The document summarizes the design of the two 650-kV substations for Project EHV, a prototype extra-high voltage transmission system operating initially at 500 kV and later at 700 kV. The substations were designed to test equipment for future 460-750 kV systems. Rigid aluminum bus was used for the North Substation, while strain bus made of bundled conductors was used for the South Substation. Special instrumentation was included to measure corona and radio noise to evaluate the performance of the high voltage equipment. The substation designs were representative of what utilities may use for future extra-high voltage systems, while meeting Project EHV's additional requirements for data collection.
The document summarizes the design of the two 650-kV substations for Project EHV, a prototype extra-high voltage transmission system operating initially at 500 kV and later at 700 kV. The substations were designed to test equipment for future 460-750 kV systems. Rigid aluminum bus was used for the North Substation, while strain bus made of bundled conductors was used for the South Substation. Special instrumentation was included to measure corona and radio noise to evaluate the performance of the high voltage equipment. The substation designs were representative of what utilities may use for future extra-high voltage systems, while meeting Project EHV's additional requirements for data collection.
The document summarizes the design of the two 650-kV substations for Project EHV, a prototype extra-high voltage transmission system operating initially at 500 kV and later at 700 kV. The substations were designed to test equipment for future 460-750 kV systems. Rigid aluminum bus was used for the North Substation, while strain bus made of bundled conductors was used for the South Substation. Special instrumentation was included to measure corona and radio noise to evaluate the performance of the high voltage equipment. The substation designs were representative of what utilities may use for future extra-high voltage systems, while meeting Project EHV's additional requirements for data collection.
(called "Project EHV" for short) comprises a complete prototype transmission system which operates at 500 kv, and will operate later at 700 kv (750 kv maximum). It was announced 1 in 1958, but technical work and acquirement of the right of way had been proceeding since early 1957. The cost of the entire project is estimated at $7,500,000 and is being contributed by 11 co-operating manufacturers and one utility. Construction work on the site was started in May 1959 and energization at 500 kv of the North Substation and adjacent section of the line took place in December 1960. In 1962 the voltage will be raised to 700 kv. Plans call for testing until the summer of 1963. In the past, ehv research installations 2 have been designed as open-ended test lines with limited and nonrepresentative terminal equipment. Usually, no effort was made to design the system for a given voltage. Instead, a broad range of voltages and system parameters was investigated. The design philosophy of Project EHV is more advanced, similar to that used by utilities in establishing a new system. On the basis of forecasts of development of ehv transmission in the United States and Canada, 2 it was decided to design all Project EHV line configurations specifically for 460 and 650 kv, and both substations for 650 kv. A voltage of this magnitude appears to be adequate for fulfilling transmission requirements in North America for the next 20 years. Project EHV includes prototypes of apparatus to be used on future ehv systems, from 460 to 750 kv. For instance, the capacity of the two 650-kv autotransformers was set at 40,000 kva, because calculations showed that this was the smallest size of a forced-oil-cooled unit, which would have basically the same construction and geometry of larger units of the same basic impulse insulation level (BIL). Actual service experience will be obtained for several years under normal weather and operating conditions. As mentioned, the Project EHV line was designed for two rated voltages, 460 and 650 kv. Conductors, hardware, and line insulation will be changed when the operating voltage is raised. The two terminal substations, however, are designed only for the 650-kv level, with the exception of the lightning arresters, which will be rated 360 kv during operation of the system at the 460Digest of paper 61-155, recommended by the AIEE Substations Committee and approved by the AIEE Technical Operations Department for presentation at the AIEE Winter General Meeting, New York, N. Y., Jan. 29-Feb. 3, 1961. Published in AIEE Power Apparatus and Systems, Aug. 1961. P. A. Abetti is with the General Electric Company, Pittsfield, Mass.; R. E. Larson is with the Aluminum Company of America, Pittsburgh, Pa.; A. H. Powell is with the General Electric Company, Philadelphia, Pa.; and M. D. Robinson is with the Stone and Webster Engineering Corporation, Boston, Mass.
676
Abetti
A. H. POWELL MEMBER AIEE
M. D. ROBINSON
ASSOCIATE MEMBER AIEE
kv level. It appears that the same design principles and
structures will be used for apparatus and substations in the 460- to 750-kv range. Consequently, operation at the highest voltage is sufficient to demonstrate the correctness of the design and its economics and reliability. Furthermore, two 460-kv substations have been built by the Pennsylvania Electric Company for their Claysax Project, and operating experience will be available from these installations. The following design criteria for the two Project EHV 650-kv substations are fundamentally the same as would be used by a utility, but are modified in certain aspects by the special instrumentation requirements: 1. The apparatus and structures are representative of future designs for 460 kv and higher voltages. At present, both rigid and strain busses are being used for 345-kv substations, and it appears that both may be used at higher voltages. Consequently, rigid aluminum bus has been used for the North Substation, and strain bus, consisting of bundled ACSR conductors, for the South Substation. 2. Radio interference from the stations is negligible compared to that generated by the line itself. This requirement is definitely more stringent than that which would be used by a utility. Conductor-generated corona and radio noise are at present important factors affecting the design of ehv lines, and therefore they will be measured by means of 23 radio-noise meters and a special device which will separate the corona pulses, according to their magnitude, and count them. For theoretical and practical reasons, it is desired that most of these pulses originate on the line and not in the station. Television interference from the station is negligible, since this usually results from hardware in poor condition or from slack insulator strings. 3. Station insulation requirements are established by lighting and switching surges, rather than by 60-cycle voltages or overvoltages, because there are no insulator pollution problems in the Berkshires. However greater distances had to be used at times between phases than would be necessitated by insulation requirements, because special instrumentation for corona loss measurements needed to be accommodated. 4. Mechanical design criteria require that the structures withstand the severe weather conditions of the area, but that they be easy to erect, despite their large dimensions. Maintenance should also be kept to a minimum. REFERENCES 1. Project EHV, P. A. Abetti. Electrical Engineering, vol. 78, Aug. 1958, pp. 669-74. 2. Progress in Extra-High-Voltage Power Transmission, P. A. Abetti, S. B. Crary. AIEE Transactions, pt. I l l , (Power Apparatus and Systems), vol. 78, J u n e 1959, pp. 357-71.