PM Assignment 2 Final
PM Assignment 2 Final
[FPT
BOOKS
PROJECT]
PROJECT MANAGEMENT
PUBLISHING
TABLE OF CONTENT
I.
INTRODUCTION........................................................................................2
II.
ANALYZES...............................................................................................2
B.
PROJECT SCHEDULE..........................................................................10
BIBLIOGRAPHY............................................................................................ 21
INTRODUCTION.
With a view to meet the soaring demand for learning and studying of
teachers and students nowaday, FPT publishing department has design a project
to bring out some new kinds of book and the report folow is specific plan.
II.
ANALYZES.
1. TASK 3.1 PROJECT PLAN.
Project objectives
A few years ago, FPT book is one of the market leaders in they field along
with FPT; however they is fast being left behind in the race of Vietnam book
market markets. With a view to creates and offer for customers a quality product
at a reasonable price to estimate to dominate and control market, FPT publishing
department has design a project to bring out some new kinds of book.
Project objectives is creates a form for FPT to focus to removed exceeded
their budgets, or have not properly met customer demand in the past. In detail,
The successful implementation of this project is expected to reduce total cost
overruns and schedule delays by 50%.
Besides, it will help for FPT department establishing program priorities,
allocating resources in a more efficient manner to get better service for Vietnam
customer.
Budget
With the purpose to provide a project cost estimate with all known details to
develop as accurate an estimate as possible, an an estimate is building:
Project cost is 35.305$
FPT education agree to invest for this project about 25,305$
FPT publishing need to borrow from the bank 10,000$ with interest rate is
5% per years (125$/ 3 months).
As a result, total cost of project is: 35.305 + 125 = 35,430$
Deliverables (Scope, specification)
FPT books publishing project is intended to produce 5 college textbooks.
There are many different between these book and other college textbooks
before.
First is about quality, FPT department will creates quality products by
purchase and translate for all international best sellers. Second is about prices,
although the quality is higher, price just is reasonable for Vietnam market.
Constraints
With the puposes to predicted for limitations that the project will be faces;
besides, ensure that all stakeholders understand the limitations within which the
project must be completed, a list of project constraints is constructed:
Funding:
FPT publishing project can being losses when they borrow from the bank
10,000$ with interest rate is 5% per years. Beisdes, the labor costs is too
high. As a result, books price can not be reasonable for customer like what
they had promise.
Solution: FPT publishing department should reduce they labor cost from
10$/staff a day to 5$/staff a day. Besides, get a better interest rate by the
way is borrow from staff family members.
Resources:
FTP publishing will using they department staffs for project who are too busy
with other project. It can be reason to get project schedule delays over 50%.
Solution: FPT publishing department should get a relax working
environment for they staff. Moreover, they need to built more motivation
strategics to keep they staffs in effective at work.
Communication plan
With a viewto Produce a consensus and
Communication plan had been building:
COMMUNICAT
ION
TIME
Week 1
Week 2
Week 3
Week 6,7
MEDIUM
FREQUE
NCE
AUDIENCE
OBJECTIVE OF
COMMUNICATION
Face to
Face
conferenc
e
Face to
Face
Face to
Face
Once
Manager and
accouter
Manager and
accouter
Manager and
accounter
Designer,
translator and
reviewer team
Gain approvals of
budget.
Finalize Project Plan
and Gain Approvals
purchase the
copyright
Review quality of
designs and
translate
Once
Twie
Weekly
Face to
Face
Weekly
Designer
translator and
reviewer team
Week 9
Face to
Face
Once
Marketer and
saler team
Week 12
conferen
ce
Once
All of project
team and
stakeholders
(Client, Project
team, Sponsors)
Expert Judgment: hire expert to calculate the total cost. The advantages
of this method is the accurate of result but it is exorbitant and slower.
Supplier Bid Analysis: Compares bids from different suppliers to arrive at
a cost estimate for the project.
