Statutory Clearances Required For Starting A Captive Coal Mine
Statutory Clearances Required For Starting A Captive Coal Mine
FOR STARTING
A CAPTIVE COAL MINE
VENKAT
July 2010
Permission / Clearance
Prospecting License
3
4
5
6
10
11
12
7
8
9
13
14
15
16
17
18
19
20
21
22
Diversion of Nallah
23
Use of Explosives
24
Authority / Act
MMDR Act
Forest Conservation Act
1981
MMDR Act
Ministry of Coal
Ministry of Coal
MMDR Act, MCR
MoEF
Forest Conservation Act
1981
Wild Life Act, MoEF
Forest Dwellers Act
Minimum Wages Act,
Contract Labor Abolition
Act
State Revenue Dept
Factories act, VT Rules,
State laws??
State Water Resource
Dept
State Industry Dept and
Electricity Board
Forest Conservation Act
1981
MoEF
Ministry of Defense
MMDR Act, MCR
VT Rules
National Highway
authority
Water Resource Depot,
Pollution Control Board
Indian Explosive Act,
Ministry of Petroleum
Indian Explosive Act,
Ministry of Petroleum
Likely Schedule
Sl. No
Permission / Clearance
25
26
27
28
29
Authority / Act
Petroleum Act, Chief
Controller of Explosives
Boilers Inspector
Factories act
LA Act
Coal Mines Regulation,
CMR
Likely Schedule
1. PROSPECTING LICENSE:
Check list:
3. MINE PLAN
Check list:
Authorisation to the RQP to prepare mine plan. This should be signed by the authorised
person.
Undertaking from the joint venture partners to abide by all the provisions of the
approved mine plan.
The block boundary marked on the cadastral plan and certified by CMPDI
The land schedule of the block area indicating forest land, agricultural land, non-forest
land, Govt. land and gochar land if any.
The land use plan
Location plan of the block with respect to nearby railway station and road.
4. MINING LEASE:
Check list
Application in Form I to the DM office of respective State, India with a non refundable
fee of Rs. 3500
Affidavit Stating No Mining dues and Income Tax due in the State.
Company registration certificate (copy).
Power of attorney of authorized person who will sign the application.
List of Board of Directors.
Resolution of the company for appointing the authorized signatory.
Attested copy of the memorandum of association and article of association.
Cadastral Map of the area on 1:4,000 scale in case of revenue land or forest Map in case
of forest land. on 1:15, 000 scale.
Copy of the Prospecting Licence Order.
Details of the financial and technical capability of the company.
Prospecting report stating proof of mineral as per UNFC system.
Self certification for filing of prospecting data.
Any other information desired by the applicant or DM office.
Copy of Grant order issued by the Dept. of Steel & Mines, State Govt.
Copy of Mining Plan with approval of I.B.M. along with Mines Closure Plan and
Reclamation plan.
N.O.C. issued By State Pollution Control Board
Copy of Forest Diversion proposal with Maps
Land Schedule of the lease area.
List of Villages with demographic features coming within 10 K.Ms from the core of the
lease area.
Cattle Population of the said villages.
Note on local geology, rock and soil.
Note on mines drainage.
Note on existing perennial nalas/seasonal nalas existing in the lease area.
Map of the lease area depicted on the corresponding Topo Sheet along with adjoining
leases within a radius of 10 K.Ms.
List of wild animals/birds etc. locally seen by the villages.
Authentication of Flora & Fauna by DS.F.O. concerned.
Note on dependence of people on the forests proposed for diversion for mining.
Note on communication to the lease area from Bhubaneswar.
Note on mode of transport of ore from the mine to the plant.
Note on employment to be generated by establishment of the plant.
Map of the lease shown on the village sheet.
Vegetation map of the area along with the zone of impact (5 K.Ms.).
Lease area shown on the District map.
Digital Photo of the Mining Lease area, virgin forest area, mine pits, sprinkling system,
reclamation area, soil conservation methods taken, sign boards provided for educating
workers etc.
Cost of Iron Ore / Manganese Ore to be produced annually vis-a vis Steel. In case of Coal
the grade and its cost and value addition cost when converted to power.
