Professional Documents
Culture Documents
International Journal of Quality & Reliability Management: Article Information
International Journal of Quality & Reliability Management: Article Information
International Journal of Quality & Reliability Management: Article Information
Article information:
Access to this document was granted through an Emerald subscription provided by emerald-srm:434496 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald for
Authors service information about how to choose which publication to write for and submission guidelines
are available for all. Please visit www.emeraldinsight.com/authors for more information.
The current issue and full text archive of this journal is available at
http://www.emerald-library.com
IJQRM
16,7
638
Received February 1998
Revised October 1998
H. Li
Introduction
Organisations wishing to systematically improve their performance must
acquire knowledge. The early management theorist Fredrick Taylor in 1915
concluded that the success of management is based upon their ability to
become scientific where knowledge is characteristically acquired through
systematic observation, experiment and deductive reasoning. Similarly, the
key to continuing success in quality management is the ability to collect
information to improve the performance of a product or service. This
information should then be incorporated into the design of the new product or
service. Concurrently, this information can also be used to measure the
performance of the product or service so that continuous improvement is based
on measurement of performance where benchmarking can be effectively
implemented. This can provide the necessary feedback mechanism, which can
allow an organisation to learn and acquire knowledge and therefore strive for
industry best practice.
In the construction industry, however, organisations generally do not have
in place an effective organisational learning mechanism that can be used to
stimulate best practice, primarily because quality management principles and
tools have been neglected (Jaafari, 1996). Therefore, little is known about the
International Journal of Quality &
Reliability Management,
Vol. 16 No. 7, 1999, pp. 638-658.
# MCB University Press, 0256-671X
The authors would like to thank the contracting organisation and consultants for participating
in this study. Without their cooperation and support the research could not of been undertaken.
Furthermore, the authors are most grateful to Dr Segun Faniran and two anonymous referees
for their extremely useful and helpful comments on an earlier version of this manuscript.
Rework
benchmark
metrics
639
IJQRM
16,7
640
(Love and Li, 1998). Consequently, the status quo of poor quality often prevails.
Moreover, the associated costs of QA have been found to be an encumbrance,
administratively, financially, and culturally to many companies. Thus,
companies eschew progressing to implement continuous improvement and
TQM principles. However, becoming quality assured is the first step in the
pursuit of quality. For QA to work effectively it needs to operate within a TQM
environment. In other words, QA is merely a technical inspection and
surveillance procedure that is just one of the components of a company-wide
application of TQM. Because companies cannot see the benefits of becoming
quality focused substandard products and services often result, which
inadvertently emerges as rework (Love et al., 1998). There is, therefore, an
increasing need to improve the quality and performance of operations in the
construction process, and thus reduce the incidence and effect of rework so as
to encourage industry best practice.
The need for rework benchmarks
Before rework can be significantly reduced and the overall performance and
output of a project improved, metrics for rework need to be established so that a
process of benchmarking can be initiated. Benchmarking focuses on the
importance of understanding the tasks and activities in a process that produce
an outcome and how improvements in processes can take place (Schaffer, 1992).
It is used to continuously measure an organization's products and services
against those of its competitors so that targets and priorities for gaining a
competitive advantage can be established and the search for best practice
initiated (Oakland and Sohal, 1996). According to Zairi (1996, p. 35) a benchmark
can be:
.
anything taken or used as a point of reference or comparison;
.
something that serves as a standard by which others may be served;
.
anything or something that is comparatively measurable; and
.
a physiological or biological reference value against which performance
is compared.
The establishment of a series of benchmarks as a point of reference can enable
industry clients, especially those who procure buildings on a regular basis,
contractors, and all stakeholders to compare their own output rates against
what has been found to be best practice performance amongst their national
and international counterparts.
For benchmarking to be effective at a project level, organisations need to
view it as a positive process of improvement rather than negatively as one that
exposes an organisation's weakness. Furthermore, benchmarking should be
viewed as an operational process of continuous learning and adaptation that
results in the development of an improved organisation.
