Opr.
Panel
Opr.
S/I/Panel
/Field
Opr.
Field
10
11
12
Opr.
Stop dm water to desalter.
Field Opr
Stop all product & reflux pump when Panel/Pu
13
14
system.
Decommission LPG wash system, if other Field Opr
15
16
17
Field
Opr.
ON RESUMPTION OF HT POWER
Ensure coil-purging steam valves are closed
d Opr.
Field
Opr.
Panel/Fie
Field
ld Opr.
Field
Opr.
Field
Opr.
Panel/Fie
ld Opr.
Panel
Opr
S/I/Field
10
11
Opr.
Field Opr
Panel/Fie
ld Opr
circulation.
Introduce stripping steam to strippers.
Panel/Fie
13
ld Opr
Panel/Fie
14
ld Opr
Start top reflux pump when level appears. Pump/Fie
15
12
ld Opr.
Pump/Fie
ld Opr
Panel
17
Opr
Pump
18
in stripper.
Adjust column condition.
Opr
Panel
19
Opr
Panel
20
Opr
Drain water from V3 when level appears & Pump/Fie
21
ld Opr
Panel/Fie
22
ld Opr
Pump/Fie
23
24
ld Opr
S/I
Panel/Fie
16
ld Opr
25
Panel
Opr
2) LT POWER FAILURE:
Following are the effects of LT power failure:
EFFECTS:
All the motors except Crude pump and Desalted crude pump will stop.
ACTIONS TO BE TAKEN:
In case of LT power failure to the unit (but steam being available) following actions
should be taken:
Sl
JOB DESCRIPTION
No
1
2
Inform RSM/TPS/CGP/OMS/SPNM
With the LT power failure, fuel oil pumps will
Action by
YES/NO
S/I
continue.
Shut FO C/V from panel.
Isolate all FO burners & flush with steam.
Panel Opr/
Field Opr.
Pump Opr.
Panel/Fiel
d Opr.
Panel opr.
Panel Opr.
S/I
RSM/SPNM/CPNM/OMS/GRE/GRSPF/SR
2
Done
U
Cut-off gas firing in the heaters by closing
individual burner block valve. Isolate main
FG isolation valve also.
Field Opr.
Remarks
3
4
Field Opr.
Panel Opr.
Field Opr.
Pump Opr.
7
8
running.
Switch off desalter.
Establish close circulation.
Field Opr.
Panel/Fiel
d Opr.
Panel Opr.
Panel/Fiel
d Opr.
S/I
Field Opr.
minutes).
Start FD fan.
Panel/Fiel
d Opr.
Field Opr.
5
6
one by one.
Take FG & FO burner in line.
Raise COT @ 40 deg C /hrs.
Field Opr.
Panel/field
Opr.
Panel/Fiel
d Opr.
circulation.
Increase COT as per requirement.
Panel/Fiel
d Opr.
S/I/Field
10
Opr.
Pump Opr.
11
Pump Opr.
12
13
appears in strippers.
Adjust unit condition.
Initially route products to off grade product
Panel Opr.
Panel/Fiel
14
tank.
Slowly
bottom
d Opr.
Panel Opr.
15
temperature.
Drain water from V3 when level appears &
Field opr.
16
Field Opr.
17
18
wash system.
Send R/D sample to lab.
If certified divert R/D to on grade tank.
S/I
Panel/Fiel
d Opr.
Panel Opr.
19
increase
stabilizer
There are chances of fire in the plant due to thermal shocks and leaks.
ACTIONS TO BE TAKEN:
In case of power failure to the unit, following actions should be taken:
Sl.N
JOB DESCRIPTION
Action by
o
1
Inform
TPS/CGP/RSM/SPNM/OMS
Cut off furnace from panel by
Panel Opr
Field Opr.
Done
YES/NO
S/I
Remarks
4
5
Sl.N
Field Opr.
Field Opr.
available.
JOB DESCRIPTION
Action by
o
6
Panel Opr.
Field Opr.
Done
Remarks
YES/NO
s to be opened.
Close all discharge valves of the
Pump Opr.
Panel Opr.
PIC bypass.
Take frequent round around of the
S/I/field opr.
if observed.
Isolate all steam battery limit valve.
On obtaining clearance for
Panel/Field Opr.
unit as follows:
Inform RSM/SPNM/CPNM/OMS
Commission steam: open all steam
header
condensate
drain
S/I
Panel/Field Opr.
trap
Panel/Field Opr.
Action by
Done
YES/NO
Remarks
Panel Opr.
flow
Physically check total unit for
S/I/Field Opr.
6
7
8
Field Opr.
Field Opr.
Panel/Field Opr.
lock.
Line up for & establish crude close
Field Opr.
10
11
circulation.
Check furnace draft.
Start FD fan after bypassing inter
Field Opr
Panel/Field opr.
12
13
lock.
Light up all pilot burners.
Bypass FG low-pressure interlock
Field Opr.
Panel/Field Opr.
14
Panel/Field Opr.
15
Panel/Field Opr.
Panel/Field Opr.
S/I/Field Opr.
if observed.
Start reflux pump when level
Panel/Pump Opr.
naphtha to stabilizer.
Start CR & Product pumps when
Pump Opr
20
21
Panel Opr.
Field Opr.
22
product tank.
Slowly increase stabilizer bottom
Panel Opr.
temperature.
23
Panel/Field/Pum
p Opr
24
Field Opr.
25
26
S/I
Panel/Field Opr.
27
tank.
Take all inter lock in line.
8.3
Panel Opr.
STEAM FAILURE
JOB DESCRIPTION
Action by
Done
YES/NO
Inform
TPS/CGP/RSM/SPNM/OMS
Cut off furnace from panel by
S/I
Panel Opr.
Remarks
&
gas
Field Opr.
available.
Isolate main FG line B/V.
Purge the heater with steam, if
Field Opr.
Field Opr.
available.
Cut off striping stream c/vs of
Panel Opr
CC-01/CC-03/CC-04
6
from
the
panel
Close CC-001/3/4 stripping steam
Field Opr.
s to be opened.
Put unit on close circulation.
Adjust
Sl
available.
JOB DESCRIPTION
No
10
11
12
13
Field Opr.
Panel/Field Opr.
Field Opr.
Panel/Field Opr.
14
Field Opr.
15
16
Field Opr.
S/I/Panel Opr.
RCO
cooler
Panel/Field
O/L
Opr.
Panel/Field
Opr.
Field
Opr.
Action by
YES/NO
Done
Inform RSM/SPNM/CPNM/OMS
S/I
Remarks
2
3
4
5
6
7
8
9
Sl
No
10
11
12
13
14
15
16
17
JOB DESCRIPTION
Field Opr.
Field Opr.
Panel/Field Opr.
Field Opr.
Field Opr.
Panel/Field Opr.
Panel Opr.
S/I/Field Opr.
Action by
Done
YES/NO
Panel/Field Opr.
Panel/Field Opr.
Pump Opr.
Pump/Field Opr.
Panel Opr.
Panel/Pump Opr.
Panel Opr.
Panel Opr.
Remarks
18
19
column condition.
Drain water from V3 when level
Panel/Field/Pum
Opr.
Field Opr.
system.
Route all products to off grade
Panel/Field Opr.
21
22
tank.
Sent sample to lab.
If certified, divert product to on
S/I
Panel/Field Opr.
23
grade tank.
Take all interlocks in line.
Panel Opr.
2) HP STEAM FAILURE
i)
ii)
iii)
iv)
v)
3) LP STEAM FAILURE
i)
ii)
iii)
EFFECTS:
No water to condensers and coolers. No water to pumps.
Hence in the absence of cooling medium, there will not be any condensation and
all columns pressure will shoot up very fast.
Pumps glands may be burnt and lube oil temp. will increase. Gland will start
leaking.
Pumps will have to be stopped.
If cooling water failure is only partial, it can be tackled by reducing throughput
and throttling water to coolers/condensers proportionally.
ACTION TO BE TAKEN:
Sl.N
JOB DESCRIPTION
Action by
o
1
Inform
tower/RSM/SPNM
Cut off furnace from panel by
Panel Opr.
Field Opr.
YES/NO
Cooling
S/I
Field Opr.
Field Opr.
Done
Panel Opr.
Remarks
Close
CC-001/3/4
stripping
Field Opr.
Panel/Field Opr.
Panel/Field Opr.
C.
Stop ID fan & switch over
Panel/Field Opr.
11
Panel/Field Opr.
under control.
Route products to off grade tank.
Stop all chemical injection
Panel/Field Opr.
Field Opr.
14
pump.
Stop all product & reflux pump
Panel/Pump Opr.
looses.
Decommission LPG / Naphtha /
Field Opr.
15
16
Field Opr.
S/I/Panel Opr.
2
3
RSM/SPNM/CPNM/OMS
Check CW flow / pressure
Line up & establish cold
Panel/Field Opr.
Panel/Field Opr.
circulation.
Take low pass flow inter lock in
Panel Opr.
line.
Purge heater box with steam &
Field Opr.
S/I
Panel/Field Opr.
7
8
9
Field Opr.
Field Opr.
Panel/Field Opr.
10
C/hr.
Check the unit for any leak. Fix
S/I/Field Opr.
11
it if so.
At 300 Deg C cut off feed by
Panel/Field Opr
circulation.
Introduce stripping steam to
Panel/Field Opr.
13
14
strippers.
Increase temp. as required.
Start top reflux pump when level
Panel/Field Opr.
Panel/Pump Opr.
appears.(
Drain
water
15
completely).
Start sour water pump & rout to
Pump/Field Opr.
16
17
SRU.
Maintain required top temp.
Start CR / Product pump, when
Panel Opr.
Panel/Pump Opr.
18
19
20
Panel Opr.
Panel Opr.
Panel/Pump/Fiel
d Opr.
Field Opr.
21
after
commissioning
caustic
22
wash system.
Route all products to off grade
Panel Opr.
23
24
tank.
Send sample to lab.
If certified, divert product to on
S/I
Panel/Field Opr.
25
grade tank.
Take all inter locks in line.
Panel Opr.
8.5
Instrument air is supplied to the unit at a pressure of about 6.7 Kg/cm 2g from the
compressor house. It is taken to an air receiver and from there it is taken to the unit. PC
on this line maintains the supply pressure at 3.0 Kg/cm2g in the header.
Air receiver in the unit can supply air for some time interval. If due to some reasons, air
supply cannot be restored within this period, then the supply lone header pressure will
fall below 3.0Kg/cm2g and will decline fast. The instruments will cease to function.
Control valves will remain fully open or close depending on whether the control valve is
air to close or air to open. Hence unit will have to be shutdown.
EFFECTS
Following are the effects of instrument air failure.
Instrument loops that are having pneumatic provision such as closed loop control
valves will stop functioning.
However open loop instruments involving electronic data transmission shall
remain.
On account of closure of FO / FG control valves, heater will trip.
Allow FD/ID fans to run as long as possible.
All the LCs will open fully.
The PCs of CC-001 and CC-005 will open fully leading to loss of pressure.
Atomizing control valve will go to full open position.
With the pumps running all the flows will go up. But since heater firing is
substantially reduced, temperature will fall down. Level in vessel will come
down. Reflux pumps will lose suction, and hence columns top temperature will
shoot up. So shutdown is imminent.
ACTIONS TO BE TAKEN:
Sl.
No
1
JOB DESCRIPTION
Action by
Done
YES/NO
Panel Opr.
Remarks
C/V.
Isolate individual oil & gas
Field Opr.
Field Opr.
Field Opr.
Panel Opr.
panel.
Close CC-001/3/4 stripping
Field Opr.
opened.
Put unit on close circulation.
Adjust RCO cooler O/L
Panel/Field Opr.
Panel/Field Opr.
deg C.
Stop ID fan & switch over
Panel/Field Opr.
10
Panel Opr.
down
Column
pressure
11
Panel/Field Opr.
12
tank.
Stop all chemical injection
Field Opr.
13
pump.
Stop all product & reflux Panel/Pump Opr.
pump when stripper / vessel
14
Field Opr.
15
16
Field Opr.
S/I/Panel Opr.
17
Field Opr.
valve.
ON RESUMPTION
INSTRUMENT AIR
1
2
OF
Panel/Field Opr.
Field Opr.
Panel/Field Opr.
Field Opr
Field Opr
Panel/Field Opr.
deg. C/hr.
Ensure low feed pass flow in
Panel Opr.
line.
Check the unit for any leak.
S/I/Field Opr.
9
10
Fix it if so.
Take oil burner.
At 300 Deg C cut off feed by
Field Opr.
Panel/Field Opr.
circulation.
Introduce stripping steam to
Panel/Field Opr.
12
13
strippers.
Increase temp. as required.
Start top reflux pump when
Panel/Field Opr.
Pump/field Opr.
completely).
Start sour water pump & rout
15
to SRU
Maintain required top temp.
Pump/field Opr.
Panel Opr.
16
Pump/field Opr.
17
18
Panel Opr.
Panel Opr.
19
Panel/Pump/fiel
d Opr.
pump&
20
adjust
column
condition.
Route LPG & Naphtha to R/D
Field Opr.
8.6
21
wash system.
Route all products to off grade
Field Opr.
22
23
tank.
Send sample to lab.
If certified, divert product to
S/I
Panel/Field Opr.
24
on grade tank.
Take all inter locks in line.
Panel Opr.
FEED FAILURE:
Crude oil is supplied to unit by booster pumps from crude control. Crude feed supply to
the unit could get interrupted due to many reasons viz. improper functioning of booster or
unit feed pumps, improper lining up and chocking of strainers & or power supply failure.
etc. Interruption in feed flow calls for immediate action.
EFFECTS
Feed pumps will lose suction
No flow to the furnace.
Rapid drop in CC-001 bottom level
JOB DESCRIPTION
Furnace will cut off on inter lock.
Isolate FO / FG burners & flush with steam and the purge heater box.
If the feed supply cannot be restored immediately bring the unit to circulation,
cut off stripping steam to columns & route the products to off spec. Tanks.