Copy of MOU made with the State Govt. for establishment of Steel Plant for mineral
beneficiation or Power Plant, if any.
Population to be benefited directly & indirectly
Rehabilitation of any village, if involved then copy of draft R & R Plan
Cost of the project i.e. Cost on infrastructure / Cost on operation / Cost of establishment
/ Cost of raw material / Cost to be paid to State Forest Dept. for Con. Affn & NPV etc.
Copy of article of Association
Copy of affidavit to sign the diversion proposal
Land use details i.e. for Mining / Storing Minerals / Storing of O.B. /Const. of
infrastructure / Road & Railway / Magazine with Safety Zone
Land schedule authenticated by Tahsildar, concerned
Details of Broken Forest Land map dully authenticated by the Official present on the
date of verification
Location of Map / Topo Sheet indicating lease area with adjoining Leases / Map of lease
area in villager sheet / Map of broken area / Existing land use map / Proposed land use
map / Safety zone map / Phased reclamation map / Method of reclamation /Map of
non-forest land identified for compensatory aforestation / Geological Map.
7. ENVIRONMENTAL CLEARANCE:
Procedure Steps
provide direction about the Coastal Regulated Zone (CRZ) approvals requirement and its
applicability.
Clearance from IAA-MoEF: This phase facilitates the steps of EC process and time limits
for completion of EC process.
Post Environmental Clearance Monitoring: This phase defines the monitoring
requirement once a project has been accorded environmental clearance.
Check List:
Screening
Siting
Obtain site clearance / consent to establish / air and water consent from State Pollution
Control Board
o Basic project information includes information about location, proposed
investment, manpower, raw materials, products, manufacturing process, siting
details, climate, settlement
o Regulations Applicable and requirement under them
o Emission inventory of air pollution
o Assessment of waste water discharge
o Information about solid waste/hazardous waste
o Other type of pollution like noise, odour pollution, emergency mgmt.
o Other attachments
Industrial license
Explosive license
Permission from local body
Land schedule of the site
Layout map of the proposed project
List of pollution control equipment
Process flow chart
o
o
o
o
o
o
o
o
o
o
o
o
o
o
Air environment
Water environment
Waste management
Noise environment
Fuel/Energy requirements
Atmospheric impact
Pollution load statement (applicable to expansion/modernization plants)
Occupational health and safety
Pollution control
Green belt
Construction phase
Human settlement
Environment Management Plan
Emergency preparedness and Response plan
Public Hearing
Conduct of public hearing of the project and grant of NOC from SPCB
o Requisite number of copies of Executive summary of the project in English and
local language.
o EIA report (on request by concerned stake holder)
o Advertisement in two newspapers notifying about the public hearing (one should
be of the local language.
o Filled in Form I prescribed under Air (prevention and control of pollution) Act
1983.
o Filled in Form 13 prescribed under Water (prevention and control of pollution)
Act
Monitoring the terms and conditions for environmental safeguards as stipulated by IAA
o Six monthly compliance report to be submitted to the regional MOEF
o Monitoring report/suggestions and recommendations to the MOEF.
For industrial use, necessary Government order has to be obtained through the Regional
Chief Engineer. To draw water of 1 mgd and above from Government sources for
industrial / drinking water use etc., approval of Government is essential. Prior to that
approval of the Water Utilization Committee / Technical Committee is required.
The withdrawal of water will be in accordance with provisions of Orissa irrigation rules.
The company will complete all the formalities required under the rule and obtain a
license from the competent authority of the Water Resource Department.
The company will execute necessary agreement(s) with competent authority of the
Water Resource Department.
The company will submit water management plan in support of their demand. They
should have appropriate arrangement for treatment and recycling of waste water
generated for reuse. Only consumptive use and evaporation loss need be drawn from
the reservoir. The proposal should include assessment and use of groundwater as well
as tapping of nearby streams or other sources.
The company will have a back up storage to meet their minimum requirement for a
period of about a month during dry season.
The company will install appropriate flow meters/measuring devices of approved quality
at their cost to measure the quantity of water drawn for industrial purposes and
domestic use purpose separately. The project authorities shall have unrestricted access
and authority to monitor and vary the withdrawal.
