Professional Documents
Culture Documents
Sample Case Studies
Sample Case Studies
Sample Case Studies
STATS Group successfully completes subsea oil line isolation in North Sea
STATS Group were contracted by Nexen UK Limited to
supply high pressure isolation plugs to provide a double
block and bleed isolation barrier for the safe tie-in of a
replacement section of the main 24-inch oil export line
from the Scott Platform. Located in the Central North
Sea approximately 155km northeast of Aberdeen, the
isolation needed to be completed without having to deoil the entire 80km pipeline.
To facilitate the double block isolation and enable a
reinstatement leak test in accordance with the pipeline
design code, STATS provided two remotely controlled
Tecno Plugs. The first Tecno Plug provided a proven
double block isolation from pipeline pressure. The
second Tecno Plug provided a local leak test boundary.
Using two plugs in this manner maintains a safe
isolation until the leak test is completed and prevents
pressurising the entire pipeline up to leak test pressure.
An expert isolation committee of a subsea engineering
and construction company, which included their global
technical risk experts, assessed the suitability of the
high pressure remote isolation plug as a double block
barrier for diver breaking containment activities. The
critical operational areas of concern were scrutinised and
Double block and bleed isolation barrier provides safe tie-in of replacement pipeline section
Tecno Plug isolates gas export pipeline to facilitate subsea metrology spool piece installation
A four module 16 Remote Tecno Plug was pigged by STATS personnel from the K5-A platform to the subsea
isolation position 300 metres from the platform. The Tecno Plug was tracked and its location confirmed using STATS
through-wall communication system via an extremely low frequency. This was carried out by a second team of STATS
technicians on-board the EDT Protea dive support vessel.
When set, the Tecno Plug isolated a pressure of 70 bar. On completion, primary and secondary seal tests were
carried out using full isolation pressure. The pressure between the primary and secondary seals was monitored
throughout the isolation, ensuring safety critical double block isolation. With the fully proven double block pipeline
isolation in place, the section of flexible riser was safely removed, allowing a new subsea valve to be added to the
pipeline behind the isolating Tecno Plug.
Divers then attached a temporary subsea receiver to the valve which allowed the Tecno Plug to be remotely unset
and reverse pigged into the receiver. The subsea valve was then closed and tested before the temporary receiver
was removed and retrieved to the Protea DVS, complete with the Tecno Plug. The new subsea valve then provided
isolation while the permanent pipeline was successfully tied-in and re-commissioned.
The project faced many challenges - the Tecno Plug had to allow bi-directional pigging through various 5D bends
and accommodate the layered helical winding present on the internal surface of a flexible pipeline. All these factors
were considered when designing and engineering the Tecno Plug.
STATS Groups subsea business stream manager, Dale Millward, said: This fast-track project was engineered, risk
assessed, assembled and mobilised within a six week window. The successful delivery demonstrates STATS ability to
provide safety critical isolation services that enabled urgent maintenance activity to be completed, within schedule
and with minimal production outage.
Tecno Plug is a Trade Mark of STATS (UK) Ltd
14 Remote Tecno Plug deployed at Natural Gas Liquids Plant (NGL-4), Mesaieed Industrial City, Qatar
The whole project was managed by a designated project engineer and co-ordinated by STATS Qatar based business
development manager. The project began by STATS deploying a specialist field technician to the workscope location
to carry out a detailed site survey, collating data and critical dimensions. Based on these findings STATS designed and
manufactured a custom built Remote Tecno Plug at their Aberdeen headquarters.
The Remote Tecno Plug was configured in a four module arrangement, as design analysis proved this to be the ideal
configuration to allow the tool to negotiate the pipeline system. A full Factory Acceptance Test (FAT) was performed
in Aberdeen in a purpose built test fixture which was created to simulate the client pipeline configuration.
Onsite, the Remote Tecno Plug was deployed from an 18 inch launcher and successfully pigged passed four valves,
a barred tee and monolithic joint before negotiating a 5D bend and setting immediately beyond the ESD valve. Once
at the desired location the plug was set using through-wall communication. Communication is achieved using an
extremely low frequency (ELF) radio control system for reliable tracking and accurate positioning. The Remote Tecno
Plug eliminates the need for tethers or specially modified pig-trap doors and is ideally suited for valve maintenance
activities.
