Cash Flow Fore Cast: Main Contract
Cash Flow Fore Cast: Main Contract
ESTIMATE(R
s. Cts)
DURATION
A Pre Tender
Documentation
Approvals
Tender Document
10.2015 to 15.02.2016
B Invitation to Tender,
Bidding Evaluation
C Approvals and Award
D Commencement of Work
15.02.2016-30.03.2016
01.04.2016-07.04.2016
22.04.2016
MAIN CONTRACT
E
Preliminaries
600,000.00
22.04.2016-01.11.2016
400,000.00
3 months
22.04.2016-22.07.2016
II.
III.
670,000.00
Concrete Works up to
DPC
1,919,250.0
0
Preliminary Estimate 1
1.5 months
22.04.2016-31.05.2016
CASH FLOW
Proposed New Church Building Complex, Sri Lanka Methodist Church, Koralawella.
C SUPER STRUCTURE
I.
Concrete Works from
DPC Level up to First
Level
II.
Masonry Work
III.
IV.
4,326,945.0
0
3 months
01.06.2016-31.08.2016
2,755,000.0
0
4,275,000.0
0
1,000,000.0
0
15.08.2015-31.08.2016 (2
weeks)
SUB CONTRACTS
I.
Fabrication
1,545700.0
0
Fixing at Site
II.
Electrical Insulation,
Wiring & Fixing
Accessories
III.
Finishes
Floors
Preliminary Estimate 1
22.04.2016-22.07.2016(3
months)
22.07.2016- 22.08.2016 (1
months)
2,000,000.0
0
26.09.2016-10.10.2016(2
weeks)
3,003,250.0
2 weeks
15.09.2016-01.10.2016
Proposed New Church Building Complex, Sri Lanka Methodist Church, Koralawella.
Walls
IV.
Painting
V.
Electrical Insulation
Wiring & Fixing
Accessories
FURNITURE
VI.
0
1,530,500.0
0
2,000,000.0
0
3,400,000.0
0
Preliminary Estimate 1
01.09.2016-01.10.2016(1
months)
03.10.2016-21.10.2016(3
weeks)
26.09.2016-10.10.2016(2
weeks)
25.07.2016-25.10.2016(3
months)