Professional Documents
Culture Documents
Part 5c Annex 1 Price Schedule-Preliminaries
Part 5c Annex 1 Price Schedule-Preliminaries
Description
GENERAL
The Preliminary items included hereunder apply to the whole of
the works contained in this document and the Contractor must
allow for complying with same and for any cost incurred in
connection therewith. The rates inserted by the Contractor for
preliminary items shall be deemed to apply to the whole of the
works carried out including all variations to this contract.
DESCRIPTION OF WORKS
The extent of works included in this Contract shall be as
described in the Contract Documents or reasonably inferred
therefrom.
The Contractor shall carefully study the Contract Documents,
and satisfy himself as to the full extent, character and nature of
the Works to be performed under this Contract. The Employer
shall not entertain any claim arising from the Contractor's failure
to study these Documents.
PRELIMINARIES
The Contractor is invited to insert rates and prices against the
items to cover the risk, work, etc., involved. Any item not priced
will be deemed to be included in the rates generally.
Clause 1
Clause 2
Clause 3
Clause 4
Clause 5
Clause 6
Clause 7
Clause 8
Clause 9
Clause 10
Clause 11
Clause 12
Clause 13
Clause 14
Clause 15
Clause 16
Clause 17
Clause 18
Clause 19
Clause 20
Clause 21
Clause 22
Clause 23
Clause 24
Clause 25
Clause 26
Clause 27
Clause 28
Clause 29
Clause 30
Conditions of Contract
Definitions
Drawings and Specification
Ownership of Drawings
Contractor to Provide and Do everything
Sufficiency of Tender
Discrepancies
Figured and Specified Dimensions
Provisional and Prime Cost Sums
Setting Out of Works
Sub-Letting
Insurances & Performance Bonds
Governing Law of Contract
Notices and Fees to Authorities
Facilities to other Parties
By-Law, regulations, Notices and Fees
Protection of Adjoining Structures
Custody of materials
Plants and Equipment
Treasure Trove
Temporary Hoarding, etc.
Project Name Board
Materials
Trade Names
Local Products
PSB Quality Certification
Testing of materials
Samples
Approval of Samples
Overpayment
Amount (S$)
Description
Clause 31
Clause 32
Clause 33
Clause 34
Clause 35
Clause 36
Clause 37
Clause 38
Clause 39
Clause 40
Clause 41
Clause 42
Clause 43
Clause 44
Clause 45
Clause 46
Clause 47
Clause 48
Clause 49
Clause 50
Clause 51
Clause 52
Clause 53
Clause 54
Clause 55
Clause 56
Clause 57
Clause 58
Clause 59
Clause 60
Clause 61
Clause 62
Clause 63
Clause 64
Clause 65
Clause 66
Clause 67
Clause 68
Clause 69
Clause 70
Clause 71
Clause 72
Clause 73
Clause 74
Notes
(1) The works in this section shall be priced on a "lump sum"
basis and shall be inclusive of all ancillary and other
works and expenditure, whether separately or specifically
mentioned or described in the drawings and documents
or not, but which are either indispensably necessary to
carry out and to bring to completion the works described
or which may contingently become necessary to
overcome difficulties before completion and shall also
comply regulations and bye-laws. No claim resulting from
failure to do so will be entertained.
Amount (S$)
Description
(2)
(3)
(4)
Amount (S$)
S$
CONDITIONS OF CONTRACT
The conditions of contract to be used for the Works shall be the Public Sector
Standard Conditions of Contract (PSSCOC for Design & Build), available from BCA.
A Supplementary Specification or List of Editorial Amendments may also be issued
which will contain additional clauses applicable to the particular contract, which shall
supersede clauses contained in this Specification where applicable. Both these
Specifications are to be read in conjunction with each other, Contract Drawings and
the Conditions of Contract.
2.
DEFINITIONS
In this Specification the following words and expressions shall have the meanings
herein assigned to them except where the context otherwise requires:-
"Employer and
Contractor"
"FAS"
"Superintending Officer"
person or "S.O."
"as shown"
"as required"
"approved"
"as directed"
"Specification"
means this
Specification,
the
Supplementary
Specification and any Appendices and Attachments.
"Works"
OWNERSHIP OF DRAWINGS
All drawings and specifications are to be considered by all parties concerned as the
sole property of FAS and are to be returned to the Superintending Officer upon
completion of the Contract.
SUFFICIENCY OF TENDER
The Contractor shall ascertain for himself the nature and extent of the works
comprised in this contract. He shall be deemed to have satisfied himself before
submitting his tender as to the correctness and sufficiency of his Tender for the
Works. His tender price shall cover all his obligations under the contract and all
matters and things necessary for the proper execution completion and maintenance
of the works. No claims arising from the Contractor's default in ascertaining for
himself all information in regard to his obligations under the contract will be
entertained.
DISCREPANCIES
If the Contractor finds any discrepancy in drawings or between the drawings and the
Specification, Schedule or Rates or any other documents pertaining to this contract,
he shall immediately refer the same to the Superintending Officer who shall decide
which shall be followed and whose decision shall be final and binding.