After monitoring the set plug for 24 hours the isolation certificate was issued to verify the double block and bleed
isolation, the client then carried out the maintenance work. With maintenance work successfully completed the Tecno
Plug was used as a test boundary to perform a reinstatement pressure test. The plug was then unset and pigged back
to the launcher for demobilisation.
Qatar Petroleums head of business planning for gas operations commented STATS Group demonstrated a professional
approach throughout right from bidding, handling of technical queries, on time mobilisation of STATS resources
and contract execution. The site personnel allocated to this project deserve special praise for their commitment and
dedication, working alongside QP operations in the most co-operative manner with the utmost regards to safety.
STATS isolation and testing services are increasingly in demand from major operators in Qatar and other Gulf States.
This workscope for Qatar Petroleum is now one of many high profile contracts recently completed in the Middle East.
Tecno Plug is a Trade Mark of STATS (UK) Ltd
STATS isolation technician Iain Reid, prepares 36 Remote Tecno Plug for deployment
STATS Remote Tecno Plugs were configured in a three module train, to allow the tools to negotiate multiple bends
as they were pigged approximately 80 metres each to their set locations. The Remote Tecno Plugs were tracked
and accurately positioned using through-wall communication. An extremely low frequency (ELF) radio control system
sets and monitors the plugs throughout the isolation. The remote control system provides a high degree of flexibility
and eliminates the need for tethers or specially modified pig-trap doors.
The Remote Tecno Plugs were constantly monitored and remained stable and in location for approximately seven
days each while tie-in operations, which included close proximity hot work activities (welding), were completed.
Finally the plugs were unset and reverse-pigged back to the receivers for demobilisation.
STATS Group managing director, Peter Duguid, said: This project marks a significant milestone for STATS as these
are the first Tecno Plug isolations carried out in Malaysia. There is great demand for STATS isolation technologies
throughout South East Asia which we look to expand with future plans for a permanent base in region.
The compact design of the single module Tecno Plug allowed the plug
to be set in the short section of pipework
To allow deployment of a tethered Tecno Plug a temporary receiver door was used with a Stuffing Box arrangement
allowing the umbilical to pass through the system while at pressure. Once a leak test was performed on the receiver,
temporary door and stuffing box, the isolation plug was pigged with water to the set location. Accurate plug location
was determined by umbilical markings with additional positional verification confirmed by an ultrasonic signaller
from outside of the pipe.
The Tecno Plug was set at location using a hydraulic system via the umbilical and an annulus test was performed to
verify the integrity of the primary and secondary seals. Both seals were independently tested with full pipeline pressure
and monitored for 12 hours and once the verification period was completed, the isolation certificate was issued. The
STATS field team consisted of four isolation technicians as part of the workscope to provide constant monitoring of the
plug during the isolation.
With the receiver and valves depressurised and the Tecno Plug providing a verified isolation against the pipeline
pressure, the receiver was rigged away, allowing the main umbilical to be disconnected and temporary control
umbilicals were attached to ensure constant communication with the Tecno Plug, allowing the main umbilical to be
removed through the valve. On completion of the valve maintenance, further umbilical management was carried out
to allow the valve to be repositioned.
After reassembling the valve, a reinstatement service test was performed on the valve to confirm integrity at pipeline
operating pressure and the plug was unset and repositioned in the minor barrel of the receiver, while the full in-situ
testing scope was performed on the valve. On completion of the full valve testing scope, the plug was unset and
recovered fully into the receiver. With the valves closed, the receiver was isolated to allow recovery of the plug and
replacement of the receiver door.
STATS Group CEO, Pete Duguid, said: The project ran like clockwork with all parties working seamlessly together.
STATS isolation services allowed valve maintenance activities to take place efficiently and prevented shutting down
the entire pipeline. This would have resulted in a loss of time and revenue, potentially costing millions of pounds in
lost production per day.
24 Remote Tecno Plug | Marnock ETAP Spur Line, Central North Sea, UK
STATS Group has successfully isolated a 24 oil export line on BPs Marnock Eastern Trough Area Project spur line
located in the Central North Sea to allow the replacement of a 16 valve.
STATS deployed its 24 Remote Tecno Plug to isolate a pressure of 60 Bar providing safe working conditions to
allow valve replacement activities. Once set the primary and secondary seal tests were carried out using full
isolation pressure.
