Professional Documents
Culture Documents
MR 2015 Case Study Group Project 240752 PDF
MR 2015 Case Study Group Project 240752 PDF
2015)
ORGANIGRAM
MANAGING DIRECTOR
Finance
Director
Logistics
Director
Operations
Manager
Materials
Manager
Marketing
Director
Planning
Manager
Distribution
Manager
Warehouse
Supervisor
Transport
Supervisor
Operatives
Drivers
RL4 M4A:1
Note: Only the Distribution Structure is expanded so use cost centre approach.
SITE DATA
Warehouse and Site Plans are attached in MR Ltd 2.
2. Yard
3. Warehouse
Walked in unchallenged.
Vehicles being off-loaded outside.
"Careless" fork lift driving.
No procedures available for stock location.
No written safety policy displayed.
People standing around talking, some smoking.
Above average absenteeism apparent (upon discussion)
Damaged product lying around.
Congested despatch area.
Morale seems low.
Fork trucks covered with stickers.
Graffiti on walls.
Toilets unclean, dirty sinks, grubby towels.
Lighting good, no space heating system.
RL4 M4A:2
SITE PLAN
NOT TO SCALE
FENCING (Rest of Perimeter Building Walls)
Grassed Area
Grassed
Grassed
Area
PRODUCTION
AREA
IN
Area
OUT
IN
Main
Office
Area
PALLET
STORE
WAREHOUSE
CAR
PARK
VEHICLE
PARK
OUT
FUEL PUMP
VEHICLE
WASH
VEHICLE
ASSEMBLY
OUT
IN
RL4 M4A:3
Grassed Area
WAREHOUSE PLAN
SCALE
<
IN
10MM = 5 METRES
70 metres
(Ground
Level)
Receipt
Area
Building Stanchions/Pillars
>
Fire
Exit
STORAGE
AREA
90
metres
CLEAR HEIGHT
AVAILABLE = 15 METRES
20 PICKING
m AREA
e
t
r
e
s W
DESPATCH
AREA
(BANKED)
CANTEEN
Fire
Exit
Office
VEHICLE ASSEMBLY
Distribution AREA (GROUND LEVEL)
OUT
(RAMPED)
RL4 M4A:4
Receive
From on site production by production trailer shuttle system (Flat 40 foot trailers).
Product palletised, 1 Line per pallet.
Pallets size 1.0 x 1.2 metre.
Offloaded by CBT from ground level.
Storage
Random locations.
Blockstacked on pallets, two high maximum, otherwise product "crushes".
Picking
Manual onto pallets, placed on Hand Pallet Truck (HPT).
RL4 M4A:5
Delivery
0900 - 1500 hours, Monday to Saturday, 51 weeks per annum.
Daily deliveries.
Each vehicle has a drivers assistant.
Unloading at Customers
Pallets removed by HPT (supplied by customer).
Cartons hand stacked onto conveyor belts by driver and his assistant.
Empty pallets are returned to vehicle.
Customer, tally counts/checks cartons only.
Identify what types of losses you believe could exist, where, and what causes
you to believe this?
How might MR Ltd minimise losses.
What immediate improvements would you suggest? (Note: the site cannot be
extended)
RL4 M4A:6
PRODUCT DATA
You are given the following data in addition to that already provided.
PRODUCT DATA
Product is dry, kept at ambient temperature.
Number of Lines
350
13 Kg
24
Pallet dimensions
Monday to Saturday, 0800 to 1800 hours, 51 weeks per annum (closed 1 week for
holiday).
Receive
From on site production by production trailer shuttle system (Flat 40 foot trailers).
Storage
Random locations.
Blockstacked on pallets.
By CBT.
RL4 M4A:7
Picking
By HPT.
By CBT.
Delivery
Daily deliveries.
Unloading at Customer
Cartons hand stacked onto conveyor belts by driver and his assistant.
RL4 M4A:8
RESOURCE DATA
(People and Equipment)
Warehouse
Pickers
CBT drivers
CBT equipment
HPT equipment
6
6
6
6
Transport
Drivers
Driver's Assistants
Vehicle numbers
GVW - Rigid
payload - Tonnes
capacity - Pallets
60
60
60
7.5 tonne
3.5
10
Administration
Note:
Order clerks
Transport clerks
Supervisors
Manager (Distribution)
2
2
2
1
COST DATA
All per annum (unless otherwise stated).
Manpower
Based on 40 hour week, 52 weeks with 4 weeks holiday.
Warehouseman
Vehicle Driver upto 7.5 tonne GVW
over 7.5 tonne GVW
Supervisor
Admin. Assistant
Vehicle Assistant
$30000
$30000
$35000
$40000
$28000
$28000
(Note. Overtime is paid pro rata at time and half. eg, if work 60 hours, are paid 40
hours basic and the overtime of 20 hours, is paid as 30 hours).
