Professional Documents
Culture Documents
Bridge Girders-Strength at Transfer
Bridge Girders-Strength at Transfer
1.
Introduction
2.
Design Considerations
23
and
2.1
2.2
Strength at Transfer
24
Pi = Pj Plri - Ple
At present, designs used in the manufacture of
precast bridge girders give a concrete strength at transfer
of 35 MPa at 18 hours after casting. This may be increased
to 40 MPa with a possible cost premium of 15% to 60%
depending on the likelihood of not maintaining daily
manufacture cycles.
For a simple rectangular stress block centred on
the prestress tendons, with no non-tensioned reinforcement
in the block and with gravity loads acting to reduce the
effect of the initial prestress Pi, the compressive failure load
Pu is given by Warner and Faulkes8:
Pu = 1.7 fcp b (ypb + 0.85 Msw/Pu)
Where:
----------- (1)
(2)
Lpt = 60db
--------------------
(3)
(4)
--------------------
(5)
1040 MPa
(imperial units)
-------------------
(6)
2.3
Development Length
25
Figure 1
2.4
De-bonding
26
Figure 2
checked against the required moment capacity. It is usual,
7
although not entirely accurate , to pro-rata the capacity of
the partially developed strands at the critical sections.
Flexural tension can occur in the concrete in the
development length of de-bonded strand at service loads,
which may affect the bonding of the strand. It is more likely
to occur where all the sheathing is terminated at one
location. AS 3600 now requires the development length of
de-bonded strand to be increased to 2 x Ld if bottom fibre
tension the cracking moment in the development length.
Alternatively designers may reduce the tensile capacity of
the de-bonded strands accordingly.
If the cracking moment is exceeded then cracks
can penetrate to the strand and anchorage will be reduced
or even destroyed. In such an event, the strand pattern and
sheathing layout should be revised or the capacity of the
partially developed strands disregarded up to this point.
Appendix A gives an example for de-bonding of
strands.
Photo 2 1000 Deep Super-T Setup two in-line
Stressing Bed
Long-line Manufacturing
Concept
3.1
Photo 1
27
28
x
x
x
x
x
x
Photo 3
Projecting Shear Reinforcement from Super-T Setup
4.
5.
References
1.
2.
3.
4.
5.
6.
7.
8.
Conclusions
29
= 2100 mm
2
= 555,850 mm
= 677 mm
= 192.96 x 106 mm3
= 234.76 x 106 mm3
= 472 mm
= 14.18 kN/m
= 50 MPa
= 38 MPa
= 32 m (c/c bearings)
= 400 mm
30
Allowable Stresses
AS 5100.5 Clause 8.1.4.2 and 8.6.2
Compression
Fc = 0.6 x fcp = 0.6 x 38 = 22.8 (Comp)
Tension
Ft = 0.25 x i fcp = 0.25 x 380.5 = 1.541 (Tension)
At the above tensile stress limit, the concrete alone will carry the stress and top reinforcement is not required. It does
however require more de-bonding.
Transmission Length
Lpt = 0.145 x Vpi x db / 3
= 0.145 x 1130 x 15.2 / 3
De-bonding Requirements
It is assumed that a completely unstressed zone of 10% x Lpt exists from the girder end-face and then the force
develops linearly to its full value of Pi at the end of the transmission length for each stage of de-bonding. It will also be assumed
that the transmission length for a fully bonded strand and an un-bonded strand is equal to Lpt = 912 mm.
Therefore, the prestress becomes fully effective at a point 912 mm from the end of the girder or 912 400 = 512 mm
from the centre of bearings.
At x = 912 mm from the beam end:
Msw = w.(x-a) . (L-(x-a)) / 2
= 14.18 x (0.912 0.4) x (32.0 (0.912 0.4)) / 2
= 114.30 kN.m
Vt(sw) = -114.30 / 192.96 = -0.592 (Comp)
Vt = Vt(ps) + Vt(sw)
= 5.019 0.592 = 4.427 (Tension)
Vb(sw) = 114.30 / 234.76 = 0.487 (Tension)
Vb = Vb(ps) + Vb(sw)
= -29.55 + 0.487 = -29.063 (Comp)
The top stress at x = 0.912 m exceeds the allowable by 4.427 1.541 = 2.886 Tension
The bottom stress exceeds the allowable by 29.063 22.80 = 6.263 Compression
Therefore, by inspection the de-bonding requirement will be governed by the bottom stress and calculations performed
to reduce the excessive stress. The excess tension will also reduce.
31
For 2 strands:
Table B1
Stress Reductions using nominated numbers of de-bonded strands
Row
Eccentricity
Number
Pi/A
Number
e, (mm)
De-bonded
4
447
2
-0.581
3
497
2
-0.581
2
547
2
-0.581
1
597
4
-1.162
Totals
10
*Vb = bottom fibre stress due to 2 or 4 strands in the row being de-bonded
Pi .e/Zb
Total *Vb
-0.615
-0.684
-0.753
-1.644
-1.196
-1.265
-1.334
-2.806
-6.601
In this example, a total of 10 strands provided a stress reduction of 6.601 MPa (>6.263 MPa). If more stress reduction
is necessary, simply increase the number of strands in rows 2 and 3.
32
Table B2
Summary of De-bond Calculations
C1
C2
C3
Row
Other rows un-boded
being
checked
Row
Resulting
numbers
Vcp.f
(MPa)
C4
Net Vcp.f
=29.55-C3
(MPa)
C5
Reqd
Vb(sw)
=net-allow
=C4-22.8
(MPa)
C6
Reqd Msw
=C5.Zb
(kN.m)
C7
x for Msw
(m)
C8
De-bonded
length
=x+0.4-0.912
Figure 5
(m)
3,2,1
-5.405
24.145
1.345
315.05
1.455
0.943
2,1
-4.140
25.410
2.610
612.25
2.975
2.463
-2.806
26.744
3.944
925.66
4.800
4.288
Nil
0.000
29.550
6.750
1584.63
10.300
9.788
Table B2 Calculations
Column C3
Column C4
Column C5
Column C6
Column C7
Column C8
Figure 5
When lifting devices or temporary supports are not located close to the bearing supports, stresses in the girder should
be checked for the actual support condition.
33