The pressure between the primary and secondary seals was monitored throughout the isolation, ensuring safety
critical double block isolation. With the valve replaced and Tecno Plug continuing to maintain isolation, a 24 extended
body in-line weld test tool was installed through the launcher to straddle the 16 tee. The test tool was then set to
carry out the reinstatement and leak test of the 16 branch and valve.
Following a site survey, STATS carried out a piggability study on the oil export line and trialled the Remote Tecno
Plug onshore with a client witnessed factory acceptance test (FAT). The test was performed a purpose built test
fixture which was created to simulate the offshore pipeline configuration. The shutdown was scheduled for up to 80
days and as the Tecno Plug was the primary isolation on the export pipeline, the request was for the Tecno Plug
to be capable of meeting this scheduled duration. STATS configured the plug in a three module train to allow an
additional module to house a contingency battery unit.
On-site, the Remote Tecno Plug was function checked and loaded into the launcher before pigging to the set
location with a mixture of water and nitrogen. The Plug was tracked and accurately positioned using through-wall
communication. An Extremely Low Frequency (ELF) radio control system sets and then monitors the plug throughout
the isolation. On issue of the isolation certificate, valve change out and maintenance activities could commence.
Once the new valves were installed STATS provided a bespoke 24 In-Line Weld Test Tool with an extended body and
additional locking module to test the newly made-up flange joints. The extended body allowed the In-Line Weld Test
Tool to straddle both flanges of the new valves.
24 Remote Tecno Plug maintains isolation while In-Line Weld Test Tool provides localised leak test of flanges
As there was a difference in the bores of the new valves, a standard In-Line Weld Test Tool once deployed with test
pressure applied would have moved due to the differential pressure areas. The lock module was set prior to each test
to prevent the test tool from creeping. The In-Line Weld Test Tool was moved to, and retrieved from the test areas
using a modular stem bar arrangement allowing the tool to be placed exactly in one of the three test locations. As
part of the planned maintenance scope the operator also replaced a 1.5 pig signaller which STATS pressure tested
with a separate 1.5 Flanged Weld Test Tool. On successful testing of all valves and flanges the Remote Tecno Plug
was unset and reverse pigged back to the launcher for demobilisation.
Head of Intervention and Isolations at STATS Group, Dave Vernon, said: This successful workscope has marked a
new milestone for STATS, our Remote Tecno Plug was constantly monitored and remained stable and in location for
seventy-two days while maintenance operations were completed, this is now the longest duration remote isolation
in STATS history. He continued We have developed a good relationship with Fairfield Energy Ltd and are currently
discussing the use of STATS isolation technology for future maintenance activities.
Tecno Plug is a Trade Mark of STATS (UK) Ltd
Client representatives, including installation OIMs, were highly impressed with the efficient, safe and professional
manner, in which the STATS team carried out their tasks and feedback from the client was extremely positive.
The six day operation was worth a six-figure sum and is STATS first project completed in the Republic of Congo.
Mr Duguid added: The successful workscope gave us a platform to demonstrate the capabilities of our technology
and we hope it may lead to similar projects in the Congo on behalf of Halliburton and Total E&P.
The BISEP was then fitted to the ball valve and housed
in a pressure competent launcher.
Leak testing of the launcher confirmed pressure
integrity allowing the ball valve to be opened and the
BISEP deployed into the pipework towards the flow
to be isolated.
Hydraulically setting the BISEP compresses the spherical
head and resultant radial expansion pushes the seals
out against the pipe bore. The twin compression seals
provide a facility to bleed and monitor the intermediate
annulus. The seal annulus port proves and monitors the
seal integrity before and during intervention work.
After performing validation tests on the BISEP, STATS
confirmed successful DB&B isolation and an isolation
certificate was issued to the client. The pipework was
then cut and removed from behind the BISEP with a
clamshell cutter. In order to allow removal of the clamp
METHODOLOGY
Weld on 14 Split Tees & Pressure Test
In this occasion STATS provided weld on fittings for this
job application. The tees were welded by BP personnel
on site with the presence of a STATS representative.
Once the welding had passed inspection the tees where
pressure tested by STATS personnel.
Slab Valve Installed & Tested
STATS provided a fully certified and tested slab valve for
the isolation work. Once the tees had been tested STATS
personnel installed the slab valve and performed testing
to confirm fully operational use.
