Professional Documents
Culture Documents
Pipeline Repair
Pipeline Repair
ABSTRACT
INTRODUCTION
As pipe-laying operation moved toward deep waters a need was
recognized for diverless repair systems, in the event severe damages to
the pipelines. Since the early eighties several Oil Companies started to
develop diverless pipeline repair systems, pursuing different
philosophies both for the connection technology and for the system
installation. SNAM and Sonsub joined their skills, in pipeline
technology and in subsea intervention works respectively, to develop a
diverless repair system, which was named ARCOS. This system has
been built and tested in sea trials and now represents the system to be
used in the event of an emergency for both the existing 20" and 26"
TRANsMED pipelines. The entire ARCOS system is housed and
SYSTEM DESCRIPTION
The ARCOS repair system to perform the repair task includes the
following equipment (see figure 1):
1) the Connection System, that is composed of:
27
01-JAN-01
D. Lazzarin
Page 1 of 5
ARCOS
Repair System
L
Connection System
to re-establish pipe functionality
Auxiliary Modules
to perform auxiliary operation
Installation Modules
to install the Connection System
End Connectors/Forging
Tool Installation Module -MICF-
H-Frames
to lift the pipe at the sea bottom
Cutting Tool
to cut the damaged pipe section
Docking Modules
to aid the SP installation
Lift Clam p
I
End Connectors -ECsto provide connection flanges
1
Spool Piece -SPto be istalled between ECs
and re-establish pipe continuity
Forging Tool
to swage the pipe against the ECs
28
01-JAN-01
D. Lazzarin
Page 2 of 5
- , .
<-.
pipe
%-
7~T
5_ 2Z<
i
,__
. . . .
__
~. . . . . . . . . .
,! ~
/--.
_q : : e 2
232:~.S:.
es
.c .....
F->
h. . . . .
:7:~:5:
:~c
,
..
'
'i
:T....... iT~ ~
..
....
/
{2 r21: ::
.
~ . ~ , . . : . ,.~ ~ . . ~ . ~ ? ~ . . . ~ , ~ - ~ ; a . . : ,
.~:~.~.-.
,~.a~.~'~a~,
,.
~i
...........
----~i~ ~ .......................................7~-. . . . . .
~-~a':~,~;~:..'.~:~.<,'.<:~:;::
..~:~:;:.::~`.:;~:..`~:~a:::~:`~::~:.::~*:;.:`~.:::.~:~:~:`~:.~.-:~:~:.~
I I?--2/> . . . .
>~ ,,:s
.__z
//
/
/"
/
//
ifp!p/
,,
/'
'.o
f!snce
::
End
"t: :"
the
~F
~e
cc,-pi-~:J
:c::,
/'
7cint
Connector
INSTALLATION MODULES
M I C F MODULE
M I S P MODULE
29
01-JAN-01
D. Lazzarin
Page 3 of 5
--J
and the Spool Piece during the final positioning and engagement phase
with the End Connectors. This is achieved by using two centering pins
that are mated with their receptacle on the Docking Modules' arms
obtaining the correct alignment of the Spool Piece with the Docking
Modules and therefore with the two pipe ends (see picture 7)
The buoyancy unit provides positive net buoyancy (about 10 kN) to the
Spool Piece during the final installation phase and consists of two tanks
complete with a lifting arrangement to lift the whole Spool Piece and
MISP assembly. Each tank is connected with a release mechanism to
allow the recovery of the buoyancy tanks after the SP installation.
The Base Frame winch, which is hydraulically driven, has the purpose
to control the Spool Piece height from the sea bottom when the tanks
are floated. This happens before the Spool Piece is positioned between
the two End Connectors, when the base winch positions the Spool
Piece at least at 8-10m from the sea bed to be ready for installation.
{-'2
.--'x.~ . . . . .
_
.~
~.
-.~
;-.
!.'?.:;
---
, i~
:!'i
k
-"--LU <
:
< Buoyancy
%
tanks
il
!I {
-~>;~
-<-;Q7
X.
--
7 - - ~
....
7-
,,
,,
~...,.-
.~
."
DOCKING MODULES
The Docking Modules (see picture 8), two identical systems, are to
perform the Spool Piece alignment with the End Connectors and the
Spool Piece installation. They are clamped on both the pipe ends
behind the End Connectors, they are secured to the Spool Piece through
wires that pull down the Spool Piece until to engage the receptacles on
the Docking Module. Then the two Docking Modules can extend the
Spool Piece up to mate the two Spool Piece ball joints with the two End
Connectors. This extension is achieved by using a combination of a
fixed and a movable clamp that allow the modules to travel along the
two pipe sections. Docking Modules are launched and recovered by
using dedicate deployment frames and are controlled and installed by
the ROV.
IHP U
30
01-JAN-01
D. Lazzarin
2Z 7 T - 2 2 "
~.2~'~t~'2:
Page 4 of 5
'.3:
AUXILIARY SYSTEMS
pulled out from a hydraulically driven winch placed on one unit, linked
to the other unit and kept in tension so that the distance and angles can
be read. One of the two unit is also used for the installation of the two
markers, that are placed on pipe ends to provide a mechanical ledge to
the End Connectors insertion.
The H-Frames, see picture 9, two identical modules, are to lift and
move the pipeline laid on the seabed before and after it is cut. The
system, deployed by a vessel crane, is controlled and hydraulically
operated by the ROV. Each H-Frame consists of the main structure, the
footings and the clamp. The main structure is composed of two legs,
which are connected together by the sliding crossbeam structure. Lead
screws are used to lift the crossbeam structure and to move sideways,
along the crossbeam, the pipe clamp. At the bottom end of each leg are
connect two mudmats through spherical joints and a vertical motion
capability is provided to allow adjusting as required by the sea bed
slopes. The clamp consists of two clamping jaws shaped to
accommodate any pipe rotation during its lifting.
The ROV. through the docking panel, provides hydraulic power and
acquires the sensors to monitor the relevant operating parameters like
clamp position and vertical load.
Picture 9, H-Frame
CUITING TOOL
The Cutting Tool is required to cut the damaged pipe section. The
cutting element is a diamond-coated wire formed into a closed loop.
This is kept under tension and rotates by two free pulleys and one
traction pulley driven by a hydraulic motor. The module is fitted with
the passive stab plate and the docking latch receptacles to provide a
stable connection with the ROV, which is to install the module pipe.
See picture 10.
TA UT WIRE MODULES
The Taut Wire Modules are used to measure the distance between the
two pipe ends and the angles in the horizontal and vertical planes. The
system includes two similar units to be deployed to the seabed together
with their storage module and then handled and operated by ROVs. The
two units are inserted and clamped each into each pipe end. A wire is
31
01-JAN-01
D. Lazzarin
Page 5 of 5