If the interruption is for a longer period the unit should be shutdown as per the
normal procedure.
8.7
With the total power supply failure to the whole refinery, there will be no supply of
circulating water, industrial and instrument air, and steam i.e. supply of all the utilities
will stop. This is major emergency and unit is automatically shutdown. Following action
will have to be taken immediately:
JOB DESCRIPTION
Close the C/V block valves and bypass valve of stripping steam to CC-001/3/4
and open bleeder to prevent backing up of crude oil/products into steam line.
Open the bleeder on steam line to drain out the product, if any, which might
have backed-up into steam line from columns.
Release the pressure from the reflux vessels to flare gas as & when required.
Since condensation will not take place in condensers column pressure will
shoot up and so safety valves may pop.
Drain the flare gas knockout drum, as well as gas bullets immediately.
Since instrument air supply will also fail, no indication will be available in
control room. Hence checks for temperatures, pressures, levels etc. Will have to
be made locally.
8.8
Whenever tube rupture takes place, bridge wall temperature will start shooting up. Smoke
will start coming from the top of the stack. It will become dense, as leak will increase.
Sharp rise in stack temperature may also be observed. Plant operating personnel and the
supervisor have to assess the extent of leak/rupture and take recourse either to normal
shutdown or emergency shutdown. Following steps are indicated to bring down the unit
quickly in the event of a failure of heater tube.
JOB DESCRIPTION
Put off all the fires in the heater. Stop ID/FD fans.
Emergency coil steam will be opened in all the passes of the heater.
Columns pressure will be watched for any rise due to additional amount of
steam put into the heater coils.
JOB DESCRIPTION
Action by
Done
Remarks
YES/NO
1
2
3
Inform I/M,E/M,RSM,SPNM,OMS
Close FG & FO C/V from panel.
Isolate individual oil & gas burners
S/I
Panel/Field
Opr.
Field opr.
with steam.
Isolate main FG line B/V.
Pilot burners should be in line,
Field Opr.
Field Opr.
Panel Opr.
Field Opr.
Panel/Field
Opr.
Panel/Field
10
Opr.
Panel/Field
11
Opr.
Panel Opr.
Column
pressure
comes
under
control.
Route product to off grade tank.
Panel/Field
13
14
Opr.
Field Opr.
Panel/Field
15
Opr
field Opr.
16
17
Field Opr.
S/I/Panel
18
Opr.
Field Opr.
12
19
Panel opr.
inter lock.
ON RESUMPTION OF 110V DC
1
2
POWER
Inform RSM/SPNM/CPNM
Check SOVs / shut down valves are
S/I
Panel Opr.
working.
Purge heater box with steam &
Field Opr.
Panel/Field
Opr.
Field Opr.
Field Opr.
Panel/Field
8
9
Opr.
Panel Opr.
S/I/Field
10
11
so.
Take oil burner in line.
At 300 Deg C cut off feed by
Opr.
Field Opr.
Panel/Field
Opr.
4
5
6
7
12
13
strippers.
Increase temp. as required.
14
Opr.
Start top reflux pump when level Pump/Field
15
16
17
SRU.
Maintain required top temp.
Start CR / Product pump, when level
Opr.
Panel Opr.
Panel/Pum
18
19
20
appears in stripper
Adjust column condition.
Heat up stabilizer bottom .
Drain water from V3 when level
p Opr.
Panel Opr.
Panel Opr.
Panel/Field
to Panel/Field
Opr.
Panel/Field
column condition.
JOB DESCRIPTION
Sl.No
Action by
Done
Remarks
YES/NO
21
Field Opr.
21
Panel/Field
22
23
Opr.
S/I
Panel/Field
24
grade tank.
Take all inter locks in line.
Opr.
Panel Opr.
CAUTION:
If FO/FG SOVs, are on bypass mode, on resumption of 110V DC supply shut-off valves
will get automatically open. To avoid this, keep FO/FG shutdown valves on interlock
mode. Low fuel pressure trip will ensure that the S/D valves do not re-open automatically
on restoration of 110V DC powers.
8.10
To supply 24V DC, 2 nos. of keltron panel and battery back up is provided. 24V Dc
supplies is used for (i) Circuit relay/logic system for interlock (ii) Pressure switch signals
(iii) Control valve limit switches for close condition. With failure of one of Keltron panel,
Trouble in Keltron Panel will come and the other Keltron panel will take over. On
failure of both the panels Battery back-up on line signal will come. If 24V DC battery
back up also fails then FO & FG SOVs will get closed and furnace shall switch over to
natural draft. Take following actions to overcome the situation.
ACTION TO BE TAKEN
Sl .No
1
2
JOB DESCRIPTION
Close FG & FO C/V from panel
Isolate individual oil & gas burners
Action by
Panel Opr.
Field Opr.
with steam.
Isolate main FG line B/V.
Field Opr.
Done
Remark
YES/No
Field Opr.
Panel opr.
Field Opr.
Panel/Field
Opr
Panel/Field
Opr.
Panel/Field
10
Opr.
Panel/Field
Column
pressure
comes
under
Opr.
control.
Route product to off grade tank.
Stop all chemical injection pump.
Stop all product & reflux pump
Field Opr.
Field Opr
Panel/Pum
p Opr.
14
down.
Decommission LPG / Naptha / SKO
Field Opr.
15
16
Field Opr.
S/I/Panel
17
battery limit
Opr.
Field Opr.
18
valve.
Do not bypass FO / FG low pressure
Panel Opr.
19
inter lock.
Inform Instrument
11
12
13
Electrical
S/I
Field Opr.
Panel/Field
3
4
5
Opr.
Field Opr.
Field Opr.
Panel/Field
6
7
C/hr.
Ensure low feed pass flow in line.
Check the unit for any leak. Fix it if
Opr.
Panel Opr.
S/I/Field
8
9
so.
Take oil burner.
At 300 Deg C cut off feed by
Opr.
Field Opr.
Panel/Field
Opr.
Introduce
stripping
steam
11
strippers.
Increase temp. as required.
Action by
to
Field Opr.
Panel/Field
Opr.
12
Panel/Pum
13
p Opr.
Pump/Field
14
15
SRU.
Maintain required top temp.
Start CR / Product pump, when level
Opr.
Panel Opr.
Panel/Field
16
17
appears in stripper.
Adjust column condition.
Heat up stabilizer bottom & adjust
Opr.
Panel Opr.
Panel Opr
18
column condition.
Route LPG & Naptha to R/D after
Field Opr.
19
Panel/Field
Opr.
Done
Remark
YES/No
20
21
S/I
Panel/Field
22
grade tank.
Take all inter locks in line.
Opr.
Panel Opr.
Sl
.No
1
2
JOB DESCRIPTION
Action by
YES/NO
Close
Panel Opr.
panel.
Isolate individual oil & gas
Field Opr.
Field Opr.
Field Opr.
Done
Panel Opr.
Remarks
Close
CC-001/3/4
steam
control
valves
and
stripping
valve
bypass
Field Opr.
block
valves.
opened.
Put unit on close circulation.
Adjust RCO cooler O/L
Panel/Field Opr.
Panel/Field Opr.
C
Stop ID fan & switch over
Panel/Field Opr.
10
Panel Opr.
under control.
Route product to off grade
Field Opr.
12
tank.
Stop all chemical injection
Field Opr.
13
pump.
Stop all product & reflux pump
Panel/Pump. Opr
comes down.
Decommission
Naphtha / sko
LPG
Field Opr.
caustic wash
15
16
system
Switch off desalter.
Inform OMS to line up crude
Field Opr.
S/I/Panel Opr.
17
Field opr.
18
valve.
Inform i/m & e/m people to
S/I
Field Opr.
Panel/Field Opr.
Field Opr.
4
5
Field Opr.
Panel/Field Opr.
deg. C/hr.
Ensure low feed pass flow in
Panel opr.
line.
Check the unit for any leak.
S/I/Field Opr.
8
9
Fix it if so.
Take oil burner.
At 300 Deg C cut off feed by
Field Opr.
Panel/Field opr.
circulation.
Introduce stripping steam to
Panel/Field Opr.
11
12
strippers.
Increase temp. as required.
Start top reflux pump when
Panel/Field Opr.
Panel/Pump Opr.
completely.
Start sour water pump & rout
Pump/Field Opr.
14
15
to SRU.
Maintain required top temp.
Start CR / Product pump, when
Panel Opr.
Panel/Pump Opr.
16
17
Panel opr.
Panel Opr.
Sl
Action by
.No
18
YES/NO
Drain water from V3 when
Field/Pump/Pane
l opr.
pump&
19
Done
adjust
column
condition.
Route LPG & Naphtha to R/D
after commissioning caustic
wash system.
Field Opr.
Remarks
20
Field Opr.
21
22
tank.
Sent sample to lab.
If certified, divert product to
S/I
Panel/Field Opr.
23
on grade tank.
Take all inter locks in line
Panel Opr.
JOB DESCRIPTION
Action by
.No
1
Field Opr.
YES/NO
burners valves and flush the
2
3
Field opr.
Field Opr.
stripping
Field Opr.
Done
pass
flow
required.
Adjust
RCO
bypass
cooler
Field Opr.
if
O/L
Field Opr.
Remarks
C.
Monitor desalter pressure from
Field Opr.
field
Stop ID fan & switch over
Field Opr.
Panel Opr.
under control.
Open Column / Vessel PIC
Field Opr
from field.
Route product to off grade tank.
Stop all chemical injection pump
Stop all product & reflux pump
Field Opr.
Field Opr.
Pump/Field Opr
Field Opr.
15
16
Field opr.
S/I
17
Field Opr.
18
valve.
Inform Instrument / Electrical
S/I
ON RESUMPTION OF 24 V
POWER SUPPLY
1
2
Panel/Field Opr.
Field Opr.
Panel/Field Opr.
4
5
6
Field Opr.
Field Opr.
Panel/Field Opr
C/hr .
Ensure low feed pass flow in
Panel opr.
line.
Check the unit for any leak. Fix
S/I/Field Opr.
9
10
it if so.
Take oil burner.
At 300 Deg C cut off feed by
Field Opr.
Panel/Field Opr.
circulation.
Introduce stripping steam to
Panel/Field Opr.
12
13
strippers.
Increase temp. as required.
Start top reflux pump when level
Panel/Field Opr.
Field /Pump Opr.
appears.(
Drain
water
14
completely).
Start sour water pump & rout to
Pump/Field Opr.
15
16
SRU.
Maintain required top temp.
Start CR / Product pump, when
Panel Opr.
Pump/Panel Opr.
17
18
19
Panel Opr.
Panel Opr.
Field/Pump/Pane
l Opr.
Field opr.
20
after
commissioning
caustic
21
wash system.
Route all products to off grade
Field Opr.
22
23
tank.
Sent sample to lab.
If certified, divert product to on
S/I
Panel/Field Opr.
grade tank.
24
Panel Opr.
CHAPTER-9
PROCEDURES FOR EQUIPMENT
HAND OVER TO
MAINTENANCE/INSPECTION
PUMP
9.1.1
COLD PUMP
Sl.No
Description
1
2
STATUS
Yes/No
Remarks
valve to be closed.
If pump service is for heavy product, take FLO and
drain in to OWS (for flushing the pump casing)
9.1.2
Sl.No
Description
8
9
STATUS
Yes/No
Remarks
Ensure pump casing liquid free by checking drain line and setting pump
pressure gauge.
If mech. Seal and pump bearing cooling water line is there, close cooling
water line value.
Isolate pump motor and its auxiliary power supply from sub-station.
9.2 VESSELS
The vessels used in oil refineries are mainly for light/heavy hydrocarbons and some
chemicals. When the necessity arises for a person to enter into the vessel, the following
procedures should be followed:
Sl.
Description
No
1
work environment
Equipment is to be properly depressurized/drained.
Depressurise vessel content to CBD /OWS after
isolation
Depressurise vessel content to flare by opening
STATUS
Yes/No
Remarks
for
any
abnormal
sound
(steam
10
11
location.
Stand by person to be provided outside the vessel
(minimum-2) near the man way. All the above activities
to be competed and vessel are cleaned with proper
precautions then man entry can be given for inspection
and maintenance purposes.
9.3 COLUMNS
In petroleum refineries, this equipment is more prone to deposit pyrophoric substance.
Deposits of iron sulfide are formed from corrosion products that most readily accumulate
at the trays, pump around zones and structured packing. If these pyrophoric iron sulfide
(PIS) deposits are not removed properly before the columns are opened up, there is a
greater likelihood of PIS spontaneous ignition. The trapped combustible hydrocarbons,
coke, etc. that do not get adequately removed during steaming / washing often get
ignited, leading to fires and explosions inside the equipment. These fires not only result
in equipment damage but can also prove fatal for the personnel who are performing
inspection and maintenance work inside the columns. This is entirely avoidable if safe
procedures for column handover are followed.
The targets of these procedures should be two fold:
First, to remove all the combustibles Second, to remove or neutralize pyrophoric iron
sulfide deposits.
Column should be completely isolated from other equipments piping etc. in order to
ensure that there should be no change in the work environment.
1) Steps for column de-pressurization/draining:
1
Column to be isolated/closed/disconnected
Column should be completely isolated from other
equipments piping etc. in order to ensure that
there should be no change in the work
environment
Column to be properly depressurised/drained:
Column under pressure to be depressurised to
fuel gas and then to flare after isolation
Deblind the closed blow down (C.B.D) and OWS
connection/pipes of column and connected
pipings, such as pump suction headers and reflux
line.
De-cap the low point drain(L.P.D) and high point
vents (H.P.V) as pipelines, level gauges, stand
pipes and other tappings connected.