11
SUB-LETTING
Refer to Clause 30 of the Conditions of Contract.
The Contractor shall not assign this Contract or any part thereof or without the written
approval of the Superintending Officer sub-contract any portion of this Contract; if he
does so, he and the unauthorised assignee or sub-contractor, will be liable to be
debarred from tendering for future FAS works.
12
13
14
16
17
18
CUSTODY OF MATERIALS
The Contractor will be held responsible for the safe custody of materials delivered to
site by specialists or nominated suppliers or sub-contractors.
19
20
TREASURE TROVE
Any treasure trove, coins or objects of antiquity which may be found on the site shall
21
22
23
MATERIALS
All materials and workmanship to be provided by the Contractor shall be the best of
their respective kinds. The Contractor will be held responsible for the proper carrying
out of the whole of the work. The work shall be done in the best and most workmanlike manner and the Contractor shall furnish the Superintending Officer or his
representative with vouchers to prove that materials are such as specified.
Samples of all materials must be submitted to the Superintending Officer or his
representative for approval before any order is placed with suppliers.
24
TRADE NAMES
Where trade names or makers' catalogue numbers are mentioned in the
Specifications or Drawings the reference is intended only as a guide to the type of
article quoted or material required. The Contractor may use any article or material
similar and equal to those described by reference to trade names or catalogue
numbers subject to the approval of the Superintending Officer. If the alternative
material offered by the Contractor is accepted by the Superintending Officer, it will be
treated as a variation to the Contract if the cost of the alternative material offered is
cheaper than the Specified Brand.
25
LOCAL PRODUCTS
Wherever any materials, required for these Works is manufactured in the Republic of
27
TESTING OF MATERIALS
Refer to Clause 10 of the Conditions of Contract.
The Contractor shall carry out all tests required by the Contract Documents and shall
pay all charges in connection with tests ordered by the Superintending Officer to be
carried out by others.
28
SAMPLES
Samples of materials and workmanship shall be submitted for approval by the
Superintending Officer and those samples may be kept by the Superintending Officer
who shall have power to reject all such materials and condemn such workmanship as
do not correspond with the approved samples.
29
APPROVAL OF SAMPLES
The Contractor is to take note that all work must be certified out in accordance with
the true intent of the Drawings and Specifications pertaining to this Contract. He must
understand that when a sample is approved by the Superintending Officer it does not
necessarily mean that there is not variation to the Contract if he carried out
subsequent work in accordance with the sample approved. The approved sample
may in fact be different from the Drawings and Specifications and this difference will
be taken care of by way of variation either in addition or in deduction as the case may
be.
It is the Contractor's sole responsibility to notify the Superintending Officer of any
item in an approved sample unit which does not fully comply with the Drawings and
Specifications. In the event of any discovery that the work as approved is in fact not
in accordance with the Drawings and Specification and that the Contractor has every
intention to hide such difference from the Superintending Officer, the Clause
regarding "Irregularities Committed" will apply and the Contractor will be charged the
relevant penalty accordingly.
30
OVERPAYMENT
If at any time during the period of this Contract, the Contractor is found to have over
claimed for the work executed, the FAS reserves the right to claim from the
31
32
LABOUR LAWS
The Contractor must pay his labourers and keep their working hours and observe
their holidays according to laws and regulations. He shall keep records and produce
them for the Superintending Officer's inspection.
33
34
FOREMAN
The Contractor shall keep at the works during all working hours a competent general
foreman who shall be employed to receive and act upon instructions given by the
Superintendent Officer and any such instructions given to the foreman shall be
deemed to have been given to the Contractor.
35
This information must be recorded before any workmen are allowed to commence
duty. Severe action will be taken by the FAS if the Contractor fails to comply with this
instruction and fails to record the name of any worker found at the site.
36
MISCONDUCT OF WORKMEN
The Contractor shall on the request of the Superintendent Officer immediately
dismiss from the works any workmen, overseer, or foreman employed thereon by him
who may in the opinion of the Superintendent Officer be incompetent or mis-conducts
himself and such person shall not be employed again on the works without
permission from the Superintending Officer.
37
NUISANCE
The Contractor shall be responsible for restricting his workmen only to the site where
the works are to be executed and shall prevent trespass into adjoining property and
existing building (if any) on site in which work is not in progress and shall take all
necessary precautions to prevent and shall indemnify the Employer against any
damage arising from nuisance of any kind.
38
40
41
42
43
44
45
46
47
48
49
VENTOR CONTROL
The Contractor is required engage a certified Environmental Control Officer to plan
and implement a comprehensive and effective vector control for the Site which shall
include all necessary measures to prevent the Site from becoming favourable to the
breeding or harbouring of mosquitoes or other vectors.
Vector control works shall comprise:
(a) Checking for mosquito breeding at least once a week.
(b) Larviciding all stagnant water using insecticides or anti-mosquito oil at least once
a week.
(c) Thermal fogging at least once a fortnight.
Thermal fogging to sit offices and workmens accommodation shall be carried out
fortnightly and if the Site is located within a malaria-sensitive area, residual spraying
of the walls at monthly intervals shall also be required.