The company will pay the water rates in force or as may be fixed by the government
from time to time.
The company will compensate the loss of power generation on account of water drawn
for industrial purpose.
Any water generated will be treated by the Company to applicable standard before
disposal into water bodies or otherwise.
The company will submit their viable and economical proposal for the intake
location/structure and conveyance arrangement to the Department for approval.
Construction of the structure can be taken up only after approval of design/drawings by
the Department. The project authorities shall have the right to check on the
implementation of the approved plan by the company. Satisfactory
functioning/operation of the intake and conveyance system would be the responsibility
of the company.
The company shall ensure that there will be no adverse impact on the ecosystem and
other environmental set up while implementing the scheme.
The pollution control board or other authorities of the government shall have the right
to monitor the implementation of the environmental management plan. All applicable
statutory stipulations should be compiled by the company.
The company shall not claim as a matter of right to get the desired quantity of water for
meeting their full industrial use during the lean period.
The R&R action plan/welfare action plan, as applicable, shall be implemented by the
company at its cost.
The safety and design of all the structures will lie fully with the company.
In case of any dispute/interpretation required, the decision of the department of water
resources, state government shall be final and binding.
Undertaking that the company or its sister concern is not involved in theft case.
Undertaking that no court case or dispute is pending with the Board.
Undertaking to the effect that the Consumer shall not Claim damages in the event of
fluctuation of voltage on the system.
Undertaking that no other connection is running in his premises.
The department will scrutinize all the application and forward to the Government with
necessary recommendation and while doing so, the matter will be informed to the
applicant.
Check list
A copy of your application to the Ministry of Information & Broadcasting (MoIB) for
setting up the CRS;
A copy of the Letter of Intent (LoI) issued to you by the ministry (Reference No., date
etc.);
A Demand Draft for Rs.1000 in favour of The Pay & Accounts Officer, Headquarters,
Dept. of Telecommunication, payable at New Delhi and preferably on the State Bank of
India. This may be shortened to PAO, HQ, DoT if necessary. (Note: SBI is to be strongly
recommended, but there are some indications that other banks drafts may also do. But
stick with SBI if you can.) You will need the DD number, issuing bank, and date.
Details regarding the proposed CRS address, location, contact details: This will include
geographical details for the station location [Latitude and longitude, and Measurement
from Sea Level (MSL) both preferably obtained from a Global Positioning System or
GPS device. You may also be able to obtain these from a Survey of India map of your
area.]
Details of the height of the building on which the mast and/or antenna will be installed
(in case they will be installed on the building);
Email address and contact details of the authorized signatory for the CRS application.
STEP 1: In the first stage of approval process the consultant has to prepare the
Feasibility report, which should includes the site plan and alignment plans for diversion
of National highway showing various options with merits and demerits, preliminary cost
estimates and necessitate / justifications for diversion.
STEP 2: Report will have to be submitted to Executive Engineer District division of
National Highway for review.
STEP 3: The proposal/ report will be reviewed by Executive Engineer and will have to be
modified as per the comments.
STEP 4: The modified proposal/ report has to be resubmitted for principal approval of
alignment.
STEP 5: The proposal/ report will be forward to the Chief Engineer National Highway
division in State capital for further processing.
STEP 6: The report will be then forwarded to Ministry of Surface Transport (MOST) for
principal approval of final alignment along with the recommendations of CE, NH State.
STEP 7: LAND ACQUISITION AND APPROVALS FROM OTHER AUTHORITIES
o After getting the approval from authority for final alignment for proposed
National Highway under diversion, the Owner has to acquire the land.
o The land acquisition will have to be taken in the name of Bharat Sarkar and will
be hand it over to National Highway Authority of India (NHAI), before starting
the construction work.
o The construction of National Highways process will be done by NHAI.
o The Owner shall have to take all the necessary approvals from the concerned
authorities for diversion of National Highways. Following are the list of approvals
to be taken by the Owner for diversion of National Highways;
Crossing the Canals and Nallah Irrigation Department, State Govt.
Crossing the existing railway lines Railway Department
Crossing the Forest Area Ministry of Environment and Forests (MoEF),
India
Submission of report to Executive Engineer (EE), town division, Water resource dept,
State.