Install Hot Tap Machine & Complete Tapping Operation
Using STATS Hot Tap Machine STATS personnel completed
successful hot tapping operations.
BISEP is a Trade Mark of STATS (UK) Ltd
Unlike a typical isolation plug project whereby the plug is generally deployed via an existing plug launcher /
receiver, or a temporary launcher mounted to a suitable valve within the system, the cell fill lines had no means
of access into the lines. This scope required an entry into each line to be created first.
Considering existing hot tap technology, particularly line stopping methods, as a method of creating an access
point and isolation, it was deemed that the robustness of the line stopping equipment was not acceptable to
the project. This decision was based on the fact that line stopping utilises a single passive seal over which the
operator has little or no control of the sealing performance. STATS chose to implement their isolation philosophy
of dual active seals with an annulus that could be used for test or bleed purposes, in essence a Double Block
and Bleed (DBB) system.
This led to the development of the BISEP, the first stage of the isolation process, providing a barrier against
the associated storage cell. However, this was an interim isolation to allow the formation of a full bore valved
access point above the initial hot tap.
In reviewing the operation, it was considered that due to the condition of the manifold valves there was the clear
potential that when venting and draining the line contents above the BISEP, the remaining fifteen cells could
cross communicate the manifolds and continue to feed and pressurise above the BISEP.
An additional means of isolating the cell fill manifolds was required to ensure that the group of four cell fill lines were
protected from the other cell fill groups. This led to the development of a floating polymeric grout material that would
fill the manifold from the top down displacing inventory through the butterfly valves towards the cells. The polymeric
grout was formulated to float in seawater. To try to formulate the grout to float in crude oil would have compromised
the structural properties of the material. To ensure the manifolds were oil free, the cell group and manifold were
exported to water prior to grout injection.
Filling from the bottom up had the potential to pressurise the manifold itself, which could only be managed by venting
any pressure increase to production with an associated risk of affecting the fill profile in the manifold. Filling from
the top down meant that during the grout injection process, no pressure increase could occur as the displaced fluids
would be managed by the storage water make up system.
With the grout compound engineered, a means of actually deploying the material into the manifold was required.
STATS extensive experience of pumping grout into repair clamps was reviewed and led to the detail engineering of
the injection process to ensure the 1,500 litres per manifold was injected effectively. The manifold end flanges were
hot tapped to provide injection and tell tale ports and a multi-pump arrangement was utilised injecting from both
ends of the manifold. The injection process was both temperature and time constrained with a point of no return
once the process was underway, careful planning and close liaison with platform operations throughout ensured the
success of these scopes.
The cell fill manifolds were injected in pairs leaving two manifolds and associated cells available for ongoing production
and export while the new piping system was connected to a reduced capacity new manifold system sited above the
old import / export system in the utility shaft.
The second phase isolation was engineered as a tethered isolation plug, a Tecno Plug, with the hydraulics and test
functions operated through a five core umbilical. These Tecno Plugs were multi-module articulated items designed
specifically for the operation using STATS isolation plug technology. The set location for the Tecno Plugs was the
utility shaft penetration, a short section of piping cast into the concrete structure of the platform. A plug set at this
location allowed all of the inboard piping to be removed. Again, the Brents project posed unusual problems. To
reach this set location the Tecno Plug had to be pigged through the cell fill lines which included negotiating bends.
Isolation plugs are typically designed for pipeline service where the usual minimum bend radius is 3D. For the cell fill
lines, where the piping was designed to ASME B31.3, the elbows were all long radius (1.5D) with Brent Delta having
double elbows configured back to back and sometimes offset at 90. Brent Bravo utilised single 1.5D elbows but had
the added complexity of a spectacle blind (confirmed as reduced bore by camera inspection and UT measurement)
directly between the utility shaft penetration and the elbow.
These slight, but critical differences in the platform
piping required two distinctly different pigging disc and
centraliser arrays to be developed for the Tecno Plugs,
the devil was in the detail.
In addition to the differences of the lower piping
arrangements for each platform, the utility shaft
penetrations differed between platforms also. Brent
Bravo had a reduced bore, coupled with a reduced length
set area; the target for pigging to location was +/100mm. Furthermore, should the set zone be overshot
during pigging, the piping bore changed again, this time
increasing as the pipework weaved its way across the cell
roof structure. Brent Delta has a continuous bore with a
much longer potential set location.