It is often argued that the construction industry is unique when compared to
other industries and that there is limited scope for applying continuous
Rework
benchmark
metrics
641
Benchmarking
The concept of benchmarking has been successfully applied in many
manufacturing industries worldwide, yet in the construction industry little
attention has been paid to its potential implementation as a quality
improvement tool. This trend may be changing as some large construction
companies in Australia are recognizing that there is a need to develop internal
and competitive/functional benchmark measures in the search for best practice.
The absence of a quality focus in construction suggests that benchmarking
is not being used positively as a tool for servicing internal and external
customer requirements but more for measures such as project time
performance (CII, 1994). As noted in Figure 2 and with a quality program in
place, it is suggested that organisations in the construction industry should
establish benchmark measures that focus on (Oakland and Sohal, 1996):
PARENT
ORGANISATION
PEOPLE AND
PROCESSES
SERVICES
PROJECT
PRODUCT
Project
Organisation
Facility
Client/End User
Quality
Design
Design Team
(Architect etc)
Quality
Contractor
Quality
Subcontractor
& Suppliers
Quality
Continuous Improvement
Figure 1.
Continuous
improvement in a
project environment
IJQRM
16,7
Internal Benchmarking
PARENT
ORGANISATION
Benchmark Measures:
Efficiency & Effectiveness
Productivity
Quality
Impact
642
Competitive/Functional
Benchmarking
Benchmark Metrics
INDUSTRY
BEST PRACTICE
Benchmark Metrics
Figure 2.
Benchmarking in the
construction industry
PROJECT
ORGANISATION
Benchmark Measures:
Efficiency & Effectiveness
Productivity
Quality
Impact
Benchmark Metrics
Competitive/Functional Benchmarking
PARENT/PROJECT
COMPARISONS
Benchmark Measures:
Efficiency & Effectiveness
Productivity
Quality
Impact
Rework
benchmark
metrics
643
Benchmark metrics
A metric is a short-term quantitative measure and its uses for benchmarking
are numerous and varied. For example, they can be used as a financial
(business performance), technical (productivity measurement) and efficiency
(human contribution measurement) indicators (Zairi, 1996). In some industries
it is common to emphasise a few operating characteristics while in others the
focus is on a wide range of performance parameters.
In some cases the parameters that describe the system will be highlighted. In
others, it may be more common to examine the performance of sub-elements of
the system. Some measures are relatively easy to obtain while others may be
difficult to identify and may need to be estimated. If measures are obtained,
benchmarking can be a significant foundation for reducing rework at the parent
and project level, which in turn will improve the organisational performance.
There are numerous methods of measurement that need to be processed and
applied to help construction organisations improve their quality and
productivity. The cost of quality is just one type of measurement that can
provide the user with information about rework and activities designed for its
prevention. It is a measurement that could be considered after-the-fact, because
it occurs after the action has occurred. Thus, the measurement of rework
should be used as a mechanism to learn from the past to improve the future.
That is, measurement becomes a proactive project management activity on a
new project. This captures the essence of benchmarks as they do not remain
passive but become dynamic measures of performance, which can be used to
inform the organisation and project managers about particular activities and
processes at a parent and project level.
In the next section of this paper a case study is presented which attempts to
establish benchmark metrics for the cost of rework from two projects that were
Type of benchmarking
Relative project cost
Operating processes
Technology
Quality procedure
Customer service/satisfaction
Labour productivity
Occupational health and safety (OHS)
Table I.
Benchmarks used by
the construction
industry
IJQRM
16,7
644
procured by the same contracting organisation. The use of a case study is used
to gain a better understanding of why and how rework occurs. If processes are
to be optimised, they must be measured and understood in the context of their
attributes and characteristics.
Methodology
The contractor used for the research was the first building and construction
company to be certified to the dual standards of ISO 9001/AS 3901 and AS 2990
Cat. A in Australia. Since becoming certified in 1991, the company has
developed and implemented an effective continuous improvement program
that has been able to reduce the amount of rework experienced in its projects as
well as improve its position in the market place. The company has been the
recipient of numerous quality awards for its excellence in the pursuit of quality
and as a result is considered to be a best practice company (Whitford and
Andrew, 1994).