Analogous Estimating: Estimate by data of company records. The
advantages of this method is very fast, less costly, and provides a quick
result but it is less accurate.
Three-Point Estimating: three estimates are determined and then their
average is taken. The advantages of this method is to reduce the
uncertainties and risks in estimating assumptions
With a view to make accuracy for total cost; besides, reduce the
disadvantages and make use for the advantages of each method, FPT publishing
department will using combination of four method are Analogous Estimating,
Parametric Estimating, Supplier Bid Analysis and Expert Judgment:
Parametric Estimating will be using to evaluate and estimate for:
Print cost
Because the price of papers which are using to print are change day by
day. The change of Vietnam dong are responsibility for this fluctuation of
papers price.
Lets analyzis vietnam dong price in 2014 as a telling example:
Though on the data of company records and the synthesize and analyze,
author have a final decided for translate cost is:
550$ for a book translate (over 350 papers)
And 275$ for translate of foundation and document online of
each book.
Supplier Bid Analysis will be using to evaluate and estimate for:
purchase the copyright cost
because the price of copyright can change according to the market
situation and always decided by the saller.
Experts (Expert Judgment) will evaluate and estimate for:
Wee
k1
Week
2
Week
3
Wee
k4
Week
5
Week
Week Week 10 &
Week 7
6
8
9
11
Revie
w
First
Purchas
Marketi qualit
Books
Print
Initiat Plan
e the
ngand
y of
Transl
and
e
project copyrig
Books design
ate
internal
ht
Design s and
transl circulati
on
ate
Week
12
The resources and cost breakdown structure following will give a clearer
view for project staffing and budget (cost):
RESOURCES AND COST BREAKDOWN STRUCTURE
Staffing
WBS
1 Initiate Project
Budget
Plan
Start
Date
Plan
End
Date
du
rat
io
ns
Staf
Labor
cost
(Includi
ng
other
allowan
ce)
Fixed
cost
total
cost
01/01/1
6
01/05/1
6
2 staf
160$
160$
01/01/16
01/01/16
01/02/16
01/01/16
01/04/16
01/01/16
01/02/16
01/02/16
01/03/16
01/05/16
1
2
1
4
2
manager
Manager
manager
Acounter
Manager
20$
40$
20$
40$
40$
2 Plan Project
01/06/1
6
01/12/1
6
6 staf
250$
Develop
Work
Breakdown Structure
Develop Project Staffing
Plan
Develop
Project
Schedule
Develop Project Budget
01/06/16
01/08/16
Manager
60$
60$
01/09/16
01/11/16
manager
60$
60$
01/11/16
01/11/16
manager
20$
20$
01/09/16
01/11/16
30$
30$
Develop Communication
Plan
01/09/16
01/10/16
40$
40$
Develop
Quality
Management Plan
01/09/16
01/09/16
20$
20$
01/12/16
01/12/16
account
er
2
markete
rs
2
reviewer
s
manager
20$
20$
3
Execute
Control Project
01/14/1
6
01/23/1
6
49
32
5,000$
26,875$
31,875$
01/14/16
01/19/16
180$
20,000$/
5 books
20,180$
Hire translaters
01/20/16
01/20/16
Translate books
01/21/16
02/03/16
14
cover
01/21/16
01/27/16
01/28/16
03/02/16
35
01/28/16
02/03/16
01/28/16
02/03/16
Review
quality
content of translates.