Drain the column material to C.B.D.
return lines
Column to be properly steamed/purged:
Open saturated steams/utility steam to the column
Open vent and other High Point Vent of all
instruments and other connected piping
Open all L.P.D of level gauges and stand pipes
etc.,
Watch column pressure and level
If required wedge to be increased and/or increase
the steam
Check the condensate for oil in condensate
Ensure
complete
steaming/oil
removal
by
observing condensate
columns in which N2 purging is to be done
wedged opening not required
5
9.4 EXCHANGERS/COOLERS/CONDENSERS/REBOILERS:
Sl.No
1
2
3
4
5
6
7
Description
Isolate
and
bypass
exchangers/coolers/condenser/reboiler
Drain the content in CBD
STATUS
Yes/No
Remarks
the
9.5 TANKS:
Sl.No
1
2
Description
Pump out tank material to OM&S respective tank till losses
suction
Get Water hose connection from drain or through dip hatch
STATUS
Yes/No
9.6
FURNACE
Sl.No
1
2
3
4
5
6
7
8
Description
STATUS
Yes/No
Remarks
Description
Ensure that all equipments connected with
flare system are depressurized after shut down
Provide steam connection if not there at the
furthest end of the system
STATUS
Yes/No
Remarks
3
4
5
6
7
8
9
10
11
12
13
Description
STATUS
Yes/No
Remarks
STATUS
Yes/No
Remarks
Description
Take spare safety valve in line if provided
2
3
4
5
CHAPTER-10
PROCEDURES FOR EQUIPMENT
TAKING OVER FROM MAINTENANCE
Description
STATUS
Yes/No
Remarks
/ FIN
COOLERS
10.2 EXCHANGERS
/REBOILERS
/ CONDENSERS
/ COOLERS
Sl.No
Description
STATUS
Yes/No
Remarks
1
2
3
4
5
6
Description
1
2
3
cleaned
Man ways, explosion doors, peep holes, header
7
8
9
10
blind list
Steam and oil connections to the individual
11
9.4 VESSELS:
STATUS
Yes/No
Remarks
Sl.No
1
2
3
4
Description
STATUS
Yes/No
Remarks
STATUS
Yes/No
Remarks
positions
and
properly
secured.
8
9
10
11
12
10.5 COLUMNS:
Sl.No
Description
1
2
3
4
5
6
7
8
10
11
new gasket
Blinding /de-blinding is complete as per master
12
blind list
NRV's are installed in their proper direction
Column bottom drains are connected properly &
13
14
15
are clear
Safety valve are installed and lined up
The instruments are in their respective position
The column is ready for service
CHAPTER-11
SAFETY
SAFETY
11.1
Design of the plant materials used for construction means of escape etc.
11.2.2 GOOD HOUSE KEEPING:
Knowledge of job.
Safe practices.
Action in case of fire.
Knowledge of fire extinguishers etc.
11.2.4 REGULAR TRAINING OF EMPLOYEES
1) INTERNAL
2) EXTERNAL
An emergency manual can be prepared to outline procedures and drills and detail
responsibilities of each individual involved.
Training
Valuable check on the adequacy and condition of exits and alarm system.
Instills a sense of security among the occupiers if careful plans are made.
Exit drills.
Plant drills (mock drills in plant area).
Mutual aid drills.
On-site/off site drills etc.
11.3
FIRE STATION:
Our refinery has two fire stations. Equipped with all modern equipments & trained man
power.
COMMUNICATION:
Ex-telephones: Fire call numbers 7333 & 63333, Hot lines for communicating mutual aid
member, P.A., paging, walkie-talkie system fire alarm: By breaking the glass of any of
the alarm located in the refinery area: At GR-62 nos. & at GHS-53 nos. Sirens 11 nos. at
various locations.
FIRE PROTECTION:
Following fire protection facilities provided depending upon/risk of the installation:
FIRE WATER SYSTEM:
Fire water storage 22,400 M3.
Fire water pumps 8300 M3/hr.
Distribution piping network- approx. 50 Km.
Hydrants (around 1000)
Monitor around (400)
Water spray system (Oil tanks & hydrocarbon pump houses) LPG area as per OISD-116.
FOAM SYSTEM:
Semi fixed:
Mobile:
DCP tender:
Emergency tender:
Foam nurser:
Fire extinguisher:
B.
Fire glass:
20 NOS.(25 kg DCP)
C.
and hydrants
D.
3 NOS.
E.
F.
G.
2 No.
(Near caustic tank, near furnace)
H.
Riser hydrant:
A) at vessel platform
B) all columns.
The task.
Its location.
Personnel involved.
Time limitation
Hot work permit is issued for an activity, which may produce enough heat to ignite a
flammable substance i.e. welding, gas, cutting etc.
11.5.1.B COLD WORK PERMIT
Cold work is an activity, which does not produce sufficient heat to ignite a flammable air
hydrocarbon mixture or a flammable substance.
11.5.1.C EXCAVATION PERMIT
Whenever any worker is engaged on work at a place from which he is liable to fall more
than 2 meters, he shall be provided with a safety belts equipped with life-lines, which are
secured with a minimum of stakes to a fixed structure of anyother effective means.
Helmet shall also be used.
11.5.1.D WORK AT DEPTHS
For entry into confined spaces permit is a must. The intent of an entry permit is that all
necessary measures are taken to protect entering personnel against such hazardous as
oxygen deficiency, hazardous gases, contamination, high temperatures, fire and difficulty
in escaping etc and also to make sure that all concerned are well informed of the job in
progress so that they can avoid hazardous operations connecting to the proposed work
site.
11.5.1.F ELECTRICAL WORK PERMIT
Before issuing any permit to the Maintenance or Engineering personnel for any
maintenance work on any equipment, the shift in charge of the production department
must ensure that electrical isolation has been obtained from the concerned electrical
supervisor. No permit for the work will be issued unless the electrical isolation has been
obtained.
11.5.1.G
Normally the permit is issued for seven days only. However, if the removal is required to
be taken if should be distinctly understood that renewal or revalidation has to be done by
the authority who is competent to issue of permit after ensuring all necessary checks as
for a fresh permit. The renewal is to be recorded on all the copies of the permit.
11.5.4
After the maintenance job is over, the permittee should fill up the permit and handover
the same to the permit issuing authority (issuer) as taken of having completed the job and
surrender the permit. Permittee must also ensure that all the tools, tackles & safety and
fire fighting equipment are removed from the site and the area cleaned to avoid accidents.
11.5.5
For any Hot work / Vessel Entry or Excavation permit on any holiday / Sunday and
extended hours working, approval / clearance of HOD of that area along with clearance
from RSM in each shift is essential.
For any cold work on Holiday / Sunday and for extended hours working, approval /
clearance of Manger / Sectional head is essential.
For Tank Dyke cutting approval / clearance of HOD is essential.
11.5.6
COPIES OF PERMIT:
Fire station
Hospital
Sectional/department head
The supervisor also fills the accident from no. A-1 in triplicate. The original copy of the
form is sent along with the injured to hospital. The medical officer on duty examines the
injured employee, if the nature of the injury is such that the injured person requires rest
for more then 48 hours. A lost time accident report is prepared by the medical officer in
the form A-II and sent the same to fire and safety department. The medical officer
indicated the probable days of rest required by the injured person.
On receipt of the Medical officer report, the personal department informs the factory
inspector as required under the provisions of factories act 1948 and Gujarat factory rules
1963. After receiving form A-II from the fire and safety section in form no.21. One copy
is sent to fire and safety section and third is retain by the personal department.
Personal department immediately informs them relatives of the injured. Police and
Inspector of factories:
INVESTIGATION REPORT:
In case of any accident, whether minor or of lost time nature, the supervisor will arrange
to send an investigation report to the fire and safety department and the concerned
department head on form number A-V within 48 hours of the accident.
11.5.9
S.No.
TAG NO.
SERVICE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
S.No.
5LV2602
5LV3104
5LV3106
5FV1807
5FV2502
5LV3202
5PV1701
5FV2501
5PV3111
5FV1508
5FV2011
5FV2503
5PV1415
5PV1504A
5PV1504B
5PV1912
5PV2011
5PV3203
5PV4406
5SDV1406
5SDV1701
5SDV1901
5SDV1902
5SDV1903
5SDV1904
5SDV2001
5SDV2002
5SDV2003
5SDV2201
5SDV2202
5SDV2203
5SDV2601
5SDV2602
5LV1201
5LV3103
5FV1201
5FV1409
5FV2501
5LV1602
TAG NO.
ACTION/ FAIL
SAFE CONDITION
A/C (FO)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/C (FO)
A/O (FC)
A/O (FC)
A/C (FO)
A/C (FO)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/O (FC)
A/C (FO)
A/O (FC)
A/O (FC)
ACTION/ FAIL
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
5PV3202
5SDV1401
5LV1202
5TV1702
5FV1401
5FV1402
5FV1403
5FV1404
5FV1804
5FV2206
5FV3102
5HV1701
5PDV1420
5SDV1402
5SDV1601
5SDV2501
5PV1423
5FV1410
5FV1412
5FV1413
5FV1414
5FV1505
5FV1805
5FV1806
5HV2001
5HV2002
5HV2201
5HV2202
5SDV1801
5FV1501
5LV1508
5LV1510
5SDV1403
5LV1206
5FV1502
5TV1116
SAFE CONDITION
LP STM TO LPG VAPORISER
A/O (FC)
FO RETURN
A/O (FC)
1st STAGE DIST. WTR I/L
A/O (FC)
NAPH. STAB. BTM. SAT. EE-018A/B
LOCK (FC)
CRUDE TO HTR PASS-1
A/C (FO)
CRUDE I/L PASS-2
A/C (FO)
CRUDE I/L PASS-3
A/C (FO)
CRUDE I/L PASS-4
A/C (FO)
HSD R/D
A/O (FC)
KERO/ATF COALASCER O/L
A/O (FC)
HP STM TO EE-028A/B/C/D
A/O (FC)
STABISER O/H VAPOUR
A/O (FC)
ATM STM TO HTR
A/C (FO)
FO SUPPLY
A/O (FC)
SOUR WTR TO SRU
A/O (FC)
LPG TO LPG SURGE DRM
A/O (FC)
FG TO HTR
A/O (FC)
DECOCKING STM TO HTR PASS-1
A/C (FO)
DECOCKING STM TO HTR PASS-3
A/C (FO)
DECOCKING STM TO HTR PASS-4
A/C (FO)
DECOCKING STM TO HTR PASS-2
A/C (FO)
TOP RFLX TO CC-001
A/C (FO)
LR TO BL(FPU)
A/O (FC)
LR TO BL STORAGE
A/O (FC)
LN+CAUSTIC TO VV-009
A/C (FO)
LN WTR TO VV-010
A/C (FO)
KERO+ATF+CAUST. TO VV-013
A/C (FO)
KERO+ATF+WASH WTR TO VV-014
A/C (FO)
LN TO CAUSTIC WASH
A/O (FC)
TOP CIR. RETURN TO CC-001
A/C (FO)
KERO STRIPPER FEED
A/O (FC)
GAS OIL STRIPPER FEED
A/O (FC)
FG SUPPLY
A/O (FC)
CRUDE BOOSTER PMP D/S
A/C (FO)
ATF/KERO CR RETURNED TO CC-001
A/C (FO)
EXCH-05-EE-006 A/B BYPASS
A/C (FO)
11.5.10
ACTION
Cut off all furnace
Take unit on circulation. If required
shutdown totally.
Block adjacent roads
Inform F&S
Isolate leaky section using PPEs &
depressurize to flare.
Inform RSM/CPNM
Open STD
Cut off fuel to furnace
Cut off feed
Put coil purging steam.
Take emergency S/D of entire
plant
Inform RSM / CPNM
Bypass exchanger-using PPE &
isolate it.
Depressurize
Keep steam Lancer
Inform RSM / CPNM
Cut off furnace if H/C vapor travels
towards furnace
Start stand by pump
Isolate the leaky pump
Depressurize
Keep fire Engine standby.
Inform RSM / CPNM
1. PSVs
2. Interlocks
3. Hydro-carbon leak detectors
4. Fire water sprinkler system
5. PPEs
1. PSVs
Purpose: PSVs are provided to protect the equipments like columns, vessels, pipe line
etc by relieving excess pressure to flare / atmosphere when there is abnormal
pressurization due to CW failure or fire etc.
Where Situated: Normally it is situated at column top vessel top, compressor discharge
and positive displacement pump discharge.
Relieve Where: Normally to flare system.
Flare Knock Out Drum: All PSV discharge is routed to flare connected to a header
which is routed to flare KOD located at AU5 battery limit. Liquid which is carried along
with gas is settled in this vessel are drained out to CBD. Only gas from its top is send to
flare. It is provided with a level indication (with alarm). Level indication is transmitted to
DCS CR. In normal condition once in a shift draining is done.
2. Interlocks
Purpose: Meant for protecting of equipment in case of extreme deviation in parameter
from operating limit, before it reaches the equipment design limit.
Location: Furnaces
What all interlocks: (Furnace fuel will cut off if there is)
Low Combined pass flow
Low FG pressure
Low Fuel Oil pressure.
FD fan failure
ID fan failure (STD does not open with in 30 sec)
3. Hydrocarbon Leak detectors:
CHAPTER-12
MATERIAL SAFTETY DATA SHEET
12.1 AHURALAN
AHURALAN ESK 50
1) CHEMICAL IDENTITY
Chemical Name
Corrosion Inhibitor
Synonyms
Corrosion Inhibitor
Formula
R1NHR2NHR3RH
Chemical
Classification
Trade Name
C.A.S. NO.
5285-60-9
UN NO.
Regulated
Identification
Ahuralan ESK 50
Hazardous
ingredients
C.a.s. No.
C.a.s. No.
