Professional Documents
Culture Documents
Theory of Constraints: Conflict Cloud
Theory of Constraints: Conflict Cloud
Theory of Constraints: Conflict Cloud
Prepared By:
Manoranjan Jha (G15031)
Ravikant Kumar (G15044)
Ritesh Pandey (G15047)
Group: 6
Background:
Many Urban infrastructure projects in Bihar were executed by a government agency named Bihar Urban Infrastructure Development Corporation. Projects
were mostly Road, Water and Waste Water. M/s Realization Technology India Pvt Ltd was assigned as a Project management Consultant for a portfolio of
15 projects of worth 1600 Cr. They were only working to arrest possible delays in projects.
For supervision, BUIDCo had its own hierarchy of engineers. But, they were grossly over worked.
Projects were executed by big construction companies of India like Gammon India, IVRCL, Ramky Infra etc. For the first time in Bihar such huge investments
were made in these sectors.
QA & QC agencies like STUP, TCE, IPE Global were hired for quality assurance and control. Project Managers of these agencies were the signing authority for
contractors work approval and payment.
Hence, in the current scenario the responsibility was not clear on part of client and quality consultant.
Work Scenario:
Normal flaw in project execution is, Resources working in high WIP environment leading to high cycle time and project delays. After the arrival of
Realization Technology some good practices were started at site, like full kitting (Task Preparation), WIP reduction (Finding priorities and bottlenecks).
Project was reviewed as per TOC (CCPM) i.e. completion of critical chain vs consumption of project buffer.
Bigger issues were escalated to the (clients) higher management for solution.
UDEs:
1) Slow decision making by the client
2) Nebulous responsibility mapping
3) Project was reviewed by the client using CCPM guidelines whereas review of clients performance was done by UDHD Secretary and Urban
Development Ministry in terms of disbursement of funds
4) Agency which made initial designs are not present in the current scenario
5) Too bureaucratic process
6) Time lines of projects were driven by political events e.g. elections
7) Other government agencies were reluctant to offer help
Group: 6
Projects are
gefng delayed
QA-QC consultant
wants to follow
their own
contract
Slow decision
making form
client
Reluctant to take
decision on their
own
Group: 6
Want collechve
decision making
by all parhes
Inihal designs
(DPR) were made
by dierent party
3
Fast decision
making by clients
officials
Redefining
Responsibilities
in terms of
disbursement
Successful
completion of
projects
Review by
disbursement of
money
Conflict
Collective decision
making by client
and QA & QC
Responsibilities
as per the agreed
contract
Review as per
physical
completion
Group: 6