50
51
52
SCAFFOLDING
The Contractor shall erect and maintain all necessary scaffolding, shoring etc.
required for the proper execution of the Works. The scaffolding, shoring, etc. shall be
erected in accordance with relevant Acts and Bye-Laws and to the satisfaction of the
Inspector of Factories.
Maintenance of scaffolding, shoring etc. shall be held to include checking the stability
of scaffolding, shoring etc. weekly or at the direction of the Inspector of Factories.
53
SITE MEETING
The Contractor shall attend periodic site meetings arranged by the Superintending
Officer and shall ensure attendance by the sub-contractor as required. The
Contractor shall make available for attendance at meeting at responsible
representative conversant with the Works and with authority to accept and make
decisions.
The Contractor shall submit to the Superintending Officer before each meeting an
agenda listing site problems, variations instructed by the Superintending Officer;
progress of works and any other matters for discussion during the meeting.
A technical meeting shall be held at least once a week to highlight outstanding
issues. These meetings shall be duly attended by the Project Manager and if
required, supported by his Technical Team.
Such meetings shall also be used as coordination meeting between the Turf
Contractor and the Infrastructure Contractor to resolve any issues arising from the
The Contractor shall prepare and submit to the Superintending Officer monthly report
(1 set in hard copy) including the following write-up:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
In all cases where a representative of the Employer is employed upon the works, the
daily report shall be submitted for checking and signing by the Employers
representative.
55
PROGRESS PHOTOGRAPHS
The Contractor is to provide colour photographs to show the stages of Works to the
Superintending Officer. Photographs shall be taken at four-week intervals throughout
the construction period. Each photograph is to be dated and marked with the
description of the photograph and location from which it was taken and printed on A4
paper.
56
CONSTRUCTION PROGRAMME
Refer to Clause 9 of the Conditions of Contract.
The Contractor is required to submit as part of his tender a linked bar chart of his
proposed construction programme showing the intended method, sequence, stages
and order of proceeding with the Works together with the period of time he has
estimated for each and every such stage of progress.
Within two weeks from the award of this contract, the Contractor shall revise the
linked bar chart and prepare from it a critical path network to incorporate all relevant
57
58
59
AS-BUILT DRAWINGS
The Contractor shall keep accurate records of the actual construction during
construction. This information shall be supplied to the Superintending Officer
progressively in two paper prints and shall form the basis of an as-built record of the
finally constructed Works.
As-built drawings shall contain all necessary information from reviewed shop
drawings, construction drawings, co-ordination drawings and as-built records. Such
drawings shall be prepared and presented in a format approved by the
Superintending Officer, duly signed off by the respective Contractor, Qualified Person
& RTO.
Prior to completion of the project, the Contractor shall hand over to the
Superintending Officer two (2) set of prints for review. After the Superintending
Officers review the Contractor shall, if necessary, correct the as-built drawings. The
Contractor shall then submit two (2) set of A0 prints of all final as-built drawings
including those prepare by the nominated sub-contractor, plus one set in CDROM
format.
60
FEB
4
AUG
6
MAR
7
SEP
7
APR
9
OCT
7
MAY
6
NOV
8
JUN
5
DEC
8
62
63
64
66
67
IRREGULARITIES COMMITTED
The stipulations of this Specification will be strictly enforced and any work
condemned must be removed from the site within 24 hours and defective works
made good. Should the Contractor fail to comply with this requirement the
Superintending Officer may cause the work to be done by others and charge the cost
of same against the Contract amount.
68
69
ADULTERATION OF PAINTS
Should paints used in this Contract be found to be adulterated or unsatisfactory, the
FAS will recover from the Contractor a sum not exceeding $10,000.00 as fees paid
for the expense of laboratory analysis incurred.
70
PROGRESS
If the rate of progress of work is unsatisfactory over a given period of time, then on
the recommendation of the Superintending Officer the Employer may invoke Clause
31 of the Conditions of Contract and remove the Contractor and his employees from
the site of works and complete the work under a new contract or in any other manner
71
72
REMOVAL OF RUBBISH
The Contractor shall arrange and pay all fees for disposing of all rubbish, unwanted
building debris, earth, rubble, chemicals, noxious or polluting matter, etc. from the
Site both at regular intervals and on completion.
The Contractor shall provide at his own cost and expense proper bulk bins of
adequate sizes at Site for storage of construction waste and debris and to make
necessary arrangements for the disposal of such waste and debris to approved
disposal grounds.
Burning of rubbish on the Site will not be permitted.
73
74
BRIBERY
During the progress of this Contract the Contractor and his representatives at the site
are forbidden to offer any bribes, commission or gift to the Superintending Officer or
any member of the FAS staff. Should it be discovered that bribes, commissions or
gifts have been given to the Superintending Officer or any of the FAS staff, this
Contract may be terminated immediately upon such discovery and the Contractor
shall be liable to forfeiture of any balance of money retained by the Employer. In
addition the Contractor is to pay any loss to the Employer resulting from such
termination.