Ahuralan
50
Hazardous
ingredients
ESK 5285-60-9
Solubility
in Insoluble
o
water @ 30 C
0.83
pH
Solubility in
others
Not applicable
Viscous,
Yellowish brown
Pungent
Flammability
Moderate
LEL (%V)
TDG
3
UEL (%V)
Flammability
Auto ignition Temperature oC
228
Explosion Sensitivity to Impact
Explosion Sensitivity to Static
Electricity
Hazardous Combustion products CO, CO2
Hazardous Polymerization
Combustible
Yes
Explosive
Liquid
Material
Flammable
Yes
Oxidiser
Material
Pyrophoric
No
Organic Peroxide
Material
0.7
5.0
No
Corrosive Material
No
Others
No
4) REACTIVITY DATA
Chemical Stability
Stable
Incompatibility
with
other None
material
Reactivity
Hazardous Reaction Products
5) HEALTH HAZARD DATA
Routes of Entry
Effects of Exposure/ Inhalation
Symptoms
Ingestion
Contact
Emergency Treatment
37 66
No
Inhalation
Ingestion
Contact
LD50
mg/kg
(Oral-Rat),
Permissible
Exposure Limit
TLV
ppm
mg/kg
ppm
(ACGIH)
STEL,
ppm
mg/kg
mg/kg
NFPA Hazard Signals
Health
Flammability
Reactivity/Stabilit
y
Special
6) PREVENTIVE MEASURES
Personal
Equipment
Fire
Extinguishing
Media
Special
EXPOSUR
E
Procedure
Unusual Hazards
First
Aid Obtain immediate medical attention.
Measures
Inhalation : Remove affected person to fresh air. If
respiratory problems develop.
Antidotes/
Dosage
SPILLS
Steps to be taken
affected area.
12.2
AMMONIA
AMMONIA
1) CHEMICAL IDENTITY
Chemical Name:
AMMONIA
Formula:
NH3
UN NO. 1005
Regulated
Identification
C.A.S.NO: 7664-41-7
Shipping Name : Ammonia
7664-41-7
2.
0.771
@ 0oC
eactivity
azardous Reaction
Combustible Liquid
Yes
Flammable Material
Pyrophoric Material
No
No
Explosive Material
Oxidiser
Organic Peroxide
No
Corrosive Material
No
No
No
Others
4.REACTIVITY DATA
Chemical Stability
Stable
Special Procedure
Unusual Hazards
by
spraying
water
Gas is suffocating.
EXPOSURE
First
Aid
Measures
Inhalation : Remove the victim to fresh air area, provide artificial respiration or oxygen, if
needed.
Skin : Remove the contaminated clothes and wash the affected area with plenty of water and
soap.
Eyes : Flush with plenty of water for 15 mins.
Seek medical aid.
Antidotes/Dosages
Not available.
SPILLS :- Steps to be taken Contain leaking liquid on sand or earth, allow to evaporate.
Dilute the vapors with plenty of water.
Waste Disposal Method :- Put into a large vessel containing water, neutralize with HCl
And discharge into sewer with sufficient water.
8.ADDITIONAL INFORMATION/REFERENCES
A human poison by an unspecified route. Difficult to ignite. NH3 and air in a fire, can
detonate. Potentially violent or explosive reactions on contact with interhalogens. Forms
sensitive explosive mixture with air and hydrocarbons. Those affected with eye and
pulmonary diseases should avoid exposure to Ammonia.
12..3
CAUSTIC SODA
CAUSTIC SODA
1. CHEMICAL IDENTITY
NaOH
Regulated
Identification
C.A.S.NO. 1310-73-2
: Corrosive, Class-8
Sodium Hydroxide
C.A.S.NO.
HAZARDOUS
1310-73-2
C 318.4 - 322
Odour:
@ 35oC 1 mm Hg at 730 oC
Solubility in water @ 30 oC
Vapour Density
Not Pertinent
Soluble in Alcohol, Methanol
(Air = 1)
Glycerol.
Specific Gravity
(Water = 1)
Vapour pressure
Appearance :
2.12
at 24oC/4 oC
Soluble
pH
13 - 14
Others:
and
Flammability
(OC)
TDG Flammability
(CC)
No
LEL
N.A.
UEL
Flash Point oC
Not pertinent
Flash Point oC
Not pertinent
Not Pertinent
Stable
Stable
Emits toxic fumes of Na2O.
Will not occur
Explosive Material
No
Oxidiser
Organic Peroxide
No
No
Corrosive
Others
Stable
Water, Acids, Flammable Liquids, Organic halides, metals,
and Nitro Compounds.
Vigorous reaction with Organic Halides, Metals, Nitro
Not available.
Severe
Emergency Treatment
respiration,
fruit juice.
L.D50 (Oral-Rat)
Permissible
3
ppm Odourless mg/m
Exposure Limit
TLV (ACGIH)
ppm Not listed mg/m3
Health
3
STEL
Not listed
Flammability
0
6.PREVENTIVE MEASURES
Personal Protective
Avoid contact with solid or liquid.
Equipment.
Provide side covered safety goggles, face shield, filter
or
dust-, type respirator, rubber shoes and rubber hand gloves.
Handling and Storage
Precautions
7.
8.ADDITIONAL INFORMATION/REFERENCES
12.4
DIETHANOL AMINE
DIETHANOL AMINE
1.CHEMICAL IDENTITY
Chemical Name
Di-ethanol amine
Synonyms
DEA, 2,2-Iminodiethanol
Formula
Regulated
Identification
Chemical
Classificatio
n
Trade Name
C.A.S. NO.
Shipping Name
111-42-2
DEA
UN
NO.
Di-ethanol amine
Codes/Label
Hazardous waste
I.D. No.
17
Hazchem Code
2T
HAZARDOUS
INGREDIENTS
C.A.S. NO.
1. Diethanolamine
111-42-2
HAZARDOUS
INGREDIENTS
C.A.S. NO.
Physical State
Liquid
Appearance
Fainlty
coloured
Odour
Vapour pressure
@ 35 oC, mm Hg
Ammonia
Vapour
Density
(Air = 1)
1.
3.65
Solubility
in
water @ 30 oC
Solubility in
others
Specific
1.0919
pH
Gravity
(Water = 1)
FIRE AND EXPLOSION HAZARD DATA
LEL (%V)
148.89
TDG
UEL (%V)
Flammability
Auto ignition Temperature oC
662
151.6
Flammability
Slight
Corrrosive
Material
Others
No
No
REACTIVITY DATA
Chemical Stability
Stable
Incompatibility
with
other Oxidising materials
material
Reactivity
Hazardous Reaction Products
3.HEALTH HAZARD DATA
Routes of Entry
Effects of Exposure/ Symptoms
Inhalation/ingestion/contac
Diethanol amine has been characterized as being of low
toxicity.
LD50
mg/kg
Permissible
Exposure Limit
mg/kg
ppm
Health
1
4.PREVENTIVE MEASURES
Personal Protective
Handling and Storage Precautions
STEL,
Flammability
1
ppm
mg/kg
Reactivity/Stabilit
y
0
Special
Fire
Extinguishing Foam, CO2, DCP, Water spray
Media
Special Procedure
EXPOSUR
E
SPILLS
Unusual Hazards
First Aid Measures
Antidotes/ Dosage
Steps to be taken
Waste
Method
Disposal
Use water spray, dry chemical, foam or carbondioxide. Water or foam may cause frothing. Use water
to keep fire exposed containers cool. Water spray may
be used to flush spills away from exposure.
IMMEDIATE MEDICAL ATTENTION REQUIRED.
Remove victim to fresh air. Remove contaminated
clothing Wash affected part with plenty of water for
atleast 30 mins.
Give plenty of water to conscious victim to drink and
induce vomiting
12.5
DEMULSIFIER
DEMULSIFIER
1.CHEMICAL IDENTITY
Chemical Name
Synonyms
Demulsifier
Chemical
Classificatio
n
Mixture
compounds
Formula
Regulated
Identification
C.A.S. NO.
Shipping Name
Codes/Label
Hazardous waste
I.D. No.
Hazchem Code
HAZARDOUS
INGREDIENTS
1.
Petroleum solvent
2.
Aromatics
C.A.S. NO.
of
organic
Demulsifier
UN
NO.
Demulsifier
HAZARDOUS
INGREDIENTS
C.A.S. NO.
Physical State
Liquid
Appearance
Dark Brown
Vapour pressure
@ 35 oC, mm Hg
Odour
Solubility in Aromatic
others
solvent,
kerosene
Specific
Gravity
(Water = 1)
pH
6.0 to 7.0
Yes
TDG
3
Flammability
Auto ignition Temperature oC
LEL (%V)
UEL (%V)
4.REACTIVITY DATA
Chemical Stability
Incompatibility
material
Reactivity
with
CO, CO2
Stable
other
No
Corrosive
Material
Others
No
>93
Inhalation
Inhalation, contact
May cause headache and nausea.
Nausea, vomiting. If retained leads to symptoms of
central nervous system depression.
Contact
Skin : Dermatitis,
Eyes : Irritation
Emergency Treatment
Inhalation
Ingestion
Contact
LD50
mg/kg
Permissible
Exposure Limit
TLV
ppm
(Oral-Rat),
mg/kg 50 mg/m3
ppm 10
(ACGIH)
STEL,
ppm
mg/kg
15
75 mg/m3
mg/kg
NFPA Hazard Signals
Health
Flammability
Reactivity/Stabilit
y
Special
6.PREVENTIVE MEASURES
Personal Protective Equipment
Handling and Storage Precautions
Special Procedure
Unusual Hazards
EXPOSUR
E
Antidotes/ Dosage
SPILLS
Steps to be taken
Waste
Disposal
vermiculite.
Method
8. DISCLAIMER
Information contained in this material safety data sheet is believed to be reliable but no
representation, guarantee or warranties of any kind are made as to its accuracy, suitability for
a particular application or results to be obtained from them.
CHAPTER-13
PROCESS UPSET & CORRECTIVE
ACTIONS
Equpt No
Column
Measured parameter
Top Pressure
Deviation
High
High
Action to be taken
Check top pressure C/V
Reduce bottom firing /COT
if required
Differential pressure
High
Maintain
required
top
temperature
Vessel
Level
High
more HSD
Increase R/D flow
Optimize
inflow-keeping
specification on grade.
Check
for
any
R/D
blockage
Pressure
High
Maintain
temperature as required
vessel
Temperature
High
Increase
CW
flow
in
Cooler / Condenser
Reduce
CW
supply
temperature
Maintain
product
draw
temperature as required.
3
Furnace
Skin temperature
High
High
pass
Adjust furnace firing to
High
Stack temperature
High
Do shoot blowing.
VV-02
Boot water PH
High
injection
VV02
Low
Reduce ammonia / caustic
injection
VV-02
CL content
High
Check
caustic
solution
strength
Fe content
High
Check
operation
Corrosion inhibitor pump
increase dozing
of
&
LPG
& H2S slippage by Pb- +ve
Naphtha
acetate test
caustic /
water
wash
Replenish
with
10%
spent
strength
caustic
fresh
caustic
2800 C-2900 C
1200 C - 1250 C
12.0 13.5 kg/cm2
25- 30 M3
1090 C --1120 C
3450 C -3550 C
2.2 - 2.4 kg/cm2
2.3 2.5 kg/cm2
300 C - 400 C
3730 C - 3780 C
8- 12 M3
1500 C -1650 C
2000 C --2100 C
C2 Reboil temp.
S/steam in C3
S/steam in C4
S/steam in C1
C05 Feed temp.
C05 tray 13 temp.
C05 bottom temp
C05 top pressure
C05 bottom pressure
C5 Reflux Temp.
V-9 Caustic flow
V-10 water flow
C-6 top pressure
1850 C -1950 C
9001000 Kg/hr
190-210 Kg/hr
45005000 Kg / hr
1200 C --1300 C
850 C --950 C
1800 C --1900 C
10-11 kg/cm2
11-12 kg/cm2
400 C --500 C
812 M3
8-12 M3
11-12 kg/cm2
3000 C --3100 C
140155 M3
1100 C -- 1200 C
200 - 250 M3
1300 C --1400 C
380420 M3
2100 C --2300 C
L. amine flow
V6 caustic flow
V7 water flow
Furnace Arch
Skin
Box
5-7 M3
8-12 M3
8-12 M3
8700C Max
550 0C Max
1100 0C Max
Equipment
Furnace
Pass flow
Critical
Parameter
110 - 125
m3/hr
Instrumen
t Provided
FRC
Furnace
COT
373 3770C
TC
cascaded
IMPLICATION
If pass flow decreases, its skin &
COT will increase.
If pass flow increases, its skin &
COT will decrease.
Ensure flow above low alarm limit
Ensure equal pass flow through all
passes
Ensure steady oil temp.
with PC
on oil or
PC on gas
Furnace O2
02-03%
O2
analyzer
Furnace
arch
pressure
-5 to +2
mmwc
PI
Sl.N
o
5
Equipment
Furnace arch
temperature
Critical
Parameter
8700C
Max
Instrumen
t Provided
TI
Furnace stack
temperature
160
1800 C
TI
Implication:
Adjust burner flame height.
Adjust air requirement
If required reduce Tput
High arch temp. Tube life will
reduce. Refractory may damage.
Ensure furnace is not hard fired
Arrange for APH cleaning
At high stack temp. APH efficiency
will reduce & fuel consumption will
increase.
C1 Column
top Pressure
2.2-2.5
Kg/Cm2
PC split
range
between
FG &
Flare
Column top
Temperature
109-1120C
TC
cascaded
with top
reflux
Over Flash
08-12
m3/hr
FI
10
Column
Bottom Level
40-50%
LI / LCV
cascaded
with
bottom
R/D flow
11
30 to 40%
LDIC
12
Desalter
Amps
< 20 amps
Ammeter
13
Desalter
Pressure
11.5 to
13.5
PG / PC
on pre
desalter
crude
pump
discharge
line.