RL4 M4A:9
Warehouse Equipment/unit/yr
HPT
CBT
$150
$14500
Transport Equipment
Fixed Cost, excluding people
Variable cost, per KM
$25000
$0.30
RL4 M4A:10
CUSTOMER DATA
Two major JIT manufacturers are supplied.
Throughputs are shown on the volume data sheet.
The percentage split of volume is:Wellington Customer
70%
30%
Customer Service
Customer Orders
Delivered By.
1500 hours Tuesday
to
1500 hours Saturday
1500 hours Monday
VOLUME DATA
In Cartons
MONTH
RECEIVE
DELIVER
STOCK
JANUARY
FEBRUARY
MARCH
APRIL
MAY
JUNE
JULY
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
75000
75000
75000
75000
75000
75000
75000
75000
75000
75000
75000
75000
900000
90000
108000
162000
99000
72000
63000
54000
36000
45000
54000
63000
54000
900000
170520
137520
50520
26520
29520
41520
62520
101520
131520
152520
164520
185520
RL4 M4A:11
What key cost elements within MR Ltd. Your answer should include the elements and
their values.
What is your possible warehouse capacity? (Options must be justified and costed)
NOTE: You should use your professional judgement to decide what areas you are going to cost
and at what depth! Show justification for your decision. Note however, that you will use these
costs later in the course to compare them against the costs you calculate after recommending
improvements.
NOTE: Vehicles currently average three deliveries per week and 45,000 kms per year,
each vehicle.
Select and define the areas within MR Ltd where you believe that method study is a
suitable means of improving productivity.
Performance data
The Supervisors believe the following currently apply:
1.
Warehouse CBT can move about 15 pallets per hour per operation.
2.
Each Picker can manage about 150 cartons per hour (which includes moving picked
pallet to despatch area).
3.
Transport Vehicles currently average 3 deliveries per week, and around 45000
miles per annum. (The Transport Supervisor is aware vehicles are not always fully
loaded, but says "customer service is King around here").
RL4 M4A:12
NOTE: You should be looking at those areas where resources of people, space and equipment
are used. Do not try to use standards which can be calculated from formal methods of
investigation, - just use the historical standards.
Variable Times
30.5m/min
122m/min
91.5m/min
61m/min
- Loading/Unloading
Fixed Time
10 mins per stop
(eg, stopping vehicle, opening doors, documentation, etc.)
And, to cover physical unloading per piece/package, add the following:Fixed/Variable Times, as warehouse performance data.
Travel Times
Motorway
80 kph
Class 2 Roads
75 kph
Urban Roads
40 kph.
Distance. (Crow Fly Factor) Straight line plus 20 per cent.
RL4 M4A:13
IMPROVEMENT DATA
You may find the following data useful for improvement purposes.
Warehouse
Capital Cost
CBT LPG
CBT Electric
$32000
$25000
$16000
$12000
$44000
$16000
$80000
$40000
$24000
$18000
Conveyor
Racking - Drive In
Racking - Flow
Shortside
Longside
3.3m
2.5m
1.5m
3.0m
2.13m
1.32m
CBT
NART
TT/MLPT
RL4 M4A:14
Building changes
CAPITAL COST
FIRE EXIT
$2000
GOODS DOOR
$20000
$2000
OPEN CANOPY
SPACE HEATING
YARD EXTENSION
Transport
TYPE
TONNES
3.5T GVW
RIGID
7.5T GVW
RIGID
17T GVW
RIGID
24T GVW
RIGID
32T GVW
ARTIC/12M TRAILER
35T GVW
Drawbar/2 bodies
38T GVW
ARTIC/12M TRAILER
12 METRE TRAILER
DRAWBAR DEMOUNT
BODY
DRAWBAR TRAILER
CAPACITY
VARIABLE
COST PER
KM
PALLETS
1.75
$45000
$5000
$1.00
3.5
10
$56000
$12000
$1.00
11
14
$120000
$40000
$1.65
16
14
$240000
$88000
$1.95
19
24
$480000
$140000
$2.70
21
28
$550000
$150000
$3.00
24
-
24
24
14
$490000
$45000
$25000
$140000
$4500
$2500
$2.30
$0.50
$0.30
$15000
$2500
$0.24
RL4 M4A:15
Carry out work measurement/time study in those areas of MR Ltd that you feel are
appropriate.
Using the cost elements given above and apply these to improve ALL operations to
produce better operational costings.
Note: Your answer should show storage costs, warehouse handling costs for each part
of the overall operation, and transport costs for each customer.
Draw up a budget for MR Ltd for the next year based on the current cost elements but
applied to the improved operation.
How you present the budget is up to you but it should identify the individual costs for
each part of the business. (Note: You do not need to consider income, as this is not
available to you).
2.
3.
Volumes
Current volumes are to double.
Product
Introduce to same customer base the following:
RL4 M4A:16
Pallets
Possible changes to Euro-pallets (1.2 x 0.8 metres).
[Recall the Managing Director is looking for your outline recommendations only on the
above].
RL4 M4A:17