Professional Documents
Culture Documents
Bhakar Mukesh Copyright
Bhakar Mukesh Copyright
INTRODUCTION
Every anthropogenic activity has some impact on the
environment. More often it is harmful to the
environment than benign. However, mankind as it is
developed today cannot live without taking up these
activities for his food, security and other needs.
Consequently, there is a need to harmonize
developmental activities with the environment concern.
Environmental impact assessment(EIA) is one of the
tool available with the planners to achieve the above
mentioned goal.
It is desirable to ensure that the development options
under consideration are sustainable. In doing so,
environmental consequences must be characterized
early in the project cycle and accounted for in the
project design.
Law requires that every project proponent must take
Environmental Clearance from Ministry of Environment
and Forests, New Delhi or SEIAAS before starting up any
project. The environmental clearance is also mandatory
for the expansion modernization or renewal projects.
The conditions are applicable as per the MOEF
guidelines and EIA notifications issued and amended
time to time. There are many acts / rules and
notifications issued by MOEF, New Delhi for keeping the
environment in and around projects sides congenial for
LITERATURE REVIEW
The Role for EIA was formally recognized at the earth
Submit held at Rio Conference in 1992. Principles 17 of
the Rio declaration states thatEIA is a national instrument shall be undertaken of the
proposed activities that are likely to significant adverse
impact on the environment and are subject to a
decision of a competent national authority
The environmental professional, vol. 15, No. 01,
1993 (Canter and L.W.) according to its based on
recent expansion in coverage of mining both risk
assessment (RA) and EIA studies should be required to
Project Proposal:
Any proponent embarking on any major
development project shall notify IAA in writing by
the submission of a project proposal. The project
proposal shall include all relevant information
available including all relevant information available
including a land use map in order for it to move the
Scoping:
This stage identifies the key issues and impacts that
should be further investigated. This stage also defines
the boundary and time limit of the study.
Impact Analysis:
This Stage of EIA identifies and predicts the likely
environmental and social impact of the proposed
project and evaluates the significance. For every
project, possible alternatives should be identified and
environmental attributes compared.
Alternative should cover both project
location and process technologies. Alternative should
than ranked for selection of the best environmental
optimum economic benefits to the community at large.
10
EIA Report:
An EIA report should be provide clear information to the
decision-maker on the different environmental
scenarios without the project, with the project and
provide information in logical and transparent manner.
Public Hearing:
After the completion of EIA report the law requires that
the public must be informed and consulted on a
proposed development after the completion of EIA
report.
The State Pollution Control Boards will conduct the
public hearing before the Proposals are sent to MOEF
for obtaining environmental clearance.
Decision Making:
It decides whether the project is rejected, approved or
needs further change accordance to EIA report.
11
12
ii.
13
14
to
in
(iv)
If the application involves different leases of
the same company from the same area/region,
then a separate application for each lease has to
be made and the forwarding letter should also
preferably be for each separate application. In
case, the State Government forwards the
proposals in one composite letter, then the letter
must clearly specify the names of all the leases,
their location (village and District), lease area and
production capacity for each of the applications.
(v)
Routing of proposal is not required
for the following:
(a) If the project has already been accorded
environmental clearance once from MOEF
(after 27.01.1994) and is now again applying
for expansion (in lease area and/or production)
for the same project.
15
16
CASE STUDY
For the case study the Wolkem Ltd. Mine was taken to get
the required details of the environment and the studies
based on the environmental scenario.
General
Wolkem Ltd mine is a private Limited company, engaged in
the business of mineral mining. Mining lease hold area (ML
Area) measures 49.480 Ha, and Wollastonite, Calcite and
Feldspar minerals are being extracted from the area.
The worlds largest miner and producer of Wollastonite.
Indias leading miner and producer of Calcite and Wet
Ground Calcium Carbonate. The mineral Wollastonite is
being used in Ceramics, brake lining, paints, plastics and
wall-tiles and other industries as an important industrial
Mineral.The use of Calcite in acid neutralization, soil
conditioner and low hardness abrasives.
Wolkem a 100% family owned business was established in
1972 in Rajasthan in North-West of India. Having operations
in 4 countries and 20 mining and processing plants in 6
Indian states.
: 244529 N to 24 46 04 N
Longitude
: 73 09 56 E to 73 10 30 E
18
Objectives
of
Environmental
Assessment Study
Impact
19
DATA COLLECTED:
The EIA study has been done for the Mine Lease (core
zone) and area within 10km periphery from ML area (buffer
zone), both of which comprise the Study Area of 10km.
1. Details of fauna (Wild and Domestic), flora.
2. Major Habitat.
3. Major industries.
4. Sensitive places/Historical monuments and
sanctuaries.
5. Land use pattern within core and buffer zone.
6. Demography and socio-economic on based
data.
7. Relevant Rainfall data for previous decade
from India Meteorological Department (IMD).
8. Study of present environmental protection and
mitigating measure in Nearby operating similar
projects (if any).
9. Geo-hydrological aspects based on available
data from various sources.
10. Identification of water bodies, hill, roads etc
within buffer zone.