14
De-salter
temperature
120-130
15
Reflux drum
boot level
40 to 50%
LCV
16
Caustic /
water wash
vessels inter
phase level
10 to 20%
LCV
17
Boot Water
Chloride
content
High
Fe
content
57
m3/hr
High
18
L. Amine flow
in C6
FCV
CHAPTER-14
HANDING & TAKING OVER OF
INFORMATION DURING SHIFT CHANGE
CHAPTER-15
CONTROL OF HAZARDOUS CHEMICAL
INVENTORY LEVEL
NaOH
Ammoni
AU1
AU2
AU5
AU1
Average
AU5
Inventory level
consumption
for 15 days
715 Kg
189 Kg
280 Kg
5 Kg
10 Mt
2.5 Mt
4 Mt
75 Kg
8 kg
cylinder
120
/
2 4 Cylinders
10
cylinder
150
/
4 5 cylinders
a
AU2
daily Requirement
Cylinder
(requirement+
10%)
12 Mt
2.75 MT
4.4 Mt
2 3 cylinders
CHAPTER-16
PLANT EQUIPMENT IDLING METHOD
ACTION
Float with Fuel gas
Stop all chemical injection
drum (VV-02)
Desalter
Heat Exchanger
on
IFO
CHAPTER-17
TASK PERFORMED BY OPERATORS
Action
Desalter temperature
too high
Desalter temperature
too low
High salt content in
desalter outlet
Desalter tripped
LPG recovery
Product colored
Other job
(AU1/2)
Adjust HSD CR
Increase/decrease SKO draw (if permissible), after
consulting PNE
Increase / decrease HSD draw
Increase / decrease HSD draw
Adjust HSD CR flow
Reduce/increase ammonia injection to column over head line
If any margin exists in main column stripping steam (with
respect to Tput), increase column stripping steam flow
Raise COT, if margin exists.
Raise HSD with draw rate by keeping the required quality
Keep minimum over flash flow
Ask pump operator to check color at draw pump vent.
If it is colored at pump, ask instrument to check fractionator
bottom level. Taking RCO r/d controller on manual mode,
pump out more to reduce level. Ask pump operator to check
RCO pump load, if required start 2nd pump.
Divert the colored product to slop tank.
If color is normal at pump, ask to check color at each heat
exchanger outlet. Identify & isolate the leaky heat exchanger.
As & when asked by shift in-charge.
17.2
Furnace Operation:
Sl. Observation
No
1 Furnace hazy, smoky burner.
COT is low
Flame impingement
5
6
8
9
10
11
12
13
14
15
16
Action
17
18
19
20
21
22
23
24
25
Inform to S/I
Keep a steam lancer at the location,
if required
Inform PNE
Check line up / its tracing steam
If problem persists, line up RCO to
surge drum
Adjust steam to heater coil by
furnace operator
In morning & evening shift.
Inform panel man to open STD
before starting soot blowing
If soot blowers are not functioning,
inform S/I to attend by respective
maintenance group.
Check stack damper opening
Check for any air ingress inside the
furnace
Reduce the fuel gas consumption, if
possible
Adjust air register
Adjust fuel oil burners
Adjust air, oil, steam etc wherever
required.
Check / keep close all peepholes.
Inform S/I to rectify the defective
one.
Check for any hot spot on the tubes.
Report if any.
Check for any abnormality on
furnace roof (hole etc). Report to S/I
for corrective action.
Adjust stack damper after consulting
S/I wherever applicable.
Inform S/I to rectify the defective
PGs
Check record IFO tank level
Check healthiness of IFO pump
If VR system fails, take IFO system
in line (For AU1/AU2)
Line AU5 RCO to VR drum in case
of VR receiving fails from GHC
26
27
28
Emergency handling
29
30
31
32
33
34
35
36
operator
Incase of ID fan, stop ID fan by
coordinating with panel operator
Report to PNE to attend it by
maintenance
Report to PNE/Panel Operator
If stand by is present, took other FD
fan in line immediately to avoid
damage to equipment/furnace
tripping
In case of ID fan, stop ID fan by
coordinating with panel operator.
Check the lube oil quality in fluid
coupling chamber (water carry over)
Report to PNE for any tube puncture
in the lube oil cooler
As per guidance of shift in-charge
Action
Log in log book / display in board
Up date log book and display board
Inform Panel operator for any abnormality.
Change over the tank with full one.
Top up / prepare solution in the empty
tank.
Check the performance of running
pump/motor
If it not pumping, start the stand by
pump and observe change in tank level
Check discharge PSV is popped up
Report to PNE to attend it by
maintenance
Check whether the pump is
developing a required pressure or not
If it is not developing, check discharge
b/v NRV passing
Start the stand by pump, as per
procedure and observe tank level
Report to PNE to attend it by
maintenance
Inform S/I to arrange to connect CI
drum.
Transfer required amount of CI to tank
Dilute with K9 bottom / H. Naphtha
(1:4 ratio)
Circulate solution for 3-4 hr.
Adjust dozing to respective column
top as per requirement.
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Desalter desludging
29
30
31
32
33
34
35
36
37
38
39
40
Emergency Handling
41
42
43
44
45
17.4
Pump Operator
5
6
7
8
9
11
12
10
Action
Make up. Ensure oil level in bearing.
Drain & replace it. Inform S/I or
maintenance
Inform PNE for attending the same by
maintenance
Inform S/I. If abnormally high, C/O the
pump & inform S/I.
Inform PNE for attending it by maintenance
C/O pump, after informing to PNE
Inform PNE for attending it by maintenance
Throttle discharge after consulting panel
operator
Adjust load by adjusting discharge valve
Inform PNE for attending it by maintenance
13
14
16
17
18
19
20
21
22
Emergency Handling
23
15
24
25
26
27
28
29
30
31
32
33
CHAPTER-18
DCS INFORMATION
DCS INFORMATION
1.Refinery name and location
Gujarat Refinery
2. Plant data
AU- 5 Ver.10.20
3. DCS
3.1 MAKE
YOKOGAWA BLUE STAR
3.2 MODEL CENTUM-VP
4. DCS OPERATING SYSTEM
4.1 SOFTWARE TYPE/ VERSION
4.2HARDWARE PLATFORM
HICS:HP 9000WORKSTATION
FCS & ICS: YBL PROPRIETARY STATIONS
5.PLC (FOR SHUTDOWN SYSTEM)
5.1 MAKE
5.2 MODEL
5.3 ARCHITECTURE
6.CONTROLLER SUB SYSTEM
6.1MULTI LOOP
ABB-AUGUST SYSTEMS
CS 300E
TMR
6.1.1 MODEL NO
6.1.2 SCAN TIME
6.2 SINGLE LOOP
6.2.1 MODEL NO
6.2.2 SCAN TIME
CP 334D
1 ms to 500 ms (configurable)
N/A
MULTIDROP/TOKEN
PASSING
10 MBPS (V- NET)
91
421
239
NOT IMPLIMENTED
CHAPTER-19
ADVANCE PROCESS CONTROL SYSTEM
MVC VARIABLES
Three types of variables are input to MVC
A) Controlled Variables (CVs)
These are the Plant parameters, i.e. the plant parameters operators' watch
and try to keep at pre-decided values. They are either measured values (Eg. SKO
draw Temperature) or inferred values (Eg. SKO FBP)
MVC attempts to keep the CVs at operator specified set points or within the range
(i.e. between high and low Limits)
Multivariable Control
Multivariable control means simultaneous control of more than one CV
by coordinated adjustment of more than one MV. Controllers consider additional
DV effect on the CVs for feed forward disturbance rejection and control action. .
MVC models between MV and CV obtained during plant step testing and it uses
this model for doing plant control.
Example Adjustment of Gas oil Flow (MV) affects Gas Oil Draw
Temperature (CV) as well as Overflash flow (CV). Therefore the value of Gas oil
flow-rate should be adjusted in such a way that both Gas oil draw temperature and
Overflash flow are within the acceptable limits. MVC tries to maintain both the
CVs within limits by adjusting the MV.
Also any change in COT (which is not under control of MVC) affects
Overflash flow. Therefore if there is any change in COT, say due to Fuel Gas
pressure disturbance, MVC predicts that Overflash flow will get affected after
some time due to disturbance in COT and takes advance action to minimize the
effect of disturbance on process.
Benefits of MVC :
The benefits of MVC are
Tighter Control
Plant pushed towards Constraints.
Economic (Operational) Optimization.
The incentive for MVC is reduction in plant parameter variations leading
to profitable plant operation. MVC is much useful, when process is interactive i.e.
when one MV affects Multiple CVs. (For Eg. Varying GO CR flow affects draw
tray temperatures as well as top reflux flow)
Implementation Platform for MVC Controller:
MVC controller runs in server (Windows based Computer), it is positioned
in IS building.
medium between MVC and DCS making to and fro (bi-directional) dataflow
between DCS and Computer. Software called RDI (Real Time data Interface) runs
in the Real Time database server.
RMPCT
Computer
(MIS Building)
(MIS
Building)
RMPCT (AU-5)
PHD
PHD
PHD-PHD
RDI
RDI-CM50S
RefineryLAN
PLNM
(AU-5 Control Room)
Physical Network.
------------------------- Software Connection..
AU-5 DCS
Manipulated Variable
TOP CR Flow
LN R/D Flow
HN R/D Flow
SKO Rundown Flow
HSD R/D Flow
SKO CR Flow
HSD CR Flow
Furnace COT
Controlled Variables
Top Pressure Control valve to flare opening, Top Reflux Flow
Gas oil to EE-14 (Stabiliser Reboiler)
Top Pressure Control valve to flare opening, SKO flash, SKO
R/D flow
HN R/D Flow, SKO, HSD draw temperatures, Overflash flow
HSD draw temperature, Overflash flow
SKO draw Temperature, Top Reflux flow, Top Pressure
Control valve to flare opening.
HSD draw Temperature, Top Reflux flow, Top Pressure
Control valve to flare opening
Top Reflux Flow, Flare valve opening, Overflash flow, Top
Pressure Control valve to flare opening, Bottom Temperature
1)
2)
3)
4)
Wait for at least one minute after changing the MODE from CASCADE to
AUTO before changing the set point or Valve opening values (Unless there is an
immediate need to do so). Immediately changing the set point or opening after
taking the mode from CASCADE to AUTO or MANUAL (within one minute)
may sometimes cause the entire controller to shed control fully. Watchdog timer
becoming 0 indicates this in the DCS. The controller then has to be reset by
advanced control group before RMPCT controller can again be started.
E) Taking out One or More CVs from RMPCT Control:
Touch the STATUS column for the corresponding CV. GOOD/DROP
option will appear at the bottom. By selecting DROP, the respective CV can be
dropped from MVC control. Once DROP for a particular CV has been selected,
after about one minute, the corresponding GOOD value in STATUS column will
change to DROP. By dropping a CV, MVC will not consider the CV value while
doing the calculation and it will not try to maintain a dropped CV within limits.
this case, the operator may expect that RMPCT will Decrease SKO Run down
flow to bring the draw temperature within limit, but it is not doing it.
The most likely reason for the same is that some other parameters say
HSD draw temperature is 294 Deg C whereas the low and high limits are 296 and
298 Deg C respectively and HSD TC controller has is at the highest limit. So the
controller feels that decreasing the SKO rundown flow from 25 M3/HR will cause
the HSD draw temperature to still go down from 294 Deg C and it cannot increase
the HSD TC opening to increase HSD draw temperature because it is already hit
the higher limit.
In this case, the operator can either widen the limits of least important CV
(either SKO or HSD draw temperature) or drop that CV altogether so that
controller takes action based only on most important CV. If possible the upper
limit of the MV can be increased so that both the targets can be achieved.
4) The main benefit of MVC is optimisation of the parameters, which have an impact
on quality, economics within the given constraints. Thus MVC helps in improving
the Refinery operation. However while MVC is in line, monitoring whether the
operational targets are being achieved by MVC or not is the responsibility of
operating group, because there may be some peculiar condition in the plant due to
which MVC may be taking the plant slowly towards the target or may not be
taking towards it at all. Such situations are most likely to happen when there is a
conflict in upper and lower limits among interacting parameters. Relaxing a less
important parameter (i.e. widening the limits) will most likely make MVC achieve
the operational target and if still such problem persists, Advance control group
may be informed of the same for corrective action.
1)
Check whether the Watch Dog Timer is not in Zero. If it is in Zero, MVC will
not start and the undersigned needs to be contacted for starting MVC program in
computer.
2)
If watchdog is on, check whether the low & high limits for Manipulated
Variables and Controlled Variables are ok. If any of the actual values are outside
the low or high limits, it will be indicated by Red colour.
3)
Once Watch dog is on, Touch ON button on MVC screen and press Enter. ON
button starts blinking.
4)
Check whether the status of the desired MVs (right hand corner of each
MV) to be taken in CASCADE mode is in RMPC. If the status of the MV to
be taken in MVC is in OPR, touch the STATUS column of the particular MV (3rd
Column from Left). Two options will come in the bottom viz. OPR, RMPC.
Touch RMPC. Now the status of that MV changes from OPR to RMPC in the
right hand corner. The same procedure needs to be repeated for other MVs
which are to be taken in cascade and is in OPR.
5)
Once the right hand corner of desired MV is in RMPC and the MVC has been
switched to ON position, Check whether the MVs have gone to CASCADE
MODE or not. If the other MVs have not gone to CASCADE mode, select those
MVs and change mode from AUTO to CASCADE.
6)
Once all the desired MVs have come to CASCADE mode after one minute the
STATUS column (3rd column from left) changes from FFWD to ON for the
MVs in CASCADE mode. The MVs for which the status is indicated ON are
under MVC control.
1)
Completely Switching MVC OFF : Select OFF button on MVC screen and
press enter. MVC will be switched off and all the controllers will go their earlier
mode (i.e. AUTO / MANUAL /BCAS) depending on the configuration.
2)
CHAPTER-16
LABORATORY TEST SCHEDULE
CHAPTER-20
LABORATORY TEST SCHEDULE
STREAM
1.
LPG
2.
LIGHT
NAPHTHA
3.
4.
HEAVY
NAPHTHA
SKO
5.
GASOIL
TEST
FREQUENCY
COPPER CORROSION
H2S &CAUSTIC WASH
DENSITY
DISTILATION
RVP
COPPER CORROSION
1/D
1/D
2/D
1/D
2/D
Once in an
alternate day
2/D
1/D
2/D
2/D
2/D
2/D
2/D
2/D
DENSITY
DISTILATION
DENSITY
FLASH
DISTILATION
DENSITY,FLASH
POURPOINT,
DISTILATION
TEST
PERFORMED
SHIFT
SHIFT
SHIFT
SHIFT
SHIFT
SHIFT
6.