As a further restriction to the operation, a pigging pressure
limit was imposed to prevent any damage being caused to
the lines or any of the existing repairs, significant onshore
trialling allowed the pigging disc arrays to be fine tuned
to minimise the pigging pressure requirement and also
verified the reliability of the system.
In total, approximately 80 people (both shifts from both platforms) completed the onshore training programme (the
full offshore team from technicians to construction superintendents). In addition to the core operation, specialist
onsite machining was involved and the Rope Access technicians also attended OEM training.
The main training programmes were also witnessed by OIMs, Offshore Supervisors, Project Team Leaders, Technical
Authorities and the Project Engineering Team. Attendance and completion of the onshore training was deemed a
pre-requisite for being included in the offshore team.
As the project progressed offshore, the platforms were nearing their EoFL (End of Field Life), with Brent Delta
proposed as the first platform targeted for Cessation of Production. The original strategy of replacing all of the lines
was reviewed. Considering the reduced production profile of both platforms the reinstatement strategy was revised.
This new strategy meant that only four cell fill lines were to be replaced which was considered sufficient for platform
production purposes. The redundant cell fill lines would be isolated and disconnected from the redundant manifold
system leaving each individual line with a full bore valved entry point for any subsequent access requirements
as required by the Decommissioning Project for any cell sampling or remediation works. The manifolds were fully
capped using STATS LC-01 connectors.
On completion, the project end state left all of the original manifolds and pipework completely isolated from the
final hydrocarbon production system of the platform. The new cell fill lines and manifold system are the only piping
carrying hydrocarbons in the shaft.
For the duration of the project, the STATS team had no LTIs, a commendable achievement and a reflection
of the professionalism of the whole team and their attitude towards delivering a quality project in a safe and
effective manner.
To quote Shell, More hot tapping has been used on this project than in the whole of Shells previous history and the
pioneering plugging technology has been pivotal. Above all the projects six month safety and competency training
programme is second to none.(1)
1. Extract from Technology & Innovation Shell World website
BISEP and Tecno Plug are Trade Marks of STATS (UK) Ltd
STATS Project Manager Steve Gardiner said: Our technicians had to overcome grouting and hydro testing problems
associated with the low temperatures on site but the project was completed on schedule and within a four week time
frame.
The pipeline temperature made the selection of suitable materials challenging but working alongside our seal
suppliers, a material was identified that would perform well in the extreme temperature ranges identified by the
client (-29C to 32C).
Our BISEP tools allow dual seal isolation of a pipeline through a single entry point and an increasing number of
clients are discovering the benefits of this unique isolation technology.
STATS Group supply a range of products and services for piping and pipeline isolation, intervention, inspection, repair,
connection and testing workscopes. All products in the STATS portfolio is designed, manufactured, assembled and
tested in-house at the companys purpose built headquarters and workshop at Kintore, near Aberdeen.
On arrival at the platform STATS Isolation Technicians began the workscope by fitting the mechanical hot tap clamp
and ball valve to the air line, with the integrity confirmed the hot tapping was performed to provide access for the
BISEP.
The BISEP was deployed into the air line to provide double block and bleed isolation. With the line isolated the
pipework section could be cut and removed from behind the BISEP.
In order to allow removal of the clamp and hot tap penetration from the system, STATS then installed a temporary
launcher with a pre-installed 3 inch Tecno Plug. This allows the BISEP to be retracted and the Tecno Plug
deployed beyond the hot tap penetration and set to provide a new isolation barrier.
With the Tecno Plug isolation verified the hot tap clamp, ball valve and BISEP assembly could be removed
from the air line, the pipework was then cut using a clamshell cutter to remove the hot tap penetration. The
Tecno Plug is now providing line isolation.
To provide a tie-in point for the new valve and pipework a mechanical flange was attached to the cut pipework behind
the Tecno Plug. The new valve and a temporary launcher were then attached and pressure tested against the back
of the Tecno Plug to confirm integrity.
The Tecno Plug could then be unset and retracted into the temporary launcher and removed with the new valve
providing isolation. The remaining workscope was then completed to tie-in the remaining piping spools before the
platform finished shutdown.
BISEP and Tecno Plug are Trade Marks of STATS (UK) Ltd