02/04/16
02/10/16
Manager
&
account
er
Account
er
4
translate
rs
2
Designer
s
2
Marketer
s
2
Designer
s
4
Translate
rs
2
rewiers
140$
140$
02/11/16
02/11/16
5
salers
50$
50$
Design
page
binding/
and
20$
40$
20$
40$
40$
0
10$
10$
2,250$/5
books
140$
700$
250$
2,250$
140$
500$
140$
1,200$
140$
1,125$/5
books
1,125$
02/12/16
02/12/16
on
02/13/16
02/17/16
02/18/16
02/24/16
Announce availability of
book
02/25/16
03/02/16
02/25/16
03/02/16
03/03/16
03/16/16
03/17/1
6
03/17/16
03/23/16
Internal circulation
FPT student
2
Reviewe
rs
1
saler
20$
2
Designer
s&2
reviewer
s
2
Marketer
s
5
Salers
280$
280$
140$
140$
14
20
Sales
2,800$
03/23/1
6
03/22/16
32 staf
120$
120$
03/23/16
2
Reviewe
rs
All staff
0$
500$
500$
84
32
5530$
27,375$
32,905$
50$
350$
20$
500$/
1,000
books
2,500$/5
,000
books
550$
2,850$
2,800$
500$
620$
120$
The project will be starts in the beginning of january 2016 and ends at the
end of March. In general, this project dendegoes various steps aroud 12 weeks
with the support of human power and also equipment.
The plans of the various tasks of activity are fulfilled in a harmonious way. In
detail, All most task are connect dependence on the other task. Besides, the
publishing plan will be implemented in three phases, each phase and task will be
support from seniors and peers.
With greatly increased workloads, the number of staf and team will be
increasing too. For example, in the first three week just need only the presence
of management and accounting but the folloing weeks witnesses the presence
of all team.
Like quantity of staffs, the duration keeps increasing with the greatly
increased of workloads. The duration are increasing day by day with a highest is
35 days of direct and internet marketing, followed by 14 days of translates and
14 days of books sale.
Interestingly, there are four tasks need to doing at the same time of week six: translate books, Direct marketing and internet marketing
strategies, Design content - chapter layout and translate for foundation
and documentation online.
In comment
The plan was carried out to 50% (6 weeks) of time but the schedule just
make up below 42%. Manager need to put strigger discipline on translate
and design team (specially is translate team) to ensure for project
schedule and also push up the process of implementing the project.
PROJECT CRITICAL PATH
The critical path methods (CPM) is a network diagram of the project
that shows which activities follow which other ones.
The advantages of this method is find out all possible paths of the project.
Critical Path Analysis is a very useful tool for Project Managers. These path may
helps manager to known that what they need to get better control to ensure for
project schedule. And hence, It helps them to focus on the key activities of a
project and how they all fit together (business cases tudies, 2014).
Activity
Description
Week
Initiate project
1
Required
Predeces
sor
(None)
4 and 5
7
A
Purchase the
copyright
Hire translaters
Books Translate
5,6,7,8,9
G
5
A
Plan project
Duration
7
B
14
C
7
C
35
E
7
E
7
D, G
I
7
7
I
8
9
10 and 11
Announce availability of
book
Second Print
Sale on the market
7
J
14
K, F
7
L
D
1
2
1
B
3
I
7
7
J
9
10
G
E
11
12
ABCDHIJKLM: 84 days
ABCEGHIJKLM: 84 days
ABCEFLM: 84 days
This diagram shows the three possible paths of the project are:
ABCDHIJKLM ABCEGHIJKLM and ABCEFLM. General speaking, there are
different between other path in the number of task.
However, interestingly that although experience different tasks with the
number of tasks is also difference, all path have the same length about 84
days.
As concequently, there are three Critical Path (ABCDHIJKLM
ABCEGHIJKLM and ABCEFLM). It means all task of project is stroger
relationship that they always connect and support by other tasks; Besides, it
means scheduce is very closely that staffs need to work continuously in
project.
About solution:
Because there are three Critical Path, FPT have to be done all task on time or
else the whole project will take longer.
About work perfomance, work for a long time will created significant
pressure on staffs. In this case, motivation being the most effective way. With a
view to makes the staff more productive, company must reward the creativity
and energy of them (motivation theories, 2013). Not only ussing extrinsic
motivation theory by reward money, he also building surprise for emotion and
inspiration of employee by self-esteem, self-actualization; Besides, creates
interesting work environments by change culture that reduce code of conduct;
moreover is using non-monetary reward such as encouragement, chance to
promotion to motivate they staffs.