Review by EE, Town Division, Water resource department, State.
Review by Chief Engineer (CE), WR Dept-State headquarters, State.
Put up the proposal by CE to Committee, Water resource department, State.
Send to Water resource department, New Delhi, Govt. of India for approval
Acceptance by Water resource department, GoI with recommendations.
The venture/project management shall give application to Senior General Manger (TP &
C) of State Power Transport Corporation Limited (SPTCL) giving details of project and
proposal for diversion. The proposal is presented before a committee chaired by CMD of
SPTCL and approval for re routing will be given by CMD.
After receiving approval venture has to conduct route survey and route map has to be
submitted to SPTCL for review and approval.
Based on approved route SPTCL will prepare estimate and calculate Supervision charges
and deposit. The supervision charges are 22% of total estimate.
The execution of work has to be done by venture.
Purpose of license form 22 - The license in Form-22 of Explosives Rules, 1983 is granted to
possess and use of explosives from a magazine
After completion of construction of the facilities, submission of drawings and the other
required documents by the party to the licensing authority for grant of license of the
premises.
5. Grant of license by the licensing authority.
6. Inspection of the magazine by the officer of the Department of Explosives.
7. Endorsement of the license.
4.
1.
Application Form 17 duly filled in and signed showing distances actually observed.
Six copies of drawings (blue print or computerized one without hand correction). Each
copy of drawing must show the details of site, layout, construction, sectional and
elevation view and necessary noting as stated below:
Approach road to the premises may also be incorporated in the site details for
proper identification of the location and approach to the premises.
The applicant should ensure and confirm that the site selected for the proposed
premises should have a clear title or undisputed legal status.
The proposed premises should have proper access and approach road for the
purpose of inspection, fire-fighting and rescue operation, movement of firetenders etc.
The proposed site should no way interfere or bring legal confrontation with other Acts
and Rules administered by the Central Govt., State Govt., local authority etc.
3.
In the site plan of the drawing whether proper road direction with approach has been
shown for exact identification of location. Khasra no., distances from other existing
structures etc. has to be shown in the plan. If
Note:- The magazine shall be made of brick, stone or concrete building which is closed
and secured so as to prevent unauthorized person from having access thereto
i.
Noting to be depicted in the drawing and in no way adversely affect the public
interest.
ii.
The proposed site should have preferably open land surrounding it and should
not be vulnerable to natural calamities.
Note:
The purpose of the site plan is to identify and demarcate the location of the premises. In
many cases the area up to 100 metres is open land and hence such cases does not fulfill
the main purpose. Sometimes reference structures lie or located much beyond 100
metres. Therefore all such reference structures (even not coming within the scale of the
drawing) for example the nearest km stone, road crossing with road directions, temple,
village, schools, hospitals, canals, rivers, railway line or other such immovable reference
structures along with.
Note:
1. In this connection it is stated that one of the important documents is NOC from
District Authority. In some cases it is seen that the NOC is considerably delayed
and as a consequence, grant of license is delayed and finally the party will have to
suffer irreparable loss.
2. The party should ensure that construction of facilities and the premises are
confined within the NOC land.
3. It is reasonable to prehensile that the purpose of NOC is to ensure the lawful
possession of the site and verification of antecedent of the applicant.
4.
After completion of the facilities the applicant must submit the following documents:Appropriate Bank Draft as license fee payable in same manner as mentioned during
approval
Application Form-4 duly filled and signed.
Specimen signature of the applicant/authorized person to verify the reference to initial
application filled by the applicant or authorized person of the company.
Completion report that of the construction of the facilities of premises have been
completed as per the approved plan.
Three copies of the drawing which are faithful reproduction of the original approved
drawing. In case of conditional approval all such conditions are to be complied with.
Forwarding letter mentioning details of enclosures, Bank Draft No & date etc.
5.
Applicant must submit the following documents to the licensing authority for grant of license:
2.
Bank draft of Rs. 600 as scrutiny fee and license fee for two years. The B/D should be
drawn on any nationalized bank, in favour of Jt. CCE/appropriate authority and should
be payable at appropriate place as applicable for the concerned licensing authority. The
Bank Draft should have at least 2 months validity from the date of submission of
application for grant of license. Note: Explosive Van license renewal for 2 years at a
time.