The authors established personal contact with senior management within
the contracting organisation to explain the nature and purpose of the research.
The projects used for the research were selected on practical grounds; namely
their availability. Meetings were conducted with site management and the
consultants to explain the nature of the research and the information required.
A full guarantee of confidentiality and anonymity was given, and the
independence and neutrality of the researchers was stressed.
Case study
A case study can be simply defined as ``methodology based on interviews,
which are used to investigate technical aspects of a contemporary phenomenon
with its real life context; when the boundaries between phenomenon and
context are not clearly evident; and in which multiple sources of evidence are
used'' (Yin, 1989, p. 3).
The authors have based their methodological framework on theoretical
replication. Yin (1989) supports this approach and specifically notes that
multiple cases should be regarded as multiple experiments and not multiple
respondents in survey and so replication logic and not sampling logic should be
used for multiple case studies. The case studies provide valid findings from
which other organisations can learn. The case studies used for establishing
initial benchmark metrics for rework were:
.
Project A
Residential development
43
5
10,960,000
12,065,900
806,356
299,544
40,960
5,000
3.15
Project B
Industrial development
30
8
4,450,000
4,769,333
319,333
64,078
42,905
2.40
Rework
benchmark
metrics
645
Table II.
Characteristics of
project A and project B
IJQRM
16,7
646
Rework
benchmark
metrics
647
IJQRM
16,7
648
Both project managers were well respected by the site workforce because of
their understanding of the problems that often emerge on-site. As a result, there
were no non-conformances issued on either project, despite the contractors
prestigious corporate image built on their approach to quality. The contractors'
project managers preferred to operate on an informal basis with their
subcontractors. They initially gave the subcontractors informal warnings
about the quality of their work. If defective work was not rectified within 24
hours then a non-conformance would be issued.
In both projects the contractor required their subcontractors and suppliers to
have a quality management system in place so that the project could be
delivered effectively. However, this was hindered because the suppliers of
information, namely the design consultants were not QA accredited, nor did
they have a quality focus. Some of the information supplied by the designers
was inaccurate and incomplete and as result rework emerged downstream onsite. Using a classification similar to Burati et al. (1992) as described in the
Appendix, Tables III and IV highlight the cost of rework classified by the cause.
The main causes in project A were design changes, although the number of
rework incidents due to construction errors are significantly greater than any
other cause. The costs of a design change far exceed the costs of a construction
error, primarily because activities are programmed and materials are often
ordered in accordance with the original contract documentation. Whereas,
when a construction error occurred it was predominantly due to simple
mistakes made by subcontractors, for example installing a door incorrectly.
In project B, construction changes and errors were found to be the most
prevalent cause of rework. This was primarily due to the large amount of
prefabricated components and the lack of design standardization. Moreover,
the quality of finishes for trades such as painting, tiling and concrete placing
was considered to be of a low standard by the clerk of works. Typically, design
and construct projects have been criticized for their simplicity and poor quality;
in this case this was clearly evident. Common sources of the changes in both
Cause
Table III.
A summary of the cost
of rework causes for
project A
Design change
Design error
Design omission
Construction change
Construction error
Construction omission
Construction damage
Construction
improvement
Total
Number of
events
Nonproductive
time (days)
Total
cost ($)
Mean per
event ($)
Benchmark
metric for
causes % total
rework (%)
65
12
2
14
120
2
3
20
13
7
2
14
14
182,893
59,233
6,837
72,979
19,514
760
3,288
2,814
4,936
3,419
5,213
163
380
1,096
53.70
17.40
2.00
21.40
5.75
0.20
0.97
218
69
345,504
100
Cause
Design change
Design error
Design omission
Construction change
Construction error
Construction omission
Construction damage
Construction
improvement
Total
Number of
events
Nonproductive
time (days)
Total cost
($)
Mean per
event ($)
Benchmark for
causes % total
rework (%)
10
6
1
25
37
20
29
2
7
0
5
13
0
9
11,100
11,020
300
25,840
27,575
5,340
13,190
1,110
1,837
300
1,034
745
267
455
10.38
10.30
0.28
24.15
25.78
4.99
12.33
38
166
3
39
12,618
106,983
332
11.79
100
projects were the end-users. Their input to the design and internal layout of the
facilities had not been clearly addressed by their project representative.