7.
8.
9.
10.
11.
12.
13.
14.
SOUR
WATER
EX.V2
V-6/9/13
CAUSTIC
DESALTER
CRUDE
I/L,O/L
DESALTER
BRINE
WATER
V-7/10/14
WATER
FLUE GAS
CAUSTIC/
AMMONIA
RCO
TK-2A/B &
TK-6A/B
PH
CHLORIDE
FE
STRENGTH
1/D
1/D
1/D
1/D
SHIFT
DENSITY
SALT
BS&W
PH
OIL CONTENT
1/W
1/W
1/W
1/W
1/W
SHIFT- SUN
% OF CAUSTIC
1/W
G/S -WED
ORSAT
STRENGTH
ON REQ
ON REQ
SHIFT
SHIFT
RECOVERY AT 360C
CAUSTIC SOLUTION
STRENGTH
1/W
ON REQ
G/S
SHIFT
CHAPTER-21
MASTER BLIND LIST
SHIFT
SHIFT- SUN
BLIND LIST
BLIND LIST
S. No
1.
1
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
DESCRIPTION
SIZE
S/D
TYPE
24
RUNNI
NG
Out
CW inlet
In
Tail
2
2
2
14
10
6
14
12
6
2
6
6
4
4
Out
Out
out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
In
In
In
In
In
In
In
In
In
In
In
In
In
In
Spect
Spect
Spect
Tail
Tail
Spect
Tail
Spect
Spect
Tail
Spect
Spect
Spect
Spect
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
SrN
o
1.
1
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
DESCRIPTION
2
3
4
4
4
4
4
4
4
3
4
6
6
8
10
12
10
8
2
3
6
24
24
CC01- COLUMN
SIZE
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
out
Out
Out
In
Out
Out
Out
Out
Out
Out
In
Out
Out
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
In
S/D
TYPE
In
Tail
In
In
In
In
In
In
In
In
In
In
In
In
In
In
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Feed Entry
30
RUNNI
NG
Out
Desalter PSV-1
Desalter PSV-1
Bottom O/L
Top O/L
Gas Oil CR Return
Kero CR Return
Top CR return
Top Reflux
Top CR Draw Off
Side Draw Off
Kero (to Stripper) Draw Off
Kero CR Draw Off
Gas Oil draw Off
Gas Oil CR Draw Off
10
10
14
30
14
14
12
8
16
8
16
16
16
16
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Out
Spect
Spect
Spect
Tail
Spect
Spect
Spect
Spect
Spect
Spect
Spect
Spect
Spect
Spect
Tail
Tail
Tail
Spect
Spect
Tail
Tail
Tail
Tail
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
SrN
o
1
2
3
4
5
6
7
DESCRIPTION
1
2
3
4
5
6
Vapour Outlet
Top Vent
Stripping Steam I/L
Reboiler Feed
Reboiler Return
Bottom Outlet
Vapour Outlet
Top Vent
Stripping Steam I/L
Reboiler Feed
Reboiler Return
Bottom Outlet
Steam Out point
10
12
14
10
3
8
8
1
1
Out
Out
Out
Out
In
Out
Out
In
Out
Out
In
In
In
In
Out
In
In
In
In
In
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
10
2
2
6
10
6
2
Out
In
Out
Out
Out
Out
In
In
Out
In
In
In
In
Out
Tail
Tail
Tail
Tail
Tail
Tail
Tail
RUNNI
NG
Out
In
Out
Out
Out
Out
In
S/D
TYPE
In
Out
In
In
In
In
Out
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Out
In
Out
Out
Out
Out
In
Out
In
In
In
In
Tail
Tail
Tail
Tail
Tail
Tail
CC03- COLLUMN
SIZE
12
2
8
12
12
2
CC04-COLUMN
12
3
10
14
12
1
2
3
4
5
6
7
8
9
Vapour Outlet
Top Vent
Reflux Nozzle
Reboiler Feed
Reboiler Return
Bottom Outlet
Steam Out Point
2 Nos Feed Inlet
PSVs
3
CC05- COLUMN
14
2
4
14
18
10
2
8
6
CC06- COLUMN
1
Vapour Outlet
2
Top Vent
3
Sour LPG Feed Inlet
4
Lean Amine Feed Inlet
5
Rich Amine outlet
6
Utility Connection
7
PSVs
4
2
4
2
2
2
4
In
out
Tail
Out
In
Out
Out
Out
Out
In
Out
Out
In
Out
In
In
In
In
Out
In
In
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Tail
Out
In
Out
Out
Out
In
Out
In
Out
In
In
In
Out
In
Tail
Tail
Tail
Tail
Tail
Tail
Tail
CHAPTER-22
CONTROL VALVES DATA
TAG NO.
5F
5LV2602
5LV3104
5LV3106
5FV1807
5FV2502
5LV3202
5PV1701
5FV2501
5PV3111
5FV1508
5FV2011
5FV2503
5PV1415
5PV1504A
5PV1504B
5PV1912
SERVICE
BOILER FEED WTR
RICH AMINE TO ARU
STM CONDEN. TO FLASH DRM
LP STM COND. FRM VV-035
HY. NAPHTHA FOR GAS OIL
LPG BOOSTER PMP FLW
LPG TO LPG DRM VV-029
VENT FRM VV-003
LPG SURGE DRM
FO TO VV-026(BPC)
STRIPPING STM TO CC-001 BTM.
HY. NAPHTHA TO KERO R/D
LPG FRM PA-014A/B
FO TO HTR
FG TO FLARE FRM CC-001
FG TO VV-002
LPG PRODUCT R/D
SIZE(in.) RATING
1
300
1
300
1
600
1
150
1.5
300
1.5
300
1.5
300
1.5
300
2
300
2
300
2
300
2
300
2
300
2
300
2
150
2
150
2
300
CV
3.8
7.5
6
7.5
22
7.5
22
12
45.63
60
27
22
22
12
49
49
49
MAKE
MIL
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
ARCA
MOTOYAMA
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
S.No.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
5PV2011
5PV3203
5PV4406
5SDV1406
5SDV1701
5SDV1901
5SDV1902
5SDV1903
5SDV1904
5SDV2001
5SDV2002
5SDV2003
5SDV2201
5SDV2202
5SDV2203
5SDV2601
5SDV2602
5LV1201
5LV3103
5FV1201
5FV1409
5FV2501
5LV1602
5PV3202
5SDV1401
TAG NO.
5LV1202
5TV1702
5FV1401
5FV1402
5FV1403
5FV1404
5FV1804
5FV2206
5FV3102
5HV1701
5PDV1420
5SDV1402
5SDV1601
5SDV2501
5PV1423
5FV1410
5FV1412
5FV1413
5FV1414
5FV1505
22
43
43
49
49
49
49
49
49
49
49
49
49
49
49
49
49
43
150
88
49
49
49
88
108
CV
88
117
140
140
140
140
195
95
115
195
195
195
195
195
444.6
359
359
359
359
250
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
UCH PIG.
MOTOYAMA
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
MAKE
UCH PIG.
ARCA
MIL
MIL
MIL
MIL
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
ARCA
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
63
64
65
66
67
68
69
70
71
72
73
74
75
76
5FV1805
LR TO BL(FPU)
5FV1806
LR TO BL STORAGE
5HV2001
LN+CAUSTIC TO VV-009
5HV2002
LN WTR TO VV-010
5HV2201
KERO+ATF+CAUST. TO VV-013
5HV2202 KERO+ATF+WASH WTR TO VV-014
5SDV1801
LN TO CAUSTIC WASH
5FV1501
TOP CIR. RETURN TO CC-001
5LV1508
KERO STRIPPER FEED
5LV1510
GAS OIL STRIPPER FEED
5SDV1403
FG SUPPLY
5LV1206
CRUDE BOOSTER PMP D/S
5FV1502 ATF/KERO CR RETURNED TO CC-001
5TV1116
EXCH-05-EE-006 A/B BYPASS
6
6
6
6
6
6
6
8
8
8
8
8
10
12
CHAPTER-23
LIST OF INTERLOCKS
300
300
300
300
300
300
300
150
150
150
150
300
300
300
440
440
250
250
359
359
341
475
475
475
680
475
900
1521
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
PIGNONE
UCH PIG.
ARCA
ARCA
Settings of software alarms can be wired to any value if the output from field is coming
through a transmitter, while hardwired alarms originating from switches have more or
less prefixed settings and are normally not varied
AU-5 TRIP SETTINGS (Warning vs: action alarm)
TAG NO
DESCRIPTION
TRIP
RANGE
Alarm
ACTION
VALUE
High 35 Kg/cm2
warning
Level
31 Kg/Cm2
05PSHH1130
P01A/B/Cv.
05PSHH2607
Dis. Pressure
CC-06 Top Pressure 18.9 Kg/cm2
0 25 Kg/cm2
17 Kg/Cm2
05PSL3102
V. High
P45A/B
0 -- 15
8.7 Kg/Cm2
05PSH1810
05FSL1401B
05FSL1402B
05FSL1403B
05FSL1404B
05PSLL1427
Discharge pressure
LR to SLOP
Low Flow in pass 1
Low Flow in pass 2
Low Flow in pass 3
Low Flow in pass 4
Very low pressure
0-215M3/hr
0-215M3/hr
0-215M3/hr
0-215M3/hr
0 10 Kg/cm2
120 M3/hr
120 M3/hr
120 M3/hr
120 M3/hr
4.0 Kg/Cm2
05PSLL1424
in fuel oil
Very low pressure 0.5 Kg/cm2
0 7 Kg/cm2
1.5 Kg/Cm2
05PSL1435
TAG NO
in fuel gas
Fuel gas to FF-01
DESCRIPTION
0 7 Kg/cm2
RANGE
1.5 Kg/Cm2
05FSLL1453
VALUE
Very low flow in 30000NM3/hr
0-164KNM3/hr
32000
05PSHH1452
combustion Air
High pressure in 10 mm WC
NM3/hr
-20,+20mm WC 05 mmWC
A
Furnace Arch
05PSHH1452B V. High pressure in 10 mm WC
-20,+20mm WC 05 mmWC
Furnace Arch
05PSHH1452C V. High pressure in 10 mm WC
-20,+20mm WC 05 mmWC
05SSLL1483
0.8 Kg/cm2
TRIP
Furnace Arch
Very low speed of 200 rpm
0 40 Kg/cm
1000 rpm
700 rpm
05SSLL1484
FD fan A
Very low speed of 200 rpm
05FSL1455
FD fan B
Low flow in FD 15000 NM3/hr 82000 NM3/hr
18000
05FSL1454
Fan A suction
Low flow in FD 15000 NM3/hr 82000 NM3/hr
NM3/hr
18000
05SSLL1485
Fan B suction
Very low speed of 200 rpm
1000rpm
NM3/hr
700 rpm
05TSHH1497
ID
Very high temp in 245 C
0 300 0C
2200C
05FSLL1460
CAPH
V. low flow cir. 60 lts/min
0 120 lts/min
100 lts/min
05FSLL1463
Oil in FD fan A
V. low flow cir. 60 lts/min
0 120 lts/min
100lts/min
05FSLL1457
Oil in FD fan B
V. low flow cir. 60 lts/min
0 120 lts/min
80 lts/min
PSLL-1427
Oil in ID fan A
Fuel Oil Pressure
0 8 Kg/cm2
4.0 Kg/Cm2
BPS -1407
PSLL-1424
Low
Fuel gas Pressure 0.8 Kg/Cm2
0-3
1.5 Kg/Cm2
BPS -1404
LALL-2502
LALL_2605
Low
V-20 level low
C-06 level low
0 -- 100
0 100
30%
22%
2.5 Kg/Cm2
5%
10%
1000 rpm
700 rpm
FAL 1401
05-FC-1402-PASS FLOW LOW
close
IFO Return SDV 1401 close
---FAL1402
BPS 1405
05-FC-1403-PASS FLOW LOW
---FAL1403
05-FC-1404-PASS FLOW LOW
B
---FAL1404
FUEL OIL PRESS LOW
PSLL-14271407
1407
PAHH-1452--- BPS STACK DAMPER OPEN
1410
NOTE: - If stack Damper does not open within 30 sec, Furnace will CUT-OFF.
VERY LOW COMBUSTION AIR FALL-1453 -- BPS FUEL OIL SDV CLOSE
FLOW
1409
STD OPEN.
05-KA-01B CIRCUL OF OIL FSLL-1463 ---BPS- - FD 1B TRIP
FLOW LOW
05-KA-01A CIRCUL.
FLOW LOW
LOW SPEED ID FAN
1417
OF OIL FSLL-1460 -- BPS- -- FD 1A TRIP
1416
BPS 1415
TSHH-1497
OPEN
STACK DAMPER OPEN
NOTE: In case stack damper will not open automatically, ID fan will trip and furnace
J
FLOW LOW
FD FAN 1A SPEED LOW
1418
BPS 1412
FD FAN 1A TRIP
BPS 1413
FD FAN 1B TRIP
HIGH
05-VV-20 LEVEL HIGH
05 PM-01A/B/C TRIP
LAHH-2501
SDV-2501
CLOSE
(LPG
LALL-2502
INLET TO VV-20)
TRIP 05-PM-50A/B (LPG
BOSTER PUMPS)
PAHH-2607
TO C-06)
NOTE: - In case of high pressure in C- 06, FC-2601 will shut off. After attaining normal
condition FC-2601 will work as normal flow controller.
05-CC-06
BOTTOM
LOW
CLOSE SDV 2602
LEVEL LALL-2605
05-PM-45A
If pump (B) is running then selection switch [SS 3110] should be on (A), so that in case
at pressure low [PAL 3102B] pump (A) will start.
NOTE: - OFF push button of stand by pump must not be in lock condition.