Schedule
Quality
staffs
Determine
the types
Estimate
the
probability
and volume
of change
to project
deliverable
s
Define
change
manageme
nt roles,
responsibili
ties, and
competenci
es
monitoring
, and
reporting
requiremen
ts
and
Define
Probability
change:
90%
of
The responsible:
Both of manager and
they staff who make
the mistake will be
responsible for this
mistake.
The influence:
As the pressures of the
job increased, all team
will be impacted. As a
result, company will be
losing productivity and
effectiveness.
Probability
change:
50%
Because
the
quality of books is
not only decided
by
quality
of
paper but it also
creates by design
and translate of
content Which is
uncontrol factors.
Probability
change:
90%
of
The
responsible:
Designers,
translators
and
manager will be
responsible
for
this mistake.
The influence:
Customers
are
person
who
is
most impact by
this
change.
Followed by FPT
department
because
project
will be fail and
they will losses of
money.
The responsible:
Manager
will
be
responsible for this
mistake because they
are
person
who
decided
for
project
staffs.
The influence:
Productivity
and
effectiveness reduced
is the first impact to
FPT
publishing
department. Besides,
the pressures of the
job
increased
will
impact to all staff. As a
concequence, it can
impact to quality of
books.
The minimize of
quality mean the
develop of project
cost for sale and
marketing.
And
hence,
the
number of sale
of
priority
categories
to be used
Evaluation
of change
impacts
Establish
guidelines
for
integrating
changes
into project
documents
III.
because
of
the
pressures of the job
increased,
company
need to hire more staff
to do the same task.
Thus, project cost will
be reduce.
FPT
publishing
department need to
priorities and focus to
control they number
of staf and project
cost
Chage of quality
has
some
negative impact
on
Customers
profit
and
company
incomes.
CONCLUSION.
Bibliography
Method to estimate cost. (2014) Retrieved 11 25, 2015, from PM Study Circle:
http://pmstudycircle.com/2012/06/4-tools-to-estimate-costs-in-the-projectmanagement
The devaluate of Vietnamese dong. (2015). Retrieved 11 25, 2015, from ANZ
reseach:
http://cafef.vn/tai-chinh-ngan-hang/tien-dong-da-mat-gia-5-trong-nam-nay20150819145339073.chn
http://vietnamnet.vn/vn/kinh-doanh/257647/tien-dong-co-con-matgia-.html
Pros and cons of gantt chart. ( 2013) Retrieved 11 25, 2015 techad visory:
http://www.techadvisory.org/2013/08/pros-and-cons-of-the-gantt-chart/
What is project
projectinsight
management
schedule.
(2014)
Retrieved
11
25,
2015
http://www.projectinsight.net/project-management-basics/projectmanagement-schedule
The advantages and disadvantages of critical path analysis. (2014) Retrieved 11
26, 2015, from business cases tudies:
http://businesscasestudies.co.uk/network-rail/critical-path-analysis-atnetwork-rail/advantages-and-disadvantages-of-critical-pathanalysis.html#axzz3sWNYRvla
Critical path method (CPM). (2014) Retrieved 11 26, 2015, from the constructor:
http://theconstructor.org/constrution/constmanagement/scheduling/advantages-of-critical-path-method-cpm/6873/
Two-factor theory. (n.d.). Retrieved 10 15, 2015, from Two-factor theory:
https://explorable.com/two-factor-theory-of-motivation
Earned value management explained. (2015) Retrieved 11 26, 2015, from
projects mart:
https://www.projectsmart.co.uk/earned-value-management-explained.php
Earn value management quick guide. (2014) ) Retrieved 11 27, 2015, from
tutorial spoint:
http://www.tutorialspoint.com/earn_value_management/evm_quick_guide.
htm
management
plan.
(2015)
management
advisor:
http://www.pma.doit.wisc.edu/plan/3-4/print.htm