Professional Documents
Culture Documents
05 Cost Planning
05 Cost Planning
Generally
The cost estimate has a single total value and may have identifiable component values
Substructure
Superstructure
COST
ESTIMATE
Finishes
Building
Services
Estimate accuracy is a measure of how closely the estimate is able to predict the actual
expenditures for the project (This can only be known after the project is completed)
Estimate accuracy is traditionally represented as a +/- percentage range around the point
estimate; with a stated confidence level that the actual cost outcome will fall within this range
An example: for a definitive estimate might be that the estimate has a -5/+10% range of accuracy with a 90%
confidence that the final value will fall in that range
The accuracy of an estimate is measured by how well the estimated cost compares to the actual
total installed cost
For the same project, the range of uncertainty about the total estimate decreases, as illustrated
in the cone of uncertainty diagram
A good cost estimatewhile taking the form of a single numberis supported by detailed
documentation that describes how it was derived and how the expected funding will be spent in
order to achieve a given objective
This documentation is often titled Basis of Estimate (or BOE). Additional documentation may
accompany the estimate, including quantity takeoff documentation and supporting calculations,
quotes, etc.
Cost Contingency
Keywords: UNCERTAINITY
The estimated cost of events those are likely to occur of which the occurrence or the exact cost
is NOT definitely known at the moment of estimate preparation.
Another definition:
An amount added to an estimate to allow for items, conditions, or events for which the state,
occurrence, or effect is uncertain and incurs additional costs
Typically estimated using statistical analysis or judgment based on past asset or project
experience
Additional classification of Contingency depending on the current stage of the project life cycle
Contingency exclusions
Major scope changes (such as changes in end product specification, capacities, building sizes, and
location of the asset or project)
Management reserves
Cost Contingencycontd
Known-unknowns include (but are not limited to);
Expert judgment
Simulation analysis (primarily risk analysis judgment incorporated in a simulation such as MonteCarlo)
The selected method should comply with the first principles of risk management. I.e. the method must
start with risk identification, and only then are the probable cost of those risks quantified. In best
practice, the quantification will be probabilistic in nature (Monte-Carlo is a common method used for
quantification).
Contingency is included in budgets as a control account. As risks occur on a project, and money is
needed to pay for them, the contingency can be transferred to the appropriate accounts that need
it. The transfer and its reason is recorded. In risk management, risks are continually reassessed
during the course of a project, as are the needs for cost contingency
11.