CHAPTER-24
SKO/ATF SALT DRYER
outlet at the top. Wet ATF/SKO enters the vessel through a Johnson Screen. A bypass
valve is also provided between inlet & outlet lines to bypass the dryer. A drain line is
provided at the bottom, which is connected with OWS & CBD. Two numbers of PSV are
installed at the top of the vessel, which is release to CBD & OWS. PGs provided at the
inlet and outlet to enable monitoring the pressure drop across the salt bed. As feed enters
at the bottom, the salt absorbs water droplets and its density increases. The dense brine
droplets settle at the bottom, which are drain out easily. Field operator drain out water
twice in a shift.
Design data: Salt to load: 61 Mt.
Inlet moisture: 1300-1500 ppm.
Outlet moisture: <200 ppm
Start up:
Ensure PSV are lined up
Line up outlet valve
Line up inlet valve slowly
Check that vessel top pressure is healthy.
Check that delta P across drier bed is healthy.
Shut down:
Bypass drier
Close inlet valve
Close outlet valve
Check that top pressure is below PSV set value
Drain out residual water at the bottom
Trouble shooting:
High-pressure drop. Johnson screen is chocked
Above calls for unloading of salts and inspection of Johnson screen
Moisture Slippage
Bed channeling due to high flow/partial chockage of Johnson screen.
High moisture in the bed due to unsatisfactory coalescer performance
Insufficient salt in the drier
High pressure in the vessel
Outlet valve partially closed
Rundown line restriction
Correct the problem by opening the valve
CHAPTER-25
HSD COALESCER
HSD COALESCER
PROJECT
INSPECTION :
M/S LRIS
ITEM
DIESEL COALESCER
TAG NO
05-VV-301 / ONE
DESCRIPTION:
MULTITEX DIESEL COALESCER is a compactly made mechanical device
manufactured to a high degree of accuracy. If complete instructions regarding
installation, operation and maintenance of these units are observed carefully, the
coalescer should give trouble free service for a very long period.
THE DIESEL COALESCER in its simplest form, designed and manufactured as per
ASME Section VIII Div. I. It consists of a horizontal shell having dished end at its both
ends and one manhole connection at the middle to facilitate the easy removal of coalescer
and separator elements for cleaning and replacement.
INSTALLATION:
The Coalescer is a precision product and requires extremely careful handling during
transportation, fitting and installation. The coalescer is thus normally despatched in wellpacked installation. It should be unpacked just before installation only and the whole
coalescer may be checked for any damage.
The coalescer should be fitted in position taking care of the orientation of nozzles etc. the
coalescer should be rigidly hooked upto various piping connection and base to avoid any
vibration due to flow. Ensure sufficient empty space on the front of the Manhole opening
to facilitate the element removal without tilting.
IMPORTANT: To avoid damage to the element by any leftover material in the piping
system, up-stream of the element should be flushed thoroughly before the fitment of
coalescer/separator element in the housing.
METHOD OF WORKING
The Diesel Coalescer housing is provided with the inlet and outlet nozzles of suitable
sizes at the front end on dish and at far end on dish of housing respectively. Connection
for safety relief valve has been provided. The water droplets coalesced through the
element gets collected in the horizontal sump provided below main vessel and thereafter
drained through the drain nozzle provided at its bottom.
Horizontal sump with dished end on its both end has been provided. Connections for
Level Transmitter and Level Gauge have also been provided to mount instruments on the
horizontal sump.
The Diesel coalescer consists: 1st stage: Coalescer element to coalesce fine mist of water and to retain dust particle
2nd Stage: Separator element to separate out water droplets (At outlet < 20 ppm)
All the solid particles 10 microns (98%) are trapped in the element. In addition liquid
droplets do not wet the fibers but remain attached to them as beads of liquid. As more
liquid droplets are separated, more they agglomerated and coalesced into large drops due
to their surface attraction to each other. When the coalesced liquid drops attains a
sufficient size from 100 to 200 times their initial size, the force of gravity and frictional
drag of the fluid causes them to drain out the element and they are carried into sump of
the vessel. Due to their size, they are readily stripped out in the horizontal sump through
downcomers.
OPERATION
The coalescer has been thoroughly subjected to inspection and testing at their works
before dispatch, but to check the leak proofness of matching flanged connections, the
coalescer along with the up-stream and downstream piping should be subjected to
hydrostatic testing. After satisfying that there is no leaking joint causing spillage and
wastage of service fluid, the coalescer should be put to the operation as follows :
Supply of stream (at required temperature) should be started before putting the coalescer
into operating
Provide all instrument / isolation valves at per drawing P&ID
Close all valves including inlet, outlet and drain plug. Open air vent.
Open inlet valves slowly so that coalescer is in operation.
Open drain plug and flush out any debris.
Close drain plug.
Allow coalescer to fill in with liquid and when the liquid starts coming out of the
air vent, close the air vent again.
Open coalescer outlet valve.
If there is a by-pass valve, close it slowly.
The fluid enters through the inlet to the coalescer. In the process of passing through the
elements, the entrained particles (Liquid+Dust) are caught through the depth of the
element and clean fluid passes out through the outlet.
MAINTENANCE AND CLEANING / REPLACEMENT
The element of the coalescer supplied has been designed for the following pressure drop:
Pressure Drop (clean): - 0.75 kg/cm2
MULTITEX coalescer will give satisfactory service if it is ensured that the element is
replaced on attaining the maximum permissible pressure drop as indicated above.
CHAPTER-26
CHECKLISTS FOR TASK
OBSERVATION
Centrifugal pump
(B)
Reciprocating pump
(C)
Rotary/Gear pump.
Motor, bearing housing, coupling, pump casing, impeller and shaft, mechanical
seal/gland packing, cooling, flushing and quenching systems.
(A)
Start-Up Procedure
1. COLD PUMP
Check the quality and level of lube oil. Change/top up lube oil, if required.
Open suction valve and fill the casing with liquid. Bleed/Vent if necessary.
Check the discharge pressure and wait till amperage comes down
Check the amperage of the motor. Adjust the load, if required in consultation with
Panel Operator.
Check for any abnormal conditions like vibrations, abnormal sound, leakage, bearing
temperature etc.
2. HOT PUMP
The procedure is same as that for cold pump except for the following additional
points.
(B)
Open warm up b/v for hot pump to keep it hot. Ensure that the pump is not rotating.
(C)
Open the discharge valve gradually. Simultaneously close the discharge valve of
running pump and keep a watch on the discharge pressure gauge/flow-meter.
Motor, gear-box coupling, pump cylinder, piston/plunger, stroke adjuster, safety valves,
suction/discharge valve.
(A)
Start Up Procedure
Check the minimum flow circuit and discharge relief valve in line.
Note: Discharge valve of reciprocating pump should never be closed/throttled while the
motor is running.
(B)
Shut-Down Procedure
(C)
Immediately switch off originally running pump as soon as the pressure starts
increasing.
In this pump rotary vanes/gears/lobes displace liquid from suction to discharge. This is
also a positive displacement pump. It consists of following parts:
Motor, coupling, pump casing, vanes/gears/lobes, safety valve, bearing housing.
Leakage
Pressure gauges
2. ID/FD FANS
FD fan supplies combustion air to the furnace and ID fan maintains the furnace pressure.
Main parts of ID/FD fans are:
Motor, bearing housing, coupling, rotor, impeller, suction vanes, discharge dampers
etc.
Pre-Start-Up Checks
Check the quality and level of lube oil in the bearing housing.
Start-Up Procedure
Slowly open suction vanes of FD and ID fans and adjust air flow/furnace pressure
respectively, as per requirement.
Routine Checks
DESCRIPTION
STATUS
Yes/No
Remarks
DESCRIPTION
Inform panel operator / shift in-charge
Check all casing unwanted holes are plugged
Check suction / discharge are de-blinded and
there is no short / long bolts
Check coupling is properly fixed & covered
Check bearing cooling water are proper
Check motor connection is proper & earthing is
normal
Close casing drain & open pump suction valve 2
STATUS
Yes/No
Remarks
8
9
10
11
12
thread
Slowly open vent & allow air + liquid to vent
Check seal for any leakage
Vent liquid till all water etc are removed
If hot pump, open warm up valve & allow for
proper warming up
Check freeness of shaft.
26.3 TASK:
SR.
NO.
1
2
3
4
5
6
7
8
9
10
11
12
DESCRIPTION
2
3
STATUS
Yes/No
Remarks
26.4 TASK:
SR.
NO.
1
COMMISSIONING OF VESSEL
DESCRIPTION
Ensure cleaning of vessel inside & instrument
tapping before manhole boxing up
Check all blinds are removed as per blind list &
are boxed up with new / proper gasket
Check there is no long / short bolts.
STATUS
Yes/No
Remarks
4
5
6
7
8
9
9
10
11
12
13
14
DESCRIPTION
Check all inlet / outlet blinds are removed. All bull
plugs are fixed
Check all disturbed flanges are boxed up with new
gasket & check for short / long bolting.
Provide air connection at both shell & tube side
vent. Blow air from top & drain out water to OWS.
Provide hose connection at tube & shell side vent.
Fill tube & shell side with flushing oil. Vent air
from both shell & tube high point vent.
After filling is over, hold for hr. Drain out settled
water from both sides.
Refill both side with flushing oil. Close & end
blind the vents.
STATUS
Yes/No
Remarks
15
16
26.6 TASK:
SR.
NO.
1
2
3
4
5
6
7
8
9
10
HEATEXCHANGER DE-COMMISSIONING
DESCRIPTION
De-blind both side CBD & FLO
Inform panel operator
Gradually open hot side by pass valve followed by
cold side bypass valve.
Isolate both side inlet & outlet valves. Drain both
sides to CBD at slow rate. Ensure both CBD lines
are hot during draining.
Check CBD level. Pump out, whenever required.
After sufficient time of draining, charge flushing oil
to both side & push out line content to CBD. Check
drain sample. If it is like HSD, stop flushing.
Check / ensure all 4 valves are holding by opening
drain valve to OWS.
Open vent valves of both side. Provide steam
connection & do steaming for 8 hrs.(Initially drain
into CBD & after that to OWS)
Give clearance for blinding both side inlet & outlet
valves.
After blinding is over H/O exchanger to
maintenance.
STATUS
Yes/No
Remarks
26.7 TASK:
SR.
NO.
1.
2.
3.
4.
DESCRIPTION
Pump out material till pump looses suction
Water hose connection done from drain point and
level build up done up to 100 cms above
hydrocarbon level.
Pumping of hydrocarbon done
5.
6.
7.
8.
9.
10.
11.
12
STATUS
Yes/No
Remarks
13.
14
15
26.8 TASK:
SR.
NO.
1.
DESCRIPTION
Ensure maintenance job is over
2.
4
5
10
STATUS
Yes/No
Remarks
26.9 TASK:
SR.
NO.
1.
2
3
4
5
6
7
DESCRIPTION
STATUS
Yes/No
Remarks
STATUS
Yes/No
Remarks
DESCRIPTION
Ensure instrument maintenance job is over
Close drain valve & plug.
DESCRIPTION
26.12 TASK:
DESCRIPTION
26.13 TASK:
SR.
Remarks
SR.
NO.
1.
STATUS
Yes/No
STATUS
Yes/No
Remarks
DESCRIPTION
STATUS
Remarks
NO.
1.
2
3
4
5
Yes/No
Inform panel operator to open main stack damper
Stop ID fan & allow running furnace in forced draft
mode.
Allow maintenance to open inlet & outlet APH
manholes.
Allow for water wash. Man entry should not be
allowed.
Inform PNE to inform water block for additional
water consumption
DESCRIPTION
Field operator informs the panel operator
before starting the job.
Panel operator constantly observes the vessel
level and takes the level controller in manual
mode, where ever applicable.
Field operator, first fully open U/S drain valve
and then slowly open the D/S valve and start
draining the water at a controlled rate.
Field operator stands continuously (without
leaving the place) and observes the drainage
material.
When LPG fumes start coming out along with
water, immediately close the U/S drain valve
and then D/S drain valve.
Field operator inform panel operator and
leave the place before ensuring that no
material is coming out from drain point
STATUS
Yes/No
Remarks
26.15 TASK:
SR.
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
DESCRIPTION
Check all oil / gas / pilot gas burner valves are
closed.
Check all oil / gas / pilot gas line drain / vent valves
are closed and capped/ end blinded.
Inform panel operator to bypass IFO security &
establish IFO circulation through coil.
Purge furnace box with steam. Allow steam to come
out from stack. Confirm negative draft inside the
furnace.
De-blind fuel gas and pilot gas line.
Inform panel operator to bypass FG & PG inter lock
Open FG/PG SDV from panel/field.
Inform panel to open FG/PG PRC. Check line
pressure from Pressure gauge.
Light up pilot gas burners by electrical igniter &
simultaneously light up main fuel gas burner
Start FD fan for combustion air supply to furnace
Light up other gas burners, as per requirement.
Inform panel operator to maintain atomizing steam
pressure.
Flush oil burner with steam & light up fuel oil burner
as per requirement.
Start ID fan after observing high stack temp.
Check the furnace for any flame impingement on
tubes, excess air, incomplete combustion for all
burners (after closing the stack damper)
STATUS
Yes/No
Remarks
DESCRIPTION
2
3
4
5
6
7
8
9
26.17 TASK:
SR.
NO.
1
2
3
4
5
STATUS
Yes/No
Remarks
DESCRIPTION
Check mechanical / Electrical completion of job.
Check lube oil quality and lube oil level in the lube
oil cup/ bearing. If required, top-up the lube oil.
Check the shaft movement & ensure that it is free
Check coupling / coupling guard
Check / commission bearing CW system
STATUS
Yes/No
Remarks
6
7
8
9
10
11
12
26.18 TASK:
SR.
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
DESCRIPTION
Inform panel operator
Check lube oil quality & lube oil in lube oil cup /
bearing. If required, top-up.
Check the shaft movement & ensure that it is free.
Check coupling / coupling guard
Check / commission bearing CW system
Adjust quenching steam to seal
Check hotness of pump. It should be sufficiently hot.
Isolate warm up valve
Slightly open the discharge valve
Switch on the motor and wait till it attains the full RPM
Gradually open discharge valve.