Additional Studies/Points:
Hydrological & Hydro-geological study.
Bio-logical Study.
Preparation of R & R Plan.
20
2008
675.0 mm
2009
610.0 mm
2010
630.0 mm
2011
670.0 mm
2012
596.0 mm
2013
570.0 mm
2014
645.0 mm
2015
635.0 mm
Months
March
Minimum
32.4
21.6
21
April
35.3
25.9
May
44.8
36.2
Mean
37.5
27.9
Humidity:
The relative humidity is high during the monsoon generally
up to 65%. After the monsoon season humidity decrease
and during the winter season the air is fairly dry. However
the relative humidity remains approximately 40% in
summer season.
Wind speed:
Wind speed plays a dominant role in the dispersion of air
pollutants. The wind speed were found in the range
between 4km/hr to 26km/hr with average value of 17km/hr.
Schedule of sampling:
Air quality:- Quarterly all seasons other then monsoon.
Noise Sampling:- Quarterly all seasons other then
monsoon.
Water Quality:- Quarterly all seasons.
Soil Sampling: - Half yearly.
Air Environment:
22
NOX
SO2
RPM
Samplin
Result in (g/m)
g
Pre Monsoon(April)
Post Monsoon(Nov.)
Station
PM
10
PM
2.5
SO2
NO2
PM
10
PM
2.5
SO
NO2
Near
magazi
ne in
SW
directio
n
Mine
85.9 43.4 9.39 15.8 92.2 50.2 8.1 11.5
working 0
5
6
4
8
7
4
area
near
electric
tower
Near
social
forestor
y
4
Top of
khera
mine
office
Top of
guest
house
belka
Crushin
g plant
S.NO.
Pollutant
CPCB Norms
(g/m) In
Industrial,
Residential, Rural
& Other area
1.
PM 10
100
2.
PM 2.5
60
3.
SO2
80
4.
NOX
80
25
Noise:
Noise Level:-The noise level measurements have been
made at 13 locations within the study area. All the
monitoring stations were located in the below:S.NO Location
.
Noise level in dB
Measured value
Permissible
limit
26
Day
Night
Day
Night
51.6054.80
75
65
Close to crushing
plant
62.2064.80
49.8052.90
70
65
OB dumps
55.7059.20
42.6045.20
60
55
Office at colony
52.3055.10
42.6045.20
55
45
Near Belkapahar
mine 1km away
48.9051.30
40.9043.90
50
45
Near NichlaKhera
52.7055.20
42.6045.20
55
50
Near Gharat
52.6054.40
44.1047.20
60
50
Near Jack
Hammer Drilling
in work area
82.2084.40
Not in 95
operat
ion
80.5082.80
Not in 95
operat
ion
10
Near loharcha
50.8052.60
43.3047.60
60
50
27
Night: 10 P.M. to 6
Waste Dumping:
Year wise waste rock generate and dumping done outside
the ML area on revenue land.
S.
N.
Year
OB in
cum.
25%
increa
se OB
in
RL of
dump
Length Heig
of
ht in
dump met
er
Volu
me
28
cum.
1.
First
Year
3300
06
41250
8
(20132014)
Sub Total
41250
8
2.
28448
8
Second 2275
Year(20 90
142015)
Sub Total
28448
8
3.
39938
1
Third
3195
Year(20 05
152016)
Sub Total
Total
700710
200
4100
0
710720
375
8.5
2868
75
720722
375
9750
0
4253
75
722728
375
2925
00
2925
00
728730
375
9750
0
730735
375
3112
50
39938
1
4087
50
8774 10963
13
77
1126
635
29
Land Use:
Land use of the mining lease area at different stages of
mining:At the
beginnin
g of the
mining
Area
(ha)
Within
49.48
ML Forest
Outside
ML with
in forest
Total Land
4.65
Area (ha)
38.33
Dumping of
overburden
8.61
2.04
Infrastructure with in
ML
0.5
Sub Total
49.48
3.45
Sub Total
4.65
Total
54.13
30
Water Resources:
Physico Chemical analysis of water in core zone and
buffer zone:locatio Particular
n
Colour
pH
(Haze
n unit)
TDS
TSS
Total
Ca+2 Clin
(pp
m)
(ppm)
Desirable
6.5
to
8.5
500
300
75
250
10
2000
600
200
1000
W-2
<5
8.5
1
576
316
51.6
82
W-5
<5
8.9
5
472
10
345
80.80 142
W-9
<5
7.4
6
456
144
56.60 58
W-10
<5
7.4
9
482
268
98.40 68
W-11
<5
7.6
7
556
196
82.30 54
Limit
Permissibl
e
31
Water Quality:
To evaluate the physico-chemical characteristics
of the water resources existing in the study area, water
samples from surface and ground water sources were
collected during the summer season and characterized for
physic-chemical parameters.
33
Ecology:
Wild life sanctuary: Mines area was declared a wild life sanctuary in 1980. No
national park and elephant reserve exits in mines area.