Application Form 7 duly filled in and signed by the applicant/ authorized employee.
Typed copy of form 7 (given in the Explosive Rules, 1983) is acceptable. Please note that
no column of the form should be left blank. Inapplicable columns should be filled as NA
i.e., not applicable. Full postal address with pin code should be written. No overwriting
or major corrections will be accepted. Minor correction should be initialed.
Application Form 7 duly filled in and signed by the applicant/ authorized employee.
Typed copy of form 7 (given in the Explosive Rules, 1983) is acceptable. Please note that
no column of the form should be left blank. Inapplicable columns should be filled as NA
i.e., not applicable. Full postal address with pin code should be written. No overwriting
or major corrections will be accepted. Minor correction should be initialed.
Attested copy of the RC book showing name, address, laden, unlade weight.
Specimen signature of the applicant.
Three copies of drawings (blue print or computerized one without hand correction).
Each copy of drawing must show the details of construction, dimensions ( i.e. the length,
width/dia, height, plate thickness, distance between tyres, type of tyres total length, gap
between the cab and the body, the rear gap, position and the nos. of the fire
extinguishers, location and guarding of the fuel tank, the location of the various safety
fittings, fire screen, the gap between fire screen and ground, double leaf door at the
back of the Van opening outside, brass plate with usual fall at the door sil level, position
of spare wheel etc. The drawing must also show necessary noting like registration no.,
engine no., chassis no., fabricators name, applicants full postal address with pin code
etc.
Forwarding letter mentioning details of enclosures, Bank Draft No & date etc.
Note:
1. For detailed construction, please see Specifications 1 of Schedule VII to the
Explosive Rules, 1983.
2. The license for Explosive Van only granted to person/company who already
possesses valid magazine license.
3.
The registration of the Boiler will be done within 30 days or shorter period as may be prescribed
from the date of the receipt for examination of the boiler giving not less than 10 days notice of
the date fixed.
After satisfactory completion of open inspection and hydraulic test provisional order will be
issued pending steam test.
Obtain permission to erect the Boiler through an authorized Boiler repairer from the Chief
Inspector of Boilers.
Submit following Original documents pertaining to the Boiler intended for
Registration to the concerned divisional Inspector.
o Form-II, Form-III, and Form-IVA
o Form-IIIC of all mounting s and fittings
o Form-IIIC of all mountings and fittings
o Boiler Drawings in original
o Form-IIIA of feed pipe
o Registration fee paid in challan
Offer the Boiler for carrying out stage inspection to the concerned divisional inspector and
obtain his clearance at every stage
Obtain approval of the proposed steam line drawing from the Chief Inspector of Boilers by
submitting following documents.
o Steam line drawing in triplicate showing clearly welding details, materials
specifications, working pressure of boilers and feed pipeline and registration
Number of Boilers
o Steam line drawing scrutiny fee paid in challan ( Fee is Rupees 30/- for every 30
meters or part thereof)
o Mention the authorized boiler repairer through whom you are getting the same
erected
After obtaining approval of proposed steam line drawing from the Chief Inspector of Boilers
make application for registration of proposed steam line with the divisional inspector by
submitting the following original documents
o steam line certificates in Form-IIIA
Offer steam pipe and fittings for material inspection and obtain clearance for erection from
the inspector of boilers.
Offer the weld set up and weld edge preparation for inspection and obtain clearance for
erection from the inspector of boilers.
Subject the erected steam line for hydraulic test to the inspector of boiler
Submit revised steam line drawing incorporating any deviations caused during the erection
due site condition for approval to the Chief Inspector of boiler through inspector of Boiler
drawing scrutiny fee.
Estimate
Assessment report on rate.
Fund certificate
Certificate stating no change of land schedule
Map
Xerox copy of sale statistics
Xerox copy of annual yield
Xerox copy of bench mark valuation
Xerox copy of rent chart
Xerox copy of valuation of trees
Xerox copy of valuation of structure
Xerox copy of the valuation of the fruit bearing trees.