Check Amp (Load). If the Amperage increased,
gradually close the discharge valve of former
(Running) pump. Repeat this operation till the pump
attains a full load.
Stop the previous pump.
Inform panel operator & confirm required discharge
flow
Check for any abnormality such as Vibration/ abnormal
sound / abnormal temperature etc. Report to shift incharge.
Slowly open warm up valve of the stand by pump,
pinch the cooling water valve to bearings and kept
pump as a stand by
STATUS
Yes/No
Remarks
26.19 TASK:
SR.
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
DESCRIPTION
Inform panel operator
Check lube oil quality & lube oil level in lube oil cup /
bearing. If required, top-up lube oil.
Check the shaft movement & ensure that it is free
Check coupling / coupling guard
Check / commission bearing CW system
Adjust quenching steam to seal
Slightly open discharge valve
Switch on the motor and wait till it attains full RPM
Gradually open discharge valve.
Check up Amp (Load). If the Amps are increased,
gradually close discharge valve of former (Running)
pump. Repeat this operation till the pump attains a full
load.
Stop the previous pump.
Inform panel operator & confirm required discharge
flow is obtained.
Check for any abnormality such as vibration/ abnormal
sound / abnormal temperature etc. Report shift incharge.
STATUS
Yes/No
Remarks
DESCRIPTION
Remarks
26.21 TASK:
SR.
NO.
1
2
STATUS
Yes/No
DESCRIPTION
Inform shift in-charge & ETP
Slowly open tank siphon drain valve. Watch
STATUS
Yes/No
Remarks
3
4
5
6
26.22 TASK:
SR.
NO.
1
2
3
4
5
DESCRIPTION
2
3
4
5
6
7
8
STATUS
Yes/No
Remarks
26.23 TASK:
SR.
NO.
1
DESCRIPTION
Inform S/I to arrange to connect Corrosion
Inhibitor (CI) drum.
Log initial tank dip in register
Top up the vessel with K9 bottom / H. Naphtha up
to required level
Transfer required amount of CI to tank (1:99 ratio)
Circulate solution for 3-4 hr.or Start nitrogen in
Sparger of ahuralan tank for proper mixing of the
solution
Log final tank dip in register
Start / adjust dozing to respective columns top, as
per requirement.
Log CI transferred in chemical register
STATUS
Yes/No
Remarks
26.24 TASK:
SR.
NO.
1
2
3
4
5
6
DESCRIPTION
26.25 TASK:
SR.
NO.
1
Remarks
Inform S/I
Log initial tank dip in register
STATUS
Yes/No
DESCRIPTION
Inform S/I
6
7
STATUS
Yes/No
Remarks
8
9
26.26 TASK:
AMMONICAL CAUSTIC SOLUTION
PREPARATION (NON-CRITICAL)
SR.
NO.
1
DESCRIPTION
STATUS
Yes/No
Remarks
Inform S/I
2
3
4
5
26.27 TASK:
CAUSTIC REPLENISHMENT IN NAPHTHA / LPG
CAUSTIC WASH SYSTEM (NON-CRITICAL)
SR.
NO.
1
2
3
4
5
6
7
8
DESCRIPTION
Inform S/I, panel operator and ETP
Open 2-3 thread the vessel drain to spent caustic
degasser tank (AU5 / GRE)
Inform panel operator to open drain line SDV (In
AU5)
Drain at slow rate. Continuously watch fall of
vessel level. Do not leave the place. Pure LPG /
Naphtha should never be drained to the degasser
vessel
After draining is over, isolate the drain valve &
inform panel operator to close the SDV
Line up caustic receiving to the vessel
Start pump taking suction from fresh caustic tank
& receive up to the required level.
Ensure receiving from DCS panel & from local
STATUS
Yes/No
Remarks
LG
Stop pump & inform panel operator
26.28 TASK:
WATER REPLENISHMENT IN NAPHTHA / LPG CAUSTIc
WASH SYSTEM (NON-CRITICAL)
SR.
NO.
1
2
3
4
5
6
7
8
9
DESCRIPTION
3
4
5
STATUS
Yes/No
Remarks
DESCRIPTION
Remarks
26.29 TASK:
SR.
NO.
1
STATUS
Yes/No
CHAPTER-27
LIST OF GAS/SMOKE DETECTORS
Sl.No.
Tag. No.
1
2
3
4
5
05AI-1101
05AI-1102
05AI-1103
05AI-1104
05AI-1105
Between 05 P005A/B
Between 05 P006A/B
Between 05 P007A/B
Between 05 P0050A/B
Between 05 P0014A/B
Sl.No
1
2
3
4
CCTV Location
At battery limit
Near P01E
On Instrument air vessel
Behind new heat exchanger area
CHAPTER-28
PROCESS FLOW DIAGRMS
CHAPTER-29
FURNACE DECOKING
PROCEDURE
Mechanism of decoking:
The principle mechanism of decoking with steam and air are spalling and burning.
During spalling period steam is admitted to furnace tubes while they are being heated in
the furnace. Comparatively cooler steam cools and the hot outer surface of the tube
induces thermal shock causing coke to crack and break away from the tube surface. The
broken particles are picked up by high velocity steam. As much as 80-90% of the coke
can be removed by spalling alone.
The burning period consists of injecting both steam and air simultaneously while the
furnace is fired at higher temperature. The air ignites and consumes any coke residue
remaining after spalling. Burning effectively removes all coke deposit but requires close
monitoring to prevent overheating of furnace tubes.
Decoking Procedure:
The general description of the procedure in sequence of operation is as follows.
1. After shutting down and steaming out, isolate and blind the heater coils from the
rest of the unit.
2. Reverse the swing elbows at heater inlet and outlet to decoking position.
3. Line up outlet of the coils to the decoking effluent.
4. Light furnaces as per standard procedure. At firebox temperature of 200-250 Deg.
C, introduce steam at about 5.5 T/hr in each of the coils.
5. Increase outlet temperature at the rate of 50 Deg. C/hr.
6. Commission service water quenches to decoking pot to reduce the temperature.
7. For uniform heating of tubes, use alternate burners and preferably utilize fuel gas
firing to obtain good control.
8. Spalling will be done simultaneously in all passes but air will be introduced only
to one pass at a time during burning cycle. During the period when air is
introduced to one coil steam flow to the other passes will continue for
spalling/cooling.
9. When the outlet temperature reaches 475-500 Deg. C, hold at this temperature till
no more coke comes out of the decoking pot outlet.
10. During this spalling period reverse the flow of steam to the coils every 2 hours to
get maximum of coke removed.
11. Through the coil connected to the decoking manifold gradually introduce air in
steps of 25 kg/hr limited to 400 kg/hr. Burning is evident from presence of black
colour in effluent from decoking pot.
12. In tubes having heavy deposition of coke the tube will glow when the coke is
being burnt. The tube skin temperature must never exceed 650 Deg. C.
Reduce/cut the air or increase steam flow to control temperature.
13. Take samples of effluent at points provided at effluent line in decoking pot and
analyze for CO2.
14. Flow should not be reversed during burning.
15. When two consecutive effluent gas analysis show less than 1% CO2, the decoking
is considered to be complete.
16. Repeat this procedure of burning for the other coils.
17. When decoking is complete gradually reduce the furnace firing till the box
temperature comes down to 250-300 Deg. C and put off burners. Get fuel oil and
fuel gas header blinded.
18. Increase steam rate to the coils to remove the residual ash and clean the tubes.
Precautions:
1. Heater temperature must be raised slowly in order to obtain an even distribution
of heat.
2. The damper should be closed as much as possible without creating pressure
condition in the heater. This will aid in obtaining uniform distribution of heat. It
will also prevent overheating of convection tubes.
3. A close watch should be maintained on the firebox, skin and outlet temperature.
This alone should not be guiding factor as thermocouples may be coked up or
damaged during normal run. Visual inspection of the furnace is very important for
judging and controlling decoking.
4. Coils should not be allowed to be overheated. In case cherry red color is observed
on the tubes, which is about 600-650 deg C, cut air immediately or stop air flow
altogether. Also increase steam if required.
NOTE: 1. During the decoking procedure a Decoking register is maintained wherein all the
skin temps, fire box temps, flue gas temps, steam flow rates, air flow rate and
direction are noted on hourly basis.
CHAPTER-30
EQUIPMENT DRAIN LINE
DECHOCKING PROCEDURE
CHAPTER 31
INTER CONNECTION / ROUTINGS
UNDER RUP
provided to
route
routing
light naptha to
ISOM (NHT)
through
and 05PC7216,
HEAVY NAPTHA:
1-One 4 routing provided to DHDT feed tanks through 05FCV6204.
ATF/SKO :
1-To route SKO to DHDT
6line.
GAS OIL:
1-Facility provided to troute Gas Oil through 05FCV 6205 to DHDT
feed tanks 8 line , and to FLO tanks in DHDT area through 8 line
( TK NO-730).
LONG RESIDUE /RCO;
1-Facility
05FCV6203 and
routings.
cold RCO
Annexture-1
Modifications During M&I- 2013
Sub: AU5: Extension of Nitrogen through the plant area upto B/L.
Description of Present System:
Presently nitrogen from DHDS plant comes to AU5 through 2 header.
Nitrogen is mainly consumed in AU5 for the use of bubbling in corrosion
inhibitor solution tanks.
Description of Proposed Change:
A new 2 nitrogen line is extended from the Corrosion inhibitor tank to the unit
B/L. are provided at three locations to use the nitrogen.
Reason(s) of Asking for change:
During shut down and start up period initial and final steaming of different
columns . And vessels nitrogen is required as gas backup for avoiding vacuum.
Nitrogen to
AHURULAN
TANKfor
dilution
OPERATING CONDITIONS
TEMPERATURE:40 DEG.C
PRESSURE
:6.0KG/CM2
SEVICE
:Nitrogen
PRESSURE: 6 KG/cm2
115-120
After modification C
132
PROPOSED:
EXISING :
LEGEND
During the M&I of APR-2013 All the over head condensers of CC-01
(05-EE-016A/B/C/D/E/F) & The over head condensers of CC-05( 05EE-017A/B/C) provided with back flushing system.The main purpose
was to increase the condenser efficiencies as well as to avoid fouling of
condensers
. During the M&I of APR-2013 , A 3 line with isolation valve was made in
the 05-EE-012A/B/C O/L, to route the wash water to 05- EE-013D/E/F
tube side to exchange heat with HEAVY NAPTHA Run down before
entering in to the desalter. By this wash water temp.raises upto 130Cto
140C. After exchanging heat, wash water enters to desalter .Still the system
is not yet commissioned due to non availability of bundles in EE-13D/E/F.
EE-13D/E/F
Installation of MOVs:
MOVs were installed in the following under mentioned locations.The objective is
to ensure the safe isolation during emergencies.
V-3 MOV-1703:
During M&I of APR-2013 MOV-1703 is installed in the V-3 ex .in the
common suction line of 05-P-06A/B/C The purpose was to ensure the
safe& Remote isolation during emergencies,MOV-1703 can be operated
from both field& DCS.
V-4 MOV-1501:
During M&I of APR-2013 MOV-1501 is installed in the common
suction line of P-11A/B for the remote &safe isolation during
emergencies. The MOV is provided with local switch in the field as well
as in the panel
2-nos of stubs with isolation valves provided in the main flare header
system for future hook-up jobs
ANNEXTURE-2
All safety valves must be kept in line with both sides isolation valves car sealed/
wire sealed in wide open condition. If any of the safety valves isolated due to
passing or leak, ensure that it is attended on priority. Every shift to highlight the
isolated safety valve in the logbook.
While handling chemicals, use safety wears. Shift PNE/SPNE should satisfy
themselves regarding the adequacy of protection (use of PVC hand gloves, apron,
face shield, safety goggle, hand gloves or gas mask etc.,) required to carry out the
job.
All drains and vents on lines and equipments handling hydrocarbons and
dangerous chemicals are to be kept properly capped or blinded. Sample points
from where regular samples are collected should be kept hand tight.
Light hydrocarbons are NOT to be drained into OWS as it may create vapor cloud
at other places leading to fire and explosion.
Any line/ equipment which has been under hydrocarbon service, should not be
exposed to atmosphere/ air unless it is made free of hydrocarbons either by
steaming or by water flushing or passivation/washing procedure as applicable to
that equipment.Similarly when any equipment is exposed to air, it is to be made
free of air before putting it into hydrocarbon service.
Wooden planks, bamboos, ropes, oil soaked cotton wastes or any other
combustible material must not be allowed to remain in the unit area specially near
hot equipments as it can result in fire.
First-Aid box must be available in ONE/SPNE office. Ensure refill of the box as
and when required. Record in the logbook for any deficiency.
Constant watch to be kept on firebox conditions. Boxes must be clear and there
should be no flame impingement on the tubes.
Scales/ mucks taken out from equipments under lighter hydrocarbon service (e.g.
fuel gas, LPG and naphtha) are to be kept wet and carefully removed to a safer
place and buried. This is to prevent fire due to presence of pyrophoric iron.
ANNEXTURE-3
HVLR-MONITOR
HIGH VELOCITY LONG RANGE MONITOR
ANNEXTURE-4
SEQ / PN (GR-1)/R/7.5.1 / 4
LABORATORY RESULTS OF AU-5
SEQ / PN (GR-1)/R/7.5.1 / 8
TANK DIPS OF AU-5
SEQ / PN (GR-1)/R/7.5.1 / 12
CHEMICAL CONSUMPTION RECORDS OF AU-5
SEQ / PN (GR-1)/R/7.5.1 / 16
UTILITY CONSUMPTION RECORDS OF AU-5
SEQ / PN (GR-1)/R/7.5.1 / 20
INSTRUCTION REGISTER OF AU-5
SEQ / PN (GR-1)/R/7.5.1 / 22
SEQ / PN (GR-1)/R/7.5.1 / 23
&
SEQ / PN (GR-1)/R/7.5.1 / 24
SEQ / PN (GR-1)/R/7.5.1 / 27
SEQ / PN (GR-1)/R/7.5.1 / 29