Flora: The mine lease hold area is having same natural
vegetation except some scanty bushes. It is very reach in
floral bio-diversity starting from xenomorphic sub-tropical
thorn forests in the foot hills to sub-tropical evergreen
forests along priyen water courses and valleys at higher
altitudes. The place is also reach in bryophytes and algae.
All species of the plants and fauna found in the study area
were recorded. The details are as under:
S.
No.
Local name
Scientific name
Family
1.
Babool
Acacia nilotica
Mimosaceae
2.
Bar
Ficusbengalenbsis
Urticaceae
34
3.
Khejri
Prosopis cineraria
Mimosaceae
4.
Vilatibabool
Prospisjuliflora
Mimosaceae
5.
Peepal
Ficusreligiosa
Urticaceae
6.
Neem
Azadiracstaindica
Meliaceae
7.
Sheesham
Dalbergiasissoo
Adhashishi
9.
Akra
Calotropisprocera
Asclepiadace
ae
1o.
Arusa
Adhatodavasica
Acanthaceae
11.
Bapchi
Ocimumamericanum
Labiaceae
12.
Bekaria
Indigoferacordifolia
Papilionaceae
13.
Bor
Zizyphusnummularia
Rhamnaceae
14.
Bui
Aruatomentasa
Amaranthace
ae
15.
Dandathor
Euphordianivulia
Euphorbiseea
e
16.
Dhanasa
Tephrosiatuepurea
Caesalpiniace
ae
17.
Jhojhar
Cropolariamebicogeni Papilionaceae
a
18.
Kentali
Solanumxanthcrpum
Solonactae1
19.
Satyanasi
Argemone Mexicana
Papavaracea
e
20.
Unthkateli
Ehchinopsechinatus
Compositae
21.
Bhurat
Cechruscatharticus
Graminae
------
35
22.
Chiribajra
Eragrospis species
Graminae
23.
Bhiribzara
Sporobolusioclados
Graminae
24.
Dab
Desmostachyabipinan Graminae
ti
25.
Kuri
Digitariacrucita
Graminae
26.
Lapla
Aristatiada species
Graminae
27.
Suraval
heteopogoncontortus
Graminae
Fauna:
Irrespective of its unfriendly terrain, Rajasthan gives shelter
to a variety of animals and birds. They live in smaller herds
and thrive mainly on wild grasses and various type of
shrubs. The Nilgai are abundant on the open planes and in
the foothills on the Aravalli. The blue cow is actually not a
cow it is an antelope, the largest in India. The mining lease
area is located at undulating terrain and hillock. This area
is relatively calm and there is no source of high noise level.
It was found a variety of animal inhabited this area.
S.NO.
Common name
Latin name
36
1.
Babbler, common
Turdoidescaudatus
2.
Babbler, jungle
Turdoidescaudatus
3.
House crow
Corvussplendens
4.
Passer domesticus
5.
Shrike, grey
Laniusexcubitor
6.
Shrike, baybacked
Laniusvittatus
7.
Parakeet, roseringed
Psittaculakrameri
8.
Partridge, grey
Francolinuspondiceria
nus
9.
Jungle cat
Falischaus
10.
Nil gai
Boselaphustragocame
lus
Air quality mitigation measure in mine: As already indicated the ground level concentration SO 2,
NO2, PM10, PM2.5 are well within limit. For dust
suppression primarily water spraying would be adopted.
For drilling equipment dust collection system would be
provided. For blasting NONEL system adopted. The
proposed crusher would be housed in an enclosed building
37
38
40
Fauna
A variety of fauna, including highly rare threatened and
endangered species are found in the kheratarla mines area.
In mines earlier days mainly lion and tiger presence in that
area. Presently the leopard is the apex predator. And other
animals found in mines areas was sambhar, jungle cat,
small Indian civet, wolf, hyaena, jackal, Indian fox, common
languor, wild boar, bear, pangolin, common mongoose,
Indian hare, porcupine and hedgehog. A proper sanctuary
should be provided to these above animals for protect
them. The sanctuary provides an ideal habitat for the sloth
bear too.
Flora
There are a lot off variety of species were found in
kheratarla mine lease hold area. Some of them are like
babool, bar, khejri, peepal, aakra, bapchi, bekaria.
Vilatibabool, sheesham, arusa, dhanasa, jhojhar, lapla etc.
We should be used less harmful equipment to protect these
above mentioned flora. Waste water of mine should be
proper cleaned before discharge into outside the mine and
a proper drainage system should be carried out. A proper
41
42
43
PROPOSED
Year
Locati
on
ACHIEVED
Are No.
a
Of
plan
( in
ts
Ha.
)
Speci Survi
es
val
2015 E
-
0.5
0
850
2016 F
0.3
0
0.9
0
G1
SUB
TOT
AL
Are No.
a
Of
plan
( in
ts
Ha.
)
Speci Survi
es
val
10-15 80
0.4
0
200
0
15
90
415
10-15 80
0.2
5
320
14
74
125
0
10-15 80
1015
0.6 232
5
0
15
82
1.7 251
0
5
in %
80
in %
45
v
46
47