Consequently, as the buildings were being erected their dissatisfaction with the
product being procured began to emerge. Clearly, end-user involvement during
the development of the brief should minimize potential change orders.
Subcontract rework costs
The calculated costs of rework for each subcontract package for projects A and
B are tabulated in Tables V and VI respectively. Note that only those
subcontract trade packages where their contract value could be determined
have been tabulated and a benchmark presented. The party responsible for the
cost of rework was determined and can also be seen in Tables V and VI. It can
be clearly seen in project A that the contractor was directly responsible for only
$13,500 of rework costs.
Through discussions with the project manager in project A, it was found
that the contractors off-loaded any additional costs to their contract on to their
client and subcontractors. The rework costs for the ceilings and internal
partitions subcontract were due to end-users changing their minds with regard
to the layout of their apartments and clashes with the mechanical, electrical and
hydraulic services. Partitions had to be dismantled and this interrupted the
flow and sequencing of activities. This had demotivating effects on the
partition subcontractor and preceding subcontract trades and as result lowered
productivity levels. In an attempt to eliminate any further delays and maintain
their schedule, the subcontractor had to allocate additional resources to the
project, which were charged back to the client. The costs of rework to the
contractor resulted from additional resources being required to re-establish the
partition set out.
The mechanical and structural steel subcontracts were also significantly
affected by changes and errors as a benchmark of 10.59 per cent and 35.70 per
cent respectively for rework as a percentage of the subcontract value has been
established. As the costs of mechanical works form a substantial part of
Rework
benchmark
metrics
649
Table IV.
A summary of the cost
of rework causes for
project B
IJQRM
16,7
650
Table V.
Benchmark costs of
rework for subcontract
packages in project A
Table VI.
Benchmark costs of
rework for subcontract
packages in project B
Subcontract package
Number of
Cost to
Cost to
Rework
rework subcontractor contractor Cost to benchmark
Value ($) events
($)
($)
client ($) metric (%)
Balustrades
Blockwork
Carpentry
Ceiling and partitions
Concrete
Doors
Electrical and fire
Formwork
Joinery
Landscape
Lifts
Mechanical
Metalwork
Painting
Piling
Plumbing and drainage
Reinforcement
Roofing
Structural steel
Tanking
Tiling
111,165
391,230
145,596
768,841
572,735
53,649
694,401
830,277
399,279
332,976
338,704
488,520
139,304
446,892
251,795
914,862
578,236
40,795
90,481
221,775
485,078
Subcontract package
Trade Number of
Cost to
Cost to
Rework
package
rework subcontractor contractor Cost to benchwork
value ($)
events
($)
($)
client ($) metric (%)
Blockwork
185,559
Carpentry
16,492
Carpet and vinyl
915
Ceiling and partitions
140,269
Concrete
1,032,626
Doors
33,445
Electrical and fire
571,750
Excavation
181,712
Lifts
111,000
Mechanical
288,200
Metal work
36,380
Painting
70,420
Piling
156,243
Plumbing and drainage 320,000
Roofing
135,464
Specialist shelving
151,795
Structural steel
230,273
Tiling
10,307
Windows and glazing
30,345
7
4
5
32
3
9
30
4
7
11
1
17
7
13
2
19
6
4
8
1
5
6
1
2
7
10
7
20
1
2
8
7
12
1
13
6
11
4
2
4
300
3,400
750
0
300
1,250
2,950
500
250
1,000
300
450
2,800
450
2,260
200
300
1,000
25
2,275
700
25
550
500
750
1,920
300
3,500
3,495
2,900
250
1,850
50
50
8,900
1,500
2,000
1,000
500
500
2,000
1,175
1,250
150
5,083
3,775
5,860
7,500
150
4,895
1,950
1,500
6,825
3,100
350
345
1,912
8,000
5,121
51,062
1,431
1,788
29,250
10,434
708
50,735
1,192
1,338
32,000
6,503
32,000
4,757
625
100
6,500
100
125
3,960
~
195
250
10,375
45
1.99
2.91
3.52
7.90
0.51
3.89
4.68
0.48
0.13
3.21
0.21
10.59
1.07
0.40
1.11
3.60
1.60
0.49
35.70
0.90
1.19
0.98
7.58
27.32
6.26
0.57
11.74
1.81
4.13
0.59
0.26
5.28
7.65
2.24
1.70
3.43
11.50
2.15
3.88
1.45
Rework
benchmark
metrics
651
IJQRM
16,7
652
rework and concluded that it is necessary to know how the cost of expenditures
relates to quality to justify budget allocations. Brown (1991) found that every
dollar spent in reducing rework costs could significantly improve profits. With
this in mind, prevention clearly is the most appropriate action that industry
practitioners should seek to undertake as it can help reduce internal and
external failure costs inasmuch as mistakes are eliminated. In the case of
inspection, if mistakes are found, there will still be an internal failure cost
because of the rework required. Therefore, it can be seen, especially in the case
of the contractor described above that inspection does not build quality into the
process whereas prevention can.
The need for a quality focus
The reported costs of rework figures in the case studies are significantly lower
than the 12 per cent quoted by Burati et al. (1992). This leads the authors to
suggest that the nature of the project, contractual arrangement, effectiveness of
the project team and the quality of the subcontractors will have a bearing on
the cost of rework experienced. The rework experienced in these projects could
have been greater if it were not for the contractor's project managers' proactive
approach to planning and scheduling. That is, they were able to identify
potential problems before they emerged on-site. By checking and inspecting
contract documentation the contractor acted as a quality buffer, though this
often resulted in the contractor having to wait for elements to be re-designed
and for additional information, which further meant that project activities were
disrupted and re-scheduled. This meant that considerable amounts of nonproductive time were experienced as noted in Tables III and IV (69 days and 39
days respectively).
The non-productive time experienced in project A is significantly greater
than that in project B. Interviews with the architects revealed that their internal
management had not effectively planned the design and documentation phases
of the project. They had numerous commissions being undertaken
simultaneously with project A and as a result had limited resources to attend to
all the clients' needs and requirements. Consequently, the documentation
provided to the contractor failed to provide the information that was needed to
manage the construction process. Arge (1995) suggests that direct and constant
communication between the architect and client/end-user is a critical factor that
can affect the quality of the end product. Arge further notes that if architects
are to deliver clients/end-users quality architecture, they need to improve their
internal management practices and consider limiting the commissions they
undertake.
Notably, the designers in both projects did not follow nor implement quality
management procedures and practices because the immediate benefits were not
considered tangible. Nevertheless, it must be stressed that it may appear that an
organisation is spending money on effective and practical quality management
systems without seeing any benefits. However, it must be seen as an investment
in efficiency and effectiveness. The effective implementation of TQM and its
associated tools and techniques could solve most rework problems before they
occur. According to CIDA (1995) projects that have a formal quality
management system in place record lower levels of rework. They found the
average cost of rework, as a percentage of contract value, for projects with a
quality system can be as low as 0.72 per cent. Conversely, those projects without
a quality system in place were found to have an average cost of rework 6.5 per
cent. Similarly, Burati et al. (1989) states that when TQM is applied throughout
a project, rework can be virtually non-existent, especially if incentive schemes
are introduced. As rework is reduced, performance, productivity, and quality
will improve, which will reduce costs and increase profit.
Managing the interfaces in the quality-chain
To reduce rework in construction a conceptual model for benchmarking the
interfaces of the quality-chain is proposed in Figure 3. Rework essentially
originates from the design process. Indeed it would appear that because quality
is not ingrained within the culture of architectural and engineering practices
the notion of the customer-supplier relationship is abated, which has
ramifications throughout the quality-chain in a project. Juxtaposed with poor
internal management practices this could be a recipe for rework occurring
downstream in the construction process. Therefore, at parent level, senior
management must develop a corporate strategy that focuses on developing a
quality culture, which seeks to develop an inherent customer-supplier focus. By
implementing a continuous improvement philosophy built on a sound QA base
that utilises benchmarking as its driving force for best practice, an
organisation's performance and competitive advantage may improve.
Benchmarking core business processes should form an integral part of the
organisation's corporate strategy. Only when all parent key organisations
involved in a project are benchmarking will the performance of the industry
begin to improve (Ireland, 1996). Implicitly, this will require each organisation
involved in those interfaces identified in Figure 3 to develop benchmarks for
those processes used to support its internal and project-based operations.
By improving the parent's project-based processes, rework may be reduced,
which may improve customer satisfaction and project performance. Though we
do suggest that improvements in overall project performance will be dependent
on the ubiquitous nature of best practice programmes initiated by those
organisations participating in the project.
The factors impacting design effectiveness and the subsequent impact of
changes on construction cost and schedule have been well documented in the
construction management literature over the last ten years. Despite these
problems being well known and understood by industry practitioners, very few
improvements have been made in the construction industry. Thus, in an
attempt to achieve dramatic improvements in project performance numerous
researchers and practitioners in construction have suggested that business
process re-engineering could be the panacea for success (Mohamed and Tucker,
1996; Ireland, 1994). However, before such an approach can implemented a
Rework
benchmark
metrics
653
IJQRM
16,7
PARENT ORGANISATION
Corporate Strategy (Vision, mission and competitive advantage)
Commitment & Leadership to change
Customer & supplier focus
Partnership development
654
PROJECT ORGANISATION
Design Process
(Upstream)
Input
Concept
(Client Requirements)
Performance Measurement
Continuous Improvement Cycle
Improvement
A P
QUALITY CHAIN
C D
QA
Conversion
Design
Benchmark
Time
VARIABILITY REDUCTION
Construction Process
(Downstream)
Documentation
(Drawings &
Specification)
Benchmark
Output
Construction &
Manufacture
Operation of
Facility
Figure 3.
A conceptual model for
benchmarking the
interfaces of the qualitychain
Input
Benchmark
Conversion
Benchmark
Output
culture founded on quality is needed to act as the primary enabler for change
(Love and Gunasekaran, 1997). Those TQM practices that could be employed to
reduce rework and improve project performance include:
.
Rework
benchmark
metrics
655
IJQRM
16,7
656
Rework
benchmark
metrics
657
IJQRM
16,7
658
Construction
Client/client representative
Occupier
Manufacture
Unknown
Construction
Site conditions
Client/client representative
Occupier
Manufacture
Unknown
17. Jim Smith, Peter E.D. Love, Ray Wyatt. 2001. To build or not to build? Assessing the strategic needs
of construction industry clients and their stakeholders. Structural Survey 19:2, 121-132. [Abstract] [Full
Text] [PDF]
18. Jim Smith, Peter E.D. Love. 2001. Adapting to clients needs in construction a dialogue. Facilities 19:1/2,
71-79. [Abstract] [Full Text] [PDF]
19. Peter E.D. Love, Gary D. Holt. 2000. Construction business performance measurement: the SPM
alternative. Business Process Management Journal 6:5, 408-416. [Abstract] [Full Text] [PDF]
20. Peter E. D. Love, Purnendu Mandal, Jim Smith, Heng Li. 2000. Modelling the dynamics of design error
induced rework in construction. Construction Management and Economics 18, 567-574. [CrossRef]
21. Peter E. D. Love, Heng Li. 2000. Quantifying the causes and costs of rework in construction. Construction
Management and Economics 18, 479-490. [CrossRef]
22. Peter E.D. Love, Heng Li, Zahir Irani, Gary D. Holt. 2000. Rethinking TQM: toward a framework
for facilitating learning and change in construction organizations. The TQM Magazine 12:2, 107-117.
[Abstract] [Full Text] [PDF]
23. Peter E.D. Love, A. Gunasekaran. 1999. Learning alliances: a customersupplier focus for continuous
improvement in manufacturing. Industrial and Commercial Training 31:3, 88-96. [Abstract] [Full Text]
[PDF]