Proedure For Plastering
Proedure For Plastering
Client
Contractor
Procedure No.
INDCON-PJPL-STN-PNP-CIVIL-09
20.08.07
Anuj
Vijay
GSB
REV. NO.
DATE
DRN. BY
CHKD.BY
APPV.BY
Approved (IOCL)
Page 2 of 4
CONTACT NO: -
Rough cast plastering:Rough cast plastering shall consist of two layers, under layer 12 mm thick
cement plaster 1:4 and a top layer of 10 mm thick cement plaster 1:3 mixed with
10% finally grounded hydrated lime by volume of cement. Top layer shall be
applied a day to two after the under layer has taken initial set. The later shall not
be allowed to dry out, before the top layer is laid down.
The mortar shall be sufficiently plastic so that the mix of sand and gravel gets
well pitched in to the plastered surface. In order to make the plaster base plastic,
about 10% of finally grounded hydrated lime by volume of cement shall be added
to mortar to ensure even thickness and a true surface, plaster about 15cms x
15cms shall be first applied horizontally and vertically, at more than 2.0 meters
intervals.
Rough cast finish:Rough cast mixture shall consist of sand and gravel or crushed stone from 6 mm
to 12.5 mm nominal size. The mix shall be wetted and shall be dashed on the
plaster base in plastic state by hand scoop so that the mix gets well pitched in to
the plaster base. The mix shall again be dashed over the vacant spaces, if any
so that the finished surface represents a homogeneous surface of sand mixed
with gravel.
Page 3 of 4
Curing for plastered surface shall be started 24 hours after finishing the plaster
and be kept wet for a period of 7 days.
Plastering at junction of masonry / RCC:All junction of masonry wall with R.C.C structures e.g. column, beam etc. shall be
plastered after providing and fixing of approved G.I. chicken mesh 250 mm vide
centrally over the length of junction either vertically or horizontally.
Page 4 of 4
Activity Description
Layout, lines and levels
Soring and shuttering
Quality of coarse aggregate.
Quality of construction water.
Quality of cement & other ingredients
( if any).
Check for obstacles encountered such
as electrical, conduits, pipes etc.
Preparing concrete mix as designed
and adding water proofing compounds
wherever required.
Curing.
6.
7.
8.
W
RM
R
Inspection by
INDCON
Verification by
IOCL
W
W
W
W
W
R
RM
RM
RM
RM
Records to be
maintained
by INDCON
Register
Register
Lab test report
Lab test report
MTC
RM
-do-
RM
-do-
RM
-do-
- Witness
- Random Check
- Review Documents
07.09.07
Rev.
Date
Prepared by
(INDCON)
Checked by
(INDCON)
Approved
by
(INDCON)
Reviewed